JPS582831Y2 - Walkway scaffolding saddle device - Google Patents

Walkway scaffolding saddle device

Info

Publication number
JPS582831Y2
JPS582831Y2 JP6000976U JP6000976U JPS582831Y2 JP S582831 Y2 JPS582831 Y2 JP S582831Y2 JP 6000976 U JP6000976 U JP 6000976U JP 6000976 U JP6000976 U JP 6000976U JP S582831 Y2 JPS582831 Y2 JP S582831Y2
Authority
JP
Japan
Prior art keywords
scaffolding
saddle
concrete
scaffold
walkway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP6000976U
Other languages
Japanese (ja)
Other versions
JPS52151638U (en
Inventor
大橋賢二
Original Assignee
大橋 賢二
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 大橋 賢二 filed Critical 大橋 賢二
Priority to JP6000976U priority Critical patent/JPS582831Y2/en
Publication of JPS52151638U publication Critical patent/JPS52151638U/ja
Application granted granted Critical
Publication of JPS582831Y2 publication Critical patent/JPS582831Y2/en
Expired legal-status Critical Current

Links

Description

【考案の詳細な説明】 本考案は、スラブ配筋後に配置される通路用足場のサド
ル装置に関するものである。
[Detailed Description of the Invention] The present invention relates to a saddle device for a passage scaffold placed after slab reinforcement is placed.

=般(ら鉄筋コンクリートを打設する場合、第1図に示
すように、仮設の床板1の上に、やや浮いた状態でスラ
ブ筋2がくもの巣状に配筋される。
When pouring reinforced concrete, slab reinforcements 2 are arranged in a spider web shape above a temporary floorboard 1 in a slightly floating state, as shown in FIG.

このスラブ配筋完了後に、型枠工事、電気設備工事、コ
ンクリート打設工事などを行うとき、作業者が直接配筋
上に乗ると、配筋が乱れ、この配筋が乱れた状態でコン
クリート打設をすると、コンクリートのひび割れが生じ
て、振動や音が階下に直接伝わったり、漏水したりする
おそれがある。
After this slab reinforcement is completed, when performing formwork work, electrical equipment work, concrete pouring work, etc., if a worker stands directly on the reinforcement, the reinforcement will be disturbed, and concrete will be poured with this disturbed reinforcement. If this is done, there is a risk that the concrete will crack, allowing vibration and sound to be transmitted directly to the downstairs floor, or causing water leakage.

そのため、従来は、第1図に示すように、まず単体のサ
ドル3だけを所定の間隔で配置し、これらのサドル3の
上に足場板4を載せて通路を作り、この上で型枠工事や
電気設備工事をしたり、コンクリート配送管5を配置し
たりしていた。
Therefore, conventionally, as shown in Fig. 1, only single saddles 3 are placed at predetermined intervals, scaffolding boards 4 are placed on top of these saddles 3 to create a passage, and formwork work is carried out on top of this. They were also doing electrical equipment work and laying out concrete delivery pipes5.

しかし、このような従来のものでは、サドル3の配置の
際と、サドル3の上に足場板4を載せる際には、どうし
ても配筋上に乗らなければならず、また、コンクリート
打設の際に、足場を移動したり盛替えたりする際にも配
筋上に乗らなければならず、かつ、これらの足場の配置
や変更に多くの時間を要して作業能率が悪く、さらに、
工事終了後におけるサドル3の保管時にかさ張るなどの
種々の欠点があった。
However, in this conventional method, when placing the saddle 3 and placing the scaffolding board 4 on the saddle 3, it is necessary to stand on the reinforcing bars, and when placing concrete, it is necessary to stand on the reinforcement. In addition, when moving or rearranging the scaffolding, it is necessary to stand on the reinforcing bars, and it takes a lot of time to arrange and change the scaffolding, resulting in poor work efficiency.
There have been various drawbacks such as the saddle 3 being bulky when stored after the construction is completed.

本考案は、このような従来の欠点を改良するためになさ
れたもので、金属板をV字状に折曲して脚部を形成し、
この脚部の上部に足場板挾持部を形成してサドルを構成
し、このサドルに足場板を嵌めるようにしたものである
The present invention was made to improve such conventional drawbacks, and the legs are formed by bending a metal plate into a V-shape.
A scaffold board holding part is formed on the upper part of this leg part to constitute a saddle, and the scaffold board is fitted into this saddle.

本考案の実施例を図面について説明する。Embodiments of the present invention will be described with reference to the drawings.

第2図および第3図において、所定の巾と厚さを有する
鉄板などの金属板を両側で互いに同一側にV字状に折曲
してこの折曲片6,7によって脚部8を形成し、また、
折曲片6,7の上方部分を互いに所定の間隔をもって同
一方向に折面して足場板挾持部9を形成する。
In FIGS. 2 and 3, a metal plate such as an iron plate having a predetermined width and thickness is bent on both sides to the same side in a V shape, and the bent pieces 6 and 7 form a leg portion 8. Also,
The upper portions of the bent pieces 6 and 7 are folded in the same direction at a predetermined distance from each other to form the scaffold board holding part 9.

前記脚部8を形成する折曲片6,7の途中には、それぞ
れ貫通孔10゜11を穿設し、この貫通孔10,11に
締付はボルト12を内方から挿入し、蝶ナツト13を螺
合する。
Through holes 10° and 11 are formed in the middle of the bent pieces 6 and 7 that form the leg portion 8, respectively, and bolts 12 are inserted from inside and tightened into the through holes 10 and 11. 13.

締けけボルト12,12の間には、上方から荷重がかか
ったとき脚部8が曲って広がるのを防止するため連結杆
14で互いに連結する。
The tightening bolts 12, 12 are connected to each other by a connecting rod 14 in order to prevent the legs 8 from bending and spreading when a load is applied from above.

このようにしてサドル15が構成される。The saddle 15 is constructed in this way.

このような構成において、サドル15の蝶ナツト13を
ゆるめ、足場板挾持部9の間に、ベニヤ板などからなる
足場板16を挿入する。
In such a configuration, the wing nut 13 of the saddle 15 is loosened, and a scaffold board 16 made of plywood or the like is inserted between the scaffold board clamping parts 9.

足場板16の長さ、厚さ、上方からかかる荷重等に応じ
て、第4図に示すように、一枚の足場板16に対し、4
〜5個のサドル15が用いられる。
Depending on the length, thickness, load applied from above, etc. of the scaffolding board 16, as shown in FIG.
~5 saddles 15 are used.

つぎに、蝶ナツト13を締め付けると、脚部8における
両折曲片6,7が互いに接近するので、足場板挾持部9
の間隔も狭くなってサドル15は足場板16に固く取付
けられ、足場台17となる。
Next, when the wing nut 13 is tightened, the bent pieces 6 and 7 of the leg portion 8 approach each other, so that the scaffolding plate holding portion 9
The distance between the saddles 15 is also narrowed, and the saddles 15 are firmly attached to the scaffolding boards 16, forming a scaffolding platform 17.

第2図の場合には、相対するサドル15の足場板挾持部
9を形成する上部の折曲片7が互いに一体の場合につい
て説明したが、第1図に示すように、下部の折曲片6が
互いに一体の場合であってもよく、また、サドル15を
形成する金属板に強度があって、上方からの荷重によっ
ても折れて広がるおそれのないときには連結杆14は必
要とせず、さらに蝶ナツト13は内側から螺合してもよ
い。
In the case of FIG. 2, the case where the upper folded pieces 7 forming the scaffold plate holding parts 9 of the opposing saddles 15 are integral with each other has been explained, but as shown in FIG. 6 may be integral with each other, and if the metal plate forming the saddle 15 is strong and there is no risk of it breaking and spreading due to a load from above, the connecting rod 14 is not necessary, and the connecting rod 14 is not required. The nut 13 may be screwed together from the inside.

また、第2図および第7図の場合は、相対する2個のサ
ドル15が一体に構成されているが、第8図に示すよう
に、それぞれ分離してもよい。
Further, in the case of FIGS. 2 and 7, the two opposing saddles 15 are integrally constructed, but as shown in FIG. 8, they may be separated.

このようにして構成されたサドル15と足場板16とか
らなる足場台17を、具体的に建築現場において使用す
る例を第5図および第6図について説明すると、建築物
18の仮設の床板1が、根太パイプ19と大引き角材2
0の上に載せら札下から下柱21で支える。
A concrete example of using the scaffolding platform 17 composed of the saddle 15 and the scaffolding board 16 constructed in this way at a construction site will be explained with reference to FIGS. 5 and 6. However, the joist pipe 19 and the large square timber 2
It is placed on top of 0 and supported by the lower pillar 21 from below.

床板1の上には、この床板1よりやや浮かしてスラブ筋
2がくもの巣状に張設される。
Slab strips 2 are stretched over the floorboard 1 in a spider web shape, slightly floating above the floorboard 1.

一方、足場板16に所定数のサドル15を取付け、第4
図Iこ示すような足場台11を形成しておく。
On the other hand, a predetermined number of saddles 15 are attached to the scaffolding board 16, and a fourth
A scaffolding platform 11 as shown in FIG. 1 is formed in advance.

そして、建造物内部の廊下、スラブ配筋個所等に、足場
台17を交互に配置して通路を形成する。
Scaffolding platforms 17 are arranged alternately in corridors, slab reinforcement locations, etc. inside the building to form passageways.

特に、コンクリート打設のためのコンクリート配送管5
の部分には、所定間隔で複数個配置してステージを作り
、コンクリート配送管5の先端の可撓管部ダが左右に振
れるようにする。
In particular, concrete delivery pipe 5 for concrete pouring
A stage is formed by arranging a plurality of concrete pipes at predetermined intervals, so that the flexible pipe section at the tip of the concrete delivery pipe 5 can swing from side to side.

スラブ配筋されている個所に足場台17を配置するには
、スラブ配筋されていない個所からまず1個の足場台1
Tをサドル15の脚部8がスラブ筋2に載らないように
して設置し、つぎに、この足場台11に作業者が乗って
つぎつぎと足場台17を設置してゆく。
To place a scaffolding platform 17 at a location where slab reinforcement is arranged, first place one scaffolding platform 17 from the location where slab reinforcement is not arranged.
The T is installed so that the leg part 8 of the saddle 15 does not rest on the slab reinforcement 2, and then a worker stands on this scaffolding platform 11 and installing the scaffolding platforms 17 one after another.

足場台17が設置され通路が形成されると、つぎに、端
部からコンクリートを打設する。
After the scaffolding platform 17 is installed and the passageway is formed, concrete is poured next from the end.

コンクリートの打設を完了した位置から足場台17を第
6図の矢印のように後退盛替えしてゆき、全体のコンク
リート打設を行う。
From the position where concrete pouring is completed, the scaffolding platform 17 is moved back and forth as shown by the arrow in FIG. 6, and the entire concrete is poured.

本考案は上述のように構成したので、このサドル15を
使用すれば軽量で組立ての簡単な足場台を作ることがで
き、しかも型枠工事、電気設備工事、コンクリート打設
工事などの際、スラブ配筋を乱すことなく通路を作るこ
とができ、したがって、コンクリートのひび割れが生じ
たり、それに基く種々の弊害が生ずることがない。
Since the present invention is constructed as described above, by using this saddle 15, it is possible to make a lightweight and easy-to-assemble scaffolding platform.In addition, it can be used for slab construction during formwork work, electrical equipment work, concrete pouring work, etc. A passage can be created without disturbing the reinforcement arrangement, so cracks in the concrete and various other problems caused by this do not occur.

また、通路やステージの変更、移動、撤去なども能率よ
く行うことができる。
It is also possible to efficiently change, move, and remove passages and stages.

さらに、締付はボルト12で折曲片6,7間を締付けれ
ばサドル15と足場板が確実に取付けられ、かつ分解も
容易であり、さらにまた、締付はボルト12間を連結杆
14で連結したので、サドル15が比較的薄い金属板で
あっても相当な荷重によっても折曲したりすることがな
いなどのすぐれた効果を有するものである。
Furthermore, the saddle 15 and the scaffolding board can be reliably attached by tightening the bolts 12 between the bent pieces 6 and 7, and disassembly is also easy. Since the saddles 15 are connected with each other, even if the saddle 15 is a relatively thin metal plate, it has an excellent effect that it will not bend even under a considerable load.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は従来の足場の使用例を示す斜視図、第2図は本
考案による装置の正面図、第3図は一部の側面図、第4
図は全体の側面図、第5図は具体的使用例の縦断面図、
第6図は同上平面図、第1図は他の実施例の正面図、第
8図はさらに他の実施例の正面図である。
Fig. 1 is a perspective view showing an example of the use of a conventional scaffold, Fig. 2 is a front view of the device according to the present invention, Fig. 3 is a partial side view, and Fig. 4 is a perspective view showing an example of the use of a conventional scaffold.
The figure is an overall side view, and Figure 5 is a vertical cross-sectional view of a specific example of use.
FIG. 6 is a plan view of the same as above, FIG. 1 is a front view of another embodiment, and FIG. 8 is a front view of still another embodiment.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 金属板をV字状に折曲した両折曲片6,7をもって脚部
8を形成し、前記両折曲片6,7の上方部分を向一方向
に折曲するとともに、これら折曲した上方部分間に互い
に所定の間隔をもたせて足場板挾持部9を形成してなる
ことを特徴とする通路用足場のサドル装置。
A leg portion 8 is formed by both bent pieces 6 and 7, which are formed by bending a metal plate into a V-shape, and the upper portions of the two bent pieces 6 and 7 are bent in one direction. A saddle device for a passageway scaffold, characterized in that scaffold plate clamping portions 9 are formed with a predetermined distance between the upper portions.
JP6000976U 1976-05-12 1976-05-12 Walkway scaffolding saddle device Expired JPS582831Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6000976U JPS582831Y2 (en) 1976-05-12 1976-05-12 Walkway scaffolding saddle device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6000976U JPS582831Y2 (en) 1976-05-12 1976-05-12 Walkway scaffolding saddle device

Publications (2)

Publication Number Publication Date
JPS52151638U JPS52151638U (en) 1977-11-17
JPS582831Y2 true JPS582831Y2 (en) 1983-01-18

Family

ID=34917743

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6000976U Expired JPS582831Y2 (en) 1976-05-12 1976-05-12 Walkway scaffolding saddle device

Country Status (1)

Country Link
JP (1) JPS582831Y2 (en)

Also Published As

Publication number Publication date
JPS52151638U (en) 1977-11-17

Similar Documents

Publication Publication Date Title
US8234827B1 (en) Express framing building construction system
US20060137269A1 (en) Concrete panel construction system and method of making panels
CN112832368A (en) Quick construction process for cantilever beam at ultrahigh position
US3959423A (en) Modular construction system
GB2141475A (en) Method and lining system for erecting buildings
US4294052A (en) Prefabricated load bearing structure
JPS582831Y2 (en) Walkway scaffolding saddle device
CN107060338A (en) A kind of secondary method for pouring stair studding of formwork
US2379636A (en) Method of making reinforced concrete buildings
KR200392341Y1 (en) Fixing Device for Aerial Scaffolding
JP2000234410A (en) Driven form and slab construction method making use thereof
CN210289158U (en) Temporary support device for connecting laminated plate with beam or wall
CN217711698U (en) Steel bar truss combined template free of supporting detachable bottom die
KR20020082966A (en) The construction method and device for slab panel which can instal psc bridge beam
JP2885023B2 (en) Construction method of reinforced concrete slab which does not need support under slab and temporary beam generating peeling
JP2002180553A (en) Method and device for joining receiving frame of template
JPH03129034A (en) Construction of floor and connecting device between striking-in mold frame for floor slab and self erection type truss-shaped steel reinforcement
KR960002478Y1 (en) Prefabricating form
KR0137465Y1 (en) Deck Girder of Reinforced Concrete Slab
JP2881585B2 (en) Integral foundation formwork components
JP3098214U (en) Large flutter
JPS6029534Y2 (en) Unit panel connection structure
SU57276A1 (en) Fixture for suspension formwork to beams
KR0137464Y1 (en) Deck Girder of Reinforced Concrete Slab
JPH0144685Y2 (en)