JPS5988551A - Construction of air membran structured construction - Google Patents
Construction of air membran structured constructionInfo
- Publication number
- JPS5988551A JPS5988551A JP19947482A JP19947482A JPS5988551A JP S5988551 A JPS5988551 A JP S5988551A JP 19947482 A JP19947482 A JP 19947482A JP 19947482 A JP19947482 A JP 19947482A JP S5988551 A JPS5988551 A JP S5988551A
- Authority
- JP
- Japan
- Prior art keywords
- construction
- wire
- membrane
- post
- work
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Tents Or Canopies (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
この発明は、空気膜構造構築物の施工法の提案に係わる
。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a proposal for a construction method for an air membrane structure construction.
空気膜構造の構築物は、我が国では、殆んど例がないが
、現在性なわれている工法としては、第1図、第2図に
示されるような工法で施工している。There are almost no examples of structures with air membrane structures in Japan, but the construction methods currently in use are as shown in Figures 1 and 2.
すなわち、第1図に示すのは、先ず、ワイヤー1をレッ
カー2、軍用ヘリコプタ−21等によシ躯体3上端のリ
ングビーム4に先行架設を行ない(a図)、その後、該
ワイヤーl交点の締め付は並びに膜5貼を該ワイヤーl
に架設のゴンドラ6で行なう(b図)方法若しくは、第
2図に示す如く、所定σ膜面レベル下部に全面にステー
ジ7を架け、これを用いてワイヤー1.膜5を貼る方法
の2種類がある。That is, as shown in FIG. 1, the wire 1 is first erected on the ring beam 4 at the upper end of the body 3 by a tow truck 2, a military helicopter 21, etc. (Fig. a), and then the wire 1 is erected at the intersection of the wire 1. Tighten and attach the membrane 5 to the wire l.
Alternatively, as shown in FIG. 2, a stage 7 is installed over the entire surface below a predetermined σ film surface level, and this is used to conduct the wire 1. There are two methods for applying the membrane 5.
いずれも観覧席S等の内部構築物の完了後に膜屋根の架
構工事が行なわれる。In both cases, the construction of the membrane roof structure will be carried out after the internal structures such as the bleachers S are completed.
しかるに、斜上の如き要領の工法にあっては、先ス、膜
屋根架構の点については、第1図の工法では高所作業の
為、交点、膜の接続等の品質管理が不十分となシやすく
、ワイヤーの鞘度の不良、膜のよれ等が発生し易い、又
、工期的にも非能率であって長く、安全面も問題があり
、他方、第2図の工法では、前者の問題点を消去し得る
が、高い所への架設はステージが膨大なものとな夛、工
期、コストの面で問題となる、
又、工期の点については、内部構築物の施工を露天で行
なうものであるため、天候によって工期が影響を受ける
こととならざるを得ないが、現在のきびしい受注県外の
なかで特に、短工期を克服しなければならない工事が多
くなっているのに、天候のために作業不能となる日が多
くなシ一層工期もきびしくなるという難点がある。However, when it comes to construction methods such as diagonal construction, the quality control of intersections, membrane connections, etc. is insufficient in the construction method shown in Figure 1 for the membrane roof structure due to the work being done at height. The construction method shown in Figure 2, on the other hand, However, construction at a high place requires a huge number of stages, which poses problems in terms of construction time and cost.Also, in terms of construction time, it is possible to construct internal structures in the open air. Since the construction period is limited, the construction period will inevitably be affected by the weather, but even though there are many construction projects outside the prefecture that have to overcome short construction periods, especially in areas outside the prefecture where orders are currently tight, The disadvantage is that there are many days when work is not possible due to this, and the construction period becomes even tighter.
本発明は、斜上の事情に鑑み、上記の諸Xle点を全く
解消し得る新規な工法を開発すべくなされたもので、そ
の要旨とするところは、観覧席等の内部構築物を除く外
周躯体工事を先行し、当該躯体内周面に立設の架設ワイ
ヤー吊シ上げガイドボストにワイヤ一端部を係止させて
当該ボストの中途所定位置まで上昇させ、この状態にて
ワイヤー交点の締め付は並びに膜貼を地上作業にて行な
い、完了後、ワイヤーをさらに上昇させて躯体上端のリ
ングビームに配設の取付用金具にワイヤ一端部を種化組
み付け、しかる後、該ボストを撤去するとして、膜屋根
架構作業をワイヤー、膜の架設が高所に於ける作業があ
ったのを地上作業でなし得るものとして作業性(品質)
の向上、工期短縮、安全性の増加を図るとすると共に、
当該膜屋根架設が完了後、デフレート状態の膜面上部に
水を貯めると共に膜面中央部下面と地上間にロープ等を
架は渡して張設して風に対して安定させ、かかる膜屋根
の養生下で観覧席等の内部構築物、内部施設の内部作業
を行なうとして天候の如何にかかわらず、作業を可能と
して工期の短縮化を実現した点にある。The present invention has been made in view of the circumstances of the slope, and has been made to develop a new construction method that can completely eliminate the above-mentioned Xle points. Prior to the construction work, one end of the wire is locked to a wire hoisting guide post erected on the periphery of the body and raised to a predetermined position midway through the post, and in this state the wire intersections are tightened. In addition, the membrane pasting will be carried out on the ground, and after completion, the wire will be raised further and one end of the wire will be attached to the mounting bracket installed on the ring beam at the top of the structure, after which the post will be removed. Workability (quality): Membrane roof frame work can be done with wires, and membrane construction can be done on the ground instead of work at high places.
In addition to aiming to improve safety, shorten construction time, and increase safety,
After the construction of the membrane roof is completed, water is stored in the upper part of the deflated membrane surface, and a rope or the like is stretched between the central lower surface of the membrane surface and the ground to stabilize it against wind. The main advantage of this system is that it enables work to be carried out on internal structures such as bleachers and internal facilities under curing conditions, regardless of the weather, thereby shortening the construction period.
以下、これを実施例図にもとづいて詳細に説明する。Hereinafter, this will be explained in detail based on embodiment figures.
すなわち、第3図に於いて、図中8は外周躯体、9は尚
該外周躯体8」)周縁に立設の架設ワイヤー吊シ上げガ
イドボストで、これは、各架設ワイヤー10両端が沿移
動可に係止組付けられるものであって、各架設ワイヤー
につき外周躯体8周辺に相対峙して設置されるものであ
る、
該架設ワイヤー10は該ボスト9に沿って上昇移動制御
されるが、その駆動手段としては、ストロークジヤツキ
とピニオン・ラックの組合せ等種々前えられるが、図示
例にあっては、架設ワイヤー10の端部に装着の金具1
1を吊るワイヤーロープブ12を該ボスト9上端上端に
配設の情事13を介して地上に設置のウィンチ14で巻
取るものとしている。That is, in FIG. 3, reference numeral 8 in the figure is the outer peripheral frame, and 9 is an erection wire hoisting guide boss installed on the periphery of the outer circumferential frame 8. Each construction wire is installed facing each other around the outer peripheral frame 8, and the construction wire 10 is controlled to move upward along the post 9. Various driving means are available, such as a combination of a stroke jack and a pinion rack, but in the illustrated example, a metal fitting 1 attached to the end of the construction wire 10 is used.
1 is wound up by a winch 14 installed on the ground via a wire rope 13 provided at the upper end of the boss 9.
かくして、全ての架設ワイヤー10の両端をボスト9に
組み付けたならば、これを集中制御でもって地上作業に
好適な所定高さとなるボスト9中途所定位置まで上昇さ
せて一旦停止し、この状態にて地上作業による架設ワイ
ヤー交点の締め付は並びに膜15の貼作業をとり行なう
。In this way, once both ends of all the construction wires 10 have been assembled to the post 9, they are raised under centralized control to a predetermined position midway through the post 9, which is a predetermined height suitable for ground work, and then stopped once. Tightening of the intersection points of the construction wires is carried out by ground work, as well as the pasting work of the membrane 15.
しかる後、この交点締め付は並びに膜貼を完了した架設
ワイヤー10′を再度上昇させ、該外周躯体8上端のリ
ングビーム16に配設の取付用アンカー17に該端部金
具11會枢止組付することで架設力五女される。Thereafter, this intersection tightening is carried out, and the construction wire 10', which has been pasted with a membrane, is raised again, and the end fitting 11 is pivoted to the mounting anchor 17 provided on the ring beam 16 at the upper end of the outer frame 8. By attaching it, the power of construction becomes five women.
このあと、ワイヤーロープ12を端部金具11より取り
はずすと共に該ボスト9を撤去する。Thereafter, the wire rope 12 is removed from the end fitting 11 and the post 9 is removed.
図に於いて、架設ワイヤー10′の点鎖線態様は内圧付
加にて屋根膜がふくらんだインフレートの態様を示す・
斜上実施例に於ける該架設ワイヤ一端部金具11と架設
ワイヤー吊シ上げガイドボスト9の詳細を第4図、第5
図に示す。In the figure, the dotted chain line of the construction wire 10' shows the inflated state in which the roof membrane swells when internal pressure is applied.The construction wire one end fitting 11 and the construction wire hoisting in the diagonal embodiment. Details of the guide post 9 are shown in Figures 4 and 5.
As shown in the figure.
fR4図a、bは架設ワイヤ一端部会具11を示し、こ
れは略コの字状枠Ll&の前面壁11t)に架設ワイヤ
ー10端部のボルトロッドioatm通させ、ワッシャ
ー18、止めポル) 19・・・にて止着させ、両Il
l壁11(! t 11’(!のテール部をブラケツ)
1lcLに構成して、これと該取付用アンカー17の
先端部に発子しの透孔17aとの間に止めボルト(図示
省略)を差し渡すことによってリングビーム16に対し
ての架設ワイヤーlOの種化をなすとし、枠ILa前端
部には鞘状の吊フックlieが溶接さitてわり、これ
にワイヤーロープ12が止められ−C上記の金具11の
吊シがなされるものとし、さらに、該両側壁lie $
11’oより取付軸ll±’ a ll’fを突設し、
これにローラー11g、 l]、’gを組み付け、とれ
を図示の如く、該ボスト9を構成するところの対峙組付
けのH儒柱20 、2o’間に渡架させることによって
、ボスト9に対する係止をなさしめたものである、次に
、ボスト9は第5図に詳示され、これは図示例では上述
の如く、HfII柱20 、20’を所定間隔をもって
対峙させ、所定個所にヨーク21・・・を配して構成さ
れる、
伺、図中21 、21’は該ローラー11g e 11
’媚係防止用のためにH鋼柱20 、20’端部に溶接
のレール角fIJA22はリングと一ム16との間に差
し渡しのスペーサーである。Figures a and b of fR4 show one end fitting 11 of the construction wire, which is a substantially U-shaped frame Ll & front wall 11t) through which the bolt rod ioatm at the end of the construction wire 10 is passed, a washer 18, and a stopper 19. Attach it at..., and attach both Il.
l wall 11 (! t 11' (bracket the tail of !)
1lcL, and by inserting a stop bolt (not shown) between this and the through hole 17a formed at the tip of the mounting anchor 17, the erection wire lO can be connected to the ring beam 16. A sheath-shaped hanging hook lie is welded to the front end of the frame ILa, and the wire rope 12 is fastened to this to hang the metal fitting 11, and further, Both side walls lie $
A mounting shaft ll±'a ll'f is provided protruding from 11'o,
Assemble the roller 11g, L] and 'G, and the Rolling is in charge of Bost 9 by putting between the H Confucian pillars 20 and 2O' in the confrontation of the Bost 9, as shown in the illustration. Next, the post 9 is shown in detail in FIG. 5, and in the illustrated example, as described above, the HfII pillars 20 and 20' are opposed to each other at a predetermined interval, and the yoke 21 is attached at a predetermined position. 21 and 21' in the figure are the rollers 11g e 11.
The rail angle fIJA 22 welded to the ends of the H steel columns 20 and 20' is a spacer across between the ring and the arm 16 to prevent sexual intercourse.
斜上の如く構成される本発明工法に於ける膜屋根架に5
にあっては、ワイヤー交点の締め付は並びに膜貼の全て
を地上作業でもってなし得るため、良好なる品質管理の
もとで作業し得、かつ、作業性も向上し得、工期短縮、
安全性、コストが著しく改善され、特に、大規模な模購
造の場合、安全性、工期、コストに大きなメリットを発
揮することとなる。5 for the membrane roof frame in the construction method of the present invention which is constructed as if it were tilted upward.
In this case, all of the tightening of wire intersections and the application of the membrane can be done on the ground, so the work can be done under good quality control, and the work efficiency can be improved, shortening the construction period.
Safety and cost are significantly improved, and especially in the case of large-scale counterfeit purchasing, there will be significant benefits in terms of safety, construction time, and cost.
次いで、第6図に示す如く、架設の完了したデフレート
状態の膜屋根23上部に水24を貯めると共に膜面中央
部下面と地上間にロープ25.・・・等を架は渡して張
設して風に対して安定させ、かかる膜屋根23の養生下
にて、観覧席S等の内部構築物、内部施設の内部作業を
と9行なう。Next, as shown in FIG. 6, water 24 is stored in the upper part of the deflated membrane roof 23, which has been completely erected, and a rope 25 is placed between the lower surface of the center of the membrane surface and the ground. . . . etc. are stretched over the roof to stabilize it against the wind, and under the protection of the membrane roof 23, internal work on the internal structures such as the bleachers S and internal facilities is carried out.
同、この状態での降雨等による必要以上の貯水に対して
は膜面中央にドレイン26を設け、各グリッドからオー
バーフローした水を下へ流して排水し・てコントロール
すれば良い。Similarly, in case of excess water storage due to rain or the like in this state, a drain 26 may be provided at the center of the membrane surface, and water overflowing from each grid may be drained by flowing downward to control the water storage.
この内部作業は天候に一切影響されないので、工期の短
縮化に太いに寄与する、This internal work is completely unaffected by the weather, which greatly contributes to shortening the construction period.
第1図a、b並びに第2図は従来工法の説明図、第3図
は、本発明工法に於ける膜屋根架構の説明図、第4図a
、bは本発明工法に於ける膜屋根架構に使用する一治具
の平面、側面図、第5図8゜bは本発明工法に於ける膜
屋根架構に使用するボストの側面、正面図、第6図は本
発明工法に於ける内部作業の態様を示す説明図である。
S・・・観覧席、8・・・外周躯体%23・・・空調設
備、9・・・ガイドボスト、10・・架設ワイヤー、1
5・・・膜、1G・・・リングビーム、23・・・膜屋
根、25・・・ローブ。
発明者 へ重樫 茂 夫
発明者 菅 井 徒 史
出願人 株式会社竹中工務店
代表者 竹 中 統 −Figure 1 a, b and Figure 2 are explanatory diagrams of the conventional construction method, Figure 3 is an explanatory diagram of the membrane roof frame in the construction method of the present invention, and Figure 4 a.
, b is a plane and side view of a jig used for the membrane roof frame in the construction method of the present invention, FIG. FIG. 6 is an explanatory diagram showing aspects of internal work in the construction method of the present invention. S...Grandstand seats, 8...Outer frame%23...Air conditioning equipment, 9...Guide posts, 10...Erection wire, 1
5... Membrane, 1G... Ring beam, 23... Membrane roof, 25... Lobe. Inventor: Shigeo Shigegashi Inventor: Toshi Sugai Applicant: Takenaka Corporation Representative: Osamu Takenaka −
Claims (1)
該躯体内局面に立設の架設ワイヤー吊り上げガイドポス
トにワイヤ一端部を係止させて当該ポストの中途所定位
置まで上昇させ、この状態にてワイヤー交点の締め付は
並びに膜貼を地上作業にて行ない、完了後、ワイヤーを
さらに上昇させて躯体上端のリングビームに配設の取付
用金具にワイヤ一端部を枢止組み付け、しかる後、該ポ
ストを撤去するとして、膜屋根架構作業會とり行ない、
当該膜屋根架設が完了後、デフレート状態の膜面上部に
水を貯めると共に膜面中央部下面と地上間にロープ等を
架は渡して張設して風に対して安定させ、かかる膜屋根
の養生下で観覧席等の内部構築物、内部施設の内部作業
を行なうとしてなることを特徴とする空気[構造構築物
の施工法。Prior to construction of the outer frame excluding internal structures such as spectator seats, one end of the wire is latched to an erection wire lifting guide post erected on the side of the frame, and the post is raised to a predetermined position midway, and in this state. Tightening the wire intersections and pasting the membrane are done on the ground. After completion, the wire is raised further and one end of the wire is pivoted and assembled to the mounting bracket installed on the ring beam at the top of the structure. To remove the post, a membrane roof frame work meeting will be held.
After the construction of the membrane roof is completed, water is stored in the upper part of the deflated membrane surface, and a rope or the like is stretched between the central lower surface of the membrane surface and the ground to stabilize it against wind. A construction method for structural structures that is characterized by the fact that work is carried out on internal structures such as bleachers and internal facilities under curing conditions.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP19947482A JPS5988551A (en) | 1982-11-13 | 1982-11-13 | Construction of air membran structured construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP19947482A JPS5988551A (en) | 1982-11-13 | 1982-11-13 | Construction of air membran structured construction |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS5988551A true JPS5988551A (en) | 1984-05-22 |
JPS6226381B2 JPS6226381B2 (en) | 1987-06-09 |
Family
ID=16408394
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP19947482A Granted JPS5988551A (en) | 1982-11-13 | 1982-11-13 | Construction of air membran structured construction |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS5988551A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH01203572A (en) * | 1988-02-05 | 1989-08-16 | Taiyo Kogyo Kk | Extension of suspension film |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62136491U (en) * | 1986-02-21 | 1987-08-27 |
-
1982
- 1982-11-13 JP JP19947482A patent/JPS5988551A/en active Granted
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH01203572A (en) * | 1988-02-05 | 1989-08-16 | Taiyo Kogyo Kk | Extension of suspension film |
Also Published As
Publication number | Publication date |
---|---|
JPS6226381B2 (en) | 1987-06-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108532769A (en) | A kind of jack-up construction method of the additional elevator shaft structure of assembled | |
US4880024A (en) | Self-supporting tent | |
JPS5988551A (en) | Construction of air membran structured construction | |
US3769764A (en) | Mobile home holdown apparatus | |
US3846953A (en) | Beams for hyperbolic paraboloid roofs | |
JPS5988553A (en) | Construction of air membran structured construction | |
JPH0657741A (en) | Earth retaining wall | |
JP3072214B2 (en) | Temporary shed | |
JP2950726B2 (en) | Construction method of multi-layer suspension structure | |
JP2858891B2 (en) | Construction method of large span dome roof | |
GB2115368A (en) | A method of raising a transmission pole or lighting mast | |
JPS5934346A (en) | Construction of film structure | |
JPS5841160A (en) | Method and apparatus for preventing pain scattering in painting work of high chimney | |
JP2779998B2 (en) | Lifting device for temporary tents | |
JPH0776933A (en) | Method of constructing large roof | |
JPS6339754B2 (en) | ||
JP3239154B2 (en) | Lift-up device for all-weather temporary roof | |
JP3381046B2 (en) | Construction method of large span roof frame | |
JP2663102B2 (en) | Long span canopy equipment and its construction method | |
JP2634271B2 (en) | Jack-up method and device | |
JPS5988552A (en) | Construction of film structure | |
JPS61169584A (en) | Construction of fence | |
JP2994205B2 (en) | Structural assembly method | |
JPH0642185A (en) | Installing method of long structure | |
JPS6220612Y2 (en) |