JPS598810A - Construction of bridge beam box - Google Patents

Construction of bridge beam box

Info

Publication number
JPS598810A
JPS598810A JP11549782A JP11549782A JPS598810A JP S598810 A JPS598810 A JP S598810A JP 11549782 A JP11549782 A JP 11549782A JP 11549782 A JP11549782 A JP 11549782A JP S598810 A JPS598810 A JP S598810A
Authority
JP
Japan
Prior art keywords
blocks
adjacent
block
steel
abutments
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP11549782A
Other languages
Japanese (ja)
Other versions
JPS6056842B2 (en
Inventor
坂田 敏雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sato Kogyo Co Ltd
Original Assignee
Sato Kogyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sato Kogyo Co Ltd filed Critical Sato Kogyo Co Ltd
Priority to JP11549782A priority Critical patent/JPS6056842B2/en
Publication of JPS598810A publication Critical patent/JPS598810A/en
Publication of JPS6056842B2 publication Critical patent/JPS6056842B2/en
Expired legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 鉄道線路下、或いは道路下に道路若しくは河川等シ立体
交叉させて構築させるため、従来種々の悔工法が提案さ
れている。
DETAILED DESCRIPTION OF THE INVENTION Various construction methods have been proposed in the past for constructing roads, rivers, etc. under railroad tracks or under roads to cross over them.

同残工法と一つとして、鋼製の管体を例えば鉄道線路の
下にはぼこれと直角方向に管体内部よりオーガー掘削し
ながら押込み、同管体な複数本並列して押込むことによ
って横桁を構成し、その両端に線路方向に延びる主桁な
怖工して一種の下略桁な構成し、橋台、橋脚に相当する
位置にも#4Mの管体を推進して一時的な土留す惰工し
、橋梁内部の土砂を掘削したのち鉄筋コンクリート擁壁
を怖工する方法が行なわれている。また前記鋼製管体を
鉄筋コンクリート管体に置換した工法も行なわれている
One of the remaining construction methods is to push a steel pipe under a railroad track, for example, by digging an auger from inside the pipe in a direction perpendicular to this, and then pushing multiple pieces of the same pipe in parallel. The cross girder is constructed, and the main girders extending in the direction of the track are constructed at both ends to form a kind of lower girder, and #4M pipes are also pushed into the positions corresponding to the abutments and piers to create a temporary structure. The method used is to construct earth retaining walls, excavate the earth and sand inside the bridge, and then construct a reinforced concrete retaining wall. Furthermore, a construction method in which the steel pipe body is replaced with a reinforced concrete pipe body is also being used.

しかしながら前記工法においては管体を横桁に使用し、
線路方向の主桁1工して両者一体となった橋梁を構成し
ているので、管体のみでは使用できず、また横桁の延長
が長い場合には適用し難くなる。
However, in the above construction method, pipe bodies are used as cross beams,
Since the bridge consists of one main girder in the track direction and both are integrated, it cannot be used with just the pipe body, and it is difficult to apply it when the cross girder is long.

また所要の橋梁ボックスの周辺に鋼製パイプシ推進して
その内部の土砂を掘削しなから支保エシ建込んだのち、
鉄筋コンクリートを場所打ちしてボックスを完成する方
法も提案されているが、橋梁のスノぞンが大きくなると
支保工も大きくなり。
In addition, a steel pipe is moved around the required bridge box, the earth and sand inside is excavated, and the support is erected.
Another method proposed is to complete the box by pouring reinforced concrete in place, but the larger the bridge's snow zone, the larger the shoring will need to be.

工事が困難になる。Construction becomes difficult.

本発明はこのような欠点を除去するために提案さ牙また
もので、長手方向に貫通する作業通路と側壁との間に同
通路と略々直交するPC鋼材挿貫孔シ連通せしめてなる
複数の鉄筋コンクリート内体ブロックシ所定位置に水平
方向に並列して一体ブロック内部より地中tm削して推
進し、相隣る前記一体ブロック間に接合モルタルを充填
するとともに、相隣る肉体のPC鋼材挿貫孔間にPC鋼
材を挿貫緊締して水平版体を構築し、次いで同版体の下
部両側に垂直方向に複数の前記一体ブロツクシ並列して
前記同様にして地中に掘進するとともに、旧下に隣る一
体ノロツクを連結して左右一双の橋台を構築し、前記水
平版体及び橋台で囲繞された土砂を押開排除することを
特徴とする橋梁ボックスの怖工方法に係るものである。
The present invention has been proposed in order to eliminate such drawbacks, and has a plurality of prestressing steel insertion holes which are connected between a longitudinally penetrating working passage and a side wall and are substantially orthogonal to the working passage. The reinforced concrete inner blocks are horizontally paralleled at predetermined positions, and the inside of the blocks are excavated underground by tm, and the joint mortar is filled between the adjacent blocks, and the prestressed concrete steel of the adjacent bodies is A horizontal slab is constructed by inserting and tightening a PC steel material between the insertion holes, and then a plurality of the integral blocks are paralleled in a vertical direction on both sides of the lower part of the slab, and are dug into the ground in the same manner as described above. This relates to a method for constructing a bridge box, which is characterized by constructing a pair of bridge abutments on the left and right by connecting integral blocks adjacent to each other under the former, and pushing and removing the earth and sand surrounded by the horizontal slab and the abutments. be.

本発明においては長手方向にに通する作業通路と側壁と
の間に、同通路と略々直交するPC<IE材挿貫孔シ連
通せしめてなる鉄筋コンクリート一体ブロックを橋梁ボ
ックス構成用のエレメントとして使用し、横桁に相当す
る部分に前記p病体ブロックな複数個並列して、その長
手方向に貫通する作業通路を利用してni)体ブロック
内部より池中を掘削するとともに、掬削土砂シ排出して
地中に推進し、相隣る國体間に接合モルタルな充填する
とともに、同各肉体ブロックのPCC鋼種挿貫孔PC鋼
材を挿貫緊締することにより、前記複数の一体が水平方
向に一体に結合された水平版体が構成されるものである
In the present invention, a reinforced concrete monolithic block is used as an element for constructing a bridge box, with a PC<IE material insertion hole that is substantially orthogonal to the working passage extending in the longitudinal direction communicating with the side wall. Then, by arranging a plurality of the P disease blocks in parallel in the part corresponding to the crossbeam, and using the work passage penetrating through the body blocks in the longitudinal direction, ni) excavate the pond from inside the body blocks and discharge the scooped earth and sand. By propelling it into the ground and filling it with joining mortar between adjacent national bodies, as well as inserting and tightening the PC steel material through the PCC steel insertion hole of each body block, the plurality of bodies are horizontally moved. An integral horizontal plate is constructed.

このように本発明においては、傾数の鉄筋コンクリート
的体ブロックを並列して地中に推進し、相隣る一体ブロ
ック相互間を結合して全体が一体化された版状の桁を構
成するようにしたので、これな支持する主桁な必要とせ
ず、前記一体ブロックな継接することによって長大な桁
の怖工も可能となる。
In this way, in the present invention, inclined reinforced concrete body blocks are pushed underground in parallel, and adjacent solid blocks are connected to each other to form an integrated plate-like girder. Therefore, there is no need for a main girder to support it, and by connecting the integral blocks, it is possible to construct a long girder.

艷に本発明においては前記版体の下部両側におけろ橋台
、橋脚に相当する部分に前記1体ノロツクを垂直方向に
並列して、前記同様にし、て同各一体ブロックを池中に
推進ぜしめてL下に隣る内体ノロツクシ連結して左右の
橋脚、橋台を怖工し、これらと前記版体との1lJlに
囲繞された土砂な掘削排除して橋梁ボックスナ怖工する
ようにしたものである。
Furthermore, in the present invention, the one-piece blocks are vertically arranged in parallel on the lower sides of the plate at the portions corresponding to the abutments and piers, and the same blocks are propelled into the pond in the same manner as described above. The inner body norotsukushi adjacent to the bottom of the L is connected, and the left and right piers and abutments are constructed, and the earth and sand surrounding these and the above-mentioned slab is removed by excavation and the bridge box is constructed. It is.

このように本発明は既製の鉄筋コンクリート的体ブロッ
クを使用してこハを地中の所定位置に並列推進するとと
もに、連結して橋梁ボックス+m工するようにしたので
、鉄筋コンクリート一体ブロック自体が本体構造となる
ので経済的で怖工期間が短縮され、また前記的体ブロッ
クの長手方向に設けられた作業通路を利用して的体ブロ
ックを掘進するようにしたので、作業が簡単、叶つ能率
的に行なわれ、線路、道路下に一体ブロックを推進する
場合も掘削断面が少なくて安全であり、他の工法に比し
て推進のための設備が小さくて済み竪坑を小さくするこ
とができる。
In this way, the present invention uses ready-made reinforced concrete body blocks to propel the blocks in parallel to a predetermined position underground, and connects them to construct a bridge box + m, so that the reinforced concrete block itself is part of the main structure. This makes it economical and shortens the construction period, and since the target block is excavated using the working path provided in the longitudinal direction of the target block, the work is easy and efficient. Even when this method is used to propel an integral block under railroad tracks or roads, it is safe because the excavation cross section is small, and compared to other construction methods, the equipment for propulsion is smaller and the shaft can be made smaller.

また前記一体ブロックの連結に際しては、同両体ブロッ
クの作業通路と側壁との間を連通ずるPC鋼材挿貫孔を
利用して、相隣る一体ブロックの各挿貫孔にPC@材を
挿貫緊締するようにしたので、前記作業通路より容易に
連結作業な行なうことができ、PC鋼材及びその緊締用
ジヤツキも既製の製品な使用しうるものである。
In addition, when connecting the integral blocks, insert the PC@ material into each insertion hole of the adjacent integral blocks using the PC steel material insertion holes that communicate between the working passage and the side wall of the two integral blocks. Since it is designed to be tightened through, the connection work can be easily performed from the working passage, and the prestressed steel material and its tightening jack can be used as ready-made products.

虹にまた本発明において使用される鉄筋コンクリート的
体ブロックは工場で製作が可能、であるため1品質のよ
い製品ができる等、本発明は多くの利点な有するもので
ある。
Additionally, the present invention has many advantages, such as the fact that the reinforced concrete blocks used in the present invention can be manufactured in a factory, resulting in a product of good quality.

以下本発明を図示の実施例について説明する。The present invention will be described below with reference to the illustrated embodiments.

(んは鉄筋コンクリート的体ブロック内部し、その長手
方向に亘って作業1m路(1)が貫通さオ]、同作業通
路fl)と側壁との間に亘って同通路と略々直交するP
C鋼材挿貫孔(2)が列設されている。(第6図参照) 而して前記一体ブロックIAI 、1所要数所定位置に
水平方向に列設し、その作業通路(1)を利用してブロ
ック内部より地中を掘削し、掘削硼を前記通路(1)よ
り排出し、掘削進度に合わせて前記一体ブロツク(〜シ
池中に推進する。
(The work passage (1) is inside the reinforced concrete body block, and the work passage (1) passes through it in the longitudinal direction.) The work passage (1) extends between the work passage (fl) and the side wall and is approximately perpendicular to the passage.
C steel material insertion holes (2) are arranged in a row. (Refer to Fig. 6) Then, a required number of integral blocks IAI are arranged horizontally in a row at predetermined positions, and the working passage (1) is used to excavate underground from inside the block, and the excavation chamber is It is discharged from the passageway (1), and is propelled into the integrated block (-) pond according to the progress of excavation.

第4図は前配一体ブロック(Alの推進状態を示し、(
3)は竪坑、(4)は的体ブロック推進架台、(5)は
一体ブロックfAjの後端に配設さねたアタッチメント
(6)と竪坑(3)の内壁反力支持壁(力との間に介装
された推進ジヤツキ、(8)は土留矢板で、前記剛体ブ
ロック[A)の先端刃口(9)で所要の電盤iB)を掘
削(7,硼シ作業通路(1)を介して排出するとともに
、推進ジヤツキ(5)によって一体ノロック(Nを地盤
fBl内に推進するもので本、る。
Figure 4 shows the propulsion state of the front integrated block (Al).
3) is the shaft, (4) is the target block propulsion mount, and (5) is the attachment (6) installed at the rear end of the integral block fAj and the inner wall reaction support wall of the shaft (3). The propulsion jack (8) interposed in between is the earth retaining sheet pile, and excavates the required power board iB) with the cutting edge (9) at the tip of the rigid block [A] (7. At the same time, the propulsion jack (5) propels the N into the ground fBl.

かくして前記各画体グロック(A]シ所ボ位置まで地盤
fBl内に推4μすると、相隣る内体ブロックIIUI
AJ間に接合モルタル(10)または接着剤な充填する
とともに、相隣る画体ブロックfAl(Alの各PC@
材挿貫挿貫孔)f2)間にPC鋼線旧)を挿通してジヤ
ツキで緊張し、同pct線(印な介して相隣る画体ブロ
ック(にF、In−緊結し、かくして同各一体ブロック
(Alよりなる一枚の連続した水平の版体を構成する。
In this way, when each image body Glock (A) is pushed 4μ into the ground fBl to the position of the hole, the adjacent inner body block IIUI
Fill the space between AJ with bonding mortar (10) or adhesive, and fill the adjacent image block fAl (each PC of Al
Insert the PC steel wire (former) between the material insertion insertion hole) f2) and tighten it with a jack, and connect it to the adjacent image block (F, In-) through the same pct wire (mark), thus making the same Each integral block constitutes one continuous horizontal plate made of Al.

次いで同版体の下部両側の橋台に相当する位置に、上下
方向に暇って前記画体ブロック(んシ重合し、前記版体
の怖工と同様にして同各一体ブロックfAlを池中に推
進し、E下に相隣る的体ブロックfA1間に接合モルタ
ル(10な充填するとともに、相隣る画体ブロックfA
ljんのPC術材挿四孔を利用して前記の場合と同様に
して前記各的体ブロック(ん(〜なPC鋼線を介して連
結し、橋台な構成する。
Next, at the positions corresponding to the abutments on both sides of the lower part of the plate, the image blocks fAl are placed in a pond at a distance in the vertical direction. Propel, fill the joint mortar (10) between the adjacent target blocks fA1 under E, and fill the adjacent target blocks fA1 with
In the same manner as in the previous case, using the four holes for inserting the PC material, connect each of the target blocks via PC steel wires to construct an abutment.

次いで前記版体及び橋台で囲繞された土砂な掘削排除し
て、所要の橋梁ボックスな構成する。
Next, the earth and sand surrounded by the slab and abutment are excavated and removed to construct the required bridge box.

なお第2図は1本発明の方法によって怖工された橋梁ボ
ックスの他の実悔例シ示すものである。
FIG. 2 shows another example of a bridge box constructed by the method of the present invention.

以上本発明な実施例について説明したが1本発明は勿論
このような実癩例にだけ局限されるものでなく、本発明
の精神な逸脱しない範囲内で種々の設計の改変す怖しう
るものである。
Although the embodiments of the present invention have been described above, the present invention is of course not limited to such practical examples, and various modifications of the design may be made without departing from the spirit of the present invention. It is.

【図面の簡単な説明】[Brief explanation of drawings]

第1回)は本発明の方法によって構築された橋梁ボック
スの一実施例の斜面図、第2図は同橋梁ボックスの他の
実施例な示す正面IX+、第6図は鉄筋コンクリート前
体ブロックの掘進状態を示す縦断側面図、第4図は同勲
体ブロックの斜面図である。 (ん・・鉄筋コンクリート画体ブロック(1)・・作業
lff1路     (2)・・PC鋼材挿挿孔孔10
)・・腹合モルタル   (111°−PGq材代理人
 井理士 岡 本 重 文 外2名 10   10 I 才1関 第2図 +3図
Part 1) is a slope view of one embodiment of a bridge box constructed by the method of the present invention, Fig. 2 is a front view of another embodiment of the same bridge box, and Fig. 6 is a view of the excavation of a reinforced concrete front block. FIG. 4 is a longitudinal side view showing the condition, and a slope view of the body block. (Hmm...Reinforced concrete painting block (1)...Work lff1 road (2)...PC steel material insertion hole 10
)...Haraiai mortar (111°-PGq material agent Rishi I, Shige Okamoto, two outsiders 10 10 I Sai1 Seki Fig. 2 + Fig. 3

Claims (1)

【特許請求の範囲】[Claims] 長手方向に貫通する作業通路と側壁との間に同通路と略
々直交するPC鋼材挿貫孔な連通せしめてフよる複数の
鉄筋コンクリート噛体ブロックな所定位@に水平方向に
並列して的体ブロック内部より曲中を掘削して推進し、
相隣る前記一体ノロック間に接合モルタルを充填すると
ともに、相隣る的体のPC鋼材挿貫孔間にPC鋼材な挿
貫緊締して水平版体を構築し、次いで同版体の下部両側
に垂直方向に複数の前記一体プロックシ並列して前記同
様にして地中に掘進するとともに、に下に隣る嘴体ブロ
ックを連結して左右一双の橋台を構築し、前記水平版体
及び橋台で囲繞された土砂を掘削排除することな特徴と
する橋梁ボックスの怖工方法。
A plurality of reinforced concrete block blocks are connected horizontally in parallel at a predetermined position by connecting a working passage penetrating in the longitudinal direction and the side wall with a PC steel insertion hole that is substantially orthogonal to the passage. Excavate the curve from inside the block and propel it.
A horizontal plate is constructed by filling the joint mortar between the adjacent one-piece blocks, and inserting and tightening the PC steel material between the PC steel insertion holes of the adjacent target bodies, and then filling both sides of the lower part of the same plate. A plurality of the integrated blocks are paralleled in the vertical direction and dug into the ground in the same manner as described above, and the beak blocks adjacent below are connected to construct a pair of left and right abutments, and the horizontal blocks and abutments are connected to each other. A bridge box construction method characterized by excavating and removing surrounding earth and sand.
JP11549782A 1982-07-05 1982-07-05 Construction method of bridge boxes Expired JPS6056842B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11549782A JPS6056842B2 (en) 1982-07-05 1982-07-05 Construction method of bridge boxes

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11549782A JPS6056842B2 (en) 1982-07-05 1982-07-05 Construction method of bridge boxes

Publications (2)

Publication Number Publication Date
JPS598810A true JPS598810A (en) 1984-01-18
JPS6056842B2 JPS6056842B2 (en) 1985-12-12

Family

ID=14663967

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11549782A Expired JPS6056842B2 (en) 1982-07-05 1982-07-05 Construction method of bridge boxes

Country Status (1)

Country Link
JP (1) JPS6056842B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6273281A (en) * 1985-09-27 1987-04-03 Fuji Xerox Co Ltd Registration adjusting device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6273281A (en) * 1985-09-27 1987-04-03 Fuji Xerox Co Ltd Registration adjusting device

Also Published As

Publication number Publication date
JPS6056842B2 (en) 1985-12-12

Similar Documents

Publication Publication Date Title
JP4295272B2 (en) Friction cut plate used in open shield method and its fixing method
KR100784201B1 (en) Method for construction of tunnel
JP3382183B2 (en) Construction method for underground structure and roof cylinder used therefor
JP2003193495A (en) Underground structure constructing method
JPS598810A (en) Construction of bridge beam box
JPS584094A (en) Method of constructing low road cross
JP2816741B2 (en) How to build a large cavity
JPH06306853A (en) Construction of underground structure
JPS622116B2 (en)
KR200417399Y1 (en) Pipe roof structures
JPH0440519B2 (en)
JP2668648B2 (en) Construction method of underground structure and starting pit used for it
JPS6062327A (en) Construction of underwater continuous wall
JP3088929B2 (en) How to build underground structures
JP3146333B2 (en) Tunnel construction method
JPS6141836Y2 (en)
JPS59195996A (en) Tunnel constructing method
KR102048831B1 (en) Non-excavation type tunnel structure using steel pipe loof and leading pipe and method of constructing thereof
KR20070090345A (en) Pipe roof structures and construction method of pipe roof structures
JPH09317374A (en) Method of construction of subsurface structure
KR200247005Y1 (en) Cast-in-site diaphragms wall with benoto method and grouting method of high pressure
JPH06280469A (en) Element structure used for underground structure
JPS59185295A (en) Tunnel drilling method
JP3162947B2 (en) Hollow segment for forming underground wall and method of connecting hollow segment
JPS60133116A (en) Structure of joint part for steel pipe sheet pile