JP3888564B2 - Construction method of underground structure - Google Patents
Construction method of underground structure Download PDFInfo
- Publication number
- JP3888564B2 JP3888564B2 JP24792697A JP24792697A JP3888564B2 JP 3888564 B2 JP3888564 B2 JP 3888564B2 JP 24792697 A JP24792697 A JP 24792697A JP 24792697 A JP24792697 A JP 24792697A JP 3888564 B2 JP3888564 B2 JP 3888564B2
- Authority
- JP
- Japan
- Prior art keywords
- continuous wall
- underground
- underground continuous
- roof
- constructed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Filling Or Discharging Of Gas Storage Vessels (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、地中構造物、特にLNGタンク等の地中構造物の構築方法に関する。
【0002】
【従来の技術】
恒温性、気密性、不燃性、防爆性、高剛性などの地下特性を生かして地下空間が様々な用途に利用されているが、石油地下備蓄、LNGやLPGのタンク、ガスタービン発電用の圧気貯蔵タンク、超伝導コイル電力貯蔵、原子力発電所などのエネルギー施設についても積極的な地下空間利用が実施あるいは検討されている。
【0003】
このような地下構造物、例えばLNGタンクを構築するには、図7の例に示すように、まずは環状の地中連続壁1を工事当初の地盤面である地表9から構築し、次いで、該地中連続壁1を土留め壁としながらそれに取り囲まれた内部空間2を掘り下げる。そして、該内部空間の底部に底板3を施工した後、該底板の周縁から順次上方に向けて側壁4を一定高さ(ロット)ごとに構築し、該側壁が最頂部まで完成したならば、該最頂部に屋根6を架け渡す。
【0004】
一方、これらの土木工事と並行してあるいは土木工事終了後に必要な設備工事を行い、最後に盛土8を施工してLNGタンクを完成させるのが一般的である。
【0005】
【発明が解決しようとする課題】
ここで、屋根6の架け渡し作業は、通常、全体工程の中でもかなり後半に行われるので、地中連続壁1の内部空間2の掘削工事をはじめ、底板3や側壁4の施工工事が当然ながら屋外での作業となる。
【0006】
そのため、炎天下での過酷な作業環境を招いて作業効率が低下したり、降雨や降雪といった悪天候によって工程が大幅に遅延するといったことが生じ、工事の合理化を図る上では屋外での工事期間を短縮することが不可欠となっていた。
【0007】
本発明は、上述した事情を考慮してなされたもので、天候の影響をできるだけ回避して工事の合理化を図ることが可能な地中構造物の構築方法を提供することを目的とする。
【0008】
【課題を解決するための手段】
上記目的を達成するため、本発明に係る地中構造物の構築方法は請求項1に記載したように、地中連続壁を構築し、該地中連続壁の内側に地中構造物を構築する地中構造物の構築方法であって、前記地中連続壁を構築後、該地中連続壁の頂部近傍に屋根を架け渡して前記地中連続壁の内側上方を覆い、しかる後に、前記地中連続壁で囲まれた掘削空間内に前記地中構造物の躯体を施工する地中構造物の構築方法において、
前記屋根を架け渡す際、前記地中連続壁の頂部外周であって該地中連続壁に相互接続される形で補強体を予め構築するとともに、前記屋根の周囲を構成する縁部を前記地中連続壁及び前記補強体の天端に予め構築し、しかる後、前記屋根が前記縁部に接続されるように前記地中連続壁の頂部に架け渡し、
前記躯体を施工する際、該躯体を構成する底版を前記掘削空間内の底部に施工するとともに、前記躯体を構成する側壁を前記底版から上方に向けて立設し、該側壁の天端を前記縁部に一体化するものである。
また、本発明に係る地中構造物の構築方法は請求項2に記載したように、地中連続壁を構築し、該地中連続壁の内側に地中構造物を構築する地中構造物の構築方法であって、前記地中連続壁を構築後、該地中連続壁の頂部近傍に屋根を架け渡して前記地中連続壁の内側上方を覆い、しかる後に、前記地中連続壁で囲まれた掘削空間内に前記地中構造物の躯体を施工する地中構造物の構築方法において、
前記屋根を架け渡す際、前記地中連続壁の頂部内側であって前記躯体を構成する側壁の最頂部となる位置にかつ前記地中連続壁に相互接続される形で所定の補強体を予め構築し、前記屋根が前記補強体に接続されるように前記地中連続壁の頂部に架け渡し、
前記躯体を施工する際、該躯体を構成する底版を前記掘削空間内の底部に施工するとともに、前記側壁を前記底版から上方に向けて立設して前記補強体に一体化することで該補強体を前記側壁の最頂部とするものである。
【0009】
また、本発明に係る地中構造物の構築方法は、前記地中連続壁で囲まれた領域の掘削作業を前記屋根の架け渡しの後に行うものである。
【0012】
本発明に係る地中構造物の構築方法においては、地中連続壁を構築後、まずは該地中連続壁の頂部近傍に屋根を架け渡し、地中連続壁の内側上方を覆う。次に、地中連続壁で囲まれた掘削空間内に地中構造物の躯体を施工する。
【0013】
このようにすると、地中構造物の躯体工事においては、先行施工された屋根によって掘削空間への降雨や降雪あるいは直射日光を遮ることが可能となり、該躯体工事をいわゆる全天候で進めることが可能となる。
【0014】
地中連続壁で囲まれた領域の掘削作業を屋根の架け渡しの前に行うか後に行うかは任意であるが、該掘削作業を前記屋根の架け渡しの後に行うようにすれば、掘削作業も全天候で行うことができるとともに、屋根の架け渡し作業を、地上に立設した屋根構築用足場を利用して行うことが可能となり、屋根の架け渡しが高所作業となるのを回避することができる。
【0015】
また、屋根を架け渡す際、地中連続壁の頂部外周であって該地中連続壁に相互接続される形で補強体を予め構築するとともに、屋根の周囲を構成する縁部を、地中連続壁及び補強体の天端に予め構築し、しかる後、屋根が縁部に接続されるように地中連続壁の頂部に架け渡し、躯体を施工する際、該躯体を構成する底版を掘削空間内の底部に施工するとともに、躯体を構成する側壁を底版から上方に向けて立設し、該側壁の天端を縁部に一体化するようにすれば、屋根重量を支持する際や、地中連続壁の外側近傍に設置された重機の重量を支持する際の補強とすることができる。
【0016】
また、屋根を架け渡す際、地中連続壁の頂部内側であって躯体を構成する側壁の最頂部となる位置にかつ地中連続壁に相互接続される形で所定の補強体を予め構築し、屋根が補強体に接続されるように地中連続壁の頂部に架け渡し、躯体を施工する際、該躯体を構成する底版を掘削空間内の底部に施工するとともに、側壁を底版から上方に向けて立設して補強体に一体化するようにすれば、屋根重量を支持する際の補強とすることができる。
加えて、躯体工事終了後に補強体を撤去する必要がなくなるし、該補強体を躯体の一部として有効利用することも可能となる。
【0017】
【発明の実施の形態】
以下、本発明に係る地中構造物の構築方法の実施の形態について、添付図面を参照して説明する。なお、従来技術と実質的に同一の部品等については同一の符号を付してその説明を省略する。
【0018】
図1は、本実施形態に係る地中構造物の構築方法の手順を示したフローチャートである。同図でわかるように、本実施形態の構築方法においては、まず、従来技術で説明したと同様の地中連続壁1を円筒状に構築する(ステップ101)。
【0019】
次に、図2(a)に示すように、地中連続壁1の頂部外周に該地中連続壁に相互接続される形で鉢巻き状の補強体11をRC造として構築する(ステップ102)。なお、地中連続壁1や補強体11の天端には接続用差し筋12、13を予め埋設しておく。
【0020】
次に、図2(b)に示すように、屋根6の周囲を構成する縁部14を地中連続壁1及び補強体11の天端に構築する(ステップ103)。このとき、地中構造物の側壁4に一体化するための差し筋16を下方に突出させておく。
【0021】
次に、図3に示すように、地中連続壁1の内側を必要に応じて若干掘り下げ、その地面22上に屋根構築用足場21を組み立てる(ステップ104)。
【0022】
次に、縁部14に屋根6を接続することによって、該屋根を地中連続壁1の頂部に架け渡し、地中連続壁1の内側上方を覆う(ステップ105)。
【0023】
次に、屋根6の養生期間を待って屋根構築用足場21を解体し、しかる後に、図4に示すように、地中連続壁1で囲まれた領域を掘り下げる(ステップ106)。掘削された土砂については、屋根6に形成された搬出入用仮開口31を介して地上に搬出する。
【0024】
次いで、図5に示すように、掘削された空間2内の底部に底版41、42、43、44を順次施工するとともに、引き続いて円筒状の側壁4を底版43から順巻き工法、すなわち上方に向けて立設する(ステップ107)。
【0025】
なお、側壁4は、高さ数mのロット単位で構築していくのがよい。また、底版41〜44並びに側壁4に必要な資材あるいは不要となった資材については、搬出入用仮開口31を介して随時搬出入すればよい。
【0026】
次に、側壁4の天端を図3で説明した縁部14と一体化し、側壁4の施工を完了する(ステップ108)。なお、搬出入用仮開口31は、保冷工事等の内部設備工事等の工程を適宜考慮して、適当な時期に塞いでおく。
【0027】
以上説明したように、本実施形態に係る地中構造物の構築方法によれば、先行施工された屋根6によって掘削空間2への降雨や降雪あるいは直射日光を遮ることが可能となり、底版41〜44を敷設する工事及び側壁4を立ち上げる工事をいわゆる全天候で進めることが可能となる。
【0028】
また、本実施形態によれば、掘削作業を屋根6の架け渡しの後に行うようにしたので、地中連続壁1で囲まれた領域を掘削する作業も全天候で行うことができるとともに、屋根6の架け渡し作業を、地上に立設した屋根構築用足場21を利用して行うことが可能となり、屋根の架け渡しが高所作業となるのを回避することができる。
【0029】
また、本実施形態によれば、地中連続壁1の頂部に該地中連続壁に相互接続される形で補強体11を構築し、屋根6をその縁部14を介して地中連続壁1及び補強体11に固定するようにしたので、屋根6の重量を支持する際の補強となるとともに、地中連続壁1の頂部の水平剛性が増加するので、図4のように地中連続壁1の外側近傍に重機32を据え付けた場合にも、該重機の重量を十分に支持することが可能となる。
【0030】
本実施形態では、掘削作業を屋根6の架け渡しの後に行うようにしたが、掘削作業を全天候で行う必要がないのであれば、地中連続壁で囲まれた領域の掘削作業を屋根の架け渡しの前に行ってもかまわない。
【0031】
かかる構成における屋根の架け渡し方法としては、例えば、掘削終了後、地中連続壁1で囲まれた掘削空間底面にて屋根6を組み立て、しかる後に、該屋根6を例えば地中連続壁の頂部に設けた反力架台で反力をとりながらリフトアップし、これを縁部14に接続するようにするのがよい。なお、屋根6を組み立てる時期については、底版41〜44を施工する前でもよいし、施工した後でもよい。
【0032】
また、本実施形態では、鉢巻き状の補強体11を予め構築し、該補強体と地中連続壁1の上に屋根6の縁部14を構築するようにしたが、強度上問題がないのあれば、補強体11を省略して屋根6の縁部14を地中連続壁1にのみ接続するようにしてもよい。
【0033】
また、本実施形態では、補強体11を地中連続壁1の外周に構築するようにしたが、これに代えて図6に示すように、地中連続壁1の頂部内側に補強体51を構築するようにしてもよい。かかる構成において、補強体51を側壁4の最頂部となる位置に構築しておけば、躯体工事完了後は、補強体51が該側壁4の最頂部を構成することとなり、該補強体を撤去する必要もなくなるし、躯体の一部として有効利用することも可能となる。
【0034】
なお、かかる構成においても、上述の実施形態で述べたステップ104〜105と同様、地中連続壁1の内側を必要に応じて若干掘り下げ、その地面22上に屋根構築用足場21を組み立て、しかる後に、補強体51に屋根6を接続して地中連続壁1の頂部近傍に架け渡し、地中連続壁1の内側上方を覆うようにすればよい。
【0035】
【発明の効果】
以上述べたように、本発明に係る地中構造物の構築方法によれば、先行施工された屋根によって掘削空間への降雨や降雪あるいは直射日光を遮ることが可能となり、底版を敷設する工事及び側壁を立ち上げる工事をいわゆる全天候で進めることが可能となる。
特に、請求項1に係る本発明の地中構造物の構築方法によれば、屋根の重量を支持する際の補強となるとともに、地中連続壁の頂部の水平剛性が増加するので、地中連続壁の外側近傍に重機を据え付けた場合にも、該重機の重量を十分に支持することが可能となるという効果も奏する。
また、請求項2に係る本発明の地中構造物の構築方法によれば、屋根の重量を支持する際の補強となるとともに、補強体を撤去する必要もなくなり、躯体の一部として有効利用することも可能となるという効果も奏する。
【0036】
また、請求項3に係る本発明の地中構造物の構築方法によれば、地中連続壁で囲まれた領域を掘削する作業も全天候で行うことができるとともに、屋根の架け渡し作業を、地上に立設した屋根構築用足場を利用して行うことが可能となり、屋根の架け渡しが高所作業となるのを回避することができる。
【0039】
【図面の簡単な説明】
【図1】本実施形態に係る地中構造物の構築方法の手順を示したフローチャート。
【図2】本実施形態に係る地中構造物の構築方法の施工手順を示した図であり、(a)は、地中連続壁1の近傍に補強体11を構築した様子、(b)は地中連続壁1及び補強体11の上に屋根6の縁部14を構築した様子をそれぞれ示した図。
【図3】引き続き本実施形態に係る地中構造物の構築方法の施工手順を示した図であり、地中連続壁1の内側の地面22に屋根構築用足場21を組み立てた様子を示した図。
【図4】引き続き本実施形態に係る地中構造物の構築方法の施工手順を示した図であり、屋根6を架け渡した後で地中連続壁1で囲まれた領域を掘削している様子を示した図。
【図5】引き続き本実施形態に係る地中構造物の構築方法の施工手順を示した図であり、掘削された空間2内に地中構造物の躯体、すなわち底版41〜44を施工するとともに底版43から側壁4を順巻きで立設している様子を示した図。
【図6】変形例に係る地中構造物の構築方法を示したものであり、地中連続壁1の内側に側壁4の一部となる補強体51を先行施工した様子を示した図。
【図7】地中構造物である従来のLNGタンクを示した縦断面図。
【符号の説明】
1 地中連続壁
4 側壁
6 屋根
11 補強体
14 縁部(屋根)
21 屋根構築用足場
41〜44 底版(地中構造物の躯体)
51 補強体(地中構造物の躯体、側壁)[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method for constructing underground structures, particularly underground structures such as LNG tanks.
[0002]
[Prior art]
Underground space is used for various applications by taking advantage of underground properties such as constant temperature, air tightness, incombustibility, explosion proof, high rigidity, etc., but oil underground storage, LNG and LPG tanks, pressurized air for gas turbine power generation Active use of underground space is being implemented or studied for energy facilities such as storage tanks, superconducting coil power storage, and nuclear power plants.
[0003]
In order to construct such an underground structure, for example, an LNG tank, as shown in the example of FIG. 7, first, an annular underground
[0004]
On the other hand, it is common to perform necessary facilities work in parallel with these civil works or after completion of the civil works, and finally, the embankment 8 is constructed to complete the LNG tank.
[0005]
[Problems to be solved by the invention]
Here, since the work of spanning the
[0006]
As a result, the harsh working environment under hot weather may lead to a decrease in work efficiency or a significant delay in the process due to bad weather such as rain or snowfall. It was essential to do.
[0007]
The present invention has been made in consideration of the above-described circumstances, and an object of the present invention is to provide a construction method of an underground structure that can avoid the influence of the weather as much as possible and can rationalize the construction.
[0008]
[Means for Solving the Problems]
In order to achieve the above object, the underground structure construction method according to the present invention constructs an underground continuous wall as described in
When spanning the roof, a reinforcing body is preliminarily constructed in the form of being interconnected to the underground continuous wall at the top outer periphery of the underground continuous wall, and the edges constituting the periphery of the roof are formed on the ground. Pre-constructed at the top of the middle continuous wall and the reinforcing body, and then spans the top of the underground continuous wall so that the roof is connected to the edge,
When constructing the housing, the bottom plate constituting the housing is constructed at the bottom of the excavation space, the side walls constituting the housing are erected upward from the bottom plate, and the top end of the side wall is It is integrated with the edge.
Moreover, the construction method of the underground structure according to the present invention is as described in
When spanning the roof, a predetermined reinforcing body is preliminarily provided at a position on the inner side of the top of the underground continuous wall and at the top of the side wall constituting the housing and interconnected to the underground continuous wall. Build and span the top of the underground continuous wall so that the roof is connected to the reinforcement,
When constructing the frame, the bottom plate constituting the frame is constructed at the bottom of the excavation space, and the side wall is erected upward from the bottom plate to be integrated with the reinforcement. The body is the top of the side wall.
[0009]
Moreover, the construction method of the underground structure which concerns on this invention performs the excavation operation | work of the area | region enclosed by the said underground continuous wall after spanning of the said roof.
[0012]
In the underground structure building method according to the present invention, after building the underground continuous wall, first, a roof is bridged near the top of the underground continuous wall to cover the upper inside of the underground continuous wall. Next, the underground structure frame is constructed in the excavation space surrounded by the underground continuous wall.
[0013]
In this way, in the underground construction of the underground structure, it is possible to block rain, snowfall or direct sunlight in the excavation space by the roof that was previously constructed, and it is possible to proceed with the construction in all-weather conditions. Become.
[0014]
It is optional whether the excavation work in the area surrounded by the underground continuous wall is performed before or after the roof is bridged. However, if the excavation work is performed after the roof is bridged, the excavation work is performed. Can be done in all weather, and it is possible to carry out the work of building the roof by using a roof construction scaffold standing on the ground, and avoiding the work of building the roof to work at a high place. Can do.
[0015]
In addition, when the roof is built, a reinforcing body is preliminarily constructed in the form of being interconnected to the underground continuous wall at the top outer periphery of the underground continuous wall, and the edges constituting the periphery of the roof are Pre-constructed at the top of the continuous wall and the reinforcement body, and then over the top of the underground continuous wall so that the roof is connected to the edge, when excavating the bottom plate that constitutes the frame when constructing the frame When constructing at the bottom in the space, standing up the side wall constituting the frame from the bottom plate upwards, and integrating the top end of the side wall with the edge, when supporting the roof weight, It can be a reinforcement for supporting the weight of heavy equipment installed near the outside of the underground continuous wall.
[0016]
In addition, when the roof is built, a predetermined reinforcing body is built in advance at a position inside the top of the underground continuous wall and at the top of the side wall constituting the frame and interconnected to the underground continuous wall. When constructing the frame so that the roof is connected to the reinforcement body, the bottom plate constituting the frame is constructed at the bottom of the excavation space, and the side wall is directed upward from the bottom plate. If it stands up and it is made to integrate with a reinforcement body, it can be set as reinforcement at the time of supporting a roof weight.
In addition, it is not necessary to remove the reinforcing body after the housing construction is completed, and the reinforcing body can be effectively used as a part of the housing.
[0017]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, an embodiment of a construction method of an underground structure according to the present invention will be described with reference to the accompanying drawings. Note that components that are substantially the same as those of the prior art are assigned the same reference numerals, and descriptions thereof are omitted.
[0018]
FIG. 1 is a flowchart showing the procedure of the underground structure construction method according to the present embodiment. As can be seen from the figure, in the construction method of the present embodiment, first, the underground
[0019]
Next, as shown in FIG. 2 (a), a headband-shaped reinforcing body 11 is constructed as an RC structure in the form of being interconnected to the underground continuous wall on the outer periphery of the top of the underground continuous wall 1 (step 102). . In addition, connecting reinforcing bars 12 and 13 are embedded in advance at the top ends of the underground
[0020]
Next, as shown in FIG.2 (b), the edge part 14 which comprises the circumference | surroundings of the
[0021]
Next, as shown in FIG. 3, the inside of the underground
[0022]
Next, by connecting the
[0023]
Next, the
[0024]
Next, as shown in FIG. 5,
[0025]
The
[0026]
Next, the top end of the
[0027]
As explained above, according to the construction method of the underground structure according to the present embodiment, it becomes possible to block rain, snowfall or direct sunlight to the
[0028]
Further, according to the present embodiment, the excavation work is performed after the
[0029]
Further, according to the present embodiment, the reinforcing body 11 is constructed at the top of the underground
[0030]
In this embodiment, the excavation work is performed after the
[0031]
As a method for bridging the roof in such a configuration, for example, after excavation is completed, the
[0032]
In this embodiment, the headband-shaped reinforcing body 11 is constructed in advance, and the edge portion 14 of the
[0033]
Moreover, in this embodiment, although the reinforcement body 11 was constructed | assembled in the outer periphery of the underground
[0034]
Even in such a configuration, as in
[0035]
【The invention's effect】
As described above, according to the construction method of the underground structure according to the present invention, it is possible to block rain, snowfall or direct sunlight into the excavation space by the previously constructed roof, and the construction of laying the bottom plate and The construction for raising the side walls can be carried out in so-called all weather.
In particular, according to the construction method of the underground structure of the present invention according to
Moreover, according to the construction method of the underground structure of this invention which concerns on
[0036]
Further, according to the construction method of the underground structure of the present invention according to
[0039]
[Brief description of the drawings]
FIG. 1 is a flowchart showing a procedure of a construction method of an underground structure according to the present embodiment.
FIG. 2 is a diagram showing a construction procedure of a construction method for an underground structure according to the present embodiment, in which (a) shows a state in which a reinforcing body 11 is constructed in the vicinity of the underground
FIG. 3 is a diagram showing a construction procedure of the underground structure building method according to the present embodiment, and shows a state in which a
FIG. 4 is a diagram showing a construction procedure of the underground structure building method according to the present embodiment, and excavating a region surrounded by the underground
FIG. 5 is a diagram showing the construction procedure of the underground structure construction method according to the present embodiment, and constructing the underground structure frame, that is, bottom plates 41 to 44 in the excavated
FIG. 6 is a view showing a construction method of an underground structure according to a modified example, and shows a state in which a reinforcing
FIG. 7 is a longitudinal sectional view showing a conventional LNG tank which is an underground structure.
[Explanation of symbols]
DESCRIPTION OF
21. Scaffolds for roof construction 41-44 Bottom plate (frame of underground structure)
51 Reinforcing body (Body of underground structure, side wall)
Claims (3)
前記屋根を架け渡す際、前記地中連続壁の頂部外周であって該地中連続壁に相互接続される形で補強体を予め構築するとともに、前記屋根の周囲を構成する縁部を前記地中連続壁及び前記補強体の天端に予め構築し、しかる後、前記屋根が前記縁部に接続されるように前記地中連続壁の頂部に架け渡し、
前記躯体を施工する際、該躯体を構成する底版を前記掘削空間内の底部に施工するとともに、前記躯体を構成する側壁を前記底版から上方に向けて立設し、該側壁の天端を前記縁部に一体化することを特徴とする地中構造物の構築方法。An underground structure construction method for constructing an underground continuous wall and constructing an underground structure inside the underground continuous wall, wherein after the underground continuous wall is constructed, the top of the underground continuous wall Construction of an underground structure that covers a roof in the vicinity and covers the upper inside of the underground continuous wall, and then constructs the structure of the underground structure in an excavation space surrounded by the underground continuous wall In the method
When spanning the roof, a reinforcing body is preliminarily constructed in the form of being interconnected to the underground continuous wall at the top outer periphery of the underground continuous wall, and the edges constituting the periphery of the roof are formed on the ground. Pre-constructed at the top of the middle continuous wall and the reinforcing body, and then spans the top of the underground continuous wall so that the roof is connected to the edge,
When constructing the housing, the bottom plate constituting the housing is constructed at the bottom of the excavation space, the side walls constituting the housing are erected upward from the bottom plate, and the top end of the side wall is A construction method of an underground structure characterized by being integrated with an edge.
前記屋根を架け渡す際、前記地中連続壁の頂部内側であって前記躯体を構成する側壁の最頂部となる位置にかつ前記地中連続壁に相互接続される形で所定の補強体を予め構築し、前記屋根が前記補強体に接続されるように前記地中連続壁の頂部に架け渡し、
前記躯体を施工する際、該躯体を構成する底版を前記掘削空間内の底部に施工するとともに、前記側壁を前記底版から上方に向けて立設して前記補強体に一体化することで該補強体を前記側壁の最頂部とすることを特徴とする地中構造物の構築方法。An underground structure construction method for constructing an underground continuous wall and constructing an underground structure inside the underground continuous wall, wherein after the underground continuous wall is constructed, the top of the underground continuous wall Construction of an underground structure that covers a roof in the vicinity and covers the upper inside of the underground continuous wall, and then constructs the structure of the underground structure in an excavation space surrounded by the underground continuous wall In the method
When spanning the roof, a predetermined reinforcing body is preliminarily provided at a position on the inner side of the top of the underground continuous wall and at the top of the side wall constituting the housing and interconnected to the underground continuous wall. Build and span the top of the underground continuous wall so that the roof is connected to the reinforcement,
When constructing the frame, the bottom plate constituting the frame is constructed at the bottom of the excavation space, and the side wall is erected upward from the bottom plate to be integrated with the reinforcement. A construction method of an underground structure, characterized in that a body is the top of the side wall.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP24792697A JP3888564B2 (en) | 1997-08-28 | 1997-08-28 | Construction method of underground structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP24792697A JP3888564B2 (en) | 1997-08-28 | 1997-08-28 | Construction method of underground structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH1171775A JPH1171775A (en) | 1999-03-16 |
JP3888564B2 true JP3888564B2 (en) | 2007-03-07 |
Family
ID=17170610
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP24792697A Expired - Fee Related JP3888564B2 (en) | 1997-08-28 | 1997-08-28 | Construction method of underground structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3888564B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008232187A (en) * | 2007-03-16 | 2008-10-02 | Ohbayashi Corp | Underground cryogenic liquefied gas storage tank and method for designing it |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5223701B2 (en) * | 2009-01-28 | 2013-06-26 | 株式会社大林組 | Construction method of side wall of underground tank structure |
CN104060830B (en) * | 2014-06-13 | 2015-05-06 | 长江勘测规划设计研究有限责任公司 | Method for lifting and transporting large parts of underground nuclear power station |
JP6474653B2 (en) * | 2015-03-13 | 2019-02-27 | 公益財団法人鉄道総合技術研究所 | Connection structure for new and existing underground structures |
-
1997
- 1997-08-28 JP JP24792697A patent/JP3888564B2/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008232187A (en) * | 2007-03-16 | 2008-10-02 | Ohbayashi Corp | Underground cryogenic liquefied gas storage tank and method for designing it |
Also Published As
Publication number | Publication date |
---|---|
JPH1171775A (en) | 1999-03-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5422793B2 (en) | Low temperature storage construction method | |
RU2430295C2 (en) | Reservoir for storage of cryogenic liquids | |
EP2711487B1 (en) | Concentrated solar tower assembly and method | |
JP5946579B1 (en) | Storage tank structure and storage method | |
US3106772A (en) | Method of erecting buildings, tanks, domes or similar structures | |
JP3888564B2 (en) | Construction method of underground structure | |
JP5348559B2 (en) | Above-ground cryogenic tank and its construction method | |
JP2015036493A (en) | Method for constructing underground storage tank | |
JP4702674B1 (en) | Construction method of underground tank | |
JP5207086B2 (en) | Construction method of underground tank | |
JPH04161566A (en) | Constructing apparatus for large space building | |
JPH09281268A (en) | Method for constructing turbine building of atomic power plant | |
JP2000297476A (en) | Building method for dome structure | |
JP4853430B2 (en) | Construction method of underground tank, underground tank constructed by the construction method, and formwork apparatus | |
JP2612804B2 (en) | How to build an amorphous tall building | |
JPH04161565A (en) | Construction of large space building | |
CN115821955A (en) | Double-splayed internal oppositely-supported large-space light single-wall box-jacketed steel cofferdam and construction method | |
JP5239634B2 (en) | Construction method of underground tank structure | |
JP2538759B2 (en) | Basement and how to build a basement | |
JPH0762925A (en) | Construction method for concrete outer tank low-temperature tank | |
JP2008115614A (en) | Construction method for concrete roof | |
JPH06212829A (en) | Method of constructing roof for tank | |
JPH10227194A (en) | Construction method of shaft | |
TW202332826A (en) | Method for constructing triple-shell tank | |
TW202332825A (en) | Method for constructing triple-shell tank |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20040402 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20060421 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060426 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20060623 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20061110 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20061123 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091208 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101208 Year of fee payment: 4 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101208 Year of fee payment: 4 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111208 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121208 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121208 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131208 Year of fee payment: 7 |
|
LAPS | Cancellation because of no payment of annual fees |