JPS5967495A - Method of constructing atomic power facility - Google Patents

Method of constructing atomic power facility

Info

Publication number
JPS5967495A
JPS5967495A JP57178944A JP17894482A JPS5967495A JP S5967495 A JPS5967495 A JP S5967495A JP 57178944 A JP57178944 A JP 57178944A JP 17894482 A JP17894482 A JP 17894482A JP S5967495 A JPS5967495 A JP S5967495A
Authority
JP
Japan
Prior art keywords
building
construction
constructing
unit
ceiling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP57178944A
Other languages
Japanese (ja)
Other versions
JPS646426B2 (en
Inventor
石原 俊治
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP57178944A priority Critical patent/JPS5967495A/en
Publication of JPS5967495A publication Critical patent/JPS5967495A/en
Publication of JPS646426B2 publication Critical patent/JPS646426B2/ja
Granted legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Crystals, And After-Treatments Of Crystals (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔発明の技術分野〕 本発明は原子力設備の建設工法に係り、特に原子炉格納
容器(以下pcvと称す)を囲む生体遮蔽壁(以下SW
と称す)に隣接している主蒸気管(以下MSと称す)ト
ンネル室の建築工事、およびMS)ンネル室内の原子炉
給水系(以下FDWと称す) 、 M S系の配管石と
その架台の据伺工事に適用するのに好適な原子力設備j
の建設工法に関する。
[Detailed Description of the Invention] [Technical Field of the Invention] The present invention relates to a construction method for nuclear power facilities, and in particular to a biological shielding wall (hereinafter referred to as SW) surrounding a nuclear reactor containment vessel (hereinafter referred to as PCV).
construction work of the main steam pipe (hereinafter referred to as MS) tunnel room adjacent to Nuclear equipment suitable for use in construction work
Concerning construction methods.

〔発明の技術的背景〕[Technical background of the invention]

第1図および第2図に示すように、MS)ンネル室/は
原子炉建屋a内のPOV、?を囲む5w1Iに隣接して
設けられており、このMS)ンネル室/内には、第2図
および第3図に示すようにPCV貫通%ils、M S
第コ弁6a、FDW第β弁6b、共用架台7、MS第J
弁ga、FDW第3弁t b、配管?、POV貫通管ベ
ローズ10、配管アンカー/ハおよびPOV貝1】貿′
内配管/、2等のFDW。
As shown in Figures 1 and 2, MS) tunnel room/ is a POV in reactor building a, ? The PCV penetration %ils, MS
Co-valve 6a, FDW β-valve 6b, common pedestal 7, MS J
Valve ga, FDW third valve t b, piping? , POV penetration pipe bellows 10, piping anchor/c and POV shell 1] trade'
Internal piping/, 2nd class FDW.

MS系の配管類およびその架台が据付けられている。MS system piping and its stand have been installed.

ところで従来、この稲の原子力設備を建設する場合には
、第q Mlないし第を図および第7図(a)に示す手
順により行なわれている。
Conventionally, when constructing this nuclear power facility for rice, the steps qMl to No. 1 are carried out according to the procedure shown in Fig. 7 and Fig. 7(a).

すなわち、まずMS)ンネル室lの床が施工され、次に
壁が施工され、最後に天井が施工される。
That is, first the floor of the tunnel room l is constructed, then the walls are constructed, and finally the ceiling is constructed.

そしてMSトンネル室/の建染工事が完了した後建屋明
渡しとなり、その後前記配管部等の枦椋側の施工が開始
される。これは天井部のコンクリート拐股後の養生期間
中、第9図に示すようにMSトンネル室l内に天井部の
荷重を支える支保工/3が立てられており、支保工/3
の撤去後で々ければ配管類等を搬入することができない
ためである。
After the construction work for the MS tunnel room is completed, the building will be vacated, and the construction of the piping section and other parts on the side of the building will begin. This is because during the curing period after concrete is removed from the ceiling, shoring/3 is erected inside the MS tunnel room l to support the load of the ceiling, as shown in Figure 9.
This is because piping etc. cannot be brought in until after the removal of the pipes.

建屋明渡しを受けると、第S図に示すように配管9 、
 M S gp、コ弁乙a、MS第3弁g a 、 F
DW第コ弁Ab、FDW第3弁rb、および共用架台7
をMSトンネル室/内に搬入する。
When the building is vacated, the piping 9, as shown in Figure S,
MS gp, Koben Otsu a, MS 3rd valve g a, F
DW third valve Ab, FDW third valve rb, and common stand 7
into the MS tunnel room/inside.

次いで、紀6図に示すようにまずpcv貫通貫通管間先
加工を行なってpcv貫通管ベローズ10を取付け、そ
の後POV其通管内配管7.2との溶接および両箱λ弁
Aa、Abの取付けを行なう。
Next, as shown in Fig. 6, the end of the PCV penetration pipe is first processed and the PCV penetration pipe bellows 10 is installed, and then the POV penetration pipe internal piping 7.2 is welded and both box lambda valves Aa and Ab are installed. Do the following.

次いで、共用架台7を据付けるとともに、両第2弁4a
、Abと両第3弁ga、g’oとの間の配管9を据利け
、その後両温3弁ga、gbの取付けおよび配管りを共
用架台7に固定するための配管アンカー//の取付けを
行なう。そしてその後、両第3弁ga、g’oとの取り
合い配管の施工を行々う。
Next, the common pedestal 7 is installed, and both second valves 4a are installed.
, Ab and both the third valves ga and g'o are installed, and then the three temperature valves ga and gb are installed and the piping anchors for fixing the piping to the common frame 7 are installed. Perform installation. After that, the connecting piping with both third valves ga and g'o will be constructed.

〔背景技術の問題点〕[Problems with background technology]

シ上説明した従来の建設工法では、建屋明渡しを受けた
せ2で々ければ機械側の工事に着手することができず、
しかも機械側の工事に当っては、まず各部品をそれぞれ
MSトンネル室内に搬入し、その後MS)ンネル室内で
これらを1付は据付けを行なっている。このため、工事
工程が長期になり工数も増大し、甘だ機械側が現g施工
のため品質が低下するおそれがある。
With the conventional construction method explained above, it is not possible to start construction on the machinery side until the building is vacated within 2 days.
Moreover, when carrying out construction work on the machine side, each part is first transported into the MS tunnel room, and then one of these parts is installed inside the MS tunnel room. For this reason, the construction process becomes long, the number of man-hours increases, and there is a risk that the quality will deteriorate because the machinery is not working properly.

〔発明の目的〕[Purpose of the invention]

本発明はかかる現況に鋳みなされたもので、工期の大中
1f1な知縮と松)棹側の品質の向上とを図ることがで
きる原子力設備の建設工法を提供することを目的とする
The present invention was developed in view of the current situation, and an object thereof is to provide a construction method for nuclear power facilities that can shorten the construction period and improve the quality of the construction period.

〔発明の概要〕[Summary of the invention]

本発明は、建屋内に折付けられる配管、弁およびこれら
の架台を予め一体に糾付けてユニメト化し、これにより
機械側の品質向上なし1す、甘だ原子炉建屋の床および
壁の建設後前記ユニットを建屋内に搬入して架台を掘伺
け、次いで前記屋と架台との間に、H,tと架台のみで
支持されて天井の埋め殺し型枠を4パ−成する仕切板を
配fff+シ、次いで天井側の工事とユニット側の工部
とを並行して行ない、こねにより大幅な工期の短縮およ
び工数の低減を図るようにしたことを特徴とする。
The present invention is to make the pipes, valves, and their mounts that are folded into the building into a unitary structure by pre-tapping them together, thereby improving the quality of the machinery. The unit was carried into the building and the frame was dug out, and then a partition plate was installed between the building and the frame, supported only by H, T and the frame to form a 4-part ceiling filling form. It is characterized by the fact that the construction work on the ceiling side and the construction work on the unit side are carried out in parallel, and the kneading process significantly shortens the construction period and reduces the number of man-hours.

〔発明の実施例〕[Embodiments of the invention]

以下本発明を図示するMS)ンネル室部分の建設を例に
採って説明する・ 第2図ないし第11図は、MS)ンネル室7部分の施工
方法を施工手順に従って順次示すもので、また第1ユ図
ないし第1ダ図は、λ48トンネル字/内に据付けられ
るPy hx”のユニット20の詳細を示すものである
。M S )ンネル室/はまずその床および皆の沖設工
43が行なわれ、その後ユニット20が搬入されてその
共用架台7が据付けられ、その後S W 419(iの
支持名、・1材、2/aと共用り゛台7141iの支持
砂(材〕/bとの間にこれらの支持併へ材2/h 、 
:)、/ j)のみにより支持されて荷重を支えるテソ
キブレート工カ響′・設され、その後MSトンネル室/
の天井側の工事とユニット20側の工事とが並行して行
なわれるようになっている。
The present invention will be explained below by taking the construction of the MS) tunnel room part as an example. Figures 2 to 11 show the construction method of the MS) tunnel room part 7 in order according to the construction procedure, and Figures 1 and 1 show the details of the Pyhx" unit 20 installed in the λ48 tunnel. First, the floor of the tunnel room and the offshore construction work 43 After that, the unit 20 was carried in and its common pedestal 7 was installed, and then SW 419 (supporting name of i, ・1 material, shared with 2/a, support sand (material) of pedestal 7141i)/b and Between these supporting materials 2/h,
:), /j), and then the MS tunnel room /
Construction on the ceiling side and construction on the unit 20 side are carried out in parallel.

前記ユニット、20は、W7.2図ないし7d:n図に
示すようにIAS第a弁4a、FDW第ユ弁A t)、
共用架台7、M B 第J弁、ga、FDW第3弁gb
、配管9、および配管アンカー/lから構成されており
、このユニット20は、予め工場内に」?いて溶接作業
、応力除去、検査船が行なわれ完+j−!’品として一
体化されている。そしてこのユニット20は、MSトン
ネル室/の庁j、、−よひ壁の建築後、建屋内に搬入さ
れるようになっている。
As shown in Figures W7.2 to 7d:n, the unit 20 includes an IAS a valve 4a, a FDW valve A t),
Common mount 7, M B J valve, ga, FDW 3rd valve gb
, piping 9, and piping anchor/l, and this unit 20 is installed in advance in the factory. The welding work, stress relief, and inspection ship were carried out, and it was completed +j-! 'It is integrated as a product. This unit 20 is to be carried into the building after the building walls of the MS tunnel room are constructed.

次に、第2図ないし第1/図および第7図(b)を参照
してMSトンネル室/部分の建設工法を説明する。
Next, the construction method of the MS tunnel chamber/section will be explained with reference to FIGS. 2 to 1 and FIG. 7(b).

建設に際しては、まず第2図に示すようにMSトンネル
室/の床を施工し、次いでMS)ンネル室/の壁を兼ね
る5WIIをMS)ンネル室/の天井位置までPOV3
を囲むように施工する。そしてSW<tの頂部に支持銀
材2/ aを取付ける。
During construction, first construct the floor of the MS tunnel room/, as shown in Figure 2, then move the 5WII, which also serves as the wall of the MS) tunnel room, to the ceiling of the MS) tunnel room/in POV 3.
Constructed to surround. Then, attach the supporting silver material 2/a to the top of SW<t.

次いで、第9図に示すようにユニット2oをMSトンネ
ル室/に搬入し、共用架台7を据付ける。
Next, as shown in FIG. 9, the unit 2o is carried into the MS tunnel room/, and the common pedestal 7 is installed.

そしてその後、Ms)ンネル♀/の天井までの高さを有
している共用架台7の頂部に支持鋼−121bを取付け
、第1O図に示すように5Wll側の支持銅相2/aと
の間にデツキプレート、22を数段する。以後、天井側
の工事とユニッ)l側の工事とを並行して行なう。
After that, the support steel 121b is attached to the top of the common frame 7 which has a height up to the ceiling of Ms) tunnel ♀/, and as shown in Figure 1O, it is connected to the supporting copper phase 2/a on the 5Wll side. Place several deck plates 22 in between. After that, work on the ceiling side and work on the unit l side will be carried out in parallel.

すなわち、天井側では配筋工事およびコンクリートエ小
が行なわれ、一方ユニットJ側ではユニッ)lと他の配
管類との接続が行なわれる。
That is, on the ceiling side, reinforcing work and concrete work are performed, while on the unit J side, connections are made between unit 1 and other piping.

この接続に際しては、まず第1/図に示すようにPOV
貫通貫通管間先加工を行なってpcv7通管ベローズ1
0をJ収伺け、次いでpaveJ通管内配VIAとユニ
ット20の両箱a弁A a 、 6’bとを溶接する。
When making this connection, first, as shown in Figure 1/
After processing the end of the through-through pipe, install the PCV7 through-pipe bellows 1.
0 to J, and then weld the pave J internal piping VIA and both box a valves A a and 6'b of the unit 20.

この除、ユニット20の配管アンカーl/を一旦取外し
て溶接を行ない、溶接後m度配貿アンカー//を装着し
て配((jl gを共用架台7に固定する。
For this purpose, the piping anchor l/ of the unit 20 is once removed and welding is performed, and after welding, the m degree distribution anchor // is attached and fixed (jl g to the common frame 7.

次いで、両箱3弁g a、 、 g bとの取り合い配
管をが1.I工する。
Next, connect the connecting piping with the three valves ga, g, and b of both boxes to 1. I will work on it.

しかして、前記する工法により施工することにより、M
S)ンネル室lの天井工41の完了を待つととカフ機械
側の工事を行なうことができ、機械側はユニット化され
ているので、工期を大幅に短縮し1截の低減も図ること
ができる。
However, by carrying out the construction method described above, M
S) By waiting for the completion of the ceiling work 41 in the tunnel room l, the work on the cuff machine side can be carried out.Since the machine side is unitized, the work period can be significantly shortened and the number of cuts can be reduced. can.

またユニット20は雰1境のよい工場内で組立てられる
ので、現場施工によっていた従来法に比較して品質を向
上させることができる。
Furthermore, since the unit 20 is assembled in a factory with a good atmosphere, quality can be improved compared to the conventional method of on-site construction.

なお前記実施例の一態様では、MSトンネル室/部分の
建設を例に採って説明したが、屏子力設備の他の部分へ
も適用することが可能である。
Although one aspect of the above-mentioned embodiment has been explained by taking the construction of an MS tunnel room/section as an example, the present invention can also be applied to other sections of folding force equipment.

〔発明の効果〕〔Effect of the invention〕

以上説明したように本発明は、配管、弁および架台を予
め一体に組付けてユニット化し、原子炉建屋の床および
壁の建設後前記ユニットを建屋内に搬入して架台をや一
:付け、次いで前記壁と架台との間に、壁と架台のみで
支持されて天井の埋め殺し型枠を(”1′4成する仕切
板を配置し、次いで天井111!1の工事とユニッ) 
fil+の工事とを並行して行なうようにしているので
、建屋工事完了後に機械側の1眉1を行なうようにし、
しかも機械側を現場組立てしていた従来工法に比較して
工期を犬1f’:Aに短縮することができ、工数の低減
も可能となる。捷だ機械側はユニット化されているので
、現場工事の場合に比較して品質を安定させ(m9’t
i性を向上させることができる。
As explained above, the present invention involves assembling piping, valves, and pedestals into a unit in advance, and after constructing the floor and walls of a reactor building, carrying the unit into the building and attaching the pedestal. Next, between the wall and the pedestal, a partition plate that is supported only by the wall and the pedestal and forms a part of the ceiling (1'4) is placed, and then the ceiling 111!1 construction and unit work are carried out.
Since we are trying to do the fil+ construction in parallel, we will perform 1 eyebrow 1 on the machine side after the building construction is completed.
Moreover, compared to the conventional construction method in which the machine side was assembled on site, the construction period can be shortened to 1f':A, and the number of man-hours can also be reduced. Since the cutting machine side is unitized, quality is more stable compared to on-site construction (m9't
i-ness can be improved.

【図面の簡単な説明】[Brief explanation of drawings]

第1図はMS)ンネル室の原子炉建屋内における位置を
示す説明図、第2図は第1図のt+−n線拡大断面図、
第3図は12図のIff−I線矢視図、第り図ないし第
6図は従来工法を工程順に示す説明図、第7図(alは
従来工法の工程図、同図(句は本発明に係る工法の一例
を示す工程図、第2図ないし第1/図は本発明実施の一
態様を工程順に示す説明図、第12図は本発明に係るユ
ニ・ノドの一例を示す詳細平面図、第〆3図は第7.2
図のX1ll −X usiI断面図、第1q図は第1
ユ図のXIV −XIV線断面図である。 ゛ l・・MS)ンネル室、コ・・・原子炉建屋、3・
・PCV、 i=s W、 A a−M S第2弁、A
”D−・−FDW第2弁、7・・共用架台、ga・MS
第3弁、g’b−FDWあ)3弁、ワ・配管、/l・−
配管アンカー、J・ユニット、2/ a 、 21 b
−・支持銀材1.2.2デツキプレート。 出願人代理人  猪  股     清心12菌 躬13] 第14菌
Figure 1 is an explanatory diagram showing the position of the MS) tunnel room in the reactor building, Figure 2 is an enlarged sectional view taken along line t+-n in Figure 1,
Fig. 3 is a view taken along the If-I line in Fig. 12, Figs. A process diagram showing an example of the construction method according to the invention, FIGS. 2 to 1/FIG. are explanatory diagrams showing an embodiment of the present invention in the order of steps, and FIG. Figure, Figure 3 is 7.2
The X1ll-XusiI cross-sectional view in the figure, Figure 1q is the
It is a sectional view taken along the line XIV-XIV of the diagram.゛ l...MS) channel room, co...reactor building, 3...
・PCV, i=s W, A a-M S second valve, A
``D-・-FDW 2nd valve, 7...Common mount, ga・MS
3rd valve, g'b-FDW a) 3rd valve, wa piping, /l-
Piping anchor, J unit, 2/a, 21b
-・Support silver material 1.2.2 deck plate. Applicant's agent Inomata Seishin 12 Bacteria 13] 14th Bacterium

Claims (1)

【特許請求の範囲】 /、原子炉建屋の床および壁を建設した後、原子炉建屋
の天井工事と建屋内に配される配管、弁およびこれらの
架台の工事とを行なうものにおいて、前記配管、弁およ
び架台を予め一体に組付けてユニノ)化し、原子炉建屋
の床および壁の建設後前記ユニットを建屋内に搬入して
架台を据利け、次いで前記壁と架台との間に、壁と架台
のみで支持されて天井の埋め殺し型枠を構成する仕切板
を配置し、次いで天井側の工事とユニット側の工事とを
並行して行なうことを特許とする原子力設備の建設工法
。 2原子炉格納容器を囲む生体遮蔽壁に隣位する主蒸気管
トンネル室の建築工事および主蒸気管トンネル室内に配
される配管類とその架台の据付工事に適用することを特
徴とする特許請求の範囲卯、/項記載の坤子力設備の?
Ia設工法。
[Scope of Claims] / In a method for constructing the floor and walls of a reactor building, and then constructing the ceiling of the reactor building and constructing the pipes, valves, and frames for the pipes and valves disposed inside the building, , the valve and the pedestal are assembled together in advance to form a unit, and after constructing the floor and walls of the reactor building, the unit is carried into the building and the pedestal is installed, and then between the wall and the pedestal, This is a patented construction method for nuclear power facilities that involves arranging partition plates that are supported only by walls and frames and forming the fill-in formwork for the ceiling, and then carrying out work on the ceiling side and the unit side in parallel. 2. A patent claim characterized in that it is applied to the construction work of a main steam pipe tunnel room adjacent to the biological shielding wall surrounding the reactor containment vessel, and the installation work of piping arranged in the main steam pipe tunnel room and its frame. What is the range of the power equipment mentioned in the / section?
Ia construction method.
JP57178944A 1982-10-12 1982-10-12 Method of constructing atomic power facility Granted JPS5967495A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP57178944A JPS5967495A (en) 1982-10-12 1982-10-12 Method of constructing atomic power facility

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP57178944A JPS5967495A (en) 1982-10-12 1982-10-12 Method of constructing atomic power facility

Publications (2)

Publication Number Publication Date
JPS5967495A true JPS5967495A (en) 1984-04-17
JPS646426B2 JPS646426B2 (en) 1989-02-03

Family

ID=16057369

Family Applications (1)

Application Number Title Priority Date Filing Date
JP57178944A Granted JPS5967495A (en) 1982-10-12 1982-10-12 Method of constructing atomic power facility

Country Status (1)

Country Link
JP (1) JPS5967495A (en)

Also Published As

Publication number Publication date
JPS646426B2 (en) 1989-02-03

Similar Documents

Publication Publication Date Title
JPS5967495A (en) Method of constructing atomic power facility
JP3946352B2 (en) Construction method of reactor containment vessel
JP3283735B2 (en) Method for constructing upper dry well of reactor containment vessel and module used for the method
JPH05107381A (en) Method for constructing nuclear power plant reactor
JPH0464096A (en) Construction method of nuclear power plant
JP4352071B2 (en) Construction method of reactor containment vessel
JPH0699959B2 (en) Nuclear power plant building construction method
JPS63308B2 (en)
JPS60205288A (en) Method of executing steam-generator chamber wall in nuclear power plant
JPS63272690A (en) Construction of lining tank
JPS61286462A (en) Integral suspension construction method of iron beam and pipings of atomic power plant building
JPS60122390A (en) Method of constructing diaphragm floor of nuclear reactor container
JPS62157591A (en) Construction structure and method of container for nuclear reactor
JPS6329057B2 (en)
JPH0213757B2 (en)
JPS6244634B2 (en)
JPS6113183A (en) Method of constructing mat for housing of nuclear reactor
JPS58118987A (en) Method of constructing building
JPS6331074B2 (en)
JPS6331075B2 (en)
JPS6345555B2 (en)
JPS6344200B2 (en)
JPS6280383A (en) Installation structure of piping unit and method of installation construction thereof
JP2004309191A (en) Construction method of diaphragm floor of nuclear reactor containment, and module used for its construction
JPS60168086A (en) Method of assembling reactor housing vessel