JPS5996358A - Construction of steel structural roof or upper stair floor - Google Patents

Construction of steel structural roof or upper stair floor

Info

Publication number
JPS5996358A
JPS5996358A JP20449882A JP20449882A JPS5996358A JP S5996358 A JPS5996358 A JP S5996358A JP 20449882 A JP20449882 A JP 20449882A JP 20449882 A JP20449882 A JP 20449882A JP S5996358 A JPS5996358 A JP S5996358A
Authority
JP
Japan
Prior art keywords
roof
construction
upper floor
beams
height
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP20449882A
Other languages
Japanese (ja)
Other versions
JPS62309B2 (en
Inventor
寛次 山田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Nippon Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Corp filed Critical Nippon Steel Corp
Priority to JP20449882A priority Critical patent/JPS5996358A/en
Publication of JPS5996358A publication Critical patent/JPS5996358A/en
Publication of JPS62309B2 publication Critical patent/JPS62309B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 本発明は、鋼構造屋根または上階床の施工時に、主梁と
つなぎ梁等の直交する梁組からなる、いわゆる平面骨組
の屋根または上階床を上架前に組立てた後、吊り上げる
か或いは押し上げて所定の高さ位置に上架する施工方法
の改良に関する。
DETAILED DESCRIPTION OF THE INVENTION When constructing a steel structure roof or upper floor, the so-called flat frame roof or upper floor, which is composed of orthogonal beam sets such as main beams and connecting beams, is assembled before being elevated. This relates to an improvement in a construction method in which the structure is then lifted or pushed up to a predetermined height.

従来、屋根及び上階床の骨組を組立てる場合には、所定
の高さ位置に順次、該当する部材単品を上架する施工方
法が主流を占めていた。
Conventionally, when assembling frames for roofs and upper floors, the mainstream construction method has been to sequentially erect individual members at predetermined height positions.

しかし、最近では、高所で組立て作業を行なうとび職の
技能は一般的に低下してきており、また高所作業に要求
される仮設安全対策はより厳しくなってきていることか
ら、地上近くで屋根または上階床の骨組を組み立ててブ
ロック化したものを所定の高さ位置に上架する施工方法
が指向されるに至っている。
However, in recent years, the skills of jumpers who perform assembly work at heights have generally declined, and temporary safety measures required for work at heights have become more stringent. A construction method has become popular in which the framework of the upper floor is assembled into blocks and then elevated at a predetermined height.

上記従来の施工方法によると、屋根または上階床を上架
する途上に於いて高さの不均等を少なくすることに苦心
している。
According to the above-mentioned conventional construction methods, it is difficult to reduce the unevenness in height during the construction of the roof or upper floor.

平面骨組の屋根または上階床に於ては供用状態での鉛直
荷重の処理、風による吹き上げ力の処理。
For flat frame roofs or upper floors, handle vertical loads and uplift forces caused by wind while in service.

建屋のねじれ防止等を目的として、主梁とつなぎ梁の接
合部に方杖を設けることが行なわれる。
To prevent the building from twisting, braces are installed at the joints between the main beam and the connecting beam.

その結果、平面骨組の屋根または上階床に於ても、組立
てた状態では立体骨組のような状態となり、例えば支持
部4点以上で吊上げ上架するに際し、高さの不均等によ
る屋根のねじれ変形が生じた場合には、骨組に付加的な
応力が生じ、該応力を小さく抑えるためには高さ不均等
を小さく抑えておく必要がある。
As a result, even if the roof is a flat frame or the upper floor, the assembled state becomes like a three-dimensional frame. For example, when hoisting the roof using four or more supporting points, the roof may be twisted and deformed due to uneven height. When this occurs, additional stress is generated on the frame, and in order to keep this stress low, it is necessary to keep the height unevenness small.

従って、従来の施工方法に於ては、高さの不均等を少な
くするために、複数台の油圧ジヤツキによる平坦状態で
の同時上昇による高さ制御、上昇速度制御等を行なって
おり、そのため上昇速度は遅く、揚重設備費も高価とな
り、しかも施工期間が長く、上昇施工に関するノウハウ
も必要で特定の建設業者にのみ可能である、という欠点
を有していた。
Therefore, in conventional construction methods, in order to reduce unevenness in height, multiple hydraulic jacks are used to raise the height at the same time in a flat state, and control the rate of rise. The disadvantages are that the speed is slow, the cost of lifting equipment is expensive, the construction period is long, and know-how regarding lifting construction is required, which can only be done by specific construction companies.

本発明は、上記欠点をなくし、極めて一般的な揚重機械
、即ちトラッククレーン或いはウィンチ等で短時間に施
工できる方法を提供するもので、その要旨は、鋼構造建
家屋根または上階床の平面骨組を上架前に組立て、所定
の高さに上架させる施工方法において、主梁とつなぎ梁
の接合部の方杖に軸力が生じない状態とするか、または
方杖を取付けない状態で上架作業を行ない、上架後に該
方杖を主梁とつなぎ梁に対して正規の状態に取付けるこ
とを特徴とする鋼構造屋根または上階床の施工方法であ
る。斯様に本発明は、供用状態で、屋根または床に必要
である主梁とつなぎ梁の接合部の方杖に上架作業中は軸
力が生じない状態とするか、または方杖を取り付けない
状態で上架作業を行なうので、上架点相互の高さ不均等
によるねじれ変形を拘束することなく自由な状態とし、
ねじれ変形による付加的な応力を防止することができる
The present invention eliminates the above-mentioned drawbacks and provides a method that can be constructed in a short time using extremely common lifting machines such as truck cranes or winches. In a construction method in which a flat frame is assembled before being elevated and the structure is hoisted to a predetermined height, it is necessary to ensure that no axial force is generated in the beams at the joints between the main beams and connecting beams, or to raise the structure without attaching beams. This is a construction method for a steel structure roof or upper floor, which is characterized by carrying out the work and attaching the beams to the main beam and the connecting beam in a regular state after the work is carried out. In this way, the present invention provides a system in which no axial force is generated on the beam at the joint between the main beam and the connecting beam, which is necessary for the roof or floor, in the in-service condition, or no beam is attached. Since the work on the elevated structure is carried out in such a state, the torsional deformation caused by the uneven height of the elevated points is free without being constrained.
Additional stress due to torsional deformation can be prevented.

また本発明では、上架作業中は屋根または上階床のねじ
れ剛性が確保されない状態[4るが、各骨組の鉛直方向
の剛性が確保されており、ブロック化された屋根または
上階床を上架することは可能であり、上架保持部も従来
の施工法の場合と同様の位置とすることができる。
In addition, in the present invention, the torsional rigidity of the roof or upper floor is not ensured during the raising work [4], but the vertical rigidity of each frame is ensured, and the block roof or upper floor is It is possible to do so, and the overhead rack holding part can also be placed in the same position as in the case of the conventional construction method.

本発明は、上述した如く、屋根または上階床の上架作業
中に於て、従来の施工法で最も困難であった上架途上に
おける高さ制御、上昇速度制御を不要にすることができ
る。
As described above, the present invention makes it possible to eliminate the need for height control and rising speed control during the process of elevating a roof or an upper floor, which were most difficult in conventional construction methods.

次に従来例および本発明の実施例を第1図〜第3図にも
とづいて説明する。
Next, a conventional example and an embodiment of the present invention will be explained based on FIGS. 1 to 3.

第1図は従来方法による上架対象の屋根または上階床の
骨組の一例であり、主梁1とつなぎ梁2゜小梁4.母屋
5を組み立て、つなぎ梁端部には方杖6を取り付けた状
態で上架作業を行っていた。
Figure 1 shows an example of the framework of a roof or upper floor to be elevated using the conventional method, with a main beam 1, a connecting beam 2°, a small beam 4. The main building 5 was assembled, and work on the elevating structure was carried out with the support beams 6 attached to the ends of the connecting beams.

本発明は、上記方杖3を取付けない状態で、第2図に示
すように上架保持部A、B、C,Dをそれぞれトラック
クレーン6、ウィンチ7を使用して上架作業を行ない。
In the present invention, as shown in FIG. 2, the hoisting work is carried out using a truck crane 6 and a winch 7 on the hoist holding parts A, B, C, and D, respectively, without the cane 3 attached.

その後に方杖6を固着するものである。After that, the cane 6 is fixed.

本実施例では、第2図のように屋根骨組90部材を本締
めした後、塗装し、次いで屋根の仮葺後、屋根8を上架
して固定したが、上架前の施工内容と上架後の施工内容
はそれぞれ任意に設定できる。
In this example, as shown in Fig. 2, after the roof frame 90 members were fully tightened, they were painted, and then after the roof was temporarily roofed, the roof 8 was mounted and fixed. Construction details can be set as desired.

また本実施例では、前述のごとく方杖6を取り外してお
く例を示しているが、方杖に軸力が生じない状態として
もよい。上記の手段としては該方杖の端部または中間部
の接合部を接合しないでおくか、またはつなぎ梁や方杖
乙の各接合部(ボルト穴)をルーズな状態にしておく等
のことが考えられる。また本実施例では揚重設備配置を
第2図に示すようにトラッククレーンとウィンチの組み
合わせとしたが、単一種の揚重設備でも良く、また組み
合わせの方法も任意に設定できる。
Further, in this embodiment, as described above, an example is shown in which the cane 6 is removed, but the cane may be in a state where no axial force is generated. As a means of achieving the above, it is possible to leave the ends or intermediate joints of the beams unjoined, or to leave the joints (bolt holes) of the connecting beams and beams loose. Conceivable. Further, in this embodiment, the lifting equipment arrangement is a combination of a truck crane and a winch as shown in FIG. 2, but a single type of lifting equipment may be used, and the method of combination can be set arbitrarily.

尚、本実施例に示すつなぎ梁2の構造は第1図に示す従
来のものに限定することなく、第6図。
The structure of the connecting beam 2 shown in this embodiment is not limited to the conventional structure shown in FIG. 1, but is shown in FIG.

第5図に示す各種の構造に適用できる。第6図はラチス
梁で主梁との高さの差が大きい梁を示し、第4図は単材
梁を示し、第5図はラチス梁で主梁と同じ高さの梁を示
す。
It can be applied to various structures shown in FIG. Fig. 6 shows a lattice beam with a large height difference from the main beam, Fig. 4 shows a single material beam, and Fig. 5 shows a lattice beam with the same height as the main beam.

上述したように、本発明によれば、通常の揚重設備()
ラッククレーン、ウィンチ、ジヤツキ等)を用いて屋根
または上階床の骨組の上架作業を行なうことができ、特
別な精度をもう高さ制御、上昇速度制御システムは不要
であり、例えば従来、上昇に約8時間、固定作業に約2
時間と計約10時間も要していたが、本発明方法によっ
て上昇速度も大きくすることができるため揚重設備費も
安価で施工期間も上昇に約1時間、固定作業に約2時間
と計約6時間で完了し、すなわち従来の1/3で済み、
さらに今まで特定の建設業者でないと施工できなかった
上昇施工方法を更に広汎な業者に壕で拡大して可能なら
しめることができ、建設業界に寄与するところ極めて犬
である。
As mentioned above, according to the invention, ordinary lifting equipment ()
Elevation of roofs or upper floor frames can be carried out using rack cranes, winches, jacks, etc.), and special precision height control and climbing speed control systems are no longer required, e.g. Approximately 8 hours, approximately 2 hours for fixed work
However, since the lifting speed can be increased by the method of the present invention, the cost of lifting equipment is also low, and the construction period is approximately 1 hour for lifting and 2 hours for fixing. It can be completed in about 6 hours, which is 1/3 of the conventional time.
Furthermore, the elevated construction method, which until now could only be carried out by a specific construction company, can now be extended to a wider range of companies using trenches, making it an extremely valuable contribution to the construction industry.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は上架する屋根または上階床の骨組の例を示す斜
視図、第2図は本発明に係る上架作業の全体概略斜視図
、第6図〜第5図は第1図に示すつなぎ梁の他の各種例
を示すもので、第6図はラチス梁で主梁との高さの差が
大きい梁を示す説明図、第4図は単材梁を示す説明図、
第5図はラチス梁で主梁と同じ高さの梁を示す説明図で
ある。 図において、1は主梁、2はつなぎ梁、乙は方杖、4は
小梁、5は母屋、6は揚重設備(トラッククレーン)、
7は揚重設備(ウィンチ)、8は屋根、9は屋根骨組ま
たは上階床、A−Dは上架保持部である。
Fig. 1 is a perspective view showing an example of the frame of the roof or upper floor to be elevated, Fig. 2 is a schematic perspective view of the overall elevating work according to the present invention, and Figs. 6 to 5 are the connections shown in Fig. 1. Various other examples of beams are shown; Fig. 6 is an explanatory diagram showing a lattice beam with a large height difference from the main beam, Fig. 4 is an explanatory diagram showing a single material beam,
FIG. 5 is an explanatory diagram showing a lattice beam having the same height as the main beam. In the figure, 1 is the main beam, 2 is the connecting beam, O is the bridge, 4 is the small beam, 5 is the main building, 6 is the lifting equipment (truck crane),
7 is a lifting equipment (winch), 8 is a roof, 9 is a roof frame or upper floor, and A-D are overhead holding parts.

Claims (1)

【特許請求の範囲】[Claims] 鋼構造建家屋根または上階床の平面骨組を上架前に組立
て、所定の高さに上架させる施工方法において、主梁と
つなぎ梁の接合部の方杖に軸力が生じない状態とするか
、または方杖を取付けない状態で上架作業を行ない、上
架後に該方杖を主梁とつなぎ梁に対して正規の状態に取
付けることを特徴とする鋼構造屋根または上階床の施工
方法。
In the construction method where the flat frame of the steel structure building roof or upper floor is assembled before being elevated and raised to a predetermined height, is there a condition in which no axial force is generated in the beam at the joint between the main beam and the connecting beam? , or a construction method for a steel structure roof or an upper floor, characterized in that the elevating work is carried out without installing the girders, and after the elevating, the girders are attached to the main beam and the connecting beam in a normal state.
JP20449882A 1982-11-24 1982-11-24 Construction of steel structural roof or upper stair floor Granted JPS5996358A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP20449882A JPS5996358A (en) 1982-11-24 1982-11-24 Construction of steel structural roof or upper stair floor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP20449882A JPS5996358A (en) 1982-11-24 1982-11-24 Construction of steel structural roof or upper stair floor

Publications (2)

Publication Number Publication Date
JPS5996358A true JPS5996358A (en) 1984-06-02
JPS62309B2 JPS62309B2 (en) 1987-01-07

Family

ID=16491520

Family Applications (1)

Application Number Title Priority Date Filing Date
JP20449882A Granted JPS5996358A (en) 1982-11-24 1982-11-24 Construction of steel structural roof or upper stair floor

Country Status (1)

Country Link
JP (1) JPS5996358A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009161943A (en) * 2007-12-28 2009-07-23 Nippon Sheet Glass Environment Amenity Co Ltd Building construction method

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63169777U (en) * 1987-04-21 1988-11-04
JP7265328B2 (en) 2018-08-27 2023-04-26 アズビル株式会社 VALVE MAINTENANCE SUPPORT DEVICE AND SUPPORT METHOD

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009161943A (en) * 2007-12-28 2009-07-23 Nippon Sheet Glass Environment Amenity Co Ltd Building construction method

Also Published As

Publication number Publication date
JPS62309B2 (en) 1987-01-07

Similar Documents

Publication Publication Date Title
JPH04111829A (en) Method for constructing large-span roof
CN103883129A (en) Method for installing steel structure roof beams
CN106759909B (en) Bearing structure system and its construction method are hung up under one kind
CN104775363B (en) The spelling method of upper king-post strut reinforcing bar sections
JPS5996358A (en) Construction of steel structural roof or upper stair floor
JP2927320B2 (en) How to assemble a large hanging boiler
JP6879613B1 (en) Curing system at the time of building demolition and demolition method of the building to be demolished
JPH04161566A (en) Constructing apparatus for large space building
JP2003120037A (en) Construction lifting system for multistoried building
JPH07150767A (en) Beam truss erecting method in building having overhead traveling crane
JP2529067B2 (en) Crane flexible climbing method
CN219100670U (en) Low-level jacking climbing construction platform
CN219430545U (en) Operation platform for utilizing stiffness framework for tower column head section
CN213234454U (en) Buckling restrained brace structure
CN214003793U (en) Lifting platform for mounting inner component of pipe culvert
JPH0642184A (en) Construction of skeleton using half precast floor board
JP2690822B2 (en) Steel construction method for low-rise buildings
JP2779258B2 (en) Roof lift-up method
CN117188597A (en) Steel frame internal arch structure and flexible back-pull relay hoisting construction method thereof
JP2551488B2 (en) Lifting method by crane and lifting jig
JPH0791603A (en) Assembly parallel progressing method for large suspension type boiler
CN111535146A (en) Method for installing steel truss girder of suspension bridge
JPH0437897B2 (en)
JPS5840629B2 (en) Assembly method for power transmission towers
JPS61270461A (en) Construction of large beam