JPH11210369A - Underground submerged object - Google Patents
Underground submerged objectInfo
- Publication number
- JPH11210369A JPH11210369A JP2520098A JP2520098A JPH11210369A JP H11210369 A JPH11210369 A JP H11210369A JP 2520098 A JP2520098 A JP 2520098A JP 2520098 A JP2520098 A JP 2520098A JP H11210369 A JPH11210369 A JP H11210369A
- Authority
- JP
- Japan
- Prior art keywords
- shaft
- piece
- concrete
- starting
- port
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】この発明は、複数のピース部
材、たとえばセグメントピースと呼ばれるものを連結し
て地下に沈設して、立坑を構築し、トンネルを掘削する
シールド掘削機等の発進立坑または到達立坑とするため
の地下沈設体に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a starting shaft or a reaching shaft of a shield excavator or the like for connecting a plurality of piece members, for example, so-called segment pieces, and sunk them underground to construct a shaft and excavate a tunnel. It relates to an underground buried body to be used as a shaft.
【0002】[0002]
【従来の技術】たとえば、地下に地下鉄を建設する場合
などには、地下鉄用のトンネルを掘削しようとするルー
トの両端部に、地盤に対し略鉛直方向に発進立坑及び到
達立坑を構築する。そして、シールド掘削機を発進立坑
内部へ下ろし、発進立坑から発進させ、所定のルートを
掘削した後に、到達立坑へ到達する。2. Description of the Related Art For example, when a subway is constructed underground, a starting shaft and a reaching shaft are constructed at both ends of a route where a tunnel for a subway is to be excavated in a direction substantially perpendicular to the ground. Then, the shield excavator is lowered into the start shaft, is started from the start shaft, excavates a predetermined route, and then reaches the arrival shaft.
【0003】この場合のシールド掘削機の発進と到達
は、両立坑の発進側及び到達側の地盤を地盤改良して、
両立坑の内部から人力によるはつりを行い、発進口及び
到達口を丁寧に形成していた。In this case, the starting and reaching of the shield excavator is performed by improving the ground on the starting side and the reaching side of both shafts,
The start and the entrance were carefully formed by hanging from the inside of both shafts by human power.
【0004】そして、地盤改良の方法としては、セメン
ト系の注入材を高圧噴射注入工法により地盤に注入する
ものや、地盤に複数の管を貫通させ管の内部に冷媒を通
し地盤を凍結させる方法などがある。これによりシール
ド掘削機の発進及び到達時に発進口や到達口などの周囲
の地盤が崩れてしまうのを防止する。[0004] As a method of soil improvement, a cement-based injection material is injected into the ground by a high-pressure injection injection method, or a method in which a plurality of pipes are penetrated through the ground and a refrigerant is passed through the pipes to freeze the ground. and so on. This prevents the surrounding ground, such as the starting port and the reaching port, from collapsing when the shield excavator starts and reaches.
【0005】しかし、このような地盤改良は、環境汚染
の危険性があり、また、地盤改良工事により工期が長く
なってしまうなどの制約があった。また、はつり作業
は、作業者の安全管理が難しく、また塵埃が多く発生し
てしまうという問題もあった。これらのため、地盤改良
作業やはつり作業には、時間とコストがかかるという問
題があった。[0005] However, such ground improvement has a risk of environmental pollution, and there are restrictions such as a longer construction period due to ground improvement work. In addition, there is a problem that the hanging operation is difficult for the worker to manage safely, and that a large amount of dust is generated. For these reasons, there has been a problem that it takes time and cost for ground improvement work and hanging work.
【0006】このような問題を解決するために、シール
ド掘削機のカッタービットで切削可能な材料を、発進立
坑及び到達立坑の立坑を構成する壁体に用い、地盤改良
作業やはつり作業を省略する方法が提案されている。す
なわち、立坑の壁体は、例えばH型鋼を縦に配置したも
のを、立坑の周方向に多数連続させて構成するものであ
るが、発進口及び到達口に相当する部分には、H型鋼の
変わりに、シールド掘削機により切削可能な材料を用い
る。In order to solve such a problem, a material that can be cut by a cutter bit of a shield excavator is used for a wall constituting a starting shaft and a reaching shaft, and ground improvement work and hanging work are omitted. A method has been proposed. That is, the wall of the shaft is formed by, for example, vertically arranging a plurality of H-shaped steels in the circumferential direction of the shaft, and constructing the H-shaped steel in portions corresponding to the start port and the arrival port. Instead, a material that can be cut by a shield excavator is used.
【0007】ここでいう切削可能とは、カッタービット
で切断された後も、通常の鉄筋のようにカッタービット
に絡みついたりせず、開口をスムースに達成させるもの
のことである。すなわち、鉄系の材料であっても切削後
にカッタービットに絡みついたりしなければ、「切削可
能」である。[0007] The term "cuttable" as used herein means that even after being cut by the cutter bit, the opening is smoothly achieved without being entangled with the cutter bit unlike a normal rebar. That is, even if it is an iron-based material, it is "cuttable" if it does not become entangled with the cutter bit after cutting.
【0008】このような材料の一例としては、炭素繊維
で補強し石灰石骨材を使用した高強度コンクリートなど
がある。切削可能な材料は、同時に、壁体として土圧や
水圧によって発生する引っ張り力等に十分に耐えられる
ものであることが必要であるので、補強がなされる。One example of such a material is high-strength concrete using limestone aggregate reinforced with carbon fibers. At the same time, the material that can be cut is required to be sufficiently resistant to a tensile force generated by earth pressure or water pressure as a wall, so that the wall is reinforced.
【0009】[0009]
【発明が解決しようとする課題】しかしながら、切削可
能な材料を発進口又は到達口に用いた発進立坑又は到達
立坑は、H型鋼などの長物の材料を縦方向に配置し立坑
の周方向に複数連続させた構造であるため、立坑を掘削
する工事自体が、時間及びコストを必要とするものであ
った。However, a starting shaft or a reaching shaft using a cuttable material for a starting port or a reaching port has a structure in which a long material such as an H-section steel is arranged in a vertical direction and a plurality of shafts are arranged in a circumferential direction of the shaft. Because of the continuous structure, the construction itself for excavating the shaft requires time and cost.
【0010】この発明は、以上の課題を解決するために
なされたもので、圧入沈設工法における地盤改良工事
や、はつり工事を省略でき、且つ立坑の掘削工事にかか
る時間及びコストを低減できる地下沈設体を提供するこ
とを目的とする。SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems, and it is possible to omit the ground improvement work and the hanging work in the press-in squatting method, and to reduce the time and cost required for excavating the shaft. The purpose is to provide the body.
【0011】また、この発明に係る地下沈設体は、最上
端から加圧することで地下に沈設を行うものであるが、
前記引っ張り力のみならず、この加圧力に伴う圧縮力に
も十分に耐えられる地下沈設体を提供することをも目的
とする。Further, the underground submerged body according to the present invention is to submerge underground by applying pressure from the uppermost end.
It is another object of the present invention to provide an underground submerged body that can sufficiently withstand not only the above-described tensile force but also the compressive force caused by this pressing force.
【0012】[0012]
【課題を解決するための手段】以上の目的を達成するた
めに、第一の発明は、複数のピース部材を連結して構成
する中空筒体を、内部を掘削し最上端から加圧すること
で、地下に沈設して構築され、シールド掘削機によりト
ンネルを掘削する際の発進立坑または到達立坑とされる
地下沈設体において、前記ピース部材のうち発進口また
は到達口に相当する部分のピース部材が、前記シールド
掘削機によって切削可能な材料からなることを特徴とす
る地下沈設体である。Means for Solving the Problems To achieve the above object, a first aspect of the present invention is to excavate the inside of a hollow cylindrical body formed by connecting a plurality of piece members and pressurize the hollow cylindrical body from the uppermost end. In the underground buried body which is constructed to be laid underground and is a starting shaft or a reaching shaft when excavating a tunnel by a shield excavator, a piece member corresponding to a starting port or a reaching port of the piece members is An underground submerged body made of a material that can be cut by the shield excavator.
【0013】第二の発明は、さらに、前記切削可能なピ
ース部材の材料がコンクリートであり、他のピース部材
の材料が鋼材、または鉄筋コンクリートであることを特
徴とする前記地下沈設体である。[0013] The second invention is the underground submerged structure further characterized in that the material of the cuttable piece member is concrete and the material of the other piece members is steel or reinforced concrete.
【0014】第三の発明は、さらに、前記コンクリート
を材料とするピース部材の厚さが、鋼材、または鉄筋コ
ンクリートを材料とするピース部材の厚さより厚く、両
者の間で厚さが変化する部分に、該変化が連続的に行わ
れるよう傾斜が施されたことを特徴とする前記地下沈設
体である。According to a third aspect of the present invention, the thickness of the piece made of concrete is greater than the thickness of the piece made of steel or reinforced concrete, and the thickness of the piece changes between the two. The underground submerged body is characterized by being inclined so that the change is performed continuously.
【0015】[0015]
【発明の実施の形態】以下、この発明の一実施形態を、
図1乃至図10において説明する。まず、図1において
地下に地下鉄などを建設するためにトンネル掘削を行う
際の工事全体の概略工程を説明する。BEST MODE FOR CARRYING OUT THE INVENTION Hereinafter, one embodiment of the present invention will be described.
This will be described with reference to FIGS. First, referring to FIG. 1, a schematic process of the entire construction when a tunnel is excavated for constructing a subway or the like underground will be described.
【0016】シールド掘削機1によりトンネル3を掘削
するための発進立坑5を構築するために、始めに、地上
に中空筒体7を据え付ける(図1(A))。この中空筒
体7は複数のピース部材9を連結して構成する。そし
て、中空筒体7の内部を掘削すると同時に、最上端から
加圧を行い、中空筒体7を地下に埋設する。中空筒体7
の最上端にはピース部材9が次々と連結され、中空筒体
7の上下方向の全長は長くなる(図1(A)(B))。
そして、掘削と加圧を繰り返すことで、地中深く地下沈
設体が構築される(図1(C))。In order to construct a starting shaft 5 for excavating the tunnel 3 by the shield excavator 1, first, a hollow cylindrical body 7 is installed on the ground (FIG. 1A). The hollow cylinder 7 is formed by connecting a plurality of piece members 9. Then, at the same time as the inside of the hollow cylinder 7 is excavated, pressure is applied from the uppermost end, and the hollow cylinder 7 is buried underground. Hollow cylinder 7
Piece members 9 are successively connected to the uppermost end of the hollow cylindrical member 7, and the overall length of the hollow cylindrical body 7 in the vertical direction becomes longer (FIGS. 1A and 1B).
Then, by repeatedly excavating and pressurizing, an underground submerged body is constructed deep underground (FIG. 1C).
【0017】このようにして地下沈設体として構築され
た発進立坑5に、シールド掘削機1を吊り下ろし(図
(D))、発進口11に向かって発進させる(図(D)
(E))。発進口11に相当するピース部材9には、切
削可能な材料が用いられる。シールド掘削機は、この切
削可能なピース部材を切削して発進を開始し、トンネル
を所定のルートに沿って掘削する(図(F))。The shield excavator 1 is suspended from the starting shaft 5 constructed as an underground submerged body (FIG. (D)), and is started toward the starting port 11 (FIG. (D)).
(E)). For the piece member 9 corresponding to the starting port 11, a cuttable material is used. The shield excavator cuts the cuttable piece member and starts moving, and excavates the tunnel along a predetermined route (FIG. (F)).
【0018】やがて、所定のルートの最終端に構築され
た到達立坑13にシールド掘削機1が到達する(図
(G))。この到達立坑13も、前記発進立坑5と同様
の手順(図1(A)(B)(C))で予め構築される。
また、到達口15に相当する部分のピース部材も、発進
立坑5の場合と同様に切削可能な材料からなる。到達に
際しても、シールド掘削機によりピース部材が切削され
る(図(G)(H))。到達立坑13内に到達したシー
ルド掘削機1(図(H))は、吊り上げられ、地上に搬
出される。Eventually, the shield excavator 1 reaches the reaching shaft 13 constructed at the end of the predetermined route (FIG. (G)). The reaching shaft 13 is also constructed in advance by the same procedure (FIGS. 1A, 1B, and 1C) as the starting shaft 5.
Further, the piece member corresponding to the arrival port 15 is also made of a material that can be cut in the same manner as in the case of the starting shaft 5. Upon reaching, the piece member is cut by the shield excavator (FIGS. (G) and (H)). The shield excavator 1 (FIG. (H)) that has reached the arrival shaft 13 is lifted and carried out to the ground.
【0019】次に、発進立坑5または到達立坑13を構
築する際の様子(図1(B))を、図2をもとに詳しく
説明する。Next, the construction of the starting shaft 5 or the reaching shaft 13 (FIG. 1B) will be described in detail with reference to FIG.
【0020】中空筒体7が加圧され沈設されるスペース
の周囲には、あらかじめ複数のグラウンドアンカー17
が打ち込まれ、このグラウンドアンカー17に接続され
たアンカワイヤー19は、中空筒体7の上方に備えられ
る上部ビーム21に固定される。中空筒体7の上部には
保護リング23を介して圧入桁25が乗せられ、この圧
入桁25と前記上部ビーム21との間に、ジャッキ受け
台27および圧入ジャッキ29が設けられる。A plurality of ground anchors 17 are previously provided around the space where the hollow cylindrical body 7 is pressurized and settled.
Is anchored, and the anchor wire 19 connected to the ground anchor 17 is fixed to the upper beam 21 provided above the hollow cylinder 7. A press-fit girder 25 is mounted on the upper part of the hollow cylinder 7 via a protection ring 23, and a jack receiving stand 27 and a press-fit jack 29 are provided between the press-fit girder 25 and the upper beam 21.
【0021】圧入ジャッキ29が働いて上部ビーム21
と圧入桁25の間を広げると、圧入力が圧入桁25およ
び保護リング23を介して中空筒体7に伝えられ、中空
筒体7は下方へ地盤に向かって圧入される。The press-in jack 29 works to operate the upper beam 21.
When the space between the press-fitting girder 25 and the press-fitting girder 25 is widened, the press-fitting force is transmitted to the hollow cylinder 7 via the press-fitting girder 25 and the protection ring 23, and the hollow cylinder 7 is pressed down toward the ground.
【0022】また、掘削機の一種であるハンマーグラブ
バケット31がワイヤー33によって吊り下げられ、中
空筒体7内部の地盤を掘削する。このようにして、中空
筒体7が地下に沈設され、立坑7、23が構築されてい
く。A hammer grab bucket 31, which is a type of excavator, is hung by a wire 33 to excavate the ground inside the hollow cylinder 7. In this way, the hollow cylinder 7 is laid underground, and the shafts 7 and 23 are constructed.
【0023】次に、発進立坑5からシールド掘削機1が
発進する際の状態を図3に詳しく示す。図中35は、ト
ンネルが掘削されるルートを示す。同様に、シールド掘
削機1が到達立坑13へ到達する詳細図を図4に示す。Next, the state when the shield excavator 1 starts moving from the starting shaft 5 is shown in detail in FIG. In the figure, 35 indicates a route through which a tunnel is excavated. Similarly, FIG. 4 shows a detailed view of the shield excavator 1 reaching the reaching shaft 13.
【0024】そして、図3における発進口11および図
4における到達口15の水平断面図を図5に示す。発進
口11または到達口15に相当する複数枚のピース部材
9が、コンクリート系の掘削可能な材料37からなる。FIG. 5 is a horizontal sectional view of the starting port 11 in FIG. 3 and the reaching port 15 in FIG. The plurality of piece members 9 corresponding to the starting port 11 or the reaching port 15 are made of a concrete-based excavable material 37.
【0025】次ぎに、発進口11の拡大した様子を図6
に示し、到達口15の拡大した様子を図7に示す。な
お、発進口11と到達口15は、この実施形態では、同
じ構造を有する部分の裏と表である。Next, an enlarged view of the starting port 11 is shown in FIG.
FIG. 7 shows an enlarged view of the arrival port 15. In this embodiment, the starting port 11 and the reaching port 15 are the back and front of the portion having the same structure.
【0026】図6(A)及び図7(A)に示すように、
発進口11または到達口15に相当する4枚のピース部
材9がコンクリート系の掘削可能な材料37からなる。
なお、シールド掘削機1のカッタービット(図示せず)
が接触する部分39を円形の破線で示す。コンクリート
系の切削可能な材料37としては、(1)炭素繊維で補
強した石灰石骨材を使用する高強度のコンクリート、
(2)前記(1)の石灰石骨材の変わりに軽量骨材を使
用するコンクリート、(3)炭素繊維などの筋材を使用
しない無筋の石灰石コンクリート、などが考えられる。
このうち(3)は小径のトンネルを掘削する小径の立坑
の場合に用いられる。As shown in FIGS. 6A and 7A,
The four piece members 9 corresponding to the starting port 11 or the reaching port 15 are made of a concrete-based excavable material 37.
The cutter bit of the shield excavator 1 (not shown)
Are indicated by circular broken lines. Concrete-based machinable materials 37 include (1) high-strength concrete using limestone aggregate reinforced with carbon fiber,
(2) Concrete using a lightweight aggregate instead of the limestone aggregate of (1), (3) Unstripped limestone concrete without using a reinforcing material such as carbon fiber, and the like can be considered.
Of these, (3) is used in the case of small diameter shafts for excavating small diameter tunnels.
【0027】また、他の実施形態においては、コンクリ
ート系以外の切削可能な材料を用いることも可能であ
る。すなわち(4)硬質発泡ウレタンをガラス長繊維で
強化した部材を積層した複合材、(5)耐引っ張り力な
どに優れた樹脂製材料などが考えられる。In another embodiment, it is also possible to use a cuttable material other than concrete. That is, (4) a composite material obtained by laminating members in which hard urethane foam is reinforced with long glass fibers, and (5) a resin material having excellent tensile strength and the like can be considered.
【0028】コンクリート系の材料37からなるピース
部材9以外の他のピース部材9は、この実施形態におい
ては、鋼材を材料とする鋼製セグメントピースである。
鋼製セグメントピースは、湾曲する平行な一対の主桁4
1と、これら主桁41の両端に接合される一対の継手板
43と、両主桁41の中央部分に接合される縦リブ45
と、これらの部材41、43、45の外側に接合される
スキンプレート47などからなる。The piece members 9 other than the piece member 9 made of the concrete material 37 are steel segment pieces made of steel in this embodiment.
The steel segment piece is a pair of parallel main beams 4 that are curved.
1, a pair of joint plates 43 joined to both ends of the main girder 41, and a vertical rib 45 joined to a center portion of the main girder 41.
And a skin plate 47 joined to the outside of these members 41, 43, and 45.
【0029】コンクリート系のピース部材9に隣接する
ピース部材9である鋼製セグメントピース9には、主桁
41、継手板43、縦リブ45に傾斜49が施されてい
る。コンクリート系のピース部材9の厚さは、他の鋼製
セグメントピースであるピース部材9の厚さよりも厚く
なっており、中空筒体7を地下に沈設する際に加えられ
る加圧力によって生じる大きな圧縮力に耐えられるよう
設計されている。On the steel segment piece 9 which is the piece member 9 adjacent to the concrete piece member 9, the main girder 41, the joint plate 43, and the vertical rib 45 are provided with an inclination 49. The thickness of the concrete piece member 9 is larger than the thickness of the piece member 9 which is another steel segment piece, and a large compression caused by the pressing force applied when the hollow cylindrical body 7 is laid underground. Designed to withstand the forces.
【0030】この傾斜49によって、コンクリート系の
ピース部材9から鋼製セグメントピースであるピース部
材9との間の厚さの変化が、不連続に行われるのを防止
し、連続的に行われるようにすることで、応力の集中を
防止する。The inclination 49 prevents the change in thickness between the concrete piece member 9 and the steel segment piece 9 from being discontinuous, so that the change is made continuously. By doing so, concentration of stress is prevented.
【0031】鋼製セグメントピースであるピース部材9
同士の連結は、従来と同様にボルト51によって行われ
る(図8)。すなわち、それぞれの鋼製セグメントピー
スの主桁41または継手板43に形成されたボルト孔同
士を連結し、ボルト51とナット53によって締結し連
結を行う。Piece member 9 which is a steel segment piece
The connection between them is performed by bolts 51 as in the conventional case (FIG. 8). That is, the bolt holes formed in the main girder 41 or the joint plate 43 of each steel segment piece are connected to each other, and the bolts 51 and the nuts 53 fasten the connection.
【0032】コンクリート系のピース部材9と鋼製セグ
メントピースの連結は、コンクリート系ピース部材9に
埋め込まれた埋め込みナット55を用いて行う(図
9)。すなわち、コンクリート系の材料に予め埋め込ま
れた埋め込みナット9に対し、鋼製セグメントピースの
主桁41または継手板43に形成されたボルト孔を連通
させ、鋼製セグメントピース側からボルト51を螺合し
締結して連結を行う。The connection between the concrete piece member 9 and the steel segment piece is performed using an embedded nut 55 embedded in the concrete piece member 9 (FIG. 9). That is, a bolt hole formed in the main girder 41 or the joint plate 43 of the steel segment piece is communicated with the embedding nut 9 previously embedded in the concrete material, and the bolt 51 is screwed from the steel segment piece side. Then, the connection is made.
【0033】コンクリート系ピース部材9同士の連結
は、コンクリート系ピース部材9の連結面に形成された
凹部57と凸部59、及び樹脂製の埋め込みナット61
及び樹脂製のボルト63によって行われる(図10)。
すなわち、連結面において、一方のコンクリート系のピ
ース部材9には三角形断面の凸部59が形成され、他方
のコンクリート形のピース部材9には三角形断面の凹部
57が形成され、これら凹部57と凸部59が嵌合す
る。The concrete piece members 9 are connected to each other by a concave portion 57 and a convex portion 59 formed on the connecting surface of the concrete piece member 9 and an embedded nut 61 made of resin.
And a bolt 63 made of resin (FIG. 10).
That is, on the connecting surface, one concrete piece member 9 is formed with a triangular cross-section convex portion 59, and the other concrete piece member 9 is formed with a triangular cross-sectional concave portion 57. The part 59 is fitted.
【0034】また、凸部59の斜面に埋め込まれた樹脂
製の埋め込みナット61に対し、凹部57に所定の間隔
をおいて隣接する作業用穴65の内壁に形成されたボル
ト孔67が連通され、作業用穴65において樹脂製のボ
ルト63がボルト孔67へ挿入され、埋め込みナット6
1に締結されることで連結が行われる。このようにコン
クリート系のピース部材9同士の連結は、凹部57と凸
部59によって行われ、補助的な連結として用いられる
埋め込みナット61とボルト63も共に樹脂製であるた
め、シールド掘削機のカッタービットで切削できる性質
が維持される。A bolt hole 67 formed in the inner wall of a working hole 65 adjacent to the concave portion 57 at a predetermined interval communicates with the resin embedded nut 61 embedded on the slope of the convex portion 59. In the working hole 65, the resin bolt 63 is inserted into the bolt hole 67, and the embedded nut 6 is inserted.
Connection is performed by being fastened to 1. As described above, the connection between the concrete piece members 9 is performed by the concave portion 57 and the convex portion 59, and the embedded nut 61 and the bolt 63 used as the auxiliary connection are both made of resin. The property of cutting with a bit is maintained.
【0035】(実施形態の効果)この実施形態によれ
ば、複数のピース部材9を連結して構成する中空筒体7
を、内部の地盤を掘削し、最上端から加圧することで地
下に沈設して、発進立坑又は到達立坑を構築するので、
従来のようにH型鋼などを縦方向に配置し、立坑の周方
向に多数を連続させ壁体を構成して立坑を構築する場合
に比べ、工事にかかる時間とコストを低減できる。(Effects of Embodiment) According to this embodiment, the hollow cylindrical member 7 formed by connecting a plurality of piece members 9 is formed.
Since the ground inside is excavated and submerged underground by pressurizing from the top end, a starting shaft or a reaching shaft is constructed,
The time and cost required for the construction can be reduced as compared with the conventional case where an H-section steel or the like is arranged in the vertical direction, a large number of the shafts are continuously formed in the circumferential direction of the shaft, and a wall is constructed to construct the shaft.
【0036】また、ピース部材9のうち発進口11また
は到達口15に相当する部分のピース部材9が、コンク
リート系の切削可能な材料37からなることにより、地
盤改良工事やはつり工事を省略しても、発進口11や到
達口15において地盤が崩れてしまうということを防止
できる。Further, since the portion of the piece member 9 corresponding to the start-up port 11 or the arrival port 15 is made of a concrete cuttable material 37, ground improvement work and hanging work can be omitted. Also, it is possible to prevent the ground from collapsing at the start port 11 and the arrival port 15.
【0037】また、切削可能な材料37であるコンクリ
ートの厚さを厚くすることで、中空筒体7を加圧して沈
設する際の加圧力によって生じる圧縮力にも十分に耐え
ることができる。すなわち、切削可能な材料37は、周
囲の土圧や水圧を受けるに十分な引っ張り力に耐えるも
のであり、同時に、加圧力によって生じる圧縮力にも十
分に耐えるものであり得る。Further, by increasing the thickness of the concrete, which is the material 37 that can be cut, it is possible to sufficiently withstand the compressive force generated by the pressing force when the hollow cylindrical body 7 is pressurized and settled. That is, the cuttable material 37 can withstand a sufficient tensile force to receive the surrounding earth pressure and water pressure, and at the same time, can sufficiently withstand the compressive force generated by the pressing force.
【0038】(他の実施形態)以上の実施形態において
は、中空筒体7を地下に埋設するための加圧力によって
生じる圧縮力に耐えるために、コンクリート系のピース
部材9の厚さが他のピース部材9よりも厚く設定される
ものであったが、他の実施形態においては、例えば図1
1に示すように、発進口11または到達口15に隣接す
るピース部材9に補強材71、73を施して、圧縮力を
発進口11または到達口15に受けず、隣接する補強さ
れたピース部材9によって受けるようにすることが可能
である。(Other Embodiments) In the above embodiment, in order to withstand the compressive force generated by the pressing force for burying the hollow cylindrical body 7 underground, the thickness of the concrete piece member 9 is set differently. Although it is set to be thicker than the piece member 9, in other embodiments, for example, FIG.
As shown in FIG. 1, the reinforcing members 71 and 73 are applied to the piece member 9 adjacent to the start port 11 or the arrival port 15 so as not to receive a compressive force at the start port 11 or the arrival port 15 and the adjacent reinforced piece member 9 to receive it.
【0039】すなわち、発進口11または到達口15に
相当する部分のピース部材9は、直接に発進口11また
は到達口15となる部分のみ(図中の円形の部分)がコ
ンクリート系の切削可能な材料37からなる。すなわ
ち、シールド掘削機のカッタービットが接触する円形の
部分39の斜線をカバーする大きな円形の補強材71が
設けられ、この円形の補強材71の周囲に、更に概略同
心状の曲線を有する補強材73が配置される。That is, only the portion (circular portion in the figure) of the piece member 9 corresponding to the start port 11 or the arrival port 15 can be concrete-based, and can be directly cut. It consists of material 37. That is, a large circular reinforcing member 71 is provided to cover the oblique line of the circular portion 39 with which the cutter bit of the shield excavator comes into contact, and around this circular reinforcing member 71, a reinforcing member having a further approximately concentric curve is provided. 73 are arranged.
【0040】これらの補強材71、73は、発進口11
または到達口15の中心を通る上下方向の線に対し、左
右対称の形状を有する。円形の補強材71は、継手板4
3または縦リブ45の一端と接合されている。また、曲
線を有する補強材73は、上下端部が継手板43または
縦リブ45の一端と接合されている。The reinforcing members 71 and 73 are provided at the starting port 11.
Or, it has a symmetrical shape with respect to a vertical line passing through the center of the arrival port 15. The circular reinforcing member 71 is connected to the joint plate 4.
3 or one end of the vertical rib 45. In addition, the reinforcing material 73 having a curve has upper and lower ends joined to one end of the joint plate 43 or the longitudinal rib 45.
【0041】このような形状を有する補強材71、73
によって、沈設時の加圧力によって発生する圧縮力の応
力ベクトルは、以上の発進口11または到達口15を直
接に通過せずに、周囲の補強材71、73を通ることに
なる。したがって、コンクリート系の切削可能な材料3
7は、炭素繊維などで補強したものであって土圧などに
よる引っ張り力に変えられるものであれば良いこととな
る。The reinforcing members 71, 73 having such a shape
Accordingly, the stress vector of the compressive force generated by the pressing force at the time of sinking passes through the surrounding reinforcing members 71 and 73 without directly passing through the starting port 11 or the reaching port 15 described above. Therefore, concrete-based cuttable material 3
Reference numeral 7 is a material reinforced with carbon fiber or the like, as long as it can be changed to a tensile force due to earth pressure or the like.
【0042】また、図11の補強材71、73はピース
部材9から取り外されることはないが、更に他の実施形
態においては、図12に示すように、ピース部材9から
取り外し可能な補強材75を設けることも可能である。Although the reinforcing members 71 and 73 shown in FIG. 11 are not removed from the piece member 9, in still another embodiment, as shown in FIG. It is also possible to provide.
【0043】すなわち、圧縮力が加わるのは沈設のため
の加圧力が加えられる時のみであり、一旦、立坑5、1
3が構築された後は、シールド掘削機が発進したり到達
したりする時を含めて、大きな圧縮力は加わらない。し
たがって、圧縮力が加わる時にのみ補強材75を設け、
それ以外の時には補強材75を取り外してシールド掘削
機の発進や到達に備えることが可能である。That is, the compressive force is applied only when the pressing force for subsidence is applied.
After 3 is built, no significant compression is applied, including when the shield excavator launches and reaches. Therefore, the reinforcing member 75 is provided only when a compressive force is applied,
At other times, the reinforcements 75 can be removed to prepare for the launch or arrival of the shield excavator.
【0044】図12に示すように発進口11または到達
口15に相当する部分の4枚のピース部材9は、コンク
リート系の切削可能な材料37と、この材料37の周囲
を囲む円形の補強材71を有する。この円形の補強材7
1は、主桁41、継手板43、縦リブ45などと接合さ
れている。更に、円形の補強材71には、上下方向に複
数本の上下補強材75が取り付けられる。すなわち、上
下補強材75の両端と下端は、それぞれ継手板43や縦
リブ45の付近に、ボルト77により取り付けられる。As shown in FIG. 12, the four piece members 9 corresponding to the starting port 11 or the reaching port 15 are made of a concrete-based cuttable material 37 and a circular reinforcing material surrounding the material 37. 71. This circular reinforcement 7
1 is joined to the main girder 41, the joint plate 43, the vertical rib 45, and the like. Further, a plurality of upper and lower reinforcing members 75 are attached to the circular reinforcing member 71 in the vertical direction. That is, both ends and the lower end of the upper and lower reinforcing members 75 are attached to the vicinity of the joint plate 43 and the vertical rib 45 by the bolts 77, respectively.
【0045】このようにして、沈設時の圧縮力はコンク
リート系の材料37よりも、上下補強材75を通って支
えられることとなる。また、圧縮力が加わらなくなった
際には、ボルト77が外され、上下補強材が取り除かれ
ることで、シールド掘削機がコンクリート系の切削可能
な材料37を掘削できるように準備される。In this way, the compressive force at the time of laying is supported by the upper and lower reinforcing members 75 rather than the concrete material 37. When the compressive force is no longer applied, the bolt 77 is removed and the upper and lower reinforcing members are removed, so that the shield excavator is prepared to excavate the concrete-based cuttable material 37.
【0046】また、以上の実施形態においては、切削可
能な材料37はコンクリート系のものであったが、他の
実施形態においては必ずしもコンクリート系のものに限
らず、前記(4)の複合材、(5)の樹脂製のものなど
が考えられる。In the above embodiment, the cuttable material 37 is concrete. However, in other embodiments, the material 37 is not limited to concrete. (5) Resins made of resin are conceivable.
【0047】また、以上の実施形態においては切削可能
な材料37からなるピース部材9以外のピース部材9
は、材料が鋼材の鋼製セグメントピースであったが、他
の実施形態においては、材料が鉄筋コンクリートである
ピース部材とすることも可能であるIn the above embodiment, the piece members 9 other than the piece member 9 made of the cuttable material 37 are used.
Is a steel segment piece made of steel, but in other embodiments, it is also possible to use a piece member made of reinforced concrete.
【0048】また、以上の実施形態においてはピース部
材9の厚さの変化を連続的に行うための傾斜49は、鋼
製セグメントピースの主桁41、継手板43、縦リブ4
5などに施されるものであったが、他の実施形態におい
ては、コンクリートや鉄筋コンクリートを材料とするピ
ース部材の厚さ自体に傾斜を施すものとすることも可能
である。In the above embodiment, the inclination 49 for continuously changing the thickness of the piece member 9 is provided by the main girder 41, the joint plate 43, and the vertical rib 4 of the steel segment piece.
5, but in another embodiment, the thickness itself of the piece member made of concrete or reinforced concrete may be inclined.
【0049】また、以上の実施形態では、切削可能な材
料37は圧縮力に耐えるために厚さを厚くしたり、補強
材71、73、75を設けたが、他の実施形態におい
て、地盤の状態によっては、あまり大きな加圧力を加え
なくても沈設が可能な場合には、厚くしたり、補強材を
設けたりしなくてもよいばあいが考えられる。In the above embodiment, the cuttable material 37 is thickened to withstand the compressive force, and the reinforcing members 71, 73, and 75 are provided. Depending on the state, if the siding can be performed without applying a large pressing force, it may be possible to eliminate the need for thickening or providing a reinforcing material.
【0050】以上の実施形態によれば、発進口11また
は到達口15を形成する切削可能な材料37は、複数の
ピース部材によって分割され、ボルト63などにより連
結されるものであったが、他の実施形態では、そのよう
な分割をせずに、発進口11または到達口15の部分を
独立した丸い形のピース部材とし、周囲の部分を独立し
た特別の形のピース部材とすることもできる。According to the above embodiment, the cuttable material 37 forming the starting port 11 or the reaching port 15 is divided by a plurality of piece members and connected by bolts 63 or the like. In the embodiment, without such division, the portion of the starting port 11 or the arrival port 15 may be formed as an independent round piece member, and the surrounding portion may be formed as an independent special shaped piece member. .
【0051】[0051]
【発明の効果】以上説明したように、第一乃至第三の発
明によれば、複数のピース部材を連結して構成する中空
筒体を、内部の地盤を掘削し、最上端から加圧すること
で地下に沈設して、発進立坑又は到達立坑を構築するの
で、従来のようにH型鋼などを縦方向に配置し、立坑の
周方向に多数を連続させ壁体を構成して立坑を構築する
場合に比べ、工事にかかる時間とコストを低減できる。As described above, according to the first to third aspects of the present invention, a hollow cylindrical body constituted by connecting a plurality of piece members is formed by excavating the inner ground and pressing the hollow cylindrical body from the uppermost end. In order to construct the starting shaft or the reaching shaft, the H-shaped steel is arranged in the vertical direction as before, and a large number is continuously formed in the circumferential direction of the shaft to form a wall to construct the shaft. Compared to the case, the time and cost required for the construction can be reduced.
【0052】また、ピース部材のうち発進口または到達
口に相当する部分のピース部材が切削可能な材料からな
ることにより、地盤改良工事やはつり工事を省略して
も、発進口や到達口において地盤が崩れてしまうという
ことを防止できる。Further, since the portion of the piece member corresponding to the starting port or the reaching port is made of a cuttable material, the ground at the starting port and the reaching port can be obtained even if the ground improvement work or the hanging work is omitted. Can be prevented from collapsing.
【0053】また、第三の発明によれば、さらに、切削
可能なピース部材の材料であるコンクリートの厚さを厚
くすることで、中空筒体を加圧して沈設する際の加圧力
によって生じる圧縮力にも十分に耐えることができる。
また、厚さの変化が連続的に行われるように傾斜を施す
ことで、応力集中が生じるのを防止でき、全体としての
中空筒体の強度を向上できる。According to the third aspect of the present invention, the thickness of the concrete, which is the material of the cuttable piece member, is increased, so that the compression generated by the pressing force when the hollow cylindrical body is laid down is pressed. Can withstand enough force.
In addition, by inclining so that the thickness changes continuously, it is possible to prevent stress concentration from occurring, and to improve the strength of the hollow cylinder as a whole.
【図1】この発明の一実施形態の地下沈設体による立坑
を構築してトンネルを掘削する工事全体の概略工程を示
すものであり(A)は立坑を掘削するためにピース部材
を連結して中空筒体を構成し地上に据え付ける工程を示
す図(B)は中空筒体の内部を掘削し加圧力を加えるこ
とで沈設を行い、ピース部材を継ぎ足して中空筒体の全
長を長くしていく工程を示す図(C)は立坑が完成した
図(D)は完成した立坑を発進立坑としシールド掘削機
を吊り下ろして据え付ける工程を示す図(E)は中空筒
体を構成する切削可能な材料からなるピース部材を切削
してシールド掘削機が発進する工程を示す図(F)はシ
ールド掘削機が所定のコースにしたがってトンネルを掘
削する状態を示す図(G)はシールド掘削機が到達立坑
に到達する工程を示す図(H)はシールド掘削機が到達
立坑の切削可能な材料からなるピース部材を切削して中
空筒体の内部に移動する工程を示す図である。BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 shows a schematic process of an entire construction work for constructing a shaft with an underground buried body and excavating a tunnel according to an embodiment of the present invention. FIG. 1 (A) shows connecting piece members to excavate a shaft. The figure (B) which shows the process which comprises a hollow cylindrical body and installs it on the ground excavates the inside of a hollow cylindrical body, performs squatting by applying a pressurizing force, adds piece members, and lengthens the entire length of a hollow cylindrical body. Figure (C) showing the process is a completed shaft, and Figure (D) is a diagram showing a process in which the completed shaft is used as a starting shaft and a shield excavator is suspended and installed. Figure (E) is a cuttable material forming a hollow cylindrical body. (F) showing a process in which a shield excavator starts by cutting a piece member consisting of (G) is a diagram showing a state in which the shield excavator excavates a tunnel according to a predetermined course, and FIG. The process of reaching To FIG. (H) are diagrams showing the process of moving into the hollow cylindrical body by cutting a piece member shield excavator is made of cuttable material arrival pit.
【図2】図1の(B)を詳細に説明する図である。FIG. 2 is a diagram for explaining FIG. 1B in detail;
【図3】図1の(D)を詳細に説明する図である。FIG. 3 is a diagram for explaining (D) in FIG. 1 in detail;
【図4】図1の(G)を詳細に説明する図である。FIG. 4 is a diagram for explaining (G) of FIG. 1 in detail;
【図5】図3の発進口または図4の到達口を示す水平断
面図である。FIG. 5 is a horizontal sectional view showing the starting port of FIG. 3 or the reaching port of FIG. 4;
【図6】(A)は図3の発進口を中空筒体の内側から示
す正面図(B)は(A)のB部拡大図である。6 (A) is a front view showing the starting port of FIG. 3 from the inside of the hollow cylindrical body, and FIG. 6 (B) is an enlarged view of a portion B of FIG.
【図7】(A)は図4の到達口を中空筒体の外側から示
す正面図(B)は(A)のB部拡大図である。7A is a front view showing the arrival port of FIG. 4 from the outside of the hollow cylindrical body, and FIG. 7B is an enlarged view of a portion B of FIG.
【図8】は図6(B)のVIII部拡大図である。FIG. 8 is an enlarged view of a portion VIII in FIG. 6 (B).
【図9】は図6(B)のIX部拡大図である。FIG. 9 is an enlarged view of an IX part of FIG. 6 (B).
【図10】は図6(B)のX部拡大図である。FIG. 10 is an enlarged view of a part X in FIG. 6 (B).
【図11】他の実施形態を示すもので(A)は発進口ま
たは到達口を中空筒体の内側から示す正面図(B)は
(A)の一部拡大図である。11A and 11B show another embodiment, and FIG. 11A is a front view showing a starting port or a reaching port from the inside of a hollow cylindrical body, and FIG. 11B is a partially enlarged view of FIG.
【図12】更に他の実施形態を示すもので(A)は発進
口または到達口を中空筒体の内側から示す拡大図(平面
的に示した図)(B)は(A)の要部拡大図である。12A and 12B show still another embodiment, in which FIG. 12A is an enlarged view (a plan view) showing a starting port or a reaching port from the inside of a hollow cylindrical body, and FIG. 12B is a main part of FIG. It is an enlarged view.
1 シールド掘削機 5 発進立坑 7 中空筒体 9 ピース部材 13 到達立坑 17 グラウン
ドアンカー 19 アンカワイヤー 21 上部ビー
ム 23 保護リング 25 圧入桁 27 ジャッキ受け台 29 圧入ジャ
ッキ 31 ハンマーグラブバケット 33 ワイヤ 35 所定のルート 37 コンクリート系の切削可能な材料 51 ボルト 53 ナット 55 植え込みナット 57 凹部 59 凸部 61 樹脂製の
植え込みナット 63 樹脂製のボルト 65 作業用孔 71、73 補強材 75 上下補強
材DESCRIPTION OF SYMBOLS 1 Shield excavator 5 Start shaft 7 Hollow cylindrical body 9 Piece member 13 Arrival shaft 17 Ground anchor 19 Anchor wire 21 Upper beam 23 Protective ring 25 Press-fitting girder 27 Jack cradle 29 Press-fit jack 31 Hammer grab bucket 33 Wire 35 Predetermined route 37 Concrete cuttable material 51 Bolt 53 Nut 55 Planted nut 57 Concave portion 59 Convex portion 61 Resin planted nut 63 Resin bolt 65 Work hole 71, 73 Reinforcement material 75 Vertical reinforcement material
───────────────────────────────────────────────────── フロントページの続き (72)発明者 濱田 良幸 愛知県海部郡蟹江町大字蟹江新田字下市場 1 9番地の1 株式会社加藤建設内 (72)発明者 竹田 倫也 愛知県海部郡蟹江町大字蟹江新田字下市場 1 9番地の1 株式会社加藤建設内 ────────────────────────────────────────────────── ─── Continuing on the front page (72) Inventor Yoshiyuki Hamada Kanie-cho, Kaifu-gun, Aichi Prefecture 1-9, Kanie-Nitta-shi Shimo Market, Kato Construction Co., Ltd. (72) Inventor Tomoya Takeda Kanie-cho, Kaifu-gun, Aichi Prefecture Kanie-Shinden-shi, Shimo-shi, 1-9 Kato Construction Co., Ltd.
Claims (3)
空筒体を、 内部を掘削し最上端から加圧することで、地下に沈設し
て構築され、掘削機によりトンネルを掘削する際の発進
立坑または到達立坑とされる地下沈設体であって、 前記ピース部材のうち発進口または到達口に相当する部
分のピース部材が、前記シールド掘削機によって切削可
能な材料からなることを特徴とする地下沈設体。1. A hollow cylindrical body formed by connecting a plurality of piece members is constructed by being buried underground by excavating the inside and pressurizing from the top end, and starting when excavating a tunnel by an excavator. An underground submerged body that is a shaft or an arrival shaft, wherein a piece member of a portion corresponding to a start port or an arrival port of the piece members is made of a material that can be cut by the shield excavator. Sinking body.
クリートであり、他のピース部材の材料が鋼材、または
鉄筋コンクリートであることを特徴とする請求項1記載
の地下沈設体。2. The underground submerged body according to claim 1, wherein the material of the cuttable piece member is concrete, and the material of the other piece members is steel or reinforced concrete.
材の厚さが、鋼材、または鉄筋コンクリートを材料とす
るピース部材の厚さより厚く、両者の間で厚さが変化す
る部分に、該変化が連続的に行われるよう傾斜が施され
たことを特徴とする請求項2記載の地下沈設体。3. The thickness of the piece member made of concrete is larger than the thickness of the piece member made of steel or reinforced concrete, and the change is continuous at a portion where the thickness changes between the two. 3. The underground submerged body according to claim 2, wherein the submerged body is inclined.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP02520098A JP4098871B2 (en) | 1998-01-23 | 1998-01-23 | Underground structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP02520098A JP4098871B2 (en) | 1998-01-23 | 1998-01-23 | Underground structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH11210369A true JPH11210369A (en) | 1999-08-03 |
JP4098871B2 JP4098871B2 (en) | 2008-06-11 |
Family
ID=12159321
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP02520098A Expired - Lifetime JP4098871B2 (en) | 1998-01-23 | 1998-01-23 | Underground structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4098871B2 (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003064995A (en) * | 2001-08-29 | 2003-03-05 | Tokyoto Gesuido Service Kk | Construction method of shield tunnel and segment for opening part |
JP2006225929A (en) * | 2005-02-16 | 2006-08-31 | Sekisui Chem Co Ltd | Segment, and method for constructing tunnel structure by using the segment |
JP2007321537A (en) * | 2006-06-05 | 2007-12-13 | Shimizu Corp | Non-open-pit construction method for tunnel branch confluent |
JP2008019663A (en) * | 2006-07-14 | 2008-01-31 | Maeda Corp | Tunnel construction method |
JP2009191507A (en) * | 2008-02-14 | 2009-08-27 | Fujita Corp | Tunneling method and earth retaining member used therefor |
JP2018135717A (en) * | 2017-02-23 | 2018-08-30 | 積水化学工業株式会社 | Arch segment and segment assembly including the same |
-
1998
- 1998-01-23 JP JP02520098A patent/JP4098871B2/en not_active Expired - Lifetime
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003064995A (en) * | 2001-08-29 | 2003-03-05 | Tokyoto Gesuido Service Kk | Construction method of shield tunnel and segment for opening part |
JP4601878B2 (en) * | 2001-08-29 | 2010-12-22 | 東京都下水道サービス株式会社 | Construction method of shield tunnel and segment for opening |
JP2006225929A (en) * | 2005-02-16 | 2006-08-31 | Sekisui Chem Co Ltd | Segment, and method for constructing tunnel structure by using the segment |
JP2007321537A (en) * | 2006-06-05 | 2007-12-13 | Shimizu Corp | Non-open-pit construction method for tunnel branch confluent |
JP4730608B2 (en) * | 2006-06-05 | 2011-07-20 | 清水建設株式会社 | segment |
JP2008019663A (en) * | 2006-07-14 | 2008-01-31 | Maeda Corp | Tunnel construction method |
JP2009191507A (en) * | 2008-02-14 | 2009-08-27 | Fujita Corp | Tunneling method and earth retaining member used therefor |
JP2018135717A (en) * | 2017-02-23 | 2018-08-30 | 積水化学工業株式会社 | Arch segment and segment assembly including the same |
Also Published As
Publication number | Publication date |
---|---|
JP4098871B2 (en) | 2008-06-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101302743B1 (en) | Phc pile and its using the same soil cement wall construction methode | |
CN109723065A (en) | Deep basal pit freezing partly reinforced construction method in bracing means and rich water sandy pear variety | |
CN101122131B (en) | Foundation pit supporting pile using pipe casting pile embedding in rock | |
JP3876278B2 (en) | Easy-cut tunnel segment structure | |
JP3824114B2 (en) | Whale bone method for large section tunnel | |
JP4098871B2 (en) | Underground structure | |
KR100455247B1 (en) | Cast-in-site diaphragms wall and the method with benoto method and grouting method of high pressure | |
JP2821555B2 (en) | Shaft shaft for shield excavation | |
CN114411781A (en) | Construction method of rock geological sheet pile cofferdam | |
JP2593356B2 (en) | Tunnel construction method | |
KR100432782B1 (en) | Supporting structure for tunnel and underground tunnel construction method using the same | |
JP2697762B2 (en) | Tunnel structure and construction method | |
JP3896003B2 (en) | Connection method and structure of shaft | |
JPH10331569A (en) | Steel segment piece with joint box opened to its outer surface and method for constructing sunk body using the same | |
KR960016755B1 (en) | Working method and working apparatus of underground structure | |
CN217107041U (en) | Underpinning structure for pile foundation in tunnel | |
CN217998366U (en) | Permanent and temporary combined basement structure | |
JP3678463B2 (en) | Starting and reaching shaft for shield machine | |
CN220726302U (en) | Shallow bias tunnel hole entering structure | |
CN116145481B (en) | Arc track slab reinforcement | |
CN208023611U (en) | Steel strand wires oblique pull prestressing force assembled pipe gallery | |
JPH04115024A (en) | Sheathing method | |
JP3698505B2 (en) | Underground cylinder drawing method and split ring used in the method | |
KR200247005Y1 (en) | Cast-in-site diaphragms wall with benoto method and grouting method of high pressure | |
JP4275296B2 (en) | A sinking body having an opening forming portion structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20041119 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20061205 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20070201 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20070424 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20070622 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20071127 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20080122 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20080219 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20080314 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110321 Year of fee payment: 3 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |