JPS5842334B2 - Steel pipe column erection equipment - Google Patents

Steel pipe column erection equipment

Info

Publication number
JPS5842334B2
JPS5842334B2 JP5283479A JP5283479A JPS5842334B2 JP S5842334 B2 JPS5842334 B2 JP S5842334B2 JP 5283479 A JP5283479 A JP 5283479A JP 5283479 A JP5283479 A JP 5283479A JP S5842334 B2 JPS5842334 B2 JP S5842334B2
Authority
JP
Japan
Prior art keywords
steel pipe
pipe column
vertical
vertical hole
main body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP5283479A
Other languages
Japanese (ja)
Other versions
JPS55145212A (en
Inventor
比呂志 三浦
正信 山根
七生一 青柳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP5283479A priority Critical patent/JPS5842334B2/en
Publication of JPS55145212A publication Critical patent/JPS55145212A/en
Publication of JPS5842334B2 publication Critical patent/JPS5842334B2/en
Expired legal-status Critical Current

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 この発明は建造物を構築する際に、地下部分の逆打工法
の1として行われる大型鋼管柱を建て込む装置に関する
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to an apparatus for erecting large steel pipe columns, which is performed as one of the reverse construction methods for underground parts when constructing a building.

従来、機械削孔による縦穴内に鉄骨部材を建込むに当た
り、地表で鉄骨部材上部を支持し垂下されることにより
自体鉛直姿勢をとることは知られているが、梁接続のカ
セットを有する鉄骨柱等では対称設計とならずに偏心を
生じ、下端の位置決めの手段を要する。
Conventionally, it is known that when a steel frame member is erected in a machine-drilled vertical hole, the upper part of the steel frame member is supported on the ground surface and is suspended so that it assumes a vertical posture. etc., the design is not symmetrical and eccentricity occurs, requiring means for positioning the lower end.

削孔用に満たされた泥水内において建て込昔れた鋼管柱
の鉛直精度を確認する手段は、有効なものがほとんどな
いため、限定された狭い範囲内において、例えば水中ジ
ヤツキを使用して泥水内の鋼管柱の鉛直度を不十分な形
で修正していた。
There are almost no effective methods for checking the vertical accuracy of old steel pipe columns in muddy water filled with drilling holes, so it is necessary to check the vertical accuracy of old steel pipe columns in muddy water by using an underwater jack, for example. The verticality of the steel pipe columns inside was incorrectly corrected.

lた、この際にあらかじめ掘削された縦穴内に泥水が存
在するような軟弱地盤においては、縦穴壁からの反力を
十分に得ることができず、鉛直性の精度を上げることが
非常に困難であり、鋼管柱の建込の誤差が後続工事に与
える影響が大きかった。
In addition, in soft ground where muddy water exists in the pre-drilled vertical hole, it is not possible to obtain sufficient reaction force from the vertical hole wall, making it extremely difficult to improve the accuracy of verticality. Therefore, errors in the erection of steel pipe columns had a large impact on subsequent construction.

この発明は上記事情に鑑みてなされたもので、その目的
とするところは、鉛直度を正確に測定し得て、この結果
により鋼管柱の傾斜を簡単に修正し得るとともに、軟弱
地盤および泥水が発生する悪条件の下でもほとんど影響
されないようにすることにあり、縦穴内に挿入される鋼
管柱の上部を建込架台で支承し、縦穴内壁の強固な部分
(スタンドパイプ)と鋼管柱との間に水中ジヤツキを取
り付け、かつ鋼管柱内に同軸に取り付けた上下ターゲツ
ト板を建込架台に取り付けた鉛直トランシットで監視す
ることによって、鉛直度の測定および修正をさせること
を特徴とするものである。
This invention was made in view of the above circumstances, and its purpose is to be able to accurately measure the verticality, and use the results to easily correct the inclination of steel pipe columns, as well as to prevent soft ground and muddy water. The aim is to ensure that the upper part of the steel pipe column inserted into the vertical hole is almost unaffected even under the adverse conditions that occur. The verticality is measured and corrected by installing an underwater jack in between and monitoring the upper and lower target plates coaxially installed in the steel pipe column with a vertical transit attached to the erected frame. .

以下、この発明を図面に示す実施例に基いて詳細に説明
する。
Hereinafter, the present invention will be explained in detail based on embodiments shown in the drawings.

図中符号1で示すものは地表、2はこの地表1に挿入さ
れたスタンドパイプ、3はこのスタンドパイプ2で開口
部などを補強されはビ鉛直に形成された縦穴、4はスタ
ンドパイプ2の周囲の地表1に敷設された剛性を有する
敷板、5は縦穴3内に建て込昔れる鋼管柱である。
The symbol 1 in the figure is the ground surface, 2 is a standpipe inserted into the ground surface 1, 3 is a vertical hole formed vertically with the opening etc. reinforced with this standpipe 2, and 4 is the standpipe 2. A rigid floor plate 5 is laid on the surrounding ground surface 1, and a steel pipe column 5 is installed in the vertical hole 3.

上記縦穴3に臨む上方には、鋼管柱5の上方を支承する
建込架台10が設けられる。
A erected frame 10 that supports the upper part of the steel pipe column 5 is provided above the vertical hole 3.

この建込架台10は、上記敷板4上に載置される枠体1
1と、この枠体11の水平度を調整する複数個のジヤツ
キ12と、枠体11に固定されたレール13゜13上を
水平移動する台車14と、この台車14上に取り付けら
れた複数個の調整ジヤツキ15と、これらの調整ジヤツ
キ15上に載置され鋼管柱5を支承する支持枠16と、
枠体11に取り付けられ、第2図に示すように、鋼管柱
5の水平位置を調整または固定する補助ジヤツキ17と
、捷た枠体11および台車14の間に取り付けられ手動
の油圧ポンプ18によって操作される油圧ジヤツキ19
とがそれぞれ設けられた構成となっている。
This built-in frame 10 includes a frame 1 placed on the floor plate 4.
1, a plurality of jacks 12 for adjusting the levelness of this frame 11, a cart 14 that moves horizontally on rails 13° 13 fixed to the frame 11, and a plurality of jacks 12 mounted on this cart 14. adjustment jacks 15; a support frame 16 placed on these adjustment jacks 15 and supporting the steel pipe column 5;
As shown in FIG. 2, the auxiliary jack 17 is attached to the frame 11 and adjusts or fixes the horizontal position of the steel pipe column 5, and the manual hydraulic pump 18 is attached between the bent frame 11 and the truck 14. Hydraulic jack operated 19
The configuration is such that these are provided respectively.

筐た、上記縦穴3と鋼管柱5との間には、鋼管柱5の垂
直位置を調整する複数個の水中ジヤツキ20が設けられ
る。
A plurality of underwater jacks 20 for adjusting the vertical position of the steel pipe column 5 are provided between the vertical hole 3 and the steel pipe column 5 in the housing.

この水中ジヤツキ20ば、上記スタンドパイプ2の上端
部に支承され縦穴3および鋼管柱5の間隙に吊り下げら
れる複数個(図示例では4個)の支持フレーム21と、
以下第3図に示すように、これらの支持フレーム21に
調整スペーサ22を介して中心部に臨むように取り付け
られかつ鋼管柱5の外周面に接触するチャック板23を
有する油圧シリンダ24と、上記地表1の敷板4などに
載置され油圧ホース25を介して油圧シリンダ24に油
圧を伝達する油圧ユニット26と、支持フレーム21の
上端部に取り付けられワイヤ27を介して油圧シリンダ
24を上下方向に回動させるウィンチ28とがそれぞれ
設けられた構成となっている。
The underwater jack 20 includes a plurality of (four in the illustrated example) support frames 21 supported on the upper end of the stand pipe 2 and suspended between the vertical hole 3 and the gap between the steel pipe column 5;
As shown in FIG. 3, a hydraulic cylinder 24 is attached to these support frames 21 through adjustment spacers 22 so as to face the center thereof, and has a chuck plate 23 that contacts the outer peripheral surface of the steel pipe column 5; A hydraulic unit 26 is placed on the floor plate 4 on the ground surface 1 and transmits hydraulic pressure to the hydraulic cylinder 24 via a hydraulic hose 25, and a hydraulic unit 26 is attached to the upper end of the support frame 21 and connects the hydraulic cylinder 24 in the vertical direction via a wire 27. A winch 28 for rotation is provided respectively.

lた、上記鋼管柱5内にはその鉛直度を測定する鉛直検
査装置30が挿入される。
Additionally, a vertical inspection device 30 is inserted into the steel pipe column 5 to measure its verticality.

この鉛直検査装置30は、鋼管柱5上端部などに支承さ
れ鋼管柱5内に長さ方向に沿って適宜距離挿入されかつ
管状に形成された本体31と、第4図、第5図に示すよ
うに、この本体31の半径方向に回動自在に取り付けら
れ鋼管柱5の内周面に接触するローラ32を先端部に有
しかつ複数個(図示例では4個)を一群とするフラップ
アーム33と、これらフラップアーム33、・・・の一
群にステー34、・・・を介して連結され鋼管柱5の外
周に上下動自在に嵌合され複数個所(図示例では本体3
1の上下端部に2個所)に難関して配されるスライドパ
イプ35、・・・と、これらスライドパイプ35を本体
31に支承する油圧シリンダ36、・・・と、上記枠体
11などに取り付けられ油圧ホース37を介して各油圧
シリンダ36に油圧を伝達する油圧ポンプ38と、本体
31内部の上下に難関した位置に同心に取り付けられた
第6図atbに示す上下ターゲット板39.40と、本
体31の下ターゲット板40の下方に取り付けられ外部
(鋼管柱内部など)と遮蔽されかつ下ターゲット板40
に臨む照明灯41と、枠体11の上ターゲット板39に
臨む位置に水平方向に移動自在に取り付けられた微調整
台42と、この微調整台42に取り付けられた鉛直トラ
ンシット受台(転倒待遇り式)43と、上ターゲット板
39に臨む鉛直トランシット44と、微調整台42を固
定するブレーキ45とがそれぞれ設けられた構成とされ
ている。
This vertical inspection device 30 includes a main body 31 which is supported on the upper end of a steel pipe column 5 and inserted into the steel pipe column 5 by an appropriate distance along the length direction, and which is formed into a tubular shape, as shown in FIGS. 4 and 5. The flap arm has a roller 32 at its tip that is rotatably attached to the main body 31 in a radial direction and contacts the inner circumferential surface of the steel pipe column 5, and has a group of a plurality of rollers (four in the illustrated example). 33 and a group of these flap arms 33, . . . via stays 34, .
1), hydraulic cylinders 36, . . ., which support these slide pipes 35 on the main body 31, and the frame 11, etc. A hydraulic pump 38 is attached and transmits hydraulic pressure to each hydraulic cylinder 36 via a hydraulic hose 37, and upper and lower target plates 39 and 40 shown in FIG. , is attached below the lower target plate 40 of the main body 31 and is shielded from the outside (inside the steel pipe column, etc.) and the lower target plate 40
A fine adjustment table 42 is installed movably in the horizontal direction at a position facing the upper target plate 39 of the frame 11, and a vertical transit pedestal (not provided for overturning) is installed on the fine adjustment table 42. 43, a vertical transit 44 facing the upper target plate 39, and a brake 45 for fixing the fine adjustment table 42.

以下、このように構成されたこの発明の作用を詳細に説
明する。
Hereinafter, the operation of the present invention configured as described above will be explained in detail.

1ず、鋼管柱5の建て込み位置に、正確にスタンドパイ
プ2を打ち込み、このスタンドパイプ2内をはソその長
さく深さ)分だけ手掘し、次いでリバース機を設置して
はソ鋼管柱5の長さに対応する縦穴3を形成する。
1. First, accurately drive the stand pipe 2 into the position where the steel pipe column 5 will be installed, and then manually excavate the inside of the stand pipe 2 by the length and depth of the steel pipe. Next, install a reverse machine and remove the steel pipe. A vertical hole 3 corresponding to the length of the pillar 5 is formed.

次いで、この縦穴3の開口部の周囲に設置する建込架台
10の4方向柱位置に敷板4を敷設、し、この敷板4の
上に縦穴3に臨む建込架台を正確に設置する。
Next, a floor plate 4 is laid at the four-direction pillar position of the built-in frame 10 to be installed around the opening of the vertical hole 3, and the built-in frame facing the vertical hole 3 is accurately installed on the base plate 4.

次いで、との建込架台10のジヤツキ12、・・・を調
整して枠体11を水平にし、柱脚部をスタンドパイプ2
に固定する。
Next, adjust the jacks 12, .
Fixed to.

また必要に応じて鉄筋かと(図示略)などを縦穴3内に
挿入し、次いで複数個の水中ジヤツキ20、・・・を支
持フレーム21を介してスタンドパイプ2の内周面に沿
って挿入し、支持フレーム21の上端をスタンドパイプ
2の上開口縁部に支承させ、ウィンチ28を操作してワ
イヤ27を上動させ第3図にかいて油圧シリンダ24を
上方に回動させる。
Further, if necessary, a reinforcing bar (not shown) or the like is inserted into the vertical hole 3, and then a plurality of underwater jacks 20, . . . are inserted along the inner peripheral surface of the stand pipe 2 via the support frame 21. The upper end of the support frame 21 is supported on the upper opening edge of the stand pipe 2, and the winch 28 is operated to move the wire 27 upward and rotate the hydraulic cylinder 24 upward as shown in FIG.

次いで、鋼管柱5を吊持して縦穴3の中心部に挿入し、
上端部を建込架台10の支持枠16に支承させた状態と
する。
Next, the steel pipe column 5 is suspended and inserted into the center of the vertical hole 3,
The upper end portion is supported by the support frame 16 of the erection frame 10.

そして、支承された鋼管柱5上端の高さく地表1に対す
る高さ)の調整は調整ジヤツキ15二基を上下させて行
い、水平度をきめる。
The height of the upper end of the supported steel pipe column 5 (the height relative to the ground surface 1) is adjusted by raising and lowering the two adjustment jacks 15 to determine the levelness.

また鋼管柱5中心の水平垂直位置の調整は補助ジヤツキ
17.訃よび油圧ジヤツキ19を油圧ポンプ18で操作
して行うのである。
The horizontal and vertical position of the center of the steel pipe column 5 can be adjusted using the auxiliary jack 17. This is done by operating the hydraulic jack 19 with the hydraulic pump 18.

次いで、鋼管柱5内に鉛直検査装置30の本体31を挿
入し、油圧ポンプ38を操作して油圧シリンダ36によ
ってスライドパイプ35を上動させ、フラップアーム3
3を半径方向に回動してローラ32を鋼管柱5の内周面
に接触させる。
Next, the main body 31 of the vertical inspection device 30 is inserted into the steel pipe column 5, the hydraulic pump 38 is operated, the slide pipe 35 is moved upward by the hydraulic cylinder 36, and the flap arm 3
3 in the radial direction to bring the rollers 32 into contact with the inner circumferential surface of the steel pipe column 5.

この操作によって本体31が鋼管柱5と同心に配置され
ることになる。
By this operation, the main body 31 is arranged concentrically with the steel pipe column 5.

この際に、照明灯41が点灯(バッテリー電源筐たはコ
ードにより外部から導かれた電源によって点灯)してい
る場合は、上下ターゲット板39.40が照明されて本
体31の上部から測定し得る状態となっている。
At this time, if the illumination lamp 41 is lit (lighted by a power source led from the outside through a battery power supply case or a cord), the upper and lower target plates 39 and 40 are illuminated and measurements can be taken from the top of the main body 31. It is in a state.

次いで微調整台42を操作して、それに取付けられた鉛
直トランシット受台43に鉛直トランシット44を設置
し上ターゲット板39の中心を介して下ターゲット板4
0に臨1せ、上下ターゲット板39.40中心のずれ(
即ち鋼管柱5の傾斜)を観測する。
Next, operate the fine adjustment table 42 to install the vertical transit 44 on the vertical transit cradle 43 attached to it, and move the lower target plate 4 through the center of the upper target plate 39.
0, the upper and lower target plates 39.40 center deviation (
In other words, the inclination of the steel pipe column 5) is observed.

ずれがある際には鉛直検査装置30の微調整台42を固
定し、建込架台10の支持枠16に支承された鋼管柱5
を水中ジヤツキ20により調整する。
If there is a deviation, the fine adjustment table 42 of the vertical inspection device 30 is fixed, and the steel pipe column 5 supported on the support frame 16 of the erection frame 10 is fixed.
is adjusted using the underwater jack 20.

即ち、水中ジヤツキ20の油圧ユニット26を操作して
油圧シリンダ24を進退させ、鋼管柱5を鉛直状態に調
整するのである。
That is, the hydraulic unit 26 of the underwater jack 20 is operated to move the hydraulic cylinder 24 forward or backward, and the steel pipe column 5 is adjusted to a vertical state.

鉛直検査装置30は、水中ジヤツキ20の操作毎に第6
図aybに示す刻線イ、口または目盛を観測し中心部に
合わせることが出来、そのずれた距離から鋼管柱5の傾
斜度を算出することが可能である。
The vertical inspection device 30 performs a sixth inspection every time the underwater jack 20 is operated.
It is possible to observe the marked line A, the opening or the scale shown in Figure ayb and align it with the center, and it is possible to calculate the degree of inclination of the steel pipe column 5 from the shifted distance.

例えば目盛のずれが1CrrLで、上下ターゲット板3
9,40と鋼管柱5とのそれぞれの長さ寸法比が1=3
であれば、鋼管柱5の下端が3crnずれていることに
なる。
For example, if the scale deviation is 1 CrrL, the upper and lower target plates 3
The length dimension ratio of each of 9 and 40 and the steel pipe column 5 is 1=3
If so, the lower end of the steel pipe column 5 is shifted by 3 crn.

鋼管柱5の鉛直度が許容範囲内に調整されたら、鉛直検
査装置30の油圧ポンプ38を操作して、各フラップア
ーム33、・・・を中心方向に回動させ、鉛直検査装置
30を建込架台10から取り除く。
Once the verticality of the steel pipe column 5 is adjusted to within the permissible range, operate the hydraulic pump 38 of the vertical inspection device 30 to rotate each flap arm 33, . . . toward the center, and construct the vertical inspection device 30. Remove it from the stand 10.

次いで、鋼管柱5を若干量ジ上げ、梁取付用のカセット
を利用してスタンドパイプ2上部に仮支持させ、鋼管柱
5の梁材下部をスタンドパイプ2上部に柱頭固定し、縦
穴3と鋼管柱5のスライム処理をなし下部(スタンドパ
イプ2を除く部分など)との間に柱礎コンクリートを打
設するなどの処理をなし、その後に水中ジヤツキ20を
緩めて除去し、また、建込架台10も鋼管柱5の支承を
解除して撤去する。
Next, the steel pipe column 5 is raised slightly, temporarily supported on the upper part of the stand pipe 2 using a beam attachment cassette, the lower part of the beam material of the steel pipe column 5 is fixed to the column head on the upper part of the stand pipe 2, and the vertical hole 3 and the steel pipe are fixed. The column 5 is treated with slime and concrete is poured between the column and the lower part (excluding the stand pipe 2), and then the underwater jack 20 is loosened and removed, and the erected frame is removed. 10 also releases the support of the steel pipe column 5 and removes it.

次いで、縦穴に土砂、砕石などを埋め戻し、鋼管柱5の
内部に中詰めコンクリートを打設し、スタンドパイプ2
を引き抜き、整地、打設コンクリートの養生をして一連
の作業が終了する。
Next, the vertical hole is backfilled with earth and sand, crushed stones, etc., and filling concrete is placed inside the steel pipe column 5, and the stand pipe 2 is
The series of work is completed by pulling out the concrete, leveling the ground, and curing the poured concrete.

また、これら一連の作業に釦いて、縦穴3内に泥水が存
在し、かつ鋼管柱5内に泥水が浸入する場合でも、鉛直
検査装置30の本体31内の上下ターゲット板39.4
0および照明灯41には泥水が浸入しない液密構造とす
ることによって、泥水の存在によって鉛直度の測定釦よ
び調整が左右されることがなく、かつ軟弱地盤でも剛性
を有するスタンドパイプ2によって縦穴3を支承し得て
水中ジヤツキ20の操作を確実にしている。
In addition, in this series of operations, even if muddy water exists in the vertical hole 3 and muddy water infiltrates into the steel pipe column 5, the upper and lower target plates 39.4 in the main body 31 of the vertical inspection device 30
0 and the illumination light 41 have a liquid-tight structure that prevents muddy water from entering, so that the verticality measurement button and adjustment will not be affected by the presence of muddy water, and the standpipe 2, which is rigid even on soft ground, allows vertical holes to be 3 to ensure reliable operation of the underwater jack 20.

以上詳述したように、この発明は、縦穴内に挿入される
鋼管柱の上部を建込架台で支承し、縦穴上部のスタンド
パイプと建て込1れる鋼管柱との間に水中ジヤツキを介
在させ、鋼管柱内に挿入される円筒軸に取り付けたター
ゲツト板を鉛直トランシットで監視することによって、
鋼管柱の鉛直度の測定釦よび修正をさせるものであるか
ら、鋼管柱の鉛直度を正確に測定することが可能であり
、かつそれは鉛直トランシットをのぞく簡単な操作であ
るから、鋼管柱の鉛直度を繰り返し確認でき、軟弱地盤
や泥水が発生するなどの悪条件下であっても観測部分を
独立させ得て影響されることがなく、これらの結果鋼管
柱の傾斜を簡単に修正し得るなどの優れた効果がある。
As described in detail above, the present invention supports the upper part of the steel pipe column inserted into the vertical hole with the erection frame, and interposes an underwater jack between the stand pipe at the upper part of the vertical hole and the steel pipe column to be inserted. By monitoring a target plate attached to a cylindrical shaft inserted into a steel pipe column using a vertical transit,
Since it is a button for measuring and correcting the verticality of a steel pipe column, it is possible to accurately measure the verticality of a steel pipe column, and since it is a simple operation that involves looking into the vertical transit, it is possible to measure the verticality of a steel pipe column accurately. The angle can be checked repeatedly, and even under adverse conditions such as soft ground or muddy water, the observation part can be made independent and will not be affected, and as a result, the slope of the steel pipe column can be easily corrected. It has excellent effects.

【図面の簡単な説明】[Brief explanation of the drawing]

図面はこの発明の一実施例を示すもので、第1図は全体
の構成を示す縦断面図、第2図は第1図の■−■線に沿
う断面図、第3図は第1図の鎖線Aで囲んだ部分の詳細
図、第4図は第1図の鎖線Bで囲んだ部分の詳細図、第
5図は第1図のV−■矢視図、第6図aは第4図のVl
−Vl矢視図、第6図すはその他の実施例である。 2・・・・・・スタンドパイプ、3・・・・・・縦穴、
5・・・・・・鋼管柱、10・・・・・・建込架台1.
20・・・・・・水中ジヤツキ、21・・・・・・支持
フレーム、30・・・・・・鉛直検査装置、31・・・
・・・本体、33・・・・・・フラップアーム、39・
・・・・・上ターゲット板、40・・・・・・下ターゲ
ット板、44・・・・・・鉛直トランシット。
The drawings show one embodiment of the present invention; FIG. 1 is a longitudinal sectional view showing the overall configuration, FIG. 2 is a sectional view taken along the line ■-■ in FIG. 1, and FIG. Figure 4 is a detailed view of the part surrounded by chain line A in Figure 1, Figure 5 is a view taken along the V-■ arrow in Figure 1, and Figure 6a is a detailed view of the part surrounded by chain line B in Figure 1. Vl in figure 4
-Vl arrow view and FIG. 6 show other embodiments. 2...stand pipe, 3...vertical hole,
5...Steel pipe column, 10...Erection frame 1.
20...Underwater jack, 21...Support frame, 30...Vertical inspection device, 31...
...Main body, 33...Flap arm, 39.
...Upper target plate, 40...Lower target board, 44...Vertical transit.

Claims (1)

【特許請求の範囲】[Claims] 1 はぼ鉛直に掘削された縦穴の上方地表面に設置され
る架台と、この架台に上端部を支持されて上記縦穴内に
挿入される鋼管柱の下端部に装備され、上記鋼管柱を鉛
直に保持するための水平調整装置とからなる鋼管柱の建
込装置において、上記水平調整装置は、上記縦穴内に設
けたスタンドパイプの地表部から下部にわたって装着さ
れる支持フレームと、この支持フレームの下端部と鋼管
柱外周面との間に配設され、地上から上下揺動及び伸縮
可能に操作される水中ジヤツキとから構成されるととも
に、上記鋼管柱の鉛直検査装置が上記鋼管柱の内部に地
上から挿入される長尺の管状本体と、この本体を上記鋼
管柱内に同心に支持するフラップアームと、上記本体の
内部に設けた上下のターゲツト板と、上記架台に取り付
けられ、上記上下のターゲツト板に臨む鉛直トランシッ
トとから構成されたことを特徴とする鋼管柱の建込装置
1 A pedestal is installed on the ground surface above a vertically excavated vertical hole, and a pedestal is installed at the lower end of a steel pipe column whose upper end is supported by this pedestal and is inserted into the vertical hole. In a steel pipe column erection device, the horizontal adjustment device comprises a support frame installed from the ground surface to the bottom of the standpipe provided in the vertical hole, and a support frame of the support frame. It consists of an underwater jack that is installed between the lower end and the outer peripheral surface of the steel pipe column and is operated from the ground to be able to swing up and down and expand and contract, and a vertical inspection device for the steel pipe column is installed inside the steel pipe column. A long tubular main body inserted from the ground, a flap arm that supports the main body concentrically within the steel pipe column, upper and lower target plates provided inside the main body, and an upper and lower target plate that is attached to the mount and supports the upper and lower target plates. A steel pipe column erection device characterized by comprising a vertical transit facing a target plate.
JP5283479A 1979-04-28 1979-04-28 Steel pipe column erection equipment Expired JPS5842334B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5283479A JPS5842334B2 (en) 1979-04-28 1979-04-28 Steel pipe column erection equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5283479A JPS5842334B2 (en) 1979-04-28 1979-04-28 Steel pipe column erection equipment

Publications (2)

Publication Number Publication Date
JPS55145212A JPS55145212A (en) 1980-11-12
JPS5842334B2 true JPS5842334B2 (en) 1983-09-19

Family

ID=12925866

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5283479A Expired JPS5842334B2 (en) 1979-04-28 1979-04-28 Steel pipe column erection equipment

Country Status (1)

Country Link
JP (1) JPS5842334B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014111868A (en) * 2012-12-05 2014-06-19 Takenaka Komuten Co Ltd Weld-connecting method of basement column

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4949735B2 (en) * 2006-05-19 2012-06-13 ジャパンパイル株式会社 Pile holding device and pile holding method
CN109057370B (en) * 2018-08-14 2020-09-01 河北建设集团股份有限公司 Use method of horizontal limiting device for net rack jacking construction
JP7409834B2 (en) * 2019-11-22 2024-01-09 清水建設株式会社 Pile cap joint structure and pile cap joint method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014111868A (en) * 2012-12-05 2014-06-19 Takenaka Komuten Co Ltd Weld-connecting method of basement column

Also Published As

Publication number Publication date
JPS55145212A (en) 1980-11-12

Similar Documents

Publication Publication Date Title
BR0213161B1 (en) foundation segment for a tower of a wind power installation, and process for building a foundation for a tower of a wind power installation.
JP2014137329A (en) System and method for measuring plumbing error of plumbing member and method for plumbing reversely driven column
US7484913B2 (en) Placing elements in piles
JPS5842334B2 (en) Steel pipe column erection equipment
CN108895967B (en) Position detection method and detection device for karst cave pile foundation casing
JP4359909B2 (en) Form raising control method in slip form method
CN114279837B (en) Segment detector for vertical vacuum tunnel, turnover machine and installation method of detector
JP3616895B2 (en) Construction pillar erection device
JP3750042B2 (en) Construction pillar erection device
KR100302871B1 (en) Underground Steel Beam Vertical Adjuster
CN114809093A (en) Manhole cover positioning and mounting device and mounting construction method
JP3030377B2 (en) Construction and repair equipment for trussed pillars
JP2556215B2 (en) Construction method
CN209976462U (en) Drilling device for grouting
JPH09133620A (en) Method and system for soil load test
CN219530243U (en) Wall body straightness detection device that hangs down
CN219105171U (en) Pile hole center positioning device
JPH0531631B2 (en)
JP5060894B2 (en) Construction method
JPH04281916A (en) Base device for construction of main post
JPH07122273B2 (en) Structure pillar built-in stand
CN107964991A (en) A kind of building forced falling rectifying deviation equipment and the method using the equipment
CN219731993U (en) Steel pipe pile auxiliary guiding and positioning device built on steel trestle construction platform
CN215368789U (en) Slope finding tool for concrete surface in circular sedimentation tank
JP2556216B2 (en) Construction pillar installation jig