JPH10121450A - Binding engineering method of caison and foundation pile - Google Patents

Binding engineering method of caison and foundation pile

Info

Publication number
JPH10121450A
JPH10121450A JP29931896A JP29931896A JPH10121450A JP H10121450 A JPH10121450 A JP H10121450A JP 29931896 A JP29931896 A JP 29931896A JP 29931896 A JP29931896 A JP 29931896A JP H10121450 A JPH10121450 A JP H10121450A
Authority
JP
Japan
Prior art keywords
caisson
foundation pile
pile
concrete
template
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP29931896A
Other languages
Japanese (ja)
Inventor
Yoichi Zaisho
陽一 税所
Isao Saikawa
功 才川
Tetsuji Shibuya
哲二 渋谷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maeda Corp
Original Assignee
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maeda Corp filed Critical Maeda Corp
Priority to JP29931896A priority Critical patent/JPH10121450A/en
Publication of JPH10121450A publication Critical patent/JPH10121450A/en
Pending legal-status Critical Current

Links

Landscapes

  • Revetment (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a binding engineering method of a caison and a foundation pile capable of sufficiently securing binding power while speedily depositing binding concrete of the caison and the foundation pile. SOLUTION: This binding engineering method is to integrate a caison 1 and a foundation pile by depositing pile head binding concrete C2 underwater in a dead space after sinking the caison 1 through the foundation pile in the dead space formed by burying a sleeve pipe 50 in a bottom base concrete C of the caison 1. Thereby, an irregular part is formed by previously fixing band steels 53, 54 on an inner surface of the sleeve pipe 50 and on an outer surface of the foundation pile, and binding power is secured even without arrangement of reinforcing bars. Consequently, work is speedily progressed without arrangement of the reinforcing bars and attachment of seaweeds to reduce binding power of the pile head binding concrete C2 is prevented.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、ケーソンと基礎杭
との結合工法、特に、人工島などの施工に用いる巨体な
鋼殻ケーソンを、海底地盤に打設した複数の基礎杭上に
据え付けて固定する技術に関する。
BACKGROUND OF THE INVENTION The present invention relates to a method of joining a caisson and a foundation pile, in particular, a method in which a giant steel shell caisson used for construction of an artificial island or the like is installed on a plurality of foundation piles cast on the seabed ground. Related to fixing technology.

【0002】[0002]

【従来の技術】例えば、人工島のような巨体な海洋構造
物の施工においては、岸壁や護岸などの施工に用いる一
般的なコンクリート製ケーソンに代えて、巨体な鋼殻ケ
ーソンを用いることがある。この鋼殻ケーソン自体は、
上面が開口した内部中空な箱形に形成されるのが普通で
ある。
2. Description of the Related Art For example, in the construction of a huge marine structure such as an artificial island, a giant steel shell caisson may be used in place of a general concrete caisson used for construction of a quay or a seawall. . This steel shell caisson itself,
It is usually formed in the shape of a hollow box with an open top.

【0003】ところで、こうしたケーソンの従来の据え
付け工法としては、通常、海底に捨て石マウンドを形成
してその上に沈設する工法が採られる。しかし、水深が
深くて潮流も速く、しかも海底の地盤表面の支持強度が
十分でない場所では、海底地盤の支持層に達する基礎杭
を打設して、その基礎杭上にケーソンを据え付けて固定
する工法の採用が望ましい場合がある。実際に基礎杭上
にケーソンを固定するには、ケーソンの底部に複数の空
所を設け、この空所に基礎杭を貫通させた状態で、空所
に水中コンクリートを打設して、基礎杭とケーソンとを
結合させる工法が採られる。
As a conventional caisson installation method, a method of forming a waste stone mound on the sea floor and laying it on the mound is usually employed. However, in places where the water depth is deep and the tide is fast, and the supporting strength of the seabed ground surface is not sufficient, a foundation pile reaching the submarine ground support layer is cast, and a caisson is fixed on the foundation pile. It may be desirable to adopt a construction method. In order to actually fix the caisson on the foundation pile, a plurality of cavities are provided at the bottom of the caisson, and underwater concrete is poured into the vacant space with the foundation pile penetrated, and the foundation pile is pierced. And a caisson.

【0004】[0004]

【発明が解決しようとする課題】ところが、通常、コン
クリートを打設する場合には、補強用の鉄筋を予め配筋
したところにコンクリートを打設するが、上記のように
ケーソンの空所に鉄筋を配筋するには、スペースが狭い
ので作業できない。さらに、杭を打設してから杭頭結合
コンクリートを打設するまでに日数がかかってしまうこ
とにより、互いに一体化すべきコンクリート打設面に海
草が付着するおそれが生じる。海草が付着すると、コン
クリートの結合力が極端に低減するので、これは回避せ
ねばならない課題であった。また、杭頭部分に養生シー
トを被せておく対策も考えられるが手間がかかる。
However, usually, when concrete is cast, concrete is cast in places where reinforcing bars for reinforcement are arranged in advance. Can not work because the space is narrow. Furthermore, since it takes days from the placement of the pile to the placement of the pile head joint concrete, seaweed may adhere to the concrete placement surfaces to be integrated with each other. This is a problem that must be avoided because the adhesion of seaweed greatly reduces the bonding strength of concrete. A countermeasure to cover the pile head with a curing sheet is also conceivable, but it takes time.

【0005】本発明は上記事情に鑑みてなされたもので
あり、ケーソンと基礎杭との結合コンクリートを速やか
に打設できながら結合力も十分に確保できるケーソンと
基礎杭との結合工法を提供することを目的としている。
SUMMARY OF THE INVENTION The present invention has been made in view of the above circumstances, and provides a method of connecting a caisson and a foundation pile which can quickly pour the connection concrete between the caisson and the foundation pile while ensuring a sufficient bonding force. It is an object.

【0006】[0006]

【課題を解決するための手段】本発明は上記事情に鑑み
てなされたものであって、基礎杭が打設された海底地盤
上に、底部に複数の空所を有するケーソンを、前記空所
に前記基礎杭を貫通させた状態で沈設して据え付け、次
いで、前記空所にコンクリートを水中打設することによ
り、前記ケーソンと基礎杭とを一体化させるにあたり、
予め、前記ケーソンにおける前記空所に面する内面部分
および前記基礎杭における前記空所に面する外面部分
に、複数の凹凸部を形成しておくことを特徴としてい
る。上記工法において、前記凹凸部を、上下方向に凹凸
が形成された形態とすると好ましい。また、前記凹凸部
は、帯鋼等の機械要素を固定することにより形成するこ
ともできる。さらに、前記ケーソンを沈設する際に、該
ケーソンにおける前記空所に、該空所を密閉する蓋体を
撤去可能に取り付けておき、前記水中打設を行う際に
は、その蓋体を撤去するようにすると好ましい。
SUMMARY OF THE INVENTION The present invention has been made in view of the above circumstances. A caisson having a plurality of cavities at the bottom thereof is provided on a seabed on which a foundation pile is laid. In order to integrate the caisson and the foundation pile by sinking and installing the foundation pile in a state where the foundation pile is penetrated, and then by casting concrete in the void underwater,
A plurality of uneven portions are formed in advance on an inner surface of the caisson facing the void and an outer surface of the foundation pile facing the void. In the above method, it is preferable that the uneven portion has a form in which unevenness is formed in a vertical direction. In addition, the uneven portion can be formed by fixing a mechanical element such as a steel strip. Furthermore, when the caisson is laid down, a lid for sealing the cavity is detachably attached to the cavity in the caisson, and the lid is removed when the underwater casting is performed. It is preferable to do so.

【0007】[0007]

【発明の実施の形態】以下、本発明の好適な実施の形態
について、添付の図1〜図17を参照して説明する。図
1〜図5は、ケーソン(鋼殻ケーソン)据え付けの概略
を示す工程を順に示している。同工程を説明する前に、
まず、図5を参照してケーソンの構造や製作などについ
て概略的に説明する。符号1で示すケーソンは、骨組み
に大小の多数のH鋼、側板に鋼板等を用いた、いわゆる
鋼殻ケーソンからなり、内部中空な箱形に形成される。
このケーソン1は、上面が開口し、その内部が、互いに
平行する二つの隔壁2によって三つの室に区画されてい
る。隔壁2の下部は、底版コンクリートCを打設する部
分には設けられていない。つまり、隔壁2は底版コンク
リートC上から立ち上がる構造とされる。このケーソン
1の大きさは、縦、横、高さがそれぞれ数十メートルあ
るいはそれ以上にも及ぶ。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Preferred embodiments of the present invention will be described below with reference to the accompanying FIGS. 1 to 5 sequentially show steps showing the outline of caisson (steel shell caisson) installation. Before explaining the process,
First, the structure and fabrication of the caisson will be schematically described with reference to FIG. The caisson denoted by reference numeral 1 is formed of a so-called steel shell caisson using a large number of large and small H steels for the frame and steel plates for the side plates, and is formed in a hollow box shape inside.
The caisson 1 is open at the top and its interior is divided into three chambers by two partition walls 2 parallel to each other. The lower portion of the partition wall 2 is not provided at a portion where the concrete slab C is cast. That is, the partition 2 has a structure rising from the bottom slab concrete C. The size of the caisson 1 is several tens of meters or more in length, width, and height, respectively.

【0008】このような構造および大きさのケーソン1
を製作する場合には、例えば、造船所のドライドックを
利用して製作する。しかる後、コンクリートの打設作業
に適した岸壁等へ、ケーソン1を曳航して係留し、ケー
ソン1内に底版コンクリートCを打設する。この底版コ
ンクリートCの構造および機能などについて、図5を参
照してもう少し具体的に説明すると、ケーソン1は、底
版コンクリートCの打設後において、目的とする沈設場
所まで曳航され、そこで沈設される。この沈設に際して
は、予め施工しておいた支持杭10の頭部部分でテンプ
レート4を支持させ、そのテンプレート4上にケーソン
1を設置して固定する。テンプレート4は、水中コンク
リートの打設によって支持杭10を含む多数の基礎杭3
と一体化され、しかも各基礎杭3の頭部はテンプレート
4を貫通してケーソン1内に挿入される構造となる。
A caisson 1 having such a structure and size
Is manufactured, for example, using a dry dock of a shipyard. Thereafter, the caisson 1 is towed and moored to a quay or the like suitable for the concrete placement work, and the bottom concrete C is placed in the caisson 1. The structure and function of the bottom slab concrete C will be described more specifically with reference to FIG. 5. After the bottom slab concrete C is cast, the caisson 1 is towed to a target sunk place and sunk there. . At the time of this submersion, the template 4 is supported by the head part of the support pile 10 previously constructed, and the caisson 1 is set and fixed on the template 4. The template 4 includes a plurality of foundation piles 3 including support piles 10 by casting underwater concrete.
And the head of each foundation pile 3 is inserted into the caisson 1 through the template 4.

【0009】したがって、底版コンクリートCの部分に
は、各基礎杭3の頭部をそれぞれ引き込むための多数の
空所5が形成されている。これら空所5は、ケーソン1
の製作時に予め設けられ、ケーソン1自体が船体として
の機能を有するように、沈設完了までは水密性を有する
後述する仮蓋で密閉される。図5において符号6は杭頭
結合コンクリートの打設部分、7はガスケット、8a、
8bは側壁、9は上床梁を示している。
Therefore, a large number of cavities 5 are formed in the bottom slab concrete C for drawing in the heads of the respective foundation piles 3. These voids 5 are caisson 1
The caisson 1 is sealed in advance by a water-tight temporary lid so that the caisson 1 itself functions as a hull until completion of the submersion. In FIG. 5, reference numeral 6 denotes a cast-in portion of a pile head joint concrete, 7 denotes a gasket, 8a,
8b is a side wall, 9 is an upper floor beam.

【0010】次に、このケーソン1の据え付け工程につ
いて具体的に説明する。まず、図1に示すように、海底
地盤Gに対して、テンプレート4を支持するための支持
杭10、およびテンプレート4の沈設に際してこれをガ
イドするためのガイド杭20を打設する。支持杭10の
打設本数としては、テンプレート4の大きさや強度に合
わせて決定されるが、少なくとも4本以上打設して、テ
ンプレート4を海底近くで安定に支持できるようにす
る。なお、テンプレート4の構造や機能については後述
するが、その全体構造としては、図6に示すように、平
面格子状の枠組み鋼構造物である。
Next, the process of installing the caisson 1 will be specifically described. First, as shown in FIG. 1, a support pile 10 for supporting the template 4 and a guide pile 20 for guiding the template 4 when the template 4 is laid are placed on the seabed ground G. The number of the support piles 10 to be driven is determined according to the size and strength of the template 4. At least four or more support piles 10 are driven so that the template 4 can be stably supported near the seabed. Although the structure and function of the template 4 will be described later, as shown in FIG. 6, the overall structure is a frame steel structure having a plane lattice shape.

【0011】一方、ガイド杭20については、テンプレ
ート4の長手方向の両端近くに少なくとも2本打設す
る。その際、両ガイド杭20、20は、それぞれがテン
プレート4の幅方向中央位置になるように配慮するのが
好適である。なお、このガイド杭20は、テンプレート
4の沈設時のガイドとして用いるので、それらの頭部
(上端)が海面よりも突出する長さとなるように設定す
る。
On the other hand, at least two guide piles 20 are driven near both ends in the longitudinal direction of the template 4. At this time, it is preferable that both guide piles 20 and 20 be considered so as to be located at the center position in the width direction of template 4. Since the guide piles 20 are used as guides when the template 4 is laid, the heads (upper ends) of the guide piles 20 are set to have a length protruding from the sea surface.

【0012】また、支持杭10の頭部、およびガイド杭
20の外周部分に、テンプレート4の下面を受けるため
の支承部材11、21をそれぞれ取り付けておく。これ
ら支承部材11、21は互いに同じレベルとなるように
する。ガイド杭20の支承部材21については、ガイド
杭20の外周部分に水中溶接等の手段により固定する
が、支持杭10の支承部材11については、支持杭10
の頭部上に固定する構造とするのが好適である。こうす
る方が、構造強度および作業性などの点において有利に
なるからである。また、各支承部材11、21の何れ
も、中央に位置する支持杭10およびガイド杭20の外
径よりも平面的に十分に大きくなるように設計してい
る。これは、テンプレート4を安定に支持する上で十分
に大きな受圧面積を得ることができるようにするためで
ある。
Further, bearing members 11 and 21 for receiving the lower surface of the template 4 are attached to the head of the support pile 10 and the outer peripheral portion of the guide pile 20, respectively. These support members 11 and 21 are at the same level as each other. The support member 21 of the guide pile 20 is fixed to the outer peripheral portion of the guide pile 20 by means such as underwater welding, but the support member 11 of the support pile 10 is
It is preferable to adopt a structure to be fixed on the head of the camera. This is because this is advantageous in terms of structural strength and workability. Each of the support members 11 and 21 is designed to be sufficiently larger in plan than the outer diameters of the support pile 10 and the guide pile 20 located at the center. This is to ensure that a sufficiently large pressure receiving area can be obtained for stably supporting the template 4.

【0013】このようにして支持杭10およびガイド杭
20の施工を終えたら、必要に応じて支持杭20の切断
および置換砂工等を行い、しかる後、支持部材11、2
1の取り付け作業を行い、その後、テンプレート4を、
ガイド杭20をガイドに利用して沈設する。
After the support pile 10 and the guide pile 20 have been constructed in this way, the support pile 20 is cut and sand-removed if necessary.
After performing the mounting work of 1, the template 4 is
The guide pile 20 is used as a guide to settle.

【0014】テンプレート4は、図6に示すように、平
面格子状の枠組み鋼構造物として構成されている。すな
わち、大型のH鋼やI型鋼などを溶接して格子状に組ん
だもので、その多数ある升目のうち、正方形の升目とな
っている箇所が、基礎杭3の打設に際して、その基礎杭
3を上から通して位置決めした状態で打設することがで
きるように設計している部分である。
As shown in FIG. 6, the template 4 is configured as a frame steel structure having a plane lattice shape. That is, a large H steel or I-type steel is welded and assembled in a lattice shape, and among the many squares, a square square is used when the foundation pile 3 is driven. 3 is designed to be able to be driven while being positioned from above.

【0015】一方、前記ケーソン1における底版コンク
リートCの部分に形成してある空所5は、図9(a)、
(b)に示すように、基礎杭3よりも大径のスリーブ管
50が底版コンクリートCに埋設されることにより設け
られている。スリーブ管50はケーソン1の製作時に予
め設けられ、その上端開口には、ケーソン1自体が船体
としての機能を有するように、沈設完了までは水密性を
有する円盤状の仮蓋(蓋体)51で密閉される。この仮
蓋51は、スリーブ管50の上端内周縁に設けられた環
状ブラケット52に載せられ、複数の図示せぬボルトで
固定される。
On the other hand, the cavity 5 formed in the bottom slab concrete C in the caisson 1 is shown in FIG.
As shown in (b), a sleeve pipe 50 having a larger diameter than the foundation pile 3 is provided by being buried in the bottom concrete C. The sleeve tube 50 is provided in advance when the caisson 1 is manufactured, and a water-tight disk-shaped temporary lid (cover) 51 is provided at the upper end opening so that the caisson 1 itself has a function as a hull until completion of the submersion. Sealed. The temporary lid 51 is placed on an annular bracket 52 provided on the inner peripheral edge of the upper end of the sleeve tube 50, and is fixed by a plurality of bolts (not shown).

【0016】また、スリーブ管50の内周面及び外周面
と基礎杭3の内周面及び外周面には、多数の帯鋼(機械
要素)53、54がそれぞれ固定されていることにより
凹凸部が形成されている。これら帯鋼53、54は、ス
リーブ管50および基礎杭3に対し、周方向と軸方向に
沿って多数固定されている。なお、図9の符号55は、
底版コンクリートC中に埋設された補強用の鉄筋であ
る。
Further, a large number of steel strips (mechanical elements) 53 and 54 are fixed to the inner and outer peripheral surfaces of the sleeve tube 50 and the inner and outer peripheral surfaces of the foundation pile 3, respectively. Are formed. A large number of these steel strips 53 and 54 are fixed to the sleeve tube 50 and the foundation pile 3 along the circumferential direction and the axial direction. Note that reference numeral 55 in FIG.
This is a reinforcing steel bar buried in the bottom slab concrete C.

【0017】テンプレート4の周囲には、ケーソン1の
沈設時におけるそのケーソン1の沈設位置ガイドとして
機能させるためのガイド装置40を複数設けている。こ
のガイド装置40は、図7および図8に示すように、ケ
ーソン1の底部周囲をガイドする斜面40aを備えた構
成となっている。また、テンプレート4における前記空
所5が設けられる以外の升目の適宜箇所は、図8に示す
ように、十字材4bと斜材4cとにより補強がなされて
いる。なお、このテンプレート4は陸上で地組みし、た
とえば、大型のクレーン船にて吊り上げた状態で沈設現
場まで海上輸送される。吊り上げには、テンプレート4
の撓みを少なくするために、多数の吊り上げワイヤを用
いると好ましい。
A plurality of guide devices 40 are provided around the template 4 so as to function as guides for setting the caisson 1 when the caisson 1 is set. As shown in FIGS. 7 and 8, the guide device 40 has a configuration including a slope 40 a that guides around the bottom of the caisson 1. Further, as shown in FIG. 8, a suitable portion of a square other than the space 5 in the template 4 is reinforced by a cross member 4b and a diagonal member 4c. The template 4 is laid on land and, for example, lifted by a large crane ship and transported by sea to a submerging site. Template 4 for lifting
It is preferable to use a large number of lifting wires in order to reduce the bending of the wire.

【0018】そして、このテンプレート4の沈設に際し
ては、クレーン船で吊り上げた状態でガイド杭20との
位置合わせを行い、しかる後、次第に吊り下ろすことに
よって自重により沈下させつつ、支持杭10上に沈設す
ればよい。こうすることで、テンプレート4は支持杭1
0およびガイド杭20の支承部材11、21によって海
底近くにしっかりと支持される。したがって、この状態
で、支持杭10およびガイド杭20に対するテンプレー
ト4の固定を行う。
When the template 4 is settled, the template 4 is aligned with the guide pile 20 in a state of being lifted by a crane ship. Thereafter, the template 4 is gradually lowered and settled on the support pile 10 while being settled by its own weight. do it. In this way, the template 4 becomes the support pile 1
0 and the support members 11 and 21 of the guide pile 20 are firmly supported near the seabed. Therefore, in this state, the template 4 is fixed to the support pile 10 and the guide pile 20.

【0019】テンプレート4の固定作業を終えたら、次
に、図3に示すように、ガイド杭20の上部を切断し、
その後、テンプレート4を定規として多数の基礎杭3を
打設する。この基礎杭3の打設に際しては、升目を合わ
せることにより、相互に必要な間隔をおいて、目的とす
る位置に高精度に打設することができる。
After the fixing work of the template 4 is completed, the upper part of the guide pile 20 is cut next, as shown in FIG.
After that, a large number of foundation piles 3 are set using the template 4 as a ruler. At the time of placing the foundation pile 3, by matching the grids, it is possible to place the foundation pile 3 at a required interval with high accuracy at a target position.

【0020】各基礎杭3の打設作業を終えたら、図3に
示すように、必要に応じてテンプレート4の外周に中詰
め砂Sの充填作業を行い、さらに、テンプレート水中コ
ンクリート工C1を打設する。中詰め砂Sは、水中コン
クリート工C1を行う前の均し作業を兼ねており、水中
コンクリートC1は、支持杭10、ガイド杭20を含む
多数の基礎杭3と、テンプレート4とのコンクリートに
よる一体化を図る役割を受け持つ。なお、この水中コン
クリート工C1の厚さについては、テンプレート4上に
ケーソン1を設置することを考慮して、テンプレート4
の上面よりも上に突出しないように配慮される。
After completing the work of placing the foundation piles 3, as shown in FIG. 3, the outer periphery of the template 4 is filled with the filling sand S if necessary, and the template underwater concrete work C1 is driven. Set up. The filling sand S also serves as a leveling operation before the underwater concrete work C1 is performed, and the underwater concrete C1 is integrated with a large number of foundation piles 3 including the support pile 10 and the guide pile 20 and the template 4 by concrete. Responsible for the role. The thickness of the underwater concrete work C1 is determined in consideration of the caisson 1 being set on the template 4.
Care is taken not to protrude above the upper surface of the.

【0021】以上のようにして、ケーソン1を沈設する
のに必要な基礎工程を終えたら、次に、図4に示すよう
に、ケーソン1を沈設位置まで曳航し、テンプレート4
の直上に位置決めした状態で沈下させる。このケーソン
1の沈設に際しては、ケーソン1内に海水をバラスト水
として注水して行う。また、ケーソン1を目的とする位
置に鉛直に沈下させるために、ここでは特に図示してい
ないが、起重機船の他に、コンピュータを利用した解析
および画像表示等による沈設姿勢制御および計測システ
ムを用いて行う。
After completing the basic steps necessary for laying the caisson 1 as described above, the caisson 1 is then towed to the laying position, as shown in FIG.
Settle down just above. When the caisson 1 is submerged, seawater is injected into the caisson 1 as ballast water. In order to cause the caisson 1 to sink vertically to the target position, a sinking attitude control and measurement system using a computer-based analysis and image display is used in addition to the hoisting ship, although not specifically shown here. Do it.

【0022】こうして、ケーソン1を正確に順次沈下さ
せることによって、そのケーソン1の底部をテンプレー
ト4上に沈設する。図5はその状態を示しており、ここ
で、ケーソン1の底部がテンプレート4の上に載る直前
において、仮に、テンプレート4に対するケーソン1の
相対位置が設計位置より若干ずれていた場合には、テン
プレート4の周囲に設けてあるガイド装置40の働きに
より、すなわち、傾斜面40aの作用によってケーソン
1は所定の位置に案内される。
In this manner, the caisson 1 is settled accurately and sequentially, so that the bottom of the caisson 1 is set down on the template 4. FIG. 5 shows this state. If the relative position of the caisson 1 with respect to the template 4 is slightly shifted from the design position immediately before the bottom of the caisson 1 is placed on the template 4, the template The caisson 1 is guided to a predetermined position by the action of the guide device 40 provided around the periphery 4, that is, by the action of the inclined surface 40a.

【0023】そして、ケーソン1の底部がテンプレート
4上に載り、いわゆる着底した状態では、ガイド装置4
0全体の働きによって、ケーソン1はテンプレート4に
対してしっかりと位置決めされる。すなわち、ケーソン
1はガイド装置40によって水平方向に移動しないよう
拘束される。したがって、ケーソン1はテンプレート4
上に安定状態で支持されることになる。その結果、ケー
ソン1自体が潮流等の影響を受けても、これにより不安
定になるようなことがない。勿論、テンプレート4とケ
ーソン1とをボルトなどによって固定することにより、
さらに安定状態で基礎杭3上に支持することができる。
When the bottom of the caisson 1 rests on the template 4 and is so-called landed, the guide device 4
The caisson 1 is firmly positioned with respect to the template 4 by the action of the whole zero. That is, the caisson 1 is restrained by the guide device 40 so as not to move in the horizontal direction. Therefore, caisson 1 has template 4
It will be supported in a stable state above. As a result, even if the caisson 1 itself is affected by a tidal current or the like, the caisson 1 does not become unstable due to this. Of course, by fixing the template 4 and the caisson 1 with bolts or the like,
Further, it can be supported on the foundation pile 3 in a stable state.

【0024】上記のようにケーソン1の沈設作業を終え
たら、次に、ガスケット7に対するケーソン荷重による
クリープ変形が杭頭結合時にコンクリートの硬化による
影響を与えないようにするため、スリーブ管50を除い
たテンプレートとケーソンとの隙間を特殊モルタルで充
填する。その後、本発明に係る杭頭結合コンクリートC
2の水中打設に移る。
After the caisson 1 is settled as described above, the sleeve tube 50 is removed next so that the creep deformation of the gasket 7 due to the caisson load does not affect the concrete hardening when the pile head is joined. The gap between the template and caisson is filled with special mortar. Then, the pile head joint concrete C according to the present invention
Move on to 2 underwater casting.

【0025】杭頭結合コンクリートC2を水中打設する
にあたっては、まず、図10に示すように、仮蓋51を
スリーブ管50の環状ブラケット52に固定している全
てのボルトを、潜水士である作業員Pが水中切断する。
これで仮蓋51は環状ブラケット52上に単に載ってい
るだけとなる。次に、図11に示すように、予め形成さ
れている吊り用孔にシャックル等を使用して吊りタワー
クレーン等に係合させたワイヤ60を引掛ける。次い
で、タワークレーンでワイヤ60を上昇させて仮蓋51
を吊り上げ、図12および図13に示すように撤去す
る。この際、底版コンクリートC中の鉄筋55を痛めな
いよう配慮する。
In placing the pile head joint concrete C2 underwater, first, as shown in FIG. 10, all bolts fixing the temporary lid 51 to the annular bracket 52 of the sleeve tube 50 are divers. Worker P cuts underwater.
As a result, the temporary lid 51 simply rests on the annular bracket 52. Next, as shown in FIG. 11, a wire 60 engaged with a suspension tower crane or the like is hooked on a suspension hole formed in advance using a shackle or the like. Next, the wire 60 is raised by a tower crane, and the temporary lid 51 is lifted.
Is lifted and removed as shown in FIGS. At this time, care is taken not to damage the reinforcing bar 55 in the bottom slab concrete C.

【0026】上記のように仮蓋51を撤去したら、杭頭
結合コンクリート打設管であるトレミー管61を、スリ
ーブ管50内に導入する。トレミー管61は、図14に
示すように、ケーソン1の両側方に係留させたコンクリ
ートミキサー船70のクレーン71からケーソン1内に
沈下させ、まず、その先端を図15に示すように、作業
員Pによってスリーブ管50と基礎杭3との間に誘導
し、ここに杭頭結合コンクリートC2を打設する。スリ
ーブ管50と基礎杭3との間において杭頭結合コンクリ
ートC2が基礎杭3の上端まで達したら一旦打設を停止
し、今度は図16に示すように、作業員Pがトレミー管
61を基礎杭3の内部に誘導し、その内部に杭頭結合コ
ンクリートC2を打設する。
After the temporary lid 51 is removed as described above, the tremee pipe 61, which is a pile head-joined concrete casting pipe, is introduced into the sleeve pipe 50. The tremee pipe 61 is lowered into the caisson 1 from the crane 71 of the concrete mixer ship 70 moored on both sides of the caisson 1 as shown in FIG. It is guided between the sleeve pipe 50 and the foundation pile 3 by P, and the pile head connection concrete C2 is cast here. When the pile head connection concrete C2 reaches the upper end of the foundation pile 3 between the sleeve pipe 50 and the foundation pile 3, the driving is temporarily stopped, and as shown in FIG. The pile is guided into the inside of the pile 3, and the pile head combined concrete C2 is poured into the inside.

【0027】なお、杭頭結合コンクリートC2は、水中
不分離性コンクリートが用いられ、その組成としては、
たとえば下記表1に示すようなものである。杭頭結合コ
ンクリートC2は、図17に示すように、基礎杭3の上
端と底版コンクリートCの上端の間における所定高さの
位置まで打設する。その天端位置は、作業員Pが打設定
規62で確認しながら行い、例えば、仮蓋51を固定し
ていた環状ブラケット52までである。
The pile head joint concrete C2 is a non-separable underwater concrete. Its composition is as follows.
For example, it is as shown in Table 1 below. As shown in FIG. 17, the pile head joint concrete C2 is cast to a position at a predetermined height between the upper end of the foundation pile 3 and the upper end of the bottom slab concrete C. The top position is determined by the worker P while confirming the hit setting rule 62, and is, for example, up to the annular bracket 52 to which the temporary lid 51 is fixed.

【0028】◎

【表1】 [Table 1]

【0029】以上のように杭頭結合コンクリートC2を
打設すると、ケーソン1と支持杭10およびガイド杭2
0を含む基礎杭3との一体化が、杭頭結合コンクリート
C2を介して図られる。ここで、図9に示すように、ス
リーブ管50の内外周面と基礎杭3の内外周面には、多
数の帯鋼53、54がそれぞれ固定されていることによ
り凹凸が形成されているので、杭頭結合コンクリートC
2の双方に対する結合が強固になる。その結果、杭頭結
合コンクリートC2を介してのケーソン1と支持杭10
およびガイド杭20を含む基礎杭3との一体化がより強
固になる。特に、帯鋼による凹凸が上下方向に並んでい
ることにより、杭頭結合コンクリートC2が空所5から
抜けるおそれがない。また、帯鋼53、54は、溶接に
よって簡単に固定させることができ、スリーブ管50や
基礎杭3に複雑な加工を施すことなく容易に凹凸を形成
することができる。
When the pile head-joined concrete C2 is cast as described above, the caisson 1, the support pile 10, and the guide pile 2
Integration with the foundation pile 3 including 0 is achieved via the pile head connection concrete C2. Here, as shown in FIG. 9, irregularities are formed on the inner and outer peripheral surfaces of the sleeve pipe 50 and the inner and outer peripheral surfaces of the foundation pile 3 by fixing a number of strips 53 and 54 respectively. , Pile head combined concrete C
The bond to both of the two becomes stronger. As a result, the caisson 1 and the supporting pile 10 via the pile head joint concrete C2
And the integration with the foundation pile 3 including the guide pile 20 is further strengthened. In particular, since the unevenness of the steel strip is vertically arranged, there is no possibility that the pile head joint concrete C2 will fall out of the empty space 5. Further, the steel strips 53 and 54 can be easily fixed by welding, and the irregularities can be easily formed without performing complicated processing on the sleeve pipe 50 and the foundation pile 3.

【0030】このように、杭頭結合コンクリートC2を
水中打設するにあたって、通常であるならば、ケーソン
1と基礎杭3との結合強化を図るため、スリーブ管50
内や基礎杭3内に鉄筋等の補強筋を配筋することにな
る。しかしながら、狭い中での配筋作業はほとんど不可
能な上、スリーブ管50や基礎杭3の表層に海草を付着
させてしまう時間的猶予を与えてしまう。このように海
草が付着してしまうと、杭頭結合コンクリートC2の結
合力が極端に低減してしまう。ところが本実施形態で
は、スリーブ管50と基礎杭3に多数の帯鋼53、54
により凹凸が形成されて、杭頭結合コンクリートC2の
結合力が確保されるので鉄筋を配筋する必要が無く、も
って作業の迅速化が図られるに伴って海草の付着といっ
た問題、すなわち杭頭結合コンクリートC2の結合力の
低減も解消し得るのである。
As described above, when the pile head connection concrete C2 is poured underwater, if necessary, the sleeve pipe 50 is usually used to strengthen the connection between the caisson 1 and the foundation pile 3.
Reinforcing bars such as reinforcing bars are to be arranged inside or inside the foundation pile 3. However, rebar arrangement work in a narrow space is almost impossible, and time for attaching seaweed to the surface of the sleeve tube 50 and the foundation pile 3 is given. If the seaweed adheres in this way, the bonding force of the pile head-bound concrete C2 will be extremely reduced. However, in the present embodiment, a large number of steel strips 53, 54 are provided on the sleeve pipe 50 and the foundation pile 3.
As a result, there is no need to arrange reinforcing bars because the unevenness is formed and the joining force of the pile head connection concrete C2 is secured. The reduction in the bonding force of the concrete C2 can be eliminated.

【0031】以上のようにして杭頭結合コンクリートC
2の水中打設が終わったら、必要な程度にケーソン1内
の排水作業を行いながら、隔壁2、側壁8a、8b部分
のコンクリート打設作業を実施する。排水作業に際して
は、隔壁2、側壁8a、8b部分のコンクリート打設作
業の進行に合わせて行い、少なくともケーソン1に浮力
が生じないように配慮しつつ行うことになる。
As described above, the pile head combined concrete C
After completion of the submerged casting of 2, the concrete casting of the partition wall 2 and the side walls 8a and 8b is performed while draining the caisson 1 to the extent necessary. The drainage operation is performed in accordance with the progress of the concrete placing operation of the partition wall 2 and the side walls 8a and 8b, and is performed while taking care not to generate buoyancy at least in the caisson 1.

【0032】[0032]

【発明の効果】以上説明したように本発明によれば、ケ
ーソンにおける基礎杭が貫通される空所に面する内面部
分および基礎杭における前記空所に面する外面部分に複
数の凹凸部を形成しておき、空所にコンクリートを打設
してケーソンと基礎杭を一体化させるので、空所に鉄筋
頭を配筋することなくコンクリートを速やかに打設でき
ながら、そのコンクリートにより十分な結合力が確保さ
れる。
As described above, according to the present invention, a plurality of concavities and convexities are formed on the inner surface of the caisson facing the space through which the foundation pile penetrates and on the outer surface of the foundation pile facing the cavity. In addition, concrete is poured into the void and the caisson and the foundation pile are integrated, so that concrete can be quickly poured without arranging reinforcing steel heads in the void, and the concrete has sufficient bonding strength Is secured.

【0033】また、前記凹凸部を上下方向に凹凸が形成
される形態にすることにより、コンクリートの抜けが回
避されるとともに、結合力が促進される。
Further, by forming the irregularities in a form in which irregularities are formed in the vertical direction, the concrete is prevented from coming off and the bonding force is promoted.

【0034】また、前記凹凸部を、帯鋼等の機械要素を
固定して形成することにより、空所の内面や基礎杭に複
雑な加工を施すことなく容易に凹凸部を形成することが
できる。
In addition, by forming the uneven portion by fixing a mechanical element such as a steel strip, the uneven portion can be easily formed without performing complicated processing on the inner surface of the space or the foundation pile. .

【0035】さらに、ケーソンを沈設する際に、該ケー
ソンにおける空所に、該空所を密閉する蓋体を撤去可能
に取り付けておき、コンクリートの水中打設を行う際に
はその蓋体を撤去するようにすれば、ケーソン内に海水
が浸入しないので、ケーソンを船体として機能させて現
場まで曳航して運搬できる。
Further, when the caisson is laid, a cover for sealing the cavity is detachably attached to the space in the caisson, and the cover is removed when concrete is poured into water. By doing so, seawater does not enter the caisson, so that the caisson can function as a hull and be towed to the site for transport.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明に係るケーソンと基礎杭との結合工法
の工程1を示す側面図である。
FIG. 1 is a side view showing Step 1 of a method of connecting a caisson and a foundation pile according to the present invention.

【図2】 同工法の工程2を示す側面図である。FIG. 2 is a side view showing step 2 of the method.

【図3】 同工法の工程3を示す側面図である。FIG. 3 is a side view showing step 3 of the method.

【図4】 同工法の工程4を示す側面図である。FIG. 4 is a side view showing step 4 of the method.

【図5】 同工法の工程5を示す側面図である。FIG. 5 is a side view showing step 5 of the method.

【図6】 テンプレートの概略平面図である。FIG. 6 is a schematic plan view of a template.

【図7】 ガイド装置の側面図である。FIG. 7 is a side view of the guide device.

【図8】 テンプレートの要部斜視図である。FIG. 8 is a perspective view of a main part of the template.

【図9】 ケーソンと基礎杭の結合状態を示す説明図で
ある。
FIG. 9 is an explanatory view showing a connection state of a caisson and a foundation pile.

【図10】仮蓋撤去の工程1を示す側面図である。FIG. 10 is a side view showing step 1 of removing a temporary lid.

【図11】同工程2を示す側面図である。FIG. 11 is a side view showing the same step 2;

【図12】同工程3を示す側面図である。FIG. 12 is a side view showing the same step 3;

【図13】同工程4を示す側面図である。FIG. 13 is a side view showing the same step 4;

【図14】杭頭結合コンクリートの打設状態を示す概略
側面図である。
FIG. 14 is a schematic side view showing a state where a pile head combined concrete is poured.

【図15】杭頭結合コンクリートの打設工程1を示す側
面図である。
FIG. 15 is a side view showing a placing process 1 of the pile head combined concrete.

【図16】同工程2を示す側面図である。FIG. 16 is a side view showing the same step 2;

【図17】同工程3を示す側面図である。FIG. 17 is a side view showing the same step 3;

【符号の説明】[Explanation of symbols]

1 ケーソン 3 基礎杭 5 空所 10 支持杭 11 支承部材 20 ガイド杭 21 支承部材 21a H形鋼 21b 斜材 21c 支持ブラケット 40 ガイド装置 40a 斜面 50 スリーブ管 51 仮蓋(蓋体) 52 環状ブラケット 53、54 帯鋼(凹凸部、機械要素) 55 補強筋 60 ワイヤ 61 トレミー管 62 打設定規 70 コンクリートミキサー船 C2 杭頭結合コンクリート G 海底地盤 DESCRIPTION OF REFERENCE NUMERALS 1 caisson 3 foundation pile 5 void 10 support pile 11 support member 20 guide pile 21 support member 21a H-section steel 21b diagonal material 21c support bracket 40 guide device 40a slope 50 sleeve pipe 51 temporary lid (lid) 52 annular bracket 53, 54 Strip steel (uneven part, mechanical element) 55 Reinforcing bar 60 Wire 61 Ptolemy tube 62 Striking set rule 70 Concrete mixer ship C2 Pile head joint concrete G Submarine ground

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 基礎杭が打設された海底地盤上に、底部
に複数の空所を有するケーソンを、前記空所に前記基礎
杭を貫通させた状態で沈設して据え付け、次いで、前記
空所にコンクリートを水中打設することにより、前記ケ
ーソンと基礎杭とを一体化させるにあたり、 予め、前記ケーソンにおける前記空所に面する内面部分
および前記基礎杭における前記空所に面する外面部分
に、複数の凹凸部を形成しておくことを特徴とするケー
ソンと基礎杭との結合工法。
1. A caisson having a plurality of cavities at the bottom is laid down and installed on the seabed ground on which a foundation pile is cast, with the foundation pile being penetrated into the cavity, and In order to integrate the caisson and the foundation pile by placing concrete underwater in a place, in advance, an inner surface part facing the void in the caisson and an outer part facing the void in the foundation pile A method of connecting a caisson and a foundation pile, characterized by forming a plurality of uneven portions.
【請求項2】 前記凹凸部は、上下方向に凹凸が形成さ
れていることを特徴とする請求項1に記載のケーソンと
基礎杭との結合工法。
2. The method according to claim 1, wherein the uneven portion is formed with unevenness in a vertical direction.
【請求項3】 前記凹凸部は、帯鋼等の機械要素を固定
することにより形成することを特徴とする請求項1ある
いは2に記載のケーソンと基礎杭との結合工法。
3. The method of connecting a caisson to a foundation pile according to claim 1, wherein the uneven portion is formed by fixing a mechanical element such as a steel strip.
【請求項4】 前記ケーソンを沈設する際に、該ケーソ
ンにおける前記空所に、該空所を密閉する蓋体を撤去可
能に取り付けておき、前記水中打設を行う際には、その
蓋体を撤去することを特徴とする請求項1〜3に記載の
ケーソンと基礎杭との結合工法。
4. When the caisson is laid down, a lid for sealing the cavity is detachably attached to the cavity in the caisson, and the lid is used when the underwater casting is performed. The method of connecting a caisson and a foundation pile according to any one of claims 1 to 3, wherein
JP29931896A 1996-10-24 1996-10-24 Binding engineering method of caison and foundation pile Pending JPH10121450A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP29931896A JPH10121450A (en) 1996-10-24 1996-10-24 Binding engineering method of caison and foundation pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP29931896A JPH10121450A (en) 1996-10-24 1996-10-24 Binding engineering method of caison and foundation pile

Publications (1)

Publication Number Publication Date
JPH10121450A true JPH10121450A (en) 1998-05-12

Family

ID=17870995

Family Applications (1)

Application Number Title Priority Date Filing Date
JP29931896A Pending JPH10121450A (en) 1996-10-24 1996-10-24 Binding engineering method of caison and foundation pile

Country Status (1)

Country Link
JP (1) JPH10121450A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012162858A (en) * 2011-02-03 2012-08-30 Shimizu Corp Caisson and caisson installation method to foundation pile
JP2017503101A (en) * 2014-01-15 2017-01-26 シービージェイ(香港) オーシャン エンジニアリング リミテッドCbj(Hong Kong) Ocean Engineering Limited Water structure fixing roll and its construction method
CN114277821A (en) * 2021-12-29 2022-04-05 中交路桥建设有限公司 Bottom-sealing-free jacket box system and installation method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012162858A (en) * 2011-02-03 2012-08-30 Shimizu Corp Caisson and caisson installation method to foundation pile
JP2017503101A (en) * 2014-01-15 2017-01-26 シービージェイ(香港) オーシャン エンジニアリング リミテッドCbj(Hong Kong) Ocean Engineering Limited Water structure fixing roll and its construction method
CN114277821A (en) * 2021-12-29 2022-04-05 中交路桥建设有限公司 Bottom-sealing-free jacket box system and installation method thereof

Similar Documents

Publication Publication Date Title
JP4793634B2 (en) Temporary deadline construction method
JP5830423B2 (en) Pile type offshore structure construction method and pile type offshore structure
CN106812144A (en) Double-wall steel cofferdam construction method
KR101256274B1 (en) Reverse Drill Method With precast type Caisson and Jacket
CN109707002B (en) Device and method for accurately positioning, sinking and installing large water intake head
CN110939148A (en) Construction method of double-wall steel suspension box cofferdam serving as drilling platform
JP2004285735A (en) Method of constructing temporary landing bridge by using truss frame
US3890794A (en) Method of replacing piling
JPH10121450A (en) Binding engineering method of caison and foundation pile
JP2005264514A (en) Foundation slab structure of sea berth structure, and its construction method
JP3463604B2 (en) Dolphin construction method
JPH1046597A (en) Execution work method of steel shell caisson
JP5769608B2 (en) Steel plate cell arc installation method and steel plate cell connection structure
JP4529529B2 (en) Construction method of underwater structure
KR102535841B1 (en) Construction method of pier foundation using floating PC houses
JPS598835A (en) Footing type steel plate cell caisson work
JP2002047665A (en) Installation method for jacket structure
JPS60215924A (en) Settlement of steel skeleton for underwater foundation structure
JP2002121753A (en) Floating construction method for pier
JPH09279541A (en) Revetment repairing construction method
KR20110024767A (en) Device for constructing pier in the water and pier constructing method using the same
JPH0213098B2 (en)
JP2001214419A (en) Method for setting up ocean stricture using caisson
JPH09302669A (en) Caisson installation construction method
JP2024057389A (en) Substructure for floating offshore wind power generation and construction method for the substructure for floating offshore wind power generation