JPS5986427A - Power system simulator - Google Patents

Power system simulator

Info

Publication number
JPS5986427A
JPS5986427A JP57196550A JP19655082A JPS5986427A JP S5986427 A JPS5986427 A JP S5986427A JP 57196550 A JP57196550 A JP 57196550A JP 19655082 A JP19655082 A JP 19655082A JP S5986427 A JPS5986427 A JP S5986427A
Authority
JP
Japan
Prior art keywords
power
power system
system state
simulation
memory
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP57196550A
Other languages
Japanese (ja)
Inventor
秀樹 林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP57196550A priority Critical patent/JPS5986427A/en
Publication of JPS5986427A publication Critical patent/JPS5986427A/en
Pending legal-status Critical Current

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔発明の技術分野〕 本発明は、電力系統模擬装置4、特に電力系統の接続状
態及び市、力需給状況を入力し、電力系統設備に流れる
電力潮流等の系統状態量を作成する電力系統模擬装置に
関するものである。
[Detailed Description of the Invention] [Technical Field of the Invention] The present invention provides a power system simulator 4, in particular, which inputs the power system connection state, city, power supply and demand situation, and calculates the system state such as power flow flowing through power system equipment. This invention relates to an electric power system simulator that creates quantities.

C発明の技術的背景〕 一般に、電力系統の模擬をする場合は第1図にブロック
的に示す電力系統模擬装置を使用している。第1図にお
いて、電力系統模擬装置1は模擬部2と設定部3とから
なっている。模擬部2は電力系統模擬部4、模擬操作指
令入力部5、模擬結果出力部6とからなシ、設定部3は
電力系統状態保存装置7、電力系統状態設定装置8、模
擬開始・系統状態メモリ9とからなっている。そして外
部からの操作信号10を模擬操作指令入力部5に入力し
、この指令に対して電力系統模擬部4で模擬された系統
応動を模擬結果出力部6を介して出力信号11として外
部へ出力する。
C. Technical background of the invention] Generally, when simulating a power system, a power system simulator shown in block form in FIG. 1 is used. In FIG. 1, a power system simulating device 1 includes a simulating section 2 and a setting section 3. The simulation section 2 includes a power system simulation section 4, a simulation operation command input section 5, and a simulation result output section 6, and the setting section 3 includes a power system state storage device 7, a power system state setting device 8, and a simulation start/system state. It consists of a memory 9. Then, an external operation signal 10 is input to the simulated operation command input section 5, and the system response simulated by the power system simulation section 4 in response to this command is outputted to the outside as an output signal 11 via the simulation result output section 6. do.

上記した電力系統模擬を開始するに当たっては、多量の
初期電力系統状前縦を設電する必要がある。
In starting the power system simulation described above, it is necessary to install a large amount of power in the initial power system configuration.

したがって通常は、実際の電力系統12の状態を伝送装
置13を介して電力系統状態保存装置7に取込み、これ
を模擬開始・系統状態メモリ9に保存しておき、これを
系統状態の初期値として電力系統模擬部4が電力系統の
模擬を開始するようにしている。
Therefore, normally, the actual state of the power system 12 is taken into the power system state storage device 7 via the transmission device 13, and this is stored in the simulation start/system state memory 9, and this is used as the initial value of the system state. The power system simulator 4 starts simulating the power system.

又、電力系統状態設定装置8がらの設定信号14により
、系統状態メモリ9の内容を部分的に変更することもで
きる。
Further, the contents of the system status memory 9 can be partially changed using the setting signal 14 from the power system status setting device 8.

〔背景技術の問題点〕[Problems with background technology]

上記構成を有する従来装置は以下に述べる理由により必
ずと云ってよいほど模擬開始時の系統状態量間に成る程
度の電力需給不平衡、即ち、発電量総和と負荷消費縦及
び送電ロス総和との不一致が存在する。第1の理由は実
際の電力系統の全端子にテレメータ装置が設置しである
訳では々く、主要な端子にのみ設置しているのが現状で
ある。
For the reasons described below, conventional equipment with the above configuration almost always has an imbalance in power supply and demand between the system state quantities at the start of the simulation, that is, the total power generation amount and the vertical load consumption and power transmission loss total. A discrepancy exists. The first reason is that telemeter devices are not often installed at all terminals in an actual power system, but are currently installed only at major terminals.

従って伝送装置13が取込めるデータ数に限シがあり、
系統内の全発電畦ないし全角荷量を取込めないこと。第
2の理由は訓練効果を上げるために、実際の電力系統と
は一部光なる電力系紡、(接続。
Therefore, there is a limit to the amount of data that the transmission device 13 can capture.
It is impossible to capture the entire power generation ridge or full width load in the system. The second reason is that in order to increase the training effect, some parts of the power system are connected to the actual power system.

状態%)を穎力系統状態設躍装置トt、8により、一部
作成していること、等の理由である。こうした電力需給
不平衡のある状態から111、力系統の模擬を開始する
と、開始直後に、例えば系統周波数が大きく変動し、そ
れによって発電(幾出力も変動すると云った状態量の急
変が起こり、fl!j局、設定したものとは大きく異な
った状態の模擬となってしまう。
This is because a portion of the state (%) is created by the power system state construction device t, 8. When simulation of a power system is started from such a state of power supply and demand imbalance111, immediately after the start, for example, the system frequency changes greatly, which causes a sudden change in the state quantity such as a change in the power generation (a number of outputs), and fl. !j station, the simulation results in a situation that is very different from the one that was set.

一方、実際の’lli、力系統では沖故でない限り大き
な電力需給不平衡はなく、事故の模擬も正常時模擬の途
中で事故発生させるようにしているために、模擬開始後
の可能な限シ短時間内で電力需給不平衡をなくすことが
望ましい。この点で従来装置では電力需給不平衡を模擬
の過程で解消することができす、解消には比較的長助間
を要する欠点を有していた。
On the other hand, in an actual power system, there is no large power supply and demand imbalance unless there is an off-shore accident, and since the accident simulation is made to occur in the middle of the normal simulation, it is possible to simulate as much as possible after the simulation starts. It is desirable to eliminate the power supply and demand imbalance within a short period of time. In this respect, conventional devices can eliminate power supply and demand imbalances in the process of simulation, but they have the disadvantage of requiring a relatively long period of time to resolve.

〔発明の目的〕[Purpose of the invention]

本発明は」二記欠点を87演することを目的としてなさ
れたものであり、模擬開始直後に電力系統状態量が急変
することのない電力系統模擬装置を提供することを目的
としている。
The present invention has been made for the purpose of reproducing the above-mentioned drawbacks, and aims to provide a power system simulating device in which the power system state quantity does not suddenly change immediately after the simulation starts.

〔発明の概要〕[Summary of the invention]

本発明では霜1力系統状態量が急変しない模擬のできる
初期状態を作成すべく、設2〆部内にフラットスタート
データ作成装置etもうけ、ソフトウェアによって予め
初期状態量ヲつくって初期系統状態保存メモリに記憶さ
せておき、模擬開始に当ってこれを電力系統模擬部へ入
力させることによりスムースな系統模擬をさせようとす
るものである。
In the present invention, in order to create an initial state that can be simulated so that the frost 1 power system state quantity does not suddenly change, a flat start data creation device is provided in the construction section, and the initial state quantity is created in advance by software and stored in the initial system state storage memory. By storing this information and inputting it to the power system simulator when starting the simulation, smooth system simulation can be achieved.

〔発明の実施例〕[Embodiments of the invention]

以下図面を参照して実施例を説明する。第2図は本発明
による電力系統模擬装置の一実施例ブロック構成図であ
る。図中のね号工ないし14は第1図に対応している。
Examples will be described below with reference to the drawings. FIG. 2 is a block diagram of an embodiment of the power system simulator according to the present invention. Numbers 1 to 14 in the figure correspond to those in FIG.

15はフラットスタートデータ作成装置であり、ここで
つくられたデータを初期系統状態保存メモリ16に記憶
しておき、模擬開始に際して電力系統模擬部4に入力す
るものである。
Reference numeral 15 denotes a flat start data creation device, which stores the data created here in an initial system state storage memory 16 and inputs it to the power system simulator 4 at the start of simulation.

第3図はフラットデータ作成装置を電子割算機のソフト
ウェアによって実現しだ一実施例フローチャートである
FIG. 3 is a flowchart of an embodiment in which the flat data creation device is realized by software of an electronic divider.

なお、以下の説明では電力系統PA擬ハ1(の系統状態
用演算方式及び演算モデルとして、その−例を潮流計算
、発電機ガバナ効果を加味した周波数動揺計算程度のも
のとし、それに見合ったフラットスタート可能な状態M
°作成についてのみ述べるが、安定計算その他の演狼、
方式の場合についても同様にして作成できることは勿論
である。
In addition, in the following explanation, the calculation method and calculation model for the system state of the power system PA pseudo-HA1 will be used as an example of power flow calculation and frequency fluctuation calculation that takes into account the generator governor effect, and a flat calculation corresponding to that calculation will be used. Startable state M
°I will only talk about the creation, but I will explain stability calculations and other performances,
Of course, it can be created in the same manner for other systems.

第3図において、5tep 31は不足データ補完処理
であり、模擬に必要な電力系統状態量のうちで電力系統
状態保存装置7によシ取込め々かったもので、かつ電力
系統状態設定装置0′8で設定されなかったものを一5
Fの規則にしたがって補完するものである。例えば発1
1t機の無効illl全力効電力から一足力率として推
知するなどの方法が考えられる。勿論この他の方法を用
いてもよい。5tep 32は送知ロス分の初期化を行
なうが、電力需給不平衡の算出に必要な送電ロスが潮流
計算を行なうまで不明であるため、初期値として例えば
Oを与えている。3tep 33は電力需給不平衡ΔP
の4算であり、Δp−(発電量の総和)−(負荷消費知
の総和)−(送電ロス)によって狗出する。
In FIG. 3, 5tep 31 is the missing data complementing process, which is the amount of power system state required for simulation that could not be captured in the power system state storage device 7, and the power system state setting device 0. 15 for those not set in '8.
It is complemented according to the rules of F. For example, call 1
Possible methods include estimating the power factor from the reactive illll total effective power of a 1 ton machine. Of course, other methods may also be used. 5tep 32 initializes the transmission loss, but since the power transmission loss necessary for calculating the power supply and demand imbalance is unknown until the power flow calculation is performed, O is given as the initial value, for example. 3tep 33 is electricity supply and demand imbalance ΔP
It is calculated by Δp - (sum of power generation amount) - (sum of load consumption knowledge) - (power transmission loss).

5tep 34はF?fl jtdした5tep 33
によるΔPがフラットスタート可能なデータとなったか
否かの判断処理であり、本実施例では潮流計算及び周波
数動揺計算を対象としているだめに、ΔPの絶対仙が十
分小さくなったか否かの判断処理を行なう。もし3te
p 34においてΔPが十分小さければフラットスター
トが可能であるだめ終了する。又、3tep 34にお
いてΔPが十分小さくなければ5tep35へ移り、Δ
Pと発電機及び負荷の特性により系統周波数を演算する
。即ち、一般には系統の周波■動揺方程式の解を求める
。5tep 36では系統周波数と基準周波数との偏差
(以下Δfと云う)をなくすように発電機発生電力を修
正する。例えばΔfの積分値を発生電力の増分とするな
ど種々の方法があるがいずれの方式であってもよい。3
tep 37では送電線の潮流を解析して送電ロスを演
舞する。その後は5tep 33に戻υ以下各5top
を繰返してΔPの絶対値が十分小さくなるまで行なわれ
る。
5tep 34 is F? fl jtd 5tep 33
This is the process of determining whether ΔP has become data that allows a flat start, and in this embodiment, the target is tidal current calculation and frequency fluctuation calculation. Do the following. If 3te
If ΔP is sufficiently small at p 34, a flat start is possible and the process ends. Also, if ΔP is not sufficiently small at 3tep 34, the process moves to 5tep 35, and ΔP is not small enough.
The system frequency is calculated based on P and the characteristics of the generator and load. That is, in general, a solution to the frequency/sway equation of the system is found. In step 36, the power generated by the generator is corrected so as to eliminate the deviation (hereinafter referred to as Δf) between the system frequency and the reference frequency. For example, there are various methods such as using the integral value of Δf as the increment of the generated power, and any method may be used. 3
In step 37, the power flow in the power transmission line is analyzed to simulate power transmission loss. After that, return to 5tep 33 and 5top each below υ
This is repeated until the absolute value of ΔP becomes sufficiently small.

第4図は市、力系統図であり、系統模擬対果が第4図に
示す様な簡単な系統である嚇合を例として第3図に示し
た本装置rtの動作を説明する。先ず第4図において4
1a、41b、41cは夫々発電機であり、42a、4
2b、42cti発旬1機昇圧変圧器、43a〜43e
は送電線、448〜44dは負荷、45a〜45fは母
糾であって図示のように構成されている。なお、以後簡
単のために有効電力分のみに着目し、電圧及び無効電力
分を除外して説明するが、これらを考1市した場合であ
ってもほぼ同様にしてフラットスタート同曲データを作
成できることは云うまでもない。
FIG. 4 is a power system diagram, and the operation of the present device rt shown in FIG. 3 will be explained using a case where the system simulation result is a simple system as shown in FIG. 4 as an example. First, in Figure 4, 4
1a, 41b, 41c are generators, 42a, 4
2b, 42cti step-up transformer, 43a to 43e
Reference numerals denote power transmission lines, 448 to 44d are loads, and 45a to 45f are main wires, which are constructed as shown in the figure. For the sake of simplicity, from now on, we will focus only on the active power component and exclude the voltage and reactive power components, but even if these are considered, the flat start same song data will be created in almost the same way. It goes without saying that it can be done.

今、模擬開始時、系統状態メモリの内容が発電機発生電
力について、41aが100MW、41bが100MW
、41cが60 MW、負荷消費電力について、44d
が40MW、44aが100 MW、 44bが80M
W、44cが80 MWであったとする。即ち、発tI
I!:機41eのデータネ良、又は電力系統状態設定装
置8による設定変更により発箱、−が不足した状態であ
るとする。
Now, when the simulation starts, the contents of the system status memory are about the generator generated power, 41a is 100MW, 41b is 100MW
, 41c is 60 MW, load power consumption is 44d
is 40MW, 44a is 100MW, 44b is 80M
Assume that W, 44c is 80 MW. That is, the emission tI
I! : It is assumed that there is a shortage of unloaded boxes due to the data failure of the machine 41e or a setting change by the power system status setting device 8.

この場合、第3図の3tep 32において送市、ロス
の初期値をOと設定したので、3tep 33における
市、力需給不平衡は、 ΔP=100+100−1−60−(40+100−1
−80+80)−0=−40MW即ち、40 MWの発
電串不足となる。
In this case, since the initial values of transport and loss at 3tep 32 in Figure 3 are set to O, the power supply and demand imbalance at 3tep 33 is ΔP=100+100-1-60-(40+100-1
-80+80)-0=-40MW, that is, there is a power generation shortage of 40 MW.

したがって5tep 34でΔPが犬であるため5te
p35で系統周波数を演算するが、負荷に対して発電量
が大幅に不足するだめ周波数の低下を招き、そこで5t
ep 36において発雷、機発生電力が増加し、又、負
荷特性によシ負荷の消費電力が減少する(負荷の消費電
力は周波数が焉くAれは多くなシ、周波数が減少すれは
少なくなることが確められている。) この結果、発電機発生電力が41aか130MW。
Therefore, 5tep Since ΔP is a dog at 34, 5tep
The system frequency is calculated in p.35, but the amount of power generated is significantly insufficient for the load, resulting in a decrease in frequency, so 5t
In ep 36, lightning strikes, the power generated by the aircraft increases, and the power consumption of the load decreases depending on the load characteristics (the power consumption of the load is higher as the frequency decreases, and less as the frequency decreases). ) As a result, the power generated by the generator is 41a or 130MW.

41bが130 MW、 41 eが80MW、負荷消
費電力が、44dが35MW、44aが95MW、44
bが75MW、44cが75 MWとなったとする。
41b is 130 MW, 41 e is 80 MW, load power consumption is 44 d is 35 MW, 44 a is 95 MW, 44
Assume that b has become 75 MW and 44c has become 75 MW.

上記条件において5tep 37で送電ロスが計算され
、例えば5 MWであるとすると、この条件下で5te
p 33において、杓ひ、電力需給不平衡か、ΔP=1
30+1.30+8O−(35+95+75+75)−
5=55MWとなって、こんどは発箱、力が過畑jとな
る。
Under the above conditions, transmission loss is calculated at 5tep 37, and if it is, for example, 5 MW, under these conditions, 5tep 37 is calculated.
At p 33, power supply and demand is unbalanced, ΔP=1
30+1.30+8O-(35+95+75+75)-
5 = 55 MW, and the power becomes Hahahata J.

この動作を繰返すうちに第5図に示す電力需給状態に達
する。
As this operation is repeated, the power supply and demand state shown in FIG. 5 is reached.

第5図においでは、41aが120 MW、 4 l 
bが120 MW、 41 cが70MW、負荷消費電
力は、44d−が40 MW 、 44 aが100M
W、44bが80MW、44cが80MW、送電ロスI
OMWであるので、 ΔP=120+120+7O−(40+100+80+
80)−10=0となり、5tep 34によっ゛C本
処理を終了する。
In Figure 5, 41a is 120 MW, 4 l
b is 120 MW, 41 c is 70 MW, and the load power consumption is 44 d- is 40 MW, and 44 a is 100 MW.
W, 44b is 80MW, 44c is 80MW, power transmission loss I
Since OMW, ΔP=120+120+7O-(40+100+80+
80)-10=0, and the main process ends at step 34.

こうして得られた糸軸、状態は送1Fロスまで含めて電
力需給不平衡のないデータであり、この状態を初期値と
して電力系統模擬を行なえばフラットスタートすること
ができる。
The thread axis and state obtained in this way are data without power supply and demand imbalance, including the loss of 1F of feed, and if a power system simulation is performed using this state as an initial value, a flat start can be achieved.

又、上記演算は模擬過程とは無関保に行なえるので極め
て短時間に実行させることができる。
Further, since the above calculation can be performed independently of the simulation process, it can be performed in an extremely short time.

又、初期系統状態保存メモリ16)ま、こうして作成し
たフラット可能データを保存したメモリであって、この
中からデータを選び出すことにょシ1b;力系統模擬部
4に入力してフラットな電力系統樟擬を゛開始すること
ができる。
In addition, the initial power system state storage memory 16) is a memory that stores the flat possible data created in this way, and it is used to select the data from this 1b; You can start simulating.

第6図は本発明による11カ系統+9擬装7Lの他の実
施例である。図中の符号lないし16は第2図に対応し
ている。17は入出力であり、フラットスタートデータ
作成装置15シてよってつくられたデータケ入出力装置
17i介し7て外部メモリ18に記憶し、模擬開始に先
立って適尚な型式のデータを選択入力することにより種
々なパターン′f:模擬しようとするものである。その
他のM中の構成は第2図と同様である。
FIG. 6 shows another embodiment of the 11 systems + 9 disguised 7Ls according to the present invention. Reference numerals 1 to 16 in the figure correspond to those in FIG. Reference numeral 17 denotes an input/output unit, which stores the data created by the flat start data creation device 15 in the external memory 18 via the input/output device 17i, and selects and inputs data of an appropriate type before starting the simulation. Various patterns 'f: are to be simulated. The rest of the configuration in M is the same as that in FIG.

〔発明の効果〕〔Effect of the invention〕

以上説明した如く、本発明によれば電力系統模擬部にフ
ラットスタートデータ作成装置及びその作成データf1
っヌは襟数ケース保看できる初期系統状態保存メモリを
もうけてフラットスタート可能なデータを予め!t ’
IA−L、ておくよう構成したので、模擬開始直後から
フラットスタートが可能な電力系統模擬装置を提供する
ことができる。
As explained above, according to the present invention, the power system simulator includes a flat start data creation device and its creation data f1.
It has an initial system state storage memory that can store several cases of collars, and has data that can be used for a flat start! t'
Since the power system simulator is configured to hold the IA-L, it is possible to provide an electric power system simulator that can perform a flat start immediately after the simulation starts.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は従来の電力系統模擬装置を示す図、第2図は本
発明による電力系統模擬装置の一実施例ブロック構成図
、第3図はフラットスタートデータ作成装置ヲソフトウ
エアで実現したフローチャート、第4図及び第5図は動
作説明のための電力系統構成図、第6図は本発明による
霜、力系統枠擬装置の他の実施例ブロック構成図である
。 l・・・′亀力系統模擬装j@2・・・模擬部3・・・
設定部      4・・・電力系統模擬部5・・・模
擬操作指令入力部 6・・・極擬結呆出力部7・・・1
b7カ系統状態保存装置8・・・電力系統状態設定装置
9・・・模擬開始・系統状態メモリ10・・・操作信号
11・・・出力信号     12・・・7b;力系統
13・・・伝送装置it、         1s・・
・フラットスタートデータ作成装置16・・・初期系統
状態保存メモリ17・・・入出力装置18・・・外部メ
モリ 特許出願人  東京芝浦電気株式会社 代理人 弁理土石井紀男 第1図 142 第3図
FIG. 1 is a diagram showing a conventional power system simulator, FIG. 2 is a block diagram of an embodiment of the power system simulator according to the present invention, and FIG. 3 is a flowchart of a flat start data creation device realized by software. 4 and 5 are power system configuration diagrams for explaining the operation, and FIG. 6 is a block diagram of another embodiment of the frost and power system frame simulating device according to the present invention. l...' Turtle power system simulation equipment j@2... Simulation part 3...
Setting section 4...Power system simulation section 5...Simulation operation command input section 6...Polar simulation output section 7...1
b7 Power system state storage device 8...Power system state setting device 9...Simulation start/system state memory 10...Operation signal 11...Output signal 12...7b; Power system 13...Transmission Device it, 1s...
・Flat start data creation device 16... Initial system state storage memory 17... Input/output device 18... External memory Patent applicant Tokyo Shibaura Electric Co., Ltd. Agent Norio Doishi Figure 1 142 Figure 3

Claims (2)

【特許請求の範囲】[Claims] (1)  電力系統の接続状態及び電力需給状況を市。 力系統状態保存装置に入力し、前記電力状態保存装置と
電力系統状態設定装置とによシ系統状態メモリを介して
電力系統状態幅、を模擬する電力系統模擬部に出力する
よう構成された電力系統模擬装置において、上記系統状
態メモリと電力系統模擬部との間にフラットスタートデ
ータ作成装置とこれに続く初期系統状態保存メモリとを
介在せしめ、前記フラットスタートデータ作成装置は模
擬開始時における系統状態lの不足データ、発電力と消
費電力及び送電ロスとによる電力需給不平衡を消滅せし
めるよう予め演算処理がなされることを特徴とする電力
系統模擬装置。
(1) Check the connection status of the power system and the power supply and demand situation. The electric power is configured to be input to a power system state storage device and output to a power system simulating unit that simulates a power system state width via a system state memory that is connected to the power system state storage device and the power system state setting device. In the system simulator, a flat start data creation device and a subsequent initial system state storage memory are interposed between the system state memory and the power system simulator, and the flat start data creation device records the system state at the time of starting the simulation. 1. A power system simulator characterized in that calculation processing is performed in advance so as to eliminate power supply and demand imbalance caused by insufficient data of 1, power generation power, power consumption, and power transmission loss.
(2)初期系統状態保存メモリは入出力装置ヲ介して外
部メモリに接続されることを特徴とする特許請求の範囲
第1項記載の電力系統模擬装置。
(2) The power system simulator according to claim 1, wherein the initial system state storage memory is connected to an external memory via an input/output device.
JP57196550A 1982-11-09 1982-11-09 Power system simulator Pending JPS5986427A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP57196550A JPS5986427A (en) 1982-11-09 1982-11-09 Power system simulator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP57196550A JPS5986427A (en) 1982-11-09 1982-11-09 Power system simulator

Publications (1)

Publication Number Publication Date
JPS5986427A true JPS5986427A (en) 1984-05-18

Family

ID=16359598

Family Applications (1)

Application Number Title Priority Date Filing Date
JP57196550A Pending JPS5986427A (en) 1982-11-09 1982-11-09 Power system simulator

Country Status (1)

Country Link
JP (1) JPS5986427A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63186530A (en) * 1987-01-28 1988-08-02 三菱電機株式会社 Transmission and distribution line simulater
JPS63186531A (en) * 1987-01-28 1988-08-02 三菱電機株式会社 Transmission and distribution line simulater
JPH0241624A (en) * 1988-07-28 1990-02-09 Toshiba Corp Power distribution system simulative test apparatus

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63186530A (en) * 1987-01-28 1988-08-02 三菱電機株式会社 Transmission and distribution line simulater
JPS63186531A (en) * 1987-01-28 1988-08-02 三菱電機株式会社 Transmission and distribution line simulater
JPH0241624A (en) * 1988-07-28 1990-02-09 Toshiba Corp Power distribution system simulative test apparatus

Similar Documents

Publication Publication Date Title
CN106650072B (en) Semi-physical simulation-based virtual grid-connected detection system and method for same generator
CN110909920B (en) Power transmission network capacity planning optimization method and system considering multiple fault scenes
CN109766586A (en) A kind of method and system automatically generating large scale electric network electromagnetic transient simulation model
CN107516895A (en) Power distribution network rapid simulation method, device, storage medium and its computer equipment
CN108493998B (en) Robust power transmission network planning method considering demand response and N-1 expected faults
CN112597633B (en) Power system standby optimization method and system considering multiple fault scenes
CN108899895A (en) A kind of electromechanics-electromagnetism the hybrid simulation method and system of the electric system of UPFC containing THE UPFC
CN112260322B (en) Source network load storage simulation platform, method and system
WO2023103248A1 (en) Automatic device commissioning method, apparatus, device, system, and storage medium
Arrifano et al. Fuzzy stabilization of power systems in a co-generation scheme subject to random abrupt variations of operating conditions
CN107147123A (en) The wide area real time coordination control system of short-term frequency stability
JPS5986427A (en) Power system simulator
Hagmar et al. Impact of static and dynamic load models on security margin estimation methods
CN111952964A (en) Decoupling method of multi-period fault recovery model of power distribution network
CN116914786A (en) Power control method, device, equipment and medium of modularized gravity energy storage system
CN106444424A (en) Microgrid energy management system simulation test platform
CN112906200B (en) Power system energy storage configuration method and device, computer equipment and storage medium
CN113297861A (en) Experimental method and system for evaluating new energy ultimate access capability in synchronous power grid
CN112578276A (en) Relay protection dynamic performance test system
Yin et al. Modeling and Simulation of Medium Voltage Power System of a Ship Type
JP2003274561A (en) System-link control system for distributed power source, and storage medium having program stored for making computer run the program
Toma et al. Participation of the Virtual Power Plants to the frequency control in power systems
CN106651655A (en) Method and device for selecting static security auxiliary decision
Kim et al. Control Strategy of 4-terminal Multi-DC Link Hardware-in-the-loop (HIL) Simulator for Offshore Wind farms
CN117096866A (en) Three-phase distribution network ordered power supply restoration optimization method considering load cold start characteristic