JPH1161859A - Construction method and structure for underground structure - Google Patents

Construction method and structure for underground structure

Info

Publication number
JPH1161859A
JPH1161859A JP9243352A JP24335297A JPH1161859A JP H1161859 A JPH1161859 A JP H1161859A JP 9243352 A JP9243352 A JP 9243352A JP 24335297 A JP24335297 A JP 24335297A JP H1161859 A JPH1161859 A JP H1161859A
Authority
JP
Japan
Prior art keywords
underground
side wall
construction
continuous wall
constructed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP9243352A
Other languages
Japanese (ja)
Inventor
Tetsuji Sato
哲司 佐藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP9243352A priority Critical patent/JPH1161859A/en
Publication of JPH1161859A publication Critical patent/JPH1161859A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PROBLEM TO BE SOLVED: To save the labor and time for the execution of apex concrete and largely shorten the whole construction period by precedingly constructing the most apex of the side wall of an underground structure to be connected to the apex inner face of an underground continuous wall. SOLUTION: After an underground continuous wall 1 is constructed, the most apex 5 of the side wall 4 of an underground structure such as an LNG tank 21 is precedingly constructed to be connected to the apex inner face of the underground continuous wall 1 via connecting members 22. A region surrounded by the underground continuous wall 1 is excavated, and the remaining portion of the side wall 4 except for a base plate and the most apex 5 of the side wall 4 is constructed in the excavated space. The crest of the remaining portion except for the most apex 5 of the side wall 4 is integrated with the lower end of the most apex 5. The labor and time for the execution of apex concrete can be omitted, the construction period can be largely shortened, and this method contributes to the provision of a stable foundation bed in the post process.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、地中構造物、特に
LNGタンク等の地中構造物の構築方法及び構造に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method and structure for constructing an underground structure, particularly an underground structure such as an LNG tank.

【0002】[0002]

【従来の技術】恒温性、気密性、不燃性、防爆性、高剛
性などの地下特性を生かして地下空間が様々な用途に利
用されているが、石油地下備蓄、LNGやLPGのタン
ク、ガスタービン発電用の圧気貯蔵タンク、超伝導コイ
ル電力貯蔵、原子力発電所などのエネルギー施設につい
ても積極的な地下空間利用が実施あるいは検討されてい
る。
2. Description of the Related Art Underground spaces are used for various purposes by taking advantage of underground characteristics such as constant temperature, airtightness, nonflammability, explosion proof properties, and high rigidity. Underground oil storage, LNG and LPG tanks, gas Active use of underground space is also being implemented or examined for energy facilities such as compressed air storage tanks for turbine power generation, superconducting coil power storage, and nuclear power plants.

【0003】このような地下構造物、例えばLNGタン
クを構築するには、図7(a)の例に示すように、まずは
環状の地中連続壁1を工事当初の地盤面である地表9か
ら構築し、次いで、該地中連続壁1を土留め壁としなが
らそれに取り囲まれた内部空間2を掘り下げる。そし
て、該内部空間の底部に底板3を施工した後、該底板の
周縁から順次上方に向けて側壁4を一定高さ(ロット)
ごとに構築し、該側壁が最頂部5まで完成したならば、
該最頂部に屋根6を架け渡す。
In order to construct such an underground structure, for example, an LNG tank, first, as shown in an example of FIG. 7A, an annular underground continuous wall 1 is formed from a ground surface 9 which is a ground surface at the beginning of construction. Then, the interior space 2 surrounded by the underground continuous wall 1 is dug down while the underground continuous wall 1 is used as a retaining wall. After the bottom plate 3 is constructed on the bottom of the internal space, the side walls 4 are sequentially raised upward from the periphery of the bottom plate to a predetermined height (lot).
When the side wall is completed up to the top 5,
A roof 6 is hung over the top.

【0004】一方、これらの土木工事と並行してあるい
は土木工事終了後に必要な設備工事を行い、最後に盛土
8を施工してLNGタンクを完成させるのが一般的であ
る。
[0004] On the other hand, it is common practice to perform necessary facility work in parallel with or after the completion of the civil works, and finally to fill the embankment 8 to complete the LNG tank.

【0005】ここで、地中連続壁1の内部空間2を掘削
する際、該内部空間には当然ながらバックホウやブルド
ーザーといった掘削関連重機が搬入されるが、掘削され
た土砂を地上に搬出するためには、例えばテルハと呼ば
れる揚重機械を地中連続壁1の地表面近傍9に設置する
必要がある。また、掘削作業終了後には、引き続いて地
中構造物の側壁4を施工すべく、鉄筋篭や型枠を吊り込
むためのクレーン、型枠内にコンクリートを打設するた
めのミキサー車やポンプ車といった重機をやはり地中連
続壁1の地表面近傍9に設置しなければならない。
Here, when excavating the internal space 2 of the underground continuous wall 1, excavation-related heavy equipment such as a backhoe or a bulldozer is carried into the internal space, but it is necessary to carry out the excavated earth and sand to the ground. For example, it is necessary to install a lifting machine called Terha in the vicinity 9 of the ground surface of the underground continuous wall 1. Further, after the excavation work is completed, a crane for suspending a reinforced basket or a formwork, a mixer truck or a pump car for placing concrete in the formwork, to continuously construct the side wall 4 of the underground structure. Such heavy equipment must also be installed near the ground surface 9 of the underground continuous wall 1.

【0006】そのため、掘削作業に入る前に予め、同図
(b)に示すように地中連続壁1の頂部に鉢巻き状をなす
頭部コンクリート10を巻付け施工していた。
Therefore, before starting the excavation work,
As shown in (b), the head concrete 10 in the shape of a headband is wound around the top of the underground continuous wall 1.

【0007】かかる頭部コンクリート10によれば、地
中連続壁1の頂部における水平面内の曲げ剛性が向上す
るので、地表面近傍9に載荷される図示しない揚重機械
その他の荷重をしっかりと支持ことができるとともに、
安全な施工基盤が提供されることにもなる。
According to the head concrete 10, the bending rigidity in the horizontal plane at the top of the underground continuous wall 1 is improved, so that a lifting machine (not shown) loaded on the vicinity 9 of the ground surface and other loads are firmly supported. While being able to
It will also provide a safe construction base.

【0008】[0008]

【発明が解決しようとする課題】しかしながら、地中連
続壁1の構築工程と内部空間2の掘削工程との間に行わ
れる、このような頭部コンクリート10の施工工程は、
全体工程のなかではいわゆるクリティカルな工程とな
り、該頭部コンクリートの施工に要する約2〜3ヶ月が
そのまま、全体工期の遅延につながるという問題を生じ
ていた。
However, the construction process of such head concrete 10, which is performed between the construction process of the underground continuous wall 1 and the excavation process of the internal space 2, is as follows.
It is a so-called critical step in the whole process, and there has been a problem that about two to three months required for the construction of the head concrete leads to a delay in the whole construction period.

【0009】本発明は、上述した事情を考慮してなされ
たもので、頭部コンクリートの施工を省略して全体の工
期を短縮可能な地中構造物の構築方法及び構造を提供す
ることを目的とする。
The present invention has been made in consideration of the above circumstances, and has as its object to provide a method and a structure of an underground structure capable of shortening the entire construction period by omitting the construction of head concrete. And

【0010】[0010]

【課題を解決するための手段】上記目的を達成するた
め、本発明に係る地中構造物の構築方法は請求項1に記
載したように、地中連続壁を構築し、該地中連続壁の内
側に地中構造物を構築する地中構造物の構築方法におい
て、前記地中連続壁を構築後、前記地中構造物の側壁最
頂部を前記地中連続壁の頂部内面に相互接続する形で該
頂部内面に先行構築し、前記地中連続壁で囲まれた領域
を掘削し、掘削された空間内に底板及び前記側壁最頂部
を除く側壁残余部分を構築し、該側壁残余部分の天端を
前記側壁最頂部の下端に一体化するものである。
According to a first aspect of the present invention, there is provided a method for constructing an underground structure, comprising: constructing an underground continuous wall; In the method of constructing an underground structure inside an underground structure, after constructing the underground continuous wall, interconnecting a topmost side wall of the underground structure to a top inner surface of the underground continuous wall. Pre-constructing the inner surface of the top in a form, excavating an area surrounded by the underground continuous wall, constructing a bottom plate and a sidewall remaining portion excluding the top of the sidewall in the excavated space, The top end is integrated with the lower end of the top of the side wall.

【0011】また、本発明に係る地中構造物の構築方法
は、前記側壁最頂部に屋根吊上げ架台を構築し、前記側
壁残余部分の構築前若しくは構築中において前記空間内
で組み立てられた屋根を前記屋根吊上げ架台を利用して
吊り上げ、該屋根を前記側壁最頂部に架け渡すものであ
る。
Further, in the method of constructing an underground structure according to the present invention, a roof lifting stand is constructed at the top of the side wall, and the roof assembled in the space before or during the construction of the remaining portion of the side wall is constructed. The roof is lifted using the roof lifting base, and the roof is hung over the top of the side wall.

【0012】また、本発明に係る地中構造物の構築構造
は請求項3に記載したように、地中連続壁の内側に該地
中連続壁の内面に沿って地中構造物を構築する地中構造
物の構築構造において、前記地中構造物のうち、側壁最
頂部と該最頂部に対向する前記地中連続壁とを相互接続
したものである。
In the construction structure of an underground structure according to the present invention, the underground structure is constructed inside the underground continuous wall along the inner surface of the underground continuous wall. In the construction structure of an underground structure, a top of a side wall of the underground structure and the underground continuous wall facing the top are interconnected.

【0013】本発明に係る地中構造物の構築方法及び構
造においては、まずは地中連続壁を例えば環状に構築
し、しかる後に地中連続壁の頂部内面に地中構造物の側
壁最頂部を先行構築する。このとき、側壁最頂部が地中
連続壁の頂部内面に接続されるように施工する。
In the construction method and structure of an underground structure according to the present invention, the underground continuous wall is first constructed, for example, in an annular shape, and then the top of the underground structure side wall is formed on the inner surface of the underground continuous wall. Build ahead. At this time, the construction is performed so that the top of the side wall is connected to the inner surface of the top of the underground continuous wall.

【0014】このように、掘削作業前に地中構造物の側
壁最頂部をいわば逆巻き工法で地中連続壁の頂部内側に
鉢巻き状に先行施工しておくと、従来のように頭部コン
クリートを施工せずとも、地中連続壁の頂部における水
平面内の曲げ剛性を向上させることができるとともに、
後工程での安全な施工基盤が提供されることとなる。そ
して、かかる側壁最頂部は、いずれにしろ本体の一部と
して構築しなければならないものであるため、頭部コン
クリートを施工するために必要な期間や資材がそのまま
節約される。
As described above, if the top of the side wall of the underground structure is preliminarily constructed in the form of a headband inside the top of the underground continuous wall by the reverse winding method before the excavation work, the head concrete can be conventionally removed. Without construction, it is possible to improve the bending rigidity in the horizontal plane at the top of the underground continuous wall,
A safe construction base in the post-process will be provided. Since the top of the side wall must be constructed as a part of the main body anyway, a period and materials necessary for constructing the head concrete can be directly saved.

【0015】次に、前記地中連続壁で囲まれた内部領域
を掘削し、次いで、掘削された空間内に底板を施工す
る。次に、該底板の周縁から側壁最頂部を除く側壁残余
部分をいわば順巻き工法で構築する。
Next, the inside area surrounded by the underground continuous wall is excavated, and then a bottom plate is constructed in the excavated space. Next, the remaining portion of the side wall excluding the top of the side wall from the peripheral edge of the bottom plate is constructed by a so-called forward winding method.

【0016】次に、側壁残余部分の天端を側壁最頂部の
下端に一体化して地中構造物の躯体部分を完成させる。
Next, the top of the remaining portion of the side wall is integrated with the lower end of the top of the side wall to complete the skeleton of the underground structure.

【0017】ここで、側壁最頂部に屋根吊上げ架台を構
築し、側壁残余部分の構築前若しくは構築中において前
記空間内で組み立てられた屋根を屋根吊上げ架台を利用
して吊り上げ、該屋根を側壁最頂部に架け渡すようにす
れば、それ以降の内部空間の土木工事並びに設備工事を
全天候で行うことが可能となる。
Here, a roof lifting frame is constructed at the top of the side wall, and the roof assembled in the space before or during the construction of the remaining side wall portion is lifted using the roof lifting frame, and the roof is mounted on the side wall. If it is bridged to the top, it is possible to carry out civil engineering work and equipment work of the internal space thereafter in all weather.

【0018】屋根の組立は、底板施工前に掘削地盤上で
行ってもよいし、底板施工後に該底板上で行ってもよい
し、任意の空間位置で適当な支保工を使用しながら行っ
てもよい。
The roof may be assembled on the excavated ground before the construction of the bottom plate, may be performed on the bottom plate after the construction of the bottom plate, or may be performed at an arbitrary space position using an appropriate support. Is also good.

【0019】[0019]

【発明の実施の形態】以下、本発明に係る地中構造物の
構築方法及び構造の実施の形態について、添付図面を参
照して説明する。なお、従来技術と実質的に同一の部品
等については同一の符号を付してその説明を省略する。
BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of a method and structure for constructing an underground structure according to the present invention will be described below with reference to the accompanying drawings. It is to be noted that the same reference numerals are given to components and the like that are substantially the same as those in the conventional technology, and description thereof will be omitted.

【0020】図1は、本実施形態に係る地中構造物の構
築構造を示した部分拡大図である。同図でわかるよう
に、本実施形態の構築構造は、地中連続壁1の内側に地
中構造物としてのLNGタンク21が構築してあるが、
該LNGタンク21を構成する側壁4のうち、側壁最頂
部5と該最頂部に対向する地中連続壁1の頂部を接合部
材22を介して相互に接続してある。
FIG. 1 is a partially enlarged view showing a construction structure of an underground structure according to this embodiment. As can be seen from the figure, in the construction structure of the present embodiment, an LNG tank 21 as an underground structure is constructed inside the underground continuous wall 1,
Of the side walls 4 constituting the LNG tank 21, the top 5 of the side wall and the top of the continuous underground wall 1 facing the top are connected to each other via a joining member 22.

【0021】図2は、本実施形態に係る地中構造物の構
築方法の手順を示したフローチャートである。同図でわ
かるように、本実施形態に係る地中構造物の構築方法及
び構造においては、まずは環状の地中連続壁1を図3
(a)に示したように地表面9から地盤内に構築する(ス
テップ101)。ここで、地中連続壁1の構築にあたっ
ては、予め、その頂部内面に埋込み金物31を埋設して
おく。なお、地中連続壁1の中心軸線については、同図
では左方にあるものとする。
FIG. 2 is a flowchart showing a procedure of a method of constructing an underground structure according to the present embodiment. As can be seen from the figure, in the construction method and structure of the underground structure according to the present embodiment, first, the annular underground continuous wall 1 is placed in FIG.
As shown in (a), construction is performed in the ground from the ground surface 9 (step 101). Here, when constructing the underground continuous wall 1, an embedded metal member 31 is embedded in the top inner surface in advance. Note that the center axis of the underground continuous wall 1 is on the left side in FIG.

【0022】次に、同図(b)に示すように、地中連続壁
1の内側の地盤を適宜掘り下げて作業空間33を確保し
た後、該地中連続壁の頂部内面にLNGタンク21の側
壁最頂部5を環状に先行構築する(ステップ102)。
このとき、地中連続壁1の内面に設置された埋込み金物
31に予めスタッドボルト32を溶接して該金物ととも
に接合部材22とし、しかる後に必要な鉄筋及び型枠を
配設してコンクリートを打設し、スタッドボルト32を
側壁最頂部5のコンクリート躯体に定着させる。なお、
側壁最頂部5の下端には、予め縦筋34を下方に突出さ
せておく。
Next, as shown in FIG. 2B, after the ground inside the underground continuous wall 1 is dug down appropriately to secure a work space 33, the LNG tank 21 is placed on the inner surface of the top of the underground continuous wall. The top of the side wall 5 is preliminarily constructed in an annular shape (step 102).
At this time, a stud bolt 32 is welded in advance to the embedded metal member 31 installed on the inner surface of the underground continuous wall 1 to form a joining member 22 together with the metal member. Then, the stud bolt 32 is fixed to the concrete frame at the top 5 of the side wall. In addition,
At the lower end of the side wall top 5, a vertical streak 34 is projected in advance downward.

【0023】次に、図4(a)に示すように地中連続壁1
で囲まれた領域を掘削して内部空間2を形成し(ステッ
プ103)、次いで、同図(b)に示すように、掘削され
た空間2内の底部に底板41、42、43、44を順次
施工する(ステップ104)。
Next, as shown in FIG.
The area enclosed by is excavated to form an internal space 2 (step 103), and then, as shown in FIG. 2B, bottom plates 41, 42, 43, and 44 are provided at the bottom in the excavated space 2. Construction is performed sequentially (step 104).

【0024】次に、図5(a)に示すように、側壁4のう
ち最頂部5を除く側壁残余部分の構築を第3ロット51
を手始めとして順巻き工法で底板43から開始するとと
もに、屋根6を底板44の上で構築し、構築終了後、最
頂部5に取り付けられた屋根吊上げ架台54を用いて同
図矢印に示すように屋根6をリフトアップする(ステッ
プ105)。
Next, as shown in FIG. 5 (a), the construction of the remaining side wall except the top portion 5 of the side wall 4 is performed in the third lot 51.
Starting from the bottom plate 43 by the winding method, the roof 6 is constructed on the bottom plate 44, and after the construction is completed, as shown by the arrow in FIG. The roof 6 is lifted up (step 105).

【0025】次に、リフトアップされた屋根6を同図
(b)に示すように最頂部5に固定するとともに、側壁残
余部分については、第3ロット51に引き続いて、第4
ロット52、第5ロット53・・・と順次構築していく
(ステップ106)。
Next, the lifted roof 6 is shown in FIG.
(b) As shown in FIG.
A lot 52, a fifth lot 53, and so on are sequentially constructed (step 106).

【0026】なお、かかる段階では、資材56の搬出入
に用いる開口55を屋根6に設けておく。すなわち、屋
根6は、工事終了期間まで全天候型工事を可能にする屋
根として機能する。したがって、屋根6の組立及びリフ
トアップは、底板施工完了後、速やかに着手し、側壁残
余部分の工事は屋根6が最頂部5に架け渡された状態で
行われるのが望ましい。
At this stage, an opening 55 used for carrying in and out of the material 56 is provided in the roof 6. That is, the roof 6 functions as a roof that enables all-weather construction until the construction completion period. Therefore, it is desirable that the assembling and lift-up of the roof 6 be started immediately after the completion of the bottom plate construction, and that the construction of the remaining side wall be performed with the roof 6 spanned over the topmost portion 5.

【0027】次に、側壁残余部分の最後のロット56の
天端を、図6に示すように側壁最頂部5の下端に一体化
する(ステップ107)。すなわち、ロッド56のコン
クリート工事の際、最頂部5の下端に突出させておいた
縦筋34をロッド56のコンクリート躯体に定着させ
る。
Next, the top end of the last lot 56 in the remaining portion of the side wall is integrated with the lower end of the top portion 5 of the side wall as shown in FIG. 6 (step 107). That is, at the time of the concrete work of the rod 56, the vertical streaks 34 projecting from the lower end of the topmost portion 5 are fixed to the concrete body of the rod 56.

【0028】一方、これらの土木工事と並行してあるい
は土木工事終了後に必要な設備工事、例えば底板や屋根
あるいは側壁の保冷及びメンブレン工事並びに側部ヒー
タ工事をなどを行い、最後に盛土8を施工してLNGタ
ンク21を完成させる。
On the other hand, necessary equipment works such as cooling of the bottom plate, roof or side wall and membrane work and side heater work are performed in parallel with or after the civil work, and finally the embankment 8 is built. Then, the LNG tank 21 is completed.

【0029】以上説明したように、本実施形態に係る地
中構造物の構築方法及び構造によれば、掘削作業前にL
NGタンク21の側壁最頂部5をいわば逆巻き工法で地
中連続壁1の頂部内側に鉢巻き状に先行施工するように
したので、従来のように頭部コンクリートを施工せずと
も、地中連続壁1の頂部における水平面内の曲げ剛性を
向上させることができるとともにに、後工程での安全な
施工基盤が提供されることとなる。
As described above, according to the construction method and structure of the underground structure according to the present embodiment, L
Since the topmost portion 5 of the side wall of the NG tank 21 is precedently constructed in the form of a headband on the inside of the top of the underground continuous wall 1 by a reverse winding method, so that the underground continuous wall can be constructed without the need to construct the head concrete as in the related art. The bending rigidity in the horizontal plane at the top of the first part can be improved, and a safe construction base in a later process is provided.

【0030】そして、かかる側壁最頂部5は、いずれに
しろ本体側壁4の一部として構築しなければならないも
のであるため、頭部コンクリートを施工するために必要
な2〜3ヶ月の施工期間や必要な資材をそのまま省略す
ることができる。
Since the top portion 5 of the side wall must be constructed as a part of the side wall 4 of the main body anyway, the construction period of 2 to 3 months required for constructing the head concrete is required. Necessary materials can be omitted as it is.

【0031】また、従来であれば側壁4の最頂部5を施
工してからその養生期間として約1ヶ月が経過しなけれ
ば、屋根6を架けることができなかったが、本実施形態
によれば、地中連続壁1を構築している間に最頂部5の
養生が行われるので、ここにおいても約1ヶ月の工期短
縮を図ることができる。
In addition, according to the present embodiment, the roof 6 cannot be built until about one month has passed since the topmost portion 5 of the side wall 4 was constructed after the construction was completed. Since the top 5 is cured while the underground continuous wall 1 is being constructed, the construction period can be shortened by about one month.

【0032】また、本実施形態によれば、工事開始当初
に構築された最頂部5を利用して底板44上で構築され
た屋根6をリフトアップするとともにリフトアップされ
た屋根を最頂部5に架け渡すようにしたので、側壁残余
部分については、全天候で工事を行うことが可能とな
る。
According to this embodiment, the roof 6 constructed on the bottom plate 44 is lifted up by using the top 5 constructed at the beginning of the construction, and the lifted roof is moved to the top 5. Since the bridge is bridged, the remaining wall can be constructed in all weather.

【0033】本実施形態では、先行構築された最頂部を
利用して屋根をリフトアップさせるとともにリフトアッ
プさせた屋根を該最頂部に架け渡すようにしたが、かか
る構成にかえて、従来通りの手順、すなわち側壁の構築
がすべて完了してから最頂部に架け渡すようにしてもよ
い。かかる構成においては、全天候型の工事はできなく
なるが、頭部コンクリートを施工する手間を省くことが
できる点並びに最頂部の養生を待つ必要がない点につい
ては上述したと同様の効果を得ることができる。
In the present embodiment, the roof is lifted up by using the top constructed in advance, and the lifted roof is bridged over the top. However, instead of such a configuration, the conventional construction is adopted. The procedure, that is, the construction of the side wall may be completed, and then the bridge may be bridged to the top. In such a configuration, all-weather construction cannot be performed, but the same effect as described above can be obtained in that the labor for constructing the head concrete can be omitted and that there is no need to wait for curing at the top. it can.

【0034】また、本実施形態では、リフトアップされ
る屋根6を底板44上にてほぼ完成させ、リフトアップ
した後で最頂部5に接続するだけという前提で説明した
が、かかる工程が屋根6のリフトアップの遅れひいては
全天候型工事の開始の遅れにつながるのであれば、例え
ば、仮組みされたトラスの上に例えば透光性でかつ遮水
性の膜を張ったものを軽量仮設屋根として底板44上で
組み立て、しかる後にかかる軽量仮設屋根をリフトアッ
プして最頂部5に固定するようにしてもよい。
In this embodiment, the explanation is made on the premise that the roof 6 to be lifted up is almost completed on the bottom plate 44 and connected to the top 5 only after the lift up. For example, if a delay in lift-up and a delay in the start of all-weather construction would lead to a light-weight temporary roof, a truss with a light-transmitting and water-blocking film on a temporarily assembled truss, for example, may be used. The light-weight temporary roof may be lifted up and fixed to the top portion 5 after assembling above.

【0035】かかる構成によれば、仮設屋根の組立及び
リフトアップを速やかに行って全天候型工事を早期に導
入することができるとともに、本設の屋根工事について
は、仮組されたトラスを足場として側壁残余工事と並行
して行うことができるので、屋根のコンクリート工事及
びそれに続く防水工事に要する約8ヶ月にも及ぶ期間を
さらに短縮することが可能となる。
According to this configuration, the temporary roof can be quickly assembled and lifted up, so that all-weather construction can be introduced at an early stage, and the temporary roof truss can be used as a foothold for the main roof construction. Since it can be performed in parallel with the side wall residual work, it is possible to further reduce the period of about eight months required for the roof concrete work and the subsequent waterproof work.

【0036】[0036]

【発明の効果】以上述べたように、請求項1に係る本発
明の地中構造物の構築方法によれば、掘削作業前に地中
構造物の側壁最頂部をいわば逆巻き工法で地中連続壁の
頂部内側に鉢巻き状に先行施工するようにしたので、従
来のように頭部コンクリートを施工せずとも、地中連続
壁の頂部における水平面内の曲げ剛性を向上させること
ができるとともに、後工程での安全な施工基盤が提供さ
れることとなる。
As described above, according to the method of constructing an underground structure according to the first aspect of the present invention, before excavation work, the top of the side wall of the underground structure is continuously grounded by a reverse winding method. Since the head is pre-installed in the shape of a headband inside the top of the wall, it is possible to improve the bending rigidity in the horizontal plane at the top of the underground continuous wall without using the head concrete as in the past, and A safe construction base in the process will be provided.

【0037】そして、かかる側壁最頂部は、いずれにし
ろ本体側壁の一部として構築しなければならないもので
あるため、頭部コンクリートを施工するために必要な2
〜3ヶ月の施工期間や必要な資材をそのまま省略するこ
とができる。
Since the top of the side wall must be constructed as a part of the side wall of the main body anyway, it is necessary to construct the head concrete.
The construction period of up to three months and necessary materials can be omitted as it is.

【0038】また、従来であれば側壁の最頂部を施工し
てからその養生期間として約1ヶ月が経過しなければ、
屋根を架けることができなかったが、本実施形態によれ
ば、地中連続壁を構築している間に最頂部の養生が行わ
れるので、ここにおいても約1ヶ月の工期短縮を図るこ
とができる。
Also, in the conventional case, if about one month has not passed as the curing period after the top of the side wall has been constructed,
Although the roof could not be built, according to this embodiment, since the top is cured while the underground continuous wall is being constructed, the construction period can be reduced by about one month here. it can.

【0039】また、請求項2に係る本発明の地中構造物
の構築方法によれば、早期に構築された最頂部を利用し
て底板上で構築された屋根をリフトアップすることがで
きるので、側壁部分については、全天候で工事を行うこ
とが可能となるという効果も奏する。
According to the method of constructing an underground structure according to the second aspect of the present invention, the roof constructed on the bottom plate can be lifted up by using the top constructed earlier. On the side wall portion, there is an effect that construction can be performed in all weather.

【0040】また、請求項3に係る本発明の地中構造物
の構築構造によれば、地中連続壁の頂部内側に鉢巻き状
に相互接続された状態で構築された地中構造物の側壁最
頂部が、掘削作業前において、地中連続壁の頂部におけ
る水平面内の曲げ剛性を向上させること並びに後工程に
おける安定な支持基盤の提供に寄与する。
Further, according to the construction structure of the underground structure of the present invention according to the third aspect, the side wall of the underground structure constructed in a state of being connected in a headband shape inside the top of the underground continuous wall. The top portion contributes to improving the bending rigidity in the horizontal plane at the top portion of the underground continuous wall before the excavation operation and providing a stable support base in a post-process.

【0041】したがって、頭部コンクリートを施工する
手間を省くことが可能となり、2〜3ヶ月の工期短縮が
可能になるとともに、従来であれば側壁の最頂部を施工
してからその養生期間が経過しなければ、屋根を架ける
ことができなかったが、本発明によれば、地中連続壁を
構築している間に最頂部の養生を行えばよいので、ここ
においても約1ヶ月の工期短縮を図ることができる。
Therefore, it is possible to save the labor for constructing the head concrete, shorten the construction period of two to three months, and if the curing time has elapsed since the top of the side wall was conventionally constructed. Otherwise, the roof could not be built, but according to the present invention, it is only necessary to cure the top portion while the underground continuous wall is being constructed. Can be achieved.

【0042】[0042]

【図面の簡単な説明】[Brief description of the drawings]

【図1】本実施形態に係る地中構造物の構築構造を示し
た縦断面詳細図。
FIG. 1 is a detailed longitudinal sectional view showing a construction structure of an underground structure according to an embodiment.

【図2】本実施形態に係る地中構造物の構築方法の手順
を示したフローチャート。
FIG. 2 is a flowchart showing a procedure of a method of constructing an underground structure according to the embodiment.

【図3】本実施形態に係る地中構造物の構築方法の手順
に従って施工を行っている様子を示した図であり、(a)
は地中連続壁を構築している様子、(b)はその内側に地
中構造物であるLNGタンクの最頂部を先行構築してい
る様子をそれぞれ示した図。
FIG. 3 is a diagram showing a state in which construction is being performed according to a procedure of a method of constructing an underground structure according to the present embodiment, and FIG.
FIG. 3B is a diagram illustrating a state in which an underground continuous wall is being constructed, and FIG. 3B is a diagram illustrating a state in which the top of an LNG tank, which is an underground structure, has been constructed in advance.

【図4】引き続いて本実施形態に係る地中構造物の構築
方法の手順に従って施工を行っている様子を示した図で
あり、(a)は内部掘削を終えた様子、(b)は、内部空間の
底部に底板を施工した様子をそれぞれ示した図。
FIG. 4 is a view showing a state in which construction is being performed in accordance with a procedure of a method of constructing an underground structure according to the present embodiment, wherein (a) shows a state where internal excavation is completed, and (b) shows a state The figure which showed a mode that the bottom plate was constructed at the bottom of the internal space.

【図5】引き続いて本実施形態に係る地中構造物の構築
方法の手順に従って施工を行っている様子を示した図で
あり、(a)は側壁工事を順巻き工法で開始するととも
に、組み立てた屋根をリフトアップしている様子、(b)
はリフトアップした屋根を最頂部に固定するとともに、
側壁の工事を引き続き進行させている様子をそれぞれ示
した図。
FIG. 5 is a view showing a state in which construction is being performed in accordance with a procedure of a method of constructing an underground structure according to the present embodiment. FIG. Lifted up the roof, (b)
Fixes the lifted roof to the top,
The figure which showed a mode that the construction of the side wall was progressing continuously.

【図6】本実施形態に係る地中構造物の構築方法の手順
によって完成されたLNGタンクの全体図。
FIG. 6 is an overall view of an LNG tank completed by a procedure of a method of constructing an underground structure according to the embodiment.

【図7】従来技術に係る地中構造物の構築方法及び構造
を示した図であり、(a)は全体図、(b)は頂部近傍の詳細
図。
7A and 7B are diagrams showing a method and a structure of an underground structure according to the related art, wherein FIG. 7A is an overall view and FIG. 7B is a detailed view near the top.

【符号の説明】[Explanation of symbols]

1 地中連続壁 2 内部空間 4 側壁 5 最頂部(側壁) 6 屋根 21 LNGタンク 22 接合部材 31 埋込み金物(接合部材) 32 スタッドボルト(接合部
材) 41〜44 底板 51〜56 ロット(側壁)
DESCRIPTION OF SYMBOLS 1 Underground continuous wall 2 Internal space 4 Side wall 5 Top part (side wall) 6 Roof 21 LNG tank 22 Joining member 31 Embedded metal (joining member) 32 Stud bolt (joining member) 41-44 Bottom plate 51-56 lot (side wall)

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 地中連続壁を構築し、該地中連続壁の内
側に地中構造物を構築する地中構造物の構築方法におい
て、 前記地中連続壁を構築後、前記地中構造物の側壁最頂部
を前記地中連続壁の頂部内面に相互接続する形で該頂部
内面に先行構築し、前記地中連続壁で囲まれた領域を掘
削し、掘削された空間内に底板及び前記側壁最頂部を除
く側壁残余部分を構築し、該側壁残余部分の天端を前記
側壁最頂部の下端に一体化することを特徴とする地中構
造物の構築方法。
1. An underground structure construction method for constructing an underground continuous wall and constructing an underground structure inside the underground continuous wall, wherein the underground structure is constructed after the underground continuous wall is constructed. Preceding the inner surface of the underground continuous wall by interconnecting the top of the side wall of the object to the inner surface of the underground continuous wall, excavating an area surrounded by the underground continuous wall, and installing a bottom plate and a bottom plate in the excavated space. A method of constructing an underground structure, comprising: constructing a remaining portion of the side wall except for the top of the side wall, and integrating a top end of the remaining portion of the side wall with a lower end of the top of the side wall.
【請求項2】 前記側壁最頂部に屋根吊上げ架台を構築
し、前記側壁残余部分の構築前若しくは構築中において
前記空間内で組み立てられた屋根を前記屋根吊上げ架台
を利用して吊り上げ、該屋根を前記側壁最頂部に架け渡
す請求項1記載の地中構造物の構築方法。
2. A roof lifting frame is constructed at the top of the side wall, and a roof assembled in the space before or during the construction of the remaining portion of the side wall is lifted using the roof lifting frame, and the roof is lifted. The method for constructing an underground structure according to claim 1, wherein the underground structure extends over the top of the sidewall.
【請求項3】 地中連続壁の内側に該地中連続壁の内面
に沿って地中構造物を構築する地中構造物の構築構造に
おいて、 前記地中構造物のうち、側壁最頂部と該最頂部に対向す
る前記地中連続壁とを相互接続したことを特徴とする地
中構造物の構築構造。
3. A construction structure of an underground structure for constructing an underground structure inside an underground continuous wall along an inner surface of the underground continuous wall, wherein the underground structure includes: A construction structure of an underground structure, wherein the underground continuous wall facing the top is interconnected.
JP9243352A 1997-08-25 1997-08-25 Construction method and structure for underground structure Withdrawn JPH1161859A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9243352A JPH1161859A (en) 1997-08-25 1997-08-25 Construction method and structure for underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9243352A JPH1161859A (en) 1997-08-25 1997-08-25 Construction method and structure for underground structure

Publications (1)

Publication Number Publication Date
JPH1161859A true JPH1161859A (en) 1999-03-05

Family

ID=17102565

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9243352A Withdrawn JPH1161859A (en) 1997-08-25 1997-08-25 Construction method and structure for underground structure

Country Status (1)

Country Link
JP (1) JPH1161859A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010174486A (en) * 2009-01-28 2010-08-12 Ohbayashi Corp Method for constructing side wall of underground tank structure
JP2016169474A (en) * 2015-03-11 2016-09-23 大成建設株式会社 Vertical shaft, underground storage tank, construction method for vertical shaft, and construction method for underground storage tank

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010174486A (en) * 2009-01-28 2010-08-12 Ohbayashi Corp Method for constructing side wall of underground tank structure
JP2016169474A (en) * 2015-03-11 2016-09-23 大成建設株式会社 Vertical shaft, underground storage tank, construction method for vertical shaft, and construction method for underground storage tank

Similar Documents

Publication Publication Date Title
JP5422793B2 (en) Low temperature storage construction method
CN106088780A (en) The cast-in-place concrete pylon of pre-made void reinforcement bar truss mould plate and construction method thereof
JPH1150480A (en) Rebuilding method of building
US5119598A (en) Method of construction of top slab for a nuclear containment building
JPH1161859A (en) Construction method and structure for underground structure
JPH0932349A (en) Construction method of building
JP3888564B2 (en) Construction method of underground structure
JP6893134B2 (en) Building construction method
JP2002235328A (en) Cofferdam method
JPH05107381A (en) Method for constructing nuclear power plant reactor
JP3078805B1 (en) Construction method of nuclear power facilities
JPH01268971A (en) Transfer construction of masonry wall body of existing structure
JP2010174486A (en) Method for constructing side wall of underground tank structure
JP2003056186A (en) H-shape steel frame construction method in sill lifting and hauling work of wooden building using h-shape steel, specially-made anchor fitting and specially-made fine adjustment fitting in conformity with structural characteristic of wooden building
JPH04161565A (en) Construction of large space building
JP2004176434A (en) Method for constructing structure and underground skeleton
CN215254559U (en) Prefabricated formwork system for pouring basement wallboard structure
JPH08218628A (en) Construction of roof for cylindrical structure
JP2873139B2 (en) Condenser construction method for nuclear power plant turbine building.
CN102704399A (en) Reinforcement binding and jointing operating room and reinforcement binding and jointing method
JPH09281268A (en) Method for constructing turbine building of atomic power plant
JPH01178680A (en) Construction of dome roofing
JP4378241B2 (en) Vertical loading test method for existing piles
JP2000098079A (en) Method for constructing reactor power plant
JPH04297615A (en) Construction of caisson bottom slab

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20041102