JPS60119804A - Construction of off-shore structure - Google Patents

Construction of off-shore structure

Info

Publication number
JPS60119804A
JPS60119804A JP22599583A JP22599583A JPS60119804A JP S60119804 A JPS60119804 A JP S60119804A JP 22599583 A JP22599583 A JP 22599583A JP 22599583 A JP22599583 A JP 22599583A JP S60119804 A JPS60119804 A JP S60119804A
Authority
JP
Japan
Prior art keywords
ground
piles
crane
truss bridge
legs
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP22599583A
Other languages
Japanese (ja)
Other versions
JPS6237166B2 (en
Inventor
Yojiro Yoshida
吉田 洋二郎
Yoshimi Suzuki
鈴木 好実
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP22599583A priority Critical patent/JPS60119804A/en
Publication of JPS60119804A publication Critical patent/JPS60119804A/en
Publication of JPS6237166B2 publication Critical patent/JPS6237166B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment

Abstract

PURPOSE:To make easier the assurance of scaffold as well as shorten the period of construction by a method in which a movable truss bridge is set between a stage with legs and an artificial ground, and an overhead crane is operated to install blocks in pile groups below the movable truss bridge. CONSTITUTION:Steel tubular piles 1 are driven into the ground 7 by a vibro- hammer 6 attached to the tip of a crane 5. A stage 4 with legs is fixed with a given spacing by legs 8 in such a way as to cover the top ends of the piles 1. An assembled block 10 is installed on the pile group 3 driven by the crane on the ground's surface to construct an artificial ground 12, and a path 13 is formed on the ground 12. A movable truss bridge 14 is set between the path 13 and the stage 14 with legs. Piling work and block installing work can thus be proceeded concurrently and the period of construction can be shortened without affected by weather on water.

Description

【発明の詳細な説明】 この発明は桟橋等の水上構築物の禍築方法に関するもの
である。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for constructing a floating structure such as a pier.

従来、大小様々な水上構築物を堅牢かつ容易に構築する
方法として、鋼管を杭として使用し、陵部から湖、海な
どの木部に向かって互いに所定間隔離間させて杭打ちし
た複数の鋼管にこれら鋼管を相互に連結するようにして
複数のブロックを据(=lけ、これにより、水上に人工
地盤を形成する構築方法が提案されている。
Conventionally, as a robust and easy way to construct floating structures of various sizes, steel pipes are used as piles, and multiple steel pipes are piled at a predetermined distance from each other from the mountain to the wood of a lake, sea, etc. A construction method has been proposed in which a plurality of blocks are installed by interconnecting these steel pipes, thereby forming an artificial ground above water.

この構築方法においては、陵部から離れた箇所の杭打ち
は、クレーン船で杭を吊り上げ、この杭を杭打ち船で打
ち込むことにより行なっており、水底地盤が杭の最下部
に固定される受ブロックの損料高さより高い場合は、浚
渫船にて浚渫してり、する。また、人」二地盤を構成す
るブロックの損料も大型のクレーン船を使って1jなっ
ており、吊り」二げたブロフクを安定させ、据付部分に
導くための案内ロープを操作する作業員の足場は、杭近
傍に仮設した簡易型の桟橋を使って行なうようにしてい
る。
In this construction method, piles are driven in areas far from the ridge by hoisting the piles with a crane ship and driving the piles in with a pile driving ship. If the damage is higher than the block damage height, dredging is carried out using a dredger. In addition, the damage to the blocks that make up the 2nd ground was also reduced by using a large crane ship, and the scaffolding for the workers who operated the guide ropes to stabilize the suspended blocks and guide them to the installation area was This is done using a temporary pier built near the piles.

このように、従来の構築方法では、杭打ち、浚渫、ブロ
ック据伺は等のためにクレーン船、杭打ち船等の作業船
を多数使−)でおり、そのために水1□気象の影響を受
けやすく、作業船の使用コストが高いため1費が嵩んで
しまい、しかも施工速度もnい。また、仮設足場として
簡易型の桟橋を設けなければならないので、足場のコス
トも馬鹿にならない。そこで、水1−に向かって次々に
打たれた複数の杭(以下、打設杭群と称す)の木部側前
端部分に構台を溶接し、この構台な足場とする方法が考
えられる。
In this way, in the conventional construction method, a large number of work vessels such as crane ships and piling boats are used for pile driving, dredging, block inspection, etc. However, the cost of using a work boat is high, so the cost is high, and the construction speed is slow. In addition, since a simple pier must be provided as temporary scaffolding, the cost of scaffolding is not prohibitive. Therefore, a possible method is to weld a trestle to the front end portion of the wooden part of a plurality of piles driven one after another toward the water 1- (hereinafter referred to as a group of driven piles), and use this trestle as a scaffold.

しかし、このMri築方法においては杭の天端は水面近
くに位置することになるので、水]−気象が悪く波があ
る場合には構台溶接作業が行なえず、構台設置のために
は波が静まるまで待たなければならす、J゛期の遅延を
生じるテ「点があり、採用しがたい。
However, in this MRI construction method, the tops of the piles are located near the water surface, so if the weather is bad and there are waves, welding of the gantry cannot be carried out, and it is difficult to install the gantry due to the waves. We have to wait until the situation calms down, and there is a risk of delaying the J゛ period, making it difficult to adopt.

この発明は、−上記事情に鑑みてなされたものでその目
的は水−1;気象の影響を受けることがなく、足場の確
保が容易で、工期が短く済み、しかも工費の安価な水上
構築物の構築方法を提供することにあり、杭の天端に嵌
着可能な脚部を複数構台に取りつけることによって打設
杭群の前端部分に気象に影響されることなく容易に構台
を設置し、この脚伺構台」−に杭打ち用のクレーンを載
置し、このクレーンにより杭打ちをつづけるとともに、
この脚伺椙台と、打設杭群の基端部分(陸に近い部分)
にブロック据伺けにより形成された人工地盤1−の構台
との間に移動トラス橋を架設し、この−1−に天井クレ
ーンをtwし、この天井クレーンによりブロックの損料
けを行なうようにしたものである。
This invention was made in view of the above circumstances, and its purpose is water. The purpose of this method is to provide a construction method that allows a gantry to be easily installed at the front end of a group of driven piles without being affected by the weather by attaching a plurality of legs that can be fitted to the tops of piles to the gantry. A crane for piling was placed on the trestle platform, and the crane continued to drive pilings.
This foot support and the base end of the pile group (the part near the land)
A movable truss bridge was constructed between the gantry of artificial ground 1-, which was formed by the block erection, and an overhead crane was installed on this 1-1-, and this overhead crane was used to collect the blocks. It is something.

以下、この発明を図面を参照して説明中る。初期の杭打
ち、すなわち水際の杭打ちは陸」のクレーンにより行な
えばよいが、それ以降の杭打ちは第1図に不才J:うに
、鋼管杭1@・・を台船2で水1−輸送し、打設杭群3
の前端部分3 a−にに設けた脚伺構台4にに載置した
クローラクレーン5で吊り1−げ、後述するカイト部材
で固定してクレーン5先端に取りつ11たバイブロハン
マ6で地盤7中に打設する。
The present invention will be explained below with reference to the drawings. Initial pile driving, that is, piling at the water's edge, can be done using a crane on land, but subsequent pile driving is shown in Figure 1. -Transport and drive pile group 3
The front end part 3a of the front end part 3a is hoisted by a crawler crane 5 mounted on a pedestal 4 provided at 3a, and then fixed with a kite member (to be described later) and attached to the tip of the crane 5. to be poured.

1−足脚イ゛1構台4は、第2図(a)(b)に示すよ
うに、そのド面に杭lの天端1aを覆うように杭1にI
K着可能なキ、トップ状の脚部8が相互に所定間隔(杭
打ち間隔と回し間隔)を置いて固定されているもので、
第2図(b)に示すように、■スパン毎に分解、組立で
きるようなユニット構造となっている。従って、に記構
台4においては杭打ちが一列前進したら、陸側の1スパ
ン分(以下構台ユニットと称す)4aを取りはずし、打
設終rした杭1−・・1−に嵌着して連結すれば、杭打
ちに対応して構台4を前進させることができる。また、
この構台4は、上記のように脚部8が設けられていると
ともに、■スパン毎に分解、組立できるように構成され
ているので、水上での架設撤去が容易に行なうことがで
きる。
1-Leg I 1 The gantry 4 has I attached to the pile 1 so as to cover the top end 1a of the pile 1 on its surface, as shown in FIGS. 2(a) and 2(b).
The top-shaped legs 8, which can be attached, are fixed at a predetermined interval (pile driving interval and turning interval),
As shown in FIG. 2(b), it has a unit structure that can be disassembled and assembled span by span. Therefore, in the gantry 4 described in , when one row of piles are driven forward, one span of the land side (hereinafter referred to as gantry unit) 4a is removed and connected by fitting it to the piles 1-...1- that have been driven completely. Then, the gantry 4 can be moved forward in response to pile driving. Also,
This gantry 4 is provided with the legs 8 as described above, and is constructed so that it can be disassembled and assembled span by span, so it can be easily erected and removed on the water.

上記構台4の前端には、カイト部材9が固定されており
、このガイド部材9の前端枠部9a−−・に杭1拳・・
を挿入することにより杭打ちする場合の前後左右の間隔
を所定値にすることができるようになっている。
A kite member 9 is fixed to the front end of the gantry 4, and a stake is attached to the front end frame portion 9a of the guide member 9.
By inserting the , it is possible to set the distance in the front, back, left, and right when driving stakes to a predetermined value.

−l: k水際近傍の打設杭群3には陸」−のクレーン
により組イ゛1ブロックlOを損料ける。なお、これう
組伺フロック10・・0を据付けるためには予め各々の
杭1・・・の最下部に受ブロック11・・・を固定して
おく。上記組伺ブロック10はその投手方向両端に杭l
を挿通させるための貫通孔10aが形成されており、縦
横に相互に位置を違え、6杭1・・・を相互に連結する
ようにして杭l・・・に嵌着させる。このようにして組
伺ブロックlO・−・の据伺けが終ったら、これら組付
プロ、りlO・・・と杭lの隙間にモルタルを注入して
ブロックと杭1・・・を一体化させて人工地盤12を構
成する。
-l: A land crane will be used to remove one block of piles 3 near the water's edge. In addition, in order to install these grouping flocks 10...0, a receiving block 11... is fixed to the lowest part of each pile 1... in advance. The above-mentioned construction block 10 has stakes l at both ends in the direction of the pitcher.
A through hole 10a is formed through which the six stakes 1 are inserted, and the six stakes 1 are fitted onto the stakes l at mutually different positions in the vertical and horizontal directions so as to connect the six stakes 1 to each other. After the installation of the assembly blocks 1O... is completed in this way, mortar is injected into the gap between the assembly professional blocks 1O... and the piles 1 to integrate the blocks and the piles 1... The artificial ground 12 is constructed by using the artificial ground 12.

1、記のようにして、水際近傍に人工爪51 t 2を
構築した以降のブロックの据イ・jけは以下のようにし
て行なう。まず、」−記人上JI!!盤12の−1−に
通路13を形成し、この通路13と上記脚伺構台4との
間に移動トラス橋14を架設する。そして、この移動ト
ラス橋14上に天井クレーン15を載置しこの天井クレ
ーン15により受ブロツク11、組伺ブロックlO等の
ブロックの損料けを行なう。なお、この前に、水底地盤
7が杭lの最下部に固定される予定の受ブロック11の
損料は高さより高い場合には、」−記脚伺構台41:の
クローラクレーン5により鋼矢板16・・・を打設し、
1−記天11クレーン15によって浚渫管17を吊り下
げて浚渫しておく。なお、浚渫が不必要な場合は、ト記
没渫管17な吊り下げていた天井クレーン15はブロッ
クのJl< (=Iけを行なうこととする。この天井ク
レーン15は周知のように大重量に四えられしかも」:
記移動トラス橋14−1xを自由に移動可能なので1−
記浚渫、ブロック据(1けを迅速かつ効率的に行なうこ
とができる。
1. After constructing the artificial nail 51 t 2 near the water's edge as described above, the installation of the blocks is carried out as follows. First of all,” - Reporter JI! ! A passage 13 is formed at -1- of the board 12, and a movable truss bridge 14 is constructed between this passage 13 and the landing gear platform 4. Then, an overhead crane 15 is placed on the movable truss bridge 14, and the overhead crane 15 is used to collect damages on blocks such as the receiving block 11 and the assembling block IO. In addition, before this, if the height of the receiving block 11 to which the underwater ground 7 is to be fixed to the lowest part of the pile l is higher than the height, the steel sheet pile 16 is ... was poured,
1- Dredging is carried out by suspending the dredging pipe 17 by the crane 15. In addition, if dredging is unnecessary, the overhead crane 15 that was hanging the dredged pipe 17 will be moved to the block. "I might be killed":
Since the mobile truss bridge 14-1x can be moved freely, 1-
Dredging and block erection can be carried out quickly and efficiently.

−1−記のようにして、打設杭群3の前端部分3aにお
いて脚部・J構台4上のクローラクレーン5によって効
率的に杭打ちを行なうと同時に、」1記移動トラス橋1
4と天井クレーン15によって迅速にブロックの据付け
を行なって人工地盤12を連続して延設することができ
る。この時の脚伺構台4の前進は、−上記したように、
その陸側の構台ユニフト4aを取りはずし、前端側に組
付けなおすことにより行ない、移動トラス橋14の前進
は、この移動トラス橋14の陸側脚部近傍の通路13上
に油圧ジヤツキを取付け、この油圧ジヤツキにより行な
う。また、ブロックの輸送は、第1図に示t 、J: 
ウニ、通路13J二を走行するトレーラ18により迅速
に行なうことができる。
As described in -1-, piles are efficiently driven at the front end portion 3a of the driven pile group 3 by the crawler crane 5 on the leg/J gantry 4, and at the same time, the movable truss bridge 1
4 and the overhead crane 15, blocks can be quickly installed and the artificial ground 12 can be continuously extended. The forward movement of the landing gear platform 4 at this time is - As mentioned above,
The moving truss bridge 14 is moved forward by removing the land side gantry unit 4a and reassembling it on the front end side.A hydraulic jack is installed on the passage 13 near the land side leg of the moving truss bridge 14, and the moving truss bridge 14 is moved forward. This is done using a hydraulic jack. In addition, the transportation of blocks is shown in FIG. 1, t, J:
This can be done quickly by using the trailer 18 that travels along the passage 13J.

なお、上記構成において、構築物が桟橋である時は、」
=記通路13を設けた時点で完成となる。
In addition, in the above configuration, when the structure is a pier,
=It is completed when the passageway 13 is installed.

また、上記実施例では、脚伺構台4の脚部8はキャップ
状に構成したが第3図に示す脚伺構台19に示すように
、その脚部20をtfll /lta lの天端内部に
嵌入するように尖頭状に構成してもよい。
Further, in the above embodiment, the leg part 8 of the leg rest 4 is configured in a cap shape, but as shown in the leg rest 19 shown in FIG. It may be configured to have a pointed shape so as to fit into it.

このように構成すれば、打設した杭lが若干傾斜し、そ
の枕頭が位置ずれを生じている場合にも杭lに構台を取
りつけることができ、しかも、位置ずれを起している抗
頭を上記脚部18によって所定の位置に収めることが可
能となる。
With this configuration, the gantry can be attached to the pile l even if the pile l that has been driven is slightly inclined and the head of the pile is out of position. can be stored in a predetermined position by the leg portions 18.

さらに、h記実施例では構台4は鋼矢板16の打設のた
めに4スパン(第一図)または5スパン(第2図)とし
たが、鋼矢板打設が必要のない時は3スパンの構台で充
分である。
Furthermore, in Example h, the gantry 4 has 4 spans (Fig. 1) or 5 spans (Fig. 2) for driving the steel sheet piles 16, but when driving the steel sheet piles is not necessary, it has 3 spans. A gantry is sufficient.

以し説明したように、この発明の水−1−構築物の構築
方法によれば、脚伺構台とクローラクレーンおよび移!
F11 )ラス橋と大月クレーンの採用によって、杭打
ち作業とブロック据付け作業とを同時に進行させること
ができるように構成されているので、水−1−気象の影
響を受けることなく、1期が短くて済み、雅持費、運転
費などの高い作業船を使うことなく行なえ経済的である
。特に作業船を回航させなければならないへき地、海外
等で水上構築物を構築する場合に有利である。
As explained above, according to the method of constructing a water-1 structure of the present invention, a landing gear platform, a crawler crane, and a moving!
F11) By adopting a lath bridge and an Otsuki crane, the structure is configured so that piling work and block installation work can proceed at the same time, so the first stage can be completed without being affected by weather. It is economical because it is short and can be done without using a work boat, which has high transportation and operating costs. This is especially advantageous when constructing floating structures in remote areas or overseas where work vessels must be sailed around.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図はこの発明に係る水上構築物の構築方法を説明す
るためのもので、この方法により構築物を構築している
ところの全体図、第2図(a)(b)はこの発明に使用
される構台を示すもので(a)は一部切欠いて示した平
面図、(b)は側面図、第3図(a)(b)は同構台の
他の構造のものを示すもので、(a)は杭に嵌着する前
の側面図、(b)は杭に嵌着したところの側面図である
l・・Φ杭、l aa 舎・天端、2・・・台船、4.
19◆・拳脚伺構台、51・クローラクレーン、8.2
0・・・脚部IJ構台の脚部、lo・・・組付ブロック
、10a・・・貫通孔、11・・・受ブロック、12・
・・人工地盤、14・・・移動トラス橋、15・・拳天
井クレーン。
Figure 1 is for explaining the method for constructing a floating structure according to the present invention, and Figures 2 (a) and 2 (b) are an overall view of the structure being constructed by this method. (a) is a partially cutaway plan view, (b) is a side view, and Figures 3 (a) and 3 (b) show other structures of the gantry. a) is a side view before it is fitted on the pile, and (b) is a side view after it is fitted on the pile. l... Φ pile, l aa building/top, 2... barge, 4.
19◆・Fist leg support structure, 51・Crawler crane, 8.2
0... Legs of IJ gantry, lo... Assembly block, 10a... Through hole, 11... Receiving block, 12...
...Artificial ground, 14.. Mobile truss bridge, 15.. Fist overhead crane.

Claims (1)

【特許請求の範囲】 階部から湖、Vliなどの木部に向かって、水面下の地
盤にTfいに所定間隔離間させて複数の杭を打ち込んで
ゆき、i(i記杭が挿通する貫通孔を複数有するプロ、
りを前記複数の杭を相互に連結するようにして前記水面
下の所定位置から水面−ヒにかけて据伺け、これらプロ
、りと杭の隙間にモルタルを71人してこれらブロック
と前記杭とを一体化し、これにより人工地盤を形成し、
この人工地盤l−に通路、建物等の構造物を設置する水
−に構築物の構築方法において、 杭の天端に嵌着Hti能な1lll1部を複数有する脚
付構台を打設杭1工の前端部分の複数の杭の天端に前記
脚部を嵌着させることにより設置し、 この脚伺構台上にクレーンをamし、このクレーンによ
り台船−にの杭を吊りあげて木部側に向かって杭打ちを
行なうと同時に、 前記叫躬構台と前記人−[地盤との間に移動トラス橋を
架設し、この移動トラス橋上に天井クレーンを載回し、
この天井クレーンで前記移動トラス橋下の杭打に前記ブ
ロックの据付けを行なうように構成し、上記構台および
移動トラス橋を順次隆部から木部に向かって移動させな
がら連続的に前記人V地盤を構築していくことを特徴と
する水上構築物の構築方法。
[Scope of Claims] A plurality of stakes are driven into the ground below the water surface from the floor toward the lake, Vli, etc. at predetermined intervals, and Professional with multiple holes,
The blocks were installed from a predetermined position below the water surface to the water surface by interconnecting the plurality of piles, and 71 professionals poured mortar into the gaps between the blocks and the piles. to form an artificial ground,
In this method of constructing structures such as passages and buildings on artificial ground, a base with legs having a plurality of parts that can be fitted onto the top of the pile is driven for one pile. It is installed by fitting the legs to the tops of the plurality of piles at the front end, and a crane is placed on top of this platform, and the crane is used to lift the piles on the barge and place them on the wood side. At the same time, a moving truss bridge is constructed between the shouting platform and the ground, and an overhead crane is mounted on the moving truss bridge.
This overhead crane is configured to install the blocks on the pilings under the movable truss bridge, and while the above-mentioned gantry and movable truss bridge are sequentially moved from the ridge toward the wood, the man-V ground is continuously moved. A method of constructing a floating structure characterized by the following steps:
JP22599583A 1983-11-30 1983-11-30 Construction of off-shore structure Granted JPS60119804A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP22599583A JPS60119804A (en) 1983-11-30 1983-11-30 Construction of off-shore structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP22599583A JPS60119804A (en) 1983-11-30 1983-11-30 Construction of off-shore structure

Publications (2)

Publication Number Publication Date
JPS60119804A true JPS60119804A (en) 1985-06-27
JPS6237166B2 JPS6237166B2 (en) 1987-08-11

Family

ID=16838139

Family Applications (1)

Application Number Title Priority Date Filing Date
JP22599583A Granted JPS60119804A (en) 1983-11-30 1983-11-30 Construction of off-shore structure

Country Status (1)

Country Link
JP (1) JPS60119804A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008125167A (en) * 2006-11-09 2008-05-29 Kawamura Electric Inc Attaching structure of charging unit protective cover
JP2011093643A (en) * 2009-10-28 2011-05-12 Toda Constr Co Ltd Construction device and construction method for foundation work of overhead viaduct
JP2011162988A (en) * 2010-02-09 2011-08-25 Kajima Corp Temporary pier and method for constructing the same

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008125167A (en) * 2006-11-09 2008-05-29 Kawamura Electric Inc Attaching structure of charging unit protective cover
JP2011093643A (en) * 2009-10-28 2011-05-12 Toda Constr Co Ltd Construction device and construction method for foundation work of overhead viaduct
JP2011162988A (en) * 2010-02-09 2011-08-25 Kajima Corp Temporary pier and method for constructing the same

Also Published As

Publication number Publication date
JPS6237166B2 (en) 1987-08-11

Similar Documents

Publication Publication Date Title
CN110984004B (en) Method for dismantling lower supporting structure of bridge
CN110344335A (en) A kind of method of steel trestle, initial platform and cofferdam construction in bridge construction process
JP2004285735A (en) Method of constructing temporary landing bridge by using truss frame
JPS60119804A (en) Construction of off-shore structure
CN109306699B (en) Construction method of Bailey bridge in permanent-temporary combined shallow water area
CN213507989U (en) Deepwater steel trestle capable of being constructed quickly
CN211735477U (en) A tower crane foundation structure for bridge tower construction
JP5769608B2 (en) Steel plate cell arc installation method and steel plate cell connection structure
JP3614489B2 (en) Pier construction method
RU2119004C1 (en) Berthing structure
JPH10331569A (en) Steel segment piece with joint box opened to its outer surface and method for constructing sunk body using the same
CN114802621B (en) Construction method of deep sea semi-submersible type cultivation travel platform
JPH1046597A (en) Execution work method of steel shell caisson
JPH10121450A (en) Binding engineering method of caison and foundation pile
JP2002047665A (en) Installation method for jacket structure
JP3132846B2 (en) Construction method of pile type offshore structure
JPS6314909A (en) Scour-proof construction for underwater structure
JPH09279541A (en) Revetment repairing construction method
JPH10331568A (en) Steel segment piece with concrete placed in hollow part thereof and method for constructing sunk body using the same
JP3268199B2 (en) Floating body launch equipment
JPH0742179A (en) Modified inversion placing construction method
JPS6146618B2 (en)
JPH0213098B2 (en)
Bloch et al. A PILE-DRIVING RIG FOR MARINE STRUCTURES.
GB2143269A (en) Bridges for traversing waterways