JPS599384A - Method of repair construction of drain pipe - Google Patents

Method of repair construction of drain pipe

Info

Publication number
JPS599384A
JPS599384A JP57118677A JP11867782A JPS599384A JP S599384 A JPS599384 A JP S599384A JP 57118677 A JP57118677 A JP 57118677A JP 11867782 A JP11867782 A JP 11867782A JP S599384 A JPS599384 A JP S599384A
Authority
JP
Japan
Prior art keywords
pipe
diameter
water
drain pipe
support steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP57118677A
Other languages
Japanese (ja)
Inventor
常次 三戸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP57118677A priority Critical patent/JPS599384A/en
Publication of JPS599384A publication Critical patent/JPS599384A/en
Pending legal-status Critical Current

Links

Landscapes

  • Pipe Accessories (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 本発明は新規なυF水路の修復工法に係り、更に詳しく
は開削を要することなく朗水路の修復を行うu1水路の
修復工法に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a novel method for repairing a υF waterway, and more particularly to a method for repairing a u1 waterway that repairs a positive waterway without requiring excavation.

1を 増水に埋設されたu1水路は経時的変化により劣化する
。例えば老朽化によって水路内表面に侵蝕が生したり、
また、土庄によって水路の変形および破壊が生じる。更
に地盤性下等により水路勾配が変化する。加うるにυF
水路における継手材の耐化茗朽にて漏水が発生する。こ
の漏水に伴い、管路周囲の土砂を流入させるので、k路
にゆるみを生しさせる。この様に老朽化した管路は取換
えられるか、或いは廃棄されて新しい杉1水路が設けら
れる。管路の取換えは従来、開削工法1ごて行われる。
The u1 waterway, which was buried under rising water, deteriorates over time. For example, due to aging, erosion occurs on the inner surface of the waterway,
Tonosho also causes deformation and destruction of waterways. Furthermore, the slope of the waterway changes depending on the ground quality. Join υF
Water leaks occur due to the corrosion resistance of joint materials in waterways. With this water leakage, earth and sand around the pipes are allowed to flow in, causing loosening of the k-way. These dilapidated pipes will be replaced or discarded and a new Cedar 1 waterway will be installed. Conventionally, pipeline replacement is carried out using the cut-and-cover method.

開削工法は排水路上部に構造物が無いか或いは」一部構
造物の機能を一定期間停止させることができる場合であ
って、更にその構造物が比較的安価の場合に採用される
。この開削工法によれば水路全体が掘り出されて入れ換
えられるか或いは破損の甚−だしい部分が入れ換えられ
る。然るにこの工法によれば再度の掘削により生じる周
囲地盤のゆるみに対処するための山留工事等を含めて莫
大な工費と工期が必要とされる。従って周囲建造物への
影響はもとより、−1一部構造物が公的な道路等の場合
は工事完成迄に利用者に、構造物の利用および、り音等
で多大な迷惑をかける。更に、施工中急激な増水があっ
た場合に適切な対策をたてることが困難である。開削工
法を採用できない場合は、す1水路を別途新設するので
あるが、開削工法に比して用地の確保等のため、更に多
額の費用が必要とされるので他の大きな工事に附随して
行う場合以外は事実上不可能である。本発明はこれ等従
来技術における欠点に鑑みて成されたものでその1・目
的とする所は、」:圧により破壊された排水管を開削す
ることなく修復するこkのできるDI木管の修復工法を
提供するにある。
The cut-and-cover method is used when there is no structure above the drainage channel or when the function of some structures can be stopped for a certain period of time, and when the structure is relatively inexpensive. According to this cut-and-cut construction method, the entire waterway is excavated and replaced, or only severely damaged sections are replaced. However, this construction method requires a huge amount of construction cost and construction time, including retaining work to deal with the loosening of the surrounding ground caused by re-excavation. Therefore, not only will it have an impact on surrounding buildings, but -1) If some of the structures are public roads, the use of the structures and the noise will cause a great deal of inconvenience to users until the construction is completed. Furthermore, it is difficult to take appropriate measures in the event of a sudden rise in water during construction. If the open-cut method cannot be used, a new waterway will be constructed separately, but compared to the open-cut method, a larger amount of money will be required to secure the site, so it will not be necessary to construct it along with other major construction work. This is virtually impossible unless you do it. The present invention has been made in view of these shortcomings in the prior art, and its first objective is to: Repair DI wood pipes that are capable of repairing drain pipes destroyed by pressure without excavating them. We provide construction methods.

以上の目的を達成するため本発明はシャツキングにて管
路を拡張させると共に当初径より小さな径をイ]する調
整木管および分割された支持鋼管をυ1水?に内に設置
してこれらを一体化することを特(敦とする。
In order to achieve the above object, the present invention expands the conduit at the shirt king and creates an adjusted wood pipe with a diameter smaller than the initial diameter and a divided support steel pipe. The special feature is to install them inside the building and integrate them.

汝゛に本発明の好適な一実施例を添伺図面に依拠して詳
細に説明する。
A preferred embodiment of the present invention will be explained in detail to you with reference to the accompanying drawings.

第1図は上圧により破壊の進んだ排水管lの断lnj図
である。す・この排水管lは、継手の施工不良および老
朽化等による漏水および土砂流入により。
FIG. 1 is a cross-sectional view of a drain pipe 1 that has been destroyed by upper pressure. This drainage pipe has been damaged due to water leakage and sediment inflow due to poor construction and aging of the joints.

管の周辺の土砂に空隙を生じたt−め土圧によって破壊
され、鉛直方向の直径D′が施工時の正常水路径りの約
75%となっている。この様な排水管lの修復に際して
は、第2図に示す如く正常水路径りの90〜95%の管
径を有する支持鋼屑2を四ツ割にして、tJl水路水路
底部より仮旧設した後例えは100〜400トン油圧ジ
ヤツキを4〜8基組合せて当初径に近つく迄シャツキン
グする。
It was destroyed by the earth pressure that created voids in the earth and sand around the pipe, and the vertical diameter D' was about 75% of the normal channel diameter at the time of construction. When repairing such a drain pipe 1, as shown in Fig. 2, a supporting steel scrap 2 having a pipe diameter of 90 to 95% of the normal waterway diameter is cut into quarters and temporarily installed from the bottom of the tJl channel. After that, for example, 4 to 8 100 to 400 ton hydraulic jacks are combined to perform shirt kinging until the diameter approaches the initial diameter.

この時に第3図に示す如く単位水路長文よりも長く、長
手方向の長さ立′か且つ300mmX300mm程爪の
寸法を有するH型網4.4にてジヤツキベースを保持す
る様に構成すると、勾配の変化した部所5.5がジャッ
キングにて正常勾配に矯正される。シャツキングにて正
常水路径りの90〜95%に達した後、四ツ割支持鋼管
2が溶接にて木イ・1けyれて布設が完了する。なお、
第4図は油圧ジヤツキ6によるジャッキングの様子を詳
細に示す断面図である。支持fJr4管2の長之は、下
流人孔から引込む関係」−11000mm−1500m
m程度とし、また、100〜400トン近くの圧力が部
分的に作用するので厚さは20mm程度とする。
At this time, as shown in Fig. 3, if the jack base is held by an H-shaped net 4.4 which is longer than the length of the unit waterway, has a length in the longitudinal direction, and has claw dimensions of about 300 mm x 300 mm, it is possible to The changed part 5.5 is corrected to a normal slope by jacking. After reaching 90 to 95% of the normal diameter of the water channel in the shirt king, the four-split support steel pipe 2 is welded to one side to complete the installation. In addition,
FIG. 4 is a sectional view showing in detail the state of jacking by the hydraulic jack 6. The length of the support fJr4 pipe 2 is the relationship between drawing from the downstream manhole - 11000mm - 1500m
The thickness is approximately 20 mm since a pressure of approximately 100 to 400 tons is partially applied.

然しこれ等の寸法、形状は例示であって本発明はこれ等
に限定されるものではない。υ1水管lに密着して!O
設した四・ツ割支持鋼管2の継手部には重ね溶接による
段差か生じると共に、底面の勾配部分にも凹凸を生じる
。これを解消するため、支持ε11管2の内方に調整本
管7を布設する。調整本管7ぼ勾配及び左右の方向に対
する折れ等を調整する1」的で布設するものであるから
、第5図に示す如く、正常水路径りの80〜85%の径
dを有するものを用いる。調整本管7の布設にて水路径
が小さくなるか、調整本管7は鋼製であるのでコンクリ
ートの排水管1に比して粗度係数が異なる。
However, these dimensions and shapes are merely examples, and the present invention is not limited thereto. Closely attached to υ1 water pipe l! O
At the joint of the installed four-split support steel pipe 2, a step is created due to lap welding, and the sloped portion of the bottom surface is also uneven. In order to solve this problem, an adjustment main pipe 7 is installed inside the support ε11 pipe 2. Since the adjustment main pipe 7 is to be installed to adjust the slope and bends in the left and right directions, it should be installed with a diameter d that is 80 to 85% of the normal waterway diameter, as shown in Figure 5. use Either the waterway diameter becomes smaller due to the installation of the adjustment main pipe 7, or because the adjustment main pipe 7 is made of steel, the roughness coefficient is different from that of the concrete drainage pipe 1.

従って断面積が縮少されても流速が増加するので流量へ
の影響は少ない。調整本管7を布設する際は、正しい勾
配および支持鋼管2の左右方向のずれを計測した後、最
大公約数的な位置を決定し、第6図に示すようにスペー
サ8を用いて該位置に保持し、溶接付けする。なお、調
整本管7の管径および割伺数は搬入および布設地点迄の
引込状況を検討して定める。その後、調整木管7を仮組
して引込4j設する。次いで第7図に示す如く、排水路
の一単位毎に1ケ所の割合て四ヶのグラウトノズル9を
設置して薬注し、水路と調整本管7とを一体化させる。
Therefore, even if the cross-sectional area is reduced, the flow velocity increases, so there is little effect on the flow rate. When installing the adjustment main pipe 7, after measuring the correct slope and the horizontal deviation of the support steel pipe 2, determine the greatest common divisor position, and use spacers 8 to secure the position as shown in Fig. 6. Hold it in place and weld it on. In addition, the pipe diameter and number of split ends of the adjustment main pipe 7 are determined by examining the delivery and lead-in conditions to the installation point. Thereafter, the adjusted wood pipe 7 is temporarily assembled and the lead-in 4j is installed. Next, as shown in FIG. 7, four grout nozzles 9 are installed, one in each unit of the drainage channel, and the grout nozzles 9 are injected, thereby integrating the water channel and the regulating main pipe 7.

支持鋼管2を布設した状態で支持鋼管2と排水路との間
に間隙が生じている場合は、予め直径3cm程度のグラ
ウトホールを支持鋼管2に設けておくことにより、調整
本管7を介して薬注する際に間隙が充填される。なお、
調整木管に空気を抜くための空気弁を設ければ薬注が均
に行なわれる。排水管1の破壊の程度が軒く、例えば第
8図に示す如く、破壊を受けたυ1水管lの径D′が当
初径りの90%または、これ以上の場合は、排水路の拡
張工事を行わすに調整支持管を、装置する。調整支持管
の設置に際しては、第9図に示す如く、排水路一単位毎
に1ケ所当り4ケの割合で薬注ノズル10を設置して排
水路lの外部にセメント系硬化剤を注入する。これと同
時に管内勾配左右のずれおよび破壊進度を計測し、調整
支持管11の径を最大にできる様な位置を求めてこの調
整支持管11を設置する。調整支持管11として用いる
鋼管の割伺およυ一体当りの長さは調整水T 7と同様
に搬入および布設地点迄の引込状況並υ・に役人人孔断
面の寸法、形状等を検8・Jシて定める。また、調整支
持管11を引入設置する際は第10図に示す如く予め計
測した所要の寸法の調整支持管11に溶接されたスペー
サー15を用いて排水路との間隙の調整を行う。スペー
サー11は支持管11を目的位置に位置決めする役割を
はたす。調整支持管11の設置後に、排水管1の一中位
毎に1ケ所宛、グラウトノズル9を設けてセメント系硬
化剤を注入し、排水路と調整支持管11との一体化を図
る。その際注入作業によって」二Rする内圧を低下させ
、クラウドが均一に充填されるように、調整支持管11
の所要ケ所に空気弁を設ける事に依り充填が容易になる
If there is a gap between the support steel pipe 2 and the drainage channel when the support steel pipe 2 is installed, it is possible to install a grout hole with a diameter of about 3 cm in the support steel pipe 2 in advance so that the gap can be removed through the adjustment main pipe 7. The gap is filled when the medicine is dispensed. In addition,
If an air valve is installed in the adjusting wood pipe to remove air, the medicine will be poured evenly. If the degree of destruction of the drain pipe 1 is large, for example, as shown in Figure 8, if the diameter D' of the damaged water pipe υ1 is 90% or more of the original diameter, expansion work of the drainage can be carried out. Adjust the support tube to make the device. When installing the adjustment support pipe, as shown in Fig. 9, chemical injection nozzles 10 are installed at a rate of 4 nozzles per one location in each unit of the drainage channel, and cement-based hardening agent is injected into the outside of the drainage channel 1. . At the same time, the left and right deviations of the internal gradient and the degree of fracture are measured, and the adjustment support tube 11 is installed at a position where the diameter of the adjustment support tube 11 can be maximized. The cut and length of the steel pipe to be used as the adjustment support pipe 11 are determined by examining the conditions of delivery and delivery to the installation point, as well as the dimensions and shape of the cross-section of the official manhole, as well as the adjustment water T7.・Determined by J. Further, when installing the adjustment support pipe 11, the gap with the drainage channel is adjusted using a spacer 15 welded to the adjustment support pipe 11 having the required dimensions measured in advance as shown in FIG. The spacer 11 serves to position the support tube 11 at a target position. After the adjustment support pipe 11 is installed, a grout nozzle 9 is provided at one location in each middle of the drain pipe 1 to inject a cement-based hardening agent to integrate the drainage channel and the adjustment support pipe 11. At this time, the adjustment support tube 11 is lowered by the injection operation so that the internal pressure is lowered and the cloud is evenly filled.
Filling becomes easier by providing air valves at required locations.

第11図は調整支持管11の端末部におけるシールの様
子を示す断面図である。即ち、シールセメント12およ
びUGグラウト13にて排水路とのギヤツブ摺伺が行わ
れると共にグラウトのストッパーが形成yれ、より緻富
な止水か行われる。排も路の継手のみに浸蝕が見られる
程度の破壊進度の初期の排水管1に対しては、第12゜
13 図ニ示を如<シールセメン)・12とUGグラウ
ト13にて止水を施し、また、第14図に示す如く縦ク
ラックがある場合にも、これに11−水を施した後、#
J+水路1単位につき1ケ所当り4ケの割合でノズルを
設けてυ1水管1の外部にセメント系硬化剤を注入して
#J[水管1と外部との間隙を埋めることにより、配水
路の耐圧力を増大させて延命化を!図る。なお、図中1
4はセルコートを示す。
FIG. 11 is a cross-sectional view showing how the end portion of the adjustment support tube 11 is sealed. That is, the sealing cement 12 and the UG grout 13 perform gear sliding with the drainage channel, and at the same time, a grout stopper is formed, and a more precise water stop is performed. For drain pipes 1 in the early stage of destruction where erosion is seen only at the joints of the drain passages, water can be stopped using seal cement 12 and UG grout 13 as shown in Figure 12.13. , Also, if there are vertical cracks as shown in Fig. 14, after applying 11-water to the cracks, #
J + Nozzles are installed at 4 locations per unit of waterway, and a cement hardening agent is injected into the outside of υ1 water pipe 1. Increase pressure and prolong life! Plan. In addition, 1 in the figure
4 indicates cell coat.

また、鋼管部分では、エポキシ樹脂及びカラス系樹脂の
混合塗布することに依りより強力な内面保護となる。ま
た、更に人孔に対しても配水路と共に止水を施して人孔
からの1JrI水および土砂流入を防止する必要がある
。第15〜17図は夫々、人孔床版継目、人孔側塊継目
および人孔躯体クラックに対する止水の様子を示す断面
図で、シールセメント12およびUGグラウ)・13に
より止水が施される。勿論、人孔に対しても破損の程度
によって排水管lと同様に鋼管による全面止水を施すこ
とができる。なお、第18図は、排水管lの破壊が進ん
でジヤツキアップによる修復を必要とする場合における
調整木管7の引込み作業の様子を概括的に示す断面図で
、地」二に設置されたウィンチ16にて調整本管7か引
込まれる様子が示される。また、第19図はクレーン1
7を用いて大孔から調整支持管11を挿入して修復個所
に引込む作業の様子を概括的に示す断面図である。
Furthermore, by applying a mixture of epoxy resin and glass-based resin to the steel pipe section, stronger inner surface protection can be achieved. Furthermore, it is necessary to stop the water supply to the manhole as well as the distribution channel to prevent 1JrI water and sediment from flowing into the manhole. Figures 15 to 17 are cross-sectional views showing the state of water stoppage at the manhole floor slab joint, manhole side block joint, and manhole frame crack, respectively. Ru. Of course, depending on the degree of damage to the manhole, it is possible to provide a complete water stoppage using a steel pipe in the same way as the drain pipe l. In addition, FIG. 18 is a sectional view schematically showing how the adjustment wood pipe 7 is pulled in when the drainage pipe l is damaged and needs to be repaired by jacking up. The adjustment main pipe 7 is shown being drawn in. Also, Figure 19 shows crane 1
7 is a cross-sectional view schematically showing the operation of inserting the adjustment support tube 11 from the large hole and pulling it into the repaired area using the adjustment support tube 7. FIG.

」二連の如く本発明は、破壊された排水管をジャッキン
グにて拡張させると共に当初径より小さな径を有する支
持鋼管を分割して排水管内に仮イ=j設および溶接した
後、調整木管を挿入してこれ等を・体化させるので開削
を要することなく例えば当初iイの75%程度迄排水管
が破壊されている場合であっても開削を要することなく
当初の機能を有するυ1水路に修復できる効果がある。
``The present invention expands the destroyed drain pipe by jacking, divides the support steel pipe with a diameter smaller than the original diameter, temporarily installs it in the drain pipe, welds it, and then installs the adjusted wooden pipe. For example, even if about 75% of the original drainage pipe is destroyed, the υ1 waterway retains its original function without the need for excavation. It has the effect of restoring.

また、その費用も開削]二法に比して充分低い。In addition, the cost is sufficiently lower than that of the two open-cut methods.

また更に正常径に近つけられた後で、この形が保持され
、次の工程が実行されるという工程を経るため、作業の
安全性か向」−する。
Furthermore, after the diameter is brought closer to the normal diameter, this shape is maintained and the next process is carried out, which improves work safety.

【図面の簡単な説明】[Brief explanation of the drawing]

第゛1図は上圧により破壊の進んたυ1水管の一例を示
す断面図、 第2図は本発明に係る支持鋼管にて支持した排水管の一
実施例の断面図、 第3図はジヤツキアップにて勾配を嬌正する方法を示す
本発明の一実施例の側断面図、第4図はジャッキングの
様子を示す本発明の一実施例の断面図 第5図は調整木管と排水管との寸法の関係を示す断面図
、 第6図は調整木管をスペーサーにて支持する様子を示す
本発明の一実施例の断面図、 第7図は薬注を行う様子を示す本発明の一実施例の断面
図、 第8図は破損の少ない排水管の一例を示す断面図、 第9図1オ調整支持管を設置して薬注する様子を示す本
発明の一実施例の断面図、 第10図はスペーサーにて調整支持管を保持する様子を
示す本発明の一実施例の断面図、第11図は調整支持管
の端末部におけるシールの様子を示す本発明の一実施例
の断面図、第12図は継手における軽度の破壊に対する
止水の様子を示す本発明の一実施例の部分断面図、第1
3図は第12図に示す継手と異なる形式の継手に対する
止水の様子を示す本発明の一実施例・の部分断面図、 第14図は管内縦クラックの止水の様rを示す本発明の
一実施例の部分断面図。 第15図は人孔床版継目における上水の様子を示す本発
明の一実施例の部分断面図、 第16図は人孔側塊継目における止水の様子を示ヂ木発
明の一実施例の部分断面図。 第17図は人孔躯体クラックの止水の様子を示す本発明
の一実施例の断面図、 第18図は調整木管の引込み作業の様子を示す本発明の
一実施例の断面図、 第19図は調整支持管を人孔から引込む様子を示す本発
明の一実施例の断面図である。 ここて、l・・・°排水管、2・・・支持鋼管、6・・
・ジヤツキ、7・・・調整木管、8・・・スペーサー、
9・・・グラウトノズル、10・・・薬注ノズル、11
・・・調整支持管、12・・・シールセメント、13・
・・UGグラウI・である。 特許出願人  窪   盛 充 第3図 第7因 第8因 ;1j9図 第10図 第11図 第42図 )4 第131 1 第14図 第15図 2、′;16図
Fig. 1 is a cross-sectional view showing an example of a υ1 water pipe that has been destroyed due to upper pressure, Fig. 2 is a cross-sectional view of an example of a drain pipe supported by a supporting steel pipe according to the present invention, and Fig. 3 is a jack-up Fig. 4 is a sectional side view of an embodiment of the present invention showing a method of correcting a slope; Fig. 5 is a sectional view of an embodiment of the invention showing jacking; FIG. 6 is a cross-sectional view of an embodiment of the present invention showing how the adjustable wood pipe is supported by a spacer. FIG. 7 is a cross-sectional view of an embodiment of the present invention showing how to perform chemical injection. FIG. 8 is a cross-sectional view showing an example of a drain pipe with little damage. FIG. 9 is a cross-sectional view of an embodiment of the present invention showing how the 1-o adjustment support pipe is installed and medicine is injected. FIG. 10 is a sectional view of an embodiment of the present invention showing how the adjustment support tube is held by a spacer, and FIG. 11 is a sectional view of an embodiment of the invention showing how the end portion of the adjustment support tube is sealed. , FIG. 12 is a partial cross-sectional view of one embodiment of the present invention showing how water is stopped when a joint is slightly damaged;
Figure 3 is a partial cross-sectional view of an embodiment of the present invention showing water stoppage for a joint of a different type from the joint shown in Figure 12, and Figure 14 is a partial sectional view of the present invention showing water stoppage of a vertical crack in a pipe. FIG. 3 is a partial cross-sectional view of one embodiment of the invention. Fig. 15 is a partial sectional view of an embodiment of the present invention showing water supply at the manhole slab joint, and Fig. 16 is a partial cross-sectional view showing water stoppage at the manhole side block joint. A partial cross-sectional view of. Fig. 17 is a cross-sectional view of an embodiment of the present invention showing how water is stopped in a manhole skeleton crack; Fig. 18 is a cross-sectional view of an embodiment of the present invention showing how the adjustment wood pipe is drawn in; Fig. 19 The figure is a cross-sectional view of an embodiment of the present invention showing how the adjustment support tube is drawn through the manhole. Here, l...° drain pipe, 2... support steel pipe, 6...
・Jacket, 7... Adjustment woodwind, 8... Spacer,
9... Grout nozzle, 10... Chemical injection nozzle, 11
...Adjustment support pipe, 12...Seal cement, 13.
...UG Grau I. Patent Applicant Mitsuru Kubo Figure 3 Figure 7 Cause 8; 1j9 Figure 10 Figure 11 Figure 42) 4 Figure 131 1 Figure 14 Figure 15 Figure 2,'; 16 Figure

Claims (2)

【特許請求の範囲】[Claims] (1)地中に埋設された排水)1の修復1冑人であって
、ジャッキングにてtJl木管を正常径に近うける上程
と、11j記止常径より小さな債・径を有する分割され
た支持鋼管を前記排水管内に付設する工程と、前記旧設
された支持tl’l管を溶接して一体化する王1程と前
記溶接された支持鋼管内に調整木管を11j設する」−
程と、充填物質を注入して前記υ1木管と前記調整本管
とを一体化する工程とから成るυ1水管の修復工法。
(1) Drainage buried underground) 1. Repair 1. The upper part of the tJl wood pipe was jacked to a diameter close to the normal diameter, and the pipe was divided into parts with a smaller diameter than the normal diameter listed in 11j. a step of attaching a support steel pipe to the drain pipe; a process of welding and integrating the previously installed support pipe; and installing an adjustment wood pipe within the welded support steel pipe.
and a step of injecting a filling material to integrate the υ1 wood pipe and the regulating main pipe.
(2)地中に埋設されたD1水管の修復工法であって、
ジャッキングにて排水管を正常径に近づける工程と、該
正常径を保持すべく該刊水管に薬注ノズルを設けて該排
水管の外方番こ硬化剤を91人する工程と、前記正常径
より小さな管径を右する分割された支持鋼管を前記排水
管内に付設する工程と、前記イ・1設された支持鋼管を
溶接して一体化する工程と前記溶接された支持鋼管内に
調整木管を布設する工程と、充填物質を注入して前記排
水管と前記調整木管とを一体化する工程とから成る刊水
管の修復工法。
(2) A method for repairing D1 water pipes buried underground,
a step of bringing the drain pipe closer to its normal diameter by jacking, a step of installing a chemical injection nozzle in the water pipe to maintain the normal diameter and applying a curing agent to the outside of the drain pipe; A step of attaching a divided support steel pipe having a diameter smaller than the pipe diameter into the drain pipe, a step of welding and integrating the support steel pipes installed in A.1, and adjustment within the welded support steel pipe. A method for repairing a water pipe, which comprises a step of laying a wooden pipe, and a step of injecting a filling substance to integrate the drain pipe and the adjusting wood pipe.
JP57118677A 1982-07-09 1982-07-09 Method of repair construction of drain pipe Pending JPS599384A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP57118677A JPS599384A (en) 1982-07-09 1982-07-09 Method of repair construction of drain pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP57118677A JPS599384A (en) 1982-07-09 1982-07-09 Method of repair construction of drain pipe

Publications (1)

Publication Number Publication Date
JPS599384A true JPS599384A (en) 1984-01-18

Family

ID=14742469

Family Applications (1)

Application Number Title Priority Date Filing Date
JP57118677A Pending JPS599384A (en) 1982-07-09 1982-07-09 Method of repair construction of drain pipe

Country Status (1)

Country Link
JP (1) JPS599384A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5989883A (en) * 1982-11-11 1984-05-24 住友金属工業株式会社 Method of communicating connecting section of pipe
JPS63152794A (en) * 1986-12-16 1988-06-25 テイヒュー株式会社 Method of repairing pipe

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5989883A (en) * 1982-11-11 1984-05-24 住友金属工業株式会社 Method of communicating connecting section of pipe
JPS63152794A (en) * 1986-12-16 1988-06-25 テイヒュー株式会社 Method of repairing pipe
JPH0351956B2 (en) * 1986-12-16 1991-08-08 Teihyuu Kk

Similar Documents

Publication Publication Date Title
US10968594B1 (en) Manhole rehabilitation system
CN103726503B (en) Anchor rod pile reinforcing bearing platform structure used for reinforcing deformed bridge pile and construction method thereof
CN109667985B (en) Method for butting pipe pushing jack and receiving well steel sleeve in pipe pushing construction
KR101415106B1 (en) The back feel grouting apparatus for upper part of tunnel
CN106641446A (en) Anti-sedimentation pipe carrier for large-diameter pipeline and construction method of anti-sedimentation pipe carrier
CN110778333A (en) Tunnel leakage repairing method
CN106812131B (en) A kind of permanent sheet pile underground structure and its construction method
KR20180034725A (en) Medium and large diameter pipeline inner diameter around the president and grout repair and reinforcement
CN110804931A (en) Treatment method for lifting road surface
CN114687345A (en) Method for repairing surface subsidence or deformation of underground pipe outside foundation pit enclosure wall
CN109024621A (en) The compound retaining wall supporting construction of embankment high slope tubular pole and its construction method
KR100362615B1 (en) A Repairing Method of Underground Voids of Approach Slab in Abutment Constructure
JPS599384A (en) Method of repair construction of drain pipe
CN110397819A (en) A kind of fracture of wire PCCP does not cut off the water outer patch Prestressed CFRP and high polymer grouting combined-repair method
JP2012167473A (en) Reinforcement structure and reinforcement method of columnar structure
JP7451337B2 (en) Tunnel renewal method and structure
JPS5910639A (en) Repairing of drain pipe
CN112983436A (en) Water-rich shield interval measuring point-of-delivery punching construction method
CN113464721A (en) Low-noise vibration-reduction slot-opening-free construction method and device for tunnel jacking pipe
CN112112248A (en) Method for repairing defect of channel box
KR100379187B1 (en) delay-joint method of constructuction for underground structure
JPH0813495A (en) Earth retaining wall and method thereof
CN115478548B (en) Expansion soil cutting side slope expansion-reducing anti-seismic disaster-preventing combined retaining structure and construction method
JP7540678B1 (en) System and method for backfilling narrow excess trenches in a mine with liquefied hardened soil
CN111088802B (en) New and old ground wall connection interface processing structure and processing method thereof