JPS59109615A - Construction work of continuous underground sheathing wall - Google Patents

Construction work of continuous underground sheathing wall

Info

Publication number
JPS59109615A
JPS59109615A JP21947082A JP21947082A JPS59109615A JP S59109615 A JPS59109615 A JP S59109615A JP 21947082 A JP21947082 A JP 21947082A JP 21947082 A JP21947082 A JP 21947082A JP S59109615 A JPS59109615 A JP S59109615A
Authority
JP
Japan
Prior art keywords
wall
wire
twisted
sheath
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP21947082A
Other languages
Japanese (ja)
Inventor
Junro Aida
合田 潤朗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP21947082A priority Critical patent/JPS59109615A/en
Publication of JPS59109615A publication Critical patent/JPS59109615A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE:To reduce the cost of the construction work of a continuous underground sheathing wall as well as shorten the period of the construction work by a method in which an iron bar cage attached with a twisted PC wire-inserted sheath is inserted into a trench, concrete is placed, and then a prestress is introduced into the twisted PC wire. CONSTITUTION:An iron bar cage 1 attached with a twisted PC wire-inserted sheath 3 is hung down into a wall strench, and concrete 5 is placed. After the strength of the concrete develops, primary excavation 10 is made and the first step strut 6 is laid. A tension is applied to the twisted PC wire 2 by a jack 7 attached to the upper end of the twisted PC wire 2, and a cement-based grout is injected into the sheath 3. After the strength of the grout develops, the twisted PC wire 2 is fixed and a prestress is introduced against a moment by the side pressures entailed at the time of excavation into the on-site reinforced concrete wall 8 for a continuos underground wall.

Description

【発明の詳細な説明】 この発明は、対側圧曲げ耐力を大きくして側圧による変
形を低減させ、必要となる切梁段数を削減してコストダ
ウン並びに工期の短縮を図った新規な連続地下壁山土め
壁の構築工法の提供に係わる。
[Detailed Description of the Invention] This invention is a new continuous underground wall that increases the contralateral pressure bending strength, reduces deformation due to lateral pressure, and reduces the number of required struts to reduce costs and shorten the construction period. Involved in providing construction methods for mountain clay walls.

従来より、連続地下壁山土め壁は、根切時、地盤層(背
側)の側圧を受けて、根切側(腹側)に曲げられるので
、これを所定段数に亘たる切梁で支えることが行われて
いる。
Conventionally, continuous underground walls and earthen walls are bent toward the root cutting side (ventral side) due to the lateral pressure of the ground layer (back side) when root cutting is performed, so this is done by using struts over a predetermined number of steps. Support is being provided.

しかして、切梁段数が増すほど、コスト並びに工期も増
す訳であり、又、当該切梁間に形成の作業用空間の丈も
狭小化して不便である。
However, as the number of struts increases, the cost and construction period increase, and the length of the working space formed between the struts also becomes narrower, which is inconvenient.

本発明は叙上の事情に鑑みなされたもので、その要旨と
するところは、連続地下壁に於ける鉄筋カゴ製作時にP
C鋼線を挿入したシースを、その下端部を背側鉄筋に定
着金物にて固定し、途中切梁仕口部を迂回する鮫様の背
、腹側鉄筋間の蛇行をさせて、最後に当該シース上端部
を背側鉄筋に固定するとした加工を施こし、この鉄筋カ
ゴを掘削溝に挿入してコンクリートを打設し、強度発現
をまって、該POm線に張力を与えてプレストレスを導
入することにより、連続地下壁山土め壁の鉄筋コンクリ
ート壁に根切時の側圧に抵抗する曲げ耐力を付与し、こ
れによって必要となる梁段数を削減し得て、コストダウ
ン及び工期の短縮を図るとした点にある。
The present invention was made in view of the above circumstances, and its gist is that P
The lower end of the sheath into which the C steel wire has been inserted is fixed to the dorsal reinforcing bars with fixing hardware, and the dorsal part is meandered between the dorsal and ventral reinforcing bars, bypassing the joint part of the cut beam, and finally The upper end of the sheath is fixed to the dorsal reinforcing bars, this reinforcing cage is inserted into the excavation groove, concrete is poured, and after waiting for strength to develop, tension is applied to the POm wire to prestress it. By introducing this system, it is possible to give the reinforced concrete walls of continuous underground walls and earthen walls the bending strength to resist the lateral pressure during root cutting, thereby reducing the number of required beam steps, reducing costs and shortening the construction period. This is the point I was aiming for.

以下、これを図にもとづいて詳細に説明する。This will be explained in detail below based on the drawings.

すなわち、第1図は本発明に於ける地下連続壁に於ける
鉄筋カゴ1の縦断詳示図で、図示の如く、POより線2
を挿入したシース3を鉄筋カゴ1に蛇行取付けするもの
で、PGより線2の下端部はプレストレス導入時の反力
となる定着金物4を取付けて、根切時の仮想支点付近の
地下連続壁の背面側鉄筋1aに固定し、途中、切梁仕口
部を迂回する態様に、背、腹側鉄筋間の蛇行を行わせた
うえで、いま一方の上端部はコンクリート打設時にシー
ス内にコンクリートノロが流入しない様にシールを施し
た後に、コンクリート打設天端より長くして、地下連続
壁背面側の鉄筋1aに固定する。
That is, FIG. 1 is a detailed vertical sectional view of a reinforcing bar cage 1 in an underground continuous wall according to the present invention, and as shown in the figure, the PO strands 2
The sheath 3 into which the PG strands have been inserted is installed in a meandering manner to the reinforcing bar cage 1, and the lower end of the PG stranded wire 2 is fitted with a fixing metal fitting 4 that acts as a reaction force when prestress is introduced, and the underground continuity near the virtual fulcrum during root cutting is installed. It is fixed to the reinforcing bar 1a on the back side of the wall, and the back and ventral reinforcing bars are meandered so as to bypass the sill joint part, and the upper end of the other side is inserted into the sheath during concrete pouring. After applying a seal to prevent concrete slag from entering, it is made longer than the top of the concrete pouring and fixed to the reinforcing bar 1a on the back side of the underground continuous wall.

尚、第1図に示す例は、第工段切梁のみの場合を示し、
途中の迂回が存在しない場合である。
The example shown in Fig. 1 shows the case of only the first stage strut,
This is a case where there is no detour on the way.

シース3の中間部3aはなめらかな曲線を保つて地下連
続壁腹側鉄筋1bに固定する。
The middle part 3a of the sheath 3 is fixed to the ventral reinforcing bar 1b of the underground continuous wall while maintaining a smooth curve.

叙上要領にて作製した鉄筋カゴ1を用いて連続地下壁を
構築する要領を第2図に示す。
Figure 2 shows how to construct a continuous underground wall using the reinforcing bar cage 1 manufactured according to the above procedure.

但し、同図は、途中で1つの迂回を有する2段の切梁架
設の場合を示す。
However, this figure shows the case of two-stage strut construction with one detour in the middle.

すなわち、該鉄筋カゴ1を壁溝に吊り降し、コンクリー
ト5を打設する。
That is, the reinforcing bar cage 1 is suspended into a wall groove, and concrete 5 is poured.

コンクリート50強度発現をまって、1次掘削lOをし
、第1段切梁6を架設する。
Waiting for concrete 50 strength to develop, primary excavation lO is carried out, and the first stage strut 6 is erected.

第1段切梁6は、1階床と先行構築して併用することも
あり得る。
The first stage strut 6 may be constructed in advance and used together with the first floor floor.

次に、PCより線2の上端に組付けたオイルジヤツキ7
によって、POより線2に張力を与え、その状態でセメ
ント系グラウトl料をシース3の管内に注入する。
Next, the oil jack 7 attached to the upper end of the PC stranded wire 2
This applies tension to the PO stranded wire 2, and in this state, cement-based grout is injected into the tube of the sheath 3.

セメント系グラウト材料の強度発現をまって、POより
線2の定着作業を行ない、連続地下壁場所打鉄筋コンク
リート壁体8に根切時の側圧によるモーメントに対抗す
るプレストレスを導入する。
Waiting for the strength of the cement grout material to develop, the fixing work of the PO strands 2 is carried out, and a prestress is introduced into the cast-in-place reinforced concrete wall 8 of the continuous underground wall to counteract the moment due to the lateral pressure at the time of root cutting.

プレストレスはボストテンション方式とする。Prestressing shall be done using the boss tension method.

その後、2次掘削、2段切梁9の架設、最終掘削10’
を行なう。
After that, secondary excavation, erection of two-stage strut 9, final excavation 10'
Do this.

叙上の如く、本発明によるならば、連続地下壁場所打鉄
筋コンクリート壁体8は、切梁6.9、仕口部等の支点
間の対側圧曲げ耐力を大きくすることができるので、必
要となる切梁段数は削減され、コストダウン及び工期短
縮が図かり得、さらに上、下切梁間の丈も大きくとり得
て作業上好適である。
As described above, according to the present invention, the continuous underground wall cast-in-place reinforced concrete wall 8 can increase the opposite side compression bending strength between the supporting points such as the struts 6.9 and the joint parts, so that the required The number of struts can be reduced, reducing costs and shortening the construction period. Furthermore, the length between the upper and lower struts can be increased, which is suitable for work.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は第1段切梁のみの場合の地下連続壁に於ける鉄
筋カゴの詳示図、第2図は2段切梁の場合での本発明の
詳細な説明図である。 1・・・鉄筋カゴ  2・・・POより線3−シース 
  7・・・オイルジャツギ発明者     合 1)
潤 朗 出願人  株式会社竹中工務店 ン?z層
FIG. 1 is a detailed diagram of a reinforcing bar cage in an underground continuous wall in the case of only a first-stage strut, and FIG. 2 is a detailed explanatory diagram of the present invention in the case of a two-stage strut. 1... Rebar cage 2... PO stranded wire 3-sheath
7...Inventor of oil jatsugi 1)
Jun Ro Applicant: Takenaka Corporation N? z layer

Claims (1)

【特許請求の範囲】[Claims] 連続地下壁に於ける鉄筋カゴ製作時にPC鋼線を挿入し
たシースを、その下端部を背側鉄筋に定着金物にて固定
し、途中切梁仕口部を迂回する態様の背、腹側鉄筋間の
蛇行をさせて、最後に当該シース上端部を背側鉄筋に固
定するとした加工を施こし、この鉄筋カゴを掘削溝に挿
入してコンクリートを打設し、強度発現をまって、該P
C鋼線に張力を与えてプレストレスを導入することによ
り、連続地下壁山土め壁の鉄筋コンクリート壁に根切時
の側圧に抵抗する曲げ耐力を付与し、これによって、必
要となる切梁段数を削減し得るとしてなることを特徴と
する連続地下壁山土め壁の構築工法。
The lower end of the sheath into which prestressed steel wire was inserted during the fabrication of a reinforcing bar cage for a continuous underground wall was fixed to the back reinforcing bar with a fixing hardware, and the back and ventral reinforcing bars bypassed the joint part of the strut midway. Finally, the upper end of the sheath is fixed to the dorsal reinforcing bars, and this reinforcing cage is inserted into the excavated groove and concrete is poured to develop strength.
By applying tension to the C steel wire and introducing prestress, the reinforced concrete wall of the continuous basement wall and earthen wall is given bending strength to resist the lateral pressure at the time of root cutting, thereby reducing the required number of struts. A method for constructing continuous underground walls and earthen walls, which is characterized by being able to reduce.
JP21947082A 1982-12-15 1982-12-15 Construction work of continuous underground sheathing wall Pending JPS59109615A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP21947082A JPS59109615A (en) 1982-12-15 1982-12-15 Construction work of continuous underground sheathing wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP21947082A JPS59109615A (en) 1982-12-15 1982-12-15 Construction work of continuous underground sheathing wall

Publications (1)

Publication Number Publication Date
JPS59109615A true JPS59109615A (en) 1984-06-25

Family

ID=16735932

Family Applications (1)

Application Number Title Priority Date Filing Date
JP21947082A Pending JPS59109615A (en) 1982-12-15 1982-12-15 Construction work of continuous underground sheathing wall

Country Status (1)

Country Link
JP (1) JPS59109615A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60242215A (en) * 1984-05-17 1985-12-02 Taisei Corp Prestressing work method for underground wall
US5954217A (en) * 1995-05-10 1999-09-21 Tetra Laval Holdings & Finance, S.A. Packaging container and method of manufacturing the same
KR20040012290A (en) * 2002-08-02 2004-02-11 삼성물산 주식회사 shoring structure using prestressed retaining wall and building construction method using the same
CN110258529A (en) * 2019-06-04 2019-09-20 广州穗岩土木科技股份有限公司 A kind of post-tensioned prestressing diaphram wall and its construction method
CN113174931A (en) * 2021-04-30 2021-07-27 中铁六局集团有限公司 Underground continuous wall construction method based on in-situ pipeline protection

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5766223A (en) * 1980-10-06 1982-04-22 Asuku Kenkyusho:Kk Deformation reduction work for landslide protection wall

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5766223A (en) * 1980-10-06 1982-04-22 Asuku Kenkyusho:Kk Deformation reduction work for landslide protection wall

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60242215A (en) * 1984-05-17 1985-12-02 Taisei Corp Prestressing work method for underground wall
JPH0410527B2 (en) * 1984-05-17 1992-02-25
US5954217A (en) * 1995-05-10 1999-09-21 Tetra Laval Holdings & Finance, S.A. Packaging container and method of manufacturing the same
KR20040012290A (en) * 2002-08-02 2004-02-11 삼성물산 주식회사 shoring structure using prestressed retaining wall and building construction method using the same
CN110258529A (en) * 2019-06-04 2019-09-20 广州穗岩土木科技股份有限公司 A kind of post-tensioned prestressing diaphram wall and its construction method
CN110258529B (en) * 2019-06-04 2021-08-17 鑫龙冶建设工程有限公司 Post-tensioned prestressed underground continuous wall and construction method thereof
CN113174931A (en) * 2021-04-30 2021-07-27 中铁六局集团有限公司 Underground continuous wall construction method based on in-situ pipeline protection

Similar Documents

Publication Publication Date Title
JPH0115646B2 (en)
EA002344B1 (en) Cellular stirrups and ties for structural members
CN108330847A (en) A method of open web type masonry arch bridge is reinforced using steel corrugated plating cuff method
JPS59109615A (en) Construction work of continuous underground sheathing wall
KR100403835B1 (en) Reinforcements for bending-moment and shear in the part of reinforced concrete footings and construction method of its using
JPH10102487A (en) Method of introducing prestress into diaphragam wall
KR0150304B1 (en) A method of simultaneously constructing frameworks for floors and basements of a building
JPH0525821A (en) Continuous underground wall and construction method thereof
JP3020343B2 (en) Column base structure using hollow tube and method of constructing the same
JPH0361810B2 (en)
JPH05255943A (en) Construction method for underground skeleton by slide down system
JP2907038B2 (en) Joint structure and joining method between precast beam and column
Cross Post-tensioning in building structures
JPH0988348A (en) Method for constructing foundation beam
JPS6340029A (en) Beam member for prefabricated construction method
SU1040050A1 (en) Method for reinforcing foundation
JP2677159B2 (en) Structure using covered steel tube concrete columns
JPH04189922A (en) Consturction method for underground structure using core section
JPH01214641A (en) Construction of steel-pipe precast concrete pole
JP3457440B2 (en) Building construction method using earth anchor
JP2832785B2 (en) Pier construction method
JPS60173215A (en) Construction work of cast-in-place pile
JPH0337603B2 (en)
JPH0410527B2 (en)
JPH09302653A (en) Construction method of steel pipe reinforcing pile