JPH1121878A - Constructing method for water passage using sheating wall with steel pipe columns and steel pipe member for use in it - Google Patents
Constructing method for water passage using sheating wall with steel pipe columns and steel pipe member for use in itInfo
- Publication number
- JPH1121878A JPH1121878A JP18901097A JP18901097A JPH1121878A JP H1121878 A JPH1121878 A JP H1121878A JP 18901097 A JP18901097 A JP 18901097A JP 18901097 A JP18901097 A JP 18901097A JP H1121878 A JPH1121878 A JP H1121878A
- Authority
- JP
- Japan
- Prior art keywords
- steel pipe
- water
- construction
- pipe
- ground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、地下構造物等の建設に
あたって造成される鋼管柱列土留壁を利用した、地下水
の水流復元を図ることのできる構造物の施工法及びそれ
に使用する鋼管部材に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a structure capable of restoring the flow of groundwater using a steel pipe column retaining wall formed in the construction of an underground structure or the like, and a steel pipe member used therefor. It is about.
【0002】[0002]
【従来の技術】地下構造物等の建設においては、その工
事区域を囲んで、鉄筋コンクリートや鋼管柱列による土
留壁を造成して地下部分の地盤掘削が行われるが、それ
らの土留壁は工事終了後は埋め殺しされる。土留壁は一
般に遮水性が重視された構造となっているので、これが
造成されることによって、地下水流が遮断され、地下水
位に大きな変動をもたらし、周辺環境に悪影響を与える
ことが多かった。特に近年は工事が大規模化するにつ
れ、これが社会的な問題となってきている。2. Description of the Related Art In the construction of an underground structure or the like, an excavation of an underground portion is performed by constructing a retaining wall made of reinforced concrete or a column of steel pipes around the construction area. The rest is buried. Retaining walls generally have a structure that places emphasis on water shielding, and the creation of such walls often interrupts the groundwater flow, causing large fluctuations in the groundwater level and often adversely affecting the surrounding environment. In particular, in recent years, as construction has become larger, this has become a social problem.
【0003】この問題を解決するため、鉄筋コンクリー
トを使用した地中連続土留壁では、地下水を通水するた
めの対策として、挿入される鉄筋の形状を特殊なものと
したり、現場打ちのコンクリートの性状を変化させる方
法等が提案されている。また、推進工法を用いて土留壁
に通水孔を形成して地下水流の復元を図った実例もあ
る。[0003] In order to solve this problem, in the underground continuous retaining wall using reinforced concrete, as a countermeasure for permeating groundwater, the shape of the inserted reinforcing bar or the property of cast-in-place concrete is taken as a measure. And the like have been proposed. In addition, there is an actual example in which water holes are formed in the retaining wall using a propulsion method to restore the groundwater flow.
【0004】[0004]
【発明が解決しようとする課題】しかし、鉄筋コンクリ
ートによる土留壁における上記各種の通水化の方法で
は、施工が面倒で多額の経費を要し、また、推進工法を
利用する方法の場合は、推進工法のための機材を設置す
るための施工場所(立坑)が必要となり、施工範囲が広
くなるとともに、工期、工費が増大するという問題があ
る。また、鋼管柱列土留壁の場合は、既製鋼管を利用す
るため、その構造を変えることが困難なことから、地下
水流の復元を図るための構造物としては不向きなものと
されていた。However, in the above-mentioned various methods of making the retaining wall made of reinforced concrete impervious, the construction is troublesome and requires a large amount of cost. There is a problem that a construction site (a shaft) for installing equipment for the construction method is required, so that the construction range is widened, and the construction period and construction cost are increased. In addition, in the case of the steel pipe column retaining wall, it is difficult to change the structure of the prefabricated steel pipe because it is made of a pre-made steel pipe, so that it is not suitable as a structure for restoring the groundwater flow.
【0005】本発明は、上記従来の問題を解決するため
になされたもので、施工性がよく耐力及び遮水性に優れ
る等の利点の多い鋼管柱列土留壁を利用し、その土留壁
の施工範囲内において、土留壁に地上からの操作によっ
て通水機能をもたせ、地下水の水流復元を図ることので
きる、経済性及び施工性に優れた構造物の施工法及びそ
れに使用する鋼管部材を提供しようとするものである。SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned conventional problems, and utilizes a steel pipe column-lined retaining wall having many advantages such as good workability, excellent strength and excellent water shielding. Within the range, the earth retaining wall is provided with a water flow function by operation from the ground, and it is possible to provide a construction method of a structure excellent in economy and workability, which can restore the groundwater flow, and a steel pipe member used therefor. It is assumed that.
【0006】[0006]
【課題を解決するための手段】上記の目的を達成するた
めの本発明の構成について、実施例に対応する図面を参
照して説明すると、請求項1の工法は、建設地盤Bを挟
んで造成される鋼管柱列土留壁Aの施工において、該土
留壁Aに使用される鋼管2に、建設地盤Bから背面地盤
Cに至る、地上よりの操作で閉塞、開通可能とした通水
パイプ6を設け、土留壁Aを造成し、通水パイプ6を閉
塞した状態にして建設地盤Bの掘削、排土から地下構造
物の建設までの施工を行い、その後、通水パイプ6を開
通させることを特徴とするものである。The construction of the present invention for achieving the above object will be described with reference to the drawings corresponding to the embodiments. In the construction of the steel pipe column soil retaining wall A to be constructed, the steel pipe 2 used for the soil retaining wall A is provided with a water pipe 6 from the construction ground B to the back ground C, which can be closed and opened by operation from the ground. The construction of the earth retaining wall A, the construction of the construction ground B, the excavation and the construction of the underground structure are performed with the water pipe 6 closed, and then the water pipe 6 is opened. It is a feature.
【0007】また、請求項2の工法は、建設地盤Bを挟
んで造成される鋼管柱列土留壁Aの施工において、該土
留壁Aに使用される鋼管2に、建設地盤Bから背面地盤
Cに至る、地上よりの操作で閉塞、開通可能とした通水
パイプ6を設け、土留壁Aを造成し、通水パイプ6を閉
塞した状態にして建設地盤を掘削、排土し、対向する土
留壁A,Aの通水パイプ6,6間を通水管12または通水
層11を設けて接続した後、通水パイプ6を開通させるこ
とを特徴とするものである。In the construction method of the second aspect, in the construction of the steel pipe column soil retaining wall A formed with the construction ground B interposed therebetween, the steel pipe 2 used for the soil retaining wall A is attached to the steel ground 2 from the construction ground B to the rear ground C. , A drainage pipe 6 that can be closed and opened by operation from the ground is provided, a retaining wall A is created, and the construction ground is excavated and discharged with the drainage pipe 6 closed, and the opposite retaining After the water pipes 12 or the water layer 11 are provided and connected between the water pipes 6 and 6 of the walls A, A, the water pipe 6 is opened.
【0008】また、請求項3の鋼管部材は、鋼管2の、
地下水の透過が予想される深さ位置に、両端部にろ過材
7を取り付けた通水パイプ6を、鋼管2を横断して設
け、該通水パイプ6内に、鋼管2外よりの流体の注入、
排出により膨張、収縮し、通水パイプ6を閉塞、開通さ
せるパッカー10を設けたことを特徴とするものである。The steel pipe member according to claim 3 is a steel pipe member,
At a depth position where permeation of groundwater is expected, a water passage pipe 6 having filter media 7 attached to both ends is provided across the steel pipe 2, and inside the water pipe 6, a fluid from outside the steel pipe 2 is provided. Injection,
A packer 10 that expands and contracts upon discharge to close and open the water pipe 6 is provided.
【0009】[0009]
【発明の実施の形態】以下、本発明の実施の形態につい
て図面を参照して説明する。図1〜図4および図10〜図
12は本発明による通水化工法の施工過程とその構造物の
実施例を示したものであり、図5〜図9はそれに使用す
る鋼管部材の実施例を示したものである。Embodiments of the present invention will be described below with reference to the drawings. 1 to 4 and 10 to 10
FIG. 12 shows an embodiment of the construction process and the structure of the water passage method according to the present invention, and FIGS. 5 to 9 show embodiments of a steel pipe member used therein.
【0010】地下構造物D等の建設にあたっては、その
建設地盤Bを挟んだ両側の地盤に鋼管柱列土留壁(以下
土留壁という)Aを造成する。この土留め壁Aの造成
は、従来公知のように、対向する外側面に継手材3,3
を設けた鋼管部材1を互いに継手材3,3どうしの嵌合
により連結しながら、ソイルセメント5を充填した掘削
孔4に沈設して行われる。この方法は、通称ONS工法
として知られている。[0010] When constructing the underground structure D and the like, a steel pipe column retaining wall (hereinafter referred to as retaining wall) A is formed on the ground on both sides of the construction ground B. As is conventionally known, the earth retaining wall A is formed by connecting the joint members 3 and 3 to opposing outer surfaces.
While the steel pipe members 1 provided with the joints are connected to each other by fitting the joint members 3 with each other, the steel pipe members 1 are set in the excavation holes 4 filled with the soil cement 5. This method is known as the ONS method.
【0011】本発明においては、鋼管部材1として、図
5〜図7に示すものが使用される。すなわち、従来の継
手材3,3を設けた鋼管2の下部の地下水の透過が予想
される深さ位置に、建設地盤B側から背面地盤C側へと
鋼管2を横断して、両端が掘削孔4のほぼ外周に至る長
さに突出する所要径の通水パイプ6が設けられている。
そして、その通水パイプ6の開放された両端には、土砂
等の粒子は遮断されるが、水は透過可能な綱状体などの
ろ過材7が取り付けられている。In the present invention, the steel pipe member 1 shown in FIGS. 5 to 7 is used. That is, the steel pipe 2 is traversed from the construction ground B side to the back ground C side at a depth position under which the groundwater is expected to permeate below the steel pipe 2 provided with the conventional joint members 3 and both ends are excavated. A water pipe 6 having a required diameter is provided which protrudes to a length almost reaching the outer periphery of the hole 4.
At both open ends of the water pipe 6, a filter member 7 such as a rope or the like, which can block particles such as earth and sand but is permeable to water, is attached.
【0012】また、通水パイプ6には、鋼管2内を通っ
て上方に延びる小径管8が接続されており、その中に、
地上に設けられた、水や空気等流体の注排ポンプ(図示
を略す)に接続した流通チューブ9が挿入され、その先
端は通水パイプ6に内装されたパッカー10と連通されて
いる。そして、パッカー10は、流通チューブ9よりの流
体注入により、図6に示すように、通水パイプ6内全体
に膨張、拡大してろ過材7の全面を塞ぐことができ、ま
た、その注入された流体を排出することにより、図8、
図9に示すように、流通チューブ9と連通した通水パイ
プ6内上部に小形に収縮され、ろ過材7の閉塞を解除
し、両端のろ過材7,7を介して通水パイプ6内は通水
可能な状態となるようにされている。A small-diameter pipe 8 extending upward through the steel pipe 2 is connected to the water pipe 6.
A flow tube 9 connected to a pump (not shown) for supplying a fluid such as water or air, which is provided on the ground, is inserted, and the distal end thereof communicates with a packer 10 provided inside a water passage pipe 6. Then, as shown in FIG. 6, the packer 10 can expand and expand the entire inside of the water passage pipe 6 to close the entire surface of the filter medium 7 by injecting the fluid from the flow tube 9, and furthermore, inject the injected fluid. By discharging the fluid, FIG.
As shown in FIG. 9, the upper part of the water pipe 6 communicating with the distribution tube 9 is contracted into a small size, the blockage of the filter medium 7 is released, and the inside of the water pipe 6 is filtered through the filter materials 7 at both ends. Water is allowed to pass through.
【0013】土留壁A,Aの造成後は、上記のように、
流通チューブ9に流体を注入してパッカー10を膨張、拡
大して通水パイプ6の水の流通を遮断した状態で、図3
に示すように、建設地盤Bの掘削、排土を行い、地下構
造物Dを建設する。After the formation of the retaining walls A, A, as described above,
In a state where the fluid is injected into the flow tube 9 to expand and expand the packer 10 and the flow of water through the water flow pipe 6 is cut off, FIG.
As shown in (1), excavation and discharge of the construction ground B are performed, and an underground structure D is constructed.
【0014】地下構造物Dの建設を終えた後は、図8、
図9に示すように、流通チューブ9より流体を排出して
パッカー10を収縮させれば、通水パイプ6内は水の流通
が自在に行われることになる。それにより、背面地盤C
と建設地盤Bとは、土留壁A,Aの鋼管部材1の通水パ
イプ6を介して通水可能となって、通水機能を発揮する
ことになる。その結果、地下水の上流側にある一方の背
面地盤Cの地下水は、一方の土留壁の通水パイプ6を通
じて建設地盤Bに浸透し、他方の土留壁Aの通水パイプ
6を通って他方の背面地盤Cへと浸透して行くことにな
る。それにより、土留壁A,Aの造成により遮断された
地下水の流通、復水が恒久的に行えるようになる。After the construction of the underground structure D is completed, FIG.
As shown in FIG. 9, when the fluid is discharged from the flow tube 9 and the packer 10 is contracted, the flow of water in the water pipe 6 can be freely performed. Thereby, the back ground C
And the construction ground B can pass water through the water pipe 6 of the steel pipe member 1 of the retaining walls A, A, thereby exhibiting a water passing function. As a result, the groundwater on the back ground C on the upstream side of the groundwater penetrates into the construction ground B through the water pipe 6 on one of the retaining walls, passes through the water pipe 6 on the other retaining wall A, and the other. It will penetrate into the back ground C. As a result, the distribution and condensing of groundwater blocked by the formation of the retaining walls A, A can be performed permanently.
【0015】図10及び図11は、両土留壁A,A間におけ
る水を流通させる手段の請求項2の実施例を示したもの
である。図10の実施例では、土留壁Aの対向する通水パ
イプ6,6間に、砕石などを所要の厚さに敷き詰めた通
水層11を形成し、その上に地下構造物Dの建設を行うも
のである。また、図11の実施例では、地下構造物Dの建
設に先立って、対向する通水パイプ6,6を連通管12に
より接続するのである。これらの実施例の場合は、両土
留壁A,A間の水の流通は通水層11または連通管12を通
して行われるため、通水がより円滑に行われるととも
に、建設地盤Bへの水の流通による悪い影響の生ずるの
を防ぐこともできる。FIGS. 10 and 11 show a second embodiment of the means for circulating water between the retaining walls A, A. FIG. In the embodiment shown in FIG. 10, a water-permeable layer 11 in which crushed stones and the like are spread to a required thickness is formed between opposed water-permeable pipes 6 and 6 of the retaining wall A, and an underground structure D is constructed thereon. Is what you do. In the embodiment shown in FIG. 11, the water pipes 6 and 6 facing each other are connected by the communication pipe 12 before the construction of the underground structure D. In the case of these embodiments, the flow of water between the soil retaining walls A, A is performed through the water-permeable layer 11 or the communication pipe 12, so that the flow of water is performed more smoothly and the water to the construction ground B is formed. It can also prevent the adverse effects of distribution.
【0016】また、本発明においては、図12に示すよう
に、背面地盤Cの方に、土留壁Aと接して、砕石等を充
填した透水層Eを設けることができる。この透水層E
は、土留壁Aの長さ方向の全面に設けることに限らず、
土留壁Aの長さ方向に間隔をおいて適宜断片的に設ける
こともできる。このような透水層Eの形成により、背面
地盤Cと通水パイプ6の通水がより効果的に行われるこ
とになる。また、透水層Eの形成により、例えば地下水
流の深さ位置が地下構造物Bの下端レベルより高い位置
にある場合でも地下構造物下での通水が可能となる等、
地下水流の位置にかかわらず通水の復元が効率的に行え
ることになる。なお、この透水層Eを設けることは、図
10、図11の実施例の場合にも適用可能である。In the present invention, as shown in FIG. 12, a permeable layer E filled with crushed stone or the like can be provided on the back ground C in contact with the retaining wall A. This permeable layer E
Is not limited to being provided on the entire surface in the longitudinal direction of the retaining wall A,
It may be provided in a fragmentary manner at intervals in the longitudinal direction of the retaining wall A. With the formation of the water permeable layer E, the water flow between the back ground C and the water pipe 6 is more effectively performed. Further, the formation of the permeable layer E allows water to flow under the underground structure even when the depth position of the underground water flow is higher than the lower end level of the underground structure B, for example.
Regardless of the position of the groundwater flow, restoration of water flow can be performed efficiently. It should be noted that the provision of the permeable layer E is shown in FIG.
It is also applicable to the embodiments of FIGS.
【0017】[0017]
【発明の効果】以上説明したように、本発明によれば、
従来、遮水性の高い土留壁として埋め殺しにされる鋼管
柱列土留壁を、その鋼管を利用して、地上よりの操作
で、背面地盤側と建設地盤側との通水とその遮断が行え
るようにすることで、建設時は遮水壁として機能させる
とともに、建設終了後は復水可能の土留壁としての機能
を発揮させることができるので、鋼管柱列による遮水性
がよく、耐力と施工性に優れた土留壁を通水化構造物と
して経済的に造成できる。As described above, according to the present invention,
Conventionally, a steel pipe column soil retaining wall that is buried as a highly water-impervious retaining wall can be used to cut off water between the back ground side and the construction ground side by operating from the ground using the steel pipe. By doing so, it can function as a water impervious wall at the time of construction, and it can also function as a retaining wall that can be condensed after construction is completed. It can be constructed economically as a water-permeable structure with excellent retaining walls.
【0018】また、これに使用される鋼管部材は、鋼管
柱列土留壁に用いられている鋼管に、通水パイプとその
中に管外に至る流通パイプと接続したパッカーを内装し
ただけの簡単な機構を加えただけのものであるから、取
扱いが容易で操作が確実に行えるとともに、安価に製作
できる。[0018] The steel pipe member used for this is simply a steel pipe used for a steel pipe column retaining wall, in which a water pipe and a packer connected to a distribution pipe extending outside the pipe are installed. Since it is only a simple mechanism added, it is easy to handle, can be operated reliably, and can be manufactured at low cost.
【図1】本発明工法の実施態様において、土留壁を造成
した状態を示す縦断面図である。FIG. 1 is a longitudinal sectional view showing a state in which a retaining wall is formed in an embodiment of the method of the present invention.
【図2】同平面図である。FIG. 2 is a plan view of the same.
【図3】同建設地盤を掘削、排土した状態の縦断面図で
ある。FIG. 3 is a longitudinal sectional view showing a state where the construction ground is excavated and discharged.
【図4】同地下構造物建設後の縦断面図である。FIG. 4 is a longitudinal sectional view after the construction of the underground structure.
【図5】鋼管部材の半截側面図である。FIG. 5 is a half sectional side view of a steel pipe member.
【図6】同要部の半截拡大側面図である。FIG. 6 is a partially enlarged side view of the main part.
【図7】同要部の正面図である。FIG. 7 is a front view of the main part.
【図8】パッカーを収縮した状態を示す同要部半截側面
図である。FIG. 8 is a half cutaway side view of the relevant part, showing a state where the packer is contracted.
【図9】同正断面図である。FIG. 9 is a front sectional view of the same.
【図10】本発明工法の他の実施例の態様を示す縦断面図
である。FIG. 10 is a longitudinal sectional view showing an embodiment of another embodiment of the method of the present invention.
【図11】同さらに他の態様を示す縦断面図である。FIG. 11 is a longitudinal sectional view showing still another embodiment.
【図12】同さらに他の態様を示す縦断面図である。FIG. 12 is a longitudinal sectional view showing still another embodiment.
A 土留壁 B 建設地盤 C 背面地盤 D 地下構造物 E 透水層 1 鋼管部材 2 鋼管 4 掘削孔 5 ソイルセメント 6 通水パイプ 7 ろ過材 10 パッカー 11 通水層 12 連通管 A Retaining wall B Construction ground C Back ground D Underground structure E Permeable layer 1 Steel pipe member 2 Steel pipe 4 Drilling hole 5 Soil cement 6 Water flow pipe 7 Filter media 10 Packer 11 Water flow layer 12 Communication pipe
Claims (3)
留壁の施工において、該土留壁に使用される鋼管に、建
設地盤から背面地盤に至る、地上よりの操作で閉塞、開
通可能とした通水パイプを設け、土留壁を造成し、通水
パイプを閉塞した状態にして建設地盤の掘削、排土から
地下構造物等の建設までの施工を行い、その後、通水パ
イプを開通させることを特徴とする、鋼管柱列土留壁を
用いた通水化工法。Claims: 1. In the construction of a steel pipe column retaining wall formed across a construction ground, steel pipes used for the retaining wall can be closed and opened by an operation from the ground from the construction ground to the back ground. Establish a drainage pipe, construct a retaining wall, perform construction from excavation of the construction ground, excavation to construction of underground structures, etc. with the drainage pipe closed, and then open the drainage pipe A water-passing method using steel pipe column soil retaining walls.
留壁の施工において、該土留壁に使用される鋼管に、建
設地盤から背面地盤に至る、地上よりの操作で閉塞、開
通可能とした通水パイプを設け、土留壁を造成し、通水
パイプを閉塞した状態にして建設地盤を掘削、排土し、
対向する土留壁の通水パイプ間を通水管または通水層を
設けて接続した後、通水パイプを開通させることを特徴
とする、鋼管柱列土留壁を用いた通水化工法。2. In the construction of a steel column pillar retaining wall formed across a construction ground, the steel pipe used for the retaining wall can be closed and opened by operation from the ground from the construction ground to the back ground. Established drainage pipes, constructed earth retaining walls, excavated and drained the construction ground with the drainage pipes closed,
A water-passing method using a steel-column-column soil retaining wall, characterized in that a water-passing pipe or a water-permeable layer is provided between and connected to water-passing pipes of opposed soil walls, and then the water-flow pipe is opened.
位置に、両端部にろ過材を取り付けた通水パイプを、鋼
管を横断して設け、該通水パイプ内に、鋼管外よりの流
体の注入、排出により膨張、収縮し、通水パイプを閉
塞、開通させるパッカーを設けたことを特徴とする、鋼
管柱列土留壁に使用する鋼管部材。3. A water pipe having a filter material attached to both ends thereof is provided across the steel pipe at a depth of the steel pipe where the penetration of groundwater is expected. A steel pipe member for use in a steel pipe column retaining wall, comprising a packer which expands and contracts by injecting and discharging a fluid to close and open a water pipe.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18901097A JPH1121878A (en) | 1997-06-30 | 1997-06-30 | Constructing method for water passage using sheating wall with steel pipe columns and steel pipe member for use in it |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18901097A JPH1121878A (en) | 1997-06-30 | 1997-06-30 | Constructing method for water passage using sheating wall with steel pipe columns and steel pipe member for use in it |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH1121878A true JPH1121878A (en) | 1999-01-26 |
Family
ID=16233796
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP18901097A Pending JPH1121878A (en) | 1997-06-30 | 1997-06-30 | Constructing method for water passage using sheating wall with steel pipe columns and steel pipe member for use in it |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH1121878A (en) |
-
1997
- 1997-06-30 JP JP18901097A patent/JPH1121878A/en active Pending
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2001115458A (en) | Deep well construction method using earth retaining wall | |
KR101874464B1 (en) | Bottom-up ground reinforcement anchor with Front drain pipe | |
JP3245537B2 (en) | Method of forming permeable section in continuous underground wall | |
JPH11229418A (en) | Underground water recharge method in earth-retaining wall composed of steel pipe column row | |
JPH1121878A (en) | Constructing method for water passage using sheating wall with steel pipe columns and steel pipe member for use in it | |
JP3192661B2 (en) | Novel sewage wall, method of forming the sewage wall, and members used therefor | |
JPH1121892A (en) | Construction method for water passage of sheathing wall with steel pipe columns and structure | |
JPH1121877A (en) | Restoring method for underground water vein using sheathing wall with steel pipe columns | |
JPH10245841A (en) | Underground water-permeability construction method and underground water-permeable device | |
JP2900842B2 (en) | Earth retaining wall structure with water permeability | |
JPH10317367A (en) | Water-returning structure using steel-pipe-column-line earth-retaining wall and method for constructing the same | |
JP2006029020A (en) | Construction method of large cross section tunnel | |
JP2000328561A (en) | Underground water flowing construction method in soil cement column row earth retaining wall | |
JP2005330769A (en) | Structure and construction method of water passing earth retaining wall | |
JP2000220137A (en) | Steel pipe column array earth retaining wall and its water passing method | |
JPH11166229A (en) | Groundwater vein restoring method making use of steel pipe column earth retaining wall | |
JP3841570B2 (en) | Opening method of groundwater flow hole in steel pipe column retaining wall | |
JP2000328558A (en) | Underground water flowing construction method in soil cement column row earth retaining wall | |
JPS62117911A (en) | Setting of pipe for well | |
JP2000045313A (en) | Ground water permeation method making use of soil cement column strip earth retaining wall | |
JP3552925B2 (en) | Opening method of groundwater holes in steel pipe column retaining wall | |
JPS6011165Y2 (en) | Continuous column pile drilling bit | |
JPH10317368A (en) | Method for controlling underground water level using steel-pipe-column-line earth-retaining wall, and structure thereof | |
KR200315917Y1 (en) | a sheet pile | |
JP2524579B2 (en) | Reinforcement method of existing retaining wall under water surface |