JPH11247592A - Pipe jacking method for preceding intermediate shaft system - Google Patents

Pipe jacking method for preceding intermediate shaft system

Info

Publication number
JPH11247592A
JPH11247592A JP5217698A JP5217698A JPH11247592A JP H11247592 A JPH11247592 A JP H11247592A JP 5217698 A JP5217698 A JP 5217698A JP 5217698 A JP5217698 A JP 5217698A JP H11247592 A JPH11247592 A JP H11247592A
Authority
JP
Japan
Prior art keywords
shaft
pipe
propulsion device
wellhead
arrival
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP5217698A
Other languages
Japanese (ja)
Other versions
JP3965241B2 (en
Inventor
Kazukuni Tomita
和邦 冨田
Mikio Hayashi
幹雄 林
Hiroshi Hashiba
博史 橋場
Shunzo Sugimoto
俊三 杉本
Tsugio Yamamoto
次雄 山本
Yukio Ishizuka
幸雄 石塚
Koshi Kojima
紘志 児島
Minoru Fujimori
実 藤森
Katsuya Nozawa
克哉 野澤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FUKUDAGUMI KK
Takenaka Doboku Co Ltd
Original Assignee
FUKUDAGUMI KK
Takenaka Doboku Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FUKUDAGUMI KK, Takenaka Doboku Co Ltd filed Critical FUKUDAGUMI KK
Priority to JP05217698A priority Critical patent/JP3965241B2/en
Publication of JPH11247592A publication Critical patent/JPH11247592A/en
Application granted granted Critical
Publication of JP3965241B2 publication Critical patent/JP3965241B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide a pipe jacking method in which sewage pipes or the like are jacked to a target point, in order to embed the pipes in the underground. SOLUTION: An intermediate shaft 3 is constructed in the middle position of a starting shaft and an arrival shaft before the front end jacking device 2 arrives. When the front end jacking device 2 arrives at the liner of the intermediate shaft 3, the position of the front end jacking device 2 is confirmed and the base line in the shaft is measured and then, an entrance for the arrival shaft and an entrance for the starting shaft are formed in the intermediate shaft 3. A base frame is installed at the bottom of the intermediate shaft 3 and the lower half part of a protection pipe is mounted thereon. A face on which an opening allowing the front end jacking device 2 to pass through to the liner is opened along the inner periphery of the entrance for the arrival shaft to send the front end jacking device 2 toward the intermediate shaft 3. And also a face on which an opening allowing the front end jacking device 2 to pass through to the liner 4 is opened along the inner periphery of the starting shaft and the jacking device 2 is advanced to the outside of the intermediate shaft 3. An upper half part is mounted on the lower half part of the protection pipe and filling materials are injected into the sealed protection pipe and thereafter, a pipe body 1 is continued to jack.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、例えば下水道管
等を地下に埋設するにあたり、同管を地中内で目標地点
に向かって推進させて設置する管推進工法の技術分野に
係り、さらに言えば、発進立坑と到達立坑との中間にマ
ンホール等を設ける必要のために用意される中間立坑を
管の推進に先行して設け、管は中間立坑を貫通するよう
に推進させる、中間立坑先行型の管推進工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to the technical field of a pipe propulsion method in which, for example, when a sewer pipe or the like is buried underground, the pipe is propelled and installed toward a target point in the ground. For example, an intermediate shaft, which is provided for the necessity of providing a manhole or the like between the starting shaft and the reaching shaft, is provided prior to the propulsion of the pipe, and the pipe is propelled so as to penetrate the intermediate shaft. Pipe construction method.

【0002】[0002]

【従来の技術】従来、管推進工法は種々公知、周知であ
る。マンホール等の必要のため一定の管路長さ毎に設け
られる中間立坑の構築に関しては、大きくは管の推進
(通過)後に掘削して設ける方法と、中間立坑を先行し
て設ける方法とに大別される。更に後者の方法は、 構築した中間立坑において、先端推進装置を通過させ
た後、防護管による密閉を行わず、そのままの状態で放
置する方法。 構築した中間立坑において、先端推進装置を通過させ
た後、防護管による密閉の代わりに、直ちに同立坑を適
当な埋め戻し材で必要高さまで埋め戻し、その中で管を
推進、通過させ、その後再び立坑を復元する方法。 構築した中間立坑において、先端推進装置を通過させ
た後、防護管による密閉の代わりに、直ちに同立坑を泥
水等の液体で満水にし、その中で管を推進、通過させ、
その後再び立坑を復元する方法。に大別される。
2. Description of the Related Art Conventionally, various pipe propulsion methods are known and well known. Regarding the construction of intermediate shafts that are provided for each fixed pipe length due to the need for manholes, etc., there are two main methods: the method of excavating after the propulsion (passing) of the pipe and the method of providing the intermediate shaft in advance. Separated. In the latter method, after passing through the tip propulsion device in the constructed intermediate shaft, it is left as it is without sealing with a protective tube. In the constructed middle shaft, after passing through the tip propulsion device, instead of sealing with a protective tube, immediately backfill the shaft with a suitable backfill material to the required height, propelling and passing the tube in it, How to restore the shaft again. In the constructed intermediate shaft, after passing through the tip propulsion device, instead of sealing with a protective tube, immediately fill the same shaft with liquid such as muddy water, propelling and passing the tube in it,
Then restore the shaft again. Are roughly divided into

【0003】[0003]

【本発明が解決しようとする課題】I)管の推進(通
過)後に掘削して中間立坑を設ける方法についての問題
点 中間立坑の掘削に際しては埋設管が障害物となり、施工
される山留め用ライナープレートの設置は、垂直な立坑
と水平な埋設管との交差部分(交わりの稜線)を幾何学
的に解析して成形加工した複数のプレート片の集合とし
て組み立てることになり、プレートの加工及び組み立て
が大変面倒で手間がかかり、またライナープレートを使
った立坑の構造上、大きな欠損部位は立坑強度を弱くす
る。立坑の掘削に際しては管推進工の前に予め地盤改良
を行うのが一般的であるが、先端推進装置が立坑下を通
過した後、地山は乱れて水みちが付く。そのため補足の
地盤改良が行われるが、埋設管の存在によってその近隣
部位乃至下部の地盤改良が不十分となる場合がある。そ
の結果、地下水位が高い地盤では地山の崩壊、流出事故
を起こして掘削作業の進行が大幅に遅れ、工期が長引い
たり、周辺に陥没事故を起こす恐れがあり、工事が難し
い。そして、埋設管の近隣部位及び下部の掘削は手掘り
で行うほかなく、この意味でも工事が面倒で長引く。
[Problems to be Solved by the Invention] I) Problems with the Method of Excavating and Providing an Intermediate Shaft after Propulsion (Passing) of a Pipe When excavating an intermediate shaft, a buried pipe becomes an obstacle, and a liner for mountain retaining to be constructed The installation of the plates will be done by assembling a set of multiple plate pieces that have been geometrically analyzed by analyzing the intersection (intersection ridge) between the vertical shaft and the horizontal buried pipe, and processing and assembling the plates. However, it is very troublesome and time-consuming, and due to the structure of the shaft using the liner plate, a large defective portion weakens the strength of the shaft. When excavating a shaft, it is common to perform ground improvement before pipe propulsion, but after the tip propulsion device has passed under the shaft, the ground is disturbed and water sticks. Therefore, supplementary ground improvement is performed, but the ground improvement in the vicinity or below may be insufficient due to the presence of the buried pipe. As a result, in the ground with a high groundwater level, the excavation work progresses greatly due to the collapse and runoff of the ground, and the construction period may be prolonged or a collapse accident may occur in the surrounding area, making construction difficult. Excavation in the vicinity and below the buried pipe must be done by hand digging, and in this sense the construction is troublesome and prolonged.

【0004】埋設管の外径(2350mm)に比べて2カ
所の中間立坑の口径は3700〜4500mm程度と小さ
いため、作業スペースを十分にとれず、上記の問題点が
重複するという困難性もある。 II)中間立坑を先行して設け、管を推進、通過させた後
そのままの状態で放置する方法の問題点長期間の連続的
な管の通過により、坑口に付けたエントランスパッキン
が摩耗したり、転石等の異物がエントランスパッキンと
管との間に挟まったりしてエントランスパッキンを破損
する危険性がある。この場合、地下水位の高い地盤では
土砂と地下水が隙間から流出し、それが地山の崩壊を導
き、周辺地盤の沈下や陥没を起こす恐れが出てくる。 III)中間立坑を先行して設けるが、管を推進、通過さ
せるまで適切な埋め戻し材で埋め戻す方法の問題点この
方法は、上記II)の問題点を解決するための折衷案的な
ものであり、長所、短所が相半ばするが、一旦掘削し構
築した中間立坑を、管の推進、通過まで埋め戻すので、
工程の重複、2度手間の欠点は図り知れず大きい。ま
た、埋め戻しが完了するまで管推進工を停止する必要が
あり、再掘進時に大きな推力を必要とする。さらに立坑
内に切梁等が存在する場合、埋め戻しが困難である。I
V)中間立坑を先行して設けるが、管を推進、通過させ
るまで泥水等の液体で満水にする方法の問題点この方法
は、上記II)III)の問題点を解決するためのものであ
り、坑口の取り付け及び管の通過後、直ちに泥水等の液
体で立坑内を満水として再掘進することができるが、液
体内において作用する浮力が全て露出した管にかかるた
め、十分な浮力対策を行わないと管の蛇行やひねりを招
いたり、予期せぬ過大な偏圧によって管を破損する可能
性がある。
[0004] Since the diameter of the two intermediate shafts is as small as about 3700 to 4500 mm compared to the outer diameter (2350 mm) of the buried pipe, there is also a difficulty that a sufficient working space cannot be obtained and the above problems are duplicated. . II) The problem of a method in which an intermediate shaft is provided in advance, and the pipe is propelled and passed, and then left as it is after passing through the pipe for a long period of time. There is a danger that foreign materials such as boulders will be trapped between the entrance packing and the pipe, thereby damaging the entrance packing. In this case, in the ground with a high groundwater level, earth and sand and groundwater flow out from the gap, which leads to the collapse of the ground, and there is a possibility that the surrounding ground may sink or sink. III) Although an intermediate shaft is provided in advance, the problem of backfilling with an appropriate backfill material until the pipe is propelled and passed is a compromise that solves the problem of II) above. The advantages and disadvantages are half-way, but once the excavated and constructed intermediate shaft is backfilled until the pipe is propelled and passed,
The drawback of the duplication of the process and the trouble twice is inevitably large. In addition, it is necessary to stop the pipe propulsion work until the backfill is completed, which requires a large thrust when re-excavating. Further, when there are cut beams or the like in the shaft, backfilling is difficult. I
V) An intermediate shaft is provided in advance, but the problem is that the pipe is filled with liquid such as muddy water until the pipe is propelled and passed. This method is to solve the problems of II) and III) above. Immediately after the installation of the wellhead and the passage of the pipes, the shaft can be refilled immediately with liquid such as muddy water, but the buoyancy acting in the liquid is applied to the exposed pipes. Otherwise, the pipe may meander and twist, or the pipe may be damaged by an unexpectedly large bias.

【0005】従って、本発明の目的は、中間立坑を先行
して構築する長所を温存しつつ、管の推進、通過を安全
に効率よく短工期に行えるように改良した中間立坑先行
型の管推進工事を提供することである。
SUMMARY OF THE INVENTION Accordingly, an object of the present invention is to improve an intermediate shaft leading type pipe propulsion in which the advancement and construction of the intermediate shaft is preserved, and the pipe propulsion and passage can be performed safely and efficiently in a short period of time. Is to provide construction.

【0006】[0006]

【課題を解決するための手段】上記の課題を解決するた
めの手段として、請求項1記載の発明に係る中間立坑先
行型の管推進工法は、発進立坑に設置した元押し装置と
先端推進装置との協同作用により管体を到達立坑に向か
って推進させる管推進工法において、発進立坑と到達立
坑との中間位置に、管体を通過させる中間立坑を、先端
推進装置の到達以前に構築すること、先端推進装置が中
間立坑のライナーへ到達した段階で、同先端推進装置の
位置を確認して立坑内基線の測量を行い、前記の測量結
果に基づいて到達坑口と発進坑口を中間立坑内に設置す
ること、中間立坑の底部に架台を設置し、その上に前記
到達坑口と発進坑口を連絡する防護管の下半部を取り付
けること、前記到達坑口の内周に沿ってライナーに先端
推進装置を通過させる開口を設ける鏡切りを行い、先端
推進装置を中間立坑内へ進ませること、発進立坑の内周
に沿ってライナーに先端推進装置を通過させる開口を設
ける鏡切りを行い、先端推進装置を中間立坑の外まで進
ませること、前記防護管の下半部の上に上半部を取付
け、密閉された防護管の中に充填材を注入し、その後管
体の推進を続行すること、をぞれぞれ特徴とする。所謂
坑口方式である。
As a means for solving the above-mentioned problems, an intermediate shaft leading type pipe propulsion method according to the first aspect of the present invention comprises a main pushing device and a tip propulsion device installed in a starting shaft. In the pipe propulsion method of propelling the pipe toward the arrival shaft by the cooperation with the above, to construct an intermediate shaft through which the pipe passes at an intermediate position between the start shaft and the arrival shaft before the tip propulsion device reaches At the stage where the tip propulsion device reached the liner of the middle shaft, the position of the tip propulsion device was confirmed and the baseline of the shaft was measured, and based on the measurement results, the arrival well and the start well were placed in the middle shaft. Installing, installing a gantry at the bottom of the intermediate shaft, attaching the lower half of the protective tube that connects the reaching wellhead and the starting wellhead, the tip propulsion device to the liner along the inner circumference of the reaching wellhead Passed through To make the tip propulsion device advance into the middle shaft, perform the mirror cutting to provide an opening for passing the tip propulsion device through the liner along the inner circumference of the starting shaft, Going out of the shaft, mounting the upper half on the lower half of the protective tube, injecting the filler into the sealed protective tube, and then continuing to propel the tube. Each feature. This is a so-called wellhead method.

【0007】請求項2記載の発明は、請求項1に記載し
た中間立坑先行型の管推進工法において、到達坑口と発
進坑口に補強コンクリートを打設し、また、先端推進装
置を到達坑口に通過させる以前、及び発進坑口へ前進さ
せる以前に各坑口にエントランスパッキンを取付けてお
き、そこを先端推進装置を通過させてから防護管で密閉
し、速硬性または通常硬化の充填材で空隙を充填するこ
とを特徴とする。
According to a second aspect of the present invention, there is provided an intermediate shaft leading type pipe propulsion method according to the first aspect, in which reinforcing concrete is poured into the arrival wellhead and the start wellhead, and the tip propulsion device passes through the arrival wellhead. Before entrance and before proceeding to the starting wellhead, install entrance packing at each wellhead, pass it through the tip propulsion device, seal it with a protective tube, and fill the gap with fast-curing or normally hardening filler. It is characterized by the following.

【0008】請求項3記載の発明は、請求項1に記載し
た中間立坑先行型の管推進工法において、到達坑口と発
進坑口には、先端推進装置を到達坑口に通過させる以
前、及び発進坑口へ前進させる以前に各坑口にエントラ
ンスパッキンを取付けておき、そこを先端推進装置を通
過させてから防護管で密閉し、速硬性または通常硬化の
充填材で空隙を充填することを特徴とする。
[0010] According to a third aspect of the present invention, in the intermediate shaft leading type pipe propulsion method according to the first aspect, the arrival port and the start port are provided before the tip propulsion device is passed through the arrival port and to the start port. An entrance packing is attached to each wellhead before moving forward, and the entrance packing is passed through the tip propulsion device, then sealed with a protective tube, and the gap is filled with a fast-curing or normally hardening filler.

【0009】請求項4記載の発明に係る中間立坑先行型
の管推進工法は、発進立坑に設置した元押し装置と先端
推進装置との協同作用により管体を到達立坑に向かって
推進させる管推進工法において、発進立坑と到達立坑と
の中間位置に、管体を通過させる中間立坑を、先端推進
装置の到達以前に構築すると共に以下の準備を行うこ
と、先端推進装置の通過予定位置に基づいて中間立坑内
基線の測量を行い、前記の測量結果に基づいて中間立坑
の底部に架台を設置し、その上に防護管の下半部と管両
端部を取り付けること、到達側と発進側の管端部の内周
に沿ってライナーに先端推進装置を通過させる開口を設
ける鏡切りを行い、防護管の上半部を取付け、かくして
密閉された防護管の内部へ充填材を注入すること、以上
の準備を完了した後に、先端推進装置を中間立坑にまで
到達させ、更に防護管の中を通過させて管体の推進を継
続すること、をぞれぞれ特徴とする。所謂貫通方式であ
る。
According to a fourth aspect of the present invention, there is provided a pipe propulsion method in which a pipe body is propelled toward an arrival shaft by the cooperation of a main pushing device and a tip propulsion device installed in a starting shaft. In the construction method, at the intermediate position between the starting shaft and the reaching shaft, construct an intermediate shaft through which the pipe passes before the arrival of the tip propulsion device, and perform the following preparations, based on the scheduled passage position of the tip propulsion device. Survey the baseline of the middle shaft, install a gantry on the bottom of the middle shaft based on the above survey results, attach the lower half of the protective tube and both ends of the tube on it, Making a mirror cut along the inner circumference of the end to provide an opening for the tip propulsion device to pass through the liner, attaching the upper half of the protective tube, and injecting the filling material into the inside of the sealed protective tube thus closed. After completing the preparation , To reach the leading propulsion device to an intermediate vertical shaft, further passed through the inside of the protective tube to continue to promote tube, and, respectively, wherein, respectively a. This is a so-called penetration method.

【0010】請求項5記載の発明は、請求項4に記載し
た中間立坑先行型の管推進工法において、ライナーの鏡
切りの直後に管端部の坑内側端面を密閉し、速硬性の充
填材を管端部の中に充填し、同充填材が硬化した後に前
記密閉を解くことを特徴とする。請求項6記載の発明
は、請求項4に記載した中間立坑先行型の管推進工法に
おいて、防護管の内部への充填材の注入は、先ず防護管
の下半部に速硬性の充填材を充填し、続いて防護管の残
る空隙部に通常硬化の充填材を密に充填することを特徴
とする。
According to a fifth aspect of the present invention, there is provided an intermediate shaft preceding type pipe propulsion method according to the fourth aspect, wherein a pit inner end face of a pipe end is sealed immediately after mirror cutting of the liner, and a quick-curing filler is provided. Is filled in the pipe end, and the sealing is released after the filling material has hardened. According to a sixth aspect of the present invention, in the middle shaft leading type pipe propulsion method according to the fourth aspect, the filling of the filler into the inside of the protection pipe is performed by first filling the lower half of the protection pipe with a quick-hardening filler. After filling, the remaining space of the protective tube is densely filled with a normally hardening filler.

【0011】請求項7記載の発明は、請求項4に記載し
た中間立坑先行型の管推進工法において、防護管の内部
への充填材の注入は、防護管の下半部に通常硬化の充填
材を充填し、続いて防護管の残る空隙部にも通常硬化の
充填材を密に充填することを特徴とする、。
According to a seventh aspect of the present invention, in the pipe propulsion method according to the fourth aspect of the present invention, the filling of the filler into the inside of the protective tube is performed by filling the lower half of the protective tube with a normally hardened filler. Material is filled, and then the remaining space of the protective tube is also densely filled with a normally hardened filler.

【0012】[0012]

【発明の実施の形態及び実施例】請求項1記載の発明に
係る中間立坑先行型の管推進工法は、図示を省略した発
進立坑に設置された元押し装置と先端推進装置との協同
作用により管体を到達立坑に向かって推進させる管推進
工法において、所謂坑口方式として好適に実施される。
なお、図示を省略した発進立坑の反力壁裏側の地山は、
先端推進装置2及び管体の推進力によって地山が挙動し
ないように、場合によっては薬液補強注入を行う。これ
は、管内測量の精度を確保する意味もある。
DESCRIPTION OF THE PREFERRED EMBODIMENTS An intermediate shaft leading type pipe propulsion method according to the first aspect of the present invention is based on the cooperation between a main pushing device and a tip propulsion device installed in a starting shaft (not shown). In a pipe propulsion method for propelling a pipe toward an arrival shaft, a so-called wellhead method is suitably implemented.
The ground behind the reaction wall of the starting shaft not shown is
In some cases, the chemical solution reinforcement injection is performed so that the ground does not behave by the propulsive force of the distal end propulsion device 2 and the pipe. This also has the purpose of ensuring the accuracy of in-pipe surveying.

【0013】その枢要な工程図を図1〜図6に示した。
図示を省略した発進立坑と到達立坑との中間位置に、管
体1を通過させる中間立坑3を、先端推進装置2の到達
以前に構築することが第1の条件である。中間立坑3の
構築は、仮設計画段階で防護管等の部材が立坑内に搬入
できるように、覆工計画や既設管の吊り防護計画等を行
う。施工では掘削地盤について先ず薬液注入等による地
盤改良を行う。この時、特に先端推進装置2の到達と発
進坑口付近には地山補強のために薬液補足注入を行う。
その後公知の掘削工法により、山留めのライナープレー
ト4を施工しつつ地盤を中堀りする方式で所要の深さ
(例えば地下8.5m位)まで掘削し構築する。今回坑
口方式を採用した中間立坑3の口径は、最終的なマンホ
ールの仕上がりを考慮しておよそ4.5m程度である。
掘削底面には底盤コンクリート5を打設する。また、ラ
イナープレート4の外周地盤には余掘りした空隙を埋め
るために、ライナープレート設置後逐次裏込め注入を行
う。
FIGS. 1 to 6 show the essential process charts.
The first condition is that an intermediate shaft 3 through which the pipe 1 passes is constructed before the arrival of the tip propulsion device 2 at an intermediate position between the starting shaft and the reaching shaft, not shown. The construction of the intermediate shaft 3 includes a lining plan and a suspension protection plan for existing pipes so that members such as protection pipes can be carried into the shaft at the stage of the preliminary design. In the construction, the ground improvement is first performed on the excavated ground by injection of chemicals. At this time, a chemical solution supplement injection is performed especially for reaching the tip propulsion device 2 and near the starting wellhead for reinforcing the ground.
Thereafter, by a well-known excavation method, the ground is excavated to a required depth (for example, about 8.5 m underground) by the method of digging the ground while constructing the liner plate 4 of the mountain retaining. The diameter of the intermediate shaft 3 adopting the wellhead method this time is about 4.5 m in consideration of the final manhole finish.
The bottom concrete 5 is cast on the bottom of the excavation. In addition, in order to fill the gap dug in the outer peripheral ground of the liner plate 4, backfilling is sequentially performed after the liner plate is installed.

【0014】発進立坑から発進させ推進を進めて来た先
端推進装置2は、前記のように中間立坑3の構築が完成
した後に、当該中間立坑3のライナー4へ到達させる。
ここで先端推進装置2が中間立坑3のライナー4へ到達
するとは、先端推進装置2の先端をライナー4へ押し当
て坑内側へ若干膨らます程度に突き当たった状態を意味
する。この段階で、中間立坑3の内側から、先端推進装
置2の先端が当たって膨らんだ部分のライナー4を確認
作業に必要な範囲まで切り取り、目視により同先端推進
装置2の推進位置を確認して立坑内基線の測量を行う。
そして、前記の測量結果に基づいて定めた位置に到達坑
口6と発進坑口7を中間立坑3内に設置し、補強コンク
リート8を打設して強固に固定する。
The tip propulsion device 2 that has started and advanced the propulsion from the starting shaft, reaches the liner 4 of the intermediate shaft 3 after the construction of the intermediate shaft 3 is completed as described above.
Here, that the tip propulsion device 2 reaches the liner 4 of the intermediate shaft 3 means a state where the tip of the tip propulsion device 2 is pressed against the liner 4 and swells slightly to the inside of the pit. At this stage, from the inside of the intermediate shaft 3, the liner 4 of the portion protruded by the tip of the tip propulsion device 2 is cut out to a range necessary for the checking operation, and the propulsion position of the tip propulsion device 2 is visually confirmed. Conduct survey of the shaft in the shaft.
Then, the reaching wellhead 6 and the starting wellhead 7 are installed in the intermediate shaft 3 at the positions determined based on the above-described survey results, and the reinforcing concrete 8 is cast and firmly fixed.

【0015】到達坑口6と発進坑口7、補強コンクリー
ト8の詳細な構造は、図7〜図11に実施例を示したと
おりである。到達坑口6と発進坑口7は共に鋼板の組み
立て品であり、先端推進装置2が通過する線上に同先端
推進装置2が通過し得る口径(例えば管体外径が235
0mmに対して約100mmの隙間を持つ口径)の円筒体6
a又は7aの外端がライナープレート4と溶接で密接に
接合される。該円筒体6a又は7aの内端部にはリング
状のフランジ6b又は7bが直角外向きに取付けられ、
前記円筒体の外周とフランジ及びライナープレート4と
に囲まれた隅部に補強コンクリート8が打設され、もっ
て各坑口の取付け状態を大重量の先端推進装置2及び管
体1の通過に耐える構成とされている。もっとも、坑口
及び防護管の支持耐力に不安があるときは、同防護管の
下半部に補強コンクリートを打設することも行う。
The detailed structures of the reaching wellhead 6, the starting wellhead 7, and the reinforced concrete 8 are as shown in FIGS. The reaching wellhead 6 and the starting wellhead 7 are both steel plate assemblies, and have a diameter (for example, a pipe outer diameter of 235) through which the tip propulsion device 2 can pass along the line through which the tip propulsion device 2 passes.
Cylindrical body 6 with a gap of about 100 mm for 0 mm)
The outer end of a or 7a is closely joined to the liner plate 4 by welding. A ring-shaped flange 6b or 7b is attached to the inner end of the cylindrical body 6a or 7a at a right angle outward,
Reinforced concrete 8 is cast at the corner surrounded by the outer periphery of the cylindrical body, the flange, and the liner plate 4, so that the mounting state of each wellhead can withstand the passage of the heavy-weight tip propulsion device 2 and pipe 1. It has been. However, if there is any concern about the bearing capacity of the wellhead and protection pipe, reinforced concrete may be poured into the lower half of the protection pipe.

【0016】前記到達坑口6のフランジ6bには、先端
推進装置2及び管体1の通過時に土砂、地下水の流出を
可及的に防止する手段としてドーナツ形状のゴム製エン
トランスパッキン9を取り付ける。エントランスパッキ
ン9は管体1の外径よりも少し小さい(実施例では半径
にして200mm程度小さい)内径のドーナツ形状のもの
であり、これは図8のように当該パッキン9の坑内面側
に、且つ図9のように放射方向に多数配置する平プレー
ト形状のパッキン押さえ10と共にボルト11で外径寄
り位置を固定される。また、各パッキン押さえ10の内
径寄り位置に設けられたパイプ10aにワイヤー12を
一連に通して円形状に配置しておく。従って、この到達
坑口6を先端推進装置2及び管体1が通過するときは、
前記エントランスパッキン9はパッキン押さえ10と共
に図8に点線で示したように坑内側へ先細のラッパ状に
突き出すように変形する。その際前記のワイヤー12を
引き絞ることによって土砂、地下水の流出を防ぐに足る
密閉圧力をエントランスパッキン9へ付与する。
A doughnut-shaped rubber entrance packing 9 is attached to the flange 6b of the arrival well 6 as a means for preventing outflow of earth and sand and groundwater as much as possible when passing through the tip propulsion device 2 and the pipe 1. The entrance packing 9 is of a donut shape having an inner diameter slightly smaller than the outer diameter of the pipe 1 (in the embodiment, smaller by about 200 mm in radius), and is located on the inner surface side of the packing 9 as shown in FIG. Further, as shown in FIG. 9, a position close to the outer diameter is fixed by bolts 11 together with a plurality of flat plate-shaped packing holders 10 arranged in the radial direction. Further, a wire 12 is passed through a pipe 10a provided at a position close to the inner diameter of each packing retainer 10 and arranged in a circular shape. Therefore, when the tip propulsion device 2 and the pipe 1 pass through the arrival well 6,
The entrance packing 9 is deformed together with the packing retainer 10 so as to protrude toward the inside of the downhole in a tapered trumpet shape as shown by a dotted line in FIG. At this time, by closing the wire 12, a sealing pressure sufficient to prevent the outflow of earth and sand and groundwater is applied to the entrance packing 9.

【0017】また、発進坑口7のフランジ7bの坑内面
側にも、先端推進装置2及び管体1の通過時に土砂、地
下水の流出を可及的に防止する手段として、ドーナツ形
状のゴム製エントランスパッキン9を取り付ける。この
エントランスパッキン9も管体1の外径よりも少し小さ
い内径のドーナツ形状であり、これは図10のように当
該パッキン9の坑内面側に、且つ図11のように放射方
向に多数配置する平プレート形状のパッキン押さえ13
と共にボルト11で外径寄り位置を固定される。
Also, a donut-shaped rubber entrance is provided on the inner surface of the flange 7b of the starting wellhead 7 as a means for preventing outflow of earth and sand and groundwater as much as possible through the tip propulsion device 2 and the pipe 1. Attach packing 9. The entrance packing 9 also has a donut shape having an inner diameter slightly smaller than the outer diameter of the tube body 1, and is arranged in a large number on the inner surface side of the packing 9 as shown in FIG. 10 and in the radial direction as shown in FIG. Flat plate-shaped packing retainer 13
At the same time, the position closer to the outer diameter is fixed by the bolt 11.

【0018】従って、この発進坑口7を先端推進装置2
及び管体1が通過するときは、前記エントランスパッキ
ン9はパッキン押さえ13と共に図10に点線で示した
ように坑口の中へ引っ張り込まれて先細のラッパ状に変
形する。その背後をパッキン押さえ13が支えて土砂、
地下水の流出を防ぐに足る密閉圧力をエントランスパッ
キン9に生じさせる。
Therefore, the starting wellhead 7 is connected to the tip propulsion device 2.
When the pipe 1 passes, the entrance packing 9 is pulled into the wellbore together with the packing retainer 13 as shown by a dotted line in FIG. Behind that, the packing retainer 13 supports the earth and sand,
Entrance packing 9 creates a sealing pressure sufficient to prevent groundwater outflow.

【0019】上記のようにして坑口の準備が出来た後
に、当該中間立坑3の底部、即ち底盤コンクリート5の
上に架台14を設置し、その上に前記到達坑口6と発進
坑口7を連絡する防護管を半割りにした下半部15を取
り付ける。その詳細は図10に上半部16の取付け態様
を点線で図示し、図12に下半部15と上半部16の関
係を示したように行う。即ち、下半部15と坑口とは、
同坑口のフランジ6b又は7bの坑内面側に防護管取付
け用の袋ナット17を同心配置しておいて、フランジ6
b,7bに防護管の下半部15のフランジを当接させ、
両者はフランジ同士をボルト止めする。この時、下半部
15の底部のボルト止めの作業を容易にするため、予め
下半部15には作業口を適当に準備しておく。なお、下
半部15の取り付けが完了したら、作業口及び隙間はロ
ール加工した鉄板等を溶接して覆い、充填材が漏出しな
い構造とする。
After the preparation of the wellhead as described above, the gantry 14 is installed on the bottom of the intermediate shaft 3, that is, on the bottom concrete 5, and the reaching wellhead 6 and the starting wellhead 7 are communicated thereon. Attach the lower half 15 of the protective tube in half. The details are performed as shown in FIG. 10 by a dotted line showing how the upper half 16 is attached, and FIG. 12 shows the relationship between the lower half 15 and the upper half 16. That is, the lower half 15 and the wellhead
A cap nut 17 for attaching a protective tube is concentrically disposed on the inner surface side of the flange 6b or 7b of the wellhead, and the flange 6b
b, 7b abut the flange of the lower half 15 of the protection tube,
Both bolt the flanges together. At this time, in order to facilitate the work of bolting the bottom of the lower half portion 15, a working port is appropriately prepared in advance in the lower half portion 15 in advance. When the attachment of the lower half 15 is completed, the work opening and the gap are covered by welding a rolled iron plate or the like so that the filler does not leak.

【0020】次に、前記到達坑口6の内周に沿ってライ
ナー4に先端推進装置2を通過させる口径の開口を設け
る鏡切りを行う。鏡切りはライナー4を溶断する方法が
好適に実施される。この場合、ライナープレート4の外
周地盤については、当初に説明したように予め地盤改良
を施しておくので、鏡の崩壊、地山の崩壊は一応防止さ
れている。しかし、なお不測の崩壊事故を防ぐため、前
記下半部15の内周に予め防護壁18を設けておき、最
悪の場合でも地山の崩壊は45°程度の安息角で安定化
させることを図る。そして、鏡切りの後は速やかに図4
のように先端推進装置2を推進させ到達坑口6の中へ進
入させて坑口を塞ぎ、土砂及び地下水の流入を可及的に
防ぐ。その後に前記防護壁18は撤去する。従って、前
記防護壁18は撤去を容易ならしめるため、ボルト止め
としておく。
Next, mirror cutting is performed to provide an opening having a diameter through which the tip propulsion device 2 can pass through the liner 4 along the inner periphery of the arrival well 6. For the mirror cutting, a method of fusing the liner 4 is preferably performed. In this case, since the ground around the outer periphery of the liner plate 4 is previously subjected to ground improvement as previously described, the collapse of the mirror and the collapse of the ground are temporarily prevented. However, in order to prevent an unexpected collapse accident, a protective wall 18 is provided in advance on the inner periphery of the lower half portion 15, and in the worst case, the collapse of the ground is stabilized at a repose angle of about 45 °. Aim. And immediately after the mirror cutting, FIG.
As described above, the tip propulsion device 2 is propelled and made to enter the reaching wellhead 6 to close the wellhead, thereby preventing inflow of earth and sand and groundwater as much as possible. Thereafter, the protective wall 18 is removed. Therefore, the protection wall 18 is bolted to facilitate removal.

【0021】次に、発進立坑7の内周に沿ってライナー
4に先端推進装置2を通過させる開口を設ける鏡切りを
行う。その後速やかに先端推進装置2を発進立坑7へ進
入させ、更に中間立坑3(ライナープレート4)の外へ
図5のように突き出る状態にまで進ませ、もって発進立
坑7の坑口を塞ぎ、土砂及び地下水の流入を可及的に防
ぐ。
Next, mirror cutting is performed along the inner periphery of the starting shaft 7 so that the liner 4 has an opening through which the tip propulsion device 2 passes. Thereafter, the tip propulsion device 2 is promptly advanced into the starting shaft 7 and further advanced to a state of protruding out of the intermediate shaft 3 (liner plate 4) as shown in FIG. 5, thereby closing the opening of the starting shaft 7, Prevent inflow of groundwater as much as possible.

【0022】しかる後に、図5及び図6のように防護管
の前記下半部15の上に上半部16を載せ、両坑口側は
袋ナットでのボルト止めをし、下半部15と上半部16
はフランジ同士のボルト止めにて防護管を完成する。こ
のように本工法は一度先端推進装置2を中間立坑3内に
露出させるため、もし工事上の障害、事故が生じたとき
は即時の対応措置を実行することが可能であり、安全、
確実な方法である。
After that, as shown in FIGS. 5 and 6, the upper half 16 is placed on the lower half 15 of the protective tube, and the two wellheads are bolted with cap nuts. Upper half 16
Completes the protective tube by bolting the flanges together. In this way, the present method once exposes the tip propulsion device 2 to the intermediate shaft 3, so that if a trouble or accident occurs during construction, it is possible to take immediate measures to ensure safety,
It is a sure way.

【0023】前記の工程で完成された防護管は、充填材
の漏出を防止するために、外側から止水モルタル等で間
隙を密閉してから、充填材を密実に注入して防護管の中
を地山と同等な条件に保つ。使用する充填材は、例えば
セメントとベントナイトを水で混合した通常の硬化速度
のものであり、場合によっては水ガラスとセメントを混
合した速硬性の充填材を使用する。その後管体1の推進
を再開し続行する。
In the protective tube completed in the above process, in order to prevent leakage of the filler, the gap is sealed from the outside with a waterproof mortar or the like, and then the filler is injected tightly to prevent the filler from leaking. Is maintained in the same condition as the ground. The filler used is, for example, one having a normal hardening rate obtained by mixing cement and bentonite with water. In some cases, a fast-curing filler obtained by mixing water glass and cement is used. Thereafter, the propulsion of the tube 1 is restarted and continued.

【0024】本工法によれば、中間立坑3に関係する地
山の崩壊、陥没事故、周辺民家の損傷といったトラブル
は皆無で実施され、また中間立坑を管推進の前に築造で
きたことは工期及び工程面での意義も大きかった。次
に、請求項3に記載した発明に係る中間立坑先行型の管
推進工法も、やはり発進立坑に設置した元押し装置と先
端推進装置との協同作用により管体を到達立坑に向かっ
て推進させる管推進工法において、所謂貫通方式として
好適に実施される。勿論、発進立坑と到達立坑との中間
位置に、管体を通過させる中間立坑3を、先端推進装置
2の到達以前に完全に構築することが条件であるが、本
工法の場合は、先端推進装置2が到達される前に、中間
立坑3の構築と防護管の設置が完成していることが特徴
である。従って、上記の大実施例のように、中間立坑3
へ先端推進装置2を到達させたまま、準備が整うまで待
機させる方法に比べて、時間の無駄がない。本工法の場
合、先端推進装置2の到達以前に次の準備を行う。
According to the present construction method, troubles such as collapse of the ground, collapsing accidents, and damage to surrounding houses related to the intermediate shaft 3 were carried out without any trouble, and the intermediate shaft was successfully constructed before pipe propulsion. And the significance in the process was also great. Next, the intermediate shaft leading type pipe propulsion method according to the invention described in claim 3 also promotes the pipe body toward the arrival shaft by the cooperative action of the main pushing device and the tip propulsion device also installed in the starting shaft. In the pipe propulsion method, it is suitably implemented as a so-called penetration method. Of course, it is a condition that the intermediate shaft 3 through which the pipe is passed is completely constructed before the arrival of the tip propulsion device 2 at an intermediate position between the starting shaft and the reaching shaft, but in the case of this construction method, the tip propulsion is required. It is a feature that the construction of the intermediate shaft 3 and the installation of the protection pipe are completed before the device 2 is reached. Therefore, as in the above-described large embodiment, the intermediate shaft 3
There is no waste of time as compared with a method in which the front-end propulsion device 2 is made to reach the standby state until the preparation is completed. In the case of this construction method, the following preparation is performed before the tip propulsion device 2 arrives.

【0025】本工法を実施する枢要な工程を図13〜図
18に示した。今回貫通方式を採用した中間立坑3の口
径は、最終的なマンホールの仕上がりを考慮しておよそ
3.7m程度である。中間立坑3が完成すると、測量し
ながら方向制御をして推進してくる先端推進装置2の通
過予定位置に基づいて中間立坑内基線の測量を行い、前
記の測量結果に基づいて中間立坑の底部、即ち底盤コン
クリート5の上に架台14を設置し、その上に防護管の
下半部20aと管両端部20bを取り付ける(図13,
図14)。つまり、推進してくる先端推進装置2の通過
予定位置に基づいて予め防護管を用意する工法であるか
ら、その前提として、先端推進装置2の推進制御に関し
て、高度に正確な、信頼性の高い測量及び方向制御の技
術が確立されていることが要求される。
The essential steps for implementing this method are shown in FIGS. The diameter of the intermediate shaft 3 adopting the penetration method this time is about 3.7 m in consideration of the final manhole finish. When the intermediate shaft 3 is completed, the middle shaft is surveyed on the basis of the planned passage position of the tip propulsion device 2 which is controlled and directionally controlled while surveying, and the bottom of the intermediate shaft is measured based on the survey result. That is, the gantry 14 is installed on the bottom concrete 5, and the lower half 20a of the protection tube and both ends 20b of the protection tube are attached thereon (FIG. 13, FIG. 13).
(FIG. 14). That is, since the protection pipe is prepared in advance based on the expected passing position of the tip propulsion device 2 to be propelled, it is assumed that the propulsion control of the tip propulsion device 2 is highly accurate and highly reliable. It is required that the technology of surveying and direction control is established.

【0026】その後到達側と発進側それぞれの管端部2
0bの内周に沿って、ライナー4に先端推進装置2を通
過させる開口を設ける鏡切りを行う。鏡切りはライナー
4を溶断する方法が好適に実施され、溶断に際しては、
管端部20bとライナー4との接合部からライナー端片
を若干(実施例では30mmぐらい)残すように溶断す
るのが良い。本工法の場合も、ライナープレート4の外
周地盤については、当初に予め地盤改良をし、更に到達
と発進部分には補足注入をしており、また未だ先端推進
装置2が到達していないので地山が乱されていない利点
もあり、鏡の崩壊、地山の崩壊は一応防止されている。
しかし、なお不測の崩壊事故を防ぐため、管端部20b
の坑内側端面の下半部位に予め防護壁を設けておき、最
悪の場合でも地山の崩壊は前記の防護壁で抑制して45
°程度の安息角で安定化させることを図ることも良い。
そして、前記鏡切りを終えると速やかに管端部20bの
坑内側端面を防護壁により全面を密閉し、速硬性の充填
材を管端部20bの中に充填し、地山の崩壊、地下水の
流出を可及的に未然に防止する。前記充填材が十分硬化
した後に、前記防護壁を撤去して密閉を解く。前記速硬
性の充填材としては、瞬時に硬化する水ガラスとセメン
ト系の充填材が好適に使用される。
Thereafter, the tube ends 2 of the arrival side and the start side, respectively.
Along the inner periphery of Ob, the liner 4 is mirror-cut to provide an opening through which the tip propulsion device 2 passes. For the mirror cutting, a method of fusing the liner 4 is preferably performed.
The liner end piece is preferably blown so as to leave a little (about 30 mm in the embodiment) from the joint between the pipe end 20b and the liner 4. Also in the case of this method, the ground around the outer periphery of the liner plate 4 has been improved in advance at the beginning, and supplementary injection has been performed at the reaching and starting portions. Since the tip propulsion device 2 has not yet reached the ground, There is also an advantage that the mountain is not disturbed, and the collapse of the mirror and the collapse of the ground are temporarily prevented.
However, to prevent accidental collapse, the pipe end 20b
A protective wall is provided in advance in the lower half of the inner surface of the mine, and in the worst case, collapse of the ground is suppressed by the protective wall.
It is also good to stabilize at an angle of repose of about °.
When the mirror cutting is completed, the inner surface of the pipe end 20b is immediately sealed with a protective wall, and a quick-hardening filler is filled in the pipe end 20b, and the collapse of ground and groundwater. Prevent spills as much as possible. After the filler has hardened sufficiently, the protective wall is removed and the seal is broken. As the quick-setting filler, a water-glass and cement-based filler which hardens instantaneously is preferably used.

【0027】その後に、防護管の上半部を取り付けて防
護管20の組み立てを完成させる。防護管20の構造の
詳細は図18に示した通りで、全て鋼板の組み立て品で
ある。この防護管20は、先端推進装置2及び管体1の
通過時にそれらの重量に耐える強度に設計、製作されて
いる。前記の工程で完成された防護管は、充填材の漏出
を防止するために、防護管の内外側から止水モルタル等
で間隙を密閉してから、充填材を密実に注入する(図1
5)。ここで充填材の注入方法としては、先ず防護管の
下半部20aの範囲に速硬性の充填材を充填し、防護管
と両側端部の溶接箇所等からの充填材の漏出を防ぐ。続
いて防護管の残る空隙部(上半部)に通常硬化の充填材
(例えば既述したセメント、ベントナイト系充填材)を
密に充填する。その結果、防護管20の内部は、地山と
同等な条件になって地山の崩壊、地下水の流出等の事故
は未然に防止される。さらに、万一の不測の事故を未然
に防止するために、管端部20bの外周に図18のよう
に強化コンクリート8を打設したり、防護管20の外周
の下部に図16及び図19のように補強コンクリート2
1を打設して、防護管の耐力の向上を図ることも好まし
い。
Thereafter, the upper half of the protection tube is attached to complete the assembly of the protection tube 20. The details of the structure of the protection tube 20 are as shown in FIG. The protection tube 20 is designed and manufactured to have a strength to withstand the weight of the tip propulsion device 2 and the tube 1 when passing through the tube. In the protective tube completed in the above process, in order to prevent the leakage of the filler, the gap is sealed from inside and outside of the protective tube with a waterproof mortar or the like, and then the filler is injected tightly (FIG. 1).
5). Here, as a method for injecting the filler, first, a range of the lower half portion 20a of the protective tube is filled with a quick-hardening filler to prevent leakage of the filler from a welded portion between the protective tube and both ends. Subsequently, the remaining space (upper half) of the protective tube is densely filled with a normally hardening filler (for example, the cement or bentonite filler described above). As a result, the inside of the protection pipe 20 is in the same condition as the ground, and accidents such as collapse of the ground and outflow of groundwater are prevented beforehand. Further, in order to prevent an unexpected accident from occurring, reinforced concrete 8 is cast on the outer periphery of the pipe end 20b as shown in FIG. Like reinforced concrete 2
It is also preferable to improve the yield strength of the protective tube by casting 1.

【0028】以上の準備が全て完了した後に、先端推進
装置を中間立坑にまで到達させ、そのまま停止すること
なく、図17のように防護管20の中を通過させて、次
の中間立坑又は到達立坑に推進を継続する事になる。本
工法においても、中間立坑3に関係する地山の崩壊、陥
没事故、周辺民家の損傷といったトラブルは皆無で実施
され、しかも先端推進装置が到達する前に防護管設置の
準備が完了することから、坑口方式よりも工期を短縮す
ることができた。これら坑口方式と貫通方式の2つの工
法により、350mの管推進と2カ所の中間立坑の構築
を従来工法で行った場合に比較して、約1カ月の工期短
縮(3カ月が約2カ月)を行うことができた。
After all of the above preparations are completed, the tip propulsion device is allowed to reach the intermediate shaft, and without stopping, is passed through the protective pipe 20 as shown in FIG. Propulsion to the shaft will be continued. Even with this method, troubles such as collapse of the ground, collapsing accidents, and damage to surrounding houses related to the intermediate shaft 3 were carried out without any problems, and preparation for installation of the protective pipe was completed before the tip propulsion device arrived. The construction period was shortened compared to the wellhead method. With these two methods, the wellhead method and the penetrating method, the construction period is shortened by about one month (three months is about two months), compared to the case where the 350 m pipe is propelled and two intermediate shafts are constructed by the conventional method. Was able to do.

【0029】本発明は以下のことにも適用又は応用でき
る。 中間立坑に限らず、発進、到達立坑でも適用できる。 鏡切り部位はライナープレートばかりでは無く、鋼矢
板等でも良いため、中間立坑等の山留めを鋼矢板方式で
行うことができる。 推進工事に限らずシールド工事でも適用できる。 到達側は坑口方式のエントランスパッキン付きの坑口
を取り付け、発進側は貫通方式の防護管の片端部で代用
する混合方式もできる。 防護管は必ずしも円筒型でなくても良い。
The present invention can be applied or applied to the following. The invention can be applied not only to an intermediate shaft but also to a starting shaft and a reaching shaft. Since the mirror cut portion may be not only the liner plate but also a steel sheet pile or the like, a mountain retaining of an intermediate shaft or the like can be performed by a steel sheet pile method. It can be applied not only to propulsion work but also to shield work. On the arrival side, a wellhead with entrance packing of the wellhead type is installed, and on the starting side, a mixed type in which one end of a protective tube of the penetration type can be substituted. The protective tube need not necessarily be cylindrical.

【0030】[0030]

【本発明が奏する効果】本発明によれば、中間立坑を先
行して設ける管推進工法であるから、その利点を享受す
ることは勿論のこと、中間立坑先行型の数々の問題点を
統べて解決して、施工の容易さと、効率の良さ、陥没事
故等を決して起こさない安全性が達成されると共に、工
期の大幅な短縮を達成する等々の優れた効果を奏するの
である。
[Effects of the present invention] According to the present invention, a pipe propulsion method in which an intermediate shaft is provided in advance is provided. By solving the problem, it is possible to achieve excellent effects such as ease of construction, high efficiency, safety that never causes a collapse accident, etc., and a great shortening of the construction period.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の坑口方式の管推進工法の第1の工程を
示した断面図である。
FIG. 1 is a cross-sectional view showing a first step of a wellhead type pipe propulsion method of the present invention.

【図2】管推進工法の次の工程を示した断面図である。FIG. 2 is a sectional view showing the next step of the pipe propulsion method.

【図3】管推進工法の工程を示した断面図である。FIG. 3 is a cross-sectional view showing steps of a pipe propulsion method.

【図4】管推進工法の工程を示した断面図である。FIG. 4 is a cross-sectional view showing steps of a pipe propulsion method.

【図5】管推進工法の工程を示した断面図である。FIG. 5 is a cross-sectional view showing steps of a pipe propulsion method.

【図6】管推進工法の工程を示した断面図である。FIG. 6 is a cross-sectional view showing steps of a pipe propulsion method.

【図7】防護管の設置状態を示した平面図である。FIG. 7 is a plan view showing an installation state of a protection tube.

【図8】到達坑口のエントランスパッキンの部分を示し
た断面図である。
FIG. 8 is a cross-sectional view showing a part of an entrance packing at a reaching wellhead.

【図9】到達坑口のエントランスパッキンの部分を示し
た正面図である。
FIG. 9 is a front view showing a part of an entrance packing at a reaching wellhead.

【図10】発進坑口のエントランスパッキンの部分を示
した断面図である。
FIG. 10 is a sectional view showing a portion of an entrance packing at a starting wellhead.

【図11】到達坑口のエントランスパッキンの部分を示
した正面図である。
FIG. 11 is a front view showing a part of an entrance packing at a reaching wellhead.

【図12】防護管の組み立て態様を示した正面図であ
る。
FIG. 12 is a front view showing an assembling mode of the protection tube.

【図13】本発明の貫通方式の管推進工法の第1の工程
を示した断面図である。
FIG. 13 is a cross-sectional view showing a first step of the penetration type pipe propulsion method of the present invention.

【図14】管推進工法の次の工程を示した断面図であ
る。
FIG. 14 is a sectional view showing the next step of the pipe propulsion method.

【図15】管推進工法の工程を示した断面図である。FIG. 15 is a sectional view showing a step of the pipe propulsion method.

【図16】管推進工法の工程を示した断面図である。FIG. 16 is a sectional view showing a step of the pipe propulsion method.

【図17】管推進工法の工程を示した断面図である。FIG. 17 is a sectional view showing a step of the pipe propulsion method.

【図18】防護管の設置状態を示した平面図である。FIG. 18 is a plan view showing an installation state of a protection tube.

【図19】図17の19ー19線矢視図である。19 is a view taken in the direction of arrows 19-19 in FIG. 17;

【符号の説明】[Explanation of symbols]

1 管体 2 先端推進装置 3 中間立坑 4 ライナー 5 底盤コンクリート 6 到達立坑 7 発進立坑 14 架台 15 防護管の下半部 16 防護管の上半部 REFERENCE SIGNS LIST 1 pipe 2 tip propulsion device 3 middle shaft 4 liner 5 bottom concrete 6 reaching shaft 7 start shaft 14 gantry 15 lower half of protection pipe 16 upper half of protection pipe

───────────────────────────────────────────────────── フロントページの続き (72)発明者 林 幹雄 愛知県名古屋市中区三の丸三丁目1番1号 名古屋市下水道局内 (72)発明者 橋場 博史 愛知県名古屋市中区錦一丁目18番22号 株 式会社竹中土木名古屋支店内 (72)発明者 杉本 俊三 愛知県名古屋市中区錦一丁目18番22号 株 式会社竹中土木名古屋支店内 (72)発明者 山本 次雄 愛知県名古屋市中区錦一丁目18番22号 株 式会社竹中土木名古屋支店内 (72)発明者 石塚 幸雄 愛知県名古屋市中区錦一丁目18番22号 株 式会社竹中土木名古屋支店内 (72)発明者 児島 紘志 愛知県名古屋市中区錦一丁目18番22号 株 式会社竹中土木名古屋支店内 (72)発明者 藤森 実 愛知県名古屋市中区錦一丁目18番22号 株 式会社竹中土木名古屋支店内 (72)発明者 野澤 克哉 新潟県新潟市一番堀通町3番地10 株式会 社福田組内 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Mikio Hayashi 3-1-1, Sannomaru, Naka-ku, Nagoya City, Aichi Prefecture Inside the Nagoya City Sewerage Bureau (72) Inventor Hiroshi Hashiba 1-18-22 Nishiki, Naka-ku, Nagoya City, Aichi Prefecture No. Takenaka Civil Engineering Nagoya Branch Co., Ltd. (72) Inventor Shunzo Sugimoto 1-18-22 Nishiki, Naka-ku, Nagoya City, Aichi Prefecture Co., Ltd. Within Takenaka Civil Engineering Nagoya Branch (72) Inventor Tsuguo Yamamoto Naka, Aichi Prefecture 1-18-18 Nishiki, Ward Nagoya Branch of Takenaka Civil Engineering Co., Ltd. (72) Inventor Yukio Ishizuka 1-18-22 Nishiki, Naka Ward, Nagoya City, Aichi Prefecture Nagoya Branch of Takenaka Civil Engineering Co., Ltd. (72) Inventor Kojima Hiroshi 1-18-18 Nishiki, Naka-ku, Nagoya City, Aichi Prefecture Inside the Takenaka Civil Engineering Nagoya Branch (72) Inventor Minoru Fujimori 1-18-22 Nishiki, Naka-ku, Nagoya City, Aichi Prefecture Stock Company Takenakadoboku Nagoya within the Branch (72) inventor Katsuya Nozawa Niigata, Niigata Prefecture Ichibanboridori-cho, the third address 10 stock companies within the Fukudagumi

Claims (7)

【特許請求の範囲】[Claims] 【請求項1】 発進立坑に設置した元押し装置と先端推
進装置との協同作用により管体を到達立坑に向かって推
進させる管推進工法において、 発進立坑と到達立坑との中間位置に、管体を通過させる
中間立坑を、先端推進装置の到達以前に構築すること、 先端推進装置が中間立坑のライナーへ到達した段階で、
同先端推進装置の位置を確認して立坑内基線の測量を行
い、前記の測量結果に基づいて到達坑口と発進坑口を中
間立坑内に設置すること、 中間立坑の底部に架台を設置し、その上に前記到達坑口
と発進坑口を連絡する防護管の下半部を取り付けるこ
と、 前記到達坑口の内周に沿ってライナーに先端推進装置を
通過させる開口を設ける鏡切りを行い、先端推進装置を
中間立坑内へ進ませること、 発進立坑の内周に沿ってライナーに先端推進装置を通過
させる開口を設ける鏡切りを行い、先端推進装置を中間
立坑の外まで進ませること、 前記防護管の下半部の上に上半部を取付け、密閉された
防護管の中に充填材を注入し、その後管体の推進を続行
すること、 をぞれぞれ特徴とする、中間立坑先行型の管推進工法。
1. A pipe propulsion method for propelling a pipe toward an arrival shaft by a cooperative action of a main pushing device and a tip propulsion device installed in a start shaft, wherein a pipe body is provided at an intermediate position between the start shaft and the arrival shaft. To build an intermediate shaft before passing the tip propulsion device, and at the stage when the tip propulsion device reaches the liner of the intermediate shaft,
Check the position of the tip propulsion device and measure the baseline of the shaft, based on the results of the survey, install the arrival well and the start well in the middle shaft, install a gantry at the bottom of the middle shaft, Attaching the lower half of the protective tube that communicates the arrival wellhead and the starting wellhead, performs mirror cutting to provide an opening for passing the tip propulsion device to the liner along the inner circumference of the arrival wellhead, Advancing into the middle shaft, making a mirror cut in the liner along the inner periphery of the starting shaft to provide an opening for passing the tip propulsion device, and moving the tip propulsion device out of the middle shaft, under the protective tube A middle shaft leading type pipe, which is characterized by mounting the upper half on the half, injecting the filling material into the sealed protective tube, and then continuing the propulsion of the tube body Propulsion method.
【請求項2】 到達坑口と発進坑口には、補強コンクリ
ートを打設し、また、先端推進装置を到達坑口に通過さ
せる以前、及び発進坑口へ前進させる以前に各坑口にエ
ントランスパッキンを取付けておき、そこを先端推進装
置を通過させてから防護管で密閉し、速硬性または通常
硬化の充填材で空隙を充填することを特徴とする、請求
項1に記載した中間立坑先行型の管推進工法。
2. Reinforced concrete is poured into the arrival wellhead and the start wellhead, and entrance packing is attached to each wellhead before the tip propulsion device passes through the arrival wellhead and before it advances to the start wellhead. 2. The method according to claim 1, wherein the passage is passed through a tip propulsion device, sealed with a protective tube, and filled with a fast-curing or normally hardening filler. .
【請求項3】 到達坑口と発進坑口には、先端推進装置
を到達坑口に通過させる以前、及び発進坑口へ前進させ
る以前に各坑口にエントランスパッキンを取付けてお
き、そこを先端推進装置を通過させてから防護管で密閉
し、速硬性または通常硬化の充填材で空隙を充填するこ
とを特徴とする、請求項1に記載した中間立坑先行型の
管推進工法。
3. An entrance packing is attached to each of the entrance wellhead and the starting wellhead before the tip propulsion device passes through the arrival wellhead and before the forward propulsion device is advanced to the starting wellhead. 2. The method according to claim 1, wherein the space is sealed with a protective tube and the gap is filled with a fast-curing or normally hardening filler.
【請求項4】 発進立坑に設置した元押し装置と先端推
進装置との協同作用により管体を到達立坑に向かって推
進させる管推進工法において、 発進立坑と到達立坑との中間位置に、管体を通過させる
中間立坑を、先端推進装置の到達以前に構築すると共に
以下の準備を行うこと、 先端推進装置の通過予定位置に基づいて中間立坑内基線
の測量を行い、前記の測量結果に基づいて中間立坑の底
部に架台を設置し、その上に防護管の下半部と管両端部
を取り付けること、 到達側と発進側の管端部の内周に沿ってライナーに先端
推進装置を通過させる開口を設ける鏡切りを行い、防護
管の上半部を取付け、かくして密閉された防護管の内部
へ充填材を注入すること、 以上の準備を完了した後に先端推進装置を中間立坑にま
で到達させ、更に防護管の中を通過させて管体の推進を
継続すること、をぞれぞれ特徴とする、中間立坑先行型
の管推進工法。
4. A pipe propulsion method in which a pipe body is propelled toward an arrival shaft by the cooperation of a main pushing device and a tip propulsion device installed in a starting shaft, wherein a pipe body is provided at an intermediate position between the starting shaft and the arrival shaft. Constructing an intermediate shaft before the arrival of the tip propulsion device, and making the following preparations, perform surveying of the middle shaft base line based on the scheduled passage position of the tip propulsion device, and based on the above survey results Install a gantry at the bottom of the middle shaft, attach the lower half of the protection tube and both ends of the tube on it, and let the liner pass the tip propulsion device along the inner circumference of the arrival and start ends of the tube Make a mirror cut with an opening, attach the upper half of the protective tube, and inject the filler into the sealed protective tube, and after completing the above preparations, make the tip propulsion device reach the middle shaft. , And a protective tube It is passed through a medium by continuing the promotion of the tubular body, and, respectively, characterized, respectively, and tubing jacking method of intermediate shafts preceding type.
【請求項5】 ライナーの鏡切りの直後に管端部の坑内
側端面を密閉し、速硬性の充填材を管端部の中に充填
し、同充填材が硬化した後に前記密閉を解くことを特徴
とする、請求項4に記載した中間立坑先行型の管推進工
法。
5. Immediately after mirror-cutting of the liner, sealing the inner end surface of the tube end, filling the tube end with a quick-hardening filler material, and releasing the seal after the filler material has hardened. The middle shaft precedent type pipe propulsion method according to claim 4, characterized in that:
【請求項6】 防護管の内部への充填材の注入は、先ず
防護管の下半部に速硬性の充填材を充填し、続いて防護
管の残る空隙部に通常硬化の充填材を密に充填すること
を特徴とする、請求項4に記載した中間立坑先行型の管
推進工法。
6. Injecting the filler into the inside of the protective tube is performed by first filling the lower half of the protective tube with a quick-hardening filler, and then filling the remaining space of the protective tube with the normally hardened filler. The method according to claim 4, wherein the pipe is propelled in an intermediate shaft.
【請求項7】 防護管の内部への充填材の注入は、防護
管の下半部に通常硬化の充填材を充填し、続いて防護管
の残る空隙部にも通常硬化の充填材を密に充填すること
を特徴とする、請求項4に記載した中間立坑先行型の管
推進工法。
7. Injection of the filler into the inside of the protective tube is performed by filling the lower half of the protective tube with the normally hardened filler, and then filling the remaining space of the protective tube with the normally hardened filler. The method according to claim 4, wherein the pipe is propelled in an intermediate shaft.
JP05217698A 1998-03-04 1998-03-04 Pipe propulsion method with intermediate shaft leading type Expired - Lifetime JP3965241B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP05217698A JP3965241B2 (en) 1998-03-04 1998-03-04 Pipe propulsion method with intermediate shaft leading type

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP05217698A JP3965241B2 (en) 1998-03-04 1998-03-04 Pipe propulsion method with intermediate shaft leading type

Publications (2)

Publication Number Publication Date
JPH11247592A true JPH11247592A (en) 1999-09-14
JP3965241B2 JP3965241B2 (en) 2007-08-29

Family

ID=12907513

Family Applications (1)

Application Number Title Priority Date Filing Date
JP05217698A Expired - Lifetime JP3965241B2 (en) 1998-03-04 1998-03-04 Pipe propulsion method with intermediate shaft leading type

Country Status (1)

Country Link
JP (1) JP3965241B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009138483A (en) * 2007-12-10 2009-06-25 Kajima Corp Extracting and removing method of existing pipe
JP2012180651A (en) * 2011-02-28 2012-09-20 Sumitomo Forestry Co Ltd Sensitivity control structure of seismic isolator
JP2019007131A (en) * 2017-06-20 2019-01-17 株式会社大林組 Water cutoff apparatus
CN109797778A (en) * 2019-03-27 2019-05-24 中铁四局集团有限公司 One kind being suitable for the anhydrous layer of sand area upper pipe working well in desert and construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009138483A (en) * 2007-12-10 2009-06-25 Kajima Corp Extracting and removing method of existing pipe
JP2012180651A (en) * 2011-02-28 2012-09-20 Sumitomo Forestry Co Ltd Sensitivity control structure of seismic isolator
JP2019007131A (en) * 2017-06-20 2019-01-17 株式会社大林組 Water cutoff apparatus
CN109797778A (en) * 2019-03-27 2019-05-24 中铁四局集团有限公司 One kind being suitable for the anhydrous layer of sand area upper pipe working well in desert and construction method

Also Published As

Publication number Publication date
JP3965241B2 (en) 2007-08-29

Similar Documents

Publication Publication Date Title
CN106761785B (en) A kind of subway tunnel shield originates construction technology
CN112012753B (en) Shield tunneling machine starting method based on special-shaped extension steel ring
CN111396067B (en) Comprehensive shield steel sleeve receiving construction method in complex environment
CN110735653A (en) deep-hole retreating type grouting water plugging construction method for igneous rock water-rich fault
CN109667985B (en) Method for butting pipe pushing jack and receiving well steel sleeve in pipe pushing construction
JP5393947B2 (en) Multiple tunnel construction method and connection structure, and tunnel and pipe roof connection structure constituting the multiple tunnel
JP3908464B2 (en) Construction method of underwater tunnel
JP2003206691A (en) Shield machine arrival construction method
JPH11247592A (en) Pipe jacking method for preceding intermediate shaft system
US11603760B2 (en) Shield method
CN111075457A (en) In-hole repairing method for shield deformation of tail shield of shield tunneling machine under complex geological condition
CN113047853B (en) Shield originating construction method for water-rich soft soil geological region
JP2007162323A (en) Wall body forming method and wall body
JP3177468B2 (en) Standing block, standing excavation method and sewer propulsion method
JP2594864B2 (en) Widening method of underground tunnel
JP2799899B2 (en) Structure and construction method of branch of underground tunnel
JP2006152680A (en) Joining construction method for shield tunnel and structure of shield tunnel by its construction method
JP3803753B2 (en) Tunnel construction method
JP3616898B2 (en) Method for joining underground structures using propulsion device
JP3177908B2 (en) Starting method of shield excavator
JPH1162466A (en) Receiving method of shield boring machine into arrival shaft, and structure of receiving part of shield boring machine in arrival shaft
JP3153887B2 (en) Joining method of shield tunnel
JP2681511B2 (en) Vertical shaft structure of shield machine starting part, its construction method, and start / arrival method of shield machine using the structure
JPH11172708A (en) Method for forming pile penetrating existing underground structure
KR20230047673A (en) the improvement structure and this formation method of the oscillation work outlet facilitating the input of the propulsion pipe

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050207

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070402

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070501

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070528

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100601

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110601

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120601

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120601

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130601

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term