JPS58213935A - Construction of iron skeletal reinforced concrete structure having large diameter iron wire used to beam thereof - Google Patents

Construction of iron skeletal reinforced concrete structure having large diameter iron wire used to beam thereof

Info

Publication number
JPS58213935A
JPS58213935A JP9677782A JP9677782A JPS58213935A JP S58213935 A JPS58213935 A JP S58213935A JP 9677782 A JP9677782 A JP 9677782A JP 9677782 A JP9677782 A JP 9677782A JP S58213935 A JPS58213935 A JP S58213935A
Authority
JP
Japan
Prior art keywords
beams
reinforcing bars
main reinforcing
column
column steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP9677782A
Other languages
Japanese (ja)
Other versions
JPS645141B2 (en
Inventor
福嶋 孝之
鈴木 計夫
須賀 好富
常松 豪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Haseko Corp
Original Assignee
Hasegawa Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hasegawa Komuten Co Ltd filed Critical Hasegawa Komuten Co Ltd
Priority to JP9677782A priority Critical patent/JPS58213935A/en
Publication of JPS58213935A publication Critical patent/JPS58213935A/en
Publication of JPS645141B2 publication Critical patent/JPS645141B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 本発明は、柱を現場打ちによるSRC造とし、梁を現場
打ちによるttC造、特に、梁の主鉄筋として螺せん大
径鉄筋材を用い、それらの周囲にスタ −ラップを巻句
けて組立鉄筋とした梁材が内蔵されるltc造とした鉄
骨鉄筋コンクリート構造の架構工法に閃する。
DETAILED DESCRIPTION OF THE INVENTION The present invention uses cast-in-place SRC columns for columns, cast-in-place TTC structures for beams, and in particular, uses spiral large-diameter reinforcing bars as the main reinforcement of the beams, and has stars around them. I was inspired by the method of constructing a steel-framed reinforced concrete structure using LTC construction, which has built-in beams made of prefabricated reinforcing bars.

一般に、この稙の鉄骨鉄カhコンクリ−1・構造におい
ては、第1図に示すように、階高の2倍の長さを治し、
かつ、柱・梁筋点部に予め短寸の通し筋(蝉せん大?4
.鉄筋相を用いている。)aを固定して略キの字ノヒと
した柱鉄骨すを所定間隔おきに蛙込み、しかる?ル・、
梁拐(これは梁の主鉄筋として螺ゼん大径鉄筋祠を用い
た組立鉄筋である。)Cを柱鉄骨す間にレッカー等で吊
り込んで、梁主鉄筋dの両端と7’+iJ記Matし筋
aの端部とを接合するといった工程の繰返しによって架
構されていたため、次のような欠点があった。
Generally, in this type of steel-framed concrete structure, the length twice the floor height is fixed, as shown in Figure 1.
In addition, short through bars (cicada size? 4) are installed in advance at the column and beam reinforcement points.
.. A reinforcing bar phase is used. ) Fix the column a and make the column steel frame into a square shape. Le...
Liang-Kai (This is an assembled reinforcing bar that uses a large-diameter screw-on reinforcing bar as the main reinforcing bar of the beam.) C is suspended between the column steel frames using a tow truck, and both ends of the main beam reinforcing bar d and 7'+iJ Since the frame was constructed by repeating the process of joining the mats and the ends of the striations a, there were the following drawbacks.

即ち、上記の架4’iit工法による場合は、各々の柱
鉄骨すが互いに独立しており、下階の柱鉄骨に対して接
合される基端が1個所であるため、安定性に欠り、第1
図に示すように、柱鉄骨すの上端部同士を建方用仮設梁
θ、f″′C縦横に連結する必要がある。第1図中に仮
想線で示ず仮設梁fは梁材Cの架設後、撤去されたもの
である。
In other words, in the case of using the above-mentioned 4'iit construction method, each column steel frame is independent of each other, and the base end is connected to the column steel frame on the lower floor at one point, resulting in a lack of stability. , 1st
As shown in the figure, it is necessary to connect the upper ends of the column steel frames vertically and horizontally with the temporary beams θ, f'''C for erection. It was removed after it was erected.

しかも、架材0の吊込み時に前記仮設梁fか吊下げワイ
ヤーの障害物となり、梁材Cを吊り込む都度、仮設梁f
を着脱することが必要とされる。
Moreover, when the frame material 0 is suspended, the temporary beam f or the suspension wire becomes an obstacle, and each time the beam material C is suspended, the temporary beam f
It is necessary to attach and detach the

殊に、柱鉄骨すと梁材Cとが別々に吊り込まれるので、
作業工程が多く、しかも主鉄筋dの両端と通し筋aとを
接合するため、−接合個所ががなり多く、施工性が恋い
。また、柱鉄骨すの安定性がm(いため 全ての辿し筋
aと主鉄’A’+ dとの接合を完了した後でないと、
上層の+1・鉄骨すを接合することができず、その結果
、ill L−筋aと主鉄筋すの接合には高所作業が不
可欠であり、大きな危険が伴うのである。
In particular, since the column steel frame and the beam material C are hung separately,
There are many work steps, and since both ends of the main reinforcing bar d and the through bar a are joined, there are many joints that are loose and the workability is poor. In addition, the stability of the column steel frame is m (difficult).
It is not possible to join the +1 steel frame on the upper layer, and as a result, work at height is essential for joining the ill L-rebar A and the main reinforcing bar, which is accompanied by great danger.

また、柱・梁部点部における辿し筋aのli■定、は例
えば、実開昭54−119206号公報にも見られる通
り、通し筋aの蛛セん型に螺合する2個の→ツ) g 
、 g’を柱鉄骨すの各7ラング部の表面(夕1111
11 itu )にのみ当接させることによって行なわ
れていた(評S2図参j!jf )。このため、辿し力
JJ aに第2図で左方向への引張り応力が生じた場合
、左側の1ナツ)gが固定の作用をなさず、逆に右方向
への引張り応力に対しては右側ナツトg′による固定作
用かもtられないことになり、換1ずれは、通し筋IL
が7ランジt91(間のスチ7ナーとしてのtaf]L
<をイJするものでは゛なく、その峙果、節点部におけ
る1ill シtihaの伸び、コンクリートに対する
滑りが74;LJ 、m点部の靭性を期待できなかった
のである。
In addition, the li determination of the tracing line a at the point part of the column/beam is, for example, as seen in Japanese Utility Model Application Publication No. 54-119206, where two pieces are screwed together in the spiral shape of the running line a. →tsu) g
, G' is the surface of each 7 rung part of the column steel frame (1111
11 itu)) (see Figure S2, j!jf). For this reason, when a tensile stress to the left in Figure 2 occurs in the tracing force JJ a, the left side 1)g does not have a fixed effect, and conversely, for the tensile stress to the right, The fixing action by the right side nut g' will not be fixed, and the displacement of the bolt will be caused by the through-bar IL.
is 7 lunge t91 (taf as a stiff 7ner between) L
However, the result was that the elongation of the steel at the nodal point and the slippage against the concrete made it impossible to expect the toughness of the LJ and m point portions.

勿訓、上記公報中に開示されているように、溶接によっ
てli!11定ずれは、コンクリートに対するili+
 L/筋a (7)渭りは回避でセるが、この場合には
、辿し筋aを回転することができず、通し筋aと業主鉄
筋の螺せんQの位相合わせが行なえないので接合手[+
゛も自ずと((I(定さノすることになる。
Of course, as disclosed in the above publication, li! 11 The constant deviation is ili+ with respect to concrete.
L/rear a (7) The twisting can be avoided by avoiding it, but in this case, it is not possible to rotate the tracer a, and the phase of the thread Q of the through-rebar a and the main reinforcing bar cannot be aligned. Joiner [+
゛ will naturally become ((I().

尚、札、梁の双方をI(C造とした鉄筋コンクリート構
造については、第3図に示1ように、2本の相rk接す
る本fJIJ 7.(l立鉄筋hL 、 I+2に2ス
パンの長さを翁する梁材Cを、両端が各柱用組立鉄筋h
l。
In addition, for reinforced concrete structures in which both the plates and beams are I (C construction), as shown in Fig. 3, two vertical reinforcing bars hL, I+2 with a length of 2 spans are used. The beam material C that extends is attached to the assembly reinforcing bars h for each column at both ends.
l.

h2から(スパンずつ突出した状態に架設して構成した
先組体を用いる架構工法が従来より知られている。図中
の1は柱・梁部点部のコンクリートを拘束する角筒状の
m板である。梁材Cの主鉄筋dは■用i!L! lli
本4本音1!L迫lしているだけであり、静l板1やI
it用組立鉄筋hl、h2に対して固定されていない。
A construction method using a pre-assembly constructed by protruding each span from h2 has been known for a long time. 1 in the figure is a rectangular tube-shaped m that restrains the concrete at the point of the column/beam. It is a plate.The main reinforcing bar d of the beam C is for ■i!L!lli
Hon 4 Honne 1! It's just that I'm playing L
It is not fixed to the IT assembly reinforcing bars hl and h2.

しかし乍ら、この工法による場合は、柱用組立鉄筋hl
、b2の変形が生じやすく、鉛直度の修止が1111例
であり、また、上下に隣接する先組体の柱用Ka+立鉄
筋hl + b?同士を接ηする@S度、水平方向に隣
接する先組体の梁の主鉄筋d同士を接合することが必要
である。、また、業主鉄筋dが柱・梁部点部において固
定されていないため、第2図の場合と同様な欠点がある
However, when using this construction method, the assembly reinforcing bars for columns hl
, b2 is easily deformed, and the verticality has to be corrected in 1111 cases, and Ka + vertical reinforcing bar hl + b? It is necessary to join the main reinforcing bars d of the beams of the pre-assembled bodies that are horizontally adjacent to each other by @S degree that they are in contact with each other. In addition, since the main reinforcing bars d are not fixed at the points of the columns and beams, there is the same drawback as in the case of FIG. 2.

本発明は、これらの従来欠点を解消せんとするものであ
り、籾数hh N4分の長さを有する2本の相隣接する
柱鉄骨に、全長にわたり螺せん型、をJl、、!。
The present invention aims to solve these conventional drawbacks, and has two adjacent pillar steel frames each having a length corresponding to the number of rice grains hh N4, with a spiral shape extending over the entire length. .

してなる螺せん大径鉄筋材を栗の主?い7iに用い、周
囲にスターラップを巷第1け、かつ、2スパンの長さを
イ)せしめた複数111ケ層分の梁材を、前記主鉄筋が
6jj記2本の柱鉄骨のベニ)・梁部点部に4ζiいて
、当該柱鉄骨の相対向する一対のフ7ンジ都又はこれに
固着した一対の鋼板を貫通し、かつ、前記主鉄筋の螺セ
ん型と螺合−4−るねじ孔をもった初数対の定着金物で
前記−刻の7ラング部又はC1f板の表裏両面を締付け
た状態に固定されると共に、両端が各柱鉄骨から÷スパ
ンずつ突出した状態に架設して構成した先組体を使用し
、上下方向に隣接する先組体の柱鉄骨同士を階高の中央
部において互いに接合し、水平方向に隣接する先組体の
梁材の主鉄筋゛同士をスパン中央部において互いに接合
することを特徴としでいる。
Is the large-diameter rebar material made of screws the main ingredient of chestnut? 7i, with a stirrup around the periphery and a length of 2 spans, a plurality of 111 layers of beam material were used, with the main reinforcing bars being 6jj )・4ζi at the point of the beam, passing through a pair of opposing fins of the column steel frame or a pair of steel plates fixed thereto, and screwing into the spiral shape of the main reinforcing bar -4 - The first pair of fixing metal fittings with screw holes are used to tighten and fix both the front and back sides of the 7 rung section or C1f board, and both ends protrude from each column steel frame by ÷span. Using the constructed pre-assembled body, the column steel frames of the vertically adjacent pre-assembled bodies are connected to each other at the center of the floor height, and the main reinforcing bars of the beam materials of the horizontally adjacent pre-assembled bodies are connected to each other at the center of the floor height. They are characterized by being joined to each other at the center of the span.

以下、本発明の実施例を第4図以降の図面に基づいて説
明する。
Hereinafter, embodiments of the present invention will be described based on the drawings from FIG. 4 onwards.

第4図は、朴1をS+tC造とし、梁2を+tC造とし
た鉄骨鉄筋コンクリート構造における柱鉄骨3友び梁材
4の構築途中の状態を示す。Aは柱鉄・冴3と梁材4の
先組体である。5は耐aim<プレキャストコンクリー
ト製であるが、現場rJちコンクリートによるものでも
よい。)6は現場tJらコンクリートによる床スラブ、
7は往生ff/+、8はスパイラル筋を用いたフープ筋
、9は(に刃用仮設梁110は柱鉄骨3のジヨイントプ
レートである。尚、同図には、柱主筋7のFJ:、接作
)r及びフープ筋8の配筋作業が完了した部分と、これ
らの作業か行なオつれ−Cいない部分とが示されている
FIG. 4 shows the state in the middle of construction of 3 steel columns and beams 4 in a steel-framed reinforced concrete structure in which the block 1 is S+tC construction and the beam 2 is +tC construction. A is the pre-assembled body of the pillar iron 3 and the beam material 4. 5 is made of precast concrete, but it may also be made of on-site concrete. ) 6 is a floor slab made of concrete from the site tJ,
7 is Ojo ff/+, 8 is a hoop reinforcement using spiral reinforcement, and 9 is (The temporary beam 110 for the blade is a joint plate of the column steel frame 3. In addition, in the same figure, the FJ of the column main reinforcement 7: , the part where the reinforcement work of the hoop reinforcements 8 and 8 have been completed, and the part where these works have not yet been done.

前記先組体Aは、観数階屑分の長さをセする2本の相隣
接する柱鉄骨3と2スパンの長さをイラす”る伽込階層
分のuシ材4とを地組したものである。
The above-mentioned pre-assembly A consists of two adjacent column steel frames 3 that set the length of the observation floor waste, and a U-shaped material 4 for the inset floor that sets the length of the two spans. It is assembled.

前記架材4は、主鉄筋11として全長にわたり44.H
せん型を加工してなる螺せん入社@筋材を用い、それら
の周囲にスパイラル筋、りよりなるスターンツブ12を
2爪に倦きイ」け、かつ、1′i糾&戸に束したもので
あり、前記主鉄筋11が2本の柱鉄骨3のlid・梁部
点部において当該ヰ」鉄骨3を31iinし、かつ、両
柱鉄骨3に固定されると共に、両端側が各柱鉄骨13か
ら士スパンずつ突出した状態に両柱鉄骨3“に架設され
ている。
The frame member 4 has 44. H
Using a spiral strut made by processing a spiral shape, a spiral striation is placed around the struts, and a stern lubricant 12 is attached to two claws, and the stern lubricant 12 is tied into two claws, and then tied to the door. The main reinforcing bars 11 are attached to the steel frames 3 at the lid and beam points of the two column steel frames 3, and are fixed to both column steel frames 3, and both ends are connected to each column steel frame 13. Both pillars are erected on steel frames 3" with 3" spans protruding from each other.

柱鉄骨3としては、4811々のllJl面形状のもの
を使用できるが、口の実施例ではl]型鋼を使用しでい
る。−とじ−C,D’lj記主鉄筋11とU′鉄骨3と
の固定は、第5図、第6図に示すように、各柱鉄骨3の
相対向する一対の7ラン9部3aにル成された孔に主鉄
筋11を挿通し、主鉄A!、・11の螺せん型に螺合す
るねじ化分もった複数対のナツト等の定沼金物13で各
7ラン9部3aの表鳩両1面を締め付けることによって
T5なわれている。尚、柱鉄骨3に幻する主鉄’UJr
11の月jiltは、上i!c’、のように7ランジ丘
)3aに主鉄筋11を通jものに限られず、例えば7ラ
ン9部3aに相対向りる一対の釦1板を溶接し、この鋼
板に主鉄筋11を辿してもよい。
As the column steel frame 3, 4811 llJl surface shapes can be used, but in the example of the opening, 1] type steel is used. - Closing - C, D'lj The main reinforcing bars 11 and U' steel frame 3 are fixed by attaching them to a pair of opposing 7-run 9 parts 3a of each column steel frame 3, as shown in Figures 5 and 6. Insert the main reinforcing bar 11 into the hole made by A! T5 is made by tightening both sides of each 7-run 9 section 3a with a plurality of pairs of fixed nuts 13, such as nuts, which are screwed into the 11 screw molds. In addition, the main steel 'UJr' appearing on the pillar steel frame 3
11th month jilt is the top i! The main reinforcing bar 11 is passed through the 7 rung hill (7 rung hill) 3a as shown in c', but is not limited to the one shown in Fig. 3. You can follow it.

尚、先組体への地組は、現場に¥y散じた固定台(鋼製
、木製のいずれでもよい。)の上面に原寸図を描きこの
原寸図に合わせて2本のわ、鉄骨3を載置し、定着イ1
≧物を適当に回しながら主鉄筋11を柱鉄η3の7ラン
9部3a又はこれに溶接した鋼板のIす「定位11(に
予め芽1jy EVれた孔に挿入し、定着金峰)13を
島1イsl【−Jたンン・、スターラ゛ンフ12を巻き
イ=j【プることによって行なわ4しる1゜ 次に、架構手順について述べる。
In addition, for assembling the pre-assembled structure, draw a full-scale drawing on the top of the fixing base (made of steel or wood may be used) scattered at the site, and install two steel frames and three steel frames according to this full-sized drawing. Place it and fix it 1.
≧While rotating the object appropriately, insert the main reinforcing bar 11 into the 7-run 9 part 3a of the column iron η3 or the steel plate welded to it. This is done by winding the star shaft 12 and pulling the island 1 sl [-J tann.

上記の先組体Aを第6図に示すように水平方向に幀数飴
1並べて配置すに)ど共に、断面の中央部において各柱
鉄骨3の基端を下階の柱鉄骨(1階の場合は地中梁から
立設した柱鉄骨)3に前記ジヨイントブレーNO及びホ
ルトづットを介して接合する。
As shown in Fig. 6, when the pre-assembled bodies A are arranged horizontally in parallel, the base end of each column steel frame 3 is connected to the column steel frame on the lower floor (first floor) at the center of the cross section. In the case of , it is connected to the column steel frame (3) erected from the underground beam via the joint brake and the bolt.

この場合、先に)1体Aは複数のに拐4で連結一体化さ
れた2本のれ、鉄号3をイJしているので、安定性がよ
く、2本の柱鉄骨3の上端部間に仮設梁を用いなくても
自立可能な状態に建込まれることになる。尚、必要であ
れは、梁間方向に位置する先組体Aの柱鉄骨3同士は、
第4図で示したように、MiJ記仮股梁9で連結する。
In this case, first) 1 body A has two pillars connected and integrated by multiple columns 4, and the iron number 3 is attached to the top of the two pillars steel frame 3, so it has good stability. It will be built so that it can stand on its own without using temporary beams between sections. In addition, if necessary, the column steel frames 3 of the pre-assembled body A located in the direction between the beams should be
As shown in FIG. 4, they are connected by MiJ temporary cross beams 9.

次に、水平方向に隣接する梁材4の主鉄筋11の端部同
士をスパン中央部において互いに接合する。
Next, the ends of the main reinforcing bars 11 of horizontally adjacent beam members 4 are joined to each other at the center of the span.

この接合は、主鉄筋11の螺せん型に螺合するカップラ
ーと一対のナツトとによるいわゆるロックナツト方式、
カップラーとその内部に注入される接着剤とによるいわ
ゆるグラウト方式など既知の十&ICよって行なわれる
This connection is performed using a so-called lock nut method using a coupler and a pair of nuts that are screwed into the spiral shape of the main reinforcing bar 11.
This is carried out by a known method such as a so-called grouting method using a coupler and an adhesive injected into the coupler.

尚、1セツトの先組体Aにおける2本の柱鉄骨3が溶接
、本締め等により下層に完全に固定された後は、地組み
の際に締付は固定した主鉄筋11の定着金物13を緩め
ても都万に支障はない。この場合には、主鉄筋11のわ
ず力)な回転が可能なため、隣接する主鉄筋11の螺せ
ん型の位相合せを行なえ、ロックナツト方式等による接
合を容易に行なうことができる。
In addition, after the two column steel frames 3 in one set of pre-assembled body A are completely fixed to the lower layer by welding, final tightening, etc., the fixing hardware 13 of the fixed main reinforcing bar 11 is tightened during foundation assembly. There is no problem in Toman even if the restrictions are relaxed. In this case, since the main reinforcing bars 11 can be rotated without effort, it is possible to perform spiral phase alignment of adjacent main reinforcing bars 11, and it is possible to easily join them using a lock nut method or the like.

以下、同様な先組体Aを下階の先組体Aの上方に吊り上
げて、上下方向に@接する先組体Aの柱鉄骨3同士を先
の工程と同様に階高の中央部で互いに接合した後、水平
方向に隣接する梁材4の主鉄筋11の端部同士を互いに
接合するといった工程を繰り返して柱鉄骨3及び梁材C
を、部数階層ずつ架構するのである。
Hereinafter, a similar pre-assembled body A is lifted above the pre-assembled body A on the lower floor, and the column steel frames 3 of the pre-assembled body A that are in contact with each other in the vertical direction are connected to each other at the center of the floor height as in the previous process. After joining, the process of joining the ends of the main reinforcing bars 11 of horizontally adjacent beam members 4 to each other is repeated to form the column steel frame 3 and the beam member C.
The structure is constructed in layers of copies.

上記の実施例では、スパン中央部に15ける主鉄筋11
の接合を、柱鉄骨3の下層、の一定に引き続いて行なっ
ているか、1セツトの先組体Aは、伽数の梁材Cによっ
て連結された2本の柱鉄骨3を有し、当該柱鉄骨3を下
層に一定することにより安定よく自立するので、水平方
向に隣接する先組体Aの梁h’ Q同士がフリーの状態
にあっても、つまり、梁の主鉄筋11を接合しなくても
、建方には支障がない。従って、主鉄筋11の接合は、
床スラブ6の施工後、床スラブ6に載置した脚立に来っ
て行・ようことが可能であり、この場合には、床上作業
となるため、主鉄筋11の接合を安全に行なうことがで
きる。
In the above example, the main reinforcing bars 11 in 15 at the center of the span
One set of pre-assembly A has two column steel frames 3 connected by a single beam member C, and the lower layer of the column steel frames 3 is connected continuously. By fixing the steel frame 3 at the lower layer, it can stand on its own in a stable manner, so even if the horizontally adjacent beams h'Q of pre-assembled bodies A are in a free state, that is, the main reinforcing bars 11 of the beams are not connected. However, there is no problem with the construction. Therefore, the connection of the main reinforcing bars 11 is as follows:
After the construction of the floor slab 6, it is possible to go to the stepladder placed on the floor slab 6, and in this case, since the work will be done on the floor, it is not possible to safely join the main reinforcing bars 11. can.

以上のように、本発明によれは、しvi階層分の長さを
有する2本の相@接する柱鉄骨に、全長にわたり螺せん
型を加工してなる螺せん大径鉄筋材を梁の主鉄筋に用い
、周囲にスターラップを春付け、かつ、2スパンの長さ
を有せしめたし数階層分の梁材を、前記主鉄筋が前記2
本の柱鉄骨の柱第節点部において当該柱鉄骨の相対向す
る一対の7ランジ部又はこれに[i’i1着された一対
の鋼板を塔通し、かつ、前記主鉄筋の螺せん型に螺合す
る。+Lフットの定着金物で前記一対の7ランジ部1又
は婢1板の表裏両面を締(qけた状態に固定されると共
に、両端が各柱鉄骨から(スパンずつ突出した状態に架
設して構成した先組体を使用するので、柱鉄骨と梁材を
別々に吊り込む場合に比べて作業工程が少なく、かつ、
現場接合の個所が減少することはもとより、1セット先
組体がiMlの梁材によって連結一体化された2本の柱
鉄骨を冶しているため、建方の安定性がよく、2本の柱
鉄骨の上端部(1j」を連結する仮設梁を用いることな
く 自立可能な状態に建込むことができる。
As described above, according to the present invention, a spiral large-diameter reinforcing bar material formed by processing a spiral shape over the entire length of two adjacent column steel frames each having a length of 5 floors is used as the main part of a beam. The main reinforcing bars were used as reinforcing bars, and a stirrup was attached around the periphery.
A pair of steel plates attached to the opposite 7-lung portions of the main column steel frame are passed through the column at the first joint of the main column steel frame, and are screwed into the spiral shape of the main reinforcing bar. match. +L-foot fixing hardware is used to tighten both the front and back sides of the pair of 7-lunge parts 1 or 1 plate (fixed in a bent state, and both ends are constructed so as to protrude from each column steel frame (span by span). Since pre-assembly is used, there are fewer work steps compared to when the column steel frame and beam materials are hung separately, and
Not only does it reduce the number of on-site joints, but since one pre-assembled assembly has two pillar steel frames that are connected and integrated using iMl beams, the construction is more stable, and the two It can be built in a self-supporting state without using temporary beams to connect the upper ends of the steel columns (1j).

しかも、先組体の2本の柱鉄骨が溶接、本締め等により
下層に完全に固定された後は、地組みの段階で締付は固
定された主鉄筋の定着金物を綬めても、建方に支1ス(
がなく、従って、相隣る先組体の主鉄筋をスパン中央部
で接合するにあたっては、定着金物を緩めて主鉄筋のU
転を可能とすることにより両生鉄筋の螺せん型の位相合
わせを行なえ、ロックナツト方式など螺合による簡単か
つ安価な手段によって容μ、に接合できる。
Moreover, after the two column steel frames of the pre-assembled body have been completely fixed to the lower layer by welding, final tightening, etc., even if the fixing hardware of the main reinforcing bars is tightened during the foundation assembly stage, One support for construction (
Therefore, when joining the main reinforcing bars of adjacent front assemblies at the center of the span, loosen the anchors and tighten the U of the main reinforcing bars.
By making rotation possible, it is possible to match the phase of the helical reinforcing bars, and they can be joined in a simple and inexpensive manner by screwing, such as a lock nut method.

さらに、1セツトの先組体は、複数の梁材によって連結
一体化された2本の柱鉄骨を有し、当該2本のホし鉄骨
を下層に固定するため、相隣る先組体の梁1合部(スパ
ン中央部で行なわれる主鉄筋の払・合)については、フ
リーの状態にしたままでも建方に支障がない。従って、
スパン中央部における主鉄筋の接−合は、床スラブの施
工後、当該床スラブの上で安全かつ容易に行なうことが
■」能である。
Furthermore, one set of pre-assembled bodies has two column steel frames that are connected and integrated by a plurality of beam materials, and in order to fix the two pillar steel frames to the lower layer, adjacent pre-assembled bodies are As for the first joint of the beam (the main reinforcing bars are laid out and joined at the center of the span), there is no problem with erection even if it is left free. Therefore,
The main reinforcing bars at the center of the span can be joined safely and easily on the floor slab after the floor slab has been constructed.

また、先組体を地組みするにあたっては、柱鉄骨にお【
プる一対の7ランジ部又は鋼板の所定位置に形!、され
た孔に梁の主鉄筋をi!fl シ、主鉄筋の螺ぜん型と
螺合するナツト等の定着金物で1.’o Nけ固定する
ため、寸法誤差を極めて小さくすることができる。従っ
て、現場接合個所が少ないことと相まって、精良の向い
建方が可能である。
In addition, when assembling the pre-assembled body into the ground, it is necessary to
Shape a pair of 7 flange parts or a steel plate at a predetermined position! , insert the main reinforcing bar of the beam into the hole where i! 1. Use a fixing hardware such as a nut that screws into the screw type of the main reinforcing bar. Because it is fixed in place, dimensional errors can be made extremely small. Therefore, combined with fewer on-site joints, it is possible to construct the building facing the opposite direction.

殊に、柱・梁flhj点部における梁の主鉄筋の固定は
、主鉄筋のC!せん型と螺合するナツト等の定着金物で
も二鉄骨における相対向する一対のフラン・・ジ都又は
これに1¥!?Iλiした一対の鋼板の表裏両dIsを
締付りることによって?]なわれるから、換言すれば各
7ランジt−1)又はWd板の外(ill 1こけでな
く、内夕1両側から挟持した状態に1.Yr (qけ固
定するので、7ランジ部間又は酬板曲に位1F、(する
主鉄筋がスチフナーとしてm M+4シ、鉄骨鉄筋コン
クリート構造の築造後、柱・梁の十字形節点部に曲げカ
を受Gツても、コンクリートに対する衆生鉄筋の滑りが
生じないため、極めて靭性が旨い節点部となる。
In particular, the main reinforcement of the beam at the flhj point of the column/beam is fixed by C! of the main reinforcement. Fixing hardware such as nuts that screw together with the helical mold can also be used as a pair of opposing flanges on two steel frames... or 1 yen for this! ? By tightening both the front and back dIs of a pair of steel plates with Iλi? ] In other words, each 7 lunge t-1) or the outside (ill Or, on the 1st floor where the main reinforcing bars are used as stiffeners (M+4), even if the cruciform joints of the columns and beams are subjected to bending force after the construction of the steel reinforced concrete structure, the sentient reinforcing bars will slip against the concrete. Since this does not occur, the joints have extremely good toughness.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は従来例を示す概略斜視図、第2図は従来例にお
i−する柱・・梁部点部の横断平ffl+図、第3図は
従沫例を示す棚、路上面図、第4図乃至第7図は本発明
の一実施例を示し、第4′lAは斜視図、第5図は要部
の平1t11図、第6図は要部1)の止面図、第7図は
概略止面図である。 A・・・先組体、3・・・柱鉄骨、4・・・梁材、11
・・・主鉄筋、12・−・スターラップ。
Fig. 1 is a schematic perspective view showing a conventional example, Fig. 2 is a cross-sectional plane ffl+ view of the pillar/beam point part i- in the conventional example, and Fig. 3 is a shelf and road surface view showing a conventional example. , FIGS. 4 to 7 show an embodiment of the present invention, where 4'lA is a perspective view, FIG. 5 is a flat view of the main part, and FIG. 6 is a stop view of the main part 1). FIG. 7 is a schematic top view. A...Pre-assembly, 3...Column steel frame, 4...Beam material, 11
...Main reinforcing bar, 12... Stirrup.

Claims (1)

【特許請求の範囲】[Claims] 柱を5itC造、梁をRC造とした鉄骨鉄筋コンクリー
ト構造の架構工法であって、複数階要分の長さを有する
2本の相隣接する柱鉄骨に、全長にわたり螺ぜん型を加
工してなる螺せん大径鉄筋材を梁の主鉄筋に用い、周囲
にスターラップを4I付け、かつ、2スパンの1にさを
有せしめた複数階要分の梁拐を、F41I記主鉄筋が前
記2本の柱鉄骨の柱・梁筋点部において、肖該柱鉄骨の
相対向する一対の7ラング部又はこれにvil*I、た
一対のm&をh通し、かつ、nit記主鉄筋の螺ぜん型
と螺合するねじ孔を有する憤数対の定着金物で11す記
一対の7ランジ都又はν板の表裏両面をP1υ付けた状
態に固定されると共に、両端が各柱鉄骨から(スパンず
つ突出した状態に架設して構1v、シた先組体を使用し
上下方向に隣接する先組体の柱鉄骨同士を貼゛高の中央
部において互いに接合し、水平方向に隣設する先組体の
梁材の主鉄筋同士をスパン中央部に・おいて互いに接合
することを特徴とする梁に大径ま鉄筋を用いた鉄骨鉄筋
コンクリート構造の架構1へ工法。
This is a steel-reinforced concrete structure construction method in which the columns are made of 5ITC and the beams are made of RC. Two adjacent column steel frames each having a length equivalent to multiple floors are machined into a spiral shape over the entire length. F41I main reinforcing bars are used as the main reinforcing bars of the beams, and stirrups are attached around the periphery of the beams for multiple floors. At the column/beam reinforcement point of the main column steel frame, pass vil*I and a pair of m&h through a pair of opposing 7 rung parts of the column steel frame or these, and connect the threads of the nit mark main reinforcing bar. A pair of fixing metal fittings with screw holes that screw into the mold are used to fix the front and back surfaces of a pair of 11 or ν plates with P1υ attached, and both ends are connected to each column steel frame (span by span). The structure 1v is constructed in a protruding state, and the column steel frames of vertically adjacent pre-assemblies are joined to each other at the center of the height by using a pre-assembled assembly that is installed horizontally adjacent to each other. A method for constructing a frame 1 of a steel-framed reinforced concrete structure using large-diameter reinforcing bars for beams, which is characterized by connecting the main reinforcing bars of the body beams to each other at the center of the span.
JP9677782A 1982-06-04 1982-06-04 Construction of iron skeletal reinforced concrete structure having large diameter iron wire used to beam thereof Granted JPS58213935A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9677782A JPS58213935A (en) 1982-06-04 1982-06-04 Construction of iron skeletal reinforced concrete structure having large diameter iron wire used to beam thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9677782A JPS58213935A (en) 1982-06-04 1982-06-04 Construction of iron skeletal reinforced concrete structure having large diameter iron wire used to beam thereof

Publications (2)

Publication Number Publication Date
JPS58213935A true JPS58213935A (en) 1983-12-13
JPS645141B2 JPS645141B2 (en) 1989-01-27

Family

ID=14174061

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9677782A Granted JPS58213935A (en) 1982-06-04 1982-06-04 Construction of iron skeletal reinforced concrete structure having large diameter iron wire used to beam thereof

Country Status (1)

Country Link
JP (1) JPS58213935A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS618334A (en) * 1984-06-22 1986-01-16 株式会社コロナ Production unit for corrugated board
KR101157147B1 (en) 2008-09-22 2012-06-22 경희대학교 산학협력단 Composite concrete column and construction method using the same

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0560645A (en) * 1991-09-05 1993-03-12 Mitsubishi Electric Corp Multi-purpose inspection and gas analysis apparatus for vacuum system

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4958628A (en) * 1972-10-09 1974-06-06
JPS5594304U (en) * 1978-12-25 1980-06-30

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4958628A (en) * 1972-10-09 1974-06-06
JPS5594304U (en) * 1978-12-25 1980-06-30

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS618334A (en) * 1984-06-22 1986-01-16 株式会社コロナ Production unit for corrugated board
KR101157147B1 (en) 2008-09-22 2012-06-22 경희대학교 산학협력단 Composite concrete column and construction method using the same

Also Published As

Publication number Publication date
JPS645141B2 (en) 1989-01-27

Similar Documents

Publication Publication Date Title
JP4264916B2 (en) End RC steel beam
JPS58213935A (en) Construction of iron skeletal reinforced concrete structure having large diameter iron wire used to beam thereof
JP2927402B2 (en) Column-beam joint structure of concrete building
JPS6047140A (en) Steel plate concrete structure
JPS584004A (en) Construction of prefabricated prestressed steel beam
JPH10219831A (en) Joined building construction between reinforced concrete column and steel frame beam and its joined part structure, and precast reinforced concrete column
JP3394934B2 (en) Steel reinforced concrete structure
JP2003261983A (en) Tensile spline tenon
JPS602462B2 (en) Precast concrete shear wall assembly method
JP3407164B2 (en) Frame structure
JP4045502B2 (en) Structure
JP3159799B2 (en) Frame construction method of prestressed steel tube concrete structure
JPS59102037A (en) Construction of reinforced concrete structure using large diameter main iron skeletal to beam
JPS61196035A (en) Construction of concrete building
JPH03275839A (en) Connection construction of reinforced concrete column and steel beam
JPS61282526A (en) Method for connecting iron skeletal pillar and beam
CN117966885A (en) Steel pipe prestressed concrete member, connecting structure and application method
JP3250760B2 (en) Joining method of precast concrete column with beam bracket and precast concrete shear wall with steel beam
JPS628246Y2 (en)
JP3199438B2 (en) Composite frame structure of building
JPS60115773A (en) Construction method due to assembled iron wire body with frame
JP3284383B2 (en) Support hardware for SRC beam construction
JPH03166432A (en) Embedded molding box construction method
JPH0673785A (en) Steel framed reinforced concrete column and construction of this column and steel skeleton beam
JPH01190842A (en) Method for constructing reinforced concrete column and steel girder structure