JPS582136A - Loading of bulk material onto freight cars - Google Patents

Loading of bulk material onto freight cars

Info

Publication number
JPS582136A
JPS582136A JP10017481A JP10017481A JPS582136A JP S582136 A JPS582136 A JP S582136A JP 10017481 A JP10017481 A JP 10017481A JP 10017481 A JP10017481 A JP 10017481A JP S582136 A JPS582136 A JP S582136A
Authority
JP
Japan
Prior art keywords
conveyor
hopper
shirt
chute
loading
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP10017481A
Other languages
Japanese (ja)
Inventor
Seiichi Tatsumi
成一 巽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP10017481A priority Critical patent/JPS582136A/en
Publication of JPS582136A publication Critical patent/JPS582136A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G67/00Loading or unloading vehicles
    • B65G67/02Loading or unloading land vehicles
    • B65G67/04Loading land vehicles
    • B65G67/10Loading land vehicles using conveyors covering the whole length of vehicle trains

Landscapes

  • Engineering & Computer Science (AREA)
  • Aviation & Aerospace Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Loading Or Unloading Of Vehicles (AREA)

Abstract

PURPOSE:To improve the rate of loading operation by connecting a chute to the freight receiving port of a hopper wagon and loading freights by means of a shuttle conveyor and advancing the conveyor to connect the chute to the next freight receiving port when the measured weight of the freight reaches a certain set level. CONSTITUTION:The chute 6 of a shuttle conveyor 4 is connected to the first freight receiving port 5 of a hopper wagon 1, and a gate 12 is opened, and at the same time, a feed-in conveyor 3 and the conveyor 4 are driven to load bulk material. The weight loaded is measured by a conveyor scale 7, and when said weight reaches the set level, operation of the conveyor 4 is stopped, and the gate 12 is closed, and connection between the freight receiving port 5 and the chute 6 is released, Then, the conveyor 4 is advanced, and the chute 6 is connected to the second freight receivng port 5, and the conveyor 4 is driven to open the gate 12. As loading is performed through repetition of these procedured, shifting a hopper 2 or suspension of feeding onto the hopper is not required.

Description

【発明の詳細な説明】 この発明は、貨車に穀物、飼料原料、肥料等のパラ物を
積み込む方法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for loading parallaxes such as grains, feed materials, and fertilizers onto freight cars.

従来、ホッパー車にパラ物を積み込む場合、定置式積み
込み装置の直下にホッパー車を移動させたのち、ホッパ
ー車の荷受口にシュートを接続してパラ物を供給するの
で、荷受口とシュートとの継ぎかえ或はホッパー車の移
動時にパラ物の供給を休止させなければならない。
Conventionally, when loading bulk goods into a hopper car, the hopper car is moved directly below the stationary loading device, and then a chute is connected to the receiving port of the hopper car to supply the bulk goods, so there is no connection between the receiving port and the chute. The supply of parallax materials must be stopped when changing parts or moving the hopper car.

このため、積み込み稼動率が低下すると共に、上記ホッ
パー車の移動に牽引車を必要とする欠点があった。
For this reason, there was a drawback that the loading operation rate decreased and a towing vehicle was required to move the hopper vehicle.

この発明は、連続運転によってパラ物を供給し続けると
共に、ホッパー車を移動させることなく積み込めるよう
にして、上述の欠点を解消することを目的としている。
The present invention aims to solve the above-mentioned drawbacks by continuously supplying parallaxes through continuous operation and by making it possible to load the hopper truck without moving it.

この発明は、コンベヤにより定置式のホッパーにパラ物
を連続供給すると共に、上記ホッパーがらシャツトルコ
ンベヤを経て停止しているホッパー車にバラ物を積み込
むようにしたパラ物の賃車積み方法を提供する。
The present invention provides a method for loading bulk goods into a rental car, in which bulk goods are continuously supplied to a stationary hopper by a conveyor, and the bulk goods are loaded from the hopper via a shirt conveyor into a stopped hopper car. do.

以下、この発明の実権例を添付図面に基づいて説明する
Hereinafter, practical examples of the present invention will be explained based on the accompanying drawings.

図において、1はホッパー車であって、このホッパー車
1は一輌或は所要の編成長さに連結されている。
In the figure, 1 is a hopper car, and this hopper car 1 is connected to one car or to a required number of cars.

2はホッパー車1の手前上方に設けたホッパーであって
、このホッパー2には、連続運転する搬入コンベヤ3に
よりバラ物が供給されるようになっている。
Reference numeral 2 denotes a hopper provided above the front of the hopper car 1, and loose materials are supplied to the hopper 2 by a continuously operating carry-in conveyor 3.

4はホッパー車10走行方向に移動可能で上記ホッパー
2からホッパー車1にパラ物を積み込むシャツトルコン
ベヤで、このシャツトルコンベヤ4の移動範囲は、ホッ
パー車1の編成長さとなっている。
Reference numeral 4 denotes a shirt torque conveyor which is movable in the running direction of the hopper vehicle 10 and loads parallax materials from the hopper 2 to the hopper vehicle 1. The movement range of the shirt torque conveyor 4 is the length of the hopper vehicle 1.

また、シャツトルコンベヤ4のヘッドには、ホッパー車
1の荷受口5にバラ物を投入するシュート6が設けられ
ている。
Further, the head of the shirt tank conveyor 4 is provided with a chute 6 for throwing bulk materials into the receiving port 5 of the hopper car 1.

上記、シャツトルコンベヤ4の輸送能力は、上記搬入コ
ンベヤ3よりも大きくなって、積み込み運転時ホッパー
2にパラ物が溜らないようになっている。
The transportation capacity of the shirt conveyor 4 is larger than that of the carry-in conveyor 3, so that parallaxes do not accumulate in the hopper 2 during loading operation.

さらに、シャツトルコンベヤ4のヘッド側ニハ、コンベ
ヤスケ−A/7が設けられている。
Furthermore, a conveyor scale A/7 is provided on the head side of the shirt conveyor 4.

なお、ンヤットyコンベヤ4の移動は、引き込み線のレ
ー/I/8に並行するレーA/9を設けて、とのレー/
I/9にシャツトルコンベヤ4の車輪10を載せると共
に、ラックに噛み合うピニオンを駆動する(図示省略)
等の手段により行なわれるようになっている。
In addition, the movement of the Nyat Y conveyor 4 is carried out by providing a rail A/9 parallel to the lead-in line Ray/I/8.
The wheels 10 of the shirt torque conveyor 4 are placed on the I/9, and the pinion that engages with the rack is driven (not shown).
This is now done by means such as.

また、シュート6の下端にフレキシブルチューブ11を
設けておくことにより、荷受口5とシュート6との着脱
作業が容品になる。
Further, by providing the flexible tube 11 at the lower end of the chute 6, the work of attaching and detaching the cargo receiving opening 5 and the chute 6 is easy.

さらに、上記コンベヤスケ−A/7による計量の総計が
設定値になると、シャツトル・コンベヤ4の運転を止め
、かつ、ホッパー4のゲート12を閉じるようになって
いる。
Further, when the total weight measured by the conveyor scale A/7 reaches a set value, the operation of the shuttle conveyor 4 is stopped and the gate 12 of the hopper 4 is closed.

この発明の積み込み方法は、以上の構成であって、次に
、積み込み方法を説明すると、まず、ホッパー2の近傍
にシュート6が位置するようシャツトルコンベヤ4を後
退させる。
The loading method of the present invention has the above-described configuration. Next, the loading method will be explained. First, the shirt tank conveyor 4 is retreated so that the chute 6 is located near the hopper 2.

また、引き込み線にホッパー車1を乗り入れたとき、シ
ュート6と、先行ホッパー車1の進入側一番目の荷受口
5とを一致させる。
Further, when the hopper car 1 enters the drop-in line, the chute 6 is aligned with the first cargo receiving port 5 on the entry side of the preceding hopper car 1.

なお、ホッパー車1の停止時シュート6と一番目の荷受
口5とが一致しない場合は、上記シャツトルコンベヤ4
をスライドさせながら一致させる。
In addition, if the chute 6 when the hopper car 1 is stopped and the first cargo receiving port 5 do not match, the above-mentioned shirt conveyor 4
Match by sliding.

そして、荷受口5にフレキシブルホース11を接続する
Then, the flexible hose 11 is connected to the cargo receiving port 5.

しかして、ゲート12を開くと共に、搬入コンベヤ3及
びシャツトルコンベヤ4の運転を開始すると、上記搬入
コンベヤ3からシュート2にバラ物を供給し続けると共
に、上記シュート2からVヤットルコンベヤ4、シュー
ト6el[ホッパー車1にパラ物を積み込む。
When the gate 12 is opened and the operation of the carry-in conveyor 3 and the shirt conveyor 4 is started, loose materials are continuously supplied from the carry-in conveyor 3 to the chute 2, and from the chute 2 to the V-yattle conveyor 4 and the chute. 6el [Load parallax into hopper car 1.

このとき、シャツトルコンベヤ4の輸送能力は、搬入コ
ンベヤ3よりも大きくしであるので、ホッパー2内にバ
ラ物が溜らない。
At this time, since the transportation capacity of the shirt tank conveyor 4 is greater than that of the carry-in conveyor 3, loose materials do not accumulate in the hopper 2.

上記バラ物の積み込み時にコンベヤスケ−IV7により
計量すると共に、この計量の総計が設定値になると、ゲ
ート12を閉じるのと同時にシャツトルコンベヤ4の運
転を停止するので、ホッパー車1に対するパラ物の積み
込みが停止する。
When loading the above-mentioned bulk materials, the conveyor scale IV7 weighs the materials, and when the total weight reaches the set value, the operation of the shirt tank conveyor 4 is stopped at the same time as the gate 12 is closed, so that the bulk materials can be loaded into the hopper car 1. stops.

このとき、搬入コンベヤ3を運転しているので、ホッパ
ー2にパラ物が溜る。
At this time, since the carry-in conveyor 3 is being operated, parallaxes accumulate in the hopper 2.

上記シャツトルコンベヤ4の運転停止後、ただちに荷受
口5とフレキシブルホース11との接続を解除して二番
目の荷受口5とシュート6とが一致するようシャツトル
コンベヤ4を前進させる。
After stopping the operation of the shirt torque conveyor 4, the connection between the cargo receiving port 5 and the flexible hose 11 is immediately released, and the shirt torque conveyor 4 is advanced so that the second cargo receiving port 5 and the chute 6 coincide with each other.

そして、上記荷受口5にフレキシブルホース11を接続
したのち、ゲート12を開き、かつシャットμ:I:/
ぺ’r4の運転を開始するので、ホッパー2に溜ったバ
ラ物が直ちに排出され、積み込まれる。
After connecting the flexible hose 11 to the cargo receiving port 5, the gate 12 is opened and shut μ:I:/
Since the operation of Pe'r4 is started, the loose materials accumulated in the hopper 2 are immediately discharged and loaded.

以上の手順をへて一番目の荷受口から最終番目の荷受口
にパラ物を供給し、−輌目から二情目のホッパー車1に
順次パラ物を積み込む。
After going through the above procedure, the cargo is supplied from the first cargo receiving port to the final cargo receiving port, and the cargo is sequentially loaded into the hopper car 1 from the first to the second cargo receiving port.

以上のように、この発明に係るパラ物の貨車積み方法に
よれば、ホッパー車の一番目の荷受口にシャツトルコン
ベヤのシュートを接続したのち、ゲートを開くと共に搬
入コンベヤ及びシャツトルコンベヤの運転を開始して、
上記搬入コンベヤからのパラ物を、ホッパー、シャツト
ルコンベヤをへてホッパー車に積み込むと共に、コンベ
ヤスケールによって計量し、そして上記の計量の総計が
設定値になると、シャツトルコンベヤの運転を停止する
のと同時にゲートを閉じ、その後に荷受口とシュートと
の接続を解除してシャツ)A/コンベヤを前進させると
共に、二番目の荷受口にシュートを接続したのち、シャ
ツトルコンベヤの運転ヲ開始して、かつゲートを開く手
順を繰、返しながらホッパー庫にパラ物を積み込むので
、ホッパーを移動させたり、ホッパーに対するパラ物の
供給を休このため、パラ物の積み込み稼動率を向上させ
ることができる。
As described above, according to the freight car loading method for parallax goods according to the present invention, after connecting the chute of the shirt truck conveyor to the first cargo receiving port of the hopper car, the gate is opened and the loading conveyor and the shirt truck conveyor are operated. Start
The parallaxes from the carry-in conveyor are loaded into the hopper car through the hopper and shirt conveyor, and are weighed using a conveyor scale. When the total weight reaches the set value, the operation of the shirt conveyor is stopped. At the same time, the gate was closed, and then the connection between the cargo receiving port and the chute was released, and the shirt conveyor was moved forward. After connecting the chute to the second receiving port, the operation of the shirt conveyor was started. , and the steps of opening the gate are repeated to load the bulk goods into the hopper store, so the hopper can be moved or the supply of the bulk goods to the hopper can be stopped, so the loading operation rate of the bulk goods can be improved.

また、搬入コンベヤからホッパーにパラ物を投入して、
シャツトルコンベヤにより搬出するので、シャツトルコ
ンベヤの運転休止時ホッパーに搬入コンベヤからのパラ
物を溜めることができる。
In addition, parallaxes are put into the hopper from the carry-in conveyor,
Since the shirts are carried out by the shirttle conveyor, when the shirttle conveyor is not in operation, the hopper can store the parallaxes from the carry-in conveyor.

このため、撤入コンベヤの運転を一々休止する必要がな
い。
Therefore, there is no need to stop the operation of the withdrawal conveyor.

さらK、シャツトルコンベヤの輸送能力は、搬入コンベ
ヤよりも太くしであるので、シャツトルコンベヤの運転
休止にともないホッパーに溜ったパラ物を、上記ホッパ
ーが空となるよう排出することができる。
Furthermore, since the transportation capacity of the shirt conveyor is greater than that of the carry-in conveyor, it is possible to discharge the waste that has accumulated in the hopper due to suspension of operation of the shirt conveyor so that the hopper is empty.

このため、次にシャツ)A/コンベヤの運転を休止した
とき、ホッパーにパラ物を溜めることかで色る。
For this reason, the next time the conveyor is shut down, the hopper will be filled with parallaxes.

【図面の簡単な説明】[Brief explanation of drawings]

図面はこの発明の実施例を示すもので、第1図は縦断側
面図、第2図はホッパー車とシュートとの接続を示す縦
断拡大側面図である。 1・・・ホッパー車、2・・・ホッパー、3・・・搬入
コンベヤ、4・・・シャツトルコンベヤ、5・・・荷受
口、6・・・シュート、7・・・コンベヤスケール、8
・・・レール、9・・・レール、10・・・車輪、11
・・・フレキシブルチューブ、12・・・ゲート 特許出願人 巽   成 − 同 代理人 謙 出 文 二
The drawings show an embodiment of the present invention, and FIG. 1 is a longitudinal side view, and FIG. 2 is an enlarged longitudinal side view showing the connection between the hopper car and the chute. 1... Hopper car, 2... Hopper, 3... Loading conveyor, 4... Shirttle conveyor, 5... Receiving port, 6... Chute, 7... Conveyor scale, 8
...Rail, 9...Rail, 10...Wheel, 11
...Flexible tube, 12...Gate patent applicant: Sei Tatsumi - same agent: Ken Izumi 2

Claims (1)

【特許請求の範囲】[Claims] ホッパー車の手前上方に設けた定置式のホッパーと、こ
のホッパーにパラ物を投入するよう設け;&搬入:+ン
ベヤと、上記ホッパーのゲートとホッパー車との間に位
置すると共に、ホッパー車の走行方向に移動可能に設け
た搬入コンベヤよりも輸送能力の大きいシャツトルコン
ベヤと、このシャツトルコンベヤのヘッドにホッパー車
の荷受口と接続できるよう設けたシュートと、上記シャ
ツトルコンベヤのヘッド側に設ケたコンベヤスケールと
から成り、ホッパー車の一番目の荷受口にシュートを接
続したのち、ゲートを開くと共に搬入コンベヤ及びシャ
ツトルコンベヤの運転を開始して、上記搬入コンベヤか
らのパラ物を、ホッパー、シャツトルコンベヤをへてホ
ッパー車に積み込むと共に、コンベヤスケールによって
計量し、そして上記計量の総計が設定値になると、シャ
ツトルコンベヤの運転を停止するのと同時にゲートを閉
じ、その後に荷受口とシュートとの接続を解除してシャ
ツトルコンベヤを前進させると共に、二番目の荷受凸に
シュートを接続したのち、シャツトルコンベヤの運転を
開始するのと同時にゲートを開く手順を繰返しながらホ
ッパー車にパラ物を積み込むことを特徴とするパラ物の
貨車積み方法。
A stationary hopper is installed above the front of the hopper car, and the hopper is equipped to throw parallax into this hopper. A shirt conveyor that is movable in the traveling direction and has a larger transportation capacity than the loading conveyor, a chute that is provided at the head of the shirt conveyor so that it can be connected to a receiving port of a hopper car, and a chute that is installed on the head side of the shirt conveyor. After connecting the chute to the first loading port of the hopper car, the gate is opened and the loading conveyor and shirt truck conveyor are started, and the parallaxes from the loading conveyor are transported. The cargo is loaded onto the hopper car through the hopper and shirt conveyor, and is weighed using the conveyor scale. When the total weight reaches the set value, the operation of the shirt conveyor is stopped and the gate is closed at the same time. After disconnecting the shirt conveyor from the chute and moving the shirt conveyor forward, and connecting the chute to the second receiving convex, start operating the shirt conveyor and at the same time open the gate while repeating the procedure to move the shirt conveyor forward. A freight car loading method for parallax goods, which is characterized by loading parallax goods.
JP10017481A 1981-06-26 1981-06-26 Loading of bulk material onto freight cars Pending JPS582136A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10017481A JPS582136A (en) 1981-06-26 1981-06-26 Loading of bulk material onto freight cars

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10017481A JPS582136A (en) 1981-06-26 1981-06-26 Loading of bulk material onto freight cars

Publications (1)

Publication Number Publication Date
JPS582136A true JPS582136A (en) 1983-01-07

Family

ID=14266950

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10017481A Pending JPS582136A (en) 1981-06-26 1981-06-26 Loading of bulk material onto freight cars

Country Status (1)

Country Link
JP (1) JPS582136A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103863835A (en) * 2012-12-14 2014-06-18 山东中烟工业有限责任公司青岛卷烟厂 Burden distribution method for cigarette box

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS479223U (en) * 1971-02-19 1972-10-04
JPS50118465A (en) * 1974-03-08 1975-09-17

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS479223U (en) * 1971-02-19 1972-10-04
JPS50118465A (en) * 1974-03-08 1975-09-17

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103863835A (en) * 2012-12-14 2014-06-18 山东中烟工业有限责任公司青岛卷烟厂 Burden distribution method for cigarette box

Similar Documents

Publication Publication Date Title
US4923355A (en) System to feed and discharge materials continuously in operations to rehabilitate railway road beds and the like
US3756469A (en) Convertible hopper vehicle
US3651963A (en) Apparatus for loading bagged mail from a loading dock into a highway vehicle
EP2102083B1 (en) Loading and unloading device for receptacles, such as containers, silos and other filling spaces
US5400718A (en) Loading wagon for transport, storage and discharge of bulk material
US20120128442A1 (en) Container and container wagon
HU199917B (en) Carriage movable on truck for loading bulk material
US3198353A (en) Bulk material loading system
US3204797A (en) System for handling and transporting cargo
US1611882A (en) System and apparatus for handling freight
US3442404A (en) Method and apparatus for disposal of waste employing rail and off-road equipment
JPS582136A (en) Loading of bulk material onto freight cars
US5623811A (en) Process and device for packaging and supplying fiber material
JPS586842A (en) Freight car loading method of grain cargo
CN116281258A (en) Automatic train card loading system
JP2688868B2 (en) How to transfer luggage on a carrier
JPS5817024A (en) Method of loading bulk into freight car
JPS5811432A (en) Method of loading wagon with bulk cargo
US3306477A (en) Truck train
US2936910A (en) Portable storage plant
DE2260396A1 (en) TRANSPORT AND CONVEYOR DEVICE AND TRANSPORT AND CONVEYOR METHOD
CN114590543B (en) Freight integration system and control method thereof
CN221214297U (en) Double-box telescopic self-unloading trailer
CN217263450U (en) Simple train loader equipment
JPS5817025A (en) Method of loading bulk into freight car