JPS5929760B2 - How to excavate underground storage cavities - Google Patents

How to excavate underground storage cavities

Info

Publication number
JPS5929760B2
JPS5929760B2 JP51000921A JP92176A JPS5929760B2 JP S5929760 B2 JPS5929760 B2 JP S5929760B2 JP 51000921 A JP51000921 A JP 51000921A JP 92176 A JP92176 A JP 92176A JP S5929760 B2 JPS5929760 B2 JP S5929760B2
Authority
JP
Japan
Prior art keywords
tunnel
cavity
shaft
underground storage
underground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP51000921A
Other languages
Japanese (ja)
Other versions
JPS5284801A (en
Inventor
満穂 和田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP51000921A priority Critical patent/JPS5929760B2/en
Publication of JPS5284801A publication Critical patent/JPS5284801A/en
Publication of JPS5929760B2 publication Critical patent/JPS5929760B2/en
Expired legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

【発明の詳細な説明】 本発明は石油等の資源を備蓄または廃棄する等の目的で
、地下に貯蔵用空洞を掘削する方法に係るもので、地中
に掘削されるべき地下貯蔵用空洞より高いレベルに、同
空洞と直角方向に延び、両端坑口において外部に開口す
る上部坑道を掘削し、その両端部より斜坑道を掘削し、
同斜坑道に連結させて前記空洞の底部レベルに前記上部
坑道と平行に下部坑道を掘削し、次いで同下部坑道より
所要位置毎に分岐坑道を岐出掘進し、同分岐坑道の先端
に所要断面の地下貯蔵用空洞を掘削し、次いで同空洞を
前記上部坑道にシャフトを介して連結することを特徴と
し、その目的とする処は、施工性に優れ、経済性の高い
地下貯蔵用空洞の改良された掘削工法を供する点にある
Detailed Description of the Invention The present invention relates to a method of excavating a storage cavity underground for the purpose of stockpiling or disposing of resources such as petroleum. At a high level, excavate an upper tunnel that extends perpendicularly to the cavity and opens to the outside at both ends of the tunnel, and excavate an inclined tunnel from both ends of the tunnel.
A lower tunnel is excavated parallel to the upper tunnel at the bottom level of the cavity by connecting to the inclined tunnel, and then branch tunnels are dug out from the lower tunnel at each required position, and the tip of the branch tunnel has the required cross section. The feature is to excavate an underground storage cavity, and then connect the same cavity to the upper tunnel through a shaft, and the purpose is to improve the underground storage cavity with excellent construction efficiency and high economic efficiency. The point is that it provides an advanced excavation method.

以下本発明を図示の実施例について説明する。The present invention will be described below with reference to the illustrated embodiments.

先ず所要の地盤A内に、同地盤内に掘削されるべき地下
貯蔵用空洞より高いレベルに、同空洞と直角方向に延び
る両端坑口1a、lbにおいて外部に開口する上部坑道
1を掘削し、その両端部より斜坑道3、3’を掘削し、
同斜坑道3、3’に連結するように、前記空洞の底部レ
ベルに前記上部坑道1と平行に下部坑道2を掘削し、か
くして前記上下坑道1、2及び斜坑道3、3’によつて
地下貯蔵用空洞を囲繞する作業空間を構成する。なお前
記斜坑道3、3’は下部坑道2とともに作業用坑道を構
成するものであつて、車輛が自由に出入しうる程度の勾
配が附され、また前記斜坑道3、3’の何れか一方の坑
口、または前記斜坑道3、3’より特別に設けられたシ
ャフトまたは横坑に換気装置を配設して、作業用坑道の
通風を良好ならしめるものである。次いで前記下部坑道
2の所定位置毎に分岐坑道4を掘進し、その先端に公知
の工法によつて地下貯蔵用空洞B1、B2、B3、B4
・・・を順次掘削し、同各空洞掘削完了後上部坑道1と
シャフト5で連結せしめる。
First, in the required ground A, an upper tunnel 1 is excavated at a level higher than the underground storage cavity to be excavated in the same ground, and opens to the outside at both end shaft openings 1a and lb extending perpendicularly to the cavity. Excavate inclined tunnels 3 and 3' from both ends,
A lower shaft 2 is excavated at the bottom level of the cavity parallel to the upper shaft 1 so as to be connected to the upper shaft 1, 2 and the lower shaft 3, 3'. Configure a working space surrounding an underground storage cavity. The inclined tunnels 3 and 3' constitute a working tunnel together with the lower tunnel 2, and are sloped to such an extent that vehicles can freely enter and exit. A ventilation system is provided at the entrance of the tunnel, or in a shaft or side shaft specially provided from the inclined tunnels 3, 3', to improve ventilation of the working tunnel. Next, a branch tunnel 4 is dug at each predetermined position of the lower tunnel 2, and underground storage cavities B1, B2, B3, and B4 are formed at the tips of the tunnels by a known construction method.
. . . are excavated one after another, and after the excavation of each cavity is completed, the upper tunnel 1 and the shaft 5 are connected to each other.

なお同シャフト5は将来換気または、貯蔵材料の搬出入
用に供せられる。図中6は上部坑道1と地盤A表面とを
連絡する竪坑であり将来ペーパ抜き等換気の用に供せら
れる。
The shaft 5 will be used for ventilation or for carrying in and out of stored materials in the future. In the figure, 6 is a shaft connecting the upper tunnel 1 and the surface of the ground A, which will be used for ventilation such as removing paper in the future.

前記地下貯蔵用空洞の掘削に当つては、下部坑道2及び
斜坑道3、3’を作業用坑道として使用し、前記空洞の
掘削硼出は当該空洞から分岐坑道4及び下部坑道2並に
一方の斜坑道3を経て上部坑道1の一方の坑口1aより
硼を搬出することによつて行なわれ、他方の坑口1bよ
り上部坑道1及び斜坑道3′並に下部抗道2を経て分岐
坑道4より空洞に空の運搬車を搬入し、このように循環
作業により砺出作業を遂行するものである。
When excavating the underground storage cavity, the lower tunnel 2 and the inclined tunnels 3 and 3' are used as working tunnels, and the excavation of the cavity is carried out from the hollow by the branch tunnel 4, the lower tunnel 2, and one side. The process is carried out by transporting the boron from one entrance 1a of the upper shaft 1 through the inclined shaft 3, and from the other shaft 1b through the upper shaft 1, the inclined shaft 3' and the lower shaft 2, to the branch shaft 4. An empty transport vehicle is brought into the cavity, and the removal work is carried out through circulation work.

而して地下貯蔵用空洞は第1の空洞B1、第2の空洞B
2、第3の空洞B3・・・の順序で掘削されるが、前記
第1の空洞B1の掘削が完成すると、下部坑道2から掘
進された分岐坑道4をコンクリート壁で閉塞してシール
する。そして前記上部坑道1に連絡するシヤフト5に貯
蔵物質の搬出入装置を取付け、同シヤフト5及び上部坑
道1を介して前記第1の空洞B1を坑外に連絡し、同第
1の空洞B1に対する貯蔵作業を開始するものである。
かくして前記第1の空洞B1に対する貯蔵作業が開始さ
れても、地盤Aに影響を与えない位置での地下貯蔵用空
洞の掘削を行ない、かくして他の空洞の掘削中でも、既
に完成した空洞を貯蔵用に供しながら、順次地下貯蔵用
空洞を仕上げていくものである。また本方法による地下
貯蔵用空洞の掘削作業が完了した後において貯蔵量の増
加が必要となると、上下坑道1,2を左右に延長して、
下部坑道2からの分岐坑道4の掘進及び空洞の掘削を行
うことによつて所期の目的を達成しうるものである。
The underground storage cavities are the first cavity B1 and the second cavity B.
2, the third cavity B3, etc., and when the excavation of the first cavity B1 is completed, the branch shaft 4 dug from the lower shaft 2 is closed and sealed with a concrete wall. Then, a device for transporting stored materials is attached to the shaft 5 that communicates with the upper tunnel 1, and the first cavity B1 is connected to the outside of the mine via the shaft 5 and the upper tunnel 1, and the first cavity B1 is connected to the first cavity B1. The storage operation will begin.
In this way, even if the storage work for the first cavity B1 is started, the underground storage cavity is excavated in a position that does not affect the ground A, and thus, even while other cavities are being excavated, the already completed cavity can be used for storage. The underground storage cavities will be completed one by one as the project progresses. Furthermore, if it becomes necessary to increase the storage capacity after the excavation work of the underground storage cavity is completed using this method, the upper and lower tunnels 1 and 2 are extended to the left and right.
The intended purpose can be achieved by digging a branch tunnel 4 from the lower tunnel 2 and excavating a cavity.

なお前記の方法は地下水位上部の良好な地盤のみならず
、不良地盤にも適用されるものであり、空洞は地盤の状
況に応じ支保工、ロツクボルトエ及び吹込や覆工コンク
リート等で被覆されるものである。また前記各空洞間々
隔は空洞の掘削幅の3〜5倍以上とすることが必要であ
る。更に地下水位に無関係に地下貯蔵用空洞を掘削する
場合には、.地盤A内に貯蔵物質が流出しないように、
被覆構造物が特種目地板止油板やスチールプレートライ
ニング等で防止させるように設計するものである。
The above method is applicable not only to good ground above the groundwater level but also to poor ground, and cavities may be covered with shoring, rock bolts, poured concrete, lining, etc., depending on the ground condition. It is. Further, it is necessary that the distance between the cavities be at least 3 to 5 times the excavation width of the cavities. Furthermore, when excavating an underground storage cavity regardless of the groundwater level,... To prevent stored materials from flowing into ground A,
The covered structure is designed to prevent this with special joint plates, oil stop plates, steel plate lining, etc.

また前記地下貯蔵用空洞は、掘削する場所の地盤の状況
に応じて安定したものでしかもできる限り大きくなる断
面形状を有するように設計されるもので、第3図及び第
4図は夫々その実施例を示すものである。
The underground storage cavity is designed to be stable and have a cross-sectional shape that is as large as possible depending on the ground conditions at the excavation site. This is an example.

本発明においては前記したように、地中に掘削されるべ
き地下貯蔵用空洞より高いレベルに、同空洞と直角方向
に延び、両端坑口において外部に開口する上部坑道を掘
削し、その両端部より斜坑道を掘削し、同斜坑道に連結
させて前記空洞の底部レベルに前記上部坑道と平行に下
部坑道を掘削して前記各斜坑道と上下坑道とによつて囲
繞された立体的作業範囲を形成し、次いで同下部坑道よ
り所要位置毎に分岐坑道を岐出掘進してその先端に所要
断面の地下貯蔵用空洞を掘削し、かくして前記立体的作
業範囲内に地下貯蔵用空洞を並設し、同空洞を前記上部
坑道にシヤフトを介して連結することにより坑外と連絡
せしめるようにしたので、前記空洞の掘削硼を分岐坑道
から順次下部坑道、一方の斜坑道及び上部坑道並にその
一方の坑口を経て坑外に搬出する一方、上部坑道の他方
の坑口より順次同上部坑道、他方の斜坑道及び下部坑道
並に分岐坑道を経て前記空洞に空の作業用車輛を搬入し
、かくして前記空洞の掘削における硼出作業を循環して
行なつて施工能率を著しく向上せしめる。
In the present invention, as described above, an upper tunnel is excavated at a level higher than the underground storage cavity to be excavated underground, extends in a direction perpendicular to the cavity, and opens to the outside at both ends of the tunnel. Excavating a diagonal tunnel, connecting it to the diagonal tunnel, and excavating a lower tunnel parallel to the upper tunnel at the bottom level of the cavity to create a three-dimensional work area surrounded by each of the diagonal tunnels and the upper and lower tunnels. Then, branch tunnels are branched out from the lower tunnel at each required location, and underground storage cavities of the required cross section are excavated at the tips of the tunnels, and underground storage cavities are installed in parallel within the three-dimensional work area. Since the cavity is connected to the upper tunnel via a shaft to communicate with the outside of the mine, the excavation chamber of the cavity is sequentially connected from the branch tunnel to the lower shaft, one of the inclined shafts, the upper shaft, and one of them. On the other hand, an empty working vehicle is carried into the cavity from the other entrance of the upper shaft through the upper shaft, the other inclined shaft, the lower shaft, and a branch shaft, and thus the To significantly improve construction efficiency by performing surfacing work during cavity excavation in a circular manner.

この際前記斜坑道の勾配を適正に選択することによつて
、作業用車輛の進行を円滑ならしめ、能率をより向上し
うるものである。
At this time, by appropriately selecting the slope of the inclined tunnel, the work vehicle can proceed smoothly and efficiency can be further improved.

また本発明においては前記のようにして掘削された地下
貯蔵用空洞と上部坑道との間にシヤフトが連結されるの
で、同シヤフト及び土部坑道を利用して、前記空洞に対
する貯蔵物質の出入が円滑に遂行されるものである。
Furthermore, in the present invention, since a shaft is connected between the underground storage cavity excavated as described above and the upper tunnel, the storage material can be moved in and out of the cavity using the shaft and the Dobe tunnel. It will be carried out smoothly.

また本発明の方法によれば、前記のようにして掘削され
た地下貯蔵用空洞の分岐坑道をシールすることによつて
、同空洞を貯蔵用として使用しながら他の地下貯蔵用空
洞を掘削しうるので経済的に有利である。
Further, according to the method of the present invention, by sealing the branch shaft of the underground storage cavity excavated as described above, other underground storage cavities can be excavated while the same cavity is used for storage. It is economically advantageous.

更にまた本発明は地下貯油場、地下貯水場等の施工に適
用され、多数の地下貯蔵用空洞を並列で掘削する場合に
有効である。
Furthermore, the present invention is applied to the construction of underground oil storage fields, underground water storage fields, etc., and is effective when a large number of underground storage cavities are excavated in parallel.

以上本発明を実施例について説明したが、本発明は勿論
このような実施例にだけ局限されるものではなく、本発
明の精神を逸脱しない範囲内で種種の設計の改変を施し
うるものである。
Although the present invention has been described above with reference to embodiments, the present invention is, of course, not limited to such embodiments, and can be modified in various designs without departing from the spirit of the present invention. .

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の方法によつて施工された地下貯蔵用空
洞及び坑道の斜面図、第2図はその縦断面図、第3図及
び第4図は夫々空洞部分の一部欠截斜面図である。 1・・・・・・上部坑道、2・・・・・・下部坑道、3
・・・・・・斜抗道、4・・・・・・分岐坑道、5・・
・・・・シヤフト、A・・・・・・地盤、Bl,B2,
B3,B4・・・・・・地下貯蔵用空洞。
Fig. 1 is a slope view of an underground storage cavity and a mine shaft constructed by the method of the present invention, Fig. 2 is a vertical cross-sectional view thereof, and Figs. 3 and 4 are partially cut-out slopes of the cavity portion, respectively. It is a diagram. 1... Upper tunnel, 2... Lower tunnel, 3
...Diagonal tunnel, 4... Branch tunnel, 5...
...shaft, A...ground, Bl, B2,
B3, B4...Cavity for underground storage.

Claims (1)

【特許請求の範囲】[Claims] 1 地中に掘削されるべき地下貯蔵用空洞より高いレベ
ルに、同空洞と直角方向に延び、両端坑口において外部
に開口する上部坑道を掘削し、その両端部より斜坑道を
掘削し、同斜坑道に連結させて前記空洞の底部レベルに
前記上部坑道と平行に下部坑道を掘削し、次いで同下部
坑道より所要位置毎に分岐坑道を岐出掘進し、同分岐坑
道の先端に所要断面の地下貯蔵用空洞を掘削し、次いで
同空洞を前記上部坑道にシャフトを介して連結すること
を特徴とする地下貯蔵用空洞の掘削方法。
1. Excavate an upper tunnel at a level higher than the underground storage cavity to be excavated underground, extending perpendicularly to the cavity and opening to the outside at both ends of the tunnel, and excavating a diagonal tunnel from both ends of the tunnel. A lower shaft is connected to the tunnel and excavated parallel to the upper shaft at the bottom level of the cavity, and then branch shafts are dug out from the lower shaft at each required position, and an underground tunnel of the required cross section is drilled at the tip of the branch shaft. A method for excavating an underground storage cavity, comprising excavating a storage cavity and then connecting the cavity to the upper tunnel via a shaft.
JP51000921A 1976-01-07 1976-01-07 How to excavate underground storage cavities Expired JPS5929760B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP51000921A JPS5929760B2 (en) 1976-01-07 1976-01-07 How to excavate underground storage cavities

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP51000921A JPS5929760B2 (en) 1976-01-07 1976-01-07 How to excavate underground storage cavities

Publications (2)

Publication Number Publication Date
JPS5284801A JPS5284801A (en) 1977-07-14
JPS5929760B2 true JPS5929760B2 (en) 1984-07-23

Family

ID=11487137

Family Applications (1)

Application Number Title Priority Date Filing Date
JP51000921A Expired JPS5929760B2 (en) 1976-01-07 1976-01-07 How to excavate underground storage cavities

Country Status (1)

Country Link
JP (1) JPS5929760B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106050305A (en) * 2016-05-30 2016-10-26 安徽省皖北煤电集团有限责任公司含山恒泰非金属材料分公司 Method for storing molten salt based on gob of anhydrite mine

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5484613A (en) * 1977-12-19 1979-07-05 Maeda Construction Offshore underground stockpiling method of crude oil and so on
JPS54116723A (en) * 1978-03-02 1979-09-11 Buooru Pamisu Kenkiyuushiyo Yu Method of building underground crude oil storing facilities by volcanic ash drift

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106050305A (en) * 2016-05-30 2016-10-26 安徽省皖北煤电集团有限责任公司含山恒泰非金属材料分公司 Method for storing molten salt based on gob of anhydrite mine
CN106050305B (en) * 2016-05-30 2018-08-14 安徽省皖北煤电集团有限责任公司含山恒泰非金属材料分公司 A method of fused salt is stored based on Anhydrite Ore goaf

Also Published As

Publication number Publication date
JPS5284801A (en) 1977-07-14

Similar Documents

Publication Publication Date Title
US5112161A (en) Method for excavating and constructing monolithic continuous straight or circular structural walls and a machine for realizing such a method
CN109723443B (en) Tunnel construction method
JPS5929760B2 (en) How to excavate underground storage cavities
JP2000291398A (en) Underground structure and construction method therefor
JPH06306853A (en) Construction of underground structure
KR100990430B1 (en) Construction method for underground structure
JPS6117696A (en) Construction of underground head
JPH04309692A (en) Underground space construction method
JPS6317999B2 (en)
JPH0823266B2 (en) Construction method of underground space
CN213775379U (en) Construction system for small-section ultra-long water delivery tunnel in hard rock stratum
JP2673940B2 (en) How to build a horizontal plate-like structure in the ground
CN105971624A (en) Plate pushing device of channel tunneling machine
JP3748152B2 (en) Tunnel digging method
CN112282773A (en) Construction system and construction method for small-section ultra-long water delivery tunnel in hard rock stratum
JPH0227033Y2 (en)
JPS6272817A (en) Construction of retaining wall concurrently serving as sheathing
CN114165242A (en) Mechanical construction method for hard rock small-section cable tunnel
SU1300084A1 (en) Method of constructing a dam of locally available materials
JPH0650091A (en) Parallel construction method for invert excavating and lining and invert excavator
JPH0771036A (en) Method of constructing vertical slope
JPH03137319A (en) Open shield construction method
JPH0464698A (en) Construction of tunneling space
JP2003027885A (en) Construction method for underground tunnel and underground tunnel
JPH01178675A (en) Construction of basement below existing structure