JPS5941570A - Method and apparatus for constructing underground tank storage place - Google Patents

Method and apparatus for constructing underground tank storage place

Info

Publication number
JPS5941570A
JPS5941570A JP57152275A JP15227582A JPS5941570A JP S5941570 A JPS5941570 A JP S5941570A JP 57152275 A JP57152275 A JP 57152275A JP 15227582 A JP15227582 A JP 15227582A JP S5941570 A JPS5941570 A JP S5941570A
Authority
JP
Japan
Prior art keywords
concrete
underground tank
tank
underground
factory
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP57152275A
Other languages
Japanese (ja)
Other versions
JPH0231190B2 (en
Inventor
隆一 山本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YAMAMOTO BOIRAA SEIZOUSHIYO KK
Original Assignee
YAMAMOTO BOIRAA SEIZOUSHIYO KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YAMAMOTO BOIRAA SEIZOUSHIYO KK filed Critical YAMAMOTO BOIRAA SEIZOUSHIYO KK
Priority to JP57152275A priority Critical patent/JPS5941570A/en
Publication of JPS5941570A publication Critical patent/JPS5941570A/en
Publication of JPH0231190B2 publication Critical patent/JPH0231190B2/ja
Granted legal-status Critical Current

Links

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 (発明の目的) 本発明は現地での工期を大幅に短縮し、建築工事全体の
工期短縮と各種中間検査に要する人的、時間的ロスが少
なく、かつ公務にかかる消防係官の負担を軽減すると共
に、土砕崩れによる危険の防止を目的とする地下タンク
貯蔵所設置工法および装置に関する。
[Detailed Description of the Invention] (Purpose of the Invention) The present invention significantly shortens the on-site construction period, shortens the entire construction period, reduces human and time loss required for various intermediate inspections, and reduces the amount of time required for public work. This invention relates to a method and device for installing an underground tank storage facility, which aims to reduce the burden on fire department officials and prevent dangers caused by landslides.

(従来技術) 従来、地下タンク貯蔵所の設置工法は、第1図に示すよ
うに、工jllIにおいてタンクTを製作にタンク本体
の水圧検査を受ける(イ勺 (所要日数6日間)。次に
このタンクTの外面にアスファルト防水加工A(口りを
施こして現MJIGでの第4工程(ニ)へ運搬する(2
日間)。
(Prior Art) Conventionally, as shown in Figure 1, the installation method for underground tank storage facilities involves a water pressure test of the tank body (required 6 days) at the time of manufacturing the tank T at the construction stage. The outer surface of this tank T is coated with asphalt waterproofing A (glue) and transported to the fourth process (d) at the current MJIG (2).
days).

これとは平行作業で現場Gにおいては、許可された所定
位置に穴IIを掘りグリ石S1を敷<(イ)(2日間)
。仮枠Wlを組み、基礎コンクリートCB。
In parallel work, at site G, hole II was dug at the predetermined location permitted and stone stone S1 was laid. (B) (2 days)
. Assemble the temporary frame Wl and build the foundation concrete CB.

C2,C3(ニ)の鉄筋■(およびアンカーボルトUを
施工(ロ)(1日間)シ、下部配筋検査完了後、基礎、
枕、支柱のコンクリートC1、C2,C3を打ち数日間
養生する(ハ)(5日間)。次に工[1%1 から搬入
した前記アスファルト防水加工Aを施したタンクTを据
付け、バンドB、Bで固定し、検知管(図示略)を所定
の位fαに宜てローリ−アース(図示略)等を施工して
、タンクTの据付検査を受ける(二)(2日間)。次に
タンクTの頂部まで埋め戻し町を行い、プロテクターP
を試せ、オイル配管L 、 Lを施工し、配管検査を受
ける、配管の防蝕加工を行う(ホ)(4日間)。次にさ
らに支柱コンクリートc8. C3の上部まで埋め戻し
M2を行い、上部のコンクリートC4のグリ552、仮
枠W2および鉄筋1(2を組み、上部検査を受ける(へ
)(3日間)。次に上部の配筋検査完了後、コンクリー
トC4を打ち数日間養生する()−)(5日間)。
After completing the lower reinforcement inspection, the foundation,
Pour concrete C1, C2, and C3 for the pillows and pillars and cure for several days (c) (5 days). Next, install the tank T with the asphalt waterproofing treatment A brought in from the factory [1%1], fix it with bands B and B, and connect the detection tube (not shown) to the lorry ground (not shown) at a predetermined position fα. (Omitted) etc. and undergo installation inspection of Tank T (2) (2 days). Next, perform backfilling to the top of tank T and protector P.
Try it out, install oil piping L and L, undergo piping inspection, and apply corrosion-proofing treatment to the piping (E) (4 days). Next, support concrete c8. Perform backfilling M2 to the top of C3, assemble the upper concrete C4's bore 552, temporary frame W2 and reinforcing bars 1 (2), and undergo an upper inspection (3 days). Next, after completing the upper reinforcement inspection. , concrete C4 is poured and cured for several days ()-) (5 days).

最径に仕上げ清掃、W1!!!郷を行い台皿の囲器や備
品を取付け、完成検査を受け、完成検査済証をもらって
全工程を終了する(チ)(3日間)。
Finish cleaning on the deepest diameter, W1! ! ! The entire process is completed by carrying out the inspection, installing the base plate enclosure and equipment, undergoing a final inspection, and receiving a certificate of completion inspection (3) (3 days).

この従来の工法では順調に行っても現場Cにおける工事
だけでも合計25日かかり、工事がかかりすぎ、雨が降
ればさらにその分だけのびる。
With this conventional construction method, even if everything goes smoothly, it will take a total of 25 days to complete the construction work at Site C, which is too much work, and if it rains, it will take even longer.

検査は工場■において1回、現場Gにおいて5回、ti
 6回もあり、配管検査を2回に分ければ7回の多きに
達する。このように検査回数が多いので、受ける方も行
う方も、人的にも時間的にもロスが多く、検査官の負担
も多大なものがあった。
Inspection was carried out once at factory ■, five times at site G, and ti
There are as many as 6 inspections, and if you divide the piping inspection into 2 inspections, you can get as many as 7 inspections. Because of the large number of inspections, there was a lot of loss in terms of both personnel and time for both those taking and administering the tests, and the burden on the inspectors was also heavy.

また、穴nを掘ってからlO日日間ど埋め戻されないの
で、周囲の土砕が崩れたり、人が落ちたりして危険が常
につきまとうばかりか、他の工事の邪魔になり建築工事
全体の工程に影響を及ぼし、地下水の湧出する場合が多
く、下部の基礎工事がやりに<<、長期にわたり湧水の
汲上げが必要となる。
In addition, since the hole is not backfilled for several days after it is dug, not only is there a constant danger of the surrounding soil collapsing or people falling into it, but it also interferes with other construction work and disrupts the entire construction work process. In many cases, underground water gushes out, making it necessary to pump up the spring water over a long period of time, making it difficult to construct the foundations at the bottom.

さらにまた、コンクリートの養生が不充分のうちに埋め
戻す場合が生じ易く、コンクリートの強度上での問題を
生ずる。
Furthermore, it is likely that the concrete will be backfilled before it has sufficiently cured, resulting in problems regarding the strength of the concrete.

また、法規に精通した知識のある者が施工する必要が実
際に生じ、誰でも施工できるわけをこl/1カ)ず、−
品生産的要素の工事であり、非近代的工法であるため合
理化が必要である。
In addition, it actually needs to be carried out by a person who is familiar with the laws and regulations, and there is no way that anyone can carry out the construction.
Since the construction involves product production elements and uses non-modern construction methods, rationalization is necessary.

(発明の#l成・作用) 本発明は上述の不具合に鑑み、地下タンクを収納できる
。規格のコンクリートによる貯蔵室を予じめ工場におい
て完成させておき、許可現場に穴を掘り、グリ石を敷き
、基部の固着用コンクリートを打ったら直ちに前記貯蔵
室を載設し、養生後、タンク収納と配管および埋め戻し
を短時日で行うようにしたもので、本発明を実施例の図
によって説明する。
(#l Structure and Effect of the Invention) In view of the above-mentioned problems, the present invention can house an underground tank. A storage room made of standard concrete is completed in advance at the factory, a hole is dug at the permitted site, a griddle is laid, and concrete is poured for fixing the base, and the storage room is immediately installed, and after curing, the tank is installed. This invention is designed to carry out storage, piping, and backfilling in a short period of time.The present invention will be explained with reference to drawings of embodiments.

第2図乃至第16図は本発明を工程別に示す製作図で、
第2図乃至第6図は工場内での工程、第7図乃至第16
図は現場における工程を示すものである。
Figures 2 to 16 are production drawings showing the present invention step by step.
Figures 2 to 6 are processes in the factory, Figures 7 to 16
The figure shows the process at the site.

第2図(イ)において、支柱金Ill DI内に取付ボ
ルト1を突設させて配筋2を施し、第2図(ロ)におい
て上部コンクリートパーツ金型D2内に配筋3を施し、
第2図(ハ)において基礎コンクリートパーツ金fi 
D3内に配筋4およびアンカーボルト5.5.・・・・
をセットしてコンクリートcを流し込んで養生後、離型
して、第3(閾(イ)、(ロ)、(ハ)にそれぞれ示す
支柱6、上部コンクリート7および基礎コンクリート8
を得る。
In Fig. 2 (a), the mounting bolt 1 is protruded in the support metal Ill DI and reinforcement 2 is applied, and in Fig. 2 (b), the reinforcement 3 is applied in the upper concrete part mold D2,
In Figure 2 (c), the foundation concrete parts gold fi
Reinforcement 4 and anchor bolts 5.5 in D3.・・・・・・
is set, concrete c is poured in, and after curing, the mold is released and the pillars 6, upper concrete 7 and foundation concrete 8 shown in the third (threshold (a), (b), and (c), respectively) are prepared.
get.

また工場において、公知の方法により第4図(−□ に
示すタンク本体9、同(ロ)に示す検知管10および同
(ハ)に示すオイル管11を製作しタンク本体9に対す
る水圧検査はじめ各パーツに対する寸法検査等の諸検査
を受け、合格したタンク本体9の外周には第5図(イ)
に示すようなアスファルトライニング(防蝕加工)12
を施して地下タンク13を形成し、同(ロ)に示すよう
に前後検知管10をオイル管11に嵌装して基部配管1
4を形成する。
In addition, in the factory, the tank body 9 shown in Figure 4 (-□), the detection tube 10 shown in (B), and the oil pipe 11 shown in Figure 4 (C) were manufactured by a known method, and water pressure tests on the tank body 9 were carried out. The outer periphery of the tank body 9 that has passed various inspections such as dimensional inspection on parts is marked as shown in Figure 5 (a).
Asphalt lining (corrosion-resistant treatment) as shown in 12
to form an underground tank 13, and as shown in FIG.
form 4.

次に第6図において前記基礎コンクリート8の上部に前
記地下タンク13をjkIitI#シ、これに掛は陥し
たバンド15.15をアンカーボルト5.5およびナツ
ト16.16により結着し、第7図において、地下タン
ク13を基礎コンクリート8」−に結着した一体のもの
をトラックTRにより前記支柱6、上部コンクリート7
および基部配管14等と共に現場Gへ搬入する。
Next, in FIG. 6, the underground tank 13 is placed on top of the foundation concrete 8, and the fallen band 15.15 is fastened to it with the anchor bolt 5.5 and nut 16.16. In the figure, the underground tank 13 is connected to the foundation concrete 8'' and the truck TR transports the underground tank 13 to the support column 6 and the upper concrete 7.
and the base piping 14, etc., to the site G.

次に第8図乃至第9図において現場Gに所定の穴■を掘
り、底部にグリ石17,17.・・・・を敷き土固めし
、グリ石!7,17.・・・・の上面に第1回目の捨て
コンクリート18を打設し、固ってからさらに第2回目
の捨てコンクリート19を打設する。
Next, as shown in Figs. 8 and 9, a predetermined hole (2) is dug at site G, and the bottom is filled with grist stones 17, 17. Lay down the soil, harden it, and lay stone! 7,17. . . . The first sacrificial concrete 18 is placed on the top surface, and after it hardens, the second sacrificial concrete 19 is placed.

次に第1θ図において、第2回目の捨てコンクリート1
9を打設直後にまだ固まらないうちに前記基礎コンクリ
ート8とJIIJ下タンク13とがバンド15.15に
より一体になったものをクレーンCRによって前記穴+
f内の捨てコンクリ−)−19上に吊り下ろし、正位I
Nに1aIRする。
Next, in Figure 1θ, the second disposal concrete 1
Immediately after pouring the concrete 9 and before it hardens, the foundation concrete 8 and the JIIJ lower tank 13 are integrated by the band 15.
Suspended on the abandoned concrete (inside f)-19 and placed in a straight position I
1aIR to N.

次に第11図において基礎コンクリート乏3の四隅に設
けたレベル調整ねじ20,20.・・・・をハンドルN
を用いて胸し、各所の調整ねじ20を微調整して地下タ
ンク13の水平を正確に出す。
Next, in FIG. 11, level adjustment screws 20, 20. ... as handle N
The underground tank 13 is accurately leveled by finely adjusting the adjustment screws 20 at various locations.

次に第12四において前記基礎コンクリート8の四隅に
設けた支柱植設テーパ一孔21,21゜・・・・に前記
支柱6,6.・・・・、テーパー基部22゜22、・・
・・をそれぞれ嵌設すると共に、前記アンカーボルト5
,5を支柱6の基部の挿孔23,23に挿通してそれぞ
れナツト24.24で締結する。
Next, in the 124th step, the pillars 6, 6. ..., taper base 22゜22, ...
..., and the anchor bolts 5.
, 5 are inserted into the insertion holes 23, 23 at the base of the support column 6 and fastened with nuts 24, 24, respectively.

次に第13図において、前記上部コンクリート7をクレ
ーンCR(第10図参照)により吊り下ろし、四隅にM
設したそれぞれの支柱6の前記取付ボルトlに上部コン
クリート7の四隅の挿孔25に挿通すると共に支柱6の
上部テーパ一部26を上部コンクリート7のテーパ一孔
27に嵌合させる。
Next, in Fig. 13, the upper concrete 7 is lowered by crane CR (see Fig. 10), and M
The mounting bolts 1 of each of the provided columns 6 are inserted into the insertion holes 25 at the four corners of the upper concrete 7, and the upper tapered portions 26 of the columns 6 are fitted into the tapered holes 27 of the upper concrete 7.

次に第14図において、ナツト28を取付ボルト1に螺
締して上部コンクリート7を支柱6,6゜・・・・上に
固着し、上部コンクリート7の検知管挿孔29,29か
ら前記検知管10をJrri人して固定する。
Next, in FIG. 14, the nuts 28 are screwed onto the mounting bolts 1 to secure the upper concrete 7 on the supports 6, 6°, etc., and the detection tubes are inserted through the detection tube holes 29, 29 in the upper concrete 7. Fix the tube 10 by tightening it.

次に31S15図において、第1″0c埋め戻し30を
上部コンクリート7の下縁まで行い、+11記地下タン
ク13の上部のハツチ部31の周囲にプロテクター32
を取付け、監33を有する座板34により滴量して座板
34の周縁と上部コンクリート7の上面との間にモルタ
ル密封35を施す。
Next, in Figure 31S15, the first 0c backfill 30 is performed to the lower edge of the upper concrete 7, and a protector 32 is placed around the hatch part 31 at the top of the underground tank 13 marked +11.
is installed, and a mortar seal 35 is applied between the periphery of the seat plate 34 and the upper surface of the upper concrete 7 by applying a drop of water using the seat plate 34 having the groove 33.

次に第16図において、前記ハツチ部31に予じめ設け
たオイル管接続部36.3Gに前記基部配管14.14
およびさらにその延長に延長オイル管37.37を?W
J1し、上部コンクリート7の上級まで第2Y7C埋め
戻し3Bを施し、安全弁39を取付けて、完成@査を受
けて工4■は完了する。
Next, in FIG. 16, the base pipe 14.14 is connected to the oil pipe connection part 36.3G previously provided in the hatch part 31.
And further extend the extension oil pipe 37.37? W
J1, perform 2nd Y7C backfill 3B up to the upper level of the upper concrete 7, install the safety valve 39, and complete the work 4■ after receiving inspection.

図中40は(灸知管10のガイドボスを示す。In the figure, 40 indicates a guide boss of the moxibustion tube 10.

(発明の効果) 本発明はタンク本体にアスファルトライニングを施した
jft下タンク、支柱、上部コンクリート、基礎コンク
リート、検知管、基部配管等の各種部品を工場で製作し
、現場にて穴掘り、グリ石敷き、および捨てコンクリー
ト打ちを終ったところへ、基礎コンクリートと地下タン
クとを一体にバンドで11−1したものを搬送し、穴中
に吊り下して据付けて水平を出し、支柱の取付け、上部
コンクリートの嵌設、盆、プロテクター、検知器、基部
配管等の取付けと埋め戻し作業を連続して行うようにし
たので、現場での工期が大幅に短縮され、従って建築工
事全体の工期短縮に好結果をもたらす効果は極めて大き
い。
(Effects of the invention) The present invention manufactures various parts such as the JFT lower tank with asphalt lining on the tank body, supports, upper concrete, foundation concrete, detection tube, and base piping in a factory, and then performs drilling and greasing on site. After the stone paving and concrete pouring was completed, the foundation concrete and underground tank were transported together with a band, suspended in the hole, and leveled, and the supports were installed. Since the work of placing the upper concrete, installing the tray, protector, detector, base piping, etc., and backfilling work are performed in succession, the construction period on site is significantly shortened, and therefore the construction period of the entire construction work is shortened. The effect of bringing about good results is extremely large.

また各種中間検査に要する人的、時間的ロスが少なく、
公務にかかる消防係官の角担が著しく軽減でき、穴を掘
ってから埋め戻すまでの期間が短かく、周囲の土砂が崩
れたり、人が落ちたりする危険が大幅に減少し、かつ地
下水汲み上げポンプの運動期間が短縮されるので、他工
孕の進捗に支障を来たすことが少ない。
In addition, there is less human and time loss required for various intermediate inspections.
It can significantly reduce the burden on fire officials involved in official duties, shorten the period from digging a hole to backfilling it, greatly reduce the risk of surrounding earth and sand collapsing or causing people to fall, and using underground water pumps. Since the exercise period is shortened, there is less interference with the progress of other engineers.

さらにまた、消防法で定めた施行規準による現場工事を
、特にその知識に精通していない者でも簡単に施行でき
、工場での製作にあたっては、タンクおよびコンクリー
トパーツをタンクの容量毎に規格した統一寸法とし、あ
らかじめ生産およびストックしておくので、コンクリ−
1−製品の養生も充分にでき、従来工法では生じ勝ちな
養生不足による強度上の欠陥が生じることがない。
Furthermore, on-site construction work in accordance with the enforcement standards stipulated by the Fire Service Act can be easily carried out even by those who are not particularly knowledgeable about it, and when manufacturing tanks and concrete parts in factories, uniform standards are used for each tank capacity. Since the dimensions are determined, produced and stocked in advance, concrete
1- The product can be sufficiently cured, and there are no defects in strength due to insufficient curing, which tend to occur with conventional construction methods.

また従来工法と異った合理的設計によるコンクリートパ
ーツであるから、物理的強度や安全性が高く、又品質が
均一化しコンクリートの使用量に無駄がなく経済的であ
り、施工手順の合理化のため、現場施工費用も大幅に減
少する。
In addition, since the concrete parts are designed with a rational design that differs from conventional construction methods, they have high physical strength and safety, are uniform in quality, are economical with no wastage of concrete, and are designed to streamline construction procedures. , on-site construction costs will also be significantly reduced.

さらにまた、支柱の両端がテーパーになりているので、
基礎コンクリートおよび上部コンクリートとの接続がガ
タつきがなく、完全に固定できる。
Furthermore, both ends of the pillar are tapered, so
The connection between the foundation concrete and the upper concrete can be completely fixed without any wobbling.

なお、本発明の地下タンク貯蔵所はタンク容量3000
1程度が限度である。
Note that the underground tank storage facility of the present invention has a tank capacity of 3000
The limit is about 1.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図(イ)乃至(チ)および同(イ/)  (口l)
は従来技術の工程説明図、第2図乃至第6図は本発明の
工場製作工程の説明図、第7図は現場への搬送説明図、
第8図乃至第16図は本発明の現場での作業工程説明図
である。 (主要部分の符号の説明) 6・・・・支  柱    7・・”・・上部コンクリ
ート8・・・・基礎コンクリート 9・・・・タンク本体   10・・・・検 知 書1
1・・・・オイル管 12・・・・アスファルトライニング 13・・・・地下タンク  14・・・・基部配管l 
5・・・・バ  ン  ド    17・・・・グ  
リ  石18・・・・捨てコンクリート(第1図)19
・・・・1舎でコンクリート(第2図)20・・・・調
整ねじ 21・・・・支柱植設テーパ一孔 22・・・・テーパー基部 26・・・・上部テーパ一部(支柱の)27・・・・テ
ーパ一孔(上部コンクリートの)30・・・・第1次埋
め戻し 31・・・・ハツチ部3z・・・・プロテクタ
ー 33・・・・盆36・・・・オイル管接続部 37・・・・延長オイル管 38・・・・第2次埋め戻し ト・・・穴 手続補正書、ヵ□、。 昭和5′7年12月10日 特許庁長官   若 杉 和 夫  殿(特許庁審判長
             殿)(特γ「庁審査官  
           殿)1、事件の表示 昭和57年 特  許 願第 152275号2、 発
明の3称  地下タンク貯蔵所設置工法および装置3、
補正する者 事件との関係      特許出願人 住所(居所)  岐阜県各務原市那加新加納町字北荒コ
ロ、補正により増加する発明の数 第13貞第3行目「同(イ′)(口゛)はJを全文削除
して「同(す)、(ヌ)は」と訂正します。 2、本願の(9)面(第1図)を別紙の通り補正致しま
す。 添附書類の目録 (1)図 面(訂 圧)           1 通
以上 手続補正書 昭和58年6 月6 日 特許庁長官   若 杉 和 よ  殿(特許庁審判長
              殿)(特γ「庁審査宮 
            殿)1、事件の表示 昭和57 年 特  、1「  願書 152275号
2、発明の名称 地下タンク貯蔵所設置工法および装置 3、補正する者 4、代  理  人  〒500 第12頁第18行目乃至第13頁第1行目[なお、本発
明の地下タンク貯蔵所はタンク容fi30007程度が
限度である。」を全文削除します。 以上 第8図 第9図 第10図 17  17  17 第11FM 第13図
Figure 1 (a) to (ch) and the same (a/) (mouth l)
is an explanatory diagram of the process of the prior art, FIGS. 2 to 6 are explanatory diagrams of the factory manufacturing process of the present invention, and FIG. 7 is an explanatory diagram of transportation to the site,
FIG. 8 to FIG. 16 are explanatory diagrams of the on-site work process of the present invention. (Explanation of symbols of main parts) 6... Pillar 7... Upper concrete 8... Foundation concrete 9... Tank body 10... Detection note 1
1... Oil pipe 12... Asphalt lining 13... Underground tank 14... Base piping l
5... Band 17... Band
Li Stone 18...Discarded concrete (Fig. 1) 19
... Concrete in one building (Fig. 2) 20 ... Adjustment screw 21 ... Support installation taper hole 22 ... Taper base 26 ... Part of the upper taper (of the support) ) 27... Taper hole (in upper concrete) 30... Primary backfilling 31... Hatch portion 3z... Protector 33... Tray 36... Oil pipe Connection part 37...Extension oil pipe 38...Second backfilling...Hole procedure correction form, ka□,. December 10, 1975: Mr. Kazuo Wakasugi, Commissioner of the Japan Patent Office (Chief Examiner of the Japan Patent Office) (Special γ Office Examiner)
) 1. Indication of the incident 1982 Patent Application No. 152275 2. Title 3 of the invention: Underground tank storage installation method and device 3.
Relationship with the case of the person making the amendment Patent applicant address (residence) Kitarakoro, Nakashinkano-cho, Kakamigahara-shi, Gifu Prefecture Number of inventions increased by amendment ) is corrected by deleting J in its entirety and saying "Same (su), (nu) wa". 2. We will amend aspect (9) of this application (Figure 1) as shown in the attached sheet. List of attached documents (1) Drawings (revised) One or more procedural amendments June 6, 1981 Kazuyo Wakasugi, Commissioner of the Patent Office (Chief Adjudicator of the Patent Office) (Special γ Office Examination Palace)
1. Indication of the case 1982 Special, 1 "Application No. 152275 2. Name of the invention: Underground tank storage installation method and device 3. Amended person 4. Agent 500, page 12, line 18 to The entire text of page 13, line 1 [The underground tank storage facility of the present invention has a tank capacity of approximately fi30007] is deleted in its entirety. Above Figure 8 Figure 9 Figure 10 Figure 17 17 17 11FM Figure 13

Claims (4)

【特許請求の範囲】[Claims] (1)タンク本体のアスファルトライニング加工および
基礎コンクリート、支柱、上部コンクリート等の各種コ
ンクリートパーツならびに検知管および基部配管等の各
附属品を予じめ工場において製作し、建設現場において
穴掘り、グリ石敷き、捨てコンクリート打ちの後、前記
パーツを吊り下して順次に組立て埋め戻しを行うことを
特徴とする地下タンク貯蔵所設置工法。
(1) Asphalt lining of the tank body, various concrete parts such as foundation concrete, columns, upper concrete, etc., and accessories such as detection tubes and base piping are manufactured in advance at the factory, and holes are dug at the construction site and grist stone A construction method for installing an underground tank storage facility, characterized in that after laying and pouring concrete, the parts are suspended and sequentially assembled and backfilled.
(2)下部の基礎コンクリートと四隅の支柱と、上部の
上部コンクリートの工場等で単一部品として成型された
各コンクリートパーツと、タンク本体番こアスファルト
ライニングを工場等で施した地下タンクと、この地下タ
ンクを前記基礎コンク1ノートパーツに縛着するバンド
と、地下タンクのノ1亀ソチ部を保護する有量のプロテ
クターと、基部配管と、検知器等から組合わされて地下
に埋設されたことを特徴とする地下タンク貯蔵所。
(2) The foundation concrete at the bottom, the pillars at the four corners, the concrete parts at the top molded as a single part in a factory, etc., the tank body, the underground tank with asphalt lining in a factory, etc. A band that binds the underground tank to the basic concrete 1 notebook part, a substantial protector that protects the bottom part of the underground tank, base piping, a detector, etc. are combined and buried underground. An underground tank storage facility featuring:
(3)支柱の上下にテーパ一部を有し、このテーパ一部
がそれぞれ嵌合するテーパ一孔をそれぞれ四隅に有する
基礎コンクリートおよび上部コンクリートを特徴とする
特許請求の範囲第2項記載の地下タンク貯蔵所。
(3) The basement according to claim 2, characterized in that the base concrete and the upper concrete have tapered portions at the top and bottom of the support column, and taper holes in each of the four corners into which the taper portions fit respectively. tank storage.
(4)基礎コンクリートの四隅のテーパ一孔の底部に水
平微調整用の調整ねじをそれぞれ設けたことを特徴とす
る特許請求の範囲第2項および第3項記載の地下タンク
貯蔵所。
(4) An underground tank storage facility according to claims 2 and 3, characterized in that adjustment screws for fine horizontal adjustment are provided at the bottoms of each of the tapered holes at the four corners of the foundation concrete.
JP57152275A 1982-09-01 1982-09-01 Method and apparatus for constructing underground tank storage place Granted JPS5941570A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP57152275A JPS5941570A (en) 1982-09-01 1982-09-01 Method and apparatus for constructing underground tank storage place

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP57152275A JPS5941570A (en) 1982-09-01 1982-09-01 Method and apparatus for constructing underground tank storage place

Publications (2)

Publication Number Publication Date
JPS5941570A true JPS5941570A (en) 1984-03-07
JPH0231190B2 JPH0231190B2 (en) 1990-07-11

Family

ID=15536941

Family Applications (1)

Application Number Title Priority Date Filing Date
JP57152275A Granted JPS5941570A (en) 1982-09-01 1982-09-01 Method and apparatus for constructing underground tank storage place

Country Status (1)

Country Link
JP (1) JPS5941570A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61196077A (en) * 1985-02-22 1986-08-30 株式会社タツノ・メカトロニクス Tank embedding method
JP2018199962A (en) * 2017-05-29 2018-12-20 株式会社ホクコン Protecting housing and construction method of the same

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5000771B2 (en) * 2011-01-31 2012-08-15 株式会社カンケン Septic tank installation structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61196077A (en) * 1985-02-22 1986-08-30 株式会社タツノ・メカトロニクス Tank embedding method
JPH0452345B2 (en) * 1985-02-22 1992-08-21 Tokyo Tatsuno Kk
JP2018199962A (en) * 2017-05-29 2018-12-20 株式会社ホクコン Protecting housing and construction method of the same

Also Published As

Publication number Publication date
JPH0231190B2 (en) 1990-07-11

Similar Documents

Publication Publication Date Title
AU2021106549B4 (en) A construction method for an unbonded prestressed large-diameter reinforced-concrete thin-walled circular tank
CN109235499A (en) A kind of open cut hypogee Standard formula construction method
CN106150060B (en) Construction method based on assembled wall-connecting piece exterior wall scaffold system
CN106869548A (en) A kind of newel framework assembled underground parking structural system and construction method
CN107165251A (en) A kind of construction method of drainage system
CN104929047B (en) A kind of V-type pier outer support construction method
CN102877538A (en) Construction method for fixing HDPE (high-density polypropylene) pipe by embedding iron wires
JPS5941570A (en) Method and apparatus for constructing underground tank storage place
CN109594477A (en) A kind of big bent cap strutting system construction technology of only pier
KR20170126546A (en) The inner surface of pipelines medium and large repair and reinforcement
CN105970997B (en) A kind of steel towers prefabricated compound assembling external member pile foundation of thing and preparation method thereof
KR20110136987A (en) Constructing method for underground external wall using form with concrete placing inlet and vibrator inlet for preventing concrete counterflow
CN113848122A (en) Hydraulic tunnel surrounding rock and lining structure simulation test method considering external water pressure
Dave Full scale testing of corrugated metal culvert pipe rehabilitated with shotcrete liner
JP4962831B2 (en) Foundation structure of column base and its construction method
CN109667278A (en) Tower crane anti-cracking and seepage control construction method is set under underground garage isolated footing
CN113832903B (en) Water-force coupling test method for tunnel surrounding rock and lining structure bearing system
CN218462537U (en) Secondary structure prefabricated part
CN220434321U (en) Anti-seismic reinforcement column structure
CN213952218U (en) Enlarged footing prestressed concrete stock
CN105507381B (en) Direct-burried cutting-off type sleeve pipe drainage management construction method
JP2004339703A (en) Foundation construction method
CN114482238A (en) Construction method of sewage well
Cheng et al. Construction method of strengthening shear walls using prestressed steel bars for a high-rise building
CN113718853A (en) Drainage overhead construction system for high-rise residential building