JP3088929B2 - How to build underground structures - Google Patents

How to build underground structures

Info

Publication number
JP3088929B2
JP3088929B2 JP07099905A JP9990595A JP3088929B2 JP 3088929 B2 JP3088929 B2 JP 3088929B2 JP 07099905 A JP07099905 A JP 07099905A JP 9990595 A JP9990595 A JP 9990595A JP 3088929 B2 JP3088929 B2 JP 3088929B2
Authority
JP
Japan
Prior art keywords
hollow
hollow segment
pipe
pilot
buried
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP07099905A
Other languages
Japanese (ja)
Other versions
JPH08270376A (en
Inventor
栄一 畑山
孝史 三澤
利則 朝日
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Okumura Corp
Original Assignee
Okumura Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Okumura Corp filed Critical Okumura Corp
Priority to JP07099905A priority Critical patent/JP3088929B2/en
Publication of JPH08270376A publication Critical patent/JPH08270376A/en
Application granted granted Critical
Publication of JP3088929B2 publication Critical patent/JP3088929B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Lining And Supports For Tunnels (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は地中に大断面の地下空間
を形成するための地下構造物の築造方法に関するもので
ある。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing an underground structure for forming a large underground space in the ground.

【0002】[0002]

【従来の技術】従来から、地中にトンネル等の地下空間
を築造するには、地表から計画地下空間の長さと幅でも
って所望深さまで地盤を掘削したのち、壁体を構築す
る、所謂開削工法や、シールド掘削機によって地盤を掘
削しながら該掘削機のテール部でセグメントを順次組立
てゝいく工法が一般的に知られているが、開削工法によ
れば、既設の鉄道や建築物等の存在によって施工が行え
ない場合が生じるばかりでなく、施工に当たっては地上
の設備機能を長期間に亘って阻害する虞れがあり、その
上、効率的な施工が困難である等の問題点がある。
2. Description of the Related Art Conventionally, in order to build an underground space such as a tunnel in the ground, a ground is excavated from the surface of the ground to a desired depth with a length and a width of a planned underground space, and then a wall body is constructed. A construction method and a method of sequentially assembling segments at the tail portion of the excavator while excavating the ground with a shield excavator are generally known, but according to the open-cutting method, existing railways and buildings are used. Not only may construction not be possible due to the presence of the equipment, but also there is a risk that the facility functions on the ground may be hindered for a long period of time, and furthermore, there is a problem that efficient construction is difficult. .

【0003】一方、シールド工法によれば、地盤を掘削
するカッター板が大径になる程、地盤との摩擦の関係か
らその回転数を低くしなければ掘削できないために、最
大掘削径が16m程度までの掘削しか行えず、20m以上の
大断面の地下空間を築造することが困難であり、その
上、掘削径が大きくなる程、回転駆動機構やその他の構
造が複雑化し、且つ強度や精度が要求されて製作費が高
くつくという問題点がある。又、地下深層部における掘
削には適していても比較的浅い地盤中を掘削する場合に
は地盤の崩壊が生じるために、地下浅層部に大空間を建
設する工法としては適さなく、さらに、地下街のような
断面矩形状の空間部の掘削はできないものである。
[0003] On the other hand, according to the shield method, the larger the diameter of the cutter plate for excavating the ground, the lower the number of rotations is due to the friction with the ground. It is difficult to construct an underground space with a large cross section of 20m or more, and the larger the excavation diameter, the more complicated the rotary drive mechanism and other structures become, and the strength and accuracy are increased. There is a problem that the production cost is high as required. Moreover, even if it is suitable for excavation in deep underground, when excavating in relatively shallow ground, ground collapse occurs, so it is not suitable as a method of constructing a large space in shallow underground, It is impossible to excavate a space with a rectangular cross section such as an underground shopping mall.

【0004】そこで、本願出願人等は特開平4ー155
094号公報に記載しているような地下構造物の築造方
法を開発した。この工法は、所定間隔を存して掘削した
立坑間の計画地下空間の外周に沿ってパイロット管を2
本、1組として複数組を一定間隔毎に並行に埋設したの
ち、隣り合う組の対向するパイロット管の後端面に平板
形状のセグメント部材の前端両側部を当接させた状態で
パイロット管間の地盤を掘削しながら該セグメント部材
を推進させることによりパイロット管を他方の立坑側に
押し出すと共に掘削跡に該セグメント部材を埋設し、こ
の作業を順次繰り返すことによってセグメント部材列よ
りなる地下構造物の外殻を築造する方法であって、この
方法によれば、地表から浅い地中であっても断面矩形状
の大きな地下構造物を能率よく築造することが可能であ
る。
Accordingly, the applicant of the present application has disclosed in Japanese Patent Laid-Open No. 4-155.
A method for constructing an underground structure as described in JP-A-0994 was developed. In this method, two pilot pipes are placed along the outer periphery of the planned underground space between shafts excavated at predetermined intervals.
After a plurality of sets are buried in parallel at regular intervals as one set, the pilot pipes are placed in a state in which the front end sides of the plate-shaped segment member abut on the rear end faces of the opposing pilot pipes of the adjacent sets. By pushing out the segment members while excavating the ground, the pilot pipe is pushed out to the other shaft side and the segment members are buried in the excavation site, and this operation is sequentially repeated to remove the outside of the underground structure composed of the row of segment members. This is a method of building a shell, and according to this method, it is possible to efficiently build a large underground structure having a rectangular cross section even in the ground shallow from the ground surface.

【0005】[0005]

【発明が解決しようとする課題】しかしながら、このよ
うな地下構造物の築造方法では、セグメント部材の対向
側面に互いに摺動自在に係合する雌雄継手部を突設して
おいても、セグメント部材はその側部の前端面でパイロ
ット管を押し出しながら該パイロット管をガイドとして
推進するものであるから、各組のパイロット管が上下左
右方向にずれた状態で埋設されていると、先に埋設した
セグメント部材の継手部に次に埋設するセグメント部材
の対向側面から突設した継手部を正確な位置で係合させ
ながら推進させることができなくなる。特に、長距離施
工になればなる程、上記パイロット管の埋設精度に狂い
が生じることから、長い地下構造物の築造が困難である
という問題点があった。
However, in such a method of constructing an underground structure, even if the male and female joints which slidably engage with each other protrude from the opposing side surfaces of the segment member, the segment member may be provided. Because the pilot pipe is propelled as a guide while pushing out the pilot pipe at the front end face of the side part, if each set of pilot pipes is embedded in a state shifted vertically and horizontally, it is embedded first. The joint protruding from the opposite side surface of the segment member to be embedded next to the joint of the segment member cannot be propelled while being engaged at an accurate position. In particular, there is a problem that it is difficult to construct a long underground structure because the pilot pipe burial accuracy is degraded as the construction becomes longer.

【0006】さらに、既に埋設したセグメント部材の側
面に突設している継手部は地盤中に露出状態で埋設さ
れ、この継手部に次のセグメント部材の継手部を係合さ
せながら該セグメント部材を推進させるので、これらの
雌雄継手部の係合部分に土砂が入って円滑な推進の妨げ
になるばかりでなく、セグメント部材の継手部をコンク
リートで連結処理して全体を一体化するものであるから
継手部の強度の信頼性に劣り、セグメント部材列よりな
る地下構造物に弱体部分ができるという問題点があっ
た。また、セグメント部材はコンリート製であるので、
運搬等の取扱性や施工性に難点があり、そのため、大型
のセグメント部材を使用することができず、大断面の地
下構造物を構築するには問題点がある。本発明はこのよ
うな問題点を解消することを目的とする地下構造物の築
造方法を提供するものである。
Further, the joint part projecting from the side surface of the already buried segment member is buried in the ground in an exposed state, and the joint member of the next segment member is engaged with this joint part while the segment member is engaged. Since the propulsion is performed, not only the earth and sand enter into the engaging portions of the male and female joints, which hinders smooth propulsion, but also the joints of the segment members are connected and treated with concrete to integrate the whole. There is a problem that the reliability of the strength of the joint portion is inferior, and a weak portion is formed in the underground structure including the row of segment members. Also, since the segment members are made of concrete,
There are difficulties in handling and construction such as transportation, so that a large segment member cannot be used, and there is a problem in constructing a large-section underground structure. The present invention provides a method of constructing an underground structure for solving such a problem.

【0007】[0007]

【課題を解決するための手段】上記目的を達成するため
に、本発明の地下構造物の築造方法は、築造すべき地下
構造物の断面外殻位置に複数本のパイロット管を立坑間
に埋設したのち、これらのパイロット管と中空セグメン
トとを置換して地下構造物を築造する方法であって、少
なくとも中空セグメントの継手部分に中空のパイロット
管を一方の立坑から他方の立坑に向かって順次貫通状態
で埋設したのち、両側端部に全長に亘って雌雄継手部を
形成し且つ一方の継手部に仮継手管を嵌合してなる中空
セグメントの雌雄継手部の前端面を一方の立坑側から該
雌雄継手部に対応するパイロット管に後続させて該中空
セグメントを仮継手管と一体的に他方の立坑側に向かっ
て推進させることよりパイロット管を他方の立坑側に押
し出して中空セグメントとパイロット管とを置換し、次
いで、この埋設中空セグメントに隣接して次の中空セグ
メントの仮継手管を設けていない継手部分の前端面を上
記埋設中空セグメントの仮継手管の後端面に後続させる
と共に仮継手管をパイロット管の後端面に後続させて推
進させることにより、埋設中空セグメントの仮継手管を
他方の立坑側に押し出すと共にこの仮継手管で被覆され
ていた継手部に推進中空セグメントの継手部を係合させ
且つ該中空セグメントの仮継手管を嵌合させた他側端部
側でパイロット管を押し出しながら推進中空セグメント
を埋設し、こうして埋設した該中空セグメントに隣接し
て次の中空セグメントを上記同様にして推進、埋設作業
を繰り返し行って計画地下構造物の断面外殻位置に互い
に雌雄継手部を係合させた中空セグメント列を埋設した
のち、隣接する中空セグメントを一体的に連結すると共
に中空セグメントの内部にコンクリートを充填し、しか
るのち、セグメント列で囲まれた地盤を掘削することを
特徴とするものである。
In order to achieve the above object, a method of constructing an underground structure according to the present invention comprises burying a plurality of pilot pipes between shafts at the position of the outer shell of a section of the underground structure to be constructed. After that, a method of constructing an underground structure by replacing these pilot pipes and the hollow segments, and sequentially penetrating the hollow pilot pipes at least from the joints of the hollow segments from one shaft to the other shaft. After being buried in the state, the male and female joints are formed over the entire length on both side ends, and the temporary end pipes are fitted to one of the joints. The pilot pipe is pushed out to the other shaft side by pushing the pilot pipe toward the other shaft side by following the pilot pipe corresponding to the male and female joint part and propelling the hollow segment integrally with the temporary joint pipe toward the other shaft side. The pilot section is replaced with the pilot pipe, and then the front end face of the joint section adjacent to the buried hollow segment where the temporary pipe section of the next hollow segment is not provided is connected to the rear end face of the temporary pipe section of the buried hollow segment. The temporary joint pipe of the buried hollow segment is pushed out to the other shaft side by propelling the temporary joint pipe following the rear end face of the pilot pipe, and the propulsion hollow segment is inserted into the joint part covered with the temporary joint pipe. The propulsion hollow segment is buried while the pilot pipe is pushed out on the other end side of the hollow segment where the temporary joint pipe is fitted, and the next hollow segment is buried next to the hollow segment thus buried. A hollow segment in which the male and female joints are engaged with each other at the outer shell position of the cross section of the planned underground structure by repeatedly propelling and burying the hollow segment in the same manner as above After embedded cement column, the concrete filled into the hollow segments with integrally connecting the hollow adjacent segments, after accordingly, is characterized in excavating a ground enclosed by segment column.

【0008】なお、隣接する中空セグメント同士きを連
結する手段としては、請求項2に記載したように、中空
セグメントに作業員が出入り可能な透孔を設ける共にボ
ルト取付孔を設けておき、中空セグメント内から隣接す
る中空セグメントをボルトにより連結するように構成し
ている。
As means for connecting adjacent hollow segments, as described in claim 2, a through hole through which an operator can enter and leave the hollow segment and a bolt mounting hole are provided. It is configured such that adjacent hollow segments are connected by bolts from within the segment.

【0009】[0009]

【作用】立坑間に埋設したパイロット管を中空セグメン
トの推進により押し進めながら該パイロット管と中空セ
グメントとを置換する際に、中空セグメントの側部に形
成している継手部に仮継手管を嵌合させて一体的に推進
させるものであるから、継手部は地盤中に露出すること
なく仮継手管で被覆された状態で計画地下構造物の断面
外殻位置の一部分内に埋設することができる。そして、
埋設した中空セグメントの側方に隣接して次列の中空セ
グメントを埋設擦る際に、該中空セグメントの一側継手
部を埋設中空セグメントの仮継手管に後続させるように
して該仮継手管を押し出しながらこの仮継手管で被覆さ
れた継手部にその継手部を互いに係合させて推進させる
ので、パイロット管が上下左右に多少の狂いが生じた状
態で埋設されていても該パイロット管に関係なく、両中
空セグメントを雌雄継手部の係合によって計画地下構造
物の断面外殻位置に正確に埋設することができる。
When a pilot pipe buried in a vertical shaft is pushed by a hollow segment to replace the pilot pipe and the hollow segment, a temporary joint pipe is fitted to a joint formed on a side of the hollow segment. Since the joint portion is propelled integrally, the joint portion can be buried in a portion of the cross-sectional shell position of the planned underground structure in a state of being covered with the temporary joint pipe without being exposed in the ground. And
When the next row of hollow segments is embedded and rubbed adjacent to the side of the embedded hollow segment, the temporary joint tube is extruded so that one side joint portion of the hollow segment follows the temporary joint tube of the embedded hollow segment. While the joint portion covered with the temporary joint tube is propelled by engaging the joint portion with each other, even if the pilot tube is buried in a state in which there is some deviation in the vertical and horizontal directions, regardless of the pilot tube, The two hollow segments can be accurately embedded in the outer shell position of the cross section of the planned underground structure by the engagement of the male and female joints.

【0010】その際、先に埋設した中空セグメントの継
手部を被覆している仮継手管を押し進めながらこの継手
部に次の中空セグメントの継手部を係合させて該中空セ
グメントを推進させるので、これらの雌雄継手部の係合
部に土砂が入るのを仮継手管によって防止しながら中空
セグメントを円滑に推進させることができる。
At this time, while the temporary joint pipe covering the joint portion of the hollow segment previously buried is pushed forward, the joint portion of the next hollow segment is engaged with this joint portion and the hollow segment is propelled. The hollow segment can be smoothly propelled while preventing the earth and sand from entering the engaging portions of the male and female joints by the temporary joint pipe.

【0011】また、セグメントは中空であるから、軽量
であって運搬その他の取扱性や施工性が向上すると共に
大型のセグメントを作製して大断面の地下構造物の築造
に適するものであり、その上、請求項2に記載したよう
に、中空セグメントに作業員が出入り可能な透孔を設け
る共にボルト取付孔を設けておくことによって、埋設
後、中空セグメント内に作業員が入って互いに接合した
中空セグメントの継手部同士のボルトによる連結作業が
行なえると共にその連結作業後、中空セグメント内にコ
ンクリートを充填させることによって強固な地下構造物
を築造し得る。
Further, since the segments are hollow, they are lightweight and have improved transportability and other handling properties and workability, and are also suitable for building large-sized underground structures by producing large segments. Above, as described in claim 2, by providing a through hole through which the worker can enter and leave the hollow segment and by providing a bolt mounting hole, after embedding, the worker enters the hollow segment and joined to each other. The joint operation of the joints of the hollow segments can be performed with bolts, and after the joint operation, concrete can be filled in the hollow segments to build a strong underground structure.

【0012】[0012]

【実施例】本発明の実施例を図面について説明すると、
まず、図1に示すように、地下構造物の築造断面外殻位
置に一定間隔毎に中空パイロット管1を発進立坑Aと到
達立坑B(図2に示す)間に貫通するように埋設する。
この中空パイロット管1は2メートル角の鋼管からな
り、発進立坑Aから到達立坑Bに向かって水平に圧入、
埋設する。パイロット管1の埋設方法は公知のように、
適宜な掘削機(図示せず)にパイロット管1を後続させ
ながら行うか、その内部にオーガスクリューを挿入する
ことによって行うことができる。又、築造すべき地下構
造物の長さが大きい場合には、一定長のパイロット管1
を順次直列状に継ぎ足しながら埋設すればよい。
BRIEF DESCRIPTION OF THE DRAWINGS FIG.
First, as shown in FIG. 1, a hollow pilot pipe 1 is buried at regular intervals at the outer shell position of the underground structure so as to penetrate between the starting shaft A and the reaching shaft B (shown in FIG. 2).
This hollow pilot pipe 1 is made of a steel pipe of 2 meter square, and is press-fitted horizontally from the starting shaft A to the reaching shaft B,
Buried. The method of burying the pilot pipe 1 is known,
This can be done while following the pilot pipe 1 with a suitable excavator (not shown) or by inserting an auger screw inside the pilot pipe 1. If the length of the underground structure to be built is long,
May be buried while sequentially adding them in series.

【0013】なお、パイロット管1の上面には鋼製縁切
板を載置しておき、最前部のパイロット管1上の縁切板
のみをその先端を該パイロット管1の先端に溶接等によ
って固着して到達立坑B側に達した時にその固着部を切
断等によって分離させるようにすると共に後続するパイ
ロット管1上の縁切板同士は圧入時に溶接等によって連
結しておけば、縁切板の後端を発進立坑A側に固定し
て、縁切板を地中に残置させた状態でその下面に沿って
パイロット管1と後述する中空セグメント2の置換が円
滑に行える。
In addition, a steel rim plate is placed on the upper surface of the pilot tube 1 and only the rim plate on the foremost pilot tube 1 is welded to the front end of the pilot tube 1 by welding or the like. When it is fixed and reaches the reaching shaft B side, the fixed portion is separated by cutting or the like, and the subsequent edge plates on the pilot pipe 1 are connected by welding or the like at the time of press-fitting. The rear end of the pilot tube 1 is fixed to the starting shaft A side, and the replacement of the pilot pipe 1 and the later-described hollow segment 2 can be smoothly performed along the lower surface of the pilot plate 1 while the edge plate is left in the ground.

【0014】計画地下構造物の断面外殻一部にパイロッ
ト管1を両立坑A、B間に亘って埋設したのち、このパ
イロット管1から地下構造物の断面方向に一定間隔を存
して次のパイロット管1を上記同様にして両立坑A、B
間に亘って埋設する。パイロット管1の埋設位置は、少
なくとも中空セグメント2の継手部分が埋設される位
置、即ち、一定間隔を存して隣接するパイロット管1、
1の外側面間の幅が中空セグメント2の幅に等しくなる
ように埋設される。
After the pilot pipe 1 is buried between the shafts A and B in a part of the outer shell of the planned underground structure, the pilot pipe 1 is spaced from the pilot pipe 1 at a predetermined interval in the cross-sectional direction of the underground structure. Of the pilot tube 1 in the same manner as above
It is buried in between. The embedding position of the pilot pipe 1 is a position where at least the joint portion of the hollow segment 2 is embedded, that is, the pilot pipe 1 adjacent to the hollow pipe 2 at a certain interval.
1 is buried such that the width between the outer surfaces is equal to the width of the hollow segment 2.

【0015】こうして、図1に示すように、計画地下構
造物の断面外殻部分にパイロット管1を水平方向並びに
上下方向に一定間隔毎に両立坑A、B間に貫通させた状
態で埋設したのち、これらのパイロット管1と中空セグ
メント2との置換作業を行う。この中空セグメント2は
鋼製であって図3に示すように、平面横長長方形のボッ
クス形状に形成されてあり、その厚さはパイロット管1
と同一(2メートル)であって幅は計画地下構造物を複
数分割した幅を有する。そして、その一側面の中央部に
断面コ字状の凹溝よりなる雄継手部2aを、他側面の中央
部に該雄継手部2aが嵌合可能な大きさの断面コ字状の雌
継手部2bをそれぞれ全長に亘って形成している。
In this manner, as shown in FIG. 1, the pilot pipe 1 is buried in the outer shell section of the planned underground structure at a certain interval in the horizontal and vertical directions between the shafts A and B. After that, the operation of replacing the pilot pipe 1 with the hollow segment 2 is performed. The hollow segment 2 is made of steel and is formed in a box shape having a horizontally long rectangular plane as shown in FIG.
(2 meters) and the width is the width obtained by dividing the planned underground structure into a plurality. A male joint 2a having a concave groove having a U-shaped cross section is formed at the center of one side surface, and a female joint having a U-shaped cross section large enough to fit the male joint 2a is formed at the center of the other side. Each portion 2b is formed over the entire length.

【0016】さらに、雌継手部2bの奥壁、即ち、中空セ
グメント2の他側壁面の上下部に長さ方向に一定間隔毎
にボルト取付孔3aを穿設していると共に中空セグメント
2の一側内部に雄継手部2aと平行にしてボルト締結板材
4を固着してあり、このボルト締結板材4の上下部に上
記ボルト取付孔3aと対向させてボルト取付孔3bを長さ方
向に一定間隔毎に穿設してある。
Further, bolt mounting holes 3a are formed at regular intervals in the length direction in the inner wall of the female joint portion 2b, that is, the upper and lower portions of the other side wall surface of the hollow segment 2, and one of the hollow segments 2 is formed. A bolt fastening plate 4 is fixed inside the side so as to be parallel to the male joint portion 2a. Bolt mounting holes 3b are provided at upper and lower portions of the bolt fastening plate 4 so as to be opposed to the bolt mounting holes 3a and to be spaced at regular intervals in the length direction. Drilled every time.

【0017】また、この鋼製中空セグメント2の上下板
は無孔の平坦な面に形成されている一方、前後板片2c、
2dの中央部には作業員が出入り可能な大きさの横長長方
形状透孔6、7を設けていると共に該透孔6、7の周囲
に複数のボルト取付孔3c、3dを夫々穿設している。な
お、中空セグメント2内には上下板間を連結する補強板
片を複数箇所に固着しておいてもよい。
The upper and lower plates of the steel hollow segment 2 are formed on non-porous flat surfaces, while the front and rear plate pieces 2c,
At the center of 2d, there are provided horizontally long rectangular through-holes 6 and 7 large enough for workers to enter and leave, and a plurality of bolt mounting holes 3c and 3d are formed around these through-holes 6 and 7, respectively. ing. In the hollow segment 2, reinforcing plate pieces for connecting the upper and lower plates may be fixed at a plurality of locations.

【0018】このように構成した中空セグメント2を地
中に埋設する際に、図4に示すようにその雌継手部2bに
中空セグメント2と同一長さを有する鋼製仮継手管8を
添設しておく。この仮継手管8の縦幅は中空セグメント
2の厚みに等しく形成されていると共にその一側面中央
部には全長に亘って上記雌継手部2bと同一形状を有する
断面コ字状のガイド条部8aを突設してあり、該ガイド条
部8aを雌継手部2bにパッキン10(図8に示す)を介して
摺動自在に嵌合させてある。なお、パッキン10は雌継手
部2bの上下対面面に全長に亘って固着して地下水や土砂
が内部に浸入するのを防止するものである。
When the hollow segment 2 constructed as described above is buried in the ground, a steel temporary joint pipe 8 having the same length as the hollow segment 2 is attached to the female joint portion 2b as shown in FIG. Keep it. The vertical width of the temporary joint pipe 8 is formed to be equal to the thickness of the hollow segment 2 and a guide strip having a U-shaped cross section having the same shape as the female joint 2b over the entire length at the center of one side thereof. The guide strip 8a is slidably fitted to the female joint 2b via a packing 10 (shown in FIG. 8). The packing 10 is fixed to the upper and lower facing surfaces of the female joint portion 2b over the entire length to prevent groundwater and earth and sand from entering the inside.

【0019】両立坑A、B間に埋設した上記パイロット
管1と仮継手管8を添設している中空セグメント2とを
置換するには、発進立坑A内において、仮継手管付中空
セグメント2の前端面両側部を隣接するパイロット管
1、1の後方に配設する。この場合、パイロット管1、
1間が左右方向に離間しているので、これらのパイロッ
ト管1、1間の土砂を掘削、排除する必要がある。その
ため、パイロット管1、1間に土砂掘削機9を配設す
る。
In order to replace the pilot pipe 1 embedded between the shafts A and B with the hollow segment 2 having the temporary joint pipe 8 attached thereto, the hollow segment 2 with the temporary joint pipe is set in the starting shaft A. Are arranged behind the adjacent pilot pipes 1, 1. In this case, the pilot tube 1,
1 is separated in the left-right direction, so it is necessary to excavate and remove the earth and sand between these pilot pipes 1 and 1. Therefore, the earth and sand excavator 9 is disposed between the pilot pipes 1 and 1.

【0020】この土砂掘削機9は図5、図6に示すよう
に、前端が全面的に開口し且つその両側部にパイロット
管1又は仮継手管8の後端に連通する前面開口室9b、9c
を一体に設けてなる断面コ字状のケーシング9a内にオー
ガスクリュー9dを回転自在に軸支してなる構造を有す
る。
As shown in FIGS. 5 and 6, the earth and sand excavator 9 has a front opening chamber 9b which is open at the front end and which communicates with the rear end of the pilot pipe 1 or the temporary joint pipe 8 on both sides. 9c
Are integrally provided, and an auger screw 9d is rotatably supported in a casing 9a having a U-shaped cross section.

【0021】具体的には、ケーシング9aの厚みはパイロ
ット管1の縦幅(2メートル)に等しく形成されてあ
り、計画地下構造物の一側部分を掘削する場合には上記
前面開口室9b、9cがパイロット管1と同一断面形状に形
成されその開口端面を一定間隔を存して隣接するパイロ
ット管1、1の後端開口部に連通状態で合致させるよう
にし、計画地下構造物のその他の部分を掘削する場合に
はケーシング9aの一方の前面開口室9bを仮継手管8と同
一断面に形成してその開口端面を仮継手管8の後端開口
部に連通状態で合致させるようにすると共に他方の前面
開口室9cの開口端面をパイロット管1の後端面に連通状
態で当接させるように構成している。
Specifically, the thickness of the casing 9a is formed to be equal to the vertical width (2 meters) of the pilot pipe 1, and when excavating one side of the planned underground structure, the front opening chamber 9b, 9c is formed to have the same cross-sectional shape as the pilot pipe 1, and its opening end face is made to communicate with the rear end opening of the adjacent pilot pipe 1, 1 at a certain interval in communication with the pilot pipe 1, and the other parts of the planned underground structure In the case of excavating a part, one front opening chamber 9b of the casing 9a is formed in the same cross section as the temporary joint pipe 8 so that its open end face communicates with the rear end opening of the temporary joint pipe 8 in a communicating state. At the same time, the opening end surface of the other front opening chamber 9c is brought into contact with the rear end surface of the pilot tube 1 in a communicating state.

【0022】さらに、両開口室9b、9cの内壁間にオーガ
スクリュー9dの中心軸の両端部を回転自在に挿通、軸支
させていると共に一方の開口室9bにオーガスクリュー9d
による掘削室9e内に開口した送泥短管9fを、他方の開口
室9cには掘削室9e内に開口した排泥短管9gとオーガスク
リュー駆動モータ9hを配設している。
Further, both ends of the central axis of the auger screw 9d are rotatably inserted between the inner walls of the two opening chambers 9b and 9c, and are rotatably supported, and the auger screw 9d is inserted into one of the opening chambers 9b.
, A short mud feed pipe 9f opened in the excavation chamber 9e, and the other open chamber 9c is provided with a short sludge exhaust pipe 9g opened in the excavation chamber 9e and an auger screw drive motor 9h.

【0023】そして、計画地下構造物の一側部分を掘削
する場合には、発進立坑A側でパイロット管1、1の後
端開口部にその両側前面開口室9b、9cの開口端面を突き
合わせて連通させると共にこれらの室の内部に配設した
短管9f、9gをあらかじめパイロット管1、1内に挿通
状態で配設している送排泥管21、22の後端に連結、連通
させた状態とし、この掘削機9の後壁面に仮継手管付中
空セグメント2を当接させて図2に示すように発進立坑
A内の押圧ジャッキ11で推進させると共にオーガスクリ
ュー9dを駆動してパイロット管1、1間の土砂を掘削さ
せる。
When excavating one side portion of the planned underground structure, the opening end faces of the front opening chambers 9b and 9c on both sides thereof are brought into contact with the rear end openings of the pilot pipes 1 and 1 on the starting shaft A side. The short pipes 9f and 9g provided inside these chambers were connected to and connected to the rear ends of the sending and discharging mud pipes 21 and 22 previously inserted in the pilot pipes 1 and 1, respectively. The hollow segment 2 with a temporary joint pipe is brought into contact with the rear wall surface of the excavator 9 and propelled by a pressing jack 11 in the starting shaft A as shown in FIG. Excavate earth and sand between 1 and 1.

【0024】こうして、パイロット管1、1間の土砂を
掘削しながら仮継手管付中空セグメント2をその掘削跡
に埋設し、この中空セグメント2の埋設後、次の仮継手
管付中空セグメント2を互いに密接させた前後板片2c、
2d同士のボルト取付孔3c、3d間をボルトによって連結す
ることにより継ぎ足して推進し、この作業を繰り返し行
って両立坑A、B間における地下構造物の断面外殻位置
の一側部に仮継手管付中空セグメント2を直列状に埋設
する。この際、到達立坑B側にパイロット管1、1内の
送排泥管21、22に連結、連通するポンプや土砂沈澱槽
(図示せず)が設けられてあり、送泥管21を通じて掘削
室9e内に供給される泥水で掘削土砂を排泥管22を通じて
排出するものであり、パイロット管1が到達立坑B側に
押し出される毎にその部分に配設されている送排泥管の
一部も撤去すると共に残りの送排泥管を連結して掘削土
砂の排除作業を行うものである。
Thus, the hollow segment 2 with the temporary joint pipe is buried in the excavation site while excavating the earth and sand between the pilot pipes 1 and 1. After the hollow segment 2 is buried, the next hollow segment 2 with the temporary joint pipe is inserted. The front and rear plate pieces 2c that are closely attached to each other,
By connecting the bolt mounting holes 3c and 3d of the 2d with each other by bolts, the propulsion is carried out, and this operation is repeated, and a temporary joint is formed on one side of the cross-sectional outer shell position of the underground structure between the shafts A and B. The hollow segments with tubes 2 are embedded in series. At this time, a pump and a sedimentation tank (not shown) are provided on the side of the arrival shaft B to be connected to and communicate with the mud pipes 21 and 22 in the pilot pipes 1 and 1. 9e is used to discharge the excavated earth and sand through the mud pipe 22 with the mud supplied to the inside of the pipe 9e. And remove the excavated earth and sand by connecting the remaining mud pipes.

【0025】なお、仮継手管付中空セグメント2の推進
時に仮継手管8を別な押圧ジャッキによって推進しても
よいが、あらかじめそのガイド突条部8aを中空セグメン
ト2の雌継手部2bにボルト結合によって一体化してお
き、埋設後、ボルトを撤去するように構成している。こ
のボルト結合は、仮継手管8内又は中空セグメント2内
に作業員が入って結合作業を行う。ボルトの撤去作業も
同様である。
It should be noted that the temporary joint pipe 8 may be propelled by another pressing jack when the hollow segment 2 with the temporary joint pipe is propelled. However, the guide ridge 8a is previously bolted to the female joint 2b of the hollow segment 2. It is configured such that the bolts are removed after being buried after being integrated by joining. In this bolt connection, a worker enters the temporary joint pipe 8 or the hollow segment 2 to perform the connection operation. The same applies to bolt removal work.

【0026】このように複数枚の仮継手管付中空セグメ
ント2を直列に連結した状態で計画地下構造物の一側部
に埋設されると、それ以後はこの中空セグメント2の仮
継手管8と、該仮継手管8から一定間隔(継手間隔)を
存した位置に埋設されている隣接するパイロット管1と
の後端面に掘削機9の両側開口室9b、9cの前端を当接さ
せた状態にし、掘削機9に次に埋設すべき仮継手管付中
空セグメント2を後続させで上記同様に埋設作業を行
う。
When the plurality of hollow segments 2 with temporary joint pipes are buried in one side of the planned underground structure in a state of being connected in series in this way, the temporary joint pipes 8 of the hollow segments 2 are thereafter A state in which the front ends of the two-side opening chambers 9b and 9c of the excavator 9 are in contact with the rear end face of the adjacent pilot pipe 1 buried at a position having a certain interval (joint interval) from the temporary joint pipe 8. The embedding operation is performed in the same manner as described above, with the hollow segment 2 with the temporary joint pipe to be buried next to the excavator 9.

【0027】即ち、掘削機9に後続させる仮継手管付中
空セグメント2を押圧ジャッキ11で推進させると共に掘
削機9のオーガスクリュー9dで前方地盤を掘削させ、そ
の土砂を先に埋設した中空セグメント2の仮継手管8内
に配設している送泥管21と該送泥管21に連結した掘削機
9の開口室9b内の送泥短管9f、掘削室9e、排泥短管9g、
パイロット管1内の排泥管22を通じて上記同様に排出し
ながら、掘削跡に仮継手管付中空セグメント2を埋設す
る。そうすると、先に埋設した中空セグメント2の仮継
手管8とパイロット管1とが掘削機9の掘進に従って到
達立坑B側に押し出されると共に該仮継手管8によって
被覆されていた埋設中空セグメント2の雌継手部2bに掘
削機9の開口室9b及びそれに後続する中空セグメント2
の雄継手部2aが係合しながら掘削跡にこの仮継手管付中
空セグメント2が推進、埋設される。
That is, the hollow segment 2 with the temporary joint pipe which is made to follow the excavator 9 is propelled by the pressing jack 11, and the front ground is excavated by the auger screw 9d of the excavator 9, and the earth and sand is buried first. A mud feed pipe 21 provided in the temporary joint pipe 8 and a mud feed short pipe 9f in the opening chamber 9b of the excavator 9 connected to the mud feed pipe 21; a drilling chamber 9e;
The hollow segment 2 with the temporary joint pipe is buried in the excavation trace while discharging through the drain pipe 22 in the pilot pipe 1 in the same manner as described above. Then, the temporary joint pipe 8 and the pilot pipe 1 of the previously buried hollow segment 2 are extruded toward the reaching shaft B as the excavator 9 excavates, and the female of the buried hollow segment 2 covered with the temporary joint pipe 8. Opening chamber 9b of excavator 9 and hollow segment 2 following it
The hollow segment 2 with the temporary joint pipe is propelled and buried in the excavation site while the male joint part 2a of the above is engaged.

【0028】この中空セグメント2の埋設後、次の仮継
手管付中空セグメント2を接合して密接した前後板片2
c、2d間をボルトにより一体に連結したのち推進させる
ことにより掘削跡に埋設し、以下、この作業を繰り返し
て先に埋設した中空セグメント列の雌継手部2bに雄継手
部2aを係合させた次列の仮継手管付中空セグメント2を
両立坑B、C間に亘って埋設する。そして、一側方に埋
設した仮継手管付中空セグメント列にその他側方に隣接
して埋設する仮継手管付中空セグメント2によって一側
方の中空セグメント2の仮継手管8と該仮継手管8から
継手間隔を存した位置に埋設されているパイロット管1
とを到達立坑B側に押し出しながら該中空セグメント2
を埋設する作業を計画地下構造物の幅方向に順次繰り返
し行って計画地下構造物の上床断面部分並列状態で埋設
して図7に示すように地下構造物の上床W1を築造する。
なお、同図おいては中空セグメント2を3列状に埋設し
た構造を示しているが、それ以上の複数列であっても上
記の手順によって埋設することは勿論である。
After the hollow segment 2 is buried, the next hollow segment 2 with a temporary joint pipe is joined and closely joined to the front and rear plate pieces 2.
c and 2d are integrally connected by bolts and then propelled and buried in the excavation site, and this operation is repeated to engage the male joint 2a with the female joint 2b of the hollow segment row previously buried. The next row of hollow segments 2 with temporary joint pipes is buried between both shafts B and C. Then, the temporary joint pipe 8 of the hollow segment 2 on one side and the temporary joint pipe 8 are formed by the hollow segment 2 with the temporary joint pipe embedded adjacent to the other side of the hollow segment row with the temporary joint pipe embedded on one side. Pilot pipe 1 buried at a position with a joint spacing from 8
And the hollow segment 2
The work which is embedded in the top floor section part juxtaposed state plan planned underground structures sequentially repeatedly performed in the width direction of the underground structures embedded to construction floor W 1 on the underground construction as shown in FIG.
Although FIG. 1 shows a structure in which the hollow segments 2 are embedded in three rows, it is needless to say that the hollow segments 2 may be embedded in a plurality of rows in accordance with the above procedure.

【0029】中空セグメント2を埋設したのち、左右に
隣接する中空セグメント2、2同士はボルト締結によっ
て一体的に連結されるものであり、この作業は、中空セ
グメント2内に作業員が入ってこれらの中空セグメント
2、2の雌雄継手部2a、2b間をボルトにより結合するも
のであるが、ボルトによる結合作業を行うに際して雌雄
継手部2a、2bの対向面間に土砂が少しでも浸入している
と結合強度が弱くなるので、図8に示すように、まず、
雄継手部2aの先端壁面を切除して土砂を除去したのち、
一方の中空セグメント2の他側壁に穿設しているボルト
取付孔3aと他方の中空セグメント2のボルト締結板材4
に穿設しているボルト取付孔3bとの間に連結ボルト12を
挿通してナット13を螺締することにより左右中空セグメ
ント2、2を強固に一体化するものである。
After the hollow segments 2 are buried, the right and left adjacent hollow segments 2 and 2 are integrally connected by bolting. This operation is performed by a worker entering the hollow segments 2 and The male and female joints 2a and 2b of the hollow segments 2 and 2 are joined by bolts, but at the time of performing the jointing operation with bolts, even a little earth and sand has penetrated between the facing surfaces of the male and female joints 2a and 2b. And the bonding strength is weakened, as shown in FIG.
After removing the tip wall of the male joint 2a to remove the earth and sand,
A bolt mounting hole 3a formed in the other side wall of one hollow segment 2 and a bolt fastening plate 4 of the other hollow segment 2
The left and right hollow segments 2, 2 are firmly integrated by inserting a connecting bolt 12 between the bolt mounting hole 3b and a nut 13, and screwing the nut 13.

【0030】図9はこのボルト結合構造の別な実施例を
示すもので、中空セグメント2の雌継手部2bの内側に該
雌継手部2bに近接させてボルト取付板14を固着しておく
と共にこのボルト取付板14に上記各ボルト取付孔3a、3b
に連通する複数個のボルト取付孔3eを穿設してなるもの
である。そして、左右中空セグメント2、2同士を連結
するには、上記同様にして雄継手部2aの先端壁面を切除
したのち、該雄継手部2aの先端面を他方の中空セグメン
ト2の雌継手部2bの壁面に溶接15すると共に一方の中空
セグメント2のボルト締結板材4のボルト取付孔3bと他
方の中空セグメント2のボルト取付板14のボルト取付孔
3eとの間に長尺連結ボルト16を挿通してナット17により
螺締しているものである。また、この場合、図10に示す
ように、一方の中空セグメント2の雄継手部2aを全体的
に切除して該中空セグメント2の一側端雌継手部2bを他
方の中空セグメント2の雌継手部2bの上下端面に溶接18
してもよい。
FIG. 9 shows another embodiment of the bolt connection structure. A bolt mounting plate 14 is fixed inside the female joint 2b of the hollow segment 2 so as to be close to the female joint 2b. Each of the bolt mounting holes 3a, 3b
And a plurality of bolt mounting holes 3e communicating with the holes. In order to connect the left and right hollow segments 2 and 2 to each other, the distal end wall surface of the male joint portion 2a is cut off in the same manner as described above, and the distal end surface of the male joint portion 2a is connected to the female joint portion 2b of the other hollow segment 2. And the bolt mounting hole 3b of the bolt fastening plate 4 of one hollow segment 2 and the bolt mounting hole of the bolt mounting plate 14 of the other hollow segment 2.
A long connecting bolt 16 is inserted between the nut 3e and the nut 17 and is screwed with a nut 17. In this case, as shown in FIG. 10, the male joint portion 2a of one hollow segment 2 is entirely cut off, and the one end female joint portion 2b of the hollow segment 2 is connected to the female joint portion of the other hollow segment 2. Weld 18 to the upper and lower ends of part 2b
May be.

【0031】上記のように中空セグメント2によって地
下構造物の上床W1を築造したのち、図11に示すように、
該上床W1の両側端下方に地下構造物の両側壁部W2、W2
下床W3とを順次築造する。この際、上床W1の両側端部を
形成している中空セグメント2の外端部下面に両側壁部
W2、W2を形成する中空セグメント2の上端部を接続させ
るので、上記上床W1の両外側部を形成する中空セグメン
ト2においては、その外側端部の下面に図7に示すよう
に雌継手部2bを形成しておくものである。下床W3の両外
側部を形成する中空セグメント2においても同様であ
る。
[0031] After construction of the floor W 1 on the underground structures by the hollow segments 2, as described above, as shown in FIG. 11,
Side walls W 2 of the underground structures at both side ends below the upper floor W 1, W sequentially construction and 2 and the lower floor W 3. In this case, top floor W both side wall portions on the outer end part surface of the hollow segments 2 forming the side edge portions of 1
Since W 2, W 2 connects the upper end of the hollow segments 2 forming the, in the hollow segments 2 forming both outer portion of the upper floor W 1, female 7 on the lower surface of the outer end The joint 2b is formed. The same applies to the hollow segments 2 forming the outer sides of the lower floor W 3.

【0032】そして、これらの両側壁部W2、W2と下床W3
とを築造するには、上記上床築造作業と同様に、既に埋
設された中空セグメント2の雌継手部2bに嵌合している
仮継手管8と該仮継手管8から継手間隔を存して埋設さ
れているパイロット管1を他方の立坑B側に押し出すと
共にこれらの仮継手管8とパイロット管1との間の土砂
を掘削機9で掘削しながら両側壁部W2、W2及び下床W3
築造位置に順次パイロット管1を埋設するものである。
この両側壁部W2、W2及び下床W3を形成するパイロット管
1、1・・・においても、周囲に隣接するパイロット管
1同士は上記同様にしてボルト締結により一体的に連結
される。なお、上床W1の築造後、両側壁部W2、W2と下床
W3とを順次築造したが、この順序を異ならしめても地下
構造物を築造し得ることは勿論である。また、ボルトに
替えたPC鋼線によって連結してもよい。
The side walls W 2 , W 2 and the lower floor W 3
In the same manner as in the above-mentioned upper floor construction work, the temporary joint pipe 8 fitted to the female joint portion 2b of the hollow segment 2 already buried and the temporary joint pipe 8 with a joint interval are provided. The buried pilot pipe 1 is pushed out to the other shaft B side, and the earth between the temporary joint pipe 8 and the pilot pipe 1 is excavated by the excavator 9 while the side walls W 2 , W 2 and the lower floor are excavated. in which sequentially embedding the pilot tube 1 in construction position of W 3.
Also in the pilot pipe 1,1, ... which form the side wall portions W 2, W 2 and the lower floor W 3, are integrally connected by bolts fastening the pilot tube 1 adjacent to each other around in the same manner described above . Note that after construction of the top floor W 1, both side wall portions W 2, W 2 and the lower floor
Were sequentially construction and W 3, it is of course also made different this sequence may construction of the underground construction. Also, the connection may be made by a PC steel wire instead of a bolt.

【0033】こうして、計画地下構造物の断面位置に埋
設されて上床W1、両側壁部W2、W2、下床W3を形成する互
いに連結した多数の鋼製中空セグメント2内に必要に応
じて補強鉄筋等を組立てたのち、その内部にコンクリー
ト19を打設、充填して硬化させる。コンクリートの充填
後、上床W1、両側壁部W2、W2、下床W3で囲まれた内部の
土砂を立坑側から掘削、排除して図12に示すように地下
構造物を築造するものである。この際、打設コンクリー
トは各中空セグメント2の前後板片2c、2dを通じて充填
されて隣接する中空セグメント2、2同士が一層強固に
連結、一体化して剛性に優れた強度の大きい地下構造物
を築造することができるものである。
[0033] Thus, planning top floor W 1 is embedded in the cross-sectional position of underground structures, both side wall portions W 2, W 2, as required under the floor W 3 numerous steel hollow segment 2 linked together to form a After assembling the reinforcing steel bars and the like, concrete 19 is poured into the inside, filled and hardened. After filling of the concrete, top floor W 1, both side wall portions W 2, W 2, drilling the internal sediment enclosed under floor W 3 from the vertical shaft side, exclusion to be construction of the underground construction as shown in FIG. 12 Things. At this time, the cast concrete is filled through the front and rear plate pieces 2c and 2d of each hollow segment 2, and the adjacent hollow segments 2 and 2 are further connected and integrated to form an underground structure having excellent rigidity and high strength. It can be built.

【0034】なお、以上の実施例においては、中空セグ
メント2と置換するためのパイロット管1は、中空セグ
メント2の継手間隔毎に埋設したが、その間にパイロッ
ト管1を設けておいてもよく、また、パイロット管1を
互いに対向側面同士を接合させた状態で密に埋設してお
き、掘削機9を用いることなく複数本のパイロット管1
の後端面に仮継手管付中空セグメント2の前端面を直接
当接させて推進させることによりパイロット管1と置換
してもよい。
In the above embodiment, the pilot pipe 1 for replacing the hollow segment 2 is buried at every joint interval of the hollow segment 2, but the pilot pipe 1 may be provided between them. Further, the pilot pipes 1 are closely buried in a state where the opposing side surfaces are joined to each other, and a plurality of pilot pipes 1 are used without using the excavator 9.
The pilot tube 1 may be replaced by directly abutting the front end surface of the hollow segment 2 with the temporary joint tube on the rear end surface and propelling.

【0035】また、地下構造物は図12に示したように、
断面矩形状に限らず、断面円形状であっても上記同様に
して築造し得るものである。例えば、図13に示すように
計画外殻に一定間隔毎にパイロット管1'を両立坑間に亘
って埋設したのち、図14に示すように、幅方向に彎曲し
ている中空セグメント2'を該パイロット管1'と置換すれ
ばよい。この場合、中空セグメント2'は幅方向に彎曲し
ている以外は、上記中空セグメント2と同じ雌雄継手部
や仮継手管を備えている構造としているものである。
The underground structure, as shown in FIG.
The present invention is not limited to the rectangular cross-section, but can be constructed in the same manner as described above even when the cross-section is circular. For example, as shown in FIG. 13, pilot pipes 1 ′ are buried at regular intervals in a planned outer shell between both shafts, and then, as shown in FIG. 14, hollow segments 2 ′ that are curved in the width direction are formed. It may be replaced with the pilot tube 1 '. In this case, except that the hollow segment 2 'is curved in the width direction, the hollow segment 2' has the same male and female joint portion and the temporary joint tube as the hollow segment 2.

【0036】[0036]

【発明の効果】以上のように本発明の地下構造物の築造
方法によれば、立坑間に埋設したパイロット管を中空セ
グメントの推進により押し進めながら該パイロット管と
中空セグメントとを置換する際に、中空セグメントの側
部に形成している継手部に仮継手管を嵌合させて一体的
に推進させるものであるから、継手部を地盤中に露出さ
せることなく仮継手管で被覆させた状態で計画地下構造
物の断面外殻位置の一部分内に埋設することができると
共に、埋設された中空セグメントの側方に隣接して次列
の中空セグメントを埋設する際に、該中空セグメントの
一側部の継手部を埋設中空セグメントの仮継手管に後続
させるようにして該仮継手管を押し出しながらこの仮継
手管で被覆された継手部にその対向継手部を互いに係合
させて推進させることができ、従って、パイロット管が
上下左右に多少の狂いが生じた状態で埋設されていても
該パイロット管に関係なく、両中空セグメントを雌雄継
手部の係合によって計画地下構造物の断面外殻位置に正
確に埋設することができる。
As described above, according to the method for constructing an underground structure of the present invention, when replacing a pilot pipe with a hollow segment while pushing the pilot pipe buried between the shafts by pushing the hollow segment, Since the temporary joint pipe is fitted to the joint part formed on the side of the hollow segment and is integrally propelled, the joint part is covered with the temporary joint pipe without being exposed in the ground. It can be buried in a part of the cross-sectional shell position of the planned underground structure, and when burying the next row of hollow segments adjacent to the buried hollow segment, one side of the hollow segment While extruding the temporary joint pipe so that the joint section of the temporary joint pipe follows the temporary joint pipe of the buried hollow segment, the joint sections covered with the temporary joint pipe are engaged with each other and the opposed joint sections are engaged with each other and propelled. Therefore, even if the pilot pipe is buried with some deviation in the vertical and horizontal directions, regardless of the pilot pipe, both hollow segments are connected to the outside of the planned underground structure by engaging the male and female joints. It can be accurately buried in the shell position.

【0037】その際、先に埋設した中空セグメントの継
手部を被覆している仮継手管を押し進めながらこの継手
部に上述したように、次列の中空セグメントの対向継手
部を係合させて該中空セグメントを推進させるので、こ
れらの雌雄継手部の係合部に土砂が入るのを仮継手管に
よって防止しながら中空セグメントを円滑に推進させる
ことができる。
At this time, while pushing the temporary joint pipe covering the joint portion of the previously buried hollow segment, the opposed joint portion of the next row of hollow segments is engaged with this joint portion as described above. Since the hollow segments are propelled, the hollow segments can be smoothly propelled while preventing the earth and sand from entering the engaging portions of the male and female joint portions by the temporary joint pipe.

【0038】また、セグメントは中空であるから、軽量
であって運搬その他の取扱性や施工性が向上すると共に
大型のセグメントを作製して大断面の地下構造物の築造
に適するものであり、その上、計画地下構造物の断面位
置に並列状態で埋設した隣接する中空セグメント同士は
雌雄継手部の係合と共にその係合部を一体的に連結する
と共に中空セグメント内にコンクリートを充填するの
で、強固な地下構造物を築造し得るものである。
Further, since the segment is hollow, it is lightweight, which improves transportability and other handling properties and workability, and is suitable for building a large-sized segment to build a large-sized underground structure. Above, adjacent hollow segments buried side by side at the cross-sectional position of the planned underground structure are connected to the male and female joints together with the joints together, and concrete is filled into the hollow segments, so it is strong. It is possible to build a simple underground structure.

【0039】さらに、請求項2に記載したように、中空
セグメントに作業員が出入り可能な透孔を設ける共にボ
ルト取付孔を設けておくことによって、埋設後、中空セ
グメント内に作業員が入って互いに接合した中空セグメ
ントの継手部同士のボルトによる連結作業が行なえると
共に、その連結後、上記のように、中空セグメント内に
コンクリートを充填すると隣接する中空セグメントが該
透孔を通じて充填したコンリートにより一層強固に一体
化するものである。
Furthermore, as described in claim 2, by providing a through hole through which the worker can enter and leave the hollow segment and by providing a bolt mounting hole, the worker can enter the hollow segment after embedding. The joint operation of the joint portions of the hollow segments joined to each other can be performed by bolts, and after the connection, as described above, when the hollow segments are filled with concrete, the adjacent hollow segments are further filled with the concrete filled through the through holes. It is a firm integration.

【図面の簡単な説明】[Brief description of the drawings]

【図1】パイロット管を埋設した状態の簡略縦断正面
図、
FIG. 1 is a simplified vertical sectional front view of a state in which a pilot pipe is buried,

【図2】パイロット管とセグメント部材とを置換してい
る状態の簡略縦断側面図、
FIG. 2 is a simplified vertical sectional side view showing a state where a pilot pipe and a segment member are replaced.

【図3】中空セグメントの一部切欠斜視図、FIG. 3 is a partially cutaway perspective view of a hollow segment.

【図4】仮継手管を添設した状態の斜視図、FIG. 4 is a perspective view showing a state in which a temporary joint pipe is provided.

【図5】掘削機の掘削によってセグメント部材を埋設し
ている状態の一部横断面図、
FIG. 5 is a partial cross-sectional view of a state where the segment member is buried by excavation of an excavator,

【図6】掘削機の簡略縦断側面図、FIG. 6 is a simplified longitudinal side view of an excavator,

【図7】地下構造物の上床を築造したのち次の壁部を構
築する状態の簡略縦断正面図、
FIG. 7 is a simplified longitudinal front view of a state in which the upper wall of the underground structure is constructed, and then the next wall is constructed.

【図8】セグメント部材同士の連結構造を示す要部の縦
断正面図、
FIG. 8 is a longitudinal sectional front view of a main part showing a connection structure between segment members,

【図9】その変形例を示す要部の縦断正面図、FIG. 9 is a longitudinal sectional front view of a main part showing a modified example thereof,

【図10】そのさらに別な変形例を示す要部の縦断正面
図、
FIG. 10 is a longitudinal sectional front view of a main part showing still another modification.

【図11】中空セグメントにより地下構造物の壁部を形
成した状態の簡略縦断正面図、
FIG. 11 is a simplified vertical front view of a state in which a wall of an underground structure is formed by hollow segments.

【図12】地下構造物の縦断正面図、FIG. 12 is a vertical sectional front view of an underground structure;

【図13】本発明の別な施工例を示すパイロット管の埋
設状態の簡略縦断正面図、
FIG. 13 is a simplified vertical sectional front view of a buried state of a pilot pipe showing another construction example of the present invention;

【図14】セグメント部材と置換する場合を説明するめ
の簡略縦断正面図。
FIG. 14 is a simplified vertical sectional front view for explaining a case in which a segment member is replaced.

【符号の説明】[Explanation of symbols]

1 パイロット管 2 中空セグメント 2a、2b 雄雌継手部 3a〜3e ボルト取付孔 6、7 透孔 8 仮継手管 9 掘削機 12 ボルト 19 コンクリート DESCRIPTION OF SYMBOLS 1 Pilot pipe 2 Hollow segment 2a, 2b Male-female joint part 3a-3e Bolt mounting hole 6, 7 Through hole 8 Temporary joint pipe 9 Excavator 12 bolt 19 Concrete

───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 平6−294290(JP,A) 特開 平4−155094(JP,A) 特開 平2−30886(JP,A) (58)調査した分野(Int.Cl.7,DB名) E21D 9/04 E21D 13/02 ────────────────────────────────────────────────── ─── Continuation of the front page (56) References JP-A-6-294290 (JP, A) JP-A-4-155094 (JP, A) JP-A-2-30886 (JP, A) (58) Field (Int.Cl. 7 , DB name) E21D 9/04 E21D 13/02

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 築造すべき地下構造物の断面外殻位置に
複数本の鋼製パイロット管を立坑間に埋設したのち、こ
れらのパイロット管と鋼製中空セグメントとを置換して
地下構造物を築造する方法であって、少なくとも中空セ
グメントの継手部分に中空のパイロット管を一方の立坑
から他方の立坑に向かって順次貫通状態で埋設したの
ち、両側端部に全長に亘って雌雄継手部を形成し且つ一
方の継手部に仮継手管を嵌合してなる中空セグメントの
雌雄継手部の前端面を一方の立坑側から該雌雄継手部に
対応するパイロット管に後続させて該中空セグメントを
仮継手管と一体的に他方の立坑側に向かって推進させる
ことよりパイロット管を他方の立坑側に押し出して中空
セグメントとパイロット管とを置換し、次いで、この埋
設中空セグメントに隣接して次の中空セグメントの仮継
手管を設けていない継手部分の前端面を上記埋設中空セ
グメントの仮継手管の後端面に後続させると共に仮継手
管をパイロット管の後端面に後続させて推進させること
により、埋設中空セグメントの仮継手管を他方の立坑側
に押し出すと共にこの仮継手管で被覆されていた継手部
に推進中空セグメントの継手部を係合させ且つ該中空セ
グメントの仮継手管を嵌合させた他側端部側でパイロッ
ト管を押し出しながら推進中空セグメントを埋設し、こ
うして埋設した該中空セグメントに隣接して次の中空セ
グメントを上記同様にして推進、埋設作業を繰り返し行
って計画地下構造物の断面外殻位置に互いに雌雄継手部
を係合させた中空セグメント列を埋設したのち、隣接す
る中空セグメントを一体的に連結すると共に中空セグメ
ントの内部にコンクリートを充填し、しかるのち、セグ
メント列で囲まれた地盤を掘削することを特徴とする地
下構造物の築造方法。
Claims: 1. A plurality of steel pilot pipes are buried between shafts at the outer shell position of an underground structure to be built, and these pilot pipes and steel hollow segments are replaced to replace the underground structure. A method of constructing, in which a hollow pilot pipe is buried at least in a joint portion of a hollow segment from one shaft to the other shaft in a successively penetrating state, and a male and female joint portion is formed at both end portions over the entire length. And the front end face of the male and female joint portion of the hollow segment formed by fitting the temporary joint tube to one of the joint portions is made to follow the pilot pipe corresponding to the male and female joint portion from one of the shafts to temporarily join the hollow segment. The pilot tube is pushed out to the other shaft side by propelling toward the other shaft side integrally with the tube to replace the hollow segment and the pilot tube, and then adjacent to the buried hollow segment. The front end face of the joint portion where the temporary joint pipe of the next hollow segment is not provided is followed by the rear end face of the temporary joint pipe of the buried hollow segment, and the temporary joint pipe is followed by the rear end face of the pilot pipe for propulsion. Thereby, the temporary joint pipe of the buried hollow segment is pushed out toward the other shaft, the joint part of the propulsion hollow segment is engaged with the joint part covered with the temporary joint pipe, and the temporary joint pipe of the hollow segment is fitted. The propulsion hollow segment is buried while pushing out the pilot pipe on the other end side that has been combined, and the next hollow segment is protruded in the same manner as described above adjacent to the buried hollow segment in the same manner as described above, and the burial operation is repeatedly performed to carry out the planned underground. After burying a hollow segment row in which male and female joints are engaged with each other at the cross-sectional outer shell position of the structure, the adjacent hollow segments are integrally connected. Hollow segment concrete was filled in, accordingly after, construction method of underground structures, characterized in that excavating ground surrounded by segments column.
【請求項2】 中空セグメントに作業員が出入り可能な
透孔を設ける共にボルト取付孔を設けておき、中空セグ
メント内から隣接する中空セグメントをボルトにより連
結することを特徴とする請求項1記載の地下構造物の築
造方法。
2. The hollow segment according to claim 1, wherein a through hole through which an operator can enter and leave is provided in the hollow segment, and a bolt mounting hole is provided, and adjacent hollow segments are connected from within the hollow segment by bolts. How to build underground structures.
JP07099905A 1995-03-31 1995-03-31 How to build underground structures Expired - Fee Related JP3088929B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP07099905A JP3088929B2 (en) 1995-03-31 1995-03-31 How to build underground structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP07099905A JP3088929B2 (en) 1995-03-31 1995-03-31 How to build underground structures

Publications (2)

Publication Number Publication Date
JPH08270376A JPH08270376A (en) 1996-10-15
JP3088929B2 true JP3088929B2 (en) 2000-09-18

Family

ID=14259799

Family Applications (1)

Application Number Title Priority Date Filing Date
JP07099905A Expired - Fee Related JP3088929B2 (en) 1995-03-31 1995-03-31 How to build underground structures

Country Status (1)

Country Link
JP (1) JP3088929B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4889997B2 (en) * 2004-11-10 2012-03-07 株式会社錢高組 Steel shell joining device, steel shell, outer shell, and outer shell leading tunnel construction method
CN103743558B (en) * 2014-01-06 2016-08-24 北京工业大学 A kind of component for simulating immersed tube tunnel flexible joint
CN110670265B (en) * 2019-09-22 2023-11-28 赵海 Split embroidery machine frame

Also Published As

Publication number Publication date
JPH08270376A (en) 1996-10-15

Similar Documents

Publication Publication Date Title
KR101269597B1 (en) Underground structure construction method
JP3088929B2 (en) How to build underground structures
JP2979044B2 (en) Large-scale underground structures and their construction methods
JP3131118B2 (en) Shell construction method for underground structures
JP3162947B2 (en) Hollow segment for forming underground wall and method of connecting hollow segment
KR20090060608A (en) Pipe roof structure and construction method thereof
JP2006307478A (en) Method and device for constructing arch support for increasing width of tunnel
JP3122357B2 (en) Connection method of hollow segment and this hollow segment
JPH0781489B2 (en) Tunnel construction method and device
JP2663106B2 (en) Construction method of outer wall of propulsion pipe and large cavity
JPH09287389A (en) Constructing method of subsurface structure
JP2617418B2 (en) Construction method of underground large space structure
JP2787367B2 (en) Construction method of large-scale underground space by honeycomb shield method
JP2006226036A (en) Shield boring machine and execution method of underground structure
JP2002013144A (en) Device for removal of continuous wall core pile
JP2987662B2 (en) How to build a continuous underground wall
JP3506501B2 (en) Construction method and shield machine of horizontal slab structure underground
JPH09170396A (en) Construction method for roof for underground structure
JP3177058B2 (en) Excavation method of double element for tunnel lining
JP2022134329A (en) Method for constructing underground structure
JPH08284597A (en) Lining constructing method of shield tunnel
JPS5932639B2 (en) Method of constructing underground concrete structures
JPH06307182A (en) Circular pipe for pipe roof
JPH033039B2 (en)
JPH07119547B2 (en) How to build an underground space

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees