JPH10317368A - Method for controlling underground water level using steel-pipe-column-line earth-retaining wall, and structure thereof - Google Patents

Method for controlling underground water level using steel-pipe-column-line earth-retaining wall, and structure thereof

Info

Publication number
JPH10317368A
JPH10317368A JP14464897A JP14464897A JPH10317368A JP H10317368 A JPH10317368 A JP H10317368A JP 14464897 A JP14464897 A JP 14464897A JP 14464897 A JP14464897 A JP 14464897A JP H10317368 A JPH10317368 A JP H10317368A
Authority
JP
Japan
Prior art keywords
water
retaining wall
steel pipe
steel
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP14464897A
Other languages
Japanese (ja)
Inventor
Masayuki Tsuchiya
正幸 土谷
Hiroyuki Eguchi
宏幸 江口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kubota Corp
Original Assignee
Kubota Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kubota Corp filed Critical Kubota Corp
Priority to JP14464897A priority Critical patent/JPH10317368A/en
Publication of JPH10317368A publication Critical patent/JPH10317368A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a method for controlling the level of back underground water using a steel-pipe-column-line earth-retaining wall. SOLUTION: Steel pipes 1 each provided with a water hole 5 on its side making contact with back ground are connected together to construct a steel- pipe-column-line earth-retaining wall A, and a water-permeable layer B filled with crushed stones or the like is formed on the side of the wall A facing back soil D. The inside of each steel pipe 1 is dug to form a hollow pipe, in which a water distributing pipe 10 connected to a water injecting/draining pump 12 is installed. When the level of underground water in the back soil D is high, water flowing into the steel pipes 1 through the water-permeable layer B is discharged to prevent the rise of the underground water; when the level of the underground water is low, water is injected from the steel pipes 1 to supply the soil with underground water through the water-permeable layer B.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、掘削工事等において、
造成される鋼管柱列土留壁を利用して、背面地盤の地下
水位の維持や調節を行えるようにした、地下水位の制御
方法及びその構造物に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention
The present invention relates to a method for controlling a groundwater level and a structure thereof, wherein the groundwater level on the back ground can be maintained and adjusted by using a steel pipe column soil retaining wall to be formed.

【0002】[0002]

【従来の技術】地下構造物の建設等において掘削工事を
行うには、その工事区域に沿って、鉄筋コンクリートの
連続土留壁や鋼管柱列土留壁を造成することが行われて
いるが、それらの土留壁を造成することにより、工事区
域周辺の地下水脈が遮断されることが多く、そうした場
合、土留壁背面側の地盤の地下水位が大巾に増減し、排
水悪化や井戸水位の上昇、或いは渇水、井戸枯れ、地盤
沈下等、周辺環境に悪影響を与えることになる。特に近
年は、掘削工事が大規模化するにつれ、これが社会的な
問題となってきている。
2. Description of the Related Art In order to perform excavation work in the construction of an underground structure or the like, a continuous retaining wall of reinforced concrete or a steel pipe column retaining wall is formed along the construction area. The construction of earth retaining walls often blocks groundwater veins around the construction area.In such cases, the groundwater level on the ground behind the earth retaining walls greatly increases and decreases, and the drainage worsens and the well water level rises, or It will adversely affect the surrounding environment, such as drought, well withering, and land subsidence. In particular, in recent years, this has become a social problem as the excavation work becomes larger.

【0003】そこで、この問題を解決する方法として、
土留壁の背面に井戸を設けてポンプアップする方法(デ
イーブウエル)により、あるいは、鉄筋コンクリート土
留壁自体のところどころに遮水・通水機能を有する通水
枠等を設けたりして、背面地盤側の地下水を排出した
り、同地盤に地下水を涵養させるようにしている。
Therefore, as a method for solving this problem,
Groundwater on the back ground side is provided by pumping up with a well on the back side of the retaining wall (dave well) or by providing a water-permeable frame with a water-blocking / water-permeable function in some places on the reinforced concrete retaining wall itself. And recharge the ground with groundwater.

【0004】[0004]

【発明が解決しようとする課題】しかし、デイープウエ
ル等による方法では、井戸設置のための経費が多額にな
り、また、土留壁に通水枠を設ける方法では、施工が面
倒で経費も多額になるといった問題がある。また、鋼管
柱列土留壁の場合は、既製鋼管を利用するため、その構
造を変えることが困難であり、この種の構造物としては
不向きなものであった。
However, in the method using deep wells, etc., the cost for installing a well becomes large, and in the method of providing a water passage frame on the retaining wall, the construction is troublesome and the cost is large. Problem. In addition, in the case of a steel pipe column retaining wall, since a ready-made steel pipe is used, it is difficult to change its structure, which is unsuitable for this kind of structure.

【0005】本発明は、上記従来の問題を解決するため
になされたもので、耐力に優れるとともに施工性のよい
鋼管柱列土留壁を利用し、その各鋼管を地下水の集・排
水用の管として活用することにより、地下水の上下制
御、維持等の地下水位の調整や地下水の水流復元を図
る、経済性の優れた方法及びその構造物を提供しようと
するものである。
SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned conventional problems, and utilizes a steel column-column retaining wall having excellent proof strength and good workability, and using the steel pipes as pipes for collecting and draining groundwater. It is an object of the present invention to provide a highly economical method and its structure for adjusting the groundwater level such as vertical control and maintenance of the groundwater and restoring the groundwater flow by utilizing the above.

【0006】[0006]

【課題を解決するための手段】以下、本発明の構成につ
いて、実施例に対応する図面を参照して説明すると、請
求項1の地下水位の制御方法は、背面地盤Dと接する側
に通水孔5を設けた鋼管1を連結して鋼管柱列土留壁A
を造成した後、該土留壁Aの背面地盤D側に、該土留壁
Aと接して、砕石等を充填した透水層Bを形成し、該土
留壁Aの鋼管1内を掘削、排土して、鋼管1内と透水層
Bとを通水孔5を介して連通させ、鋼管1側からの注・
排水により、透水層Bを通して背面地盤Dの地下水位を
調節することを、特徴とするものである。
The structure of the present invention will be described below with reference to the drawings corresponding to the embodiments. Steel pipes 1 having holes 5 are connected to each other to connect steel pipe column retaining walls A
Is formed on the back ground D side of the retaining wall A to form a permeable layer B filled with crushed stone or the like in contact with the retaining wall A, and excavate and discharge the inside of the steel pipe 1 of the retaining wall A. Then, the inside of the steel pipe 1 and the permeable layer B are communicated with each other through the water hole 5, and
The feature is that the groundwater level of the back ground D is adjusted through the permeable layer B by drainage.

【0007】また、請求項2の構造物は、背面地盤Dと
接する側に通水孔5を設けた鋼管1の連結による鋼管柱
列土留壁Aを造成するとともに、該土留壁Aの背面側
に、該土留壁Aと接して、砕石等を充填した透水層Bを
形成し、該土留壁Aの中空とした鋼管1内と透水層Bを
通水孔5を介して連通させ、上記鋼管1内に、注・排水
用ポンプ12に接続された配水管10を設置したことを特徴
とするものである。
Further, in the structure of the second aspect, a steel pipe column retaining wall A is formed by connecting steel pipes 1 provided with water holes 5 on a side contacting the rear ground D, and the rear side of the retaining wall A is formed. A permeable layer B filled with crushed stones or the like is formed in contact with the retaining wall A, and the inside of the hollow steel pipe 1 of the retaining wall A and the permeable layer B communicate with each other through the water hole 5. 1, a water distribution pipe 10 connected to a pouring / draining pump 12 is provided.

【0008】[0008]

【発明の実施の形態】以下、本発明の実施の形態につい
て図面を参照して説明する。図1、図2は本発明構造物
の一実施例を示し、図3〜図6はその施工過程を示した
ものである。また、図7,図8は同他の実施例を示し、
図9,図10は使用する鋼管の実施例を示したものであ
る。
Embodiments of the present invention will be described below with reference to the drawings. 1 and 2 show an embodiment of the structure of the present invention, and FIGS. 3 to 6 show the construction process. 7 and 8 show another embodiment,
9 and 10 show an embodiment of a steel pipe used.

【0009】本発明の地下水位制御構造物は、鋼管柱列
土留壁Aと、その背面地盤D側に形成した透水層Bと、
上記土留壁Aの鋼管1に設置された、注・排水用の通水
孔5とよりなる。
The underground water level control structure of the present invention comprises a steel pipe column retaining wall A, a permeable layer B formed on the back ground D side thereof,
It consists of a water hole 5 for pouring and draining, which is installed in the steel pipe 1 of the retaining wall A.

【0010】鋼管柱列土留壁(以下、土留壁という)A
は、地下建造物の建設地等の掘削地盤Cに接して造成さ
れる。その造成は、図3、図4に示すように、対向する
外側面に継手材2を設けた鋼管1,1を、互いに継手材
2,2どうしを嵌合して連結しながら、ソイルセメント
3を充填した掘削孔4に沈設して形成される。この方法
は、従来公知のいわゆるONS工法と称される工法であ
るが、土留壁Aの造成はこのONS工法に限ることな
く、従来公知の他の工法、例えば、鋼管矢板を打撃や中
掘りにより沈設して形成する工法によることもできる。
本発明においては、土留壁Aの鋼管1として、背面地盤
Dと接する側に、図9、図10に示すように、上下に間隔
をおいて所要数の通水孔5を設けた鋼管が使用される。
この場合、図示のように、通水孔5を開設する個所に補
強板6を添設するのがよい。
[0010] Steel pipe column retaining wall (hereinafter referred to as retaining wall) A
Is formed in contact with an excavated ground C such as a construction site of an underground building. As shown in FIGS. 3 and 4, the steel pipes 1, 1 provided with the joint members 2 on the opposing outer surfaces are connected to each other by fitting the joint members 2, 2 to each other while connecting the steel pipes 1, 2 with each other. Formed in the excavation hole 4 filled with. This method is a conventionally known method called the ONS method, but the formation of the retaining wall A is not limited to the ONS method, and other conventionally known methods, for example, by hitting or digging a steel pipe sheet pile. It is also possible to use a construction method of forming by submerging.
In the present invention, as the steel pipe 1 of the retaining wall A, a steel pipe in which a required number of water holes 5 are provided on the side in contact with the back ground D, as shown in FIGS. Is done.
In this case, as shown in the figure, it is preferable to add a reinforcing plate 6 at a location where the water hole 5 is opened.

【0011】土留壁Aの造成についで、土留壁Aより所
要距離隔てた背面地盤Dに、土留壁Aとほぼ平行に矢板
壁7を打設する。そして、図5,図6に示すように、土
留壁Aと矢板壁7との間の地盤を掘削、排土して砕石等
の充填空間8を形成するとともに、鋼管1の通水孔5を
露出させる。なお、その際、ソイルセメントを用いた土
留壁工法(ONS工法)による場合は、鋼管1,1の継
手部分2の止水性を保つために、その充填空間側のソイ
ルセメント3は残したままとする。
After the formation of the retaining wall A, a sheet pile wall 7 is placed on the back ground D at a required distance from the retaining wall A, substantially parallel to the retaining wall A. Then, as shown in FIGS. 5 and 6, the ground between the retaining wall A and the sheet pile wall 7 is excavated and excavated to form a filling space 8 such as crushed stone, and the water hole 5 of the steel pipe 1 is formed. Expose. In this case, in the case of the earth retaining wall method (ONS method) using soil cement, the soil cement 3 on the filling space side is left as it is in order to maintain the water stopping property of the joint portion 2 of the steel pipes 1, 1. I do.

【0012】次いで、充填空間8に砕石や砂利等のろ過
材9を充填して、土留壁Aと背面地盤Dとの間に透水層
Bを形成する(図1、図2参照)。そして、各鋼管1内
をハンマーグラブやオーガにより掘削、排土して、鋼管
1を中空管に形成するとともに、土留壁Aの掘削側地盤
Cを掘削、排土する。なお、透水層Bの形成後、矢板壁
7はそのまま残置してもよく、また、抜き取ってもよ
い。残置する場合は、背面地盤Dと透水層Bとの水の流
通を阻害することのないように、矢板壁7を多孔質のも
のとすることが必要である。
Next, the filling space 8 is filled with a filtering material 9 such as crushed stone or gravel to form a water permeable layer B between the retaining wall A and the back ground D (see FIGS. 1 and 2). Then, the inside of each steel pipe 1 is excavated and excavated by a hammer grab or an auger, thereby forming the steel pipe 1 into a hollow pipe, and excavating and excavating the excavated ground C of the retaining wall A. After the formation of the water permeable layer B, the sheet pile wall 7 may be left as it is, or may be removed. When the sheet pile is left, it is necessary to make the sheet pile wall 7 porous so as not to hinder the flow of water between the back ground D and the permeable layer B.

【0013】中空となった鋼管1内には、図1,図2
に、示すように、注・排水用の配水管10を、その下端が
掘削底面よりやや上方に位置するようにして挿入、設置
する。各配水管10は、地上に設置された注・排水ポンプ
12の配水本管11に接続される。そして、注・排水ポンプ
12の配水本管11との対向側の配管13は、河川や貯水池等
所要の個所、施設と連絡される。なお、配水管10は各鋼
管1毎でなく、数本おきに設置してもよい。
FIGS. 1 and 2 show the inside of the hollow steel pipe 1.
As shown in the figure, a water supply / drainage pipe 10 is inserted and installed so that its lower end is located slightly above the bottom of the excavation. Each water pipe 10 is a ground-based injection / drainage pump
Connected to 12 water distribution mains 11. And note and drainage pump
The pipe 13 on the opposite side of the water distribution main pipe 11 is connected to required places and facilities such as rivers and reservoirs. The water distribution pipes 10 may be provided not every steel pipe 1, but every few pipes.

【0014】本発明の構造物は、上記のような施工過程
を経て造成される。それで、背面地盤Dが地下水流の上
流側であったり、湧水地帯であるような場合には、背面
地盤Dの地下水は、透水層Bに侵入し、通水孔5から鋼
管1内に流入し、貯水されることになる。本発明では、
こうした場合、注・排水ポンプ12を排水側にセットし
て、鋼管1内の水を吸い上げて排水する。それによっ
て、背面地盤Dの地下水位は制御されることになる。
The structure of the present invention is constructed through the above-described construction process. Therefore, when the back ground D is on the upstream side of the groundwater flow or in a spring area, the groundwater on the back ground D infiltrates into the permeable layer B and flows into the steel pipe 1 from the water hole 5. And will be stored. In the present invention,
In such a case, the injection / drainage pump 12 is set on the drain side, and the water in the steel pipe 1 is sucked and drained. Thereby, the groundwater level of the back ground D is controlled.

【0015】反対に、背面地盤Dが地下水流の下流側に
あたるなどして、土留壁Aにより流水が遮断された場合
は、地下水位が低下することになる。こうした場合は、
注・排水ポンプ12により他所より吸い上げた水、あるい
は、対向する上流側から排水された水を通水管10より鋼
管1内に注水する。それにより、鋼管1内の水は通水孔
5から透水層Bに流入し、透水層Bから背面地盤Dに浸
透して行く。それによって、背面地盤Dの水位の回復が
図れることになる。
Conversely, if the groundwater is interrupted by the retaining wall A, for example, when the back ground D is on the downstream side of the groundwater flow, the groundwater level will drop. In these cases,
Injection / drainage pump 12 pumps water from another location or water drained from the opposing upstream side into water pipe 10 into steel pipe 1. Thereby, the water in the steel pipe 1 flows into the permeable layer B from the permeable hole 5 and permeates from the permeable layer B to the back ground D. Thereby, the water level of the back ground D can be recovered.

【0016】背面地盤Dの地下水位は、いたずらに変化
させないようにすることが必要である。そのためには、
鋼管1内に貯留された水位を計測し、常時所要の水位と
なるように、配水管10による注・排水量を調節する。注
・排水の調節は、鋼管1内水位を目視したり、鋼管1内
に計測装置を設けたりして、注・排水ポンプ12を手動あ
るいは自動で切換え作動して行うことができる。
It is necessary that the groundwater level of the back ground D is not changed unnecessarily. for that purpose,
The water level stored in the steel pipe 1 is measured, and the injection / drainage amount by the water distribution pipe 10 is adjusted so that the required water level is always obtained. Adjustment of the pouring / draining can be performed by manually or automatically switching the pouring / draining pump 12 by visually checking the water level in the steel pipe 1 or providing a measuring device in the steel pipe 1.

【0017】図7に示すように、土留壁Aの鋼管1内へ
は、砕石や砂利等のろ過材9を充填することができる。
そうすれば、排水する場合、透水孔5より鋼管1内に流
入する水に混っている土砂をろ過して、配水管10の目詰
まりや、注・排水ポンプ12の作動の保護に役立つことに
なる。その場合は、配水管10を保護するため、小径ケー
シング14を設けて、配水管10をその中に挿入する。ま
た、使用する鋼管1がその内面を防錆処理しているもの
であれば、それを保護するため、内面に保護ネット(図
示を略す)などの加工を施すのがよい。
As shown in FIG. 7, a filter medium 9 such as crushed stone or gravel can be filled in the steel pipe 1 of the retaining wall A.
Then, when draining, the sediment mixed with the water flowing into the steel pipe 1 from the water permeation hole 5 is filtered to help clogging of the water distribution pipe 10 and protection of the operation of the injection / drainage pump 12. become. In that case, in order to protect the water distribution pipe 10, a small-diameter casing 14 is provided, and the water distribution pipe 10 is inserted therein. If the inner surface of the steel pipe 1 to be used is rust-proof, it is preferable to apply a process such as a protection net (not shown) to the inner surface to protect the inner surface.

【0018】上記の実施例では、透水層Bは土留壁Aの
長さ方向の全面にわたり設けているが、これに限らず、
例えば図8に示すように、透水層Bは土留壁Aの長さ方
向に間隔をおいて適宜断片的に設けることも可能であ
る。
In the above embodiment, the permeable layer B is provided over the entire surface of the retaining wall A in the longitudinal direction.
For example, as shown in FIG. 8, the permeable layer B can be provided in a fragmentary manner at intervals in the longitudinal direction of the retaining wall A.

【0019】[0019]

【発明の効果】以上説明したように、本発明によれば、
鋼管柱列土留壁の鋼管を水の貯留管として利用するとと
もに、該土留壁の背面に透水層を形成し、鋼管に設けた
注・排水手段により、背面地盤への注水あるいは同地盤
地下水の排出が行えるようにしたので、従来、施工が容
易で耐力及び止水性に優れながら、地下水位の調整や地
下水流の復元を図るには不向きとされていた鋼管柱列土
留壁が活用できるとともに、背面地盤の地下水の集水、
排出や、背面地盤地下水を涵養させる等、地下水位の制
御が自在かつ効果的に行えることになり、掘削工事にと
もなう地下水位の変動による周辺環境への悪影響を少な
くすることができる。
As described above, according to the present invention,
The steel pipe of the steel column pillar retaining wall is used as a water storage pipe, a permeable layer is formed on the back of the retaining wall, and water is injected into the back ground or discharged from the ground by means of pouring and draining means provided on the steel pipe. In addition to the easy construction, excellent strength and waterproof properties, the steel pipe column soil retaining wall, which was previously unsuitable for adjusting the groundwater level and restoring the groundwater flow, can be used. Collecting groundwater from the ground,
The groundwater level can be freely and effectively controlled, such as discharging and recharging the groundwater at the rear, and adverse effects on the surrounding environment due to fluctuations in the groundwater level due to excavation work can be reduced.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明構造物の一実施例を示す縦断面図であ
る。
FIG. 1 is a longitudinal sectional view showing one embodiment of the structure of the present invention.

【図2】同平面図である。FIG. 2 is a plan view of the same.

【図3】鋼管柱列土留壁の造成と矢板壁の打設時の状態
を示す縦断面図である。
FIG. 3 is a longitudinal sectional view showing a state in which a steel pipe column retaining wall is formed and a sheet pile wall is driven.

【図4】同平面図である。FIG. 4 is a plan view of the same.

【図5】充填空間を掘削、形成した状態を示す縦断面図
である。
FIG. 5 is a longitudinal sectional view showing a state where a filling space is excavated and formed.

【図6】同平面図である。FIG. 6 is a plan view of the same.

【図7】配水管設置の他の実施例を示す縦断面図であ
る。
FIG. 7 is a longitudinal sectional view showing another embodiment of installation of a water distribution pipe.

【図8】透水層形成の他の実施例を示す平面図である。FIG. 8 is a plan view showing another embodiment of forming a water-permeable layer.

【図9】鋼管の拡大縦断面図である。FIG. 9 is an enlarged vertical sectional view of a steel pipe.

【図10】同要部の背面図である。FIG. 10 is a rear view of the main part.

【符号の説明】[Explanation of symbols]

A 鋼管柱列土留壁 B 透水層 C 掘削側地盤 D 背面地盤 1 鋼管 2 継手材 3 ソイルセメント 4 掘削孔 5 通水孔 7 矢板壁 8 充填空間 9 ろ過材 10 配水管 12 注・排水ポンプ 14 ケーシング A Steel pipe pillar row retaining wall B Water permeable layer C Drilling side ground D Back ground 1 Steel pipe 2 Joint material 3 Soil cement 4 Drilling hole 5 Water flow hole 7 Sheet pile wall 8 Filling space 9 Filtering material 10 Water pipe 12 Injection / drain pump 14 Casing

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 背面地盤と接する側に通水孔を設けた鋼
管を連結して鋼管柱列土留壁を造成した後、該土留壁の
背面地盤側に、該土留壁と接して、砕石等を充填した透
水層を形成し、該土留壁の鋼管内を掘削、排土して、鋼
管内と透水層とを通水孔を介して連通させ、鋼管側から
の注・排水により、透水層を通して背面地盤の地下水位
を調節することを、特徴とする、鋼管柱列土留壁を用い
た地下水位の制御方法。
A steel pipe having a water column formed on the side in contact with the back ground to form a steel pipe column retaining soil wall. Is formed, and the inside of the steel pipe of the retaining wall is excavated and excavated, and the inside of the steel pipe and the permeable layer are communicated with each other through the water hole, and the permeable layer is poured and drained from the steel pipe side. A method of controlling a groundwater level using a steel tube column retaining wall, comprising adjusting a groundwater level of a back ground through a tunnel.
【請求項2】 背面地盤と接する側に通水孔を設けた鋼
管の連結による鋼管柱列土留壁を造成するとともに、該
土留壁の背面側に、該土留壁と接して、砕石等を充填し
た透水層を形成し、該土留壁の中空とした鋼管内と透水
層を通水孔を介して連通させ、上記鋼管内に、注・排水
用ポンプに接続された配水管を設置したことを特徴とす
る、鋼管柱列土留壁を用いた地下水位の制御構造物。
2. A steel pipe column retaining wall is formed by connecting steel pipes provided with water holes on a side in contact with the back ground, and a crushed stone is filled on the rear side of the retaining wall in contact with the retaining wall. That the permeable layer was formed, and the inside of the steel pipe having the hollow retaining wall was communicated with the permeable layer through the water hole, and a water distribution pipe connected to an injection / drainage pump was installed in the steel pipe. Characterized by a groundwater level control structure using steel pipe column retaining walls.
JP14464897A 1997-05-19 1997-05-19 Method for controlling underground water level using steel-pipe-column-line earth-retaining wall, and structure thereof Pending JPH10317368A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14464897A JPH10317368A (en) 1997-05-19 1997-05-19 Method for controlling underground water level using steel-pipe-column-line earth-retaining wall, and structure thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14464897A JPH10317368A (en) 1997-05-19 1997-05-19 Method for controlling underground water level using steel-pipe-column-line earth-retaining wall, and structure thereof

Publications (1)

Publication Number Publication Date
JPH10317368A true JPH10317368A (en) 1998-12-02

Family

ID=15366973

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14464897A Pending JPH10317368A (en) 1997-05-19 1997-05-19 Method for controlling underground water level using steel-pipe-column-line earth-retaining wall, and structure thereof

Country Status (1)

Country Link
JP (1) JPH10317368A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009046838A (en) * 2007-08-16 2009-03-05 Tokyu Construction Co Ltd Structure of condensate structure and method of constructing the same

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009046838A (en) * 2007-08-16 2009-03-05 Tokyu Construction Co Ltd Structure of condensate structure and method of constructing the same

Similar Documents

Publication Publication Date Title
Hanson et al. Ground‐water dams for rural‐water supplies in developing countries
US6840710B2 (en) Underground alluvial water storage reservoir and method
KR100593786B1 (en) The construction of waterway for tunnel
LU500273B1 (en) New comprehensive dewatering and drainage method and drainage device for mudstone subway station
CN112252336A (en) Construction method for backfilling foundation trench of premixed fluidized solidified soil
CN108867673A (en) A kind of underwater prevention method in the foundation pit based on the curtain that draws water
CN114606964B (en) Foundation pit dewatering method used under complex geological conditions
CN109339059B (en) Comprehensive recycling system and construction method for foundation pit excavation backfill ramming and precipitation recharging water resources
JP4074313B2 (en) Structure of steel sheet pile for water flow and water retaining wall, and its construction method.
JP4675130B2 (en) Drain structure of embankment bank and its construction method
CN111042144B (en) Excavation method for foundation pit of underground beam under condition of continuous flow of riverway in cold region
JPH10317368A (en) Method for controlling underground water level using steel-pipe-column-line earth-retaining wall, and structure thereof
CN110685292A (en) Foundation pit drainage system and construction method thereof
JP2809105B2 (en) How to build an underground tank
JP2900842B2 (en) Earth retaining wall structure with water permeability
CN113833524B (en) Double-hole box culvert for treating karst area tunnel water burst and construction method thereof
CN219034746U (en) Tunnel passing structure penetrating through water-rich karst cave
KR100652187B1 (en) Grouting method to the underdrain-installed point in a hillside road
JP3892576B2 (en) Maintenance method of water vein in underground retaining wall construction section
US20060171781A1 (en) Pipeline trench system and method of construction
JP3724734B2 (en) Underground cavity filling method
JPH01121414A (en) Excavation work of ground
Cashman et al. Case Histories
Day¹ et al. State of the art in bio-polymer drain construction
KR101347866B1 (en) Construction method for accelerating inundated type radial collecting well