JPS5820864A - Method of assembling tank scafford - Google Patents
Method of assembling tank scaffordInfo
- Publication number
- JPS5820864A JPS5820864A JP56118671A JP11867181A JPS5820864A JP S5820864 A JPS5820864 A JP S5820864A JP 56118671 A JP56118671 A JP 56118671A JP 11867181 A JP11867181 A JP 11867181A JP S5820864 A JPS5820864 A JP S5820864A
- Authority
- JP
- Japan
- Prior art keywords
- tank
- scaffolding
- roof
- block
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Movable Scaffolding (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
本発明はタンクの建設工事に使用する回転吊り足場の組
立方法に関する。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for assembling a rotating suspended scaffold for use in tank construction work.
内槽と外槽の間に保冷層を設けた二重殻タンクの建設工
事においては、タンク屋根の内周に沿い設けたレールを
使用して工事用足場をタンク内周に沿い移動自在に吊下
げ、該工事用足場を用いて保冷材の組付け、メンブレン
の張付け、点検等を行なっていた。When constructing a double-shell tank with a cold insulation layer between the inner tank and the outer tank, construction scaffolding is suspended along the inner circumference of the tank using rails installed along the inner circumference of the tank roof. They used the construction scaffolding to assemble cold insulation materials, attach membranes, and conduct inspections.
従来かかる工事のための工事用足場の組立ては、先ず地
上で足場ユニットを組立て、これを屋根に設けた工事孔
からタンク内に搬入し、次いでタンク底板上でこれら搬
入したユニットにより足場を組立て、最後に該組立てた
足場をタンク屋根内周のレールに吊下げていた。Conventionally, construction scaffolding for such construction work was assembled by first assembling scaffolding units on the ground, carrying these into the tank through a construction hole provided in the roof, and then assembling the scaffolding with these carried units on the tank bottom plate. Finally, the assembled scaffolding was suspended from a rail around the inner circumference of the tank roof.
しかしかかる従来の組立方法では、
(1)地上で組立てたユニットを屋根の工事孔を通して
搬入するので、該工事孔を大きくする必要がある。従っ
て大きな工事孔がとれないような場合には、適用できな
い。However, in such a conventional assembly method, (1) the unit assembled on the ground is brought in through a construction hole in the roof, so the construction hole needs to be enlarged. Therefore, it cannot be applied in cases where large construction holes cannot be made.
(11)高所作業が多く危険性が大である。(11) There is a lot of work at heights, which is very dangerous.
(iii)足場ユニットの組立のために別の足場が必要
となる。(iii) Separate scaffolding is required for assembly of the scaffolding unit.
等の問題点を有していた。It had the following problems.
本発明はかかる問題を解決するためになしたもので、作
業ステージや枠部材等の屋根部材をタンク内に搬入した
後タンク底板上でブロックに組立て、このブロックをタ
ンク屋根に設置されているホイストにより吊上げて該吊
上げだブロックの下に別のブロックを継ぎ足し、以後同
様にして次々とブロックを継ぎ足し吊上げて行くことを
特徴とするものである。The present invention was made to solve this problem, and after carrying roof members such as a work stage and frame members into the tank, they are assembled into blocks on the tank bottom plate, and the blocks are assembled into blocks by a hoist installed on the tank roof. It is characterized by lifting the block by adding another block under the lifted block, and subsequently adding blocks one after another in the same manner and lifting it up.
以下本発明の実施例を図面により説明する。Embodiments of the present invention will be described below with reference to the drawings.
第1図乃至第3図は本発明の実施例を示すもので、(1
)はタンク本体(外槽)、(2)は該タンク本体(1)
に設けた屋根、(3)は該屋根(2)に設けた工事孔、
(4)(ま工事用の回転吊り足場(5)をタンク本体(
1)の内壁面に沿い周方向に案内するため屋根(2)の
内側に円周方向に設けたレール、(6)は多数の枠部材
(6α)〜(6L)を連結して形成した2本の枠体、(
力は2本の枠体(6)間に配した作業ステージ、(8)
はレール(4)に走行自在に載置された工事用のホイス
トであり、該ホイスト(8)により回転吊り足場(5)
をタンク本体の内壁面に沿いカーテン式に移動させる。1 to 3 show embodiments of the present invention, (1
) is the tank body (outer tank), (2) is the tank body (1)
(3) is the construction hole provided in the roof (2),
(4) (Also, attach the rotating suspended scaffolding (5) to the tank body (
Rails (6) are provided in the circumferential direction inside the roof (2) for guiding in the circumferential direction along the inner wall surface of (1). The frame of the book, (
The force is applied to the work stage placed between the two frames (6), (8)
is a construction hoist mounted on a rail (4) so as to be freely movable, and the hoist (8) is used to rotate and suspend a scaffold (5).
is moved along the inner wall of the tank body in a curtain style.
又(9)は枠体(6)内に設−した作業用のエレベータ
、αO)は回転吊り足場(5)の組立時に用いる吊りワ
イヤ、01)は保冷材である。Further, (9) is a working elevator installed in the frame (6), αO) is a hanging wire used when assembling the rotating suspended scaffold (5), and 01) is a cold insulation material.
本発明の方法は、先ず、枠体(6)を形成するた)3)
タンク工事が終了した後、解体する場合は、口 虐−I
:I h 口 ↓日 lごIJ−4目コ 1 り品
Δ\ =二 II凶 し声 し h 姦vl−レートめ
の枠部材(6α)〜(6L)や多数の作業ステージ(7
)等の足場部材を工事孔(3)からタンク本体(1)内
に搬入して底板上に載置し、−組の枠部材(6a)と作
業ステージ(7)と・に、より1つの足場ブロックを組
立て、レール(4)上のホイスト(8)から吊りワイヤ
Qlを繰出し前記足場ブロックにづなぎ、該吊りワイヤ
(IIを巻取って前記足場ブロックを吊上げ、この吊上
げた第1の足場ブロックの下に、枠部材(6IJ)と作
業ステージ(7)とからなる第2の足場ブロックを継ぎ
足す。次に再びホイスト(8)にて所要高さまで吊上げ
、この吊上げた第2の足場ブロックの下に、枠部材(6
C)と作業ステージ(7)とからなる第3の足場ブロッ
クを継ぎ足し、以後同様にしてホイスト(8)にて吊上
げながら次次と足場ブロックを継ぎ足して行き、第3図
の如き回転吊り足場(5)を組立てる。In the method of the present invention, the frame body (6) is first formed.
:I h 口 ↓日 lgoIJ-4th item 1 item
Δ\ = 2
) and other scaffolding members are carried into the tank body (1) through the construction hole (3) and placed on the bottom plate, and one of the Assemble the scaffolding blocks, feed out the suspension wire Ql from the hoist (8) on the rail (4) and connect it to the scaffolding block, wind up the suspension wire (II) to lift the scaffolding block, and then lift the suspended first scaffolding. Add a second scaffolding block consisting of a frame member (6IJ) and a work stage (7) to the bottom of the block. Next, use the hoist (8) to lift it up to the required height again, and this lifted second scaffolding block Underneath the frame member (6
A third scaffolding block consisting of C) and work stage (7) is added, and in the same way, scaffolding blocks are added one after another while being hoisted by a hoist (8), until a rotating suspended scaffold ( 5) Assemble.
このようにして回転吊り足場(5ンが組立てられると、
該足場(5)を使用してタンク本体(1)への保
(部材01)の組付は作業、メンブレンの張付は作業等
の必要な諸作業を行なう。In this way, when the rotating suspended scaffold (5 tons) is assembled,
Use the scaffolding (5) to secure the tank body (1).
Necessary operations such as assembly of (member 01) and attachment of the membrane are performed.
(4)
〜(6t)・・・枠部材、(7)・・・作業ステージ、
(8)・・・ホイH凱巾ソ疋吻りJτliU孔こ逆Vノ
ナl狙V(よソm座5る。(4) ~(6t) Frame member, (7) Work stage,
(8)... Hui H Kaihin So Hijiri Jτli U Hole Reverse V Nona l Aim V (Yo Somza 5 Ru.
本発明は以上述べたように、作業ステージや枠部材等の
屋根部材をタンク底板上で組立て、ホイストにより吊上
げて下から順次継ぎ足すことにより回転吊り足場を組立
てる構成であるので、
(I)屋根の工事孔を小さくでき、広範囲のタンクに実
施できる。As described above, the present invention has a structure in which a rotating suspended scaffold is assembled by assembling roof members such as the work stage and frame members on the tank bottom plate, hoisting them up with a hoist, and sequentially adding pieces from the bottom. (I) Roof The construction hole can be made smaller and can be applied to a wide range of tanks.
(II)高所作業を少なくでき、作業の安全性を向上で
きる。(II) Work at heights can be reduced and work safety can be improved.
(ホ)足場組立てのための別の足場を不要にできる。(e) A separate scaffold for assembling the scaffold can be eliminated.
等の優れた効果を奏し得る。It can produce excellent effects such as
第1図及び第2図は本発明の実施例を示す説明図、第3
図は本発明の方法により組立てた足場の全体を示す説明
図である。
(1)・・・タンク本体、(2)・・・屋根、(3)・
・・工事孔、(4)・・・レール、(5)・・・回転吊
り足場、(6)・・・枠体、(6α)スト。
特許出願人
石川島播磨重工業株式会社
特許出願人
石川島タンク建設株式会社
第1頁の続き
■出 願 人 石川島タンク建紐株式会社東京都千代田
区平河町1丁目8
番13号(利用ビルディング)
や1 and 2 are explanatory diagrams showing embodiments of the present invention, and FIG.
The figure is an explanatory view showing the entire scaffold assembled by the method of the present invention. (1) Tank body, (2) Roof, (3)
...Construction hole, (4)...Rail, (5)...Rotating hanging scaffold, (6)...Frame, (6α) Strike. Patent Applicant Ishikawajima Harima Heavy Industries Co., Ltd. Patent Applicant Ishikawajima Tank Construction Co., Ltd. Continued from page 1 ■ Applicant Ishikawajima Tank Construction Co., Ltd. 1-8-13 Hirakawa-cho, Chiyoda-ku, Tokyo (Building used)
Claims (1)
入した後タンク底板上でブロックに組立て、このブロッ
クをタンク屋根に設置されているホイストにより吊上げ
て該吊上げだブロックの下に別のブロックを継ぎ足し、
以後同様にして次々とブロックを継ぎ足し吊上げて行く
ことを特徴とするタンク足場の組立方法。1) After carrying the work stage, frame members, and other roof members into the tank, assemble them into blocks on the tank bottom plate, lift this block with a hoist installed on the tank roof, and place another block under the hoisted block. by adding
A method for assembling tank scaffolding characterized by subsequently adding and lifting blocks one after another in the same manner.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP56118671A JPS5820864A (en) | 1981-07-29 | 1981-07-29 | Method of assembling tank scafford |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP56118671A JPS5820864A (en) | 1981-07-29 | 1981-07-29 | Method of assembling tank scafford |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS5820864A true JPS5820864A (en) | 1983-02-07 |
Family
ID=14742325
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP56118671A Pending JPS5820864A (en) | 1981-07-29 | 1981-07-29 | Method of assembling tank scafford |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS5820864A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS60184805U (en) * | 1984-05-19 | 1985-12-07 | ニチバン株式会社 | Binding machine |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS532712A (en) * | 1976-06-29 | 1978-01-11 | Kawasaki Heavy Ind Ltd | Assembling method and assembling foothold unit for dome shaped tank |
-
1981
- 1981-07-29 JP JP56118671A patent/JPS5820864A/en active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS532712A (en) * | 1976-06-29 | 1978-01-11 | Kawasaki Heavy Ind Ltd | Assembling method and assembling foothold unit for dome shaped tank |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS60184805U (en) * | 1984-05-19 | 1985-12-07 | ニチバン株式会社 | Binding machine |
JPH0110329Y2 (en) * | 1984-05-19 | 1989-03-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN210460016U (en) | Integrated form single power lift material platform | |
CN205575428U (en) | Component hoisting system | |
CN206844621U (en) | It is elevated from steady support job platform in a kind of elevator hoistways of shear wall structure | |
JPS5820864A (en) | Method of assembling tank scafford | |
WO2022233156A1 (en) | Method for disposing lifting power apparatus in attached lifting/lowering scaffold | |
CN214302804U (en) | Double-layer hanging basket of riding horse type | |
CN211545730U (en) | Hoist and mount precast beam positioner | |
JP3841242B2 (en) | Elevator parking elevating work table and construction method using it | |
JP2942054B2 (en) | How to build a building | |
CN212832466U (en) | Colliery automation equipment overhauls gallows | |
JPS6222904A (en) | Method of lifting steam drum | |
CN214611426U (en) | Transportation installation device of indoor large-scale equipment | |
CN211998557U (en) | Track type lifting machine tool on balcony beam | |
CN220909170U (en) | Convenient installation tool for lower hanging layer hanging column | |
CN113027146B (en) | Method for lifting and hoisting outer wall stone | |
CN206722407U (en) | A kind of integrated form carpenter machining shed | |
JPH07286368A (en) | Method and equipment for lifting up uppermost floor frame for constructing structure | |
JPS5912064A (en) | Method of construction of installation of elevator | |
JPS62148770A (en) | Construction method for hanging curtain wall | |
JPS5996358A (en) | Construction of steel structural roof or upper stair floor | |
JPS5934375A (en) | Hanging-down method of temporary roof | |
CN116477496A (en) | Integral installation process of pile-wound crane electrical room | |
JPS6128777U (en) | Crane suspension device | |
JPS6374884A (en) | Method of remodeling elevator | |
JPH0243928Y2 (en) |