JPH01178675A - Construction of basement below existing structure - Google Patents
Construction of basement below existing structureInfo
- Publication number
- JPH01178675A JPH01178675A JP63001198A JP119888A JPH01178675A JP H01178675 A JPH01178675 A JP H01178675A JP 63001198 A JP63001198 A JP 63001198A JP 119888 A JP119888 A JP 119888A JP H01178675 A JPH01178675 A JP H01178675A
- Authority
- JP
- Japan
- Prior art keywords
- box
- basement
- existing structure
- construction
- blocks
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title abstract description 23
- 238000000034 method Methods 0.000 claims abstract description 20
- 230000001154 acute effect Effects 0.000 abstract description 3
- 230000001141 propulsive effect Effects 0.000 abstract 1
- 238000009412 basement excavation Methods 0.000 description 13
- 239000000463 material Substances 0.000 description 8
- 238000004891 communication Methods 0.000 description 4
- 238000010586 diagram Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 3
- 239000002689 soil Substances 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 239000004576 sand Substances 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- RYGMFSIKBFXOCR-UHFFFAOYSA-N Copper Chemical compound [Cu] RYGMFSIKBFXOCR-UHFFFAOYSA-N 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000009430 construction management Methods 0.000 description 1
- 239000004035 construction material Substances 0.000 description 1
- 229910052802 copper Inorganic materials 0.000 description 1
- 239000010949 copper Substances 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Residential Or Office Buildings (AREA)
- Working Measures On Existing Buildindgs (AREA)
Abstract
Description
【発明の詳細な説明】
〈産業上の利用分野〉
本発明はヒルや一般住宅等の既設構造物の真下に地下室
を構築する構築技術に関するものである。DETAILED DESCRIPTION OF THE INVENTION <Field of Industrial Application> The present invention relates to a construction technique for constructing a basement directly under an existing structure such as a hill or a general residence.
〈従来の技術〉
既設構造物の地下部に地下室を増改築するに当たり、種
々の構築方法が提案されている。<Prior Art> Various construction methods have been proposed when extending or renovating a basement in the basement of an existing structure.
〈本発明が解決しようとする問題点〉
(イ)従来の地下室の構築技術として、既設構造物をジ
ャキアップし、適切な山留を行った後、床部を直接開削
して施工する技術が存在する。<Problems to be solved by the present invention> (a) Conventional basement construction technology involves jacking up an existing structure, performing appropriate heaping, and then directly excavating the floor. exist.
しかし、この施工技術にあっては工事期間中既設構造物
の利用が制限される。However, this construction technique limits the use of existing structures during the construction period.
また、既設構造物内において工事機械の搬出入が困難と
なる場合が多いことから、各種工事を人力に頼らざるを
得す、施工性が悪いものである。Furthermore, since it is often difficult to move construction machinery into and out of existing structures, various types of construction work must be done manually, resulting in poor workability.
さらにまた、住宅密集地や繁華街等のように近隣の既設
構造物が非常に接近するような現場ては近隣に与える悪
影響の大きさから開削工法による施工が不可能とされて
いる。Furthermore, in areas where nearby existing structures are very close together, such as in densely populated residential areas or downtown areas, it is considered impossible to carry out construction using the open cut method due to the negative impact it would have on the surrounding area.
(ロ)地下室の構築方法として、トンネル式掘削方法を
採用することが考えられる。(b) As a method of constructing a basement, it is possible to adopt a tunnel excavation method.
この方法は、立坑から横方向に向けて鋼矢板や銅製パイ
プ等の仮山留材を設け、これらの仮山留材の内部を掘削
して地下空洞を形成する方法である。In this method, temporary pile retaining materials such as steel sheet piles and copper pipes are provided laterally from a shaft, and the inside of these temporary pile retaining materials is excavated to form an underground cavity.
しかし、このトンネル式掘削方法にあっては、仮山留材
の設置精度が悪いうえに仮山留材間の連絡が不十分であ
ることから、永久構造物用としての採用が見合わされて
いるのが実状である。However, with this tunnel-type excavation method, its use for permanent structures has been postponed due to poor installation accuracy of temporary retaining materials and insufficient communication between temporary retaining materials. This is the actual situation.
また、仮山留材の内側に形成された空洞の内部に場所打
ちコンクリート等による覆工が要求されるため、施工コ
ストが高くつく。Furthermore, since the cavity formed inside the temporary pile retaining material is required to be lined with cast-in-place concrete or the like, construction costs are high.
さらに、覆工の施工時期等を誤ると地盤沈下を誘発し、
厳しい施工管理が要求される。Furthermore, if the lining is constructed at the wrong time, it will cause ground subsidence.
Strict construction management is required.
〈本発明の目的〉
本発明は以上の点に鑑みなされたもので、次のような既
設構造物下への地下室の構築方法を提供することを目的
とする。<Object of the present invention> The present invention was made in view of the above points, and an object of the present invention is to provide the following method of constructing a basement under an existing structure.
(イ)都市部のような地上側が狭い現場でも施工できる
、既設構造物下への地下室の構築方法。(a) A method of constructing a basement under an existing structure that can be constructed even in sites where the ground side is narrow, such as in urban areas.
(ロ)工費の低廉を図れる、既設構造物下への地下室の
構築方法。(b) A method of constructing a basement under an existing structure that can reduce construction costs.
(ハ)住宅密集地での施工に好適な、既設構造物下への
地下室の構築方法。(c) A method of constructing a basement under an existing structure, suitable for construction in densely populated residential areas.
(ニ)合理的に施工を行える、既設構造物下への地下室
の構築方法。(d) A method of constructing a basement under an existing structure that allows for reasonable construction.
く本発明の構成〉
以下を図面を参照しながら本発明に係る地下室の構築方
法について説明する。Configuration of the Present Invention> A method for constructing a basement according to the present invention will be described below with reference to the drawings.
(イ)ブロック
本発明では地下室の構築に当たり、次のようなブロック
をイ吏用する。(a) Blocks In the present invention, the following blocks are used in constructing a basement.
このブロックは、後述するように立坑の構成材として、
および立坑から地下室までの間を連絡する通路の構成材
として、および最終構築物の地下室Aの構成材として使
用するものである。This block is used as a component of the shaft as described later.
It is also used as a component of the passage connecting the shaft to the basement, and as a component of the basement A of the final construction.
ブロックの一例を第2図に示す。An example of the block is shown in FIG.
このブロックは方形体がらなり、平面用ブロック1と角
部用ブロック2の二種類のブロックからなる。This block has a rectangular shape and consists of two types of blocks: a flat block 1 and a corner block 2.
〈口)平面用ブロック
平面用ブロック1はその一面の中央に四部11を有し、
他面は平滑に形成しである。(Exposure) Plane block The plane block 1 has four parts 11 in the center of one side,
The other side is smooth.
ブロック1の四つの各側面には、各ブロック1゜1間を
ボルト3て連結するための連結孔12が開・設しである
。Connecting holes 12 are opened and provided in each of the four sides of the block 1 to connect the blocks 1 to 1 with bolts 3.
(ハ)角部用ブロック
角部用ブロック2は隣り合う二つの面が平滑に形成して
あり、その内部には断面り字形の作業孔21が開設しで
ある。(C) Corner block The corner block 2 has two adjacent surfaces smooth, and has a working hole 21 with an angular cross-section inside.
そして、作業孔21の開口が露出している側の面と底面
および側面にそれぞれ連結孔22が開設しである。Connecting holes 22 are provided on the side surface where the opening of the working hole 21 is exposed, the bottom surface, and the side surface, respectively.
く本発明の作用〉 つぎに地下室の構築方法について説明する。Effect of the present invention> Next, we will explain how to construct a basement.
(イ)発進立坑の構築(第3図) まず既設構造物の近傍に立坑4を構築する。(B) Construction of starting shaft (Figure 3) First, a vertical shaft 4 is constructed near the existing structure.
この立坑4は開削作業に応じて前記平面用ブロック1お
よび角部用ブロック2をボルトで接続して上下端を開放
した函体形に組み立てながら降下させる。The vertical shaft 4 is lowered while assembling the flat block 1 and the corner block 2 into a box shape with open upper and lower ends by connecting them with bolts in accordance with excavation work.
立坑4が所定の深度まで到達したら、立坑4の底面にス
ラブ版41を構築する。When the shaft 4 reaches a predetermined depth, a slab version 41 is constructed on the bottom of the shaft 4.
この立坑4の開設中は、大きくとる必要はな(、少な(
とも平面用ブロック1および角部用ブロック2を搬入で
きる寸法であれば良い。During the opening of this shaft 4, there is no need to make it large (, small (
Both dimensions may be sufficient as long as they can accommodate the plane block 1 and the corner block 2.
(ロ)推進施設の配備(第4図)
つぎに立坑4の側面を構成する一部の平面用ブロック1
を撤去して、掘進方向へ向けて鋼板製のフート板5を固
定する。(b) Deployment of propulsion facilities (Fig. 4) Next, some plane blocks 1 forming the side of the shaft 4
is removed, and a foot plate 5 made of a steel plate is fixed facing the excavation direction.
また、立坑4内の底部および側部に、掘進方向へ向けて
複数の推進用の、リンダ6を配備する。Further, a plurality of cylinders 6 for propulsion are provided at the bottom and sides of the shaft 4 in the direction of excavation.
ン
さらに前面を鋭角に形成した先導函7を立坑4内で組み
立てる。Further, a leading box 7 having an acute angle in the front is assembled in the shaft 4.
先導函7は前記平面用ブロック1や角部用ブロック2を
使用して組み立てる。The leading box 7 is assembled using the flat block 1 and the corner block 2.
先導函7は、その前面が鋭角に形成してあれば他の部材
からなる函体であっても良い。The leading box 7 may be a box made of other materials as long as its front surface is formed at an acute angle.
先導函7を掘進方向へ向けて配置したら、先導函7の掘
削範囲に渡って立坑4の側面を構成する平面用ブロック
1を撤去する。Once the leading box 7 is placed facing the direction of excavation, the flat block 1 forming the side surface of the shaft 4 over the excavation range of the leading box 7 is removed.
(ハ)掘進開始(第1.4図)
各シリンダ6を伸長操作して先導函7の先端を他山に貫
入させ、先導函7内に露出する地山を掘削し、掘削した
土砂を立坑4外へ排上する。(c) Start of excavation (Fig. 1.4) Extend each cylinder 6 to make the tip of the guide box 7 penetrate into another mountain, excavate the ground exposed inside the guide box 7, and transfer the excavated earth and sand to the shaft. 4 Drain outside.
先導函7を地中に貫入し終えたら、シリンダ6を収縮す
る。After penetrating the guide box 7 into the ground, the cylinder 6 is contracted.
つぎに平面用ブロック1および角部用ブロック2を立坑
4内に搬入する。Next, the plane block 1 and the corner block 2 are carried into the shaft 4.
搬入したこれらの両種のブロック1.2を先導函7の尾
端に接続する。These two types of blocks 1.2 carried in are connected to the tail end of the leading box 7.
平面用ブロック1および角部用ブロック2を接続して組
み立てる際、函体の天上部に相当する箇4内で組み付け
る。When connecting and assembling the plane block 1 and the corner block 2, they are assembled within a section 4 corresponding to the top of the box.
は、立坑4内を函体の天上部が閉鎖することを防止して
立坑4内の空間を有効に活用するためである。This is to prevent the top of the box from closing the inside of the shaft 4 and to effectively utilize the space inside the shaft 4.
従って、両種のブロック1.2を接続した後に排土作業
が阻止されることがなく、しかも作業の安全性が確保さ
れる。Therefore, the soil removal work is not blocked after the two types of blocks 1.2 are connected, and the safety of the work is ensured.
平面用ブロック1および角部用ブロック2の組み付は作
業を終えたら、再びシリンダ6を伸長して掘進作業を再
開する。After completing the assembly of the flat block 1 and the corner block 2, the cylinder 6 is extended again and the excavation work is restarted.
以上説明した掘進工程、排土工程、両種のブロック1.
2群を接続する工程を繰り返して、函体を掘進する。The excavation process, soil removal process, and both types of blocks 1.
Repeat the process of connecting the two groups to excavate the box.
(ニ)地下室の形成(第5図)
既設構造物Bの真下の地下室Aの構築予定位置まで函体
を掘進したら掘進作業を終了し、シリンダ6を撤去する
。(d) Formation of basement (Figure 5) Once the box has been excavated to the planned construction location of basement A directly below existing structure B, the excavation work is completed and cylinder 6 is removed.
本発明では、地下を掘進させた函体の一部を地下室Aと
して利用する。In the present invention, a part of the box dug underground is used as the basement A.
すなわち、多数の平面用ブロック1および角部用ブロッ
ク2群を用いて組み立てた函体の前部を利用し、この函
体の切羽側と立坑4側の面に壁面を組み付けて、地下室
Aを構築する。That is, the basement A is constructed by using the front part of a box assembled using a large number of plane blocks 1 and corner blocks 2, and assembling walls on the faces of the box and the shaft 4 side. To construct.
この壁面の材料は、立坑4から部分的に取り外した平面
用ブロック1および角部用ブロック2群や新たに搬入し
た平面用ブロック1および角部用ブロック2群を用いて
組み付ける。The material for this wall surface is assembled using the plane block 1 and two groups of corner blocks partially removed from the shaft 4 and the plane block 1 and corner blocks 2 groups newly brought in.
また、立坑4および立坑4から地下室Aまでの間を連絡
した通路は、原則として掘削土砂等を用いて埋め戻す。In addition, the shaft 4 and the passage connecting the shaft 4 to the basement A are, in principle, backfilled with excavated earth and sand.
= 7 −
地上側への影響がないようであれば立坑4や通路を残し
ておくことも可能である。= 7 - If there is no impact on the ground side, it is possible to leave the shaft 4 and the passage.
(ホ)地下室への連絡(第5図) 絡通路用の開孔を掘削する。(e) Connection to basement (Figure 5) Drill an opening for the trunk passage.
つづいて、連絡通路用位置に対応する地下室Aの天上部
の一部を開口して、既設構造物Bと地下室Aとを連通ず
る。Subsequently, a part of the top of the basement A corresponding to the position for the communication passage is opened to establish communication between the existing structure B and the basement A.
最後に、連絡用通路の仕上げ、階段Cの設置、地下室A
の内装仕上げを行う。Finally, finish the connecting passage, install stairs C, and basement A.
Perform interior finishing.
また既設構造物Bとの連絡口は地下室Aの天上部に限ら
ずに側部であっても良いことは勿論である。Furthermore, it goes without saying that the communication port with the existing structure B is not limited to the top of the basement A, but may be located on the side.
く本発明の効果〉
本発明は以上説明したようになるからっぎのような効果
を期待することができる。Effects of the Present Invention> The present invention can be expected to have the effects described above.
(イ)本発明は既設構造物の近隣がら小形の立坑を構築
し、この立坑から既設構造物の真下へ向けて函体を掘進
する方法である。(a) The present invention is a method of constructing a small shaft near an existing structure and excavating a box directly below the existing structure from this shaft.
従って、地上側が狭い現場であっても容易に施= 8
−
工できる。Therefore, it can be easily applied even in sites where the ground side is narrow = 8
− Can be constructed.
(ロ)函体を組立式のブロック体で構成するため、搬入
や取り扱いに便利なうえ、地下室の構成材として転用が
効く。(b) Since the box is composed of prefabricated blocks, it is convenient to transport and handle, and can also be repurposed as a construction material for basements.
従って、工費の低廉を図れる。Therefore, construction costs can be reduced.
(ハ)重機類等の大型機械を一切必要としないので、密
集住宅地での施工に好適である。(c) Since it does not require any large machinery such as heavy machinery, it is suitable for construction in densely populated residential areas.
(ニ)函体の推進方法を採用したことにより地表面の沈
下を最小に抑制できる。(d) By adopting the box propulsion method, ground surface subsidence can be minimized.
そのため、地盤沈下防止のための仮土留め材料が不要で
あり、経済的に施工できる。Therefore, there is no need for temporary soil retaining materials to prevent ground subsidence, and construction can be done economically.
第1図・本発明の一実施例の説明図であって多数のブロ
ック群からなる函体の掘進時の斜視図
第2図・ブロックの拡大説明図
第3図・立坑の構築時の説明図
第4図:函体の掘進時の縦断面図
第5図:地下室の完成時の縦断面図
図Fig. 1 - An explanatory diagram of one embodiment of the present invention, which is a perspective view of a box made up of a large number of block groups during excavation Fig. 2 - An enlarged explanatory diagram of blocks Fig. 3 - An explanatory diagram of the construction of a shaft Figure 4: Vertical cross-sectional view of the box during excavation Figure 5: Vertical cross-sectional view of the completed basement
Claims (1)
ク体を組み立ててなる函体を推進させ、前記函体の切羽
側と立坑側の各開口部に、ブロック群で壁面を構築して
地下室を構築し、地下室の一部のブロックを取り外して
既設構造物と地下室との間を連通して行う、 既設構造物下への地下室の構築方法。(1) Build a shaft near the existing structure, propel a box made up of a large number of blocks from inside the shaft directly below the existing structure, and separate the face side and shaft side of the box. Constructing a basement under an existing structure by constructing a wall with a group of blocks at each opening to construct a basement, and then removing some blocks from the basement to communicate between the existing structure and the basement. Method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP63001198A JPH01178675A (en) | 1988-01-08 | 1988-01-08 | Construction of basement below existing structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP63001198A JPH01178675A (en) | 1988-01-08 | 1988-01-08 | Construction of basement below existing structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH01178675A true JPH01178675A (en) | 1989-07-14 |
JPH0477105B2 JPH0477105B2 (en) | 1992-12-07 |
Family
ID=11494761
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP63001198A Granted JPH01178675A (en) | 1988-01-08 | 1988-01-08 | Construction of basement below existing structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH01178675A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2018131846A (en) * | 2017-02-16 | 2018-08-23 | エヌエイチパーキングシステムズ株式会社 | Assembling method of transport device and rotational structure |
-
1988
- 1988-01-08 JP JP63001198A patent/JPH01178675A/en active Granted
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2018131846A (en) * | 2017-02-16 | 2018-08-23 | エヌエイチパーキングシステムズ株式会社 | Assembling method of transport device and rotational structure |
Also Published As
Publication number | Publication date |
---|---|
JPH0477105B2 (en) | 1992-12-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH1136338A (en) | Construction method of underground structure | |
JP3930954B2 (en) | Construction method of structure | |
JPH01178675A (en) | Construction of basement below existing structure | |
JP2000291398A (en) | Underground structure and construction method therefor | |
JPS6117696A (en) | Construction of underground head | |
JP2813807B2 (en) | How to build an underground tunnel | |
KR20200145226A (en) | Continuous Steel Material constituting Wall Connected to Plurality of Units and Underground Structure Construction Method Using the Same | |
JPH0249896A (en) | Open shield method and machine thereof | |
JPS6248011B2 (en) | ||
KR102610909B1 (en) | Method and structure of steel pipe propulsion using anchor installation inside steel pipe to prevent sinking | |
JP2004316125A (en) | Work execution method for large sectional tunnel and deformed section shield machine | |
JPS5853321Y2 (en) | Element for mountain retainer | |
JPH0654016B2 (en) | Underground space construction method | |
JPS5919204B2 (en) | Underground excavation method | |
JP3646698B2 (en) | Construction method for underground structures | |
JPS61186623A (en) | Method of building foundation of building | |
JPH0122410B2 (en) | ||
JP2005200875A (en) | Divided box body and construction method for underground three dimensional intersection | |
JPH0428044B2 (en) | ||
JPH0465932B2 (en) | ||
JP2005030061A (en) | Open shield construction method | |
JP2000226980A (en) | Jacking shaft, its construction method and jacking method | |
JP2003027885A (en) | Construction method for underground tunnel and underground tunnel | |
JPH0416622A (en) | Protective structure of underground structure made of concrete and construction method thereof | |
JPH0510084A (en) | Execution method of deeper depth man hole |