CN107516895A - Power distribution network rapid simulation method and device, storage medium and computer equipment thereof - Google Patents

Power distribution network rapid simulation method and device, storage medium and computer equipment thereof Download PDF

Info

Publication number
CN107516895A
CN107516895A CN201710743617.6A CN201710743617A CN107516895A CN 107516895 A CN107516895 A CN 107516895A CN 201710743617 A CN201710743617 A CN 201710743617A CN 107516895 A CN107516895 A CN 107516895A
Authority
CN
China
Prior art keywords
distribution network
power
power distribution
model
network
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710743617.6A
Other languages
Chinese (zh)
Other versions
CN107516895B (en
Inventor
郭晓斌
李鹏
占恺峤
于力
姜臻
简淦杨
白浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China South Power Grid International Co ltd
Original Assignee
China South Power Grid International Co ltd
Power Grid Technology Research Center of China Southern Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China South Power Grid International Co ltd, Power Grid Technology Research Center of China Southern Power Grid Co Ltd filed Critical China South Power Grid International Co ltd
Priority to CN201710743617.6A priority Critical patent/CN107516895B/en
Publication of CN107516895A publication Critical patent/CN107516895A/en
Application granted granted Critical
Publication of CN107516895B publication Critical patent/CN107516895B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention provides a method, a system, a storage medium and computer equipment for quickly simulating a power distribution network, wherein the method comprises the steps of simulating the power distribution network according to a preset simulation time period and preset key measurement, acquiring power distribution network operation parameters corresponding to the current simulation time, constructing a power distribution network calculation model, carrying out network topology analysis on the power distribution network calculation model to form a power supply hierarchical relationship of the power distribution network, carrying out forward-backward substitution load flow calculation based on the power supply hierarchical relationship of the power distribution network, acquiring a load flow calculation result, returning to the step of acquiring the power distribution network operation parameters corresponding to the current simulation time if the power distribution network operation parameters are not the last time in the preset simulation time period, and carrying out cyclic operation to finally acquire key measurement data for simulating the power distribution network in the preset simulation time period. In the whole process, the operation state of the power distribution network in the change of two dimensions of time and preset key measurement (space) can be simulated rapidly, and rapid simulation of the power distribution network is realized.

Description

Power distribution network rapid simulation method, device, storage medium and its computer equipment
Technical field
The present invention relates to electric power network technical field, more particularly to power distribution network rapid simulation method, device, storage medium And its computer equipment.
Background technology
Power distribution network is near the power network of user, the power supply reliability of power network, power supply quality, power supply in whole electric network composition Amount etc. will be embodied by power distribution network, its network structure whether rationally be determine power distribution network quality height key factor it One.Electric Power Network Planning is the important component of power system overall development plan, and power grid construction and the foundation of transformation, power network The target of planning is exactly to adapt to the development of power network, meet simultaneously appropriate advance socio-economic development demand, and plays it for electricity The guide and decisive action that net is built, operation and power supply ensure.
Due to the development of each domain requirement so that emulation technology is constantly expanded in each domain requirement and needs to improve application layer It is secondary.In addition scientific and technical continuous development, simulation object gradually tends to complexity, diversity, and Simulation Application is advised Mould it is also proposed higher requirement.Distribution end region be directly facing user, be to ensure that supply of electric power quality and enhancing validity operate Key, different from power transmission network, the network connection conversion of power distribution network is more frequent, and part throttle characteristics is also more diversified, in order to Understand influence of the power distribution network wiring conversion to the network operation, power distribution network high-speed simulation will be an important research topic.
The content of the invention
Based on this, it is necessary to for current the problem of there is no power distribution network rapid simulation method, there is provided a kind of power distribution network is quick Emulation mode, device, storage medium and its computer equipment.
A kind of power distribution network rapid simulation method, including step:
According to default emulation period and default crucial measurement, power distribution network is emulated;
Obtain power distribution network operational factor corresponding to the current emulation moment, power distribution network operational factor include initial physical model, Load plan data, changes of operating modes data and equipment alteration data;
According to equipment alteration data and initial physical model, calculation of distribution network model is built;
According to changes of operating modes data, Network topology is carried out to power network computation model, forms power network power supply level Relation;
According to load plan data, based on power network power supply hierarchical relationship, pushed back before progress for Load flow calculation, obtain trend meter Calculate result;
If currently the emulation moment is not the last moment in the default emulation period, using next emulation moment again as current The moment is emulated, returns to the step of obtaining power distribution network operational factor corresponding to the current emulation moment;
According to calculation of tidal current corresponding to each emulation moment in the default emulation period, power distribution network is obtained in default emulation The crucial metric data emulated in period.
A kind of power distribution network high-speed simulation device, including:
Emulation module, for according to emulation period and default crucial measurement is preset, being emulated to power distribution network;
Parameter acquisition module, for obtaining power distribution network operational factor corresponding to the current emulation moment, power distribution network operational factor Including initial physical model, load plan data, changes of operating modes data and equipment alteration data;
Model construction module, for according to equipment alteration data and initial physical model, building calculation of distribution network model;
Topological analysis module, for according to changes of operating modes data, Network topology to be carried out to power network computation model, Form power network power supply hierarchical relationship;
Load flow calculation module, for according to load plan data, based on power network power supply hierarchical relationship, Dai Chao to be pushed back before progress Stream calculation, obtain calculation of tidal current;
Module is returned to, for when the last moment during current emulation moment is for the default emulation period, then by next emulation Moment performs phase as current emulation moment, Controlling model structure module, topological analysis module and Load flow calculation module again It should operate;
As a result statistical module, for the calculation of tidal current according to corresponding to each emulation moment in the default emulation period, obtain Obtain the crucial metric data that power distribution network is emulated within the default emulation period.
Power distribution network rapid simulation method and device of the present invention, according to default emulation period and default crucial measurement, to distribution Net is emulated, and is obtained power distribution network operational factor corresponding to the current emulation moment, structure calculation of distribution network model, power network is calculated Model carries out Network topology, forms power network power supply hierarchical relationship, and based on power network power supply hierarchical relationship, Dai Chao is pushed back before progress Stream calculation, calculation of tidal current is obtained, if not the last moment in the default emulation period, it is corresponding to return to the acquisition current emulation moment Power distribution network operational factor the step of, circulate operation, the final key for obtaining power distribution network and being emulated within the default emulation period Metric data.In whole process, can Fast simulation power distribution network in time and the default crucial change for measuring (space) two dimensions The running status of change, realize to power distribution network high-speed simulation.
In addition, the present invention also provides a kind of computer-readable recording medium, computer program is stored thereon with, the program is located Manage when device performs and realize such as the step of above-mentioned method.
In addition, the present invention also provides a kind of computer equipment, including memory, processor and storage are on a memory and can The computer program run on a processor, realize such as the step of above-mentioned method during computing device program.
Above computer readable storage medium storing program for executing and computer equipment, wherein, power distribution network rapid simulation method being capable of Fast Modular Intend the running status of change of the power distribution network in time and default crucial measurement (space) two dimensions, realize and power distribution network is quickly imitated Very.
Brief description of the drawings
Fig. 1 is the schematic flow sheet of power distribution network rapid simulation method one embodiment of the present invention;
Fig. 2 is the schematic flow sheet of second embodiment of power distribution network rapid simulation method of the present invention;
Fig. 3 is the schematic flow sheet of the one of application example of power distribution network rapid simulation method of the present invention;
Fig. 4 is the structural representation of power distribution network high-speed simulation system one embodiment of the present invention;
Fig. 5 is the structural representation of second embodiment of power distribution network high-speed simulation system of the present invention.
Embodiment
As shown in figure 1, a kind of power distribution network rapid simulation method, including step:
S100:According to default emulation period and default crucial measurement, power distribution network is emulated.
The emulation period is the simulation time section (t that user sets according to current demand1~tM), when user sets emulation starting Carve with emulation finish time, the period between emulation initial time and emulation finish time is to emulate the period.User according to Current demand setting is crucial to be measured, and herein, is directly read default crucial measurement, is formed metric data bivariate table, start imitative It is true to calculate, proceed by emulation cycle calculating.
S200:Power distribution network operational factor corresponding to the current emulation moment is obtained, power distribution network operational factor includes initial physical Model, load plan data, changes of operating modes data and equipment alteration data.
Power distribution network operational factor corresponding to the difference emulation moment is different, herein, after step S100 starts emulation, obtains Power distribution network operational factor corresponding to the current emulation moment is taken, power distribution network operational factor includes initial physical model, load plan number According to, changes of operating modes data and equipment alteration data.Initial physical model can be understood as power distribution network and initially be not in One physical model of running status, this concrete model can obtain according to current power distribution planar network architecture and historical empirical data , this is an initial data, it is however generally that, for identical power distribution network, its initial physical model is identical.Load gauge It is parameter that power distribution network gathers in the process of running to draw data, changes of operating modes data and equipment alteration data, load gauge Drawing data can be become by the load plan curve acquisition of computer drawing, changes of operating modes data by the method for operation To change event table to obtain, equipment alteration data can be obtained by equipment alteration event table, in actual applications, initial physical mould Type, load plan data, changes of operating modes data and equipment alteration data storage are in Machine-Specific Disk, physics mould Type file mainly stores following information equipment ID (keyword), title, type node number, and node 0 is numbered, and node 1 is numbered, node 2 numberings, by node serial number come the network connection relation that embodies.
S300:According to equipment alteration data and initial physical model, calculation of distribution network model is built.
Due to needing to enter initial physical model Mobile state adjustment when equipment alteration data be present, therefore, first root herein Initial physical model is adjusted according to equipment alteration data, changed, based on adjustment, amended initial physical model, structure Calculation of distribution network model.Specifically, computation model mainly includes power supply, bus, switch, load and circuit.No matter physics How complicated types of models is, can be mapped to the computation model of above-mentioned five class.In distribution transforming net, the outlet switch of feeder line typically reflects Power supply is penetrated into, distribution transforming is mapped to load, and overhead line and cable are mapped as circuit, pole-mounted circuit breaker, on-load switch, fuse, knife Switch tool inside lock and ring main unit is all mapped to the internal commonly connected device map such as switch, ring main unit, feeder pillar Into bus.
S400:According to changes of operating modes data, Network topology is carried out to power network computation model, forms power network power supply Hierarchical relationship.
The change of the method for operation can change power network power supply hierarchical relationship, therefore, herein according to changes of operating modes data, Network topology is carried out to power network computation model, forms power network power supply hierarchical relationship.
As shown in Fig. 2 in one of the embodiments, step S400 includes step:
S420:The annexation between each composition model in power network computation model is identified, generates topological island, composition model bag Include power source model, bus model, switch models, load model and circuit model;
S440:According to changes of operating modes data, the location status of switch models is obtained;
S460:In each topological island, according to the location status of switch models, topology point is carried out to power network computation model Analysis, form power network power supply hierarchical relationship.
Specifically, topological island is generated according to the annexation of computation model first, in each topological island, according to opening The location status of model is closed, topological analysis is carried out to computation model, because power distribution network is the radiation method of operation, with each power supply For root node, one " power supply level relational tree " can be formed, and power supply, load, bus are made as node, switch and circuit For branch, formed node father and elder brothers' subrelation and node with branch mapping relations, form power network power supply hierarchical relationship, subsequently Load flow calculation is carried out on the basis of tree again.
S500:According to load plan data, based on power network power supply hierarchical relationship, push back for Load flow calculation, obtain before progress Calculation of tidal current.
Load plan can influence whole calculation of tidal current, therefore, need herein according to load plan data, based on electricity Net power supply hierarchical relationship, pushes back for Load flow calculation before progress, obtains calculation of tidal current.Specifically, formed in step S400 On the basis of power network power supply hierarchical relationship, Load flow calculation is carried out according to load plan data, using the algorithm for before pushing back generation, according to Node power calculates the voltage of each node and the power current of branch.
S600:If currently the emulation moment is not the last moment in the default emulation period, next emulation moment is made again For current emulation moment, return to step S200;
Judge whether current emulation moment t is the default emulation period (t1~tM) in last moment tM, if it is not, then by under One emulation moment t+1 is again as current emulation moment, return to step S200.It is non-essential, if so, then stopping return to step S200, into step S700.Such as the default emulation period be 9 points 30 minutes to 10 points, once emulated every 1 minute, if ought The preceding emulation moment be 9 points 45 minutes, it is not the last moment in the default emulation period, by 9: 46 be allocated as new current emulation when Carve, return to step S200;If currently 10 points of the moment of emulation, it is the last moment in the default emulation period, then stops return to step S200, into step S700.
S700:According to calculation of tidal current corresponding to each emulation moment in the default emulation period, power distribution network is obtained pre- If the crucial metric data emulated in the emulation period.
Calculation of tidal current corresponding to each emulation moment in the default emulation period is obtained after step S600 circular treatments, Obtain the crucial metric data that power distribution network is emulated within the default emulation period.As described above, crucial metric data can To be characterized using bivariate table.For each emulation moment, the current critical quantity for emulating the moment is obtained according to calculation of tidal current Measured value, the row according to corresponding to the current emulation moment is converted into crucial measurement bivariate table, line information corresponding to renewal.It is inessential , the operation trend curve of some measurement can also can be obtained by row extraction according to the crucial measurement bivariate table of record, is carried by row The operation profile data at a certain emulation moment can be obtained by taking.
Power distribution network rapid simulation method of the present invention, according to default emulation period and default crucial measurement, power distribution network is carried out Emulation, power distribution network operational factor corresponding to the current emulation moment is obtained, structure calculation of distribution network model, power network computation model is entered Row Network topology, power network power supply hierarchical relationship is formed, based on power network power supply hierarchical relationship, pushed back before progress for trend meter Calculate, obtain calculation of tidal current, if not the last moment in the default emulation period, return to obtain and match somebody with somebody corresponding to the current emulation moment The step of operation of power networks parameter, circulate operation, the key that final acquisition power distribution network is emulated within the default emulation period measure Data.In whole process, can Fast simulation power distribution network in time and the default crucial change for measuring (space) two dimensions Running status, realize to power distribution network high-speed simulation.
In one of the embodiments, according to equipment alteration data and initial physical model, calculation of distribution network mould is built The step of type, includes:
Step 1:According to power distribution network operational factor corresponding to the current emulation moment, judge that the current emulation moment whether there is Equipment alteration data;
Step 2:If being not present, according to initial physical model, calculation of distribution network model is built;
Step 3:If in the presence of, according to equipment alteration data, initial physical model is changed, and according to amended initial Physical model, build calculation of distribution network model.
In one of the embodiments, according to changes of operating modes data, network topology point is carried out to power network computation model The step of analysing, forming power network power supply hierarchical relationship includes:
Step 1:According to changes of operating modes data, judge that the current emulation moment whether there is position of the switch situation of change;
Step 2:If in the presence of, according to position of the switch situation of change, Network topology is carried out to power network computation model, Form power network power supply hierarchical relationship.
In one of the embodiments, according to load plan data, based on power network power supply hierarchical relationship, generation is pushed back before progress Load flow calculation, obtain calculation of tidal current the step of include:
Step 1:According to carry calculation data, judge that the current emulation moment whether there is load variations situation;
Step 2:If in the presence of according to load variations situation, being powered hierarchical relationship based on power network, Dai Chao pushed back before progress Stream calculation, obtain calculation of tidal current.
For the technical scheme and its effect of power distribution network rapid simulation method of the present invention is further explained in detail, will use below 2 concrete application examples are illustrated further.
Embodiment one
Using the system of power distribution network rapid simulation method of the present invention, after electrifying startup, operations described below is performed:
1st, read in original physical model, load plan curve, changes of operating modes event table, equipment alteration event table with And Simulation Control information.Specifically, physical model, load plan curve, changes of operating modes event table, equipment alteration event Table stores special disk file.Physical model file mainly stores following information equipment ID (keyword), title, type node Number, node 0 are numbered, and node 1 is numbered, and node 2 is numbered.By node serial number come the network connection relation that embodies.
2nd, power network computation model is formed according to physical model.Specifically, program is generated automatically according to physical model and calculated Model:Form the computation model of power supply, bus, switch, load and circuit.Specifically, computation model mainly includes power supply, Bus, switch, load and circuit.No matter how complicated physical model type is, can be mapped to the computation model of above-mentioned five class. In distribution transforming net:The outlet switch of feeder line is typically mapped to power supply, and distribution transforming is mapped to load, and overhead line and cable are mapped as line Road.Switch tool inside pole-mounted circuit breaker, on-load switch, fuse, disconnecting link and ring main unit is all mapped to switch, ring main unit, The internal commonly connected device map such as feeder pillar is into bus.
3rd, Network topology is carried out, forms power network power supply hierarchical relationship.Program carries out topological analysis calculating automatically.Formed Topological island and trend tree.Specifically, topological island is generated according to the annexation of computation model first.In each topological island, According to the location status of switch models, topological analysis is carried out to computation model, because power distribution network is the radiation method of operation, with each Individual power supply is root node, can be formed one " power supply level relational tree ".And power supply, load, bus as node, switch and Circuit is as branch.Formed node father and elder brothers' subrelation and node with branch mapping relations.Tide is carried out on the basis of tree Stream calculation, behind referred to as " trend tree ".
4th, Load flow calculation, pushed back before being carried out on the basis of power network powers hierarchical relationship for Load flow calculation.Program is directed to automatically Trend tree carries out Load flow calculation.Specifically, Load flow calculation is carried out on the basis of step (3), using the algorithm for before pushing back generation, root The voltage of each node and the power current of branch are calculated according to node power.By physical model and the corresponding relation of computation model, The running status of whole power network can be obtained.
5th, start to emulate, the emulation period is set, the crucial process data memory space for measuring and constructing association and measure is set. Specifically, the crucial process data measured uses user-defined file.Using user-defined file, csv file.It is on number Arranged according to the bivariate table of value:The emulation moment is represented, with row:Represent data label.Data label is defined as follows:Data label is one Individual character string:Device type _ device id _ terminal _ data type, device type definition:Busbar buses, cb switches, line lines Road, load loads, gen generators, terminal:The single-ended equipment in the end of 1 head end 2 all writes 1;Dtd--data type definition:I electric currents, p is active, q Idle, pj line ends are active, and qj line ends are idle, s on off states, flt Reflectors, u voltages.Key is measured by artificial Selection, it can typically select the voltage of important distribution transforming, feeder line outlet power, the electric current of important line, the position mainly switched.
6th, according to network connection change events table, judge whether the emulation moment has mode of connection change, have, enter first Row physical model is changed.Then step 2,3,4 operation are carried out.Specifically, the local nodes of use regenerate method, root The node serial number of relevant device is only changed according to unusual fluctuation event description.
7th, according to changes of operating modes event table, judge whether the emulation moment has changes of operating modes, have, walked Rapid 3,4 operation.Specifically, judge the topological island that the switch of changes of operating modes is located at, to open up the topological island again Analysis is flutterred, forms trend tree.
8th, according to load plan curve, judge whether the emulation moment there are load variations, there is the operation for then carrying out step 4. Judge the trend tree belonging to varying loading, Load flow calculation again is carried out to the trend tree.
9th, according to the result of Load flow calculation, the crucial data measured are recorded.Current imitate is obtained according to calculation of tidal current The crucial measuring value at true moment, the row according to corresponding to the current emulation moment is converted into crucial measurement bivariate table.Corresponding to renewal Line information.
10th, the last moment set to emulation is judged whether, no, then renewal emulates the moment.Return to step 6;It is then to emulate Terminate.The process data measured according to key carries out checking the data section at any emulation moment and the operation trend of any measurement Curve.The operation trend curve of some measurement can be obtained by row extraction according to the crucial measurement bivariate table of record, can by row extraction To obtain the operation profile data at certain a moment.
Embodiment two, as shown in figure 3, power distribution network rapid simulation method of the present invention comprises the following steps:
1st, simulation operations are proceeded by, read physical model, load plan, changes of operating modes and unusual fluctuation text are set Part.
2nd, computation model, topological analysis, Load flow calculation are generated according to the physical model of power distribution network.
3rd, first time simulation calculation is determined whether, if so, then entering step 4, if otherwise entering step 5.
4th, crucial metric data bivariate table is created.
5th, simulated events are handled:Equipment alteration, changes of operating modes, load plan.
6th, modification measures bivariate table information.
7th, the initial section of Load flow calculation next time is updated.
8th, last time simulation calculation is determined whether, if so, then enter step 9, if it is not, into step 10.
9th, limit information is got in output.
10th, next trend section calculation whether is started, if so, then return to step 3, if otherwise entering step 11.
11st, trend section file is preserved.
12nd, trend Query Result is formed.
As shown in figure 4, a kind of power distribution network high-speed simulation device, including:
Emulation module 100, for according to emulation period and default crucial measurement is preset, being emulated to power distribution network;
Parameter acquisition module 200, for obtaining power distribution network operational factor corresponding to the current emulation moment, distribution network operation ginseng Number includes initial physical model, load plan data, changes of operating modes data and equipment alteration data;
Model construction module 300, for according to equipment alteration data and initial physical model, building calculation of distribution network mould Type;
Topological analysis module 400, for according to changes of operating modes data, network topology point to be carried out to power network computation model Analysis, form power network power supply hierarchical relationship;
Load flow calculation module 500, for according to load plan data, based on power network power supply hierarchical relationship, being pushed back before progress For Load flow calculation, calculation of tidal current is obtained;
Module 600 is returned to, for when the current emulation moment is to preset the last moment in the emulation period, then next will imitate The true moment is again as current emulation moment, Controlling model structure module 300, topological analysis module 400 and Load flow calculation 500 Module performs corresponding operating;
As a result statistical module 700, calculation of tidal current corresponding to the moment is emulated for each in the basis default emulation period, Obtain the crucial metric data that power distribution network is emulated within the default emulation period.
Power distribution network high-speed simulation device of the present invention, emulation module 100 are right according to default emulation period and default crucial measurement Power distribution network is emulated, and parameter acquisition module 200 obtains power distribution network operational factor corresponding to the current emulation moment, model construction mould Block 300 builds calculation of distribution network model, and topological analysis module 400 carries out Network topology to power network computation model, forms electricity Net power supply hierarchical relationship, Load flow calculation module 500 are based on power network power supply hierarchical relationship, push back for Load flow calculation, obtain before progress Calculation of tidal current, if not the last moment in the default emulation period, return to the Controlling model of module 600 structure module 300, topology Analysis module 400 and the module of Load flow calculation 500 perform corresponding operating, circulate operation, the as a result acquisition of statistical module 700 power distribution network The crucial metric data emulated within the default emulation period.In whole process, can Fast simulation power distribution network in the time and The running status of the default crucial change for measuring (space) two dimensions, is realized to power distribution network high-speed simulation.
In one of the embodiments, topological analysis module:
Judging unit, for according to changes of operating modes data, judging that the current emulation moment becomes with the presence or absence of the position of the switch Change situation;
Analytic unit, for when currently the emulation moment has position of the switch situation of change, changing feelings according to the position of the switch Condition, Network topology is carried out to power network computation model, form power network power supply hierarchical relationship.
As shown in figure 5, in one of the embodiments, topological analysis module 400 includes:
Recognition unit 420, for identifying the annexation in power network computation model between each composition model, generation topology Island, composition model include power source model, bus model, switch models, load model and circuit model;
Location status acquiring unit 440, for according to changes of operating modes data, obtaining the location status of switch models;
Topology analysis units 460, in each topological island, according to the location status of switch models, calculating power network Model carries out topological analysis, forms power network power supply hierarchical relationship.
In addition, the present invention also provides a kind of computer-readable recording medium, computer program is stored thereon with, the program is located Manage when device performs and realize such as the step of above-mentioned method.
In addition, the present invention also provides a kind of computer equipment, including memory, processor and storage are on a memory and can The computer program run on a processor, realize such as the step of above-mentioned method during computing device program.
Above computer readable storage medium storing program for executing and computer equipment, wherein, power distribution network rapid simulation method being capable of Fast Modular Intend the running status of change of the power distribution network in time and default crucial measurement (space) two dimensions, realize and power distribution network is quickly imitated Very.
Above example only expresses the several embodiments of the present invention, and its description is more specific and detailed, but can not Therefore it is construed as limiting the scope of the patent.It should be pointed out that for the person of ordinary skill of the art, On the premise of not departing from present inventive concept, various modifications and improvements can be made, these belong to protection scope of the present invention. Therefore, the protection domain of patent of the present invention should be determined by the appended claims.

Claims (10)

1. a kind of power distribution network rapid simulation method, it is characterised in that including step:
According to default emulation period and default crucial measurement, power distribution network is emulated;
Obtain power distribution network operational factor corresponding to the current emulation moment, the power distribution network operational factor include initial physical model, Load plan data, changes of operating modes data and equipment alteration data;
According to the equipment alteration data and the initial physical model, calculation of distribution network model is built;
According to the changes of operating modes data, Network topology is carried out to the power network computation model, forms power network power supply Hierarchical relationship;
According to the load plan data, based on power network power supply hierarchical relationship, pushed back before progress for Load flow calculation, obtain tide Stream calculation result;
If currently the emulation moment is not the last moment in the default emulation period, using next emulation moment again as current The moment is emulated, returns to the acquisition currently corresponding to the emulation moment the step of power distribution network operational factor;
According to the calculation of tidal current corresponding to each emulation moment in the default emulation period, power distribution network is obtained in default emulation The crucial metric data emulated in period.
2. power distribution network rapid simulation method according to claim 1, it is characterised in that described according to the equipment alteration number According to this and the initial physical model, the step of building calculation of distribution network model includes:
According to power distribution network operational factor corresponding to the current emulation moment, judge that the current emulation moment whether there is equipment alteration number According to;
If being not present, according to initial physical model, calculation of distribution network model is built;
If in the presence of, according to equipment alteration data, the initial physical model is changed, and according to the amended initial physical Model, build calculation of distribution network model.
3. power distribution network rapid simulation method according to claim 1, it is characterised in that described to be become according to the method for operation The step of changing data, Network topology is carried out to the power network computation model, forming power network power supply hierarchical relationship includes:
According to the changes of operating modes data, judge that the current emulation moment whether there is position of the switch situation of change;
If in the presence of according to the position of the switch situation of change, to power network computation model progress Network topology, formation Power network power supply hierarchical relationship.
4. power distribution network rapid simulation method according to claim 1, it is characterised in that described according to the load plan number According to the step of being powered hierarchical relationship based on the power network, being pushed back before progress for Load flow calculation, obtain calculation of tidal current is included:
According to the carry calculation data, judge that the current emulation moment whether there is load variations situation;
If in the presence of, according to load variations situation, based on power network power supply hierarchical relationship, pushed back before progress for Load flow calculation, Obtain calculation of tidal current.
5. power distribution network rapid simulation method according to claim 1, it is characterised in that described to be become according to the method for operation The step of changing data, Network topology is carried out to the power network computation model, forming power network power supply hierarchical relationship includes:
The annexation between each composition model in the power network computation model is identified, generates topological island, the composition model bag Include power source model, bus model, switch models, load model and circuit model;
According to the changes of operating modes data, the location status of the switch models is obtained;
In each topological island, according to the location status of the switch models, topological analysis is carried out to the power network computation model, Form power network power supply hierarchical relationship.
A kind of 6. power distribution network high-speed simulation device, it is characterised in that including:
Emulation module, for according to emulation period and default crucial measurement is preset, being emulated to power distribution network;
Parameter acquisition module, for obtaining power distribution network operational factor corresponding to the current emulation moment, the power distribution network operational factor Including initial physical model, load plan data, changes of operating modes data and equipment alteration data;
Model construction module, for according to the equipment alteration data and the initial physical model, building calculation of distribution network Model;
Topological analysis module, for according to the changes of operating modes data, network topology to be carried out to the power network computation model Analysis, form power network power supply hierarchical relationship;
Load flow calculation module, for according to the load plan data, based on power network power supply hierarchical relationship, being pushed back before progress For Load flow calculation, calculation of tidal current is obtained;
Return module, for when currently emulation the moment for it is described it is default emulation the period in the last moment when, then by next emulation Moment controls the model construction module, the topological analysis module and the trend meter as the current emulation moment again Calculate module and perform corresponding operating;
As a result statistical module, for the calculation of tidal current according to corresponding to each emulation moment in the default emulation period, obtain Obtain the crucial metric data that power distribution network is emulated within the default emulation period.
7. power distribution network high-speed simulation device according to claim 6, it is characterised in that the topological analysis module:
Judging unit, for according to the changes of operating modes data, judging that the current emulation moment becomes with the presence or absence of the position of the switch Change situation;
Analytic unit, for when currently the emulation moment has position of the switch situation of change, changing feelings according to the position of the switch Condition, Network topology is carried out to the power network computation model, form power network power supply hierarchical relationship.
8. power distribution network high-speed simulation device according to claim 6, it is characterised in that the topological analysis module includes:
Recognition unit, for identifying the annexation in the power network computation model between each composition model, generate topological island, institute Stating composition model includes power source model, bus model, switch models, load model and circuit model;
Location status acquiring unit, for according to the changes of operating modes data, obtaining the location status of the switch models;
Topology analysis units, in each topological island, according to the location status of the switch models, calculating the power network Model carries out topological analysis, forms power network power supply hierarchical relationship.
9. a kind of computer-readable recording medium, is stored thereon with computer program, it is characterised in that the program is held by processor The step of any one methods described in such as claim 1-6 is realized during row.
10. a kind of computer equipment, including memory, processor and storage can be run on a memory and on a processor Computer program, it is characterised in that realized during the computing device described program as described in any one in claim 1-6 The step of method.
CN201710743617.6A 2017-08-25 2017-08-25 Power distribution network rapid simulation method and device, storage medium and computer equipment thereof Active CN107516895B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710743617.6A CN107516895B (en) 2017-08-25 2017-08-25 Power distribution network rapid simulation method and device, storage medium and computer equipment thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710743617.6A CN107516895B (en) 2017-08-25 2017-08-25 Power distribution network rapid simulation method and device, storage medium and computer equipment thereof

Publications (2)

Publication Number Publication Date
CN107516895A true CN107516895A (en) 2017-12-26
CN107516895B CN107516895B (en) 2019-09-27

Family

ID=60724348

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710743617.6A Active CN107516895B (en) 2017-08-25 2017-08-25 Power distribution network rapid simulation method and device, storage medium and computer equipment thereof

Country Status (1)

Country Link
CN (1) CN107516895B (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108763665A (en) * 2018-05-14 2018-11-06 北京科东电力控制系统有限责任公司 Grid simulation analyzes date storage method and device
CN109657959A (en) * 2018-12-12 2019-04-19 国家电网有限公司 A kind of distribution network planning calculation and analysis methods containing multivariate data
CN109657395A (en) * 2018-12-29 2019-04-19 中国电力科学研究院有限公司 A kind of customized configuration method of grid simulation, terminal, server and system
CN111952959A (en) * 2020-07-14 2020-11-17 北京科东电力控制系统有限责任公司 Method and device for compressing power grid process simulation time and storage medium
CN112364531A (en) * 2021-01-13 2021-02-12 长沙树根互联技术有限公司 Compound model construction method and device, electronic equipment and storage medium
CN112560227A (en) * 2020-11-25 2021-03-26 国网河北省电力有限公司 Simulation rehearsal method for power grid dispatching day-ahead plan
CN113258578A (en) * 2021-06-16 2021-08-13 北京德风新征程科技有限公司 Power flow data generation method and device, electronic equipment and computer readable medium
CN113872210A (en) * 2021-10-14 2021-12-31 广东电网有限责任公司 Power grid key section tide checking method and device
CN114268125A (en) * 2021-11-25 2022-04-01 国网山东省电力公司青岛供电公司 Power grid operation simulation data maintenance, result and simulation system and optimization method
CN114336587A (en) * 2021-11-15 2022-04-12 南京四方亿能电力自动化有限公司 Power distribution network simulation method
CN114629767A (en) * 2020-11-26 2022-06-14 中国南方电网有限责任公司 Power dispatching network simulation method and device, computer equipment and storage medium
CN114676569A (en) * 2022-03-24 2022-06-28 中国电力科学研究院有限公司 Power grid simulation analysis example, and generation method, generation system, equipment and medium thereof
WO2022160719A1 (en) * 2021-01-29 2022-08-04 中国电力科学研究院有限公司 Eye movement device-based intelligent power flow analysis method and apparatus

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103248059A (en) * 2013-05-07 2013-08-14 广东电网公司电力科学研究院 Reactive voltage optimization method and system for distribution network
CN103778484A (en) * 2014-02-18 2014-05-07 国家电网公司 Grid connection type micro-grid optimizing configuration method and system
CN105048517A (en) * 2015-08-19 2015-11-11 国家电网公司 Multistage energy coordination control system
JP2016045285A (en) * 2014-08-21 2016-04-04 国立大学法人信州大学 Learning aid system for mechanism of electric power transmission networks

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103248059A (en) * 2013-05-07 2013-08-14 广东电网公司电力科学研究院 Reactive voltage optimization method and system for distribution network
CN103778484A (en) * 2014-02-18 2014-05-07 国家电网公司 Grid connection type micro-grid optimizing configuration method and system
JP2016045285A (en) * 2014-08-21 2016-04-04 国立大学法人信州大学 Learning aid system for mechanism of electric power transmission networks
CN105048517A (en) * 2015-08-19 2015-11-11 国家电网公司 Multistage energy coordination control system

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
于力 等: "基于RTDS的有源配电网暂态实时仿真与分析", 《电力系统及其自动化学报》 *
王建玲: "地区配电网数字化仿真与网络拓扑系统的研究", 《山东电机工程学会第四届供电专业学术交流会论文集》 *

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108763665B (en) * 2018-05-14 2020-11-03 北京科东电力控制系统有限责任公司 Power grid simulation analysis data storage method and device
CN108763665A (en) * 2018-05-14 2018-11-06 北京科东电力控制系统有限责任公司 Grid simulation analyzes date storage method and device
CN109657959A (en) * 2018-12-12 2019-04-19 国家电网有限公司 A kind of distribution network planning calculation and analysis methods containing multivariate data
CN109657395A (en) * 2018-12-29 2019-04-19 中国电力科学研究院有限公司 A kind of customized configuration method of grid simulation, terminal, server and system
CN111952959A (en) * 2020-07-14 2020-11-17 北京科东电力控制系统有限责任公司 Method and device for compressing power grid process simulation time and storage medium
CN111952959B (en) * 2020-07-14 2023-10-13 北京科东电力控制系统有限责任公司 Method, device and storage medium for compressing power grid process simulation time
CN112560227A (en) * 2020-11-25 2021-03-26 国网河北省电力有限公司 Simulation rehearsal method for power grid dispatching day-ahead plan
CN114629767A (en) * 2020-11-26 2022-06-14 中国南方电网有限责任公司 Power dispatching network simulation method and device, computer equipment and storage medium
CN112364531A (en) * 2021-01-13 2021-02-12 长沙树根互联技术有限公司 Compound model construction method and device, electronic equipment and storage medium
CN112364531B (en) * 2021-01-13 2021-03-30 长沙树根互联技术有限公司 Compound model construction method and device, electronic equipment and storage medium
WO2022160719A1 (en) * 2021-01-29 2022-08-04 中国电力科学研究院有限公司 Eye movement device-based intelligent power flow analysis method and apparatus
CN113258578A (en) * 2021-06-16 2021-08-13 北京德风新征程科技有限公司 Power flow data generation method and device, electronic equipment and computer readable medium
CN113258578B (en) * 2021-06-16 2021-10-15 北京德风新征程科技有限公司 Power flow data generation method and device, electronic equipment and computer readable medium
CN113872210A (en) * 2021-10-14 2021-12-31 广东电网有限责任公司 Power grid key section tide checking method and device
CN114336587A (en) * 2021-11-15 2022-04-12 南京四方亿能电力自动化有限公司 Power distribution network simulation method
CN114268125A (en) * 2021-11-25 2022-04-01 国网山东省电力公司青岛供电公司 Power grid operation simulation data maintenance, result and simulation system and optimization method
CN114268125B (en) * 2021-11-25 2024-07-26 国网山东省电力公司青岛供电公司 Power grid operation simulation data maintenance, result, simulation system and optimization method
CN114676569A (en) * 2022-03-24 2022-06-28 中国电力科学研究院有限公司 Power grid simulation analysis example, and generation method, generation system, equipment and medium thereof

Also Published As

Publication number Publication date
CN107516895B (en) 2019-09-27

Similar Documents

Publication Publication Date Title
CN107516895B (en) Power distribution network rapid simulation method and device, storage medium and computer equipment thereof
CN105932666A (en) Complex distribution network multi-time-scale digital-analog hybrid simulation system and simulation method therefor
CN104598671B (en) A kind of digital electric network construction method based on online data
CN106650072A (en) Detecting system and method for virtual synchronous generator grid connection based on hardware-in-the-loop simulation
CN103150426A (en) Unified modeling method for regulation and control integrated simulation of primary grid equipment and secondary grid equipment
CN103700036B (en) A kind of transient stability projecting integral method being suitable to power system Multiple Time Scales
CN103248127B (en) Multi-space-time navigating power system restoration decision support system and restoration decision method
CN108241771A (en) Secondary device modeling method based on electromagnetic transient simulation platform
CN112260322B (en) Source network load storage simulation platform, method and system
CN109145362A (en) A kind of power network modeling method and system
CN108879667B (en) Power grid closed-loop control power flow simulation method
CN112287540B (en) Electromagnetic transient joint simulation method for accessing wind power plant to power grid
CN107480432A (en) A kind of load decomposition method based on cloud platform
CN103678798B (en) It is a kind of for the electro-magnetic transient real-time emulation method containing distributed power distribution network
Schütte Simulation model composition for the large-scale analysis of smart grid control mechanisms
CN101867192B (en) Reactive compensation control simulation test system
CN103605293B (en) A kind of substation relay protection emulation test system and emulation test method thereof
Bai et al. Automatic modeling and optimization for the digital twin of a regional multi-energy system
CN103777092A (en) Cloud technology based relay protection test system and method
CN105373008A (en) Full physics model simulation method for electric power system
CN110389535A (en) A kind of configuration type simulation test system and its test method
CN108520105A (en) A kind of active power distribution network multi tate real-time emulation method based on FPGA
CN105808825B (en) A kind of roller accidental projection integration method suitable for active power distribution network dynamic simulation
Coignard et al. CyDER-a co-simulation platform for grid analysis and planning for high penetration of distributed energy resources
CN104881822A (en) Evaluation method, device and system

Legal Events

Date Code Title Description
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210615

Address after: 510700 3rd, 4th and 5th floors of building J1 and 3rd floor of building J3, No.11 Kexiang Road, Science City, Luogang District, Guangzhou City, Guangdong Province

Patentee after: China South Power Grid International Co.,Ltd.

Address before: 510663 3 building, 3, 4, 5 and J1 building, 11 building, No. 11, Ke Xiang Road, Luogang District Science City, Guangzhou, Guangdong.

Patentee before: China South Power Grid International Co.,Ltd.

Patentee before: POWER GRID TECHNOLOGY RESEARCH CENTER. CHINA SOUTHERN POWER GRID