JPH1129942A - Head part structure of cast-in-place steel pipe concrete pile, and its work execution method - Google Patents

Head part structure of cast-in-place steel pipe concrete pile, and its work execution method

Info

Publication number
JPH1129942A
JPH1129942A JP18773497A JP18773497A JPH1129942A JP H1129942 A JPH1129942 A JP H1129942A JP 18773497 A JP18773497 A JP 18773497A JP 18773497 A JP18773497 A JP 18773497A JP H1129942 A JPH1129942 A JP H1129942A
Authority
JP
Japan
Prior art keywords
steel pipe
anchoring
cast
bar
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP18773497A
Other languages
Japanese (ja)
Other versions
JP3096660B2 (en
Inventor
Koji Mori
康治 森
Kenzo Aoki
健三 青木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MARUGO KISO KOGYO KK
Original Assignee
MARUGO KISO KOGYO KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MARUGO KISO KOGYO KK filed Critical MARUGO KISO KOGYO KK
Priority to JP09187734A priority Critical patent/JP3096660B2/en
Publication of JPH1129942A publication Critical patent/JPH1129942A/en
Application granted granted Critical
Publication of JP3096660B2 publication Critical patent/JP3096660B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To improve the joining strength of a pile head part with a footing by arranging a lower part of an anchoring bar formed of high strength reinforcement close to an inner surface of a steel pipe, and extending an upper part to the construction position of the footing to improve the holding force of the anchoring bar. SOLUTION: A lock nut 32 is welded to an inner circumferential surface of a steel pipe 1 to be installed in the ground 7, a lower part of an anchoring bar 2 consisting of a threaded and knotted reinforcement is threaded therein, the interval (d) between the anchoring bar 2 and the steel pipe 1 is arranged to be within 1.5 times the diameter D of the anchoring bar 2, an upper part of the anchoring bar 2 is extended to the construction position of a footing, and the lock nut 31 as an anchoring member is threaded to an upper end. The anchoring bar 2 is a high strength reinforcement of >=490 N/mm<2> in yield point, and fixed to the steel pipe 1 before the concrete placement or after removing the chamber concrete after placement. The lower anchoring bar may be connected to the upper one at the position close to the upper end of the steel pipe 1 by a coupler. The holding force of the anchoring bar 2 is improved, and the joining strength of the pile head part with the footing can be improved.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、杭頭部を鋼管コン
クリート杭で構成した場所打鋼管コンクリート杭の杭頭
部構造及びその施工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a pile head structure of a cast-in-place steel pipe concrete pile having a pile head made of a steel pipe concrete pile, and a method of constructing the pile head structure.

【0002】[0002]

【従来の技術】建築構造物の高層化等に伴い、従来の場
所打コンクリート杭の耐震性をより一層向上するため
に、図6に示すように、場所打コンクリート杭108の
うち大きい曲げモーメントや剪断力を受ける杭頭部等を
鋼管コンクリート杭110で構成した場所打鋼管コンク
リート杭(複合場所打杭)が用いられている。
2. Description of the Related Art In order to further improve the seismic resistance of a conventional cast-in-place concrete pile with the rise of building structures, as shown in FIG. A cast-in-place concrete pipe pile (composite cast-in-place pile) in which a pile head or the like subjected to shearing force is constituted by a steel pipe concrete pile 110 is used.

【0003】ところで、この鋼管コンクリート杭110
からなる杭頭部とフーチング109の接合構造として、
従来より、 (1) 鉄筋籠方式 (2) ひげ筋方式 (3) カプラー方式 等が提案され、実用化されてきている。
[0003] By the way, this steel pipe concrete pile 110
As the joint structure of the pile head consisting of
Conventionally, (1) rebar cage method (2) whiskers method (3) coupler method and the like have been proposed and put into practical use.

【0004】上記(1)〜(3)の鋼管コンクリート杭110
からなる杭頭部とフーチング109の接合構造は、いず
れも、鋼管コンクリート杭110のフーチング109へ
の突出長さを最小限度に止め、主として鉄筋(本明細書
において、「定着筋」という。)を用いて定着を行うも
のである。
[0004] The steel pipe concrete pile 110 of the above (1) to (3)
In any case, the joint structure between the pile head made of and the footing 109 minimizes the protruding length of the steel pipe concrete pile 110 to the footing 109 and mainly serves as a reinforcing bar (hereinafter, referred to as “anchoring bar”). Is used for fixing.

【0005】このうち、(1)の鉄筋籠方式は、図7
(a)に示すように、場所打鋼管コンクリート杭を構成
する鋼管101の内部に、あらかじめ組み立てた鉄筋籠
102aを挿入するとともに、鉄筋籠102aの上端を
フーチング109の構築位置まで延出するようにして仮
止めした後、鋼管101の内部にコンクリート106を
打設することにより固定し、鉄筋籠102aを定着筋と
して利用するものである。
[0005] Among them, the rebar cage method of (1) is shown in FIG.
As shown in (a), a pre-assembled reinforced basket 102a is inserted into a steel pipe 101 constituting a cast-in-place steel pipe concrete pile, and the upper end of the reinforced basket 102a is extended to a construction position of a footing 109. After being temporarily fixed, the concrete 106 is fixed by pouring the concrete 106 into the inside of the steel pipe 101, and the rebar basket 102a is used as a fixing bar.

【0006】また、(2)のひげ筋方式は、図7(b)に
示すように、先付け又は後付けにより、場所打鋼管コン
クリート杭を構成する鋼管101の外周面に、略等間隔
に、定着筋102bの下端部を溶接するとともに、この
定着筋102bの上端をフーチング109の構築位置ま
で延出するものである。
In the beard streak method (2), as shown in FIG. 7 (b), it is fixed on the outer peripheral surface of a steel pipe 101 constituting a cast-in-place steel pipe concrete pile at substantially regular intervals by pre-installation or post-installation. The lower end of the streak 102b is welded, and the upper end of the fixing streak 102b is extended to the position where the footing 109 is constructed.

【0007】また、(3)のカプラー方式は、図7(c)
に示すように、場所打鋼管コンクリート杭を構成する鋼
管101の外周面に、略等間隔に、カプラー103を溶
接しておき、余盛りコンクリートを除去した後に、カプ
ラー103にねじふし鉄筋からなる定着筋102cの下
端部を螺合し、グラウト材の注入又はロックナットによ
る締め付けを行って固定するとともに、この定着筋10
2cの上端をフーチング109の構築位置まで延出する
ものである。
[0007] The coupler system of (3) is shown in FIG.
As shown in the figure, the coupler 103 is welded to the outer peripheral surface of the steel pipe 101 constituting the cast-in-place steel pipe concrete pile at substantially equal intervals, and after removing the excess concrete, the coupler 103 is fixed to the coupler 103 with a threaded reinforcing bar. The lower end of the streak 102c is screwed in, fixed by performing grout injection or tightening with a lock nut.
2c is extended to the construction position of the footing 109.

【0008】[0008]

【発明が解決しようとする課題】ところで、上記(1)〜
(3)の接合構造のうち、(1)の鉄筋籠方式は、最も低コス
トで、信頼性の高い構造ではあるが、近年の建築構造物
の高層化等に伴い、単独で用いられることは少なく、通
常、(2)のひげ筋方式や(3)のカプラー方式と併用して用
いられており、このため、定着筋を固定するために溶接
作業を伴うので、作業効率及び作業性が低く、コストを
要するという問題があった。なお、この鉄筋籠方式の場
合、鉄筋籠102aと鋼管101との間隔は、通常、鉄
筋の直径の3.0〜3.5倍程度に設定するようにして
いるが、その構造上、間隔を正確に設定することが困難
であった。また、(2)のひげ筋方式及び(3)のカプラー方
式は、定着筋102b,102cを鋼管101の外周面
に直接又はカプラー103を介して、それぞれ溶接の接
合力のみによって固定するものであるため、現在要請さ
れている鋼管コンクリート杭110に対する定着筋の保
持力の向上を、コストを上昇させることなく実現するこ
とには限界があった。
[Problems to be Solved by the Invention] By the way, the above (1) to
Of the joining structures in (3), the reinforced cage method in (1) is the lowest cost and highly reliable structure, but it cannot be used alone due to the recent rise in building structures. It is usually used in combination with the beard streak method of (2) and the coupler method of (3), which requires welding work to fix the anchoring streaks, resulting in low work efficiency and workability. However, there is a problem that costs are required. In addition, in the case of this rebar cage method, the interval between the rebar cage 102a and the steel pipe 101 is usually set to about 3.0 to 3.5 times the diameter of the rebar, but due to its structure, the interval is set to be about 3.0 to 3.5 times. It was difficult to set accurately. Further, in the beard streak method (2) and the coupler method (3), the fixing streaks 102b and 102c are fixed to the outer peripheral surface of the steel pipe 101 directly or via the coupler 103, respectively, only by welding bonding force. For this reason, there is a limit in realizing the currently required improvement in the holding power of the anchoring bars for the steel pipe concrete pile 110 without increasing the cost.

【0009】本発明は、上記従来の鋼管コンクリート杭
からなる杭頭部とフーチングの接合構造の有する問題点
に鑑み、鋼管コンクリート杭に対する定着筋の保持力の
向上を、コストを上昇させることなく実現可能とした場
所打鋼管コンクリート杭の杭頭部構造及びその施工法を
提供することを目的とする。
The present invention has been made in view of the above-mentioned problems of the joint structure between a pile head and a footing made of a steel pipe concrete pile, and has realized an improvement in the holding force of anchoring bars to the steel pipe concrete pile without increasing the cost. It is an object of the present invention to provide a pile head structure of a cast-in-place steel pipe concrete pile and a construction method thereof.

【0010】[0010]

【課題を解決するための手段】上記目的を達成するた
め、本発明の場所打鋼管コンクリート杭の杭頭部構造
は、場所打鋼管コンクリート杭を構成する鋼管の内周面
に、略等間隔に、高強度鉄筋からなる定着筋の下部を、
定着筋と鋼管との間隔を定着筋の直径の1.5倍以内に
設定して配設するとともに、該定着筋の上部をフーチン
グの構築位置まで延出するようにしたことを特徴とす
る。
In order to achieve the above object, the pile head structure of the cast-in-place steel pipe concrete pile according to the present invention is provided on the inner peripheral surface of the steel pipe constituting the cast-in-place steel pipe concrete pile at substantially regular intervals. , The lower part of the anchoring muscle consisting of high-strength rebar,
The distance between the anchoring muscle and the steel pipe is set to be within 1.5 times the diameter of the anchoring muscle, and the upper part of the anchoring muscle is extended to the footing construction position.

【0011】この場所打鋼管コンクリート杭の杭頭部構
造は、場所打鋼管コンクリート杭を構成する鋼管の内周
面に、略等間隔に、高強度鉄筋からなる定着筋の下部
を、定着筋と鋼管との間隔を定着筋の直径の1.5倍以
内に設定して配設することにより、鉄筋籠方式と比較し
て、定着筋の本数を多くすることができるとともに、鋼
管の内部に打設するコンクリートによる定着筋の保持力
を向上することができる。また、高強度鉄筋からなる定
着筋を用いることにより、鋼管コンクリート杭からなる
杭頭部とフーチングとを所要の強度でもって接合するた
めに要する定着筋の本数を低減することができるととも
に、これにより、定着筋の下部を、定着筋と鋼管との間
隔を定着筋の直径の1.5倍以内に設定して配設したこ
とと相俟って、隣接する定着筋間の間隔を大きく取るこ
とができる。
The pile head structure of the cast-in-place steel pipe concrete pile has a structure in which the lower part of the anchoring bar made of high-strength steel is fixed to the inner peripheral surface of the steel pipe constituting the cast-in-place steel pipe concrete pile at substantially regular intervals. By setting the distance from the steel pipe to within 1.5 times the diameter of the anchoring bar, the number of anchoring bars can be increased as compared with the reinforced cage system, and the steel bar can be punched inside the steel pipe. The holding power of the anchoring streaks by the concrete to be provided can be improved. In addition, by using anchoring bars made of high-strength rebar, it is possible to reduce the number of anchoring bars required to join a pile head made of a steel pipe concrete pile and a footing with a required strength. In addition to the arrangement of the lower portion of the anchoring muscle with the spacing between the anchoring muscle and the steel pipe set within 1.5 times the diameter of the anchoring muscle, the clearance between adjacent anchoring muscles should be increased. Can be.

【0012】この場合において、定着筋を下部定着筋と
上部定着筋とで構成するとともに、該下部定着筋及び上
部定着筋を、鋼管の上端近傍位置で、接続部材により接
続するように構成することができる。ここで、定着筋に
ねじふし鉄筋を用いた場合には、接続部材として、カプ
ラーを用いることができる。
In this case, the anchoring muscle is constituted by a lower anchoring muscle and an upper anchoring muscle, and the lower anchoring muscle and the upper anchoring muscle are connected by a connecting member at a position near the upper end of the steel pipe. Can be. Here, when a screw bar is used as the fixing bar, a coupler can be used as the connecting member.

【0013】これにより、場所打鋼管コンクリート杭を
構築し、余盛りコンクリートの除去作業を行った後、場
所打鋼管コンクリート杭に埋設された下部定着筋に接続
部材を介して上部定着筋を接続することができ、このた
め、余盛りコンクリートの除去作業を効率よく行うこと
ができるとともに、余盛りコンクリートの除去作業時に
定着筋を損傷する等の事故が発生することを未然に防止
することができる。
[0013] Thus, after constructing the cast-in-place steel pipe concrete pile and performing the work of removing the excess concrete, the upper setter is connected to the lower setter buried in the cast-in-place concrete pile via the connecting member. Therefore, the work of removing excess concrete can be efficiently performed, and the occurrence of accidents such as damage to anchoring bars during the removal of excess concrete can be prevented.

【0014】また、外周面を異形(「ねじふし」を含
む。)に形成した接続部材を用いることができる。
Further, a connection member having an outer peripheral surface formed in a deformed shape (including a "screw wiper") can be used.

【0015】これにより、接続部材とコンクリートとの
一体性を向上することができる。
[0015] Thereby, the integrity of the connection member and the concrete can be improved.

【0016】また、高強度鉄筋には、降伏点490N/
mm2以上の鉄筋(JIS Z 2241による。)を用
いることが望ましい。
The high-strength rebar has a yield point of 490 N /
It is desirable to use a reinforcing bar of mm 2 or more (according to JIS Z 2241).

【0017】これにより、従来広く使用されている鉄筋
(降伏点390N/mm2)を使用する場合と比較し
て、定着筋の本数を大幅に低減することができる。
As a result, the number of fixing streaks can be significantly reduced as compared with the case where a reinforcing bar (yield point: 390 N / mm 2 ) which has been widely used in the past is used.

【0018】また、定着筋に、ねじふし鉄筋を用いるこ
とができる。
Further, a screw bar can be used as the fixing bar.

【0019】これにより、現場における定着筋の接続等
の作業を簡略化することができ、作業効率を向上するこ
とができるとともに、コンクリートとの一体性を向上す
ることができる。
This makes it possible to simplify the work such as connection of anchoring streaks on site, thereby improving work efficiency and improving the integration with concrete.

【0020】また、定着筋の少なくとも一端部に定着部
材を配設することができる。ここで、定着部材は、定着
筋の上端部及び/又は下端部に配設し、また、定着筋に
ねじふし鉄筋を用いた場合には、定着部材として、ロッ
クナット、カプラー等の雌ねじ部材を用いることができ
る。
Further, a fixing member can be provided at at least one end of the fixing streaks. Here, the fixing member is disposed at an upper end and / or a lower end of the fixing streaks. When a screw bar is used as the fixing streaks, a female screw member such as a lock nut or a coupler is used as the fixing member. Can be used.

【0021】これにより、定着部材が定着筋のアンカー
となり、鋼管コンクリート杭からなる杭頭部とフーチン
グの接合強度を向上することができる。
Accordingly, the anchoring member serves as an anchor for the anchoring streaks, and the joining strength between the pile head made of steel pipe concrete pile and the footing can be improved.

【0022】また、接続部材又は定着筋の下端部に配設
する定着部材を、鋼管の内周面に溶接することができ
る。
Further, the connecting member or the fixing member provided at the lower end of the fixing streak can be welded to the inner peripheral surface of the steel pipe.

【0023】これにより、鋼管に対する定着筋の固定を
高い信頼性をもって行うことができる。
Thus, the anchoring streak can be fixed to the steel pipe with high reliability.

【0024】また、同じ目的を達成するため、本発明の
場所打鋼管コンクリート杭の杭頭部の施工法は、場所打
鋼管コンクリート杭を構成する鋼管の内周面に、略等間
隔に高強度鉄筋からなる下部定着筋を、下部定着筋と鋼
管との間隔を下部定着筋の直径の1.5倍以内に設定し
て配設した状態でコンクリートを打設し、場所打鋼管コ
ンクリート杭を構築した後、下部定着筋の上端部に配し
た接続部材に高強度鉄筋からなる上部定着筋を接続し、
該上部定着筋をフーチングの構築位置まで延出してコン
クリートを打設し、フーチングを構築することを特徴と
する。
Further, in order to achieve the same object, the method of constructing a pile head of a cast-in-place steel pipe concrete pile according to the present invention employs a high-strength steel pipe at substantially equal intervals on the inner peripheral surface of a steel pipe constituting the cast-in-place steel pipe concrete pile. Concrete is cast in a state where the lower anchoring bar made of reinforcing steel is arranged with the distance between the lower anchoring bar and the steel pipe set to within 1.5 times the diameter of the lower anchoring bar, and a cast-in-place steel pipe concrete pile is constructed. After that, connect the upper anchoring bar made of high-strength steel to the connecting member arranged at the upper end of the lower anchoring bar,
The footing is constructed by extending the upper anchoring streaks to the footing construction position and casting concrete.

【0025】この場所打鋼管コンクリート杭の杭頭部の
施工法は、高強度鉄筋からなる定着筋を用いることによ
り、鋼管コンクリート杭からなる杭頭部とフーチングと
を所要の強度でもって接合するために要する定着筋の本
数を低減することができるとともに、これにより、定着
筋の下部を、定着筋と鋼管との間隔を定着筋の直径の
1.5倍以内に設定して配設したことと相俟って、隣接
する定着筋間の間隔を大きく取ることができ、現場にお
ける作業効率を向上することができる。また、場所打鋼
管コンクリート杭を構築し、余盛りコンクリートの除去
作業を行った後、場所打鋼管コンクリート杭に埋設され
た下部定着筋に接続部材を介して上部定着筋を接続する
ことができ、このため、余盛りコンクリートの除去作業
を効率よく行うことができるとともに、余盛りコンクリ
ートの除去作業時に定着筋を損傷する等の事故が発生す
ることを未然に防止することができる。
The method of constructing the pile head of the cast-in-place steel pipe concrete pile is to join the pile head composed of the steel pipe concrete pile and the footing with a required strength by using the anchoring bar composed of a high-strength steel bar. The number of anchoring muscles required can be reduced, and the lower part of the anchoring muscles can be arranged with the distance between the anchoring muscle and the steel pipe set within 1.5 times the diameter of the anchoring muscle. In addition, it is possible to increase the distance between the adjacent fixing streaks, thereby improving the work efficiency in the field. In addition, after constructing the cast-in-place steel pipe concrete pile and performing the work of removing the excess concrete, it is possible to connect the upper anchorage muscle to the lower anchorage buried in the cast-in-place steel pipe concrete via a connecting member, Therefore, the work of removing excess concrete can be efficiently performed, and the occurrence of accidents such as damage to fixing streaks during the removal of excess concrete can be prevented.

【0026】[0026]

【発明の実施の形態】以下、本発明の場所打鋼管コンク
リート杭の杭頭部構造の実施の形態を図面に基づいて説
明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of a pile head structure of a cast-in-place steel pipe concrete pile according to the present invention will be described below with reference to the drawings.

【0027】図1〜図2は、本発明の場所打鋼管コンク
リート杭の杭頭部構造の第1実施例を示す。この場所打
鋼管コンクリート杭の杭頭部構造は、地盤7中に設置す
る場所打鋼管コンクリート杭を構成する鋼管1の内周面
に、略等間隔に、高強度ねじふし鉄筋からなる定着筋2
の下部を、定着筋2と鋼管1との間隔dを定着筋の直径
Dの1.5倍以内に設定して配設するとともに、この定
着筋2の上部をフーチングの構築位置まで延出するよう
に構成する。フーチングの構築位置まで延出した定着筋
2の上端部には、定着部材としてのロックナット31を
螺合することができ、また、必要に応じて、鋼管1内に
位置する定着筋2の下端部にも、定着部材としてのロッ
クナット32を螺合することができる。なお、定着筋2
の下端部に螺合したロックナット32は、必要に応じ
て、鋼管1の内周面に溶接することができ、この場合に
は、ロックナット32を鋼管1の内周面に溶接した後、
定着筋2の下端部を螺合して固定するようにする。ま
た、鋼管1の上端面には、定着筋2の中間位置を仮溶接
により固定、保持するための固定フープ4を、脚部材5
を介して配設することができる。この定着筋2の固定、
保持は、ピン等の部材を用いて行うことができる。
FIGS. 1 and 2 show a first embodiment of a pile head structure of a cast-in-place steel pipe concrete pile according to the present invention. The pile head structure of the cast-in-place steel pipe concrete pile is composed of an anchoring bar 2 made of a high-strength threaded rebar at substantially equal intervals on the inner peripheral surface of the steel pipe 1 constituting the cast-in-place steel pipe concrete pile installed in the ground 7.
Is arranged with the distance d between the anchoring muscle 2 and the steel pipe 1 set within 1.5 times the diameter D of the anchoring muscle, and the upper part of the anchoring muscle 2 is extended to the footing construction position. The configuration is as follows. A lock nut 31 as a fixing member can be screwed into an upper end portion of the fixing streak 2 extending to the footing construction position, and a lower end of the fixing streak 2 located in the steel pipe 1 as necessary. A lock nut 32 as a fixing member can be screwed into the portion. In addition, the fixing line 2
The lock nut 32 screwed to the lower end of the steel pipe 1 can be welded to the inner peripheral surface of the steel pipe 1 if necessary. In this case, after the lock nut 32 is welded to the inner peripheral surface of the steel pipe 1,
The lower end of the fixing streak 2 is screwed and fixed. Further, a fixing hoop 4 for fixing and holding the intermediate position of the anchoring streak 2 by temporary welding to the upper end surface of the steel pipe 1 is attached to the leg member 5.
Can be arranged through. Fixation of the anchoring muscle 2,
The holding can be performed using a member such as a pin.

【0028】この場合において、鋼管1には、図2に示
すように、内周面に鋼管1の内部に打設したコンクリー
ト6との一体性を向上するための突起11を形成したス
パイラル鋼管を用いることが望ましい。
In this case, as shown in FIG. 2, a spiral steel pipe having a projection 11 for improving the integrity with the concrete 6 cast inside the steel pipe 1 is formed on the inner peripheral surface of the steel pipe 1 as shown in FIG. It is desirable to use.

【0029】また、高強度ねじふし鉄筋からなる定着筋
2には、降伏点490N/mm2以上、引張強さ620
N/mm2以上、さらに好ましくは、降伏点685N/
mm2以上、引張強さ860N/mm2以上の鉄筋(JI
S Z 2241による。例えば、株式会社神戸製鋼所製
「高強度ネジコン(USD685)」(商品名))を用
いることが望ましく、これにより、従来、定着筋として
広く使用されている鉄筋(降伏点390N/mm2)を
使用する場合と比較して、定着筋の本数を大幅に(降伏
点685N/mm2以上の鉄筋を使用する場合には、4
0%以上)低減することができ、これにより、隣接する
定着筋2間の間隔sを大きく取ることができることと相
俟って、鋼管1の配設作業の作業効率及び作業性を向上
することができる。
The anchoring bar 2 made of a high-strength threaded reinforcing bar has a yield point of 490 N / mm 2 or more and a tensile strength of 620 N / mm 2.
N / mm 2 or more, more preferably a yield point of 685 N /
mm 2 or more, a tensile strength of 860N / mm 2 or more of rebar (JI
According to SZ2241. For example, it is desirable to use “High-strength screw control (USD685)” (trade name) manufactured by Kobe Steel, Ltd., whereby a reinforcing bar (yield point: 390 N / mm 2 ), which has been widely used as a fixing bar, is conventionally used. Compared to the case of using a reinforcing bar, the number of anchoring bars is significantly increased (when using a reinforcing bar having a yield point of 685 N / mm 2 or more, 4
0% or more), thereby improving the work efficiency and workability of the work of arranging the steel pipe 1 in combination with the fact that the distance s between the adjacent anchoring streaks 2 can be increased. Can be.

【0030】また、高強度ねじふし鉄筋からなる定着筋
2の定着部材には、本実施例のように、定着筋2にロッ
クナット31,32を単に螺合するだけでもよいが、ロ
ックナット31,32に代えてカプラーを用い、グラウ
ト材を注入したり、図3に示すように、別途用意した定
着板31c,32cをロックナット31a,32aやカ
プラー31b,32bにより締め付けて構成することも
できる。この場合、定着部材は、必ずしも定着筋2の両
端部に配設する必要はなく、上端部又は下端部のいずれ
か一方のみに配設することもできる。また、必要に応じ
て、定着筋2の下端部に取り付けたカプラー32b等の
定着部材を、鋼管1の内周面に溶接することができる。
Further, as in this embodiment, the lock nuts 31 and 32 may be simply screwed to the fixing streaks 2 to the fixing member of the fixing streaks 2 made of a high-strength threaded reinforcing bar. , 32, a grout material can be injected and, as shown in FIG. 3, fixing plates 31c, 32c separately prepared can be tightened by lock nuts 31a, 32a and couplers 31b, 32b. . In this case, the fixing members do not necessarily need to be disposed at both ends of the fixing streaks 2, and may be disposed at only one of the upper end and the lower end. If necessary, a fixing member such as a coupler 32b attached to the lower end of the fixing streak 2 can be welded to the inner peripheral surface of the steel pipe 1.

【0031】また、本実施例においては、定着筋2に高
強度ねじふし鉄筋を用いたが、高強度鉄筋(異形鉄筋を
含む。)からなる定着筋を使用し、上記の実施例と同
様、鋼管1の内周面に、略等間隔に、定着筋と鋼管1と
の間隔dを定着筋の直径Dの1.5倍以内に設定して配
設することができ、この場合、必要に応じて、定着筋を
鋼管1の内周面に溶接等により固定することもできる。
この定着筋の固定は、鋼管1を掘削孔に建て込む前の、
いわゆる、先付け工法によっても、あるいは、場所打コ
ンクリート杭の余盛りコンクリートを除去した後の、い
わゆる、後付け工法によっても、施工することができ
る。この場合も、定着筋には、適宜の定着部材を配設す
ることが望ましい。
In this embodiment, a high-strength threaded reinforcing bar is used as the anchoring bar 2, but an anchoring bar made of a high-strength bar (including deformed bar) is used. On the inner peripheral surface of the steel pipe 1, the distance d between the anchoring streaks and the steel pipe 1 can be set at substantially equal intervals within 1.5 times the diameter D of the anchoring streaks. Accordingly, the fixing streaks can be fixed to the inner peripheral surface of the steel pipe 1 by welding or the like.
The fixing of the anchoring muscle is performed before the steel pipe 1 is built in the borehole.
The work can be performed by a so-called post-installation method or by a so-called post-installation method after removing the excess concrete from the cast-in-place concrete pile. Also in this case, it is desirable to provide an appropriate fixing member on the fixing streak.

【0032】この場所打鋼管コンクリート杭の杭頭部構
造は、地盤7中に設置する場所打鋼管コンクリート杭を
構成する鋼管1の内周面に、略等間隔に、上端部、さら
に必要に応じて下端部に定着部材としてのロックナット
31,32を螺合した高強度ねじふし鉄筋からなる定着
筋2の下端部を、定着筋2と鋼管1との間隔dを定着筋
の直径Dの1.5倍以内に設定して配設するとともに、
この定着筋2の上端をフーチングの構築位置まで延出す
るとともに、定着筋2の中間位置を固定、保持するよう
にする。その後、鋼管1の内部を含む、地盤7上に、コ
ンクリートを打設してフーチングを構築するようにす
る。
The pile head structure of the cast-in-place cast-pipe concrete pile is formed on the inner peripheral surface of the steel pipe 1 constituting the cast-in-place cast-in-place concrete pile installed in the ground 7, at substantially equal intervals, at the upper end, and further, if necessary. The lower end of the fixing bar 2 made of a high-strength threaded rebar in which lock nuts 31 and 32 as fixing members are screwed to the lower end, and the distance d between the fixing bar 2 and the steel pipe 1 is set to 1 of the diameter D of the fixing bar. Set and arrange within 5 times,
The upper end of the anchoring line 2 is extended to the footing construction position, and the intermediate position of the anchoring line 2 is fixed and held. Then, concrete is cast on the ground 7 including the inside of the steel pipe 1 to construct a footing.

【0033】このように、高強度ねじふし鉄筋からなる
定着筋2と鋼管1との間隔を定着筋2の直径の1.5倍
以内に設定して配設することにより、定着筋2の本数を
増加させて、鋼管1の内部に打設するコンクリートによ
る定着筋2の保持力を向上することができるとともに、
ロックナット31,32が定着筋2のアンカーとなり、
鋼管コンクリート杭からなる杭頭部とフーチングの接合
強度を向上することができる。
As described above, by setting the distance between the anchoring bar 2 made of a high-strength threaded reinforcing bar and the steel pipe 1 within 1.5 times the diameter of the anchoring bar 2, the number of anchoring bars 2 can be reduced. And the holding power of the anchoring streaks 2 by the concrete poured into the steel pipe 1 can be improved,
The lock nuts 31 and 32 become anchors of the anchoring muscle 2,
The joint strength between the pile head made of steel pipe concrete pile and the footing can be improved.

【0034】なお、定着筋2の直径、定着筋2を配設す
る本数、場所打鋼管コンクリート杭を構成する鋼管1へ
の定着筋2の挿入長L1、鋼管1から上方への定着筋2
の延出長L2等は、従来、汎用されている鋼管コンクリ
ート杭からなる杭頭部とフーチングの接合構造に準じて
設定することができる。
The diameter of the anchoring bars 2, the number of the anchoring bars 2, the length of insertion of the anchoring bars 2 into the steel pipes 1 constituting the cast-in-place steel pipe concrete pile, the anchoring bars 2 extending upward from the steel pipes 1
Can be set in accordance with a joint structure between a pile head and a footing made of a steel pipe concrete pile, which is conventionally widely used.

【0035】次に、図4に、本発明の場所打鋼管コンク
リート杭の杭頭部構造の第2実施例を示す。この場所打
鋼管コンクリート杭の杭頭部構造は、図4(c)に示す
ように、高強度ねじふし鉄筋からなる定着筋を下部定着
筋21と上部定着筋22とで構成するとともに、下部定
着筋21及び上部定着筋22を、地盤7中に設置する場
所打鋼管コンクリート杭を構成する鋼管1の上端近傍位
置で、接続部材としてのカプラー33により接続するよ
うにしたものである。そして、鋼管1の内周面に、略等
間隔に、下部定着筋21を、下部定着筋21と鋼管1と
の間隔を定着筋の直径の1.5倍以内に設定して配設す
るとともに、この上部定着筋22をフーチングの構築位
置まで延出するように構成する点を始めとして、フーチ
ングの構築位置まで延出した上部定着筋22の上端部
に、定着部材としてのロックナットを螺合することがで
き、また、必要に応じて、鋼管1内に位置する下部定着
筋21の下端部にも、定着部材としてのロックナットを
螺合することができる等の基本構成は、上記第1実施例
の場所打鋼管コンクリート杭の杭頭部構造と同様であ
る。なお、下部定着筋21の上端部に螺合する接続部材
としてのカプラー33は、必要に応じて、鋼管1の内周
面に仮溶接することにより固定することができる。ま
た、接続部材としてのカプラー33は、外周面を異形
(「ねじふし」を含む。)に形成したものを用いること
ができ、これにより、カプラー33と打設するコンクリ
ートとの一体性を向上することができる。
Next, FIG. 4 shows a second embodiment of the pile head structure of the cast-in-place steel pipe concrete pile of the present invention. As shown in FIG. 4 (c), the pile head structure of this cast-in-place steel pipe concrete pile is composed of a lower anchoring bar 21 and an upper anchoring bar 22, and a lower anchoring bar consisting of a high-strength screw bar. The streaks 21 and the upper anchoring streaks 22 are connected to each other by a coupler 33 as a connecting member at a position near the upper end of the steel pipe 1 constituting the cast-in-place steel pipe concrete pile to be installed in the ground 7. The lower anchoring streaks 21 are arranged on the inner peripheral surface of the steel pipe 1 at substantially equal intervals, with the interval between the lower anchoring streaks 21 and the steel pipe 1 set within 1.5 times the diameter of the anchoring streaks. Starting from the point that the upper fixing streaks 22 are extended to the footing construction position, a lock nut as a fixing member is screwed to the upper end portion of the upper fixing streaks 22 extending to the footing construction position. In addition, if necessary, a lock nut as a fixing member can be screwed into a lower end portion of the lower fixing streak 21 located in the steel pipe 1. It is the same as the pile head structure of the cast-in-place steel pipe concrete pile of the embodiment. The coupler 33 as a connecting member screwed to the upper end of the lower fixing streaks 21 can be fixed by temporary welding to the inner peripheral surface of the steel pipe 1 as necessary. Further, as the coupler 33 as the connecting member, a coupler whose outer peripheral surface is formed in an irregular shape (including a “screw wiper”) can be used, thereby improving the integration between the coupler 33 and the concrete to be cast. be able to.

【0036】この場所打鋼管コンクリート杭の杭頭部構
造は、地盤7中に設置する場所打鋼管コンクリート杭を
構成する鋼管1の内周面に、略等間隔に、上端部に接続
部材としてのカプラー33を配した高強度鉄筋からなる
下部定着筋21を、下部定着筋21と鋼管1との間隔を
下部定着筋21の直径の1.5倍以内に設定して配設
し、仮固定する(図4(a))。そして、カプラー33
に仮込めねじ片等の閉鎖部材34を配設することによ
り、カプラー33の上部開口を閉鎖した状態にした後
(図4(b))、コンクリート6を打設し、場所打鋼管
コンクリート杭を構築する。この場合において、閉鎖部
材34には、上記の仮込めねじ片のほか、合成樹脂製の
栓部材、容易に除去可能な不定形の充填材等、カプラー
33の上部開口を閉鎖した状態にし、打設したコンクリ
ートがカプラー33の上部開口から侵入することを防止
できる任意の部材を用いることができる。また、閉鎖部
材34として仮込めねじ片を用いた場合には、仮込めね
じ片をカプラー33に螺入し、仮込めねじ片の下端面を
下部定着筋21の上端面に当接することによって、下部
定着筋21をカプラー33に強固に固定することができ
る利点があるが、下部定着筋21とカプラー33との固
定は、グラウト材の注入又はロックナットによる締め付
け等により行うこともできる。場所打鋼管コンクリート
杭を構築し、余盛りコンクリートの除去作業を行った
後、カプラー33の上部開口を閉鎖していた閉鎖部材3
4を除去し、場所打鋼管コンクリート杭に埋設された下
部定着筋21に、カプラー33を介して、高強度鉄筋か
らなる上部定着筋22を接続し、上部定着筋22をフー
チングの構築位置まで延出する(図4(c))。その
後、地盤7上に、コンクリートを打設してフーチングを
構築するようにする。
The pile head structure of the cast-in-place steel pipe concrete pile is constructed such that a connection member is provided on the inner peripheral surface of the steel pipe 1 constituting the cast-in-place steel pipe concrete pile installed in the ground 7 at substantially equal intervals and at the upper end thereof. The lower anchoring bar 21 made of a high-strength reinforcing bar provided with the coupler 33 is disposed with the distance between the lower anchoring bar 21 and the steel pipe 1 set within 1.5 times the diameter of the lower anchoring bar 21 and temporarily fixed. (FIG. 4 (a)). And coupler 33
By disposing a closing member 34 such as a temporary threaded screw, the upper opening of the coupler 33 is closed (FIG. 4 (b)), concrete 6 is cast, and the cast-in-place steel pipe concrete pile is removed. To construct. In this case, in addition to the above-mentioned temporary storage screw pieces, a closing member made of a synthetic resin, an easily removable irregular-shaped filler, or the like, is used as the closing member 34 in a state where the upper opening of the coupler 33 is closed. Any member that can prevent the provided concrete from entering through the upper opening of the coupler 33 can be used. In the case where a temporarily-inserted screw is used as the closing member 34, the temporarily-inserted screw is screwed into the coupler 33, and the lower end surface of the temporarily-inserted screw is brought into contact with the upper end surface of the lower fixing streak 21. There is an advantage that the lower fixing streaks 21 can be firmly fixed to the coupler 33, but the fixing between the lower fixing streaks 21 and the coupler 33 can also be performed by injecting a grout material or tightening with a lock nut. After constructing a cast-in-place steel pipe concrete pile and removing excess concrete, the closing member 3 closing the upper opening of the coupler 33 was removed.
4 and the upper anchoring bar 22 made of high-strength steel is connected to the lower anchoring bar 21 buried in the cast-in-place steel pipe concrete pile via a coupler 33, and the upper anchoring bar 22 is extended to the footing construction position. (FIG. 4C). Thereafter, concrete is cast on the ground 7 to build a footing.

【0037】このように、定着筋を下部定着筋21と上
部定着筋22とで構成するとともに、下部定着筋21及
び上部定着筋22を、地盤7中に設置する場所打鋼管コ
ンクリート杭を構成する鋼管1の上端近傍位置で、接続
部材としてのカプラー33により接続することにより、
場所打鋼管コンクリート杭を構築し、余盛りコンクリー
トの除去作業を行った後、場所打鋼管コンクリート杭に
埋設された下部定着筋21にカプラー33を介して上部
定着筋22を接続することができ、このため、余盛りコ
ンクリートの除去作業を効率よく行うことができるとと
もに、余盛りコンクリートの除去作業時に定着筋を損傷
する等の事故が発生することを未然に防止することがで
きる。
As described above, the anchoring bars are constituted by the lower anchoring bars 21 and the upper anchoring bars 22, and the lower anchoring bars 21 and the upper anchoring bars 22 are formed in a place-punched steel pipe concrete pile in the ground 7. At the position near the upper end of the steel pipe 1, by connecting with a coupler 33 as a connecting member,
After constructing the cast-in-place steel pipe concrete pile and performing the work of removing excess concrete, it is possible to connect the upper anchoring muscle 22 via the coupler 33 to the lower anchoring muscle 21 buried in the in-place steel pipe concrete pile, Therefore, the work of removing excess concrete can be efficiently performed, and the occurrence of accidents such as damage to fixing streaks during the removal of excess concrete can be prevented.

【0038】次に、図5に、本発明の場所打鋼管コンク
リート杭の杭頭部構造の第3実施例を示す。この場所打
鋼管コンクリート杭の杭頭部構造は、上記第2実施例の
場所打鋼管コンクリート杭の杭頭部構造と同様、図5
(c)に示すように、高強度ねじふし鉄筋からなる定着
筋を下部定着筋21と上部定着筋22とで構成するとと
もに、下部定着筋21及び上部定着筋22を、地盤7中
に設置する場所打鋼管コンクリート杭を構成する鋼管1
の上端近傍位置で、接続部材としてのカプラー33によ
り接続するようにしたものである。そして、鋼管1の内
周面に、略等間隔に、下部定着筋21を、下部定着筋2
1と鋼管1との間隔を定着筋の直径の1.5倍以内に設
定して配設するとともに、この上部定着筋22をフーチ
ングの構築位置まで延出するように構成する点を始めと
して、フーチングの構築位置まで延出した上部定着筋2
2の上端部に、定着部材としてのロックナットを螺合す
ることができ、また、必要に応じて、鋼管1内に位置す
る下部定着筋21の下端部にも、定着部材としてのロッ
クナットを螺合することができる等の基本構成は、上記
第1実施例及び第2実施例の場所打鋼管コンクリート杭
の杭頭部構造と同様である。なお、下部定着筋21の上
端部に螺合する接続部材としてのカプラー33は、必要
に応じて、鋼管1の内周面に仮溶接することにより固定
することができる。また、接続部材としてのカプラー3
3は、外周面を異形(「ねじふし」を含む。)に形成し
たものを用いることができ、これにより、カプラー33
と打設するコンクリートとの一体性を向上することがで
きる。
Next, FIG. 5 shows a third embodiment of the pile head structure of the cast-in-place steel pipe concrete pile of the present invention. The pile head structure of this cast-in-place steel pipe concrete pile is the same as that of the second embodiment of FIG.
As shown in (c), the anchoring bar composed of the high-strength screw bar is composed of the lower anchoring bar 21 and the upper anchoring bar 22, and the lower anchoring bar 21 and the upper anchoring bar 22 are installed in the ground 7. Steel pipes that make up steel piles in place
Are connected by a coupler 33 as a connecting member at a position near the upper end. Then, the lower anchoring muscles 21 and the lower anchoring muscles 2 are provided on the inner peripheral surface of the steel pipe 1 at substantially equal intervals.
Starting from the point that the distance between the steel anchor 1 and the steel pipe 1 is set within 1.5 times the diameter of the anchoring streaks, and the upper anchoring streaks 22 are configured to extend to the footing construction position. Upper anchor muscle 2 extended to the footing construction position
A lock nut as a fixing member can be screwed into the upper end of the second fixing member 2, and a lock nut as a fixing member can also be screwed into the lower end of the lower fixing streak 21 located in the steel pipe 1 as necessary. The basic configuration, such as being able to be screwed, is the same as the pile head structure of the cast-in-place steel pipe concrete pile of the first and second embodiments. The coupler 33 as a connection member screwed to the upper end of the lower fixing streaks 21 can be fixed by temporary welding to the inner peripheral surface of the steel pipe 1 as necessary. Also, a coupler 3 as a connecting member
For the coupler 3, a coupler having an outer peripheral surface formed in an irregular shape (including a "screw wrap") can be used.
And the concrete to be cast can be improved.

【0039】この場所打鋼管コンクリート杭の杭頭部構
造は、地盤7中に設置する場所打鋼管コンクリート杭を
構成する鋼管1の内周面に、略等間隔に高強度鉄筋から
なる下部定着筋21を、下部定着筋21と鋼管1との間
隔を下部定着筋21の直径の1.5倍以内に設定して配
設し、仮固定するとともに、下部定着筋21の上端部に
発泡樹脂製等の養生用キャップ35を配設する(図5
(a))。この場合、下部定着筋21の仮固定は、例え
ば、下部定着筋21の任意の位置に固定フープ(図示省
略)を仮溶接するとともに、下部定着筋21を適宜のス
ペーサ(図示省略)を介して鋼管1に仮溶接することに
より行うことができる。そして、コンクリート6を打設
し、場所打鋼管コンクリート杭を構築した後、余盛りコ
ンクリートの除去作業を行うとともに、養生用キャップ
35を除去し、下部定着筋21の上端部に接続部材とし
てのカプラー33を配設する(図5(b))。その後、
場所打鋼管コンクリート杭に埋設された下部定着筋21
に、カプラー33を介して、高強度鉄筋からなる上部定
着筋22を接続し、上部定着筋22をフーチングの構築
位置まで延出する(図5(c))。この場合において、
必要に応じて、下部定着筋21及び上部定着筋22とカ
プラー33とを、グラウト材の注入又はロックナットに
よる締め付け等により固定することができる。その後、
地盤7上に、コンクリートを打設してフーチングを構築
するようにする。
The pile head structure of the cast-in-place steel pipe concrete pile has a lower anchoring bar made of high-strength rebar at substantially equal intervals on the inner peripheral surface of the steel pipe 1 constituting the cast-in-place steel pipe concrete pile installed in the ground 7. 21 is provided with the interval between the lower anchoring streak 21 and the steel pipe 1 set within 1.5 times the diameter of the lower anchoring streak 21, temporarily fixed, and made of foamed resin at the upper end of the lower anchoring streak 21. A curing cap 35 such as the one shown in FIG.
(A)). In this case, the temporary fixing of the lower fixing streaks 21 is performed, for example, by temporarily welding a fixing hoop (not shown) to an arbitrary position of the lower fixing streaks 21 and attaching the lower fixing streaks 21 via an appropriate spacer (not shown). It can be performed by temporarily welding to the steel pipe 1. After the concrete 6 is cast and a cast-in-place steel pipe concrete pile is constructed, the excess concrete is removed, the curing cap 35 is removed, and a coupler as a connection member is connected to the upper end of the lower anchoring streak 21. 33 is provided (FIG. 5B). afterwards,
Lower anchorage 21 buried in a steel-pipe concrete pile
Then, the upper anchoring bar 22 made of a high-strength reinforcing bar is connected via a coupler 33, and the upper anchoring bar 22 is extended to the footing construction position (FIG. 5C). In this case,
If necessary, the lower fixing streaks 21 and the upper fixing streaks 22 and the coupler 33 can be fixed by injecting a grout material or tightening with a lock nut. afterwards,
The footing is constructed by placing concrete on the ground 7.

【0040】このように、定着筋を下部定着筋21と上
部定着筋22とで構成するとともに、下部定着筋21及
び上部定着筋22を、地盤7中に設置する場所打鋼管コ
ンクリート杭を構成する鋼管1の上端近傍位置で、接続
部材としてのカプラー33により接続することにより、
場所打鋼管コンクリート杭を構築し、余盛りコンクリー
トの除去作業を行った後、場所打鋼管コンクリート杭に
埋設された下部定着筋21にカプラー33を介して上部
定着筋22を接続することができ、このため、余盛りコ
ンクリートの除去作業をより効率よく行うことができる
とともに、余盛りコンクリートの除去作業時に定着筋を
損傷する等の事故が発生することを未然に防止すること
ができる。
As described above, the anchoring bars are constituted by the lower anchoring bars 21 and the upper anchoring bars 22, and the lower anchoring bars 21 and the upper anchoring bars 22 are constructed in a place-punched steel pipe concrete pile in the ground 7. At the position near the upper end of the steel pipe 1, by connecting with a coupler 33 as a connecting member,
After constructing the cast-in-place steel pipe concrete pile and performing the work of removing excess concrete, it is possible to connect the upper anchoring muscle 22 via the coupler 33 to the lower anchoring muscle 21 buried in the in-place steel pipe concrete pile, For this reason, the work of removing the excess concrete can be performed more efficiently, and it is possible to prevent the occurrence of an accident such as damage to the fixing streaks during the removal of the excess concrete.

【0041】[0041]

【発明の効果】本発明の場所打鋼管コンクリート杭の杭
頭部構造によれば、場所打鋼管コンクリート杭を構成す
る鋼管の内周面に、略等間隔に、高強度鉄筋からなる定
着筋の下部を、定着筋と鋼管との間隔を定着筋の直径の
1.5倍以内に設定して配設することにより、鉄筋籠方
式と比較して、定着筋の本数を多くすることができると
ともに、鋼管の内部に打設するコンクリートによる定着
筋の保持力を向上することができる。また、高強度鉄筋
からなる定着筋を用いることにより、鋼管コンクリート
杭からなる杭頭部とフーチングとを所要の強度でもって
接合するために要する定着筋の本数を低減することがで
きるとともに、これにより、定着筋の下部を、定着筋と
鋼管との間隔を定着筋の直径の1.5倍以内に設定して
配設したことと相俟って、隣接する定着筋間の間隔を大
きく取ることができ、定着筋の配設作業の作業効率及び
作業性を向上することができ、これに要するコストを低
廉にすることができる。
According to the pile head structure of the cast-in-place steel pipe concrete pile of the present invention, the anchoring bar composed of the high-strength rebar is provided at substantially equal intervals on the inner peripheral surface of the steel pipe constituting the cast-in-place steel pipe concrete pile. By arranging the lower portion so that the interval between the anchoring bar and the steel pipe is set to within 1.5 times the diameter of the anchoring bar, the number of anchoring bars can be increased as compared with the rebar cage method. In addition, it is possible to improve the holding power of the anchoring streaks by the concrete cast into the inside of the steel pipe. In addition, by using anchoring bars made of high-strength rebar, it is possible to reduce the number of anchoring bars required to join a pile head made of a steel pipe concrete pile and a footing with a required strength. In addition to the arrangement of the lower portion of the anchoring muscle with the spacing between the anchoring muscle and the steel pipe set within 1.5 times the diameter of the anchoring muscle, the clearance between adjacent anchoring muscles should be increased. Thus, the work efficiency and workability of the work of arranging the anchoring streaks can be improved, and the cost required for this can be reduced.

【0042】また、定着筋を下部定着筋と上部定着筋と
で構成するとともに、該下部定着筋及び上部定着筋を、
鋼管の上端近傍位置で、接続部材により接続することに
より、場所打鋼管コンクリート杭を構築し、余盛りコン
クリートの除去作業を行った後、場所打鋼管コンクリー
ト杭に埋設された下部定着筋に接続部材を介して上部定
着筋を接続することができ、このため、余盛りコンクリ
ートの除去作業を効率よく行うことができるとともに、
余盛りコンクリートの除去作業時に定着筋を損傷する等
の事故が発生することを未然に防止することができる。
Further, the anchoring muscle is composed of a lower anchoring muscle and an upper anchoring muscle, and the lower anchoring muscle and the upper anchoring muscle are
At the position near the upper end of the steel pipe, a cast-in-place steel pipe concrete pile is constructed by connecting with a connecting member, and after removing excess concrete, the connecting member is connected to the lower anchorage buried in the cast-in-place steel pipe concrete pile. The upper anchoring streaks can be connected via, so that the work of removing excess concrete can be performed efficiently,
It is possible to prevent the occurrence of accidents such as damage to anchoring streaks during the work of removing the excess concrete.

【0043】また、外周面を異形に形成した接続部材を
用いることにより、接続部材とコンクリートとの一体性
を向上することができる。
In addition, by using a connecting member having an outer peripheral surface formed in an irregular shape, the integrity of the connecting member and concrete can be improved.

【0044】また、高強度鉄筋に、降伏点490N/m
2以上の鉄筋を用いることにより、従来広く使用され
ている鉄筋(降伏点390N/mm2)を用いる場合と
比較して、定着筋の本数を大幅に低減することができ
る。
In addition, a yield point of 490 N / m
By using a reinforcing bar of m 2 or more, the number of fixing bars can be significantly reduced as compared with the case of using a reinforcing bar (yield point: 390 N / mm 2 ) which has been widely used in the past.

【0045】また、定着筋に、ねじふし鉄筋を用いるこ
とにより、現場における定着筋の接続等の作業を簡略化
することができ、作業効率を向上することができるとと
もに、コンクリートとの一体性を向上することができ
る。
Further, by using a screw bar as the anchoring bar, the work such as connection of the anchoring bar on site can be simplified, the working efficiency can be improved, and the integration with concrete can be improved. Can be improved.

【0046】また、定着筋の少なくとも一端部に定着部
材を配設することにより、定着部材が定着筋のアンカー
となり、鋼管コンクリート杭からなる杭頭部とフーチン
グの接合強度を向上することができる。
Further, by disposing the fixing member at at least one end of the fixing streak, the fixing member serves as an anchor of the fixing streak, and the joining strength between the pile head made of the steel pipe concrete pile and the footing can be improved.

【0047】また、接続部材又は定着筋の下端部に配設
する定着部材を、鋼管の内周面に溶接することにより、
鋼管に対する定着筋の固定を高い信頼性をもって行うこ
とができる。
Further, by welding the connecting member or the fixing member disposed at the lower end of the fixing streak to the inner peripheral surface of the steel pipe,
The fixing of the anchoring muscle to the steel pipe can be performed with high reliability.

【0048】また、本発明の場所打鋼管コンクリート杭
の杭頭部の施工法によれば、高強度鉄筋からなる定着筋
を用いることにより、鋼管コンクリート杭からなる杭頭
部とフーチングとを所要の強度でもって接合するために
要する定着筋の本数を低減することができるとともに、
これにより、定着筋の下部を、定着筋と鋼管との間隔を
定着筋の直径の1.5倍以内に設定して配設したことと
相俟って、隣接する定着筋間の間隔を大きく取ることが
でき、現場における作業効率を向上することができる。
また、場所打鋼管コンクリート杭を構築し、余盛りコン
クリートの除去作業を行った後、場所打鋼管コンクリー
ト杭に埋設された下部定着筋に接続部材を介して上部定
着筋を接続することができ、このため、余盛りコンクリ
ートの除去作業を効率よく行うことができるとともに、
余盛りコンクリートの除去作業時に定着筋を損傷する等
の事故が発生することを未然に防止することができる。
Further, according to the method for constructing a pile head of a cast-in-place steel pipe concrete pile of the present invention, the pile head made of a steel pipe concrete pile and a footing are required by using an anchoring bar made of a high-strength rebar. While it is possible to reduce the number of anchoring streaks required for joining with strength,
This, together with the arrangement of the lower portion of the anchoring muscle with the spacing between the anchoring muscle and the steel pipe set within 1.5 times the diameter of the anchoring muscle, increases the interval between adjacent anchoring muscles. And work efficiency at the site can be improved.
In addition, after constructing the cast-in-place steel pipe concrete pile and performing the work of removing the excess concrete, it is possible to connect the upper anchorage muscle to the lower anchorage buried in the cast-in-place steel pipe concrete via a connecting member, For this reason, while being able to perform the work of removing excess concrete efficiently,
It is possible to prevent the occurrence of accidents such as damage to anchoring streaks during the work of removing the excess concrete.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の場所打鋼管コンクリート杭の杭頭部構
造の第1実施例を示す断面図であり、(a)は縦断面
図、(b)は(a)のA−A線断面図、(c)は(a)
のB−B線断面図である。
FIG. 1 is a sectional view showing a first embodiment of a pile head structure of a cast-in-place steel pipe concrete pile according to the present invention, in which (a) is a longitudinal sectional view and (b) is a sectional view taken along line AA of (a). Figure, (c) is (a)
FIG. 7 is a sectional view taken along line BB of FIG.

【図2】本発明の場所打鋼管コンクリート杭の杭頭部構
造に用いる鋼管を示し、(a)は内部にコンクリートを
打設した状態、(b)は内部にコンクリートを打設する
前の状態を示す。
FIG. 2 shows a steel pipe used for a pile head structure of a cast-in-place steel pipe concrete pile according to the present invention, wherein (a) shows a state where concrete is cast inside, and (b) shows a state before concrete is poured inside. Is shown.

【図3】定着筋に対する定着部材の配設例を示し、
(a)は平面図、(b)は正面図、(c)は底面図であ
る。
FIG. 3 shows an example of disposing a fixing member with respect to a fixing streak;
(A) is a plan view, (b) is a front view, and (c) is a bottom view.

【図4】本発明の場所打鋼管コンクリート杭の杭頭部構
造の第2実施例の施工工程を示す縦断面図である。
FIG. 4 is a longitudinal sectional view showing a construction process of a second embodiment of the pile head structure of the cast-in-place steel pipe concrete pile of the present invention.

【図5】本発明の場所打鋼管コンクリート杭の杭頭部構
造の第3実施例の施工工程を示す縦断面図である。
FIG. 5 is a longitudinal sectional view showing a construction process of a third embodiment of a pile head structure of a cast-in-place steel pipe concrete pile according to the present invention.

【図6】場所打鋼管コンクリート杭の杭頭部構造の概略
図である。
FIG. 6 is a schematic diagram of a pile head structure of a cast-in-place steel pipe concrete pile.

【図7】従来の場所打鋼管コンクリート杭の杭頭部構造
を示す縦断面図であり、(a)は鉄筋籠方式、(b)は
ひげ筋方式、(c)はカプラー方式を示す。
FIG. 7 is a longitudinal sectional view showing a pile head structure of a conventional cast-in-place steel pipe concrete pile, in which (a) shows a reinforcing bar cage system, (b) shows a beard bar system, and (c) shows a coupler system.

【符号の説明】[Explanation of symbols]

1 鋼管 2 定着筋 21 下部定着筋 22 上部定着筋 31 定着部材(ロックナット) 32 定着部材(ロックナット) 33 接続部材(カプラー) 4 固定フープ 5 脚部材 6 コンクリート 7 地盤 DESCRIPTION OF SYMBOLS 1 Steel pipe 2 Anchoring bar 21 Lower anchoring bar 22 Upper anchoring bar 31 Anchoring member (lock nut) 32 Anchoring member (lock nut) 33 Connecting member (coupler) 4 Fixed hoop 5 Leg member 6 Concrete 7 Ground

Claims (8)

【特許請求の範囲】[Claims] 【請求項1】 場所打鋼管コンクリート杭を構成する鋼
管の内周面に、略等間隔に、高強度鉄筋からなる定着筋
の下部を、定着筋と鋼管との間隔を定着筋の直径の1.
5倍以内に設定して配設するとともに、該定着筋の上部
をフーチングの構築位置まで延出するようにしたことを
特徴とする場所打鋼管コンクリート杭の杭頭部構造。
1. An inner peripheral surface of a steel pipe constituting a cast-in-place steel pipe concrete pile, at substantially equal intervals, a lower portion of an anchoring bar made of a high-strength reinforcing bar, and an interval between the anchoring bar and the steel pipe is set to one of the diameters of the anchoring bar. .
A pile head structure of a cast-in-place steel tube concrete pile, wherein the pile head is set within 5 times, and an upper portion of the anchoring bar is extended to a footing construction position.
【請求項2】 定着筋を下部定着筋と上部定着筋とで構
成するとともに、該下部定着筋及び上部定着筋を、鋼管
の上端近傍位置で、接続部材により接続するようにした
ことを特徴とする請求項1記載の場所打鋼管コンクリー
ト杭の杭頭部構造。
2. An anchoring muscle comprising a lower anchoring muscle and an upper anchoring muscle, and the lower anchoring muscle and the upper anchoring muscle are connected by a connecting member at a position near the upper end of the steel pipe. The pile head structure of the cast-in-place steel pipe concrete pile according to claim 1.
【請求項3】 外周面を異形に形成した接続部材を用い
たことを特徴とする請求項2記載の場所打鋼管コンクリ
ート杭の杭頭部構造。
3. The pile head structure of a cast-in-place concrete pipe pile according to claim 2, wherein a connection member having an outer peripheral surface formed in an irregular shape is used.
【請求項4】 定着筋が、降伏点490N/mm2以上
の高強度鉄筋からなることを特徴とする請求項1、2又
は3記載の場所打鋼管コンクリート杭の杭頭部構造。
4. The pile head structure of a cast-in-place steel tube concrete pile according to claim 1, wherein the anchoring bar is made of a high-strength reinforcing bar having a yield point of 490 N / mm 2 or more.
【請求項5】 定着筋が、ねじふし鉄筋からなることを
特徴とする請求項1、2、3又は4記載の場所打鋼管コ
ンクリート杭の杭頭部構造。
5. The pile head structure of a cast-in-place steel pipe concrete pile according to claim 1, wherein the anchoring bar is made of a screw bar.
【請求項6】 定着筋の少なくとも一端部に定着部材を
配設したことを特徴とする請求項1、2、3、4又は5
記載の場所打鋼管コンクリート杭の杭頭部構造。
6. The fixing member according to claim 1, wherein a fixing member is provided at least at one end of the fixing streaks.
Pile head structure of cast-in-place steel pipe concrete pile described.
【請求項7】 接続部材又は定着筋の下端部に配設する
定着部材を、鋼管の内周面に溶接したことを特徴とする
請求項2、3又は5記載の場所打鋼管コンクリート杭の
杭頭部構造。
7. The cast-in-place concrete pipe pile according to claim 2, wherein the connecting member or the fixing member disposed at the lower end of the fixing stud is welded to the inner peripheral surface of the steel pipe. Head structure.
【請求項8】 場所打鋼管コンクリート杭を構成する鋼
管の内周面に、略等間隔に高強度鉄筋からなる下部定着
筋を、下部定着筋と鋼管との間隔を下部定着筋の直径の
1.5倍以内に設定して配設した状態でコンクリートを
打設し、場所打鋼管コンクリート杭を構築した後、下部
定着筋の上端部に配した接続部材に高強度鉄筋からなる
上部定着筋を接続し、該上部定着筋をフーチングの構築
位置まで延出してコンクリートを打設し、フーチングを
構築することを特徴とする場所打鋼管コンクリート杭の
杭頭部の施工法。
8. An inner peripheral surface of a steel pipe constituting the cast-in-place steel pipe concrete pile, a lower anchoring bar made of high-strength rebar is provided at substantially equal intervals, and an interval between the lower anchoring bar and the steel pipe is set to one of the diameters of the lower anchoring bar. After setting concrete within 5 times and laying it out and constructing a cast-in-place steel pipe concrete pile, connect the upper anchoring bar consisting of high-strength rebar to the connecting member arranged at the upper end of the lower anchoring bar. A method of constructing a pile head of a cast-in-place steel pipe concrete pile, comprising connecting, extending the upper anchorage to a footing construction position, placing concrete, and constructing a footing.
JP09187734A 1997-04-25 1997-06-27 Pile head structure of cast-in-place steel pipe concrete pile and its construction method Expired - Fee Related JP3096660B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP09187734A JP3096660B2 (en) 1997-04-25 1997-06-27 Pile head structure of cast-in-place steel pipe concrete pile and its construction method

Applications Claiming Priority (5)

Application Number Priority Date Filing Date Title
JP12356297 1997-04-25
JP14356997 1997-05-16
JP9-143569 1997-05-16
JP9-123562 1997-05-16
JP09187734A JP3096660B2 (en) 1997-04-25 1997-06-27 Pile head structure of cast-in-place steel pipe concrete pile and its construction method

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP2000168359A Division JP3255634B2 (en) 1997-04-25 2000-06-06 Pile head structure of cast-in-place steel pipe concrete pile

Publications (2)

Publication Number Publication Date
JPH1129942A true JPH1129942A (en) 1999-02-02
JP3096660B2 JP3096660B2 (en) 2000-10-10

Family

ID=27314744

Family Applications (1)

Application Number Title Priority Date Filing Date
JP09187734A Expired - Fee Related JP3096660B2 (en) 1997-04-25 1997-06-27 Pile head structure of cast-in-place steel pipe concrete pile and its construction method

Country Status (1)

Country Link
JP (1) JP3096660B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008050901A (en) * 2006-08-28 2008-03-06 Okabe Co Ltd Pile head joint structure
JP2017082548A (en) * 2015-10-30 2017-05-18 高周波熱錬株式会社 Concrete foundation joint member and pile structure
CN111962499A (en) * 2020-07-09 2020-11-20 广州一建建设集团有限公司 Construction method for adding section steel column in manual hole digging pile

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008050901A (en) * 2006-08-28 2008-03-06 Okabe Co Ltd Pile head joint structure
JP2017082548A (en) * 2015-10-30 2017-05-18 高周波熱錬株式会社 Concrete foundation joint member and pile structure
CN111962499A (en) * 2020-07-09 2020-11-20 广州一建建设集团有限公司 Construction method for adding section steel column in manual hole digging pile

Also Published As

Publication number Publication date
JP3096660B2 (en) 2000-10-10

Similar Documents

Publication Publication Date Title
KR100704874B1 (en) Structures of prefabricated concrete pier strengthened in shear by steel pipe
KR20070083474A (en) Shearing force reinforcing structure and shearing force reinforcing member
CN104831818B (en) The connecting node of precast reinforced concrete beam and superposed column
JP6691880B2 (en) Precast wall balustrade mounting structure and mounting method
JP3036406B2 (en) Bridge pier reinforcement structure
KR101056027B1 (en) Combined structure of edge prestressed concrete composite pile with tension member and expansion foundation
KR101414054B1 (en) Mold for phc pile and the manufacturing method for phc pile using the same and the method for reinforcement of phc pile using the same
KR102290220B1 (en) Precast counterfort retaining walls and the construction method thereof
KR20110038443A (en) Connecting method and connecting structure between footing and prestressed precast concrete pile
JP4048552B2 (en) Construction method of pile head anchor bars for steel pipe piles
JP3096660B2 (en) Pile head structure of cast-in-place steel pipe concrete pile and its construction method
JP4107452B2 (en) Joint structure of pile and foundation concrete slab
JP3255634B2 (en) Pile head structure of cast-in-place steel pipe concrete pile
KR100922121B1 (en) Construction Structure of Footing using Hybrid Pile having Various Cross-section
JP3681367B2 (en) Joint structure of steel column and foundation concrete
KR102200400B1 (en) Precast segment, pillar structure including the same and construction method of pillar structure usinging the same
JPH1121915A (en) Connecting method of pile head
JP2831934B2 (en) How to build substructure
JPS62153418A (en) Pile with connector for reinforcing bar
JP3008795B2 (en) Joint structure of reinforced concrete beams
JP2000297480A (en) Reinforcing method for steel-pipe structure column base section
JPH07292770A (en) Connective structure between corner post and beam
CN112942862B (en) Steel bar supporting device of prestressed concrete column
KR100442704B1 (en) Method and structure for reinforcement of ferroconcrete construction by using of exterior tension member
JPH07292861A (en) Connecting structure of beam and wall

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 8

Free format text: PAYMENT UNTIL: 20080804

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090804

Year of fee payment: 9

LAPS Cancellation because of no payment of annual fees