JPS5879133A - Water pressure testing method - Google Patents
Water pressure testing methodInfo
- Publication number
- JPS5879133A JPS5879133A JP17791881A JP17791881A JPS5879133A JP S5879133 A JPS5879133 A JP S5879133A JP 17791881 A JP17791881 A JP 17791881A JP 17791881 A JP17791881 A JP 17791881A JP S5879133 A JPS5879133 A JP S5879133A
- Authority
- JP
- Japan
- Prior art keywords
- water
- pressure
- test
- water pressure
- additional
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01M—TESTING STATIC OR DYNAMIC BALANCE OF MACHINES OR STRUCTURES; TESTING OF STRUCTURES OR APPARATUS, NOT OTHERWISE PROVIDED FOR
- G01M3/00—Investigating fluid-tightness of structures
- G01M3/02—Investigating fluid-tightness of structures by using fluid or vacuum
- G01M3/26—Investigating fluid-tightness of structures by using fluid or vacuum by measuring rate of loss or gain of fluid, e.g. by pressure-responsive devices, by flow detectors
- G01M3/28—Investigating fluid-tightness of structures by using fluid or vacuum by measuring rate of loss or gain of fluid, e.g. by pressure-responsive devices, by flow detectors for pipes, cables or tubes; for pipe joints or seals; for valves ; for welds
- G01M3/2807—Investigating fluid-tightness of structures by using fluid or vacuum by measuring rate of loss or gain of fluid, e.g. by pressure-responsive devices, by flow detectors for pipes, cables or tubes; for pipe joints or seals; for valves ; for welds for pipes
- G01M3/2815—Investigating fluid-tightness of structures by using fluid or vacuum by measuring rate of loss or gain of fluid, e.g. by pressure-responsive devices, by flow detectors for pipes, cables or tubes; for pipe joints or seals; for valves ; for welds for pipes using pressure measurements
Abstract
Description
【発明の詳細な説明】 本発明は水圧試験方法に関する。[Detailed description of the invention] The present invention relates to a hydraulic testing method.
例えば埋設された水道管路等の容積の大きな被試験物を
水圧試験する場合、従来はj、)、試験物内に充水しt
コ後試験水叩まで加圧し、一定j()1間に゛1′過′
4>の圧力低下の程度によって合否判断を行なっていた
。しかし、かかる試1検方法では、管貨手部や管の微移
動による初期の圧力低下ばかりでなく、ライニングへの
1(ψ水や残留V気の溶解等fこよっても圧力低下が生
ずるたり)、たとえ試a rlil iこ一定期間予備
加圧しても試験峙の圧力(((′、下は避けられず、準
がないため、使用者に不安を与え乙と共に、素人の合否
判定は危険であった。For example, when conducting a hydraulic pressure test on a large-volume test object such as a buried water pipe, conventionally the test object was filled with water and then
After the test, pressurize until the water hits, and exceed 1' in a constant j()1 period.
Pass/fail judgment was made based on the degree of pressure drop in 4>. However, in such a trial inspection method, a pressure drop may occur not only due to the initial pressure drop due to slight movement of the tube handle or pipe, but also due to the dissolution of water and residual V gas in the lining. ), Even if the test is pre-pressurized for a certain period of time, the pressure of the test (((') is unavoidable and there is no standard, so it gives anxiety to the user and it is dangerous for amateurs to judge pass/fail. Met.
また1水出1iii:i人は先に、試験水圧まで加圧し
た後もこの試験水圧を維持する様に水を補給し、この補
給水1”1によって合否判定する方法も](li案した
が、この場合も上述と同(柔に補給水Mの許容範囲の判
定において問題がある。There is also a method of replenishing water to maintain the test water pressure even after pressurizing it to the test water pressure, and making a pass/fail judgment based on this replenishment water. However, in this case as well, there is a problem in determining the allowable range of makeup water M, as described above.
さらに、ライニングへの吸水や不平均力が作用する異形
管の微移IJ1による圧力低下若しくは追加水4.1s
は、ライニング面積や異形管の数から一定の係数によっ
て算出することができるが、残存空気の溶解による圧力
低下若しくは補給水はは、残存空気もtを予じめ知るこ
とはできないので、結局許容範囲を客観的に勾えること
はできなかった。In addition, the pressure drop due to water absorption to the lining and the slight shift of the irregularly shaped pipe IJ1 where uneven force acts, or the additional water 4.1s
can be calculated using a certain coefficient from the lining area and the number of irregularly shaped pipes, but since the pressure drop due to the dissolution of residual air or make-up water cannot be known in advance, the residual air t cannot be known in advance. It was not possible to determine the range objectively.
本発明は、かかる問題点に妃16みて、試h・)j水圧
からの圧力低下や試1彷水圧にするlコめの追加水星の
許芥範1.!+4を客’gJ、l、的に与えて測定前の
合否判11ガを行う水圧試i方11Eを提(J(シよう
とするものであり、試U・(水圧を負荷する1)1■に
試験水圧より若干低い水圧で一定期間予加圧して、試験
初tU−+にJJける被試験物構成部材の敬称1qij
等による4栢変化を予じめ生じさせると共に、う・fニ
ングの1vk水や残留空気の溶解等を安定化させてJ・
コき、その後試動水圧まで加圧すると共にこの予加圧か
ら試験水圧に達するまでの補給水星を測定し、こ0)補
給水量から残留空気量を算出して試験期間にJ、Sける
残留空気の溶解による1王力(!jg下若しくはHl(
験水圧にするための追加水量を算出し、これをt+li
+l−L/た1;′1容rllii囲によって測定値
の合否判断を行うものである。The present invention has been developed in view of these problems, and has been developed to reduce the pressure drop from the water pressure in the test and to allow additional water to be added to the water pressure in the test. ! +4 to the customer'gJ,l, and perform the pass/fail test 11 before measurement. ■Prepressurize for a certain period of time at a water pressure slightly lower than the test water pressure, and at the beginning of the test tU-+ JJ
In addition to causing 4 heat changes in advance due to the
After that, pressurize to the test water pressure and measure the make-up water from this pre-pressurization until the test water pressure is reached. 0) Calculate the amount of residual air from the make-up water amount and calculate the residual air in J and S during the test period. 1 royal power (!jg lower or Hl (
Calculate the amount of additional water required to reach the test water pressure, and calculate this as t+li
The pass/fail judgment of the measured value is made based on +l-L/ta1;'1 volume rllii.
次に、本発明の実施例を図面に基づいて説明する。第1
図は2hl以下のモルタルライニングを施さ〕1.た水
通11′’!’路に対1′る圧力管理による水圧試験O
)タイヤグラムを示す。この第1図に示す実施例におい
ては、工程(a)で排気状態を7i+?i 誌1ノなが
ら徐々に充水を行い、次いで工程(+))で空気弁を開
放状態にしたま5イ)ずかづつ紹永して空気抜きを行い
、その後工程(c)で空気弁をIJ7]じて水圧が試験
水圧ip)よりわずかに低い水圧(p−Jp)になるま
で給水して予加圧する。次に、この予加圧状態を一定期
間(例えば24時間)閉鎖状態で保持する。この予加圧
保持工11(d)で管)1木手及び管の倣移!I!Ij
lこよる内賽積の変化が屏の初期において起こり、また
ライニングの吸水、残留空気の水への溶解や不平均力の
かかる異形管の微移動等の現象が安定化する。Next, embodiments of the present invention will be described based on the drawings. 1st
The figure shows mortar lining of less than 2 hl]1. Tamizudori 11''! Water pressure test by pressure management against road
) shows the tire gram. In the embodiment shown in FIG. 1, the exhaust state is set to 7i+? in step (a). i) Gradually fill water with the magazine 1, then open the air valve in step (+)), remove air little by little, and then open the air valve in step (c). IJ7], then pre-pressurize by supplying water until the water pressure becomes a water pressure (p-Jp) slightly lower than the test water pressure ip). Next, this pre-pressurized state is maintained in a closed state for a certain period of time (for example, 24 hours). With this pre-pressure holding process 11(d), pipe) 1 wood handle and pipe copy transfer! I! Ij
This change in internal volume occurs at the early stage of the folding process, and phenomena such as water absorption by the lining, dissolution of residual air into water, and micro-movement of irregularly shaped pipes subjected to uneven forces are stabilized.
前記一定期間が経過すると、給水して水圧が(p−Jp
)になるまで加圧し、さらに紡いて工程(e)で試験水
圧(p) lこj(るまで加圧すると共に、水圧が(p
−Jp)から(p)になるまでの補給水量(Qi)を測
定する。After the specified period of time has elapsed, water is supplied and the water pressure reaches (p-Jp).
), further spinning, and in step (e) pressurize until the test water pressure (p) is reached, and the water pressure becomes (p).
- Measure the amount of make-up water (Qi) from (Jp) to (p).
次に、この試験水圧(p)の加圧状態を一定期間(例え
ば24時間)閉鎖状態で保持した水圧試験工程(f)に
入り、上記一定期間経過後圧力値(pl+ )を計測す
る。そして、計測が終ると、排水工)ffi! (g)
で管路内からυ1:水して試験を終了する。Next, a water pressure test step (f) is entered in which the test water pressure (p) is maintained in a closed state for a certain period of time (for example, 24 hours), and the pressure value (pl+) is measured after the certain period of time has elapsed. Then, when the measurement is finished, the drainage works) ffi! (g)
Then υ1: water is poured from inside the pipe and the test is completed.
上記実測圧力値(ph′)o)合否判断は、次の様にし
て求められる許容圧力値(pk )との比較で、[11
11≧pkで合格、pb (pkで不合格と判断する。The above actually measured pressure value (ph')o) pass/fail judgment is made by comparing it with the allowable pressure value (pk) obtained as follows [11
11≧pk, pass, pb (pk, fail.
許容圧力値(pk)の算出に当っては、まず実測圧力値
(ph)から試験圧力顧まで加圧するに8列とする理論
追加水星を算出する。追加水を必要とする要因としては
、ライニングの吸水による追加水量Qcと、残留空気の
水への溶解による追加水MQaと、不平均力のかかる異
形管の微移動による追加水ff1Qbとがある。Qcは
、単位長さ当りのライニング面i に (kgAn)と
管路長Q功の相に実験的に得られる係数を掛けることに
よって算出でき、次の(1)式の如く与えることができ
る。In calculating the allowable pressure value (pk), first calculate the theoretical additional mercury, which is assumed to be 8 columns for pressurizing from the measured pressure value (ph) to the test pressure value. Factors that require additional water include an additional amount of water Qc due to water absorption by the lining, additional water MQa due to dissolution of residual air into water, and additional water ff1Qb due to slight movement of the irregularly shaped pipe to which uneven force is applied. Qc can be calculated by multiplying the lining surface i per unit length (kgAn) and the phase of the pipe length Q by a coefficient obtained experimentally, and can be given as in the following equation (1).
Qc= 0.0007− G −L−・・・・・(1)
Q11管内の残留空気量Va(aと試験水1:1′−p
(kQ/cd)とから実験的に得られる次の(2)式
で与えられ、その残留空気量Vaは、ΔI〕の加圧に要
した補給水量Qi(の、水の体積圧縮蔓β(= 4.8
4 X 1O−5)及びtg内bり積w (ffiによ
り(3)式で与えら1、る。Qc=0.0007-G-L-...(1)
Q11 Residual air amount in the pipe Va (a and test water 1:1'-p
(kQ/cd), and the residual air amount Va is given by the following equation (2) obtained experimentally from = 4.8
4 X 1O-5) and the internal tg product w (1, which is given by formula (3) by ffi.
Qa−−四158゛v札 316161.。Qa--4158゛V bill 316161. .
、(2゜p −1−1
va== (Qi二 ・W・ΔI))(p−IJ+IX
p+1) 、、、0.、(3゜Jp
ここで、(3)式は管内残留空気量をVaとして圧力a
がpのときの管内水量0+ −(w−菅(1+βp)と
Va
p−Jpのときの管内水量(ン2−(w 、)Jp−1
−1)(i十β(p−29月との差Ql−02が補給水
量Qiに等しいとおいた式からVaを求めることによっ
て得られる。, (2゜p −1−1 va== (Qi2・W・ΔI))(p−IJ+IX
p+1) ,,0. , (3゜Jp) Here, equation (3) calculates the amount of water in the pipe when the residual air amount in the pipe is Va, the amount of water in the pipe when the pressure a is p, and the amount of water in the pipe when the pressure a is p. 2-(w,)JP-1
-1) (i 10 β (p-29) It is obtained by finding Va from a formula in which the difference Ql-02 from September is equal to the replenishment water amount Qi.
Qbは、不平均力のかかる異形管部の数Nと管の外径り
の々とから実験的に得られる(4)式で与えられる。Qb is given by equation (4), which is experimentally obtained from the number N of irregularly shaped pipe sections to which the unbalanced force is applied and the outer diameter of the pipe.
Ql) = 0.157・N−D2 ・・・・・・
・・・(4)かくして、追加水量の理論値銅は、
Qm =Qc+Qa+Qb −−−=
(5)で与えられ、許容追加水量Qkは補正係数f
(−1,2)を掛けて
Qk = f−Qm −−(Q)で与えら
れる。そして許容圧力pki;j bこの許容追加水量
Qkと前記残留空気1ii; Va及び1.1(動圧力
pから、次の(7)式でJlえられる。すなわち、(7
)式は試験開始時の状態から許容追加水fH’j、Ql
[をt′i・内から排除したときの圧力が許容圧力F1
(でihるとす/)ことによって Va−一エーQk
が成人ン、ち、これからpkp+1 pk+1
を求めることによって得られる。Ql) = 0.157・N-D2 ・・・・・・
...(4) Thus, the theoretical value of the additional water amount is Qm =Qc+Qa+Qb ---=
(5), and the allowable additional water amount Qk is the correction coefficient f
Multiplying by (-1, 2), it is given by Qk = f-Qm --(Q). Then, the allowable pressure pki; j b This allowable additional water amount Qk, the residual air 1ii;
) formula is the allowable additional water fH'j, Ql from the state at the start of the test.
The pressure when [ is removed from t′i・ is the allowable pressure F1
(deihtosu/)by Va-1AQk
As an adult, pkp+1 can be obtained from this by calculating pk+1.
」計1 ) °V a r ・・・・・・・・・
(7)p”””(p−t−1)Qk十Va
こうして与えら才するr1客F」三方(IH’r (p
k )により」二記の如く実測圧力値(1)11 )の
合否を判定し、合格の場合はμノ(験は完了し、不合格
の場合は空気弁、θlつ吐弁、 1ilij端蓋弁等か
らの漏れ及び管路の異常を調査・俤′認し、適正な処F
、lをした後、出i1試l!′!iJを行う。”Total 1) °V a r ・・・・・・・・・
(7)p"""(p-t-1)Qk10Va In this way, r1 customer F'3 (IH'r (p
Judgment is made on whether the measured pressure value (1) (11) passes or fails as described in 2. If it passes, the test is completed, and if it fails, the air valve, θ1 discharge valve, and 1ilij end cover are Investigate and confirm leaks from valves, etc. and abnormalities in pipelines, and take appropriate action.
, After doing l, exit i1 exam l! ′! Do iJ.
第1図の実施例は圧力管理による水圧試験であっtこが
、追加水量輸]■11による水LIE f!1’Q馳で
も同松に実M11できる。例えば、第2図に示す様に、
第1図と同様の工程で水圧試験工程(f)+こ入り、そ
の一定で給水加圧し、その際に必要とした追加水JJ’
k (Qh )を計1111する。そしてこの実11t
lJ追加水量(Qll)と前記(6)式で与えら1、る
l許容追加水量(Qk)とを比較しQh≦Qkで合格、
Qll > Qkで不合イ・’?Sとする。The embodiment shown in Fig. 1 is a water pressure test using pressure control, but the water LIE f! Even with 1'Q, you can get M11 on the same pine tree. For example, as shown in Figure 2,
In the same process as shown in Fig. 1, the water pressure test step (f) is carried out, and the water supply is pressurized at a constant level, and the additional water JJ' required at that time is
k (Qh) is 1111 in total. And this fruit 11t
Compare lJ additional water volume (Qll) and allowable additional water volume (Qk) given by equation (6) above, and pass if Qh≦Qk.
Qll > Qk does not match.'? Let it be S.
さらに第3図の如く、第1図と同様の工程で予加圧保持
工程(d)に入ると共に、この予加圧保持工程(d)で
一定期間水圧が(p−Δp)に維持される碌に、水圧が
低下した場合に直ちに水を補給し、一定期間が経過する
と加圧工程(e)で試験水圧φ)になるまで加圧すると
共にその補給水u(Qi)を測定し、次にこの試験水圧
0)の加圧状態を一定勘間保持する水圧試験工程(f)
iこおいて、水圧が低下すると直ちCζ水を追加して水
圧が試験水圧(p)tこ紀持される様にすると共に、そ
の圧力維持に要した追加水量(Qh )を計測し、この
実測追加1t(Qh)とJ′(−容追加水星(Qk )
とを比較し、Q11≦Qkで合格、 Qll〉Qkで不
合格と判定する試馴)方法としても実施できる。Further, as shown in Fig. 3, the prepressure holding step (d) is entered in the same process as Fig. 1, and the water pressure is maintained at (p-Δp) for a certain period of time in this prepressure holding step (d). If the water pressure decreases, water is immediately replenished, and after a certain period of time, the pressure is increased in the pressurization step (e) until the test water pressure φ) is reached, and the replenishment water u (Qi) is measured. Water pressure test step (f) in which the pressurized state of this test water pressure (0) is maintained for a certain period of time.
When the water pressure drops, Cζ water is immediately added to maintain the water pressure at the test water pressure (p)t, and the amount of additional water (Qh) required to maintain the pressure is measured. This actual measurement addition 1t (Qh) and J' (-additional Mercury (Qk)
It can also be implemented as a test-taking method in which it is determined that Q11≦Qk passes, and Qll>Qk fails.
なお、この場合、理論追加M Qnとして前記(5)式
のかわり1こ次の(8)式を採用することにより正確な
判断を行う。In this case, accurate judgment is made by employing equation (8) of one order instead of equation (5) as the theoretical addition M Qn.
Qm = Qc+Qa−1−Qb+Qt
−−= (+1)ここで、Qtは水圧試験工程(f
)の前後の水温差による水及び残留空気の熱膨張収縮に
基づく追加水量であって、水圧試験前後の水z1.11
差ΔT (’C)及び管内容積W(のから次の(9)式
で与えられる。Qm = Qc+Qa-1-Qb+Qt
−−= (+1) Here, Qt is the hydraulic test process (f
) is the amount of additional water based on the thermal expansion and contraction of water and residual air due to the difference in water temperature before and after the water pressure test, and is the amount of water before and after the water pressure test.
It is given by the following equation (9) from the difference ΔT ('C) and the intraluminal volume W (.
Qt −± (1,2X 10−’ w +8.4
X10−’ 工)Δ′1゛°°°(9)1)11
なお、以上の実施(’lではモルタルライニングを施し
た水道管路の水圧試ムj!について説明したが、本発明
はその他、例えばライニングや異型管を有しない管路に
も]雇用し得ることは明らかであり、その場合は理論追
加水fit Qnllよ残留空気の溶解(こよる追加水
m Qa7どけとなる。一方、本発明は各抽プラント等
の水圧試験1こもが1川し復、その場合理、1lllj
来
追加AfflQ削ハ前記(5)式の項]」を適宜選択し
かつ必要な要因についてのJ負目を追加して算出すれば
良()。Qt −± (1,2X 10−' w +8.4
X10-' Engineering) Δ'1゛°°° (9) 1) 11 Although the above implementation ('l) described the hydraulic test j! of a water pipe lined with mortar, the present invention is applicable to other It is clear that it can also be used, for example, for pipelines without lining or irregularly shaped pipes. The invention is based on the water pressure test of each extraction plant, etc.
The calculation can be performed by appropriately selecting the ``additional AfflQ term in the equation (5)'' and adding the J negative value for the necessary factors ().
本発明の水圧試験方法によれば、以上の説明から明らか
な様に、試験水圧よりわずかに低い水圧で予加圧し、こ
の予加圧から試験水圧に加圧する際に必要としたh[1
給水量から残留空気量をLL出し、この残留空気の溶解
による圧力低下ないし追加水量を拙償した許谷圧力値若
しくは許容追加水量と実測値との比較(こよって合否判
断するので、客観的な基準に基づく正確な判11jrが
可能となる。According to the water pressure test method of the present invention, as is clear from the above explanation, prepressurization is performed at a water pressure slightly lower than the test water pressure, and the required h [1
Calculate the amount of residual air (LL) from the amount of water supplied, and compare the actual pressure value or allowable additional water amount, which compensates for the pressure drop due to the dissolution of the residual air or additional water amount, with the actual value (this is how you judge pass/fail, so it is an objective method. Accurate judgment 11jr based on the standard becomes possible.
第1図乃至第8図はそれぞt]本発明方法の実施例のダ
イヤグラムである。
(a)・・・充水工程、(b)・・・空気抜き工程、(
c)・・・予加圧工程、(d)・・・予加圧保持工程、
(e)・・・加圧工+d、(f)・・・水圧試験工程、
軌)・・・排水工程
代理人 森本義弘1 to 8 are diagrams of embodiments of the method of the present invention. (a)... Water filling process, (b)... Air venting process, (
c)...Pre-pressure step, (d)...Pre-pressure holding step,
(e)...Pressure process + d, (f)...Hydraulic pressure test process,
(Ki)...Yoshihiro Morimoto, wastewater engineering agent
Claims (1)
より若干低い水圧まで予加圧し、この予加圧状態を一定
期間閉鎖状#jFもしくは圧力維持状f占で保持し、そ
の後試験水圧まで加圧すると共にnII記予加圧から試
験水圧に達するまでの補給水トtを測定し、この加圧状
態を一定期間閉鎖状しでもしくは圧力維持状1)’(で
保持するとJ−Cに、この一定ル1間経過後、その間の
圧力低下量又は011記試験水圧までの加圧若しくは試
験水圧維pl:1こ要し1こ追加水量を測定し、前記補
給水垂から算出した残留空気の溶解による圧力低下若し
くは追加水量をW[酌した許ぺ水圧又は許容追加水14
と前記測定値とから合否を判定することを特徴とする水
圧試験方法。1. Tested! After filling with water on the same day, test 1 (water resistance 1)
Prepressurize to a slightly lower water pressure, maintain this prepressurized state for a certain period of time in closed state #jF or pressure maintenance state f, then pressurize to the test water pressure, and continue from the prepressurization described in nII until reaching the test water pressure. If the make-up water t is measured and this pressurized state is closed for a certain period of time or maintained in a pressure maintenance state 1)' (J-C), after this fixed period of 1 period has elapsed, the amount of pressure drop during that period or 011 Pressurization or test water pressure up to the above test water pressure pl: Measure the additional water volume per 1 pipe, and calculate the pressure drop or additional water volume due to the dissolution of residual air calculated from the replenishment water drop by W [taking into account the water pressure or allowable additional water 14
A water pressure test method, characterized in that pass/fail is determined based on the measured value and the measured value.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP17791881A JPS5879133A (en) | 1981-11-05 | 1981-11-05 | Water pressure testing method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP17791881A JPS5879133A (en) | 1981-11-05 | 1981-11-05 | Water pressure testing method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS5879133A true JPS5879133A (en) | 1983-05-12 |
JPS6322533B2 JPS6322533B2 (en) | 1988-05-12 |
Family
ID=16039337
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP17791881A Granted JPS5879133A (en) | 1981-11-05 | 1981-11-05 | Water pressure testing method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS5879133A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2015140609A1 (en) * | 2014-03-21 | 2015-09-24 | Giamboi Carmelo | Method for the remote detection of leakages in hydraulic circuits, and apparatus thereof |
-
1981
- 1981-11-05 JP JP17791881A patent/JPS5879133A/en active Granted
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2015140609A1 (en) * | 2014-03-21 | 2015-09-24 | Giamboi Carmelo | Method for the remote detection of leakages in hydraulic circuits, and apparatus thereof |
Also Published As
Publication number | Publication date |
---|---|
JPS6322533B2 (en) | 1988-05-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CA2404940A1 (en) | Improved methods for detecting leaks in pressurized piping with a pressure measurement system | |
JPS5879133A (en) | Water pressure testing method | |
RU2062282C1 (en) | Method of repairing heating ducts of coke batteries and apparatus for heating up masonry of heating ducts at their repairing | |
JPS58107225A (en) | Manufacture of double pipe | |
US4359082A (en) | Method and apparatus for hardening mold parts made of sand for making metal castings | |
US4483384A (en) | Apparatus for hardening mold parts made of sand for making metal castings | |
JPH0781619B2 (en) | Oil quantity control device for automatic transmission | |
JP2598303B2 (en) | Continuous injection system for lining resin | |
JP2700328B2 (en) | Repair method for lining of pipe inner surface | |
JPH0810937A (en) | Device for pouring molten non-ferrous metal of constant amount | |
RU2790955C1 (en) | Method for determining capacity of electromagnetic valve | |
JPH0263175B2 (en) | ||
CN108316906A (en) | A kind of modified thick oil steam drive replaces experimental provision and its experimental method | |
KR100871292B1 (en) | Apparatus for manufacturing steam | |
JPH01293167A (en) | Method for repairing lining of inner surface of pipe | |
JPH0722736B2 (en) | Pipe inner surface lining repair method | |
JP2665922B2 (en) | Repair method for lining of pipe inner surface | |
SU796680A1 (en) | Method of fluid-tightness testing of articles | |
JPH01310775A (en) | Construction method for applying lining repairing to inner surface of pipe | |
JPH01310776A (en) | Construction method for applying lining repairing to inner surface of pipe | |
JPS59160733A (en) | Method and device for testing water leakage in piping system | |
JPH0221282B2 (en) | ||
JPS6488334A (en) | Method and device for testing actual machine artificial piping | |
JPH0722738B2 (en) | Pipe inner surface lining repair method | |
JP2005095921A (en) | Casting method and casting apparatus |