JPH11131585A - Building frame body structure and construction method thereof - Google Patents
Building frame body structure and construction method thereofInfo
- Publication number
- JPH11131585A JPH11131585A JP30126397A JP30126397A JPH11131585A JP H11131585 A JPH11131585 A JP H11131585A JP 30126397 A JP30126397 A JP 30126397A JP 30126397 A JP30126397 A JP 30126397A JP H11131585 A JPH11131585 A JP H11131585A
- Authority
- JP
- Japan
- Prior art keywords
- column member
- column
- pillar
- erected
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、建築物の躯体を構
築するときに用いて好適な躯体構造およびその構築方法
に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a frame structure suitable for use in building a frame of a building and a method of building the same.
【0002】[0002]
【従来の技術】従来より、建築物の躯体を効率良く構築
するための工法として、柱等の鉛直部材と梁等の水平部
材とを別々に交互に構築していく、いわゆるVH工法と
称されるものがある。2. Description of the Related Art Conventionally, as a construction method for efficiently constructing a building frame of a building, a so-called VH construction method, in which vertical members such as columns and horizontal members such as beams are separately and alternately constructed, is referred to as a VH method. There is something.
【0003】これは、図9に示すように、例えば柱1を
鉄筋コンクリート造(以下、「RC造」と称する)と
し、梁2を鉄骨造(以下、「S造」と称する)とする場
合には、まず、図9(a)に示すように、柱1を構成す
る鉄筋3を、その下端部を基礎コンクリート4中に埋設
して設置した後、図9(b)に示すように型枠5を組
み、この型枠5内にコンクリート6を打設することによ
ってRC造の柱1を構築する。このとき、柱1と基礎コ
ンクリート4とは剛接合されることとなる。この後、図
9(c)に示すように、このように所定間隔ごとに構築
した柱1,1間にS造の梁2をセットし、連続する梁
2,2どうしを柱1の頭部上で接合することによって躯
体を構築していく。また、柱1の頭部に梁接合用のブラ
ケットを取り付け、このブラケットを介して梁2どうし
を連続的に接合することもある。For example, as shown in FIG. 9, when the column 1 is made of reinforced concrete (hereinafter, referred to as "RC structure") and the beam 2 is made of steel frame (hereinafter, referred to as "S structure"). First, as shown in FIG. 9 (a), a reinforcing bar 3 constituting a pillar 1 is installed with its lower end buried in a foundation concrete 4, and then a formwork is formed as shown in FIG. 9 (b). 5 and cast concrete 6 into the formwork 5 to construct the RC column 1. At this time, the column 1 and the foundation concrete 4 are rigidly joined. Thereafter, as shown in FIG. 9C, an S-shaped beam 2 is set between the columns 1, 1 constructed at predetermined intervals in this manner, and the continuous beams 2, 2 are connected to each other by the head of the column 1. The skeleton is built by joining on top. In some cases, a beam joining bracket is attached to the head of the column 1 and the beams 2 are continuously joined via the bracket.
【0004】本出願人は、このような技術として、例え
ば特公昭61−18620号公報に示すような技術を既
に提案し、実用化している。The present applicant has already proposed and put to practical use such a technique as disclosed in Japanese Patent Publication No. 61-18620, for example.
【0005】[0005]
【発明が解決しようとする課題】しかしながら、上述し
たような従来の技術には以下のような問題が存在する。
まず、先行して構築した柱1上に梁2を架設するに際し
ては、各柱1の頭部のレベルが違うと、連続する梁2,
2どうしが突き合わされる部分で段差が生じて梁2,2
どうしの接合が困難になったり、また梁2が斜めになっ
て柱1の頭部の上面もしくは梁接合用のブラケットに確
実に接合できない等の問題が生じる。このため、各柱1
の頭部上において梁2との取合いレベル調整しなければ
ならず、足場の組払いの手間等も余計に係るため、これ
によって柱1の施工に手間がかかってしまう。However, the above-mentioned conventional techniques have the following problems.
First, when erection of the beam 2 on the column 1 constructed in advance, if the level of the head of each column 1 is different,
2 A step is generated at the part where the two meet, and the beams 2 and 2
There are problems such as difficulty in joining together, and the fact that the beam 2 is inclined and cannot be securely joined to the upper surface of the head of the column 1 or the beam joining bracket. Therefore, each pillar 1
It is necessary to adjust the level of engagement with the beam 2 on the head of the vehicle, and the labor of assembling the scaffolding and the like is also extra. Therefore, the construction of the pillar 1 is troublesome.
【0006】また、柱1をRC造に代えてプレキャスト
コンクリート造(以下、「PC造」と称する)とする場
合、柱1の頭部のレベルを高い精度で合わせるには、こ
のPC造の柱1を立設する基礎コンクリート4のレベル
を高い精度で均さなければならない。しかも柱1を当然
のことながら鉛直に建入れる必要があるため、基礎コン
クリート4の水平出しを行わなければならず、この結
果、より手間がかかることとなる。しかも、PC造の柱
1は、基礎コンクリート4に確実に固定するため、基礎
コンクリート4に埋設したアンカー筋等に接合しなけれ
ばならず、その接合作業にも手間がかかる。When the pillar 1 is made of a precast concrete structure (hereinafter referred to as "PC structure") instead of the RC structure, it is necessary to adjust the level of the head of the column 1 with high precision by using the PC structure. The level of the foundation concrete 4 for erection 1 must be leveled with high precision. Moreover, since it is necessary to install the column 1 vertically, the foundation concrete 4 must be leveled out. As a result, it takes more time and effort. Moreover, in order to securely fix the PC-made column 1 to the foundation concrete 4, it is necessary to join it to anchor bars or the like buried in the foundation concrete 4, and the joining work also takes time.
【0007】本発明は、以上のような点を考慮してなさ
れたもので、躯体を構成する柱梁を容易かつ確実に構築
することのできる躯体構造およびその構築方法を提供す
ることを課題とする。SUMMARY OF THE INVENTION The present invention has been made in view of the above points, and has as its object to provide a skeleton structure capable of easily and surely constructing a beam and column constituting a skeleton and a method of constructing the same. I do.
【0008】[0008]
【課題を解決するための手段】請求項1に係る発明は、
躯体を構成する柱が、その下端部の所定長さをコンクリ
ート中に埋め込むことによって立設され、前記柱の頭部
に架設された梁が、該柱の頭部から側方に張り出した位
置で他の梁に接合されていることを特徴としている。The invention according to claim 1 is
The pillars constituting the skeleton are erected by embedding a predetermined length of the lower end portion thereof in concrete, and the beams erected at the heads of the pillars project from the heads of the pillars sideways. It is characterized by being joined to another beam.
【0009】請求項2に係る発明は、躯体の柱を構成す
る柱部材を所定の位置に立てた後、該柱部材を建入れ調
整し、この状態で前記柱部材の下端部にコンクリートを
打設して該柱部材を固定し、しかる後に該柱部材の頭部
に梁を架設することを特徴としている。According to a second aspect of the present invention, after the pillar members constituting the pillars of the skeleton are set at predetermined positions, the pillar members are adjusted for installation, and in this state, concrete is poured into the lower end of the pillar members. And fixing the column member, and thereafter, a beam is erected on the head of the column member.
【0010】請求項3に係る発明は、請求項2記載の躯
体の構築方法において、前記柱部材を立てるに際し、前
記柱部材を立てるべきベースの高さレベルを調整した
後、前記ベース上に前記柱部材を立てることを特徴とし
ている。According to a third aspect of the present invention, in the method for constructing a skeleton according to the second aspect, when the pillar member is erected, the height level of the base on which the pillar member is to be erected is adjusted, and then the base member is laid on the base. It is characterized by erecting a column member.
【0011】請求項4に係る発明は、請求項2または3
記載の躯体の構築方法において、前記柱部材の下端部に
下方に突出する脚部を形成しておき、前記コンクリート
を打設したときに前記柱部材の下端部の下方に前記コン
クリートが回るようにしておくことを特徴としている。[0011] The invention according to claim 4 is the invention according to claim 2 or 3.
In the method for constructing a skeleton according to the above, a leg protruding downward is formed at a lower end of the column member so that the concrete turns below the lower end of the column member when the concrete is poured. It is characterized by keeping.
【0012】請求項5に係る発明は、躯体の柱を構成す
る柱部材を所定の位置に建て込んだ後、該柱部材の頭部
に、梁を、その端部が前記柱部材から側方に張り出すよ
うセットした後、梁と、他の柱部材の頭部上にセットし
た他の梁とを接続し、しかる後に、前記梁を前記柱部材
に固定することを特徴としている。According to a fifth aspect of the present invention, after a pillar member constituting a pillar of a skeleton is erected at a predetermined position, a beam is provided on a head of the pillar member, and an end of the beam is laterally located from the pillar member. After the beam is set to overhang, the beam is connected to another beam set on the head of another column member, and then the beam is fixed to the column member.
【0013】[0013]
【発明の実施の形態】以下、本発明に係る躯体構造およ
びその構築方法の実施の形態の一例を、図1ないし図8
を参照して説明する。ここでは、例えば柱をPC造と
し、梁をS造とする場合の例を用いて説明する。これら
の図において、符号10は躯体を構成する柱、11は
梁、12は躯体の基礎である。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of a skeleton structure and a method of constructing the same according to the present invention will be described below with reference to FIGS.
This will be described with reference to FIG. Here, for example, an example in which the pillar is made of PC and the beam is made of S will be described. In these figures, reference numeral 10 denotes a column constituting a skeleton, 11 denotes a beam, and 12 denotes a foundation of the skeleton.
【0014】図1(a)に示すように、躯体を構築する
には、まず、地盤を根切りして柱10を立設するための
例えば平面視矩形の凹部13を形成する。次いで、凹部
13内に基礎12を形成するための型枠14を組み立
て、この型枠14内に、基礎12の下層部と上層部との
一体化を図るためのベース鉄筋15を配筋する。これら
ベース鉄筋15のうちには、柱10の建入れ調整に用い
るベース鉄筋15Aがあり、これには鉛直上方に延出す
るアンカー部16が形成されている。As shown in FIG. 1 (a), in order to construct a skeleton, first, for example, a rectangular recessed portion 13 in a plan view for forming a pillar 10 by cutting the ground is formed. Next, a formwork 14 for forming the base 12 in the recess 13 is assembled, and a base reinforcing bar 15 for integrating the lower layer and the upper layer of the base 12 is arranged in the formwork 14. Among these base reinforcing bars 15, there is a base reinforcing bar 15A used for adjusting the installation of the pillar 10, and an anchor portion 16 extending vertically upward is formed on the base reinforcing bar 15A.
【0015】図1(b)に示すように、ベース鉄筋15
を配筋した後、型枠14内にコンクリートC1を所定レ
ベルまで打設する。これとともに、型枠14の外周部に
は、土砂Dを埋め戻す。図1(c)に示すように、コン
クリートC1が硬化して基礎12の下層部を形成する基
礎マット12aが形成された後、その上面にモルタルを
盛り、ベースモルタル(ベース)17を形成する。この
ベースモルタル17は、その上面を設計値に対して例え
ば±2mm以内の精度のレベルで平滑に均す。[0015] As shown in FIG.
After the reinforcing bars are arranged, the concrete C1 is poured into the formwork 14 to a predetermined level. At the same time, earth and sand D are buried in the outer peripheral portion of the formwork 14. As shown in FIG. 1 (c), after the concrete C1 has hardened to form the foundation mat 12a which forms the lower layer of the foundation 12, mortar is put on the upper surface to form a base mortar (base) 17. The base mortar 17 smoothes the upper surface thereof at a level of accuracy within, for example, ± 2 mm with respect to a design value.
【0016】図2(a)に示すように、ベースモルタル
17が硬化した後、このベースモルタル17上には柱1
0を構成する柱部材18を吊り込んで立てる。図3に示
すように、この柱部材18は予め工場や現場近傍の作業
所等で所定形状に形成されたPC造で、その下端部には
四隅から下方に所定寸法突出する脚部19,19,…が
形成され、天端面には例えば4本の梁固定用ボルト20
が上方に突出するよう設けられている。図2(a)に示
したように、このような柱部材18をベースモルタル1
7状に立てると、下端部に設けられた脚部19,19,
…により、ベースモルタル17と柱部材18の底部との
間には空洞Sができるようになっている。After the base mortar 17 has hardened, as shown in FIG.
The column member 18 that constitutes 0 is hung upright. As shown in FIG. 3, the column member 18 is made of PC which is formed in a predetermined shape in a factory or a work place near the site in advance, and has legs 19, 19 projecting downward from four corners by a predetermined size at the lower end thereof. Are formed on the top end face, for example, four beam fixing bolts 20.
Are provided so as to protrude upward. As shown in FIG. 2A, such a column member 18 is connected to the base mortar 1.
Standing in a seven shape, the legs 19, 19,
, A cavity S is formed between the base mortar 17 and the bottom of the column member 18.
【0017】続いて、ベースモルタル17上にセットし
た柱部材18を建入れ調整する。これには、柱部材18
の上端部に設けられた四本の梁固定用ボルト20と、そ
の四方に基礎12から上方に延出するよう設けられてい
るベース鉄筋15Aのアンカー部16との間に、それぞ
れ建入れ調整用ワイヤー21をかける。この建入れ調整
用ワイヤー21にはターンバックル22が備えられてお
り、その長さを調整できるようになっているので、四方
の建入れ調整用ワイヤー21の長さをそれぞれ調整する
ことによって、柱部材18を鉛直に建入れ調整する。こ
のときに、柱部材18の脚部19,19,…がベースモ
ルタル17から持ち上がることもあるが、2本以上の脚
部19がベースモルタル17に設置していれば何ら問題
はない。Subsequently, the column member 18 set on the base mortar 17 is inserted and adjusted. This includes column members 18
Between the four beam fixing bolts 20 provided at the upper end of the base member and the anchor portions 16 of the base reinforcing bars 15A provided to extend upward from the foundation 12 on all sides thereof. Hang the wire 21. The installation adjustment wire 21 is provided with a turn buckle 22 and the length thereof can be adjusted. By adjusting the lengths of the four installation adjustment wires 21, respectively, The member 18 is inserted vertically and adjusted. At this time, the legs 19 of the pillar member 18 may be lifted from the base mortar 17, but there is no problem if two or more legs 19 are installed on the base mortar 17.
【0018】図2(b)に示すように、柱部材18の建
入れ調整完了後、型枠14内にコンクリートC2を打設
する。すると、このコンクリートC2中に柱部材18の
下端部の所定長が埋め込まれることとなる。そして、コ
ンクリートC2が硬化し、基礎上層部12bが形成され
ることによって、柱部材18と基礎12とが一体化され
る。このとき、柱部材18の脚部19,19,…により
ベースモルタル17と柱部材18の底部との間には空洞
Sが形成されているので、この空洞Sにもコンクリート
C2が回り込み、これによって、建入れ調整により柱部
材18がベールモルタル17から持ち上がっていたとし
ても、これを基礎12に確実に接合することができるよ
うになっている。As shown in FIG. 2B, after the adjustment of the column members 18 is completed, concrete C2 is poured into the formwork 14. Then, a predetermined length of the lower end portion of the column member 18 is embedded in the concrete C2. Then, the concrete member C2 is hardened and the foundation upper layer portion 12b is formed, whereby the column member 18 and the foundation 12 are integrated. At this time, since the cavity S is formed between the base mortar 17 and the bottom of the column member 18 by the legs 19, 19,... Of the column member 18, the concrete C2 also wraps around the cavity S. Even if the column member 18 is lifted from the bale mortar 17 due to the adjustment of the installation, it can be securely joined to the foundation 12.
【0019】コンクリートC2が硬化し、柱部材18が
自立可能となった時点で、建入れ調整用ワイヤー21,
21,…を取り外す。When the concrete C2 is hardened and the column member 18 becomes self-supporting, the construction adjusting wires 21 and
21, ... are removed.
【0020】図4および図5に示すように、このように
して各柱10を構築すべき位置に、柱部材18を順次建
て込んでいく。As shown in FIGS. 4 and 5, the column members 18 are sequentially built at the positions where the respective columns 10 are to be built.
【0021】そして、所定の位置に建て込んだ柱部材1
8上には梁11を架設する。これにはまず、一方向に沿
って列設された柱部材18,18,…上に梁鉄骨(梁)
25を架設していく。Then, the column member 1 built at a predetermined position
A beam 11 is erected on 8. First of all, a beam steel frame (beam) is placed on the column members 18, 18, ... arranged in one direction.
25 will be erected.
【0022】まず、図4に示したように、躯体の一端部
に位置する柱部材18Aと、これに隣接する柱部材18
Bとに、柱鉄骨25Aを架設する。この梁鉄骨25A
は、柱部材18A,18B間のスパンよりも所定寸法長
くなっており、その一端を柱部材18A上に位置させる
と、他端が柱部材18Bから所定寸法張り出すようにな
っている。図6に示すように、この柱鉄骨25Aは、そ
の下部フランジの所定位置に予め形成されたボルト穴
に、柱部材18A,18Bの梁固定用ボルト20を挿通
させ、これをナット26で仮固定する。このとき、この
梁鉄骨25Aは、この後に接合する梁鉄骨25Bとの接
合作業を容易とするため、梁鉄骨25Aが若干動くよう
に、ナット26を完全には締め付けないでおく。First, as shown in FIG. 4, a column member 18A located at one end of the frame and a column member 18 adjacent thereto are disposed.
B, a column steel frame 25A is erected. This beam steel frame 25A
Is longer than the span between the column members 18A and 18B by a predetermined dimension, and when one end thereof is positioned on the column member 18A, the other end projects from the column member 18B by a predetermined size. As shown in FIG. 6, in the column steel frame 25A, the beam fixing bolts 20 of the column members 18A and 18B are inserted into bolt holes formed at predetermined positions of the lower flange thereof, and these are temporarily fixed with the nuts 26. I do. At this time, the nut 26 is not completely tightened so that the beam steel 25A slightly moves, in order to facilitate the joining operation of the beam steel 25A to be subsequently joined with the beam steel 25A.
【0023】次いで、図4に示したように、柱部材18
Bに隣接する柱部材18C上に梁鉄骨25Bをセットす
る。この梁鉄骨25Bは、柱部材18B,18C間のス
パンと略同じ長さを有しており、その一端を先にセット
した梁鉄骨25Aに突き合わせると、他端が柱部材18
Cから所定寸法張り出すようになっている。図6に示し
たように、この梁鉄骨25Bは、梁鉄骨25Aと同様、
所定位置に形成されたボルト穴に、柱部材18Cの梁固
定用ボルト20を挿通させ、これをナット26で仮固定
する。Next, as shown in FIG.
The beam steel 25B is set on the column member 18C adjacent to B. This beam steel frame 25B has substantially the same length as the span between the column members 18B and 18C. When one end of the beam steel frame 25B is brought into contact with the previously set beam steel frame 25A, the other end thereof becomes the column member 18B.
A predetermined dimension is projected from C. As shown in FIG. 6, this beam steel frame 25B is similar to the beam steel frame 25A.
The beam fixing bolt 20 of the column member 18C is inserted into a bolt hole formed at a predetermined position, and is temporarily fixed with a nut 26.
【0024】そして、柱部材18Bから所定寸法張り出
した位置で互いに突き合わされた梁鉄骨25A,25B
を、ジョイントプレート27,ボルト・ナット28等の
接合手段で接合する。このようにして梁鉄骨25A,2
5Bを接合した後、梁鉄骨25Aを、各ナット26を締
め込むことによって柱部材18Aに本固定する。Then, the beam steel members 25A, 25B butted against each other at a position where they are projected from the column member 18B by a predetermined dimension.
Are joined by joining means such as a joint plate 27 and a bolt / nut 28. In this way, the beam steel 25A, 2
After joining 5B, the beam steel frame 25A is permanently fixed to the column member 18A by tightening the nuts 26.
【0025】図4に示したように、この後は、他方の柱
部材18E側に向けて、順次、梁鉄骨25の仮固定,
柱部材18から所定寸法張り出した位置における梁鉄
骨25どうしの接合,梁鉄骨25の本固定、という工
程を繰り返して、梁鉄骨25を一本ずつ架設していく。
なお、躯体の他端部に位置する柱部材18Eに架設され
る梁鉄骨25Dは、一端が柱部材18Dから所定寸法張
り出した位置に位置し、他端が柱部材18E上に位置す
るような長さを有している。As shown in FIG. 4, thereafter, the beam steel 25 is temporarily fixed and sequentially moved toward the other column member 18E.
By repeating the steps of joining the beam steel members 25 at positions protruding from the column members 18 by a predetermined dimension and permanently fixing the beam steel members 25, the beam steel members 25 are erected one by one.
The beam steel frame 25D bridged over the column member 18E located at the other end of the skeleton has a length such that one end is located at a position protruding a predetermined dimension from the column member 18D, and the other end is located on the column member 18E. Have.
【0026】図5に示したように、このようにして、一
方向に沿って列設された各列の柱部材18,18,…上
に梁鉄骨25を架設した後、これら梁鉄骨25と直交す
る方向に延在する梁鉄骨30を架設する。この梁鉄骨3
0は、通常と同様、柱部材18,18間のスパンと略同
じ長さを有している。図7に示すように、梁鉄骨30
は、各柱部材18の頭部において、先に架設された梁鉄
骨25に一体に取り付けられているジョイントブラケッ
ト31に、ボルト・ナット32等の接合手段によって接
合されるようになっている。また、各梁鉄骨30の端部
の下部フランジ30aとウェブ30bには、柱部材18
の上端部との干渉を回避する切欠き33が形成されてい
る。As shown in FIG. 5, after the beam steel members 25 are erected on the column members 18, 18,... A beam steel frame 30 extending in a direction perpendicular to the direction is erected. This beam steel frame 3
0 has the same length as the span between the column members 18 as usual. As shown in FIG.
In the head of each column member 18, a joint bracket 31 integrally attached to the beam steel frame 25 erected earlier is joined by joining means such as bolts and nuts 32. The lower flange 30a and the web 30b at the end of each beam steel frame 30 have column members 18 attached thereto.
A notch 33 is formed to avoid interference with the upper end portion.
【0027】図5に示したように、梁鉄骨30の架設完
了後、互いに隣接する梁鉄骨30,30間に、これと直
交して延在する小梁35,35を架設することによっ
て、躯体の1フロア分の構築が完了する。この後は、架
設した梁鉄骨25,30上に屋根材や天井材(図示な
し)を設け、さらに必要に応じ、上記作業を繰り返して
躯体の2階以上を積み上げ構築しても良い。As shown in FIG. 5, after the completion of the installation of the beam steel structure 30, small beams 35, 35 extending perpendicularly to the beam steel structures 30, 30 adjacent to each other are installed between the adjacent beam steel structures 30, 30, thereby forming the frame. Is completed for one floor. Thereafter, a roofing material or a ceiling material (not shown) may be provided on the erected beam steel frames 25, 30 and, if necessary, the above operation may be repeated to build up the second or higher floor of the skeleton.
【0028】ところで、上記構成において、施工時にお
けるベースモルタル17のレベル誤差を±2mm、柱部
材18自体の長さの寸法誤差を±2mmとすると、これ
らの誤差は柱部材18の頭部に集中することとなる。こ
のとき、互いに隣接する柱部材18,18において、誤
差が最大となる場合について検討してみる。By the way, in the above configuration, if the level error of the base mortar 17 at the time of construction is ± 2 mm and the dimensional error of the length of the column member 18 itself is ± 2 mm, these errors are concentrated on the head of the column member 18. Will be done. At this time, consider a case where the error is maximized in the column members 18 adjacent to each other.
【0029】まず、図8(a)に示すように、図中左側
に位置する柱部材18の頭部の誤差(許容誤差)が、ベ
ースモルタル17(図1参照)で+2mm、柱部材18
自体の寸法誤差で+2mm、合計+4mm(プラス側最
大誤差)となり、図中右側に位置する柱部材18の頭部
の誤差が、ベースモルタル17で−2mm、柱部材18
自体の寸法誤差で−2mm、合計−4mm(マイナス側
最大誤差)となった場合には、左側の柱部材18と右側
の柱部材18との頭部のレベル差は8mmとなる。この
とき、右側の柱部材18から大きく張り出した梁鉄骨2
5は、その自重により先端部25aが下方に撓む。その
撓み量δは、ω;等分布荷重,L;スパン,E;ヤング
係数,I;断面二次モーメント、とすると、 δ=ω・L4/(8・E・I) で表される。ここで、ω=90kg/m、梁鉄骨25の
柱部材18からの張出しスパンL=850cm、H型鋼
である梁鉄骨25のサイズH−500×200、断面二
次モーメントI=47000cm4とすると、 δ=約6mm となる。すると、図中左側の梁鉄骨25と右側の梁鉄骨
25との接合部において、上下方向の梁鉄骨25,25
のレベル差は、最大14mmとなる。First, as shown in FIG. 8A, the error (tolerance) of the head of the column member 18 located on the left side in the figure is +2 mm in the base mortar 17 (see FIG. 1), and the column member 18
The dimensional error of itself is +2 mm, and the total is +4 mm (the maximum error on the plus side). The error of the head of the column member 18 located on the right side in the figure is -2 mm in the base mortar 17,
If the dimensional error of the head itself is −2 mm, and the total is −4 mm (minus side maximum error), the head level difference between the left pillar member 18 and the right pillar member 18 is 8 mm. At this time, the beam steel frame 2 protruding greatly from the right column member 18
In No. 5, the tip portion 25a bends downward due to its own weight. The bending amount δ is expressed as follows: δ = ω · L 4 / (8 · E · I), where ω: uniform distribution load, L: span, E: Young's modulus, I: second moment of area. Here, assuming that ω = 90 kg / m, the overhang span L of the beam steel member 25 from the column member 18 is 850 cm, the size of the beam steel member 25 as an H-section steel is H−500 × 200, and the second moment of area I = 47000 cm 4 , δ = about 6 mm. Then, at the joint between the left beam steel frame 25 and the right beam steel frame 25 in the figure, the vertical beam steel frames 25
Is a maximum of 14 mm.
【0030】一方、図8(b)に示すように、図中左側
に位置する柱部材18の頭部の誤差(許容誤差)が、ベ
ースモルタル17(図1参照)で−2mm、柱部材18
自体の寸法誤差で−2mm、合計−4mm(マイナス側
最大誤差)となり、図中右側に位置する柱部材18の頭
部の誤差が、ベースモルタル17で+2mm、柱部材1
8自体の寸法誤差で+2mm、合計+4mm(プラス側
最大誤差)となった場合に、左側の柱部材18と右側の
柱部材18との頭部のレベル差は8mm、図中右側の梁
鉄骨25の先端部25aにおける撓み量δは約6mmで
あるので、左右の梁鉄骨25,25の接合部におけるレ
ベル差は最大2mmとなる。On the other hand, as shown in FIG. 8B, the error (allowable error) of the head of the column member 18 located on the left side in the figure is -2 mm in the base mortar 17 (see FIG. 1), and
The dimensional error of itself is −2 mm, the total is −4 mm (minus side maximum error), and the error of the head of the column member 18 located on the right side in the drawing is +2 mm in the base mortar 17 and the column member 1
When the dimensional error of the 8 itself is +2 mm and the total is +4 mm (maximum error on the plus side), the level difference between the heads of the left column member 18 and the right column member 18 is 8 mm, and the right beam steel frame 25 in the figure. Is about 6 mm at the distal end portion 25a, so that the level difference at the joint between the left and right beam steel frames 25, 25 is 2 mm at the maximum.
【0031】このようにして、柱部材18から所定寸法
張り出した位置で接合される梁鉄骨25,25のレベル
差は最大でも14mm程度であり、この程度のレベル差
であれば、梁鉄骨25,25どうしを接合した後、各梁
鉄骨25を柱部材18に本固定することによって、梁鉄
骨25と柱部材18との接合、および梁鉄骨25,25
どうしの接合を何ら問題なく進めることができる。In this way, the level difference between the beam steel members 25, 25 joined at the position where they are extended by a predetermined dimension from the column member 18 is at most about 14 mm. After joining the beam members 25 to each other, the beam steel members 25 are permanently fixed to the column members 18, thereby joining the beam steel members 25 to the column members 18 and the beam steel members 25, 25.
The joining between the members can proceed without any problem.
【0032】上述したように、柱部材18をベースモル
タル17上に吊り込んで立てた後、柱部材18を建入れ
調整し、この状態で柱部材18の下端部にコンクリート
C2を打設して柱部材18を固定し、しかる後に柱部材
18の頭部に梁鉄骨25を架設する構成となっている。
このようにして、柱部材18の下端部をコンクリートC
2に埋め込んで固定することにより、従来のような剛接
合,ピン接合を用いる必要がなくなり、アンカーボルト
も不要となることから、柱部材18の施工を、吊り込み
・建入れ調整・コンクリートC2の打設といった工程の
みで、非常に容易に行うことができる。As described above, after the column member 18 is hung on the base mortar 17 and erected, the column member 18 is adjusted for installation, and in this state, concrete C2 is poured into the lower end of the column member 18. The column member 18 is fixed, and after that, a beam steel frame 25 is erected on the head of the column member 18.
In this way, the lower end of the column member 18 is
By embedding and fixing in the concrete 2, there is no need to use rigid joints and pin joints as in the past, and anchor bolts are not required. It can be performed very easily only by the step of casting.
【0033】しかも、柱部材18を建入れ調整した状態
で、その下端部にコンクリートC2を打設して固めるこ
とによって、柱部材18を高い精度で建て込むことがで
きる。加えて、柱部材18の基礎12を構成する基礎マ
ット12aのベース鉄筋15を、建入れ調整時のアンカ
ーとして利用することにより、建入れ調整のための部材
等をわざわざ別途設置する必要もなく、この点において
も施工の容易化を図ることができる。Moreover, the concrete member C2 is cast at the lower end portion of the column member 18 in a state where the column member 18 is adjusted and set, and the column member 18 can be built with high accuracy. In addition, by using the base reinforcing bar 15 of the base mat 12a constituting the base 12 of the column member 18 as an anchor at the time of adjusting the installation, there is no need to separately install a member or the like for adjusting the installation. In this respect, the construction can be facilitated.
【0034】また、ベースモルタル17により基礎マッ
ト12a上の高さレベルを調整した後、柱部材18を立
てる構成となっている。これにより、柱部材18の柱頭
におけるレベル調整を不要とすることができ、足場の組
払い等も不要となるため手間を大幅に省くことができ、
施工の容易化、効率化を図ることができる。After adjusting the height level on the base mat 12a by the base mortar 17, the column member 18 is erected. As a result, the level adjustment at the capital of the column member 18 can be made unnecessary, and the scaffolding and the like become unnecessary, so that labor can be largely saved,
Easy and efficient construction can be achieved.
【0035】さらに、柱部材18の下端部に脚部19を
形成しておくことによって、コンクリートC2を打設し
たときに柱部材18の下方にコンクリートC2が確実に
回り込み、これにより、柱部材18の下面に隙間が生じ
ることなく、下面全面を確実に基礎マット12a上のベ
ースモルタル17に密着させることができ、したがって
柱部材18に作用する鉛直力を確実かつ効率よく下方の
基礎12に伝達することが可能となる。Further, by forming the leg portion 19 at the lower end of the column member 18, the concrete C2 surely goes under the column member 18 when the concrete C2 is cast. The lower surface of the base member 12 can be securely brought into close contact with the base mortar 17 on the base mat 12a without any gap on the lower surface of the base member 12, and therefore the vertical force acting on the column member 18 can be transmitted to the lower base 12 reliably and efficiently. It becomes possible.
【0036】また、梁11を架設するに際しては、柱部
材18の頭部に、梁鉄骨25の端部を柱部材18から側
方に張り出させてセットした後、この梁鉄骨25と他の
梁鉄骨25とを接続し、しかる後に、梁鉄骨25を柱部
材18に本固定する構成となっている。このようにして
梁鉄骨25を仮固定した状態で接続することにより、ベ
ースモルタル17のレベル誤差、柱部材18自体の寸法
誤差等を吸収することができる。しかも梁鉄骨25のオ
ーバーハング部分の撓みも利用することができるため、
寸法誤差の吸収をより容易に行うことができる。When the beam 11 is erected, the end of the beam steel member 25 is set on the head of the column member 18 so as to project laterally from the column member 18, and then the beam steel member 25 and other members are set. The beam steel frame 25 is connected, and after that, the beam steel frame 25 is permanently fixed to the column member 18. By connecting the beam steel 25 temporarily in this manner, it is possible to absorb the level error of the base mortar 17, the dimensional error of the column member 18 itself, and the like. Moreover, since the deflection of the overhang portion of the beam steel frame 25 can also be used,
The dimensional error can be more easily absorbed.
【0037】なお、上記実施の形態においてあげた各構
成は、本願発明の主旨を逸脱しない範囲内であれば、他
のいかなる構成であっても採用することができる。例え
ば、ベースモルタル17については、柱部材18を立て
る位置のレベル調整ができるのであれば、例えばボルト
等の点状のもの、あるいはライナー鉄板等の面状のも
の、ペースト状の樹脂を均して硬化させたもの等、他の
ものが適宜採用できる。また、柱部材18の脚部19に
ついても、柱部材18の全面積下にコンクリートC2を
回り込ませることができるのであれば、例えば金属等の
他の材料で形成しても良いし、またその脚数、位置等を
変えてもよい。もちろん、脚部19の形状や長さも、用
いる充填材や充填方法等に応じて最適なものとすればよ
い。柱部材18の頭部に梁固定用ボルト20を設ける構
成としたが、柱部材18と梁鉄骨25とを溶接、接着、
コンクリート巻き等、他の接合手段で接合するのであれ
ば、それに応じたものを配設すればよい。また、柱部材
18の頭部において、ライナー鉄板,均しモルタル等に
よってレベル調整するようにしてもよい。It is to be noted that each of the configurations described in the above-described embodiment can employ any other configuration without departing from the gist of the present invention. For example, as for the base mortar 17, if the level of the position where the column member 18 is erected can be adjusted, for example, a point-like material such as a bolt, a planar material such as a liner iron plate, or a paste-like resin is leveled. Others such as cured ones can be employed as appropriate. Further, the leg 19 of the column member 18 may be formed of another material such as a metal, for example, as long as the concrete C2 can be wrapped under the entire area of the column member 18. The number, position, etc. may be changed. Of course, the shape and length of the leg 19 may be optimal depending on the filler used, the filling method, and the like. Although the beam fixing bolt 20 is provided on the head of the column member 18, the column member 18 and the beam steel frame 25 are welded, bonded,
If it is to be joined by other joining means such as concrete winding or the like, an appropriate one may be provided. Also, at the head of the column member 18, the level may be adjusted with a liner iron plate, leveling mortar, or the like.
【0038】さらに、柱部材18の下端部を固定するた
めのコンクリートC2について、上記実施の形態では、
地盤内に形成した凹部13に充填する構成としたが、例
えば柱部材18の下端部を囲んで巻き付けるようにコン
クリートC2を打設しても良い。また、このコンクリー
トC2に代えて、要求強度が確保できるのであれば、例
えば樹脂等、他の材料を用いても良い。加えて、このコ
ンクリートC2を打設するための型枠14をそのまま埋
め込んでしまう埋込型枠としたが、もちろん、これを転
用可能とすることもできる。さらにコンクリートC2を
打設する範囲については、必ずしも基礎マット12aに
合わせる必要はなく、より小さくしても良い。Further, regarding the concrete C2 for fixing the lower end of the column member 18, in the above embodiment,
Although the recess 13 is formed in the ground, the concrete C2 may be cast so as to be wound around the lower end of the column member 18, for example. Further, in place of the concrete C2, another material such as a resin may be used as long as the required strength can be secured. In addition, although the embedding formwork for embedding the formwork 14 for casting the concrete C2 is used as it is, of course, it can be diverted. Further, the area in which the concrete C2 is cast does not necessarily need to be adjusted to the foundation mat 12a, and may be smaller.
【0039】さらに加えて、上記実施の形態では、基礎
マット12aをコンクリートC1で形成する構成とした
が、これについては例えばプレキャストコンクリート造
の部材や鉄板等のプレート材を用いることができる。さ
らに、十分な地耐力があるのであれば、岩盤、改良地盤
等を用いても良い。In addition, in the above embodiment, the foundation mat 12a is formed of concrete C1, but for this, for example, a precast concrete member or a plate material such as an iron plate can be used. Further, if there is sufficient ground strength, rock, improved ground, or the like may be used.
【0040】また、上記実施の形態では、柱部材18を
ターンバックル22を備えた建入れ調整用ワイヤー21
で建入れ調整する構成としたが、もちろん、ジャッキや
サポート等、他の機器を用いても良い。加えて、建入れ
調整用ワイヤー21は、梁固定用ボルト20以外の部分
にかけるようにしても良く、例えば柱部材18の本体、
もしくは梁固定用ボルト20とは別に柱部材18に取り
付けられたブラケット等、さらには柱部材18に建入れ
調整用ワイヤー21をかけるために形成した凹部等を利
用しても良い。もちろん、梁鉄骨25の接合順序は上記
のものに限定されるものではなく、例えば中央部からそ
の両側に向けて順次架設していく等、他の順序としても
良い。In the above embodiment, the column member 18 is connected to the installation adjusting wire 21 having the turnbuckle 22.
However, other devices such as jacks and supports may be used. In addition, the installation adjustment wire 21 may be applied to a portion other than the beam fixing bolt 20, for example, a main body of the column member 18,
Alternatively, a bracket or the like attached to the column member 18 separately from the beam fixing bolt 20, or a concave portion or the like formed for hanging the installation adjustment wire 21 on the column member 18 may be used. Of course, the joining order of the beam steel members 25 is not limited to the above-mentioned order, and may be another order such as, for example, sequentially extending from the center to both sides.
【0041】さらに、上記実施の形態では、柱10をP
C造とし、梁11を鉄骨造としたが、これに限定される
ものではなく、例えば、柱10については、RC造、P
C杭、鉄骨、木造、梁12についてはPC造、木造等と
しても良い。Further, in the above embodiment, the pillar 10 is
The beam 11 is made of steel, but is not limited to this. For example, the pillar 10 is made of RC, P
The C pile, the steel frame, the wooden structure, and the beam 12 may be a PC structure, a wooden structure, or the like.
【0042】これ以外にも、本発明の主旨を逸脱しない
範囲内であれば、いかなる構成を採用しても良く、また
上記したような構成を適宜選択的に組み合わせたものと
しても良いのは言うまでもない。Other than this, any configuration may be adopted as long as it does not depart from the gist of the present invention, and it is needless to say that the above-described configurations may be appropriately selectively combined. No.
【0043】[0043]
【発明の効果】以上説明したように、請求項1に係る躯
体構造、および請求項2に係るその躯体の構築方法によ
れば、柱部材を所定の位置に立てた後、この柱部材を建
入れ調整し、この状態で柱部材の下端部にコンクリート
を打設して柱部材を固定し、しかる後に柱部材の頭部に
梁を架設する構成となっている。このようにして柱部材
の下端部をコンクリートに埋め込んで固定することによ
って、従来のような剛接合,ピン接合を用いずに固定す
ることができ、またアンカーボルトを不要とすることも
できるので、柱部材の施工を容易に行うことができる。
しかも、柱部材を建入れ調整した状態で、その下端部に
コンクリートを打設して固めることによって、柱部材を
高い精度で建て込むことができる。しかも、建入れ調整
を基礎自体をアンカーとして用いて行うことにより、建
入れ調整のための部材等をわざわざ設置する必要もな
く、この点においても施工の容易化を図ることができ
る。As described above, according to the skeleton structure according to the first aspect and the method for constructing the skeleton according to the second aspect, after the column member is erected at a predetermined position, the column member is constructed. In this state, concrete is cast at the lower end of the column member to fix the column member, and then a beam is erected on the head of the column member. By embedding and fixing the lower end of the column member in concrete in this way, it is possible to fix without using a conventional rigid joint or pin joint, and it is also possible to eliminate the need for anchor bolts. Construction of the column member can be easily performed.
In addition, the concrete can be cast at the lower end of the pillar member in a state where the pillar member is adjusted for installation and solidified, so that the pillar member can be built with high accuracy. In addition, by performing the installation adjustment using the foundation itself as an anchor, there is no need to separately install a member or the like for the installation adjustment, and in this respect, the construction can be facilitated.
【0044】しかも、請求項3に係る躯体の構築方法に
よれば、ベースモルタル,ライナー鉄板等により、柱部
材を立てるべきベースの高さレベルを調整した後、柱部
材を立てる構成となっている。これにより、柱頭におけ
るレベル調整を不要とすることができ、足場の組払い等
も不要となるため手間を大幅に省くことができ、施工の
容易化、効率化を図ることができる。Further, according to the method of constructing a skeleton according to the third aspect, the height of the base on which the column member is to be erected is adjusted using the base mortar, the liner iron plate, or the like, and then the column member is erected. . As a result, the level adjustment at the capital can be made unnecessary, and assembling of the scaffolding becomes unnecessary, so that labor can be largely saved, and the construction can be facilitated and efficiency can be improved.
【0045】さらに、請求項4に係る躯体の構築方法に
よれば、柱部材の下端部に、下方に突出する脚部を形成
しておき、前記コンクリートを打設したときに柱部材の
下方にコンクリートが回るようにしておく構成となって
いる。これにより、柱部材の下面に隙間が生じることな
く、下面全面を確実に基礎に密着させることができ、し
たがって柱部材に作用する鉛直力を確実かつ効率よく下
方に伝達することが可能となる。Further, according to the method for constructing a skeleton according to the fourth aspect, a leg projecting downward is formed at the lower end of the column member, and the leg is formed below the column member when the concrete is poured. It is configured to allow concrete to rotate. Accordingly, the entire lower surface can be securely brought into close contact with the foundation without forming a gap on the lower surface of the column member, so that the vertical force acting on the column member can be transmitted reliably and efficiently downward.
【0046】また、請求項5に係る躯体の構築方法によ
れば、所定の位置に建て込んだ柱部材の頭部に、梁の端
部を柱部材から側方に張り出させてセットした後、この
梁と他の梁とを接続し、しかる後に、梁を柱部材に固定
する構成となっている。このようにして、梁をセットし
て本固定しない状態で他の梁と接合することによって、
柱部材の施工精度によって生じる梁どうしの接合部にお
ける段差等の寸法誤差を吸収することができ、作業を容
易に行うことが可能となる。さらに、柱部材から側方に
張り出した位置で梁どうしを接合することによって、梁
のオーバーハング部分の撓みを利用することができ、こ
の点によって上記寸法誤差の吸収をより容易に行うこと
ができる。According to the method of constructing a skeleton according to claim 5, after setting the end of the beam on the head of the column member erected at a predetermined position by projecting the end of the beam sideways from the column member. Then, this beam is connected to another beam, and thereafter, the beam is fixed to the column member. In this way, by setting the beam and joining it with other beams without fully fixing it,
A dimensional error such as a step at a joint between beams caused by the accuracy of the column member can be absorbed, and the work can be easily performed. Further, by joining the beams at positions protruding laterally from the column member, it is possible to utilize the bending of the overhang portion of the beam, and in this respect, the above-described dimensional error can be more easily absorbed. .
【図1】 本発明に係る躯体構造およびその構築方法の
一例を示す図であって、躯体を構成する柱を構築する手
順を示す工程図である。FIG. 1 is a diagram showing an example of a skeleton structure and a method of constructing the skeleton according to the present invention, and is a process diagram showing a procedure for constructing pillars constituting the skeleton.
【図2】 同、図1に続く工程図である。FIG. 2 is a process drawing following FIG. 1;
【図3】 前記柱に用いる柱部材を示す斜視図である。FIG. 3 is a perspective view showing a pillar member used for the pillar.
【図4】 前記躯体を示す立面図である。FIG. 4 is an elevation view showing the skeleton.
【図5】 同躯体の平面図である。FIG. 5 is a plan view of the same body.
【図6】 前記躯体を構成する柱と梁の接合構造を示す
立面図である。FIG. 6 is an elevation view showing a joint structure between a column and a beam constituting the skeleton.
【図7】 前記柱と他の梁の接合構造を示す側面図であ
る。FIG. 7 is a side view showing a joint structure between the column and another beam.
【図8】 前記梁の接合部を示す図である。FIG. 8 is a view showing a joint portion of the beam.
【図9】 従来の躯体の構築方法の一例を示す工程図で
ある。FIG. 9 is a process chart showing an example of a conventional method of building a skeleton.
10 柱 17 ベースモルタル(ベース) 18 柱部材 19 脚部 25 梁鉄骨(梁) C2 コンクリート 10 pillar 17 base mortar (base) 18 pillar member 19 leg 25 beam steel frame (beam) C2 concrete
───────────────────────────────────────────────────── フロントページの続き (72)発明者 新村 達也 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Tatsuya Shinmura 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Corporation
Claims (5)
長さをコンクリート中に埋め込むことによって立設さ
れ、前記柱の頭部に架設された梁が、該柱の頭部から側
方に張り出した位置で他の梁に接合されていることを特
徴とする躯体構造。1. A pillar constituting a skeleton is erected by embedding a predetermined length of a lower end portion thereof in concrete, and a beam erected on a head of the pillar is laterally extended from a head of the pillar. A skeleton structure characterized by being joined to another beam at a position where it overhangs.
に立てた後、該柱部材を建入れ調整し、この状態で前記
柱部材の下端部にコンクリートを打設して該柱部材を固
定し、しかる後に該柱部材の頭部に梁を架設することを
特徴とする躯体の構築方法。2. A pillar member constituting a pillar of a skeleton is set at a predetermined position, and then the pillar member is erected. In this state, concrete is poured into a lower end portion of the pillar member. , And after that, a beam is erected on the head of the column member.
て、前記柱部材を立てるに際し、前記柱部材を立てるべ
きベースの高さレベルを調整した後、前記ベース上に前
記柱部材を立てることを特徴とする躯体の構築方法。3. The method for constructing a skeleton according to claim 2, wherein when the column member is erected, the height of the base on which the column member is erected is adjusted, and then the column member is erected on the base. Construction method of the skeleton.
において、前記柱部材の下端部に下方に突出する脚部を
形成しておき、前記コンクリートを打設したときに前記
柱部材の下端部の下方に前記コンクリートが回るように
しておくことを特徴とする躯体の構築方法。4. The method for constructing a skeleton according to claim 2, wherein a leg projecting downward is formed at a lower end of the column member, and the lower end of the column member is formed when the concrete is cast. A method for constructing a skeleton, wherein the concrete is made to rotate under a part.
に建て込んだ後、該柱部材の頭部に、梁を、その端部が
前記柱部材から側方に張り出すようセットした後、該梁
と、他の柱部材の頭部上にセットした他の梁とを接続
し、しかる後に、前記梁を前記柱部材に固定することを
特徴とする躯体の構築方法。5. After a pillar member constituting a pillar of a skeleton is erected at a predetermined position, a beam is set on the head of the pillar member so that an end thereof projects laterally from the pillar member. After that, the beam is connected to another beam set on the head of another column member, and then the beam is fixed to the column member.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP30126397A JPH11131585A (en) | 1997-10-31 | 1997-10-31 | Building frame body structure and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP30126397A JPH11131585A (en) | 1997-10-31 | 1997-10-31 | Building frame body structure and construction method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH11131585A true JPH11131585A (en) | 1999-05-18 |
Family
ID=17894719
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP30126397A Pending JPH11131585A (en) | 1997-10-31 | 1997-10-31 | Building frame body structure and construction method thereof |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH11131585A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2016185570A (en) * | 2015-03-27 | 2016-10-27 | 富士重工業株式会社 | Processing facility and method for manufacturing processing facility |
JP2019078882A (en) * | 2017-10-24 | 2019-05-23 | Tianma Japan株式会社 | Optical element and method for manufacturing optical element |
-
1997
- 1997-10-31 JP JP30126397A patent/JPH11131585A/en active Pending
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2016185570A (en) * | 2015-03-27 | 2016-10-27 | 富士重工業株式会社 | Processing facility and method for manufacturing processing facility |
JP2019078882A (en) * | 2017-10-24 | 2019-05-23 | Tianma Japan株式会社 | Optical element and method for manufacturing optical element |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2001164512A (en) | Section division type precast segment construction method | |
JP3818020B2 (en) | Cross-section precast segment method | |
JPS627344B2 (en) | ||
JPH09209451A (en) | Joint construction of up and down columns with beam and joint method | |
JP3671344B2 (en) | Joint structure between foundation pile and column base and its construction method | |
JP2003328320A (en) | Construction method of precast capital part and bridge pier capital part | |
JP2537330B2 (en) | Precast reinforced concrete columns | |
JPH11131585A (en) | Building frame body structure and construction method thereof | |
JP2747678B2 (en) | Composite beam | |
JP3084654B2 (en) | Construction foundation, foundation structure using the same, and construction method thereof | |
JP3137448B2 (en) | Construction method of concrete main tower | |
JPH08120638A (en) | Connecting structure of pile and beam and execution method of structure using connecting structure | |
JP2001254495A (en) | Internal stairway for building, and building method therefor | |
JP2000160687A (en) | Construction method for composite structure and precast concrete column | |
JPH08144425A (en) | Prefabricated member of mixed structure and construction method of mixed structure | |
JPH08158341A (en) | Joining structure of pile and beam | |
JPH0380946B2 (en) | ||
JP2811211B2 (en) | Flat slab construction method | |
JP3408629B2 (en) | Precast concrete foundation structure | |
JP3262600B2 (en) | Construction method of concrete main tower and cross beam | |
JP2860501B2 (en) | Concrete foundation | |
JP2967452B2 (en) | Building construction methods and lightweight floor slabs | |
JP2784450B2 (en) | Reinforced concrete foundation | |
JPH0417718Y2 (en) | ||
JPH10331255A (en) | Method for erecting pc column on foundation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20040615 |