JPS5914520Y2 - Arm folding device at the front end of the boom using cables - Google Patents

Arm folding device at the front end of the boom using cables

Info

Publication number
JPS5914520Y2
JPS5914520Y2 JP12632579U JP12632579U JPS5914520Y2 JP S5914520 Y2 JPS5914520 Y2 JP S5914520Y2 JP 12632579 U JP12632579 U JP 12632579U JP 12632579 U JP12632579 U JP 12632579U JP S5914520 Y2 JPS5914520 Y2 JP S5914520Y2
Authority
JP
Japan
Prior art keywords
boom
arm
cylinder
cable
pulley
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP12632579U
Other languages
Japanese (ja)
Other versions
JPS5646665U (en
Inventor
一博 大山
義行 西村
浩 柿本
Original Assignee
株式会社 加藤製作所
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社 加藤製作所 filed Critical 株式会社 加藤製作所
Priority to JP12632579U priority Critical patent/JPS5914520Y2/en
Publication of JPS5646665U publication Critical patent/JPS5646665U/ja
Application granted granted Critical
Publication of JPS5914520Y2 publication Critical patent/JPS5914520Y2/en
Expired legal-status Critical Current

Links

Landscapes

  • Shovels (AREA)

Description

【考案の詳細な説明】 従来車両上にブームシリンダを介し俯仰自在に片持ち支
持されるブームと、該ブームの前端に上下回動自在に枢
着したアームとの間をアームシリンダで連結してなる建
設機械を作業現場へ移動する場合は、別の車両に搭載し
て輸送するのを普通とするが、建設機械が大型になると
、低床トレーラに搭載しても輸送時の最大高さが交通法
規による制限を越えるため、アームに対するアームシリ
ンダの連結を解いて、該アームをブーム下方に折畳まね
ばならない。
[Detailed description of the invention] Conventionally, a boom that is cantilever-supported on a vehicle via a boom cylinder so that it can be raised and lowered freely, and an arm that is pivoted to the front end of the boom so that it can be moved up and down are connected by an arm cylinder. When moving construction machinery to a work site, it is common to transport it by loading it onto another vehicle, but as the construction machinery grows larger, the maximum height during transportation is limited even if it is mounted on a low-floor trailer. In order to overcome the restrictions imposed by traffic regulations, the arm cylinder must be uncoupled from the arm and the arm must be folded under the boom.

本考案はこのような場合に索を用いてブーム前端のアー
ムを折畳む装置に関する。
The present invention relates to a device for folding the arm at the front end of the boom using a cable in such a case.

本考案は車両上にブームシリンダを介し俯仰自在に片持
ち支持されるブームの前端に、アームを上下回動自在に
枢着した建設機械において、ブーム中間部の側壁に取付
けた滑車1と、ブーム起立状態においてその前端より垂
下させたアームのブーム側枢支点より下方の部分とブー
ム後方のブーム枢架基台との間に、滑車1を経由して着
脱自在に張設される索2とを含み、ブーム倒伏時にアー
ムが索2を介してブームに引寄せられるように構成した
ことを特徴とする。
The present invention relates to a construction machine in which an arm is pivotally movable up and down on the front end of a boom that is cantilever-supported on a vehicle via a boom cylinder so that the arm can move up and down. A cable 2 is detachably stretched via a pulley 1 between the lower part of the boom side pivot point of the arm hanging from the front end in the upright state and the boom pivot base at the rear of the boom. It is characterized in that the arm is drawn to the boom via the cable 2 when the boom is lowered.

図は本考案の一実施例を示し、クローラ型走行装置3上
に旋回自在に取付けたブーム枢架基台4は、運転室5と
エンジン6を備え、該ブーム枢架基台4と、これにフー
トピン7により枢架したブーム8基部との間はブームシ
リンダ9により連結されている。
The figure shows an embodiment of the present invention, in which a boom pivot base 4 rotatably mounted on a crawler-type traveling device 3 is provided with a driver's cab 5 and an engine 6, and the boom pivot base 4 and the A boom cylinder 9 connects the base of the boom 8 which is pivoted by a foot pin 7 to the base of the boom 8 .

ブーム8の前端(先端)に枢着10シたアーム11の基
端には、該ブームにシリンダ基端を枢着12シたアーム
シリンダ13のピストンロッド先端が着脱自在のピン1
4により枢着され、ブーム8には、最縮小したアームシ
リンダ13のピストンロッド先端がピン14で止着され
る止着具15を備える。
At the base end of the arm 11 which is pivotally attached to the front end (tip) of the boom 8, there is a pin 1 to which the tip of the piston rod of an arm cylinder 13, whose cylinder base end is pivotally attached to the boom, is detachably attached.
4, and the boom 8 is provided with a fastener 15 to which the tip of the piston rod of the arm cylinder 13 that is most contracted is fixed with a pin 14.

16はアーム11上にシリンダ基端を枢着17シた作動
シリンダで、該作動シリンダ16のピストンロッド先端
には、両側の案内リンク18とリンク19の一端がピン
20により一緒に枢着され、該案内リンク18の他端は
アーム11の両側に枢着21されている。
Reference numeral 16 denotes an operating cylinder whose base end 17 is pivotally mounted on the arm 11. At the tip of the piston rod of the operating cylinder 16, one end of a guide link 18 and a link 19 on both sides are pivoted together by a pin 20. The other end of the guide link 18 is pivotally mounted 21 on both sides of the arm 11.

又リンク19の他端は、アーム11の先端に抜差自在の
ピン22により枢着した工具23に着脱自在に枢着24
され、該工具23はピン22を中心として作動シリンダ
16により回動させられる。
The other end of the link 19 is removably pivoted 24 to a tool 23 which is pivotally connected to the tip of the arm 11 by a removable pin 22.
The tool 23 is rotated about the pin 22 by the actuating cylinder 16.

図示の工具23は固定刃23 aと内蔵した油圧シリン
ダにより開閉される可動刃23 bを備える鋏状切断機
で、ビルディングの各部や鉄筋等を切断。
The illustrated tool 23 is a scissor-shaped cutting machine equipped with a fixed blade 23a and a movable blade 23b that is opened and closed by a built-in hydraulic cylinder, and cuts various parts of the building, reinforcing bars, etc.

破壊する機能を持つ。It has the ability to destroy.

滑車1は第4図に示すようにブームシリンダ9のブーム
側連結ピン25と同軸に、ブーム8のピン受8aに回動
のみ自在に取付けられ、該滑車1を経由する索2の両端
は、第3図実線示のように起立させたブーム8の前端よ
り自重で垂下したアーム11先端のピン22と、ブ二゛
ム後方のブーム枢架基台4上に設けたフック26に着脱
自在に係止される。
As shown in FIG. 4, the pulley 1 is rotatably attached to the pin receiver 8a of the boom 8 coaxially with the boom-side connecting pin 25 of the boom cylinder 9, and both ends of the cable 2 passing through the pulley 1 are The pin 22 at the tip of the arm 11, which hangs down by its own weight from the front end of the boom 8 which is erected as shown by the solid line in FIG. It is locked.

図示の索2は後述のアームシリンダ13の付替えにも使
用できるように、アーム折畳みに必要な長さ以上に索長
さを長くしたため、鉄索が経由する滑車27をブーム後
方のブーム枢架基台4上に取付けている。
The cable 2 shown in the figure is made longer than the length required for folding the arm so that it can be used for replacing the arm cylinder 13 (described later). It is installed on base 4.

従ってアームの折畳み時や振出し時の索2は、その両端
が実質上ブーム枢架基台4上の滑車27取付筒所とピン
22に連結されたと同様に機能する。
Therefore, when the arm is folded or swung out, the cable 2 functions in the same manner as if its both ends were connected to the pin 22 and the pulley 27 mounting position on the boom pivot base 4.

アームシリンダ13の付替え装置は、第2図のようにア
ームシリンダ13を最縮小した時のアーム11の先端を
、ブーム8の倒伏により接地させた場合において、該ア
ームの基端上に取付けた滑車28に索2をかけて、鉄索
の一端に着脱自在に取付けたS字状フック29をアーム
シリンダ13のピストンロッドに係合し、又他端を案内
リンク18上端のピン30に着脱自在に係止させ、作動
シリンダ16の伸縮によりアーム11との連結を解いた
アームシリンダ13を該アームへの連結位置と止着具1
5への止着位置との間で上下動し得るようにしてなる。
The arm cylinder 13 replacement device is installed on the base end of the arm 11 when the arm cylinder 13 is fully contracted and the tip of the arm 11 is brought into contact with the ground due to the collapse of the boom 8 as shown in Fig. 2. The cable 2 is hung around the pulley 28, and the S-shaped hook 29 detachably attached to one end of the iron cable is engaged with the piston rod of the arm cylinder 13, and the other end is detachably attached to the pin 30 at the upper end of the guide link 18. The arm cylinder 13 is locked to the arm 11 by the expansion and contraction of the actuating cylinder 16, and the position where the arm cylinder 13 is connected to the arm and the fixing tool 1 are adjusted.
It is configured to be able to move up and down between the fixed position and the fixed position at 5.

31はブームシリンダ9のブーム枢架基台4側の連結ピ
ンを示す。
Reference numeral 31 indicates a connecting pin on the boom pivot base 4 side of the boom cylinder 9.

建設機械のトレーラ輸送に際しては、先ずアームシリン
ダ13と作動シリンダ16を伸長すると共に、ブーム8
を倒して工具23を地面或いは他の輸送車両上に支持さ
せた後、枢着ピン22.24を抜取ってアーム11の先
端から工具23を取脱す。
When transporting construction machinery on a trailer, first extend the arm cylinder 13 and operating cylinder 16, and then extend the boom 8.
After the tool 23 is supported on the ground or other transport vehicle, the pivot pins 22, 24 are removed and the tool 23 is removed from the end of the arm 11.

次でアームシリンダ13の最縮小とブーム8の水平倒伏
とにより第2図のようにアーム11の先端を地面Gに支
持させた後、滑車28にかけた索2をアームシリンダ1
3のピストンロッドとピン300間に張設して、該アー
ムシリンダの重量を索2にかけ、作動シリンダ16の縮
小によって該アームシリンダの先端をアーム11より止
着具15に付替える。
Next, the tip of the arm 11 is supported on the ground G as shown in FIG. 2 by maximally contracting the arm cylinder 13 and horizontally lowering the boom 8.
3 between the piston rod and the pin 300, the weight of the arm cylinder is applied to the cable 2, and the tip of the arm cylinder is replaced from the arm 11 to the fastener 15 by contracting the operating cylinder 16.

次でアームシリンダ13とピン30の間に張設した索2
を取除き、第3図実線示のようにブーム8を起立させて
、該ブーム前端より垂下したアーム11のピン22とフ
ック26の間に、滑車1,27を経由させた索2を張設
した後、ブームシリンダ9を縮小してブーム8を同図鎖
線示の位置に倒伏させる。
Next, the cable 2 stretched between the arm cylinder 13 and the pin 30
The boom 8 is raised as shown by the solid line in Figure 3, and the cable 2 is stretched between the pin 22 of the arm 11 hanging from the front end of the boom and the hook 26 via the pulleys 1 and 27. After that, the boom cylinder 9 is contracted to lower the boom 8 to the position shown by the chain line in the figure.

そうすれば滑車1.フートピン7間の距離は一定である
に対し、滑車1,27間の距離はブームの倒伏につれ次
第に増大するから、アーム11は同図鎖線示のようにブ
ーム8の下方に引寄せられる。
Then pulley 1. While the distance between the foot pins 7 is constant, the distance between the pulleys 1 and 27 gradually increases as the boom is lowered, so the arm 11 is drawn below the boom 8 as shown by the chain line in the figure.

そこでブーム8とアーム11の間を着脱自在のタイロッ
ド32で連結する。
Therefore, the boom 8 and the arm 11 are connected by a detachable tie rod 32.

トレーラ輸送後再びアームシリンダ13をアーム11に
連結するに際しては、タイロッド32を取除いてブーム
8を起立させた後、滑車1やフック26等より索2を脱
し、次でブーム8を倒してアーム11の先端を接地させ
た後、クローラ3を後進させながらブーム8を更に倒伏
して、該ブームとアーム11を第2図の姿勢に戻し、滑
車28にかけた索2をアームシリンダ13とピン30間
に張設して、作動してシリンダ16の伸長によって該ア
ームシリンダの先端を止着具15よりアーム11に付替
える。
To connect the arm cylinder 13 to the arm 11 again after transporting the trailer, remove the tie rod 32 and stand the boom 8 up, remove the cable 2 from the pulley 1, hook 26, etc., then fold down the boom 8 and connect the arm 11. After the tip of the boom 11 is grounded, the crawler 3 is moved backward while the boom 8 is further lowered to return the boom and the arm 11 to the position shown in FIG. The end of the arm cylinder is transferred from the fastener 15 to the arm 11 by the extension of the cylinder 16.

以上一実施例について説明したが、本考案は起立したブ
ーム8を倒伏させる際に生ずる滑車1と索2のブーム枢
架基台側連結部分27との間の索長さの増大を利用して
、アーム11をブーム8に引寄せるのであるから、索2
は該アームのブーム側枢支点10より下方の部分に連結
しておけばよいとは明らかである。
Although one embodiment has been described above, the present invention utilizes the increase in the cable length between the pulley 1 and the boom pivot base side connecting portion 27 of the cable 2 that occurs when the boom 8 is brought down from an upright position. , since the arm 11 is drawn to the boom 8, the cable 2
It is clear that it is sufficient to connect the arm to a portion below the boom-side pivot point 10 of the arm.

図示の滑車1をブームシリンダ9のブーム側連結ピン2
5と同軸に取付けたのは、索2が該連結ピン25と干渉
するのを避けるためである。
The illustrated pulley 1 is connected to the boom side connecting pin 2 of the boom cylinder 9.
The reason why the cable 2 is attached coaxially with the connecting pin 25 is to prevent the cable 2 from interfering with the connecting pin 25.

本考案によれば、滑車1を経由した索2の両端を起立し
たブーム8の前後において該ブーム前端より垂下したア
ーム11のブーム側枢支点より下方の部分とブーム枢架
基台4に連結して、鉄索2の長さをブーム起立状態で緊
張させ得る長さとしたから、ブームシリンダ9によるブ
ームの俯仰運動を利用してアームの折畳みや振り出しを
安全に行うことができ、しかもアーム折畳み時にブーム
が倒伏しているため、タイロッド32の着脱も容易とな
る効果がある。
According to the present invention, both ends of the cable 2 passing through the pulley 1 are connected to the boom pivot base 4 to the lower part of the boom-side pivot point of the arm 11 hanging down from the front end of the boom 8 in front and behind the upright boom 8. In addition, since the length of the iron cable 2 is set to a length that allows the boom to be tensioned in the upright state, the arm can be folded and swung out safely by using the upward and upward movement of the boom by the boom cylinder 9, and moreover, when the arm is folded, Since the boom is laid down, the tie rod 32 can be easily attached and detached.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は建設機械全体の側面図、第2図はアームシリン
ダとアーム間の連結解放中における要部の側面図、第3
図はアーム格納中における要部の側面図、第4図は第3
図のX−X断面図で゛ある。 3・・・・・・クローラ型走行装置、4・・・・・・ブ
ーム枢架基台、8・・・・・・フ゛−ム、9・・・・・
・フ゛−ムシリンダ、11・・・・・・アーム、13・
・・・・・アームシリンダ、16・・・・・・作動シリ
ンダ、23・・・・・・工具、25・・・・・・ブーム
シリンダのブーム側連結ピン。
Figure 1 is a side view of the entire construction machine, Figure 2 is a side view of the main parts during connection release between the arm cylinder and arm, and Figure 3
The figure is a side view of the main parts while the arm is retracted, and Figure 4 is a side view of the main parts when the arm is retracted.
This is a sectional view taken along line XX in the figure. 3...Crawler type traveling device, 4...Boom pivot base, 8...Fam, 9...
・Fam cylinder, 11...Arm, 13.
...Arm cylinder, 16...Operating cylinder, 23...Tool, 25...Boom side connecting pin of boom cylinder.

Claims (2)

【実用新案登録請求の範囲】[Scope of utility model registration request] (1)車両上にブームシリンダ介し俯仰自在に片持ち支
持されるブームの前端に、アームを上下回動自在に枢着
した建設機械において、ブーム中間部の側壁に取付けた
滑車1と、ブーム起立状態においてその前端より垂下さ
せたアームのブーム側枢支点より下方の部分とブーム後
方のブーム枢架基台との間に、滑車1を経由して着脱自
在に張設される索2とを含み、ブーム倒伏時にアームか
゛索2を介してブームに引寄せられるように構成したこ
とを特徴とする索を用いたブーム前端のアーム折畳装置
(1) In a construction machine in which an arm is pivoted to the front end of a boom that is cantilever-supported on a vehicle via a boom cylinder so that it can move up and down, a pulley 1 attached to the side wall of the middle part of the boom and a boom includes a cable 2 that is removably stretched via a pulley 1 between the lower part of the boom-side pivot point of the arm hanging from its front end and the boom pivot base at the rear of the boom. An arm folding device at the front end of a boom using a cable, characterized in that the arm is drawn to the boom via a cable 2 when the boom is lowered.
(2)実用新案登録請求の範囲第(1)項記載の索を用
いたブーム前端のア−ム折畳装置において、滑車1をブ
ームシリンダのブーム側連結ピンと同軸に取付けたもの
(2) An arm folding device at the front end of a boom using a rope according to claim (1), in which a pulley 1 is attached coaxially with a boom-side connecting pin of a boom cylinder.
JP12632579U 1979-09-14 1979-09-14 Arm folding device at the front end of the boom using cables Expired JPS5914520Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12632579U JPS5914520Y2 (en) 1979-09-14 1979-09-14 Arm folding device at the front end of the boom using cables

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12632579U JPS5914520Y2 (en) 1979-09-14 1979-09-14 Arm folding device at the front end of the boom using cables

Publications (2)

Publication Number Publication Date
JPS5646665U JPS5646665U (en) 1981-04-25
JPS5914520Y2 true JPS5914520Y2 (en) 1984-04-27

Family

ID=29358216

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12632579U Expired JPS5914520Y2 (en) 1979-09-14 1979-09-14 Arm folding device at the front end of the boom using cables

Country Status (1)

Country Link
JP (1) JPS5914520Y2 (en)

Also Published As

Publication number Publication date
JPS5646665U (en) 1981-04-25

Similar Documents

Publication Publication Date Title
US4138805A (en) Wheeled portable trailer substructure for elevatable drawworks, masts and setback tower
US4523684A (en) Crane tool for attachment to a backhoe arm
CA1088452A (en) Apparatus for loading and unloading railroad cars
US5439343A (en) Mini boom bumper
JP4835209B2 (en) Crane winch removal method and upper swing body
JPS5914520Y2 (en) Arm folding device at the front end of the boom using cables
JP5302928B2 (en) Work machine front attachment
JP2000044173A (en) Jib projecting and storing device of movable crane
JPS5914521Y2 (en) Arm folding device at the front end of the boom using cables
JPS5914519Y2 (en) Arm cylinder replacement device using cables
JP2524537Y2 (en) Multifunctional tunnel construction equipment
JP2824032B2 (en) Boom head attachment / detachment device
JP2000350523A (en) Deforest-working vehicle
JP2781637B2 (en) Jib support rod mounting device for crane
JPH0930778A (en) Jib tensioner in jib crane truck
US4716665A (en) Folding trencher boom
JP2001302181A (en) Jib extension and storage device of mobile crane
JPH048152Y2 (en)
JPS5817794Y2 (en) pile driver
CA2530342C (en) Vehicle for setting utility poles in a remote location
JP2772669B2 (en) Counterweight attachment / detachment device
JPH07109091A (en) Jib unit of tower crane
JPH0128127Y2 (en)
JPH0328069Y2 (en)
JPS6143834Y2 (en)