JPS5850213A - Erection of panel by floating crane - Google Patents

Erection of panel by floating crane

Info

Publication number
JPS5850213A
JPS5850213A JP14887781A JP14887781A JPS5850213A JP S5850213 A JPS5850213 A JP S5850213A JP 14887781 A JP14887781 A JP 14887781A JP 14887781 A JP14887781 A JP 14887781A JP S5850213 A JPS5850213 A JP S5850213A
Authority
JP
Japan
Prior art keywords
panel
crane
targets
erecting
floating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP14887781A
Other languages
Japanese (ja)
Other versions
JPS6260533B2 (en
Inventor
Takayasu Hosono
細野 高泰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Engineering Corp
Original Assignee
NKK Corp
Nippon Kokan Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NKK Corp, Nippon Kokan Ltd filed Critical NKK Corp
Priority to JP14887781A priority Critical patent/JPS5850213A/en
Publication of JPS5850213A publication Critical patent/JPS5850213A/en
Publication of JPS6260533B2 publication Critical patent/JPS6260533B2/ja
Granted legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/18Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
    • B66C23/36Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes mounted on road or rail vehicles; Manually-movable jib-cranes for use in workshops; Floating cranes
    • B66C23/52Floating cranes

Abstract

PURPOSE:To avoid the application of tortional force to panel structures by speicifically moving a floating crane hanging a panel as the panel is erected when erecting large-size trapezoidal panels constituting the jacket of an oil drilling rig, etc. CONSTITUTION:Under a condition that the barge B of a crane 1 is positioned on the extended line of one inclined side A on the erecting side of a panel A, one inclined side A' is hung up and moved along the circular line of the crane 1 at the crossing point (as center) between one inclined side A' and other inclined side A'' on the grounded side while regulatively moving the crane 1 in such a way that targets 4 and 5 provided to the panel A are in line with targets 2 and 3 provided to the crane 1 on the same level. The barge B and the crane 1 are displaced to an imaginary place and the erection of the panel A is completed.

Description

【発明の詳細な説明】 本発明は海上クレーンのような水上クレーンを用いたパ
ネル建起し方法の創案に係抄、海上クレーンを用いてパ
ネルの建起し吊り上げ、据っけを適切に行わしめ大型ジ
ャケットの如きを的確に製作することのできti法を得
ようとする4のである。
[Detailed Description of the Invention] The present invention relates to the creation of a method for erecting panels using a floating crane such as a marine crane, and the use of a marine crane to properly erect, lift, and install panels. 4. We are trying to obtain a TI method that can accurately produce items such as large-sized jackets.

石油掘削用リグなどを形成する丸めの1つの方式として
ジキケット方式は従来から知られ九と4ろであるが、こ
のような場合における大型ジャケットの知勇を製作する
には従来各列をパネル化し、それ気み4ネルを立体組立
位置において製作し、該パネルを大型クローラクレーン
のような陸上クレーン数基の如角を用いて建て起し、そ
のiまの位置で据付け、これらパネル間を単材搭載によ
って連結させ組立てることが行わ五ている。然しこの↓
うな従来済によると舞は陸上クレーンが一般的にその作
業能力に限界があるためパネルの吊り上げかで傘ないの
でパネル製作は立体組立位置においてなさねばならない
制約を受け、このように組立位置でパネルを製作しそれ
が完成してから建て起して立体組立を行う喪め順次に組
立られるパネルは建て起され・るまでの先行パネルによ
ってその製作域が妨害され、即ち先行パネルの製作組立
てが終るまで隣接した次のパネルの製作に着手できない
こととなるので折角のパネル方式であっても相当の長い
工期を必要とし、更にパネルを製作しその場所で片側を
建て起すので立体組立時のパネル据付は調整が離かしい
などの不利がある。なお前記し九石油掘削用、リグに用
いられる大型ジャケットや鉄塔などの構造物においては
下部が寸法的に大で上部に到るに従い小となることが一
般であることからそのパネルは側面的に台形状とされる
ことが多く、斯様な台形パネルを建て起すに当って琳に
その一側辺を吊ね上げると短辺側が急速に引き起される
のに対し長辺側の引き起し速度が相当に遅い(短辺側の
引き起し半径が小であるのに対して長辺側の引き起し半
径が大舞い)こととな抄、このように引勇起し速度に差
を生ずると該引き起し過程において短辺側に強い引き起
しないし吊上げ力が作用するのに対して長辺側はなお接
地状態となってパネルに捩シカが作用し、充分な強度を
以て連結されていない建て起し過程の該パネル構成部材
連結部を破損ないし変形せしめる可能性が高い。
The Jikiket method has long been known as one of the rounding methods for forming oil drilling rigs, etc., and has nine and four ro, but in order to manufacture a large jacket in such a case, each row has traditionally been made into a panel, 4 panels are manufactured in a three-dimensional assembly position, the panels are erected using several land cranes such as large crawler cranes, and installed at the i position, and a single piece of material is used between these panels. They are connected and assembled by mounting. But this↓
According to the conventional wisdom, land-based cranes generally have limited work capacity and cannot be used to lift panels, so panel production must be done at the three-dimensional assembly position. Panels that are assembled in sequential order are fabricated and then erected after completion for three-dimensional assembly.The production area is obstructed by the preceding panel until it is erected, that is, the fabrication and assembly of the preceding panel is completed. However, even with the best panel method, it is not possible to start manufacturing the next adjacent panel until the panel is installed. has disadvantages such as being difficult to adjust. As mentioned above, in structures such as large jackets and steel towers used for oil drilling and rigs, the lower part is generally large and the upper part becomes smaller, so the panels are It is often made into a trapezoidal shape, and when erecting such a trapezoidal panel, if one side of the panel is lifted up, the short side will be pulled up rapidly, whereas the long side will be lifted up. The speed is quite slow (the pulling radius on the short side is small, while the pulling radius on the long side is large), so the difference in pulling speed can be When this occurs, a strong lifting force acts on the short side during the lifting process, while the long side remains in contact with the ground, causing a torsion to act on the panel and ensuring that it is not connected with sufficient strength. There is a high possibility that the connecting parts of the panel components will be damaged or deformed during the erection process.

即ちこの・ような台形パネルの場合には上記のような[
U)力を与えないように建て起すことが必要であるが、
従来技術においてはこのような関係を適切に解決したも
のi見当らない、。
In other words, in the case of a trapezoidal panel like this one, the above [
U) It is necessary to build up so as not to give force,
In the prior art, there is no solution that appropriately solves this kind of relationship.

本発明は上記しえような実情に鑑み検討を重ねて創案さ
れたものであって、上部したようなパネルの建起しに水
上クレーンを用い、パネルの両端部および浮体上に設け
られた水上°クレーンの浮体における軸線上の如負に夫
々ターゲットを設け、これら4点のターゲットが何れも
直線上に位置するように水上クレーン側を移動調整しな
がらパネルの建起しをなすことを提案するものである。
The present invention has been devised after repeated studies in view of the above-mentioned circumstances, and uses a floating crane to erect panels such as the upper part. °We propose setting targets on each side of the axis of the floating body of the crane, and erecting the panel while adjusting the movement of the floating crane so that these four targets are all located on a straight line. It is something.

即ち水上クレーンによると傘は海上の知勇に浮べられた
浮台を利用してクレーンの移動操作をなすことがで傘る
と共に該クレーンの能力も充分に大角<シたものが用い
られているのが普通であって、例えば3000 トン又
はそれ以上のキャパシティを有するクレーンを採用し得
るものであるから前記したような大型ジャケットなどの
パネルであっても充分に吊り上は操作することがで紮る
と共に該水上クレー/側における位置調整も浮台の浮力
を利用して比較的容易であ抄、本発明においてはこつよ
うな関係゛を有効に活用して有利なパネルの建起゛しを
図ることに成功したものである。蓋し本発明によるもの
の実施態様を添附図面に示すものについて説明すると、
陸上部Aにおいて離村は企さき前記ジャケットのバネル
ムを建起すに当って海上のような水上に浮んだ浮体Bに
よるクレーン1を用いるものであり、しかもこの場合に
おいて前記浮体Bの軸線上の如きに複数のターゲット2
.3を投砂ると共にパネルAにおいてもその両端側に第
3図に示すようなターゲット4.5を設ける。こあパネ
ルムにおけるターゲット4゜5に関しては該パネルAが
建起し、吊上げて所定位置に設定されるものであり、そ
れらの吊上は移動過程においても適切なターゲットとし
ての作用を得しめる九めに可曲条材に垂下され九重錘4
a、Smの如きを用いることがその如何なる過程におい
ても好ましい。パネルムの移動設定操作に関しては上記
のようにパネルムを吊上けた条件下において操作するこ
とが本発明における1つの要件であり、又水上クレーン
1儒に適宜に移動させて該パネルムを所定位置にセット
することがもう1つの要件である。但し吊上げに関して
は特別にな特殊な場合においてはパネルAを完全に離脱
させることなくその一側が接地状態のままで建て起し操
作し得ることは当然であるし、浮体B側においても、そ
のターゲット2,3に関しては特別なターゲット部材を
取付けるまでもなく浮体B又はクレーン1における適当
な部材の角部などをターゲット2,3に代用することが
で轡、このことはパネルA@においても同様である。何
れにしても浮体Bないしクレー71側およびパネルA側
においては夫々複数のターゲット2,3又は4.5を用
いることが必要であゆ、それによって何れの情において
も適正な方向を規定せしめることかで舞、又クレーン1
側の適当な移動によってそれら双方の方向を同一直線上
に合致させることがで舞る。クレーン1におけるパネル
Aの吊上げ位WIK関しては単一の吊上げ位置であって
もよいが、この場谷においてはパネルA側において適当
な補助作業者などによる補助的方向規制操作を必要とす
ることが一般であり、即ち補助作業者によって吊上げら
れたバネルムの方向を適当に補正して据付は位置に導き
、各ターゲット2,3および4゜5を同一直線上に導く
ことが要求される。これに対して第1図又は第2.3図
に示すように複数のクレーン1軸線方向にそった吊上点
6.7を設定し、しかもパネルムにおける岸数の吊抄ピ
ース8.sにおいて吊り上げるならば吊上げられたパネ
ルムが自動的にクレーン嘗の細線方向に合致せしめられ
る。なお浮台Bに設けられたクレーン1はこの種水上ク
レーンにおいては浮台Bに固定されているのが一般であ
り、このようにクレーンアームが固定された条件下にお
いても本発明が適切に夷・施で無、特に浮台B上に投砂
是ターゲット2゛、3を用いて常に的確に操作すること
ができる。
In other words, according to floating cranes, umbrellas are used to move the crane by using a floating platform floating on the sea, and the cranes used have sufficiently large angles. For example, a crane with a capacity of 3,000 tons or more can be used, so even panels such as large jackets as mentioned above can be lifted sufficiently. At the same time, it is relatively easy to adjust the position on the water clay/side by using the buoyancy of the floating platform.In the present invention, this unique relationship is effectively utilized to advantageously erect the panel. This is something that we succeeded in trying to achieve. The embodiments of the invention according to the present invention will be described with reference to the accompanying drawings.
In the land area A, the remote village plans to use a crane 1 with a floating body B floating on water such as the sea to erect the bunel of the jacket, and in this case, on the axis of the floating body B. multiple targets 2
.. 3, and targets 4.5 as shown in FIG. 3 are provided on both ends of panel A. Regarding the target 4.5 in the panel A, the panel A is erected, hoisted and set in a predetermined position, and these hoistings are carried out in a manner that allows them to act as an appropriate target even during the movement process. A nine-fold weight 4 is suspended from a bendable strip.
It is preferable to use a, Sm, etc. in any process. Regarding the movement and setting operation of the panel, one of the requirements of the present invention is to operate it under the condition that the panel is lifted as described above, and also to set the panel at a predetermined position by moving the panel as appropriate in 1 tsp. Another requirement is to do so. However, with regard to lifting, in special cases, it is natural that panel A can be erected and operated with one side of it in contact with the ground without completely detaching it, and also on the floating body B side, the target Regarding 2 and 3, there is no need to attach a special target member, and the corner of an appropriate member of floating body B or crane 1 can be substituted for targets 2 and 3, and this is the same for panel A@. be. In any case, it is necessary to use a plurality of targets 2, 3, or 4.5 on the floating body B or clay 71 side and on the panel A side, respectively, so that the appropriate direction can be defined in any case. Demai, Mata Crane 1
By appropriately moving the sides, it is possible to align both directions on the same straight line. Regarding the lifting position WIK of panel A in the crane 1, it may be a single lifting position, but in this case, an auxiliary direction regulating operation by an appropriate auxiliary worker etc. is required on the panel A side. is common, that is, it is necessary to appropriately correct the direction of the lifted banelm by an auxiliary worker to bring it into position and to bring each target 2, 3 and 4.5 into the same straight line. In contrast, as shown in Fig. 1 or Fig. 2.3, a plurality of cranes are set with lifting points 6.7 along the axial direction, and the number of hanging pieces 8.7 in the panel is set. When lifting at point s, the lifted panel is automatically aligned with the thin line direction of the crane mouth. Note that the crane 1 installed on the floating platform B is generally fixed to the floating platform B in this type of floating crane, and the present invention can be applied appropriately even under such conditions where the crane arm is fixed.・It is possible to always use Targets 2 and 3 to accurately control sand throwing, especially on floating platform B.

上記したよりな本発明によるものはこの種大型ジャケッ
トなどに用−られる側面的に台形をなし九パネルムの建
起しであっても適切に実施で舞る。即ちこの台形パネル
の場合においては建起し時に捩り力が作用し損壊の恐れ
の多いものであることは前記した通りであるが、水上ク
レーンを用いる本発明においては先ず第4図に示すよう
にクレーン1の浮台Bを建起すべきパネルムの引起し側
−側斜辺A′嬌長線上に位置させた状態で該−側斜辺A
′を吊上げ、その吊上げの進行に伴い対称的な台形をな
す該パネルムの地上での横倒状態で前記−側斜辺ム′と
接地側他側斜辺!の交点Oを中心としてクレーン1を第
4図の矢印で示すように水平的な円弧線にそった移動を
行わせ、最終的に第4図で仮想線で示す位置に浮台およ
びクレーン1を変位させた状態として建起しを完了させ
る。即ちこのようにすれば少くとも長辺と短辺との寸法
差が比較的少い台形のパネルの場合において適切なi起
しか得られる。
The above-mentioned structure according to the present invention can be suitably implemented even in the case of a large-sized jacket of this type, which has a trapezoidal shape on the side and has a nine-panel construction. That is, as mentioned above, in the case of this trapezoidal panel, torsional force acts upon it when it is erected, and there is a high risk of damage, but in the present invention using a floating crane, first, as shown in FIG. With the floating platform B of the crane 1 positioned on the elongated line of the - side hypotenuse A' on the lifting side of the panel to be erected, the - side hypotenuse A'
′ is lifted, and as the lifting progresses, the panel, which forms a symmetrical trapezoid, lies sideways on the ground. The crane 1 is moved along a horizontal arc line as shown by the arrow in Fig. 4, centering on the intersection O of The erection is completed in the displaced state. That is, in this way, only an appropriate i-shape can be obtained at least in the case of a trapezoidal panel in which the dimensional difference between the long side and the short side is relatively small.

更に台形パネルAにおける寸法差が比較的大舞い場合に
おいては上記したような手法に加えて第5.6図に示す
ような方法を併用すれば実質的に一ネルムに捩抄力を与
えることのない建起しが得られる。即ちこの場合におい
てはパネルムに用いられるターゲット4゜5に関して平
行四辺形の関係を採用するものであって、このためその
短辺に関しては引起し側の一儒斜辺A′と短辺との交点
におもりを有するターゲット5を取付けるが、長辺側に
おいてはその中間部において前記ターゲツト5取付点か
ら接地側他側斜辺ムにと略平行状態の直線を引いた交点
はターゲット40セツトをなすものである。なお特別な
場合において長辺と一側斜辺にの交点又はそれによ抄近
い位置にターゲット4を取付は九場合にはそれにi当し
た短辺の延長線上にターゲット5を取付けて4よい。即
ちこのようにするならば一側辺ム′と各取付点から垂下
したターゲット4、S及びそれらターゲット取付点を結
ぶ直線で形成された領域は平行四辺形状をなすこととな
るものであり、斯うして取付けられた各ターゲラ)2,
3,4.5が同じ垂直面内に位置する関係を確保して建
て起すならば捩り力の発生を有効に解消することかで^
る。
Furthermore, if the dimensional difference in the trapezoidal panel A is relatively large, using the method shown in Figure 5.6 in addition to the method described above will make it possible to substantially apply torsional force to one panel. No erection is obtained. That is, in this case, the relationship of a parallelogram is adopted with respect to the target 4°5 used for the panelum, and therefore, regarding its short side, the intersection of the short side A' and the short side is A target 5 having a weight is attached, and on the long side, the intersection point of a straight line drawn from the attachment point of the target 5 in the middle part and substantially parallel to the other oblique side of the ground side forms a set of 40 targets. . In special cases, the target 4 may be mounted at the intersection of the long side and one oblique side, or at a position close to the intersection, and in some cases, the target 5 may be mounted on the extension of the corresponding short side. That is, if this is done, the area formed by one side M', the targets 4 and S hanging down from each attachment point, and the straight line connecting these target attachment points will form a parallelogram shape. each targetera) 2,
If the relationship between 3 and 4.5 is established in the same vertical plane, the generation of torsional force can be effectively eliminated.
Ru.

なおより好ましい捩り力の解消を図るにはパネルAにお
ける吊りピース8,9の取付位置をも上記のようなター
ゲット4,5の垂下位置近傍とすることであって、この
ようにすれば単なる平行四辺形状パネルを建起す場合と
同じに台形パネルを引起すことかで轡、クレーン1の各
吊上点6.7における吊上げ速度も同一状態の下で円滑
な建起しをなし得る。
Furthermore, in order to more preferably eliminate the torsional force, the hanging pieces 8 and 9 on panel A should be installed near the hanging positions of the targets 4 and 5 as described above. By raising the trapezoidal panel in the same manner as when raising the quadrilateral panel, smooth erection can be achieved with the lifting speed at each lifting point 6.7 of the crane 1 being the same.

又大型なパネルAを建起し操作するに当っては吊上点6
.7の間隔をそれなりに大とすることが好ましいことは
第6図に示す通ねである。前記したターゲット4,5の
取付位置のずれは上記したような大型ジャケット用パネ
ルの場合においては300■程度であれば実用的に殆ん
ど支障のない建起しをなすことができる。
Also, when erecting and operating large panel A, lift point 6
.. As shown in FIG. 6, it is preferable to make the interval 7 relatively large. In the case of a large jacket panel such as the one described above, if the deviation in the mounting position of the targets 4 and 5 is about 300 cm, erection can be accomplished with almost no practical problems.

上記したような本発明によると舞は水上クレーンを用い
ると共にパネルとクレーン観に夫々複数のターゲットを
設け、これらのターゲットが何れも同一面内にある如く
クレーy側を移動操作することにより大型ジャケットの
和傘におけるパネルを円滑に建起すことができるもので
あり、斯様な建起し時に捩り力が大傘〈作用し損壊せし
められ易い台形パネルであっても殆んど捩り力の発生し
ないような操作条件で適切に建起すことかで傘るもので
あるから工業的にその効果の大きい発明である。
According to the present invention as described above, a large jacket is created by using a water crane, providing a plurality of targets on the panel and the crane, and moving the clay side so that these targets are all in the same plane. It is possible to smoothly erect the panels of Japanese umbrellas, and when erecting them, almost no torsional force is generated even on trapezoidal panels, which are easily damaged by the torsional force acting on the large umbrella. This invention has great industrial effects because it depends on proper erection under such operating conditions.

【図面の簡単な説明】[Brief explanation of drawings]

図面は本発明の実施態様を示すものであって、第1図は
本発明による操作状態の側面図、第2図iその平面図、
第3図はそのパネルにおけるターゲット配役関係の説明
図、第)図は台形パネルの建起し操作関係を平面的に示
し九説明図、第5図はそのパネルにおけるターゲット取
付は状態を垂立状態で示した側面図、第6図はその建起
し途中の状態を示した側面図である。 然してこれらの図面において、Aはパネル、B#′i浮
台、1はクレーン、2.3はクレーン儒ターゲット、4
.5はパネル側ターゲット、6.1は吊止点、a、Sは
吊りピースを示すものである。 特許出願人  日本鋼管株式会社 発  明  者  細 野 高 泰 喀  /11 番 ノ  ■ @tfll 纂 411
The drawings show an embodiment of the present invention, and FIG. 1 is a side view of the operating state according to the present invention, FIG. 2 is a plan view thereof,
Figure 3 is an explanatory diagram of the target placement relationship on that panel, Figure 9) is a plan view showing the relationship between the erection and operation of the trapezoidal panel, and Figure 5 is an explanatory diagram showing the target mounting relationship on that panel in a vertical state. Fig. 6 is a side view showing the state in the middle of being erected. However, in these drawings, A is a panel, B#'i floating platform, 1 is a crane, 2.3 is a crane target, 4 is a
.. 5 is a target on the panel side, 6.1 is a hanging point, and a and S are hanging pieces. Patent applicant Nippon Kokan Co., Ltd. Inventor Takashi Hosono / No. 11 ■ @tflll 411

Claims (1)

【特許請求の範囲】 1、パネル側および水上クレーン側に夫々複数のターゲ
ットを配設し、これらのターゲットが何れも同一水平面
内にあるように水上クレーンを移動調整しながら前記パ
ネルを建起すことを特徴とする水上クレーンによるパネ
ル建起し方法。 2、台形をなしたパネルにおいてその前後に配設したタ
ーゲットをそれらターゲット取付点を結ぶ直線と上記台
形パネルの接地側斜辺とが略平行状態をなす如く選んで
ターゲットの取付けをなし建起す特許請求の範囲第1項
に記載の水上クレーンによるパネル建起し方法。 3、 パネルにおける吊りピースを各ターゲット取付位
置近傍に設はクレーンにより吊上げ建起す特許請求の範
囲第2項に記載のパネル建起し方法。
[Claims] 1. A plurality of targets are arranged on the panel side and a water crane side, respectively, and the panel is erected while adjusting the movement of the water crane so that these targets are all in the same horizontal plane. A method for erecting panels using a floating crane. 2. A patent claim for installing and erecting targets arranged in front and behind a trapezoidal panel so that the straight line connecting the target attachment points and the hypotenuse on the grounding side of the trapezoidal panel are approximately parallel to each other. A method for erecting panels using a floating crane as described in Scope 1. 3. The method for erecting a panel according to claim 2, wherein the hanging pieces of the panel are set near each target attachment position and lifted up by a crane.
JP14887781A 1981-09-22 1981-09-22 Erection of panel by floating crane Granted JPS5850213A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14887781A JPS5850213A (en) 1981-09-22 1981-09-22 Erection of panel by floating crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14887781A JPS5850213A (en) 1981-09-22 1981-09-22 Erection of panel by floating crane

Publications (2)

Publication Number Publication Date
JPS5850213A true JPS5850213A (en) 1983-03-24
JPS6260533B2 JPS6260533B2 (en) 1987-12-16

Family

ID=15462714

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14887781A Granted JPS5850213A (en) 1981-09-22 1981-09-22 Erection of panel by floating crane

Country Status (1)

Country Link
JP (1) JPS5850213A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6786059B1 (en) 1999-09-03 2004-09-07 Daikin Industries, Ltd. Refrigeration system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6786059B1 (en) 1999-09-03 2004-09-07 Daikin Industries, Ltd. Refrigeration system

Also Published As

Publication number Publication date
JPS6260533B2 (en) 1987-12-16

Similar Documents

Publication Publication Date Title
CN104389268B (en) A kind of steel tower column with location structure and construction method for hanging thereof
CN109094723A (en) A kind of hawse-pipe and anchor station fabrication and installation method
CN106284665B (en) A kind of oblique steel column double helix space structure and its construction method
CN205907604U (en) Steel bridge segmental hoisting counterpoint fixing device
CN110171772A (en) A kind of method that shipbuilding quickly adjusts split fix in the process
JPS5850213A (en) Erection of panel by floating crane
CN113136853A (en) Assembly type drilling platform and process for reservoir bare rock group pile foundation
US3945107A (en) Process of erecting vertical rising mast
US3511057A (en) Erection and construction of multispan bridges and piers
JPH0373697B2 (en)
CN106835984B (en) The reverse construction method of installation of slug matching bridge Bridge Erector
CN215329670U (en) Integrated construction equipment for superstructure of high-pile wharf
JP6453114B2 (en) Invert support installation device and invert support installation method
WO1989004401A1 (en) Equipment and method for positioning constructions on the seafloor or on mainland
JPH05286694A (en) Construction method and crane for assembling external type steel tower
CN213709627U (en) Door plate for sunken tube end sealing door and mounting device
JP4571760B2 (en) Building construction method
JPH07109158B2 (en) Shield excavator segment simultaneous construction control method and segment simultaneous construction type shield excavator
JPH06101348A (en) Method for constructing tower
JPH10227194A (en) Construction method of shaft
CN116062122A (en) Ship chimney segment construction method
SU1240853A1 (en) Method of erecting unburdening overstructure on existing building
JP2591352B2 (en) How to build a building
CN104314590B (en) Can low-angle upset and the rectangular shield of quick-assembling rectangle section of jurisdiction and assembling method
JPS60119804A (en) Construction of off-shore structure