JPS59177428A - Construction of formwork for making underground structure - Google Patents

Construction of formwork for making underground structure

Info

Publication number
JPS59177428A
JPS59177428A JP58054596A JP5459683A JPS59177428A JP S59177428 A JPS59177428 A JP S59177428A JP 58054596 A JP58054596 A JP 58054596A JP 5459683 A JP5459683 A JP 5459683A JP S59177428 A JPS59177428 A JP S59177428A
Authority
JP
Japan
Prior art keywords
formwork
underground
concrete
construction method
retaining wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP58054596A
Other languages
Japanese (ja)
Other versions
JPS6313492B2 (en
Inventor
Hiroshi Morimoto
博 森本
Kozo Nishikawa
西川 公三
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP58054596A priority Critical patent/JPS59177428A/en
Publication of JPS59177428A publication Critical patent/JPS59177428A/en
Publication of JPS6313492B2 publication Critical patent/JPS6313492B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ

Abstract

PURPOSE:To easily make out the fitting position of concrete separator on sheathing wall by fixing the connecting screw metal fitting of the concrete separator beforehand to the steel member of the sheathing wall. CONSTITUTION:Prior to the construction of a sheathing wall 2, a connecting screw metal fittings 5 for concrete separators are beforehand fixed to the steel members 1. The steel members 1 are erectedly set at given intervals to form soil columns 2A, and a sheathing wall 2 is constructed. One end of the concrete separator 4 is connected to the metals 5, and the other end of the concrete separator 4 is connected to a formwork 3 for forming an underground structure to form a space A into which concrete for the underground structure is placed between the sheathing wall 2 and the formwork 3.

Description

【発明の詳細な説明】 本発明は、地下躯体工事の一環で、例えばソイルセメン
トを用いた柱列工法や親杭横矢板工法など適宜間隔置き
に鋼材を並置する状態で構築された山止め壁の前記鋼材
と地下躯体作製用型枠との開に亘ってコンクリートセパ
レータを固着連結することにより、g11記山止め壁と
、n11記型枠との間に地下躯体作製用のコンクリート
打股空間を構成する地下躯体作製用型枠施工法に関する
DETAILED DESCRIPTION OF THE INVENTION The present invention is a part of underground framework construction, and is a retaining wall constructed by juxtaposing steel materials at appropriate intervals, for example, using the column row construction method using soil cement or the parent pile horizontal sheet pile construction method. By firmly connecting a concrete separator across the gap between the above-mentioned steel material and the formwork for underground framework production, a concrete placement space for underground framework production is created between the g11 retaining wall and the n11 formwork. Concerning formwork construction method for constructing underground framework.

従偏一般の型枠施′工法においては、前記山止め壁の構
築後における掘削工事に伴々い、その山止め壁の主要構
成部材である前記鋼材に対して、前記セパレータの固着
すべき位置の割出しを行ない、かつそれによって割出し
た位置にセパレータを溶接手段にて固着するといった作
業要領が採用されていたが、これによる場合は、空間的
にみて比較的狭隘な地下作業であること、前記のセパレ
ータ固着位置割出しが人手による墨出しであること、及
び、そのような位置割出しを縦向き姿勢の鋼材に対して
実行するために足場を要すること等が相俟って、作業工
程が多くて能率が悪い上に作業に危険を伴ない、かつ、
位置割出し精度も低い。加えて、漏水の可能性力Vある
場所での横向き溶接であるから、能率面、安全面で一層
不利であるのみならず、溶接部の強度、品質及びセパレ
ータ固着位置精度にも多大な問題を発生し易い欠点があ
った。 殊K。
In the general formwork construction method, as the excavation work is carried out after the construction of the retaining wall, the position where the separator should be fixed to the steel material, which is the main component of the retaining wall, is determined. A work procedure was adopted in which the separator was fixed at the determined position by welding, but this meant that the underground work was relatively narrow from a spatial perspective The above-mentioned separator fixing position indexing is done manually, and a scaffold is required to perform such position indexing on a vertically oriented steel material, which makes the work difficult. There are many steps, inefficiency is high, and the work is dangerous, and
Positioning accuracy is also low. In addition, since welding is carried out horizontally in a place where there is a possibility of water leakage, it is not only disadvantageous in terms of efficiency and safety, but also poses great problems in the strength and quality of the welded part and the accuracy of the separator fixing position. There was a drawback that could easily occur. Special K.

山止め壁が近年多用されているソイルセメントを用いた
柱列工法で構築されるものである場合は、前述の位置割
出しにあたって、先ずソイル柱に対する墨出し、ソイル
柱の研)又はコアー抜きによって前記鋼材表面を露出さ
せるといった工程が加わるため、作業能率面、労力面、
溶接作業面でよシ一層の不利を伴なうものであった。
If the retaining wall is constructed using the column-row construction method using soil cement, which has been widely used in recent years, the above-mentioned positioning process must first be done by marking out the soil column, grinding the soil column, or by coring. Since the process of exposing the surface of the steel material is added, work efficiency, labor,
This was accompanied by further disadvantages in terms of welding work.

本発明は、かかる実情に鑑み、地上での作業工程を付加
する合理的手段によって前述したような従来欠点を一掃
できる地下躯体作製用型枠工法を提案する点に目的を有
する。
In view of the above circumstances, an object of the present invention is to propose a formwork construction method for producing an underground framework that can eliminate the above-mentioned conventional drawbacks by adding a work process above ground.

上記目的達成のために講じた本発明に係る地下躯体作製
用型枠工法の特徴は、前記山止め壁の構築前において前
記鋼材に予めコンクリートセパレータ螺合連結用金具を
固着しておき、山止め壁の構築後、前記金具に前記コン
クリートセパレータを螺合連結する点にあシ、このよう
な特徴を有する本発明の作用及び効果は次の通シである
The feature of the formwork construction method for underground framework production according to the present invention, which was taken to achieve the above object, is that the concrete separator screw connection fittings are fixed to the steel material in advance before the construction of the mountain stop wall. After the construction of the wall, the concrete separator is threadedly connected to the metal fittings, and the functions and effects of the present invention having such features are as follows.

(1) セパレータとの固着連結用金具を、山止め壁構
築前において鋼材に予め固着する先付は手段の採用によ
シ、セパレータ固着位置の割 1出しを、空間的に十分
に広い作業スペースがとれる地上で、かつ、長い鋼材を
横倒しにした姿勢で行なえるから、割出し作業を容易に
能率良くしかも極めて高精度に、かつ安全に実施するこ
とができる。
(1) It is advisable to use a method to pre-fix the metal fittings for fixing the separator to the steel material before constructing the retaining wall. Since the indexing work can be performed on the ground where it is possible to take a long steel workpiece and in a horizontal position, the indexing work can be performed easily, efficiently, with extremely high precision, and safely.

(2)漏水の心配等がない地上において、鋼材横倒1し
姿勢で下向き溶接することによシ、前記金具を鋼材に固
着することができるから、溶接作業の能率向上、安全性
確保が図れるばか夛でなく、溶接部の強度及び品質、位
置精度の安定化が図れる。
(2) By welding the steel material horizontally and downward on the ground, where there is no risk of water leakage, the metal fittings can be fixed to the steel material, improving the efficiency of welding work and ensuring safety. The strength, quality, and positional accuracy of the welded part can be stabilized without being too complicated.

以上(11、+21の相乗によって、施工工事全体とし
て工期短縮、工費低減、品質向上、並びに作業安全性の
確保が達成できるに至)、特に既述のようなソイルセメ
ントを用いた柱列工法で山止め壁が構築されるものにお
いて顕著に有効である。
As mentioned above (the synergy of 11 and +21 has made it possible to shorten the construction period, reduce construction costs, improve quality, and ensure work safety for the entire construction work), especially in the pillar row method using soil cement as described above. It is particularly effective in applications where retaining walls are constructed.

以下本発明施工法の実施例を図面に基づいて工程順に詳
述する。
Examples of the construction method of the present invention will be described in detail below in the order of steps based on the drawings.

[1)  シングル又はダブル式ソイfi/λ−77F
(図外)によル地盤中罠土砂(骨材)とセメントグラウ
トを混合したソイル柱(2A)を相隣るもの同志が互い
に一部ヲツブする状態で列状に造成し、それら各ソイル
柱(2人)内に補強芯材である鋼材(1)(一般的に#
iH形鋼が用いられるが、それ以外鋼管やアングル鋼等
であっても良い)を建込むといったソイルセメントラ用
いた柱列工法をもって第1図で示すような連続出走め壁
(2)を構築する前に、第2図で示すように地上におい
て、前記鋼材(1)を横倒にし、その横倒し鋼材(1)
の一方の7ランジ部中央外面で鋼材長手方向に沿って予
め設定された複数位置に1雌なじ部(5b)付き中空部
材からなるコンクリートセパレータ螺合連結用金具+5
1 tl−下向き溶接手段をもって固着しておく。 こ
のとき、前記金具(5)は、前記鋼材(1)をソイル柱
(2A)内の所定位置く建込んだ状態においてその先端
部(15a)が前記ソイル柱(IA)の外周面近くに位
置する突出長さのものに構成されている。
[1] Single or double type soi fi/λ-77F
(not shown) Soil pillars (2A) made of a mixture of ground trap earth (aggregate) and cement grout are constructed in rows with adjacent ones partially overlapping each other, and each of these soil pillars is (2 people) Inside the steel material (1) that is the reinforcing core material (generally #
Construct a continuous wall (2) as shown in Figure 1 using the column construction method using soil cement, which uses iH-shaped steel, but other materials such as steel pipes and angle steel may also be used. As shown in Fig. 2, the above-mentioned steel material (1) is laid down on its side on the ground,
Concrete separator screw connection metal fittings consisting of a hollow member with 1 female threaded part (5b) at multiple positions set in advance along the longitudinal direction of the steel material on the outer surface of the center of one of the 7 flange parts+5
1 tl- Fix with downward welding means. At this time, the tip (15a) of the metal fitting (5) is positioned near the outer peripheral surface of the soil column (IA) when the steel material (1) is erected at a predetermined position within the soil column (2A). It is constructed with a protruding length.

(2)次に、前記鋼材(1)に先付けした前記各金具(
5)の先端部に雌ねじ部養生用の色付きキャップ(6)
t−冠せた上で、第8図及び第4図で示したように、鋼
材(1)を造成ソイル柱(2人)内にそれが未硬化のう
ちに建込む。 この建込み時、地表面上には第5図で示
すよう釦、鋼材建込み精度、レベル精度を良くするため
の芯決め定規(7)が固定設置されるが、この定規(7
)の前記金具(5)下降移動相当位置には金具(510
通過移動を許す切込溝(7a)が形成されている。
(2) Next, each of the metal fittings (
5) Colored cap (6) for protecting the female thread at the tip
As shown in FIGS. 8 and 4, the steel material (1) is erected into the prepared soil column (2 people) while it is still unhardened. At the time of construction, a centering ruler (7) is fixedly installed on the ground surface as shown in Figure 5 in order to improve the accuracy of the construction of buttons, steel materials, and level accuracy.
) is located at a position corresponding to the downward movement of the metal fitting (5).
A cut groove (7a) is formed to allow passage movement.

(3)銅材(1)の建込みによシ前記の連続山止め壁(
2)が構築されたのちの地下掘削工事に伴なって、第6
図で明示のようにソイル柱(9A)の一部を祈夛、かつ
前記キャップ(6)全撤去した状態で前記金具(5)の
雌ねじ部(5b)に金属ロッド利用のコンクリートセパ
レータ(4)の一端雄ねじ部(4a) t−螺合連結す
る。 このとき、前記セパレータ(4)の長さを前記雌
雄ねじ部(5b)。
(3) For the erection of copper material (1), the continuous retaining wall (
Due to underground excavation work after 2) was constructed, the 6th
As clearly shown in the figure, with a part of the soil pillar (9A) removed and the cap (6) completely removed, a concrete separator (4) using a metal rod is attached to the female threaded part (5b) of the metal fitting (5). One end of the male screw part (4a) T-threaded connection. At this time, the length of the separator (4) is adjusted to the female and male threaded portions (5b).

(4a)Kて調整し、ナツト(8)により固定する。(4a) Adjust with K and secure with nut (8).

一方、前記セパレータ(4)の他端部は、第7図で示す
ように、前記連続山止め壁(21K相対向する状態でか
−)tfa太材19)にて支保される状態で組立てられ
たバタフォーム、メタルフオームなどの地下躯体作製用
型枠(3)に固着連結すること罠よって、前記山止め壁
(2)と前記組立型枠(3)との間に地下躯体作製用の
コンクリート打設空間囚を構成する。
On the other hand, as shown in FIG. 7, the other end of the separator (4) is assembled in a state where it is supported by the continuous mountain retaining wall (21K facing each other) TFA thick timber 19). By firmly connecting to the formwork (3) for making the underground framework such as taba foam or metal form, the concrete for making the underground framework is placed between the retaining wall (2) and the assembly formwork (3). Configure the pouring space prisoner.

以上で型枠施工は完了するが、その後、前記空間(3)
内に適宜配筋金族し、かつ、コンクリートを打設するこ
とによシ、所要の地下躯体を作製するのである。 そし
て、前記型枠(3)は撤去して転用するが、山止め壁(
2)はそのまま残置させる。
The formwork construction is completed with the above, but after that, the space (3)
By arranging reinforcing metal as appropriate and pouring concrete, the required underground framework is created. The formwork (3) is removed and repurposed, but the retaining wall (
2) will remain as is.

以下別の実施例(りいて説明する。Another embodiment will be explained below.

(e4)第8図は、前記山止め壁(2)が、適当間隔置
き罠地中に建込まれたH形鋼材(1)と相隣るH形鋼材
+11 、 +11間に亘って建込まれた矢板(2B)
とから構成される親杭横矢板工法にて構築されたものへ
の適゛用例を示し、前記H形鋼材(1)K前記金具(5
)を地上での下向き溶接作業をもって先付けする。
(e4) Figure 8 shows that the retaining wall (2) is erected between the H-shaped steel members (1), which are placed underground at appropriate intervals, and the adjacent H-shaped steel members +11 and +11. broken sheet pile (2B)
An example of its application to a structure constructed using the main pile horizontal sheet pile method consisting of
) is attached first by downward welding work on the ground.

(ロ)jgQ図は、前記金具+51が雄ねじ部(5c)
付きの軸横部材から構成されたもので、この場合は、養
生用キャップ(6)として有底筒状のものを使用し、か
つ、コンクリートセパレータ(4)と金具(5)との連
結にターンバックルαGを用いることでセパレータ(4
)を緊張状態に固着連結する。
(b) In the jgQ diagram, the metal fitting +51 is the male threaded part (5c)
In this case, a bottomed cylindrical member is used as the curing cap (6), and a turn is used to connect the concrete separator (4) and the metal fittings (5). By using buckle αG, separator (4
) are fixedly connected in tension.

【図面の簡単な説明】 図面は本発明に係る地下躯体作製用型枠施工法の実施例
を示し、第1図は連続山止め壁の概略平面図、第2図は
鋼材の拡大斜視図、第3図は山止め壁の要部平面図、第
4図は第8図の要部拡大図、第5図は鋼材建込み状態の
要部拡大#親図、jge図はセパレータ取付要領を示す
要部拡大平面図、第7図は施工伏at−示す概略平面図
、第8図は別実施例を示す概略平面図、第9図も別実施
例を示す要部拡大平面図である。 (1)・・・・・・鋼材、+21−・・・・・山止め壁
、(3)・・・・・・型枠、(4)・・・・・・セパレ
ータ、(5)・・・・・・螺合連結用金具。 第7図 第8図 コ              1         
     1第 9 ■
[BRIEF DESCRIPTION OF THE DRAWINGS] The drawings show an embodiment of the formwork construction method for producing an underground framework according to the present invention, in which Fig. 1 is a schematic plan view of a continuous retaining wall, Fig. 2 is an enlarged perspective view of steel materials, Fig. 3 is a plan view of the main part of the retaining wall, Fig. 4 is an enlarged view of the main part of Fig. 8, Fig. 5 is an enlarged main part of the main part in the state of steel construction, and JGE drawing shows the separator installation procedure. FIG. 7 is a schematic plan view showing a construction plan, FIG. 8 is a schematic plan view showing another embodiment, and FIG. 9 is an enlarged plan view of main parts showing another embodiment. (1)...Steel material, +21-...Top wall, (3)...Formwork, (4)...Separator, (5)... ...Screw connection metal fittings. Figure 7 Figure 8 1
1st 9th ■

Claims (1)

【特許請求の範囲】 ■ 適宜間隔置きに鋼材(1)全並置する状態で構築さ
れた山止め壁(2)の前記鋼材(1)と地下躯体作製用
型枠+31 (!:の間に亘ってコンクリートセパレー
タ(4)全固着連結することによp1前記山止め壁(2
)と前記型枠(3)との間に地下躯体作製用のコンクリ
ート打設空間囚を桐成す石地下躯体作製用型枠施工法で
あって、前記山止め壁(2)の構築前において前記鋼材
(1)に予めコンクリートセパレータ螺合連結用金具(
5)ヲ固  8着してお酉、山止め壁(2)の構築後、
前記金具(5)にiiT紀コンクリートセパレータ(4
)を螺合連結することを特徴とする地下躯体作製用型枠
施工法。 ■ 前記山止め壁(2)が、ソイルセメントを用いた柱
列工法で構築されたものであル、かつ前記金具(5)は
その先端部(5a)がソイ〃柱(2A)の外周面近くに
位置する突出長さのものである特許請求の範囲第0項に
記載の地下躯体作製用型枠施工法。 ■ 前記山止め壁(2)が親杭横矢板工法で構築された
ものである特許請求の範囲第0項に記載の地下躯体作製
用型枠施工法。 ■ 前記金具(5)が、雌ねじ部(5b)付き中空部材
である特許請求の範囲第0項に記載の地下躯体作製用型
枠施工法。 ■ 前記金具(5)が、雄ねじ部(5C)付き部材であ
る特許請求の範囲第0項に記載の地下躯体作製用型枠施
工法。
[Claims] ■ The steel materials (1) of the retaining wall (2) constructed with all the steel materials (1) placed side by side at appropriate intervals and the formwork +31 (!: for making underground framework). By fully fixing and connecting the concrete separator (4), p1 is connected to the retaining wall (2).
) and the formwork (3) to form a concrete casting space for producing the underground framework. The concrete separator screw connection fittings (
5) After finishing 8th place and building the mountain stop wall (2),
Attach the IIT period concrete separator (4) to the metal fitting (5).
) is a method of constructing formwork for making underground frameworks, which is characterized by screwing and connecting. ■ The retaining wall (2) is constructed by the pillar row method using soil cement, and the tip (5a) of the metal fitting (5) is connected to the outer peripheral surface of the soil pillar (2A). The formwork construction method for producing an underground framework according to claim 0, wherein the formwork is of a protruding length located nearby. (2) The formwork construction method for producing an underground framework according to claim 0, wherein the retaining wall (2) is constructed by a main pile horizontal sheet pile construction method. (2) The formwork construction method for producing an underground framework according to claim 0, wherein the metal fitting (5) is a hollow member with a female threaded portion (5b). (2) The formwork construction method for producing an underground framework according to claim 0, wherein the metal fitting (5) is a member with a male threaded portion (5C).
JP58054596A 1983-03-29 1983-03-29 Construction of formwork for making underground structure Granted JPS59177428A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP58054596A JPS59177428A (en) 1983-03-29 1983-03-29 Construction of formwork for making underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP58054596A JPS59177428A (en) 1983-03-29 1983-03-29 Construction of formwork for making underground structure

Publications (2)

Publication Number Publication Date
JPS59177428A true JPS59177428A (en) 1984-10-08
JPS6313492B2 JPS6313492B2 (en) 1988-03-25

Family

ID=12975109

Family Applications (1)

Application Number Title Priority Date Filing Date
JP58054596A Granted JPS59177428A (en) 1983-03-29 1983-03-29 Construction of formwork for making underground structure

Country Status (1)

Country Link
JP (1) JPS59177428A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100628528B1 (en) 2006-06-30 2006-09-28 주식회사 토펙엔지니어링 건축사사무소 Holding plate assembly for ground protection of earths wall
EP2003251A1 (en) * 2002-09-19 2008-12-17 Sigma Consult GmbH Holder stem

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57197315A (en) * 1981-05-27 1982-12-03 Shozo Yoshida Method and apparatus for sheathing wall work

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57197315A (en) * 1981-05-27 1982-12-03 Shozo Yoshida Method and apparatus for sheathing wall work

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2003251A1 (en) * 2002-09-19 2008-12-17 Sigma Consult GmbH Holder stem
KR100628528B1 (en) 2006-06-30 2006-09-28 주식회사 토펙엔지니어링 건축사사무소 Holding plate assembly for ground protection of earths wall

Also Published As

Publication number Publication date
JPS6313492B2 (en) 1988-03-25

Similar Documents

Publication Publication Date Title
US6027278A (en) Wedge-receiving cavity for an anchor body of a post-tension anchor system
US4219978A (en) Pre-cast reinforced concrete building panel wall structure
CN108729564B (en) Assembled building system
AU2012214539A1 (en) Precast wall panels and method of erecting a high-rise building using the panels
CN210857279U (en) Post-cast concrete temporary support column
WO2002066757A9 (en) A load bearing building panel
JPS59177428A (en) Construction of formwork for making underground structure
US3507084A (en) Tilt-up wall construction
CN206110331U (en) Prefabricated assembly building of lightweight steel construction lightweight concrete
CN114232650A (en) Prefabricated anchor rod frame lattice beam structure and construction process thereof
JP2001032409A (en) Joining method and joining structure of precast reinforced concrete aseismatic wall
KR101895803B1 (en) Housing construction method
CN216689444U (en) Prefabricated stock sash girder construction of assembled
CN108468412A (en) A kind of prefabricated column connected node of inflection point and its assembly method
DE2422586A1 (en) Underground or sunken wall prefabricated concrete component - comprises integral panel and ribs at equal intervals
JPH0314483Y2 (en)
CN217760095U (en) Spacing adjusting device of precast concrete post owner muscle
DE881869C (en) Process for the erection of walls made of straw clay and. like
CN217079458U (en) Floor support plate steel reinforced concrete combined stair
JPH0960194A (en) Precast concrete structure
KR102109900B1 (en) Reinforced Concrete Method and Reinforced Concrete Structure
DE821403C (en) Prefabricated component and method for assembling such components
JPH0868115A (en) Connecting structure for column/beam and construction method for underground skeleton using it
JPH0123614B2 (en)
JPH02236325A (en) Construction method for super-highrise building