CN111535146B - Method for installing steel truss girder of suspension bridge - Google Patents

Method for installing steel truss girder of suspension bridge Download PDF

Info

Publication number
CN111535146B
CN111535146B CN202010362299.0A CN202010362299A CN111535146B CN 111535146 B CN111535146 B CN 111535146B CN 202010362299 A CN202010362299 A CN 202010362299A CN 111535146 B CN111535146 B CN 111535146B
Authority
CN
China
Prior art keywords
bridge
hoisting
section
hoisted
steel truss
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010362299.0A
Other languages
Chinese (zh)
Other versions
CN111535146A (en
Inventor
丁亚辉
李欣
沈冲
黄阳林
刘和能
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC SHEC Second Engineering Co Ltd
Original Assignee
CCCC SHEC Second Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC SHEC Second Engineering Co Ltd filed Critical CCCC SHEC Second Engineering Co Ltd
Priority to CN202010362299.0A priority Critical patent/CN111535146B/en
Publication of CN111535146A publication Critical patent/CN111535146A/en
Application granted granted Critical
Publication of CN111535146B publication Critical patent/CN111535146B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/02Suspension bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to the technical field of bridge installation, in particular to a method for installing a steel truss girder of a suspension bridge. The method reduces the investment of rigid connection construction resources, shortens the construction period of the bridge, and has the characteristics of simple connection sequence of the steel trusses of the suspension bridge, less overhead rigid connection operation amount and low safety risk.

Description

Method for installing steel truss girder of suspension bridge
Technical Field
The invention relates to the technical field of bridge installation, in particular to a method for installing a steel truss girder of a suspension bridge.
Background
The mountain suspension bridge girder generally adopts the steel truss structure, and the steel truss comprises steel decking and steel truss, and the steel truss adopts mill's processing member usually, transports to the building site and assembles the steel truss. The bridge floor adopts factory welding small plate units, and the bridge deck is assembled in a construction site. The steel bridge deck and the steel truss of the plate truss combined steel truss are usually connected in a bolt welding combination mode, and the steel truss steel bridge deck and the steel truss of the plate truss separation structure are connected by adopting a support.
The existing suspension bridge hoisting is all realized by adopting full-hinged hoisting, wherein the traditional hoisting sequence of the steel truss is that a steel truss between sections is selected as an assembling unit, the assembling unit is hoisted one at a time, the hoisting units are temporarily hinged, and every two steel trusses are firstly rigidly connected after the whole hoisting is finished. And after the hoisting of the full-bridge steel truss is finished, hoisting the steel bridge deck. After the bridge deck and the steel truss are completely hoisted, second-stage constant-load equal-generation load pressure construction is carried out, the second-stage constant-load equal-generation load pressure construction enables the line type of the steel truss to reach the design line type, rigid connection of the steel truss is carried out under the design line type, the installation and connection sequence of the suspension bridge plate truss and the steel truss combined beam is complex by using the sequence, the high-altitude rigid connection workload is large, and the safety risk is high.
Disclosure of Invention
The invention overcomes the defects of the prior art, provides the installation method of the suspension bridge steel trusses, and particularly has the characteristics of simple connection sequence of the suspension bridge steel trusses, less overhead rigid connection workload and low safety risk.
The technical problem solved by the invention can be realized by adopting the following technical scheme:
a method for installing a steel truss girder of a suspension bridge comprises the following steps:
the method comprises the following steps: respectively building main towers at two opposite sides of a mountain, and then installing cable cranes;
step two: hoisting the beam section and the bridge deck of the bridge through a cable crane;
step three: when the beam section of the bridge is installed through the cable crane, firstly installing the beam section No. 1 of the secondary middle beam section at the central line position of the bridge, and then installing the beam section No. 0 of the middle beam section;
step four: on the basis of the third step, symmetrically hoisting the rest beam sections from the central line position of the bridge to two banks in sequence, and hinging the corresponding beam sections;
step five: inserting and hoisting steel bridge deck plates in the hoisting process of the beam sections, and performing rigid connection between corresponding beam sections when the local linear type of the hoisted beam sections reaches a bridge linear type bridge section in the hoisting process;
step six: repeating the step five, and continuing to finish hoisting the beam section and the bridge deck of the bridge;
step seven: and on the basis of the sixth step, the bridge deck is symmetrically welded and bolted from the midspan of the whole bridge to the main towers on both sides.
The beam sections are steel trusses, the structure of each steel truss is a rectangular frame structure consisting of a closed section and an open section, and the beam section No. 1 and the beam section No. 0 in the step III are both steel trusses.
In the first step, after the main towers on two sides are built, the cable crane is installed, the cable crane is debugged and tried to be hung, and then the sling and the cable clamp are installed.
And in the second step, before the girder section and the bridge deck of the bridge are hoisted, the girder section and the bridge deck assembly field is leveled, and the girder section and the bridge deck are assembled in advance.
And in the fourth step, when the beam sections are symmetrically hoisted from the central line position of the bridge to the two banks in sequence, after the beam sections are hoisted for a certain number of times, the two No. 1 beam sections, close to the main towers at the two banks, of the whole bridge are hoisted in advance in a swinging manner, and then the rest beam sections and the bridge decks are hoisted symmetrically to the two banks in sequence.
Two No. 1 beam sections close to the two-bank main tower are lifted with the integral beam section closure section in the middle in an oscillating mode, then the whole beam section is lifted, and finally the rest bridge decks are lifted.
Two No. 1 beam sections close to the two-bank main tower and the integral beam section closure section at the middle part can also be subjected to pre-deflection closure and vertical hoisting, then the hoisting of the whole beam section is completed, and finally the rest bridge deck is hoisted.
And in the fourth step, when the rest beam sections are symmetrically hoisted, the beam sections of the large bridge are hoisted firstly, then the bridge deck on the closed joint is hoisted symmetrically by utilizing the vacant time of hoisting the beam sections, the rigid connection part reaches the beam sections in the bridge line shape, and the newly formed closed joint is hoisted after rigid connection.
The mounting method of the steel truss girder of the suspension bridge, wherein the girder section comprises two main cross girders, the two main cross girders comprise a first main cross girder and a second main cross girder, when the girder section is hoisted, four hoisting points are arranged on the girder section, the four hoisting points comprise a first hoisting point, a second hoisting point, a third hoisting point and a fourth hoisting point, the first hoisting point and the second hoisting point are arranged on the first main cross girder, and the third hoisting point and the fourth hoisting point are arranged on the second main cross girder.
The invention has the beneficial effects that:
compared with the prior art, the rigid connection construction of the hoisting beam sections is gradually carried out along with the hoisting, the traditional method requires integral rigid connection after the hoisting is completely finished, a large amount of rigid connection construction is carried out simultaneously, the personnel and equipment (resource) input amount is large, the construction cost is high, the rigid connection operation occupies the main line construction period, and the construction period of the whole bridge is prolonged. The method has the characteristics of simple installation and connection sequence of the suspension bridge plate girder and the girder, less overhead rigid connection workload and low safety risk, simultaneously avoids the second-stage constant-load equal-generation load weight construction in the prior method, saves resources, adjusts the hoisting sequence of the steel truss, hoists the end girder section in advance, avoids pier-side supports in the prior method, adopts non-end girder sections in the closure section, optimizes the construction process and saves resources.
Drawings
The invention is further illustrated with reference to the following figures and examples.
Fig. 1 is a schematic structural view of a steel truss according to the present invention.
FIG. 2 is a schematic diagram of the main tower structure of the present invention.
Fig. 3 is a schematic structural view of hoisting the beam segment No. 1 and the beam segment No. 0.
Fig. 4 is a schematic structural view of an end beam section of the swing hoist of the present invention near the main towers on both sides.
Fig. 5 is a schematic structural view of the remaining steel trusses and the bridge decks of the hoisting bridge of the present invention.
Fig. 6 is a schematic view of the hoisting structure of the closure section of the integral beam section.
Fig. 7 is a schematic structural view of the integral bridge after the hoisting is completed.
Fig. 8 is a schematic structural view of the closure segment pre-biased closure of the invention, vertical hoisting.
In the figure: 1-steel truss, 11-closed internode, 12-open internode, 2-first hoisting point, 3-second hoisting point, 4-third hoisting point, 5-fourth hoisting point, 6-first main beam and 7-second main beam.
Detailed Description
Example 1:
referring to fig. 2 and 3, a method for installing a steel girder of a suspension bridge includes the steps of:
the method comprises the following steps: respectively building main towers at two opposite sides of a mountain, and then installing cable cranes;
step two: hoisting the beam section and the bridge deck of the bridge through a cable crane;
step three: when the beam section of the bridge is installed through the cable crane, firstly installing the beam section No. 1 of the secondary middle beam section at the central line position of the bridge, and then installing the beam section No. 0 of the middle beam section;
step four: on the basis of the third step, symmetrically hoisting the rest beam sections from the central line position of the bridge to two banks in sequence, and hinging the corresponding beam sections;
step five: inserting and hoisting steel bridge deck plates in the hoisting process of the beam sections, and performing rigid connection between corresponding beam sections when the local linear type of the hoisted beam sections reaches a bridge linear type bridge section in the hoisting process;
step six: repeating the step five, and continuing to finish hoisting the beam section and the bridge deck of the bridge;
step seven: and on the basis of the sixth step, the bridge deck is symmetrically welded and bolted from the midspan of the whole bridge to the main towers on both sides.
Wherein the installation order of conventional No. 1 roof beam section and No. 0 roof beam section in step three is for installing No. 0 earlier, and No. 1 is installed afterwards, advantage and principle: in the implementation case, the beam section No. 1 is a 4-sling beam section which is stable after installation, and the beam section No. 0 is a double-sling beam section which needs to be provided with temporary slings to keep stability. Then, the No. 1 beam section is installed firstly, then the No. 0 beam section is hoisted, and the No. 0 beam section is hinged with the No. 1 beam section, so that temporary slings are saved, construction steps are saved, and construction time is shortened.
And seventhly, after the bridge deck plates are symmetrically welded and bolted from the midspan of the whole bridge to the main towers at two ends, bridge deck systems and accessory facilities need to be installed, and the cable crane is dismantled to complete the whole construction traffic engineering.
The method is used for hoisting the beam sections in the rigid connection and subsection manner, the aerial full-hinged operation of the hoisting and subsection is realized, the overhead rigid connection operation amount is reduced by 50%, the safety risk is reduced, the steel bridge deck is hoisted in the hoisting process of the beam sections in an inserting manner, the local linear type of the beam sections can reach the bridge linear type in the hoisting process, the working condition that the local linear type of the beam sections can reach the bridge linear type is obtained through software calculation, the calculation method is that the basic information of a constructed large bridge is input into corresponding data calculated by software 'super-large span suspension bridge construction control analysis system 1.0', the length that the local linear type of the beam sections can reach the bridge linear type is determined, the second-stage constant load of the bridge refers to the weight of the bridge deck structure and the accessory facilities, the design linear type of the steel truss girder is consistent with the linear type finished by second-stage constant load construction, the second-stage constant load construction with the pressure weight is carried out after the hoisting of the beam sections is finished, so that the linear type of the beam sections can reach the design linear type, the internal stress can be reduced by rigid connection, is advantageous for the structure. The rigid connection construction of the steel truss girder can be completed without carrying out secondary constant load equal-generation load pressure construction by adopting the method of the invention, and the principle is as follows: the steel bridge deck is hoisted in an inserting mode in the hoisting process of the steel truss, the local linear type of the beam section can reach the bridge linear type in the hoisting process, and the local steel truss beam is just connected, so that the construction cost is reduced, the construction period is saved, wherein software 'extra-large span suspension bridge construction control analysis system 1.0' is the prior art, and the copyright registration number is 2009SR 054376.
The rigid connection construction of the hoisting beam sections is gradually carried out along with the hoisting, the traditional method requires integral rigid connection after the hoisting is completely finished, a large amount of rigid connection construction is carried out simultaneously, the input amount of personnel and equipment resources is large, the construction cost is high, the rigid connection operation occupies the main line construction period, and the construction period of the whole bridge is prolonged. The method reduces the investment of rigid connection construction resources, shortens the construction period of the bridge, and has the characteristics of simple installation and connection sequence of the suspension bridge plate girder and girder combination beam, less overhead rigid connection workload and low safety risk.
Example 2:
referring to fig. 1, the present embodiment is different from embodiment 1 in that: the beam section is a steel truss 1, the structure of the steel truss is a rectangular frame structure consisting of a closed joint 11 and an open joint 12, and the beam section 1 and the beam section 0 in the third step are both the steel truss 1.
In actual use: the steel truss 1 is hoisted once in the hoisting process, and the bridge is installed on the steel truss which is hoisted in the prior art and has a rectangular frame structure with an opening section.
The side face of a rectangular frame structure between the open sections is of an Contraband-shaped structure, the rectangular frame structure is assembled and hoisted in sections according to rigid connection, the side face of the hoisting steel truss 1 is of an opening + Contraband-shaped interface, the structure is more stable, and deformation in the installation process is avoided.
Example 3:
referring to fig. 2, the present embodiment is different from embodiment 1 in that: and in the first step, after the main towers on two sides are built, the cable crane is installed, the cable crane is debugged and tried to be hung, and then the sling and the cable clamp are installed, so that the hoisting construction can be normally carried out.
Example 4:
the present embodiment is different from embodiment 1 in that: and in the second step, before the beam section and the bridge deck of the bridge are hoisted, leveling the beam section and the bridge deck assembly field, assembling the beam section and the bridge deck in advance, and preparing early hoisting for hoisting construction.
Example 5:
referring to fig. 4, 6 and 7, the present embodiment is different from embodiment 1 in that: and in the fourth step, when the beam sections are symmetrically hoisted from the central line position of the bridge to the two banks in sequence, after the beam sections are hoisted for a certain number of times, the two No. 1 beam sections, close to the main towers at the two banks, of the whole bridge are hoisted in advance in a swinging manner, and then the rest beam sections and the bridge decks are hoisted symmetrically to the two banks in sequence.
Two No. 1 beam sections close to the two-bank main tower are lifted with the integral beam section closure section in the middle in an oscillating mode, then the whole beam section is lifted, and finally the rest bridge decks are lifted.
In actual use: when beam sections are symmetrically hoisted from the center line position of a bridge to two banks in sequence, after the beam sections are hoisted for a certain number of times, the certain number of hoisting times is obtained through software calculation, the calculation method is that basic information of the constructed bridge is input into corresponding data calculated by software 'super-span suspension bridge construction control analysis system 1.0', the number of times of hoisting the beam sections is determined, then two No. 1 beam sections of the whole bridge close to main towers at two banks are hoisted in an oscillating mode, the end beam sections are hoisted in advance, the end beam sections are used as bridge deck hoisting platforms, pier side brackets in the traditional method are replaced, the construction steps are simplified, the construction period is shortened, the software 'super-span suspension bridge construction control analysis system 1.0' is the prior art, and the copyright registration number is 2009SR 054376.
Example 6:
referring to fig. 8, this embodiment is different from embodiment 5 in that: two No. 1 beam sections close to the two-bank main tower and the integral beam section closure section at the middle part can also be subjected to pre-deflection closure and vertical hoisting, then the hoisting of the whole beam section is completed, and finally the rest bridge deck is hoisted.
The method for vertically hoisting the closure section of the pre-biased closure comprises the following steps:
take the construction of Jinan Jinshajiang river bridge pre-biased closure as an example.
The method comprises the following steps:
the cable crane sling is connected with a No. 31 beam section;
2 windlasses 8t are arranged in the beam yard, the closed beam section is reversely pulled towards the main span side, the reverse pulling point is arranged at the end part of the lower chord of the truss beam, and the reverse pulling force is about 7 t;
and the cable crane hoisting cable keeps a relaxed state, and the trolley is pulled to the approach bridge side, so that the trolley at the small pile number side is about 17m away from the center line of the cable tower.
Step two:
after the closure beam section is lifted for 1.5m, the reverse-pull winch is released to enable the cable crane hoisting cable to keep a vertical state;
the connection between the winch and the closure section is released;
at the moment, the distance between the small pile number side roadster and the center line of the tower is about 19m, and the clear distance between the closure section and the bearing platform is about 1.0 m.
Step three:
and (3) vertically lifting the closure section, when the upper chord of the main girder of the closure section is close to the lower chord of the main girder of the 30-32 girder section by about 0.5m, accurately adjusting the longitudinal position of the closure section again, ensuring that the clear distance between the closure section and the 32 girder section is about 12cm and the clear distance between the closure section and the main girder of the No. 30 girder section is about 51cm, and controlling by adopting a plumb-ball method.
Step four:
after the closure section is lifted to the installation height, the closure beam section is pulled to the installation position to the main span side, and a sling is installed;
the closure section is rigidly connected with the No. 30 beam section;
and (4) loosening the end beam section to the mounting position, and rigidly connecting the No. 32 beam section with the closure section.
Example 7:
referring to fig. 5, the present embodiment is different from embodiment 1 in that: and in the fourth step, when the rest beam sections are symmetrically hoisted, the beam sections of the large bridge are hoisted firstly, then the bridge deck on the closed internode 11 is hoisted symmetrically by utilizing the vacant time of hoisting the beam sections, the rigid connection part reaches the bridge section in a bridge line shape, and the newly formed closed internode 11 is hoisted after rigid connection. By adopting the method to separate and hoist the beam section and the bridge deck, the construction resource input amount is reduced, and the construction period of the bridge is shortened.
Example 8:
this embodiment differs from any of embodiments 1-7 in that: the beam section include two main crossbeams, two main crossbeams include first main crossbeam 6 and second main crossbeam 7, when hoist and mount the beam section, set up four hoisting points on the beam section, four hoisting points include first hoisting point 2, second hoisting point 3, third hoisting point 4 and fourth hoisting point 5, first hoisting point 2 and second hoisting point 3 set up on first main crossbeam 6, third hoisting point 4 and fourth hoisting point 5 set up on second main crossbeam 7.
In actual use: the hoisting points are usually arranged on the top surfaces of the steel truss main cross beams with high strength and stable structure when the steel truss is hoisted, if one steel truss is hoisted at one time, the side surfaces of the steel truss are asymmetrical when the steel truss is hoisted at one time, the side surfaces of the steel truss are in an Contraband-shaped structure, the steel truss is easy to deform in the hoisting process, the steel truss is not beneficial to posture control in the hoisting process, and the hoisting is not beneficial.
Example 9:
taking the construction of Jinan Jinshajiang river bridge as an example:
the construction method is adopted, the steel truss is installed in a way of separating plate girders and fully hinging, and the cable crane is hoisted by four-point hoisting, and the steel truss or the bridge deck with 1 beam section is hoisted each time. And (3) inserting and hoisting the bridge deck slab in the hoisting process of the steel truss, symmetrically hoisting from the midspan to two sides, and closing the steel truss at the secondary end beam section. The standard loading weight of the steel truss is 210t, and the hoisting weight of the bridge deck is 55 t.
The end steel truss girder is positioned outside the longitudinal movement range of the cable crane, swinging and lifting are adopted, the swinging and lifting distance is 10m, plate girders are adopted for separate lifting, the weight of the steel truss girder is 190t, and the weight of the bridge deck is 58 t.
And after the end steel truss girder is hoisted, the end girder section is used as a platform to swing and move to hoist other bridge decks by a swing distance of 2m, and the other bridge decks are symmetrically hoisted from midspan to two sides, so that the bridge deck of the closed internode steel truss girder is preferentially hoisted.
By adopting the method, the construction resource input amount is reduced after construction, the bridge construction period is shortened, and the method is suitable for wide popularization in the field.
While the embodiments of the present invention have been described in detail with reference to the drawings, the present invention is not limited to the above embodiments, and various changes can be made without departing from the spirit of the present invention within the knowledge of those skilled in the art, and the scope of the present invention is within the scope of the claims.
It should be noted that all the directional indicators (such as up, down, left, right, front, and rear … …) in the embodiment of the present invention are only used to explain the relative position relationship between the components, the movement situation, etc. in a specific posture (as shown in the drawing), and if the specific posture is changed, the directional indicator is changed accordingly.
Technical solutions between various embodiments may be combined with each other, but must be realized by those skilled in the art, and when the technical solutions are contradictory or cannot be realized, such a combination should not be considered to exist, and is not within the protection scope of the present invention.

Claims (9)

1. A suspension bridge steel truss girder installation method is characterized in that: the method comprises the following steps:
the method comprises the following steps: respectively building main towers at two opposite sides of a mountain, and then installing cable cranes;
step two: hoisting the beam section and the bridge deck of the bridge through a cable crane;
step three: when the beam section of the bridge is installed through the cable crane, firstly installing the beam section No. 1 of the secondary middle beam section at the central line position of the bridge, and then installing the beam section No. 0 of the middle beam section;
step four: on the basis of the third step, symmetrically hoisting the rest beam sections from the central line position of the bridge to two banks in sequence, and hinging the corresponding beam sections;
step five: inserting and hoisting steel bridge deck plates in the hoisting process of the beam sections, and performing rigid connection between corresponding beam sections when the local linear type of the hoisted beam sections reaches a bridge linear type bridge section in the hoisting process;
step six: repeating the step five, and continuing to finish hoisting the beam section and the bridge deck of the bridge;
step seven: and on the basis of the sixth step, the bridge deck is symmetrically welded and bolted from the midspan of the whole bridge to the main towers on both sides.
2. The method for installing a steel truss girder of a suspension bridge according to claim 1, wherein: the beam section is a steel truss (1), the structure of the steel truss is a rectangular frame structure consisting of a closed section (11) and an open section (12), and the beam section No. 1 and the beam section No. 0 in the third step are both the steel truss (1).
3. The method for installing a steel truss girder of a suspension bridge according to claim 1, wherein: in the first step, after the main towers on two sides are built, the cable crane is installed, the cable crane is debugged and tried to be hung, and then the sling and the cable clamp are installed.
4. The method for installing a steel truss girder of a suspension bridge according to claim 1, wherein: and in the second step, before the girder section and the bridge deck of the bridge are hoisted, the girder section and the bridge deck assembly field is leveled, and the girder section and the bridge deck are assembled in advance.
5. The method for installing a steel truss girder of a suspension bridge according to claim 1, wherein: and in the fourth step, when the beam sections are symmetrically hoisted from the central line position of the bridge to the two banks in sequence, after the beam sections are hoisted for a certain number of times, the two No. 1 beam sections, close to the main towers at the two banks, of the whole bridge are hoisted in advance in a swinging manner, and then the rest beam sections and the bridge decks are hoisted symmetrically to the two banks in sequence.
6. The method for installing a steel truss girder of a suspension bridge according to claim 5, wherein: two No. 1 beam sections close to the two-bank main tower are lifted with the integral beam section closure section in the middle in an oscillating mode, then the whole beam section is lifted, and finally the rest bridge decks are lifted.
7. The method for installing a steel truss girder of a suspension bridge according to claim 5, wherein: two No. 1 beam sections close to the two-bank main tower and the integral beam section closure section at the middle part can also be subjected to pre-deflection closure and vertical hoisting, then the hoisting of the whole beam section is completed, and finally the rest bridge deck is hoisted.
8. The method for installing a steel truss girder of a suspension bridge according to claim 1, wherein: and in the fourth step, when the rest beam sections are symmetrically hoisted, the beam sections of the bridge are hoisted firstly, then the bridge deck on the closed internode (11) is hoisted symmetrically by utilizing the vacant time of hoisting the beam sections, the rigid connection part reaches the bridge linear beam section, and the newly formed closed internode (11) is hoisted after rigid connection.
9. The method for installing a steel girder for a suspension bridge according to any one of claims 1 to 8, wherein: the beam section include two main crossbeams, two main crossbeams include first main crossbeam (6) and second main crossbeam (7), when hoist and mount beam section, set up four hoisting points on the beam section, four hoisting points include first hoisting point (2), second hoisting point (3), third hoisting point (4) and fourth hoisting point (5), first hoisting point (2) and second hoisting point (3) set up on first main crossbeam (6), third hoisting point (4) and fourth hoisting point (5) set up on second main crossbeam (7).
CN202010362299.0A 2020-04-30 2020-04-30 Method for installing steel truss girder of suspension bridge Active CN111535146B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010362299.0A CN111535146B (en) 2020-04-30 2020-04-30 Method for installing steel truss girder of suspension bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010362299.0A CN111535146B (en) 2020-04-30 2020-04-30 Method for installing steel truss girder of suspension bridge

Publications (2)

Publication Number Publication Date
CN111535146A CN111535146A (en) 2020-08-14
CN111535146B true CN111535146B (en) 2021-11-02

Family

ID=71971431

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010362299.0A Active CN111535146B (en) 2020-04-30 2020-04-30 Method for installing steel truss girder of suspension bridge

Country Status (1)

Country Link
CN (1) CN111535146B (en)

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005282131A (en) * 2004-03-30 2005-10-13 Sumitomo Mitsui Construction Co Ltd Construction method of upper deck type suspension floor slab bridge
JP2007051426A (en) * 2005-08-15 2007-03-01 Public Works Research Institute Bridge and construction method of bridge
CN101666068A (en) * 2009-09-28 2010-03-10 长沙理工大学 Method for hoisting and mounting stiff girder of suspension bridge in mountain areas
CN101709565A (en) * 2009-09-27 2010-05-19 中铁大桥勘测设计院有限公司 Double-deck continuous steel girder bridge for rigid suspended cable stiffening
CN104674668A (en) * 2015-01-19 2015-06-03 中铁大桥局集团有限公司 Method for hoisting construction girder sections through cables
CN105178167A (en) * 2015-06-12 2015-12-23 中国电建集团贵阳勘测设计研究院有限公司 Double-deck steel cable bridge and erection method thereof
KR101655332B1 (en) * 2015-02-23 2016-09-07 대림산업 주식회사 Suspension Bridge having Coupling Reinforcing Cables for Mail Cable, and Constructing Method of such Suspension Bridge
CN106744351A (en) * 2016-11-24 2017-05-31 中交路桥华南工程有限公司 The method that cable-stayed bridge main-beam lifting is carried out using cable crane
CN108625275A (en) * 2018-05-09 2018-10-09 中交第公路工程局有限公司 A kind of stiffening girder of suspension bridge section installation method
CN110373989A (en) * 2019-07-22 2019-10-25 中铁大桥局集团有限公司 A kind of whole segment manufacturing method of non-major P.E.subject steel truss girder closure section
CN210086060U (en) * 2019-01-23 2020-02-18 湖南路桥建设集团有限责任公司 Suspension bridge steel truss lifting and swinging device

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101736686A (en) * 2009-11-27 2010-06-16 大连理工大学 Self-anchored hybrid beam cable-stayed suspension cooperative system bridge
CN104060544B (en) * 2014-07-10 2016-01-13 四川石油天然气建设工程有限责任公司 The construction technology that a kind of pipeline suspension crossing bridge body of a bridge is installed
CN205954469U (en) * 2016-07-28 2017-02-15 广西大学 Interior earth anchor suspension bridge
CN206034290U (en) * 2016-07-29 2017-03-22 四川天元机械工程股份有限公司 Installation of suspension bridge stiffening beam is with swinging system of moving on navigable river
CN110468724B (en) * 2019-08-30 2020-12-01 西安市政设计研究院有限公司 Auxiliary device for main cable construction of space cable suspension bridge and main cable construction method

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005282131A (en) * 2004-03-30 2005-10-13 Sumitomo Mitsui Construction Co Ltd Construction method of upper deck type suspension floor slab bridge
JP2007051426A (en) * 2005-08-15 2007-03-01 Public Works Research Institute Bridge and construction method of bridge
CN101709565A (en) * 2009-09-27 2010-05-19 中铁大桥勘测设计院有限公司 Double-deck continuous steel girder bridge for rigid suspended cable stiffening
CN101666068A (en) * 2009-09-28 2010-03-10 长沙理工大学 Method for hoisting and mounting stiff girder of suspension bridge in mountain areas
CN104674668A (en) * 2015-01-19 2015-06-03 中铁大桥局集团有限公司 Method for hoisting construction girder sections through cables
KR101655332B1 (en) * 2015-02-23 2016-09-07 대림산업 주식회사 Suspension Bridge having Coupling Reinforcing Cables for Mail Cable, and Constructing Method of such Suspension Bridge
CN105178167A (en) * 2015-06-12 2015-12-23 中国电建集团贵阳勘测设计研究院有限公司 Double-deck steel cable bridge and erection method thereof
CN106744351A (en) * 2016-11-24 2017-05-31 中交路桥华南工程有限公司 The method that cable-stayed bridge main-beam lifting is carried out using cable crane
CN108625275A (en) * 2018-05-09 2018-10-09 中交第公路工程局有限公司 A kind of stiffening girder of suspension bridge section installation method
CN210086060U (en) * 2019-01-23 2020-02-18 湖南路桥建设集团有限责任公司 Suspension bridge steel truss lifting and swinging device
CN110373989A (en) * 2019-07-22 2019-10-25 中铁大桥局集团有限公司 A kind of whole segment manufacturing method of non-major P.E.subject steel truss girder closure section

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
大跨度悬索桥钢桁梁架设方法对比分析;舒大勇等;《施工技术》;20180630;第47卷(第S1期);第1193-1196页 *
山区特大跨径悬索桥钢桁梁架设工艺探讨;徐元孝等;《公路交通技术》;20180831;第34卷(第4期);第63-67、75页 *
徐元孝等.山区特大跨径悬索桥钢桁梁架设工艺探讨.《公路交通技术》.2018,第34卷(第4期),第63-67、75页. *
悬索桥板桁结合加劲梁现场拼装施工技术;张明闪;《公路》;20180930(第12期);第139-143页 *

Also Published As

Publication number Publication date
CN111535146A (en) 2020-08-14

Similar Documents

Publication Publication Date Title
CN110259145A (en) A kind of arch tubular truss rapid constructing method
WO2018133045A1 (en) Method for mounting self-anchored suspension bridge
CN106087752B (en) Multispan cable-carried arch bridge construction method
CN110130652A (en) Large complicated composite structure steel worm-gearing construction method for lifting whole
CN101537976B (en) Dual-tower-mast giant self-lifting crane and following-carrying lifting method thereof
CN103882812A (en) Construction method for midspan main beams of cable-stayed bridge
CN114215170B (en) Lifting method for ultrahigh-altitude giant-suspension multilayer conjoined structure
CN109972494B (en) Design and construction method of large-segment hoisting self-anchored suspension bridge with hinges between segments
CN111039206B (en) Method for hoisting steel box girder of cable-stayed bridge
CN108894496A (en) A kind of over-the-counter construction method of Large-span Truss String Structure beam
CN103147405B (en) Method for erecting steel girder of cable-stayed bridge with diagonal main trusses
CN100545353C (en) Adopt external eccentric prestress system to carry out steel girder cantilever erection construction method
CN104775363B (en) The spelling method of upper king-post strut reinforcing bar sections
CN111535146B (en) Method for installing steel truss girder of suspension bridge
CN102877657B (en) Large-span H-shaped plane composite structure beam string upper-air cable replacement construction method
CN110040632A (en) A kind of segmental hoisting construction method of large span section steel beam
CN110172915A (en) A kind of high tower shaped form crossbeam Joint Re-bar Construction
CN210002233U (en) Hoisting system suitable for suspension bridge steel structure bridge deck system
CN113832864A (en) Lifting closure construction method for arch rib of steel box arch bridge
CN111535185A (en) Method for installing plate girder combination beam of suspension bridge
CN114086482B (en) Suspension bridge girder erection method
CN109457613B (en) Bridge maintenance truss vehicle installation construction method
CN112709146B (en) Construction method for erecting continuous steel truss girder
CN102427204B (en) Installation method for 1000kV alternating-current substation structure
CN108249286B (en) Method for lifting gantry crane girder by lifting lugs and gantry crane girder

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant