JPH11115882A - Concrete plant ship - Google Patents

Concrete plant ship

Info

Publication number
JPH11115882A
JPH11115882A JP28806997A JP28806997A JPH11115882A JP H11115882 A JPH11115882 A JP H11115882A JP 28806997 A JP28806997 A JP 28806997A JP 28806997 A JP28806997 A JP 28806997A JP H11115882 A JPH11115882 A JP H11115882A
Authority
JP
Japan
Prior art keywords
concrete
barge
plant
ship
concrete plant
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP28806997A
Other languages
Japanese (ja)
Inventor
Yuji Nishiwaki
裕二 西脇
Hiroshi Ishikawa
寛 石川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taiheiyo Cement Corp
Yorigami Maritime Construction Co Ltd
Original Assignee
Taiheiyo Cement Corp
Yorigami Maritime Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taiheiyo Cement Corp, Yorigami Maritime Construction Co Ltd filed Critical Taiheiyo Cement Corp
Priority to JP28806997A priority Critical patent/JPH11115882A/en
Publication of JPH11115882A publication Critical patent/JPH11115882A/en
Pending legal-status Critical Current

Links

Landscapes

  • Underground Or Underwater Handling Of Building Materials (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

PROBLEM TO BE SOLVED: To stably supply concrete with even quality even under bad weather, and moor a concrete plant ship on an optional spot with certainty. SOLUTION: A lower end of each spud 10 of this concrete plant ship is seated on a sea bottom in the vicinity of a quay 8. A barge 2 is thus fixed at a position higher than a water level. Concrete material in silos 12 to 14 of a material supplying ship 5 is supplied to a receiving hopper of the barge 2 by a belt conveyor 15. The material is then transferred to a measuring hopper 4 by a belt conveyor 7. Concrete mixing is thus performed in a concrete plant 3. The prepared concrete is stored in an agitator car 17 which is moved from the barge 2 to a ground through a ramp way 9. The concrete is thus transferred to an application spot.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、コンクリートプ
ラント船に係り、特にコンクリートプラントが搭載され
た台船をスパットを用いて水面の上方に固定することが
できる自己昇降式のコンクリートプラント船に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a concrete plant ship, and more particularly to a self-elevating concrete plant ship capable of fixing a barge on which a concrete plant is mounted above a water surface using a spat.

【0002】[0002]

【従来の技術】陸地から離れている島や埋立地等にコン
クリートの打設を行う場合に、新たにコンクリート製造
プラントを築造しようとすると、広大な築造場所と莫大
な費用がかかると共に必要に応じて打設が完了した後に
プラントを撤去しなければならない。そこで、台船上に
コンクリートプラントを搭載したコンクリートミキサ船
が従来から用いられている。陸上のコンクリートの打設
目的箇所に近い海上位置までコンクリートミキサ船を移
動し、プラントで製造されたコンクリートをベルトコン
ベヤ、ポンプ圧送等により目的箇所に打設したり、ある
いはアジテータ車を用いて打設目的箇所までコンクリー
トを搬送する。
2. Description of the Related Art When constructing a concrete manufacturing plant in the case of placing concrete on an island or landfill away from land, a large construction site and enormous cost are required, and it is necessary to construct a new plant. After the installation is completed, the plant must be removed. Therefore, a concrete mixer ship having a concrete plant mounted on a barge has been conventionally used. Move the concrete mixer ship to a sea location close to the target location for placing concrete on land.Concrete produced at the plant is poured into the target location by belt conveyor, pumping, etc., or cast using an agitator truck. Convey concrete to destination.

【0003】このようなコンクリートミキサ船を用いる
ことにより、新たにコンクリート製造プラントを築造す
ることなく陸上の目的箇所へのコンクリートの打設が可
能になる。また、コンクリートの打設が完了した後は、
コンクリートミキサ船を移動させるだけでよく、一旦築
造したプラントを撤去する必要がない。
[0003] By using such a concrete mixer ship, it becomes possible to cast concrete at a target location on land without constructing a new concrete manufacturing plant. Also, after concrete placement is complete,
All you have to do is move the concrete mixer ship and there is no need to remove the plant once it was built.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、従来の
コンクリートミキサ船は、海上に浮いた台船上のプラン
トでコンクリートを製造するため、うねりや波高の高い
荒天時には台船と共にプラントが動揺し、コンクリート
材料の計量誤差が生じて品質が均一なコンクリートを安
定して供給することが困難であるという問題点があっ
た。また、従来のコンクリートミキサ船においては、台
船上にウインチを搭載し、岸壁の係留設備を利用すると
共に台船の後方へアンカーを投錨して台船の係留を行っ
ていた。このため、岸壁に係留設備がない場合や、台船
の後方へアンカーを投錨できるような広大な工事区域を
確保できない場合には、台船の係留が困難になるという
問題点もあった。この発明はこのような問題点を解消す
るためになされたもので、荒天時であっても品質が均一
なコンクリートの安定供給が可能で且つどのような場所
でも確実に係留することができるコンクリートプラント
船を提供することを目的とする。
However, since the conventional concrete mixer ship manufactures concrete at a plant on a barge floating on the sea, the plant shakes together with the barge during swelling and high stormy weather, and concrete material There is a problem that it is difficult to stably supply concrete of uniform quality due to the measurement error of the above. In a conventional concrete mixer ship, a winch is mounted on the barge, and the mooring of the barge is performed by using the mooring equipment on the quay and anchoring the anchor behind the barge. For this reason, when there is no mooring equipment on the quay, or when it is not possible to secure a large construction area where anchors can be anchored behind the barge, there is a problem that mooring of the barge becomes difficult. The present invention has been made to solve such a problem, and a concrete plant capable of stably supplying concrete of uniform quality even in stormy weather and capable of securely mooring anywhere. The purpose is to provide a ship.

【0005】[0005]

【課題を解決するための手段】この発明に係るコンクリ
ートプラント船は、台船と、台船上に搭載されたコンク
リートプラントと、台船に昇降自在に設けられた複数の
スパットとを備え、複数のスパットを降下して海底に着
底させることにより台船を水面の上方に固定した状態で
コンクリートプラントを稼働させるものである。なお、
コンクリート材料は、台船の近傍に係留された材料供給
船から受入れホッパーを介して供給する、あるいは陸上
に設置された材料ヤードから材料搬送手段を介して供給
するようにすることができる。また、製造されたコンク
リートは、台船と岸壁とをランプウエイで連絡してアジ
テータ車により搬送する、あるいはディストリビュータ
により打設現場に直接供給することができる。さらに、
プレクーリング用の冷却プラント、海水から淡水を生成
する淡水化装置、コンクリート材料を収容する材料スト
ッカを備えることもできる。
SUMMARY OF THE INVENTION A concrete plant ship according to the present invention includes a barge, a concrete plant mounted on the barge, and a plurality of spats provided on the barge so as to be able to move up and down. The concrete plant is operated with the barge fixed above the water surface by lowering the spat to land on the sea floor. In addition,
The concrete material may be supplied via a receiving hopper from a material supply boat moored near the barge, or may be supplied via a material transport means from a material yard located on land. Further, the produced concrete can be transported by an agitator vehicle by connecting the barge and the quay by a ramp way, or can be directly supplied to a casting site by a distributor. further,
A cooling plant for pre-cooling, a desalination device for producing fresh water from seawater, and a material stocker for containing concrete material can also be provided.

【0006】[0006]

【発明の実施の形態】以下、この発明の実施の形態を添
付図面に基づいて説明する。 実施の形態1.図1〜3にこの発明の実施の形態1に係
るコンクリートプラント船1を示す。台船2上の中央部
に2系列のコンクリートプラント3が搭載されている。
各コンクリートプラント3は、計量ホッパー4を有する
と共に、図示しないミキサ及びコンクリート供給部等を
備えている。また、台船2上の後部には、各コンクリー
トプラント3に対応して材料供給船5からコンクリート
材料を受け入れるための二つの受入れホッパー6が設け
られると共に各受入れホッパー6に受け入れられたコン
クリート材料を対応するコンクリートプラント3の計量
ホッパー4へ搬送するためのベルトコンベヤ7が設けら
れている。一方、台船2上の前部には、岸壁8と台船2
とを連絡するランプウエイ9が回動自在に設けられてい
る。
Embodiments of the present invention will be described below with reference to the accompanying drawings. Embodiment 1 FIG. 1 to 3 show a concrete plant ship 1 according to Embodiment 1 of the present invention. Two series of concrete plants 3 are mounted in the center of the barge 2.
Each concrete plant 3 has a weighing hopper 4 and a mixer and a concrete supply unit (not shown). In addition, two receiving hoppers 6 for receiving concrete material from the material supply ship 5 are provided at the rear part of the barge 2 corresponding to each concrete plant 3 and the concrete material received by each receiving hopper 6 is provided. A belt conveyor 7 is provided for transporting to a corresponding weighing hopper 4 of the concrete plant 3. On the other hand, the quay 8 and the barge 2
A lampway 9 for communicating with the vehicle is provided rotatably.

【0007】さらに、台船2の四隅には、それぞれスパ
ット10が立設されている。各スパット10は、台船2
を鉛直方向に貫通しており、それぞれ昇降機構11によ
って昇降可能に設けられている。各スパット10を上昇
させると、台船2は海面に浮かび、曳航船等によって海
上を自由に曳航することができる。一方、各スパット1
0を下降させてその下端部を海底に着底させ、さらに台
船2に対してスパット10を下降させると、相対的に台
船2はスパット10に対して上昇し、図1及び図3に示
されるように台船2を水面の上方に固定することができ
る。
Further, at the four corners of the barge 2, spats 10 are provided upright. Each spat 10 is a barge 2
Are vertically penetrated, and each is provided so as to be able to move up and down by a lifting mechanism 11. When each spat 10 is raised, the barge 2 floats on the sea surface and can be towed on the sea freely by a towing ship or the like. Meanwhile, each spat 1
0, the lower end of the boat 10 is settled on the seabed, and the spat 10 is further lowered with respect to the barge 2. When the barge 2 relatively rises with respect to the spat 10, the barge 2 rises relative to the spat 10, as shown in FIGS. The barge 2 can be fixed above the water surface as shown.

【0008】このような実施の形態1に係るコンクリー
トプラント船1の動作について説明する。まず、各スパ
ット10を上昇させて台船2を海面に浮かべ、曳航船等
によって海上を曳航して、陸上のコンクリートの打設目
的箇所に近い岸壁8の近傍まで移動させる。ここで、台
船2の四隅に設けられた昇降機構11により各スパット
10を下降し、各スパット10の下端部を海底に着底さ
せる。さらに、昇降機構11で各スパット10を下降さ
せることにより、台船2を相対的にスパット10に対し
て上昇させ、図1及び図3に示されるように台船2を水
面の上方に固定する。これにより、海上にうねりや高い
波があっても、台船2は動揺することなく、確実に固定
される。さらに、図1及び図2に示されるように、台船
2の前部に設けられたランプウエイ9を回動して岸壁8
と台船2とを連絡させる。
The operation of the concrete plant ship 1 according to the first embodiment will be described. First, each spat 10 is raised, the barge 2 is floated on the sea surface, towed on the sea by a towing ship or the like, and moved to the vicinity of the quay 8 close to the target location for placing concrete on land. Here, each spat 10 is lowered by the elevating mechanism 11 provided at the four corners of the barge 2, and the lower end of each spat 10 is landed on the seabed. Further, by lowering each spat 10 by the elevating mechanism 11, the barge 2 is relatively raised with respect to the spat 10, and the barge 2 is fixed above the water surface as shown in FIGS. . Thereby, even if there are swells and high waves on the sea, the barge 2 is securely fixed without shaking. Further, as shown in FIGS. 1 and 2, a rampway 9 provided at the front part of the barge 2 is rotated to
And the barge 2 are communicated.

【0009】次に、台船2の後方の海上に材料供給船5
を位置させ、アンカーを投錨して係留させる。材料供給
船5は、粗骨材サイロ12、細骨材サイロ13及びセメ
ントサイロ14を有すると共にこれらのサイロ内に格納
されたコンクリート材料を搬送する材料供給ベルトコン
ベヤ15を有している。材料供給船5が係留された後、
材料供給船5の材料供給ベルトコンベヤ15の一端が台
船2の受入れホッパー6に連結される。なお、材料供給
船5の各サイロには材料運搬船16を介してそれぞれ材
料が供給される。
Next, a material supply ship 5 is placed on the sea behind the barge 2.
And anchor the anchor to moor it. The material supply ship 5 has a coarse aggregate silo 12, a fine aggregate silo 13, and a cement silo 14, and has a material supply belt conveyor 15 that conveys the concrete material stored in these silos. After the material supply ship 5 is moored,
One end of the material supply belt conveyor 15 of the material supply ship 5 is connected to the receiving hopper 6 of the barge 2. In addition, the material is supplied to each silo of the material supply ship 5 via the material carrier 16.

【0010】コンクリートの製造時には、材料供給船5
の各サイロ12〜14に格納されていたコンクリート材
料が材料供給ベルトコンベヤ15により台船2の受入れ
ホッパー6へと供給され、さらに台船2のベルトコンベ
ヤ7によってコンクリートプラント3の計量ホッパー4
へ搬送される。このとき、スパット10により台船2が
水面の上方に固定されているので、海上のうねりや波の
影響を受けにくく、荒天時であっても陸上のプラントと
同様の精度で計量を行うことができる。従って、品質が
均一なコンクリートを安定して製造することが可能とな
る。
At the time of concrete production, the material supply ship 5
The concrete material stored in each of the silos 12 to 14 is supplied to the receiving hopper 6 of the barge 2 by the material supply belt conveyor 15, and furthermore, the weighing hopper 4 of the concrete plant 3 is supplied by the belt conveyor 7 of the barge 2.
Transported to At this time, since the barge 2 is fixed above the water surface by the spat 10, it is hardly affected by swells and waves on the sea, and it is possible to perform measurement with the same accuracy as a plant on land even in stormy weather. it can. Therefore, it is possible to stably produce concrete of uniform quality.

【0011】製造されたコンクリートは、コンクリート
プラント3の図示しないコンクリート供給部からアジテ
ータ車17に積み込まれ、アジテータ車17は台船2か
らランプウエイ9を陸上へと渡り、打設目的箇所へ移動
する。
The produced concrete is loaded on an agitator car 17 from a concrete supply unit (not shown) of the concrete plant 3, and the agitator car 17 crosses the rampway 9 from the barge 2 to the land, and moves to a place to be poured. .

【0012】なお、昇降機構11により台船2の水面上
の高さ位置を調節することができるので、岸壁8の高さ
に無関係にランプウエイ9の角度を一定にすることが可
能となる。また、従来のように台船2が海面に浮かんで
いるのであれば、台船2上の全重量の変化による喫水差
に応じてランプウエイ9の角度が変わるが、この発明に
おいては台船2が海面の上方に固定されるため、台船2
上の全重量が変化してもランプウエイ9の角度が変わる
ことはない。従って、アジテータ車17はランプウエイ
9上をスムーズに走行することができる。
Since the height position of the barge 2 on the water surface can be adjusted by the elevating mechanism 11, the angle of the ramp way 9 can be made constant regardless of the height of the quay 8. Further, if the barge 2 is floating on the sea surface as in the prior art, the angle of the rampway 9 changes according to the draft difference due to the change in the total weight on the barge 2. Is fixed above the sea surface,
The angle of the lampway 9 does not change even if the total weight above changes. Therefore, the agitator wheel 17 can run on the rampway 9 smoothly.

【0013】台船2は鉛直方向に移動する4本のスパッ
ト10により海面の上方に固定されるので、岸壁8の係
留設備を利用したり、アンカーを投錨して台船2を係留
させる必要がない。このため、他の船舶等との接触の惧
れが少なく、狭い工事区域でも作業を行うことができ
る。また、台船2上に係留用のウインチを搭載する必要
もない。
Since the barge 2 is fixed above the sea surface by four spats 10 which move in the vertical direction, it is necessary to use the mooring equipment of the quay 8 or anchor the anchor by anchoring the anchor. Absent. For this reason, there is little fear of contact with other ships and the like, and work can be performed even in a narrow construction area. Further, it is not necessary to mount a mooring winch on the barge 2.

【0014】実施の形態2.図4及び5に実施の形態2
に係るコンクリートプラント船21を示す。このコンク
リートプラント船21は、図1〜3に示した実施の形態
1のコンクリートプラント船1において、材料供給ベル
トコンベヤ22を備えたものである。材料供給ベルトコ
ンベヤ22は、岸壁8に設置された材料ヤード23から
コンクリートプラント3の計量ホッパー4までコンクリ
ート材料を搬送するための材料搬送手段となるもので、
この実施の形態2においては、材料供給船5を用いず、
陸上の材料ヤード23からコンクリート材料のコンクリ
ートプラント3への供給が行われる。
Embodiment 2 FIG. 4 and 5 show a second embodiment.
1 shows a concrete plant ship 21 according to the first embodiment. The concrete plant ship 21 has a material supply belt conveyor 22 in the concrete plant ship 1 of the first embodiment shown in FIGS. The material supply belt conveyor 22 serves as a material conveying means for conveying the concrete material from the material yard 23 installed on the quay 8 to the weighing hopper 4 of the concrete plant 3.
In the second embodiment, the material supply ship 5 is not used,
The supply of the concrete material to the concrete plant 3 is performed from the land material yard 23.

【0015】すなわち、岸壁8の近傍の海底にスパット
10の下端部を着底させて、台船2を水面の上方に固定
し、ランプウエイ9で岸壁8と台船2とを連絡させると
共に材料供給ベルトコンベヤ22の先端を岸壁8上の材
料ヤード23に連結する。材料ヤード23に格納されて
いたコンクリート材料が材料供給ベルトコンベヤ22に
より台船2のコンクリートプラント3の計量ホッパー4
へ搬送され、海上のうねりや波の影響を受けることな
く、品質が均一なコンクリートが安定して製造される。
製造されたコンクリートはアジテータ車17に積み込ま
れ、アジテータ車17は台船2からランプウエイ9を陸
上へと渡り、打設目的箇所へ移動する。
That is, the lower end of the spat 10 is settled on the seabed near the quay 8, the barge 2 is fixed above the water surface, the rampway 9 connects the quay 8 and the barge 2, and The leading end of the supply belt conveyor 22 is connected to a material yard 23 on the quay 8. The concrete material stored in the material yard 23 is transferred to the weighing hopper 4 of the concrete plant 3 of the barge 2 by the material supply belt conveyor 22.
The concrete is transported to the sea and is not affected by swells and waves on the sea, and concrete of uniform quality is produced stably.
The produced concrete is loaded on the agitator wheel 17, and the agitator wheel 17 crosses the rampway 9 from the barge 2 to the land and moves to the destination for casting.

【0016】このように、岸壁8に材料ヤード23を設
置できれば、あるいは予め材料ヤード23が設置されて
いる岸壁8においては、材料供給船5及び材料運搬船1
6を用いることなく台船2のコンクリートプラント3に
材料を供給することができ、さらに狭い工事区域であっ
ても作業を行うことが可能となる。
As described above, if the material yard 23 can be installed on the quay 8, or on the quay 8 where the material yard 23 is previously installed, the material supply ship 5 and the material transport ship 1
The material can be supplied to the concrete plant 3 of the barge 2 without using the barge 6, and work can be performed even in a narrow construction area.

【0017】実施の形態3.図6〜8に実施の形態3に
係るコンクリートプラント船31を示す。このコンクリ
ートプラント船31は、図1〜3に示した実施の形態1
のコンクリートプラント船1において、台船2の前部に
コンクリート打設用のディストリビュータ32を設けた
ものである。例えば、沖合等の水深の大きい場所に打設
目的箇所33がある場合には、アジテータ車17でコン
クリートを搬送することができないので、台船2に設け
たディストリビュータ32を用いて目的箇所33にコン
クリートを直接打設することが望ましい。
Embodiment 3 6 to 8 show a concrete plant ship 31 according to the third embodiment. This concrete plant ship 31 has a structure similar to that of the first embodiment shown in FIGS.
In the concrete plant ship 1, a distributor 32 for placing concrete is provided in front of the barge 2. For example, if the target location 33 is located in a place with a large depth of water, such as offshore, concrete cannot be transported by the agitator truck 17, and the concrete 32 can be transported to the target location 33 using the distributor 32 provided on the barge 2. It is desirable to cast directly.

【0018】すなわち、打設目的箇所33の近傍の海底
にスパット10の下端部を着底させて、台船2を水面の
上方に固定し、ディストリビュータ32の先端を打設目
的箇所33へ向ける。また、台船2の後方の海上に材料
供給船5を係留させ、材料供給船5の材料供給ベルトコ
ンベヤ15の先端を台船2の受入れホッパー6に連結さ
せる。材料供給船5の各サイロ12〜14に格納されて
いたコンクリート材料が材料供給ベルトコンベヤ15に
より台船2の受入れホッパー6へ供給され、さらに台船
2のベルトコンベヤ7によってコンクリートプラント3
の計量ホッパー4へ搬送され、海上のうねりや波の影響
を受けることなく、品質が均一なコンクリートが安定し
て製造される。製造されたコンクリートはディストリビ
ュータ32を介して目的箇所33へ打設される。
That is, the lower end of the spat 10 is settled on the seabed near the casting point 33, the barge 2 is fixed above the water surface, and the tip of the distributor 32 is directed to the casting point 33. Further, the material supply ship 5 is moored on the sea behind the barge 2, and the tip of the material supply belt conveyor 15 of the material supply ship 5 is connected to the receiving hopper 6 of the barge 2. The concrete material stored in each of the silos 12 to 14 of the material supply ship 5 is supplied to the receiving hopper 6 of the barge 2 by the material supply belt conveyor 15, and further, the concrete plant 3 is conveyed by the belt conveyor 7 of the barge 2.
Is transported to the weighing hopper 4 and concrete of uniform quality is stably manufactured without being affected by undulations and waves on the sea. The produced concrete is poured into the destination 33 via the distributor 32.

【0019】このように、台船2にディストリビュータ
32を設けることにより、コンクリートプラント3で製
造されたコンクリートを目的箇所33に直接打設するこ
とが可能となる。
As described above, the provision of the distributor 32 on the barge 2 allows the concrete produced in the concrete plant 3 to be directly poured into the target location 33.

【0020】実施の形態4.図9に実施の形態4に係る
コンクリートプラント船41を示す。このコンクリート
プラント船41は、図1〜3に示した実施の形態1のコ
ンクリートプラント船1において、コンクリートプラン
ト3に隣接してプレクーリング用の冷却プラント42を
設けたものである。冷却プラント42としては、粗骨
材、細骨材及びセメント等の材料を冷却する装置、練混
ぜ水を冷却する装置、練混ぜ水の代わりに用いる氷を製
造する装置、練混ぜ中のコンクリートを冷却する装置、
製造されたコンクリートを冷却する装置等のいずれを用
いることもできる。また、冷却の方法としては、冷水、
冷風、冷凍機、製氷機、液体窒素、ドライアイス等によ
る各種の方法を用いることができる。
Embodiment 4 FIG. 9 shows a concrete plant ship 41 according to the fourth embodiment. This concrete plant ship 41 has a cooling plant 42 for pre-cooling provided adjacent to the concrete plant 3 in the concrete plant ship 1 of the first embodiment shown in FIGS. As the cooling plant 42, a device for cooling materials such as coarse aggregate, fine aggregate and cement, a device for cooling mixing water, a device for producing ice used in place of mixing water, and concrete during mixing are used. Cooling equipment,
Any device such as a device for cooling manufactured concrete can be used. In addition, as a cooling method, cold water,
Various methods using cold air, a refrigerator, an ice machine, liquid nitrogen, dry ice, and the like can be used.

【0021】このような冷却プラント42を備えること
により、マスコンクリート、暑中コンクリートに対応し
た良質のコンクリートを安定して製造・供給することが
可能となる。
By providing such a cooling plant 42, it becomes possible to stably produce and supply high-quality concrete corresponding to mass concrete and hot concrete.

【0022】実施の形態5.図10に実施の形態5に係
るコンクリートプラント船51を示す。このコンクリー
トプラント船51は、図1〜3に示した実施の形態1の
コンクリートプラント船1において、台船2上に淡水化
装置52を設けたものである。淡水化装置52は、海水
を取り込んで、海水からコンクリート製造に用いる淡水
(練混ぜ水)を生成する装置である。
Embodiment 5 FIG. 10 shows a concrete plant ship 51 according to the fifth embodiment. This concrete plant ship 51 has a desalination device 52 provided on the barge 2 in the concrete plant ship 1 of the first embodiment shown in FIGS. The desalination device 52 is a device that takes in seawater and generates freshwater (mixed water) used for concrete production from the seawater.

【0023】このような淡水化装置52を備えることに
より、台船2の周辺に豊富に存在する海水を用いて淡水
を生成することができ、材料供給船5あるいは陸上から
コンクリートプラント3に淡水を供給しなくても済む。
By providing such a desalination apparatus 52, fresh water can be generated using seawater abundantly present around the barge 2, and fresh water can be supplied to the concrete plant 3 from the material supply ship 5 or from land. No need to supply.

【0024】実施の形態6.図11に実施の形態6に係
るコンクリートプラント船61を示す。このコンクリー
トプラント船61は、図1〜3に示した実施の形態1の
コンクリートプラント船1において、台船2上にコンク
リート材料を収容する材料ストッカ62を設けると共
に、材料ストッカ62内のコンクリート材料をコンクリ
ートプラント3の計量ホッパー4へ搬送する材料供給ベ
ルトコンベヤ63を設けたものである。
Embodiment 6 FIG. FIG. 11 shows a concrete plant ship 61 according to the sixth embodiment. The concrete plant ship 61 is different from the concrete plant ship 1 according to the first embodiment shown in FIGS. 1 to 3 in that a material stocker 62 for containing a concrete material is provided on a barge 2 and the concrete material in the material stocker 62 is removed. This is provided with a material supply belt conveyor 63 that conveys the material to the weighing hopper 4 of the concrete plant 3.

【0025】このような材料ストッカ62を台船2上に
備えることにより、材料供給船5あるいは陸上からコン
クリートプラント3にコンクリート材料を供給しなくて
も、コンクリートの製造を行うことができる。従って、
材料供給船5を係留させる程の広い工事区域を確保でき
ない場合や、岸壁8に材料ヤード等の施設がない場合で
あっても、材料ストッカ62の材料収容量に応じた量の
コンクリートを製造することが可能となる。
By providing such a material stocker 62 on the barge 2, concrete can be manufactured without supplying concrete material to the concrete plant 3 from the material supply ship 5 or from land. Therefore,
Even if it is not possible to secure a construction area large enough to moor the material supply ship 5 or if there is no facility such as a material yard on the quay 8, concrete is produced in an amount corresponding to the material capacity of the material stocker 62. It becomes possible.

【0026】なお、上述した各実施の形態に係るコンク
リートプラント船においては、台船2上に2系列のコン
クリートプラント3が搭載されているので、要求される
コンクリート供給量に応じて、いずれか一方のコンクリ
ートプラント3あるいは双方のコンクリートプラント3
を稼働させることができる。また、コンクリートプラン
ト3は2系列に限るものではなく、1系列のみ、あるい
は3系列以上のコンクリートプラントを搭載してもよ
い。
In the concrete plant ship according to each of the above-described embodiments, since two lines of concrete plants 3 are mounted on the barge 2, any one of the concrete plants 3 is installed in accordance with the required concrete supply amount. Concrete plant 3 or both concrete plants 3
Can be operated. The number of concrete plants 3 is not limited to two, and one or three or more concrete plants may be mounted.

【0027】図9〜図11に示した実施の形態4〜6に
おいては、いずれもランプウエイ9で台船2と岸壁8と
を連絡し、アジテータ車によりコンクリートを打設現場
へ搬送する形式で図示されたが、実施の形態3のように
ディストリビュータを備え、打設目的箇所にコンクリー
トを直接打設するように構成してもよい。さらに、実施
の形態4〜6においては、それぞれ台船2上に冷却プラ
ント42、淡水化装置52及び材料ストッカ62を備え
たが、これら冷却プラント42、淡水化装置52及び材
料ストッカ62の設備の全て、あるいはいずれか二つの
設備を一つの台船2上に備えるようにしてもよい。
In the embodiments 4 to 6 shown in FIGS. 9 to 11, the barge 2 and the quay 8 are connected by a ramp way 9, and the concrete is transported to the casting site by an agitator car. Although illustrated, a distributor may be provided as in the third embodiment, and concrete may be directly poured into a placement target location. Further, in the fourth to sixth embodiments, the cooling plant 42, the desalination device 52, and the material stocker 62 are provided on the barge 2, respectively, but the equipment of the cooling plant 42, the desalination device 52, and the material stocker 62 is provided. All or any two facilities may be provided on one barge 2.

【0028】[0028]

【発明の効果】以上説明したように、この発明によれ
ば、スパットにより台船を水面の上方に固定した状態で
コンクリートプラントを稼働することにより、うねりや
波高の高い荒天時であっても品質が均一なコンクリート
を安定して製造することが可能となる。また、岸壁の係
留設備やアンカーを用いることなく、スパットによって
台船を固定するため、狭い工事区域でも作業を行うこと
ができる。
As described above, according to the present invention, by operating the concrete plant with the barge fixed above the water surface by the spat, the quality can be improved even in stormy weather with high swells and wave heights. It is possible to stably produce uniform concrete. In addition, since the barge is fixed by the spat without using mooring equipment and anchors on the quay, work can be performed even in a small construction area.

【図面の簡単な説明】[Brief description of the drawings]

【図1】この発明の実施の形態1に係るコンクリートプ
ラント船を示す側面図である。
FIG. 1 is a side view showing a concrete plant ship according to Embodiment 1 of the present invention.

【図2】実施の形態1に係るコンクリートプラント船を
示す平面図である。
FIG. 2 is a plan view showing the concrete plant ship according to the first embodiment.

【図3】実施の形態1に係るコンクリートプラント船を
示す正面図である。
FIG. 3 is a front view showing the concrete plant ship according to the first embodiment.

【図4】実施の形態2に係るコンクリートプラント船を
示す側面図である。
FIG. 4 is a side view showing a concrete plant ship according to a second embodiment.

【図5】実施の形態2に係るコンクリートプラント船を
示す平面図である。
FIG. 5 is a plan view showing a concrete plant ship according to a second embodiment.

【図6】実施の形態3に係るコンクリートプラント船を
示す側面図である。
FIG. 6 is a side view showing a concrete plant ship according to a third embodiment.

【図7】実施の形態3に係るコンクリートプラント船を
示す平面図である。
FIG. 7 is a plan view showing a concrete plant ship according to a third embodiment.

【図8】実施の形態3に係るコンクリートプラント船を
示す正面図である。
FIG. 8 is a front view showing a concrete plant ship according to a third embodiment.

【図9】実施の形態4に係るコンクリートプラント船を
示す平面図である。
FIG. 9 is a plan view showing a concrete plant ship according to a fourth embodiment.

【図10】実施の形態5に係るコンクリートプラント船
を示す平面図である。
FIG. 10 is a plan view showing a concrete plant ship according to a fifth embodiment.

【図11】実施の形態6に係るコンクリートプラント船
を示す平面図である。
FIG. 11 is a plan view showing a concrete plant ship according to a sixth embodiment.

【符号の説明】[Explanation of symbols]

1,21,31,41,51,61 コンクリートプ
ラント船 2 台船 3 コンクリートプラント 4 計量ホッパー 5 材料供給船 6 受入れホッパー 7 ベルトコンベヤ 8 岸壁 9 ランプウエイ 10 スパット 11 昇降機構 17 アジテータ車 22,63 材料供給ベルトコンベヤ 23 材料ヤード 32 ディストリビュータ 42 冷却プラント 52 淡水化装置 62 材料ストッカ
1, 21, 31, 41, 51, 61 Concrete plant ship 2 barge 3 Concrete plant 4 Weighing hopper 5 Material supply ship 6 Receiving hopper 7 Belt conveyor 8 Wharf 9 Rampway 10 Spat 11 Elevating mechanism 17 Agitator car 22, 63 Material Supply belt conveyor 23 Material yard 32 Distributor 42 Cooling plant 52 Desalination equipment 62 Material stocker

Claims (8)

【特許請求の範囲】[Claims] 【請求項1】 台船と、 前記台船上に搭載されたコンクリートプラントと、 前記台船に昇降自在に設けられた複数のスパットとを備
え、複数のスパットを降下して海底に着底させることに
より前記台船を水面の上方に固定した状態で前記コンク
リートプラントを稼働させることを特徴とするコンクリ
ートプラント船。
1. A barge, a concrete plant mounted on the barge, and a plurality of spats provided on the barge so as to be able to move up and down, wherein the plurality of spats descend to land on the sea floor. A concrete plant ship, wherein the concrete plant is operated with the barge fixed above the water surface.
【請求項2】 前記台船の近傍に係留された材料供給船
からコンクリート材料を受け入れるための受入れホッパ
ーを備えた請求項1に記載のコンクリートプラント船。
2. The concrete plant ship according to claim 1, further comprising a receiving hopper for receiving concrete material from a material supply ship moored near the barge.
【請求項3】 陸上に設置された材料ヤードから前記コ
ンクリートプラントへコンクリート材料を搬送するため
の材料搬送手段を備えた請求項1または2に記載のコン
クリートプラント船。
3. The concrete plant ship according to claim 1, further comprising material transport means for transporting the concrete material from a material yard installed on land to the concrete plant.
【請求項4】 前記台船と岸壁とを連絡してアジテータ
車を通行させるためのランプウエイを備えた請求項1〜
3のいずれか一項に記載のコンクリートプラント船。
4. A ramp way for communicating the barge with a quay and passing an agitator vehicle therethrough.
4. The concrete plant ship according to any one of items 3 to 5.
【請求項5】 前記コンクリートプラントで製造された
コンクリートを打設現場に直接供給するためのディスト
リビュータを備えた請求項1〜4のいずれか一項に記載
のコンクリートプラント船。
5. The concrete plant ship according to claim 1, further comprising a distributor for directly supplying the concrete produced by the concrete plant to a casting site.
【請求項6】 プレクーリング用の冷却プラントを備え
た請求項1〜5のいずれか一項に記載のコンクリートプ
ラント船。
6. The concrete plant ship according to claim 1, further comprising a cooling plant for pre-cooling.
【請求項7】 海水からコンクリート製造に用いる淡水
を生成する淡水化装置を備えた請求項1〜6のいずれか
一項に記載のコンクリートプラント船。
7. The concrete plant ship according to any one of claims 1 to 6, further comprising a desalination apparatus for producing fresh water used for concrete production from seawater.
【請求項8】 コンクリート材料を収容する材料ストッ
カを備えた請求項1〜7のいずれか一項に記載のコンク
リートプラント船。
8. The concrete plant ship according to claim 1, further comprising a material stocker for storing a concrete material.
JP28806997A 1997-10-21 1997-10-21 Concrete plant ship Pending JPH11115882A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP28806997A JPH11115882A (en) 1997-10-21 1997-10-21 Concrete plant ship

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP28806997A JPH11115882A (en) 1997-10-21 1997-10-21 Concrete plant ship

Publications (1)

Publication Number Publication Date
JPH11115882A true JPH11115882A (en) 1999-04-27

Family

ID=17725421

Family Applications (1)

Application Number Title Priority Date Filing Date
JP28806997A Pending JPH11115882A (en) 1997-10-21 1997-10-21 Concrete plant ship

Country Status (1)

Country Link
JP (1) JPH11115882A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011226223A (en) * 2010-04-23 2011-11-10 Fudo Tetra Corp Floating soil improving boat
CN104846813A (en) * 2015-04-27 2015-08-19 浙江宏力阳生态建设股份有限公司 Stirring pile ship used for underwater soft foundation construction
JP2015160337A (en) * 2014-02-26 2015-09-07 東亜建設工業株式会社 Ready mixed concrete weighing device and installation device for mounting on vessel, and working ship

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011226223A (en) * 2010-04-23 2011-11-10 Fudo Tetra Corp Floating soil improving boat
JP2015160337A (en) * 2014-02-26 2015-09-07 東亜建設工業株式会社 Ready mixed concrete weighing device and installation device for mounting on vessel, and working ship
CN104846813A (en) * 2015-04-27 2015-08-19 浙江宏力阳生态建设股份有限公司 Stirring pile ship used for underwater soft foundation construction

Similar Documents

Publication Publication Date Title
RU2471697C2 (en) Method for reloading materials from offshore wharf using transhipment barge and transhipment system
CN107075824A (en) Sea bed terminal for offshore activity
JP2000505166A (en) Modular caisson for use in port construction, expansion and modernization
CN101597896A (en) Adopt large-scale side's body barge to build the method for man-made island jackstone dike island, off-lying sea wall
US5853264A (en) Bridge, dock and pier shoring-up bulk-delivery floating conveyor unit
JPH11115882A (en) Concrete plant ship
CN217414491U (en) Concrete production platform on water
JP5658168B2 (en) Deep water port
JP2000345544A (en) Concrete production facilities
KR100724055B1 (en) Material loading and unloading system and operation ship thereof
JP3276617B2 (en) Marine landfill method using sea sand
JPH0521375Y2 (en)
CN212859942U (en) Portable concrete system of stirring on water mixes device and system
JP2895595B2 (en) Landfill work boat
JP7300218B1 (en) mooring equipment
WO2008013505A1 (en) A bulk cargo transportation system
JPS6351512A (en) Method and base ship with frame for direct spreading of soil, crushed stone, and sand
JP3926027B2 (en) Caisson construction method
JPS6175090A (en) Marine transport for offshore structure preparatorily prepared
JPS63255195A (en) Dredger consisting of two floaters
CN116104093A (en) Mixing and pumping pouring device and method for underwater foundation scour protection fluid solidified soil
JPS58168734A (en) Reclamation work
CN118390554A (en) Caisson shipment installation construction method
JPS5815356B2 (en) A device on a ship that raises and lowers the open-bottom hold.
KR100891976B1 (en) System for transferring sea soil directly and method thereof

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040928

A131 Notification of reasons for refusal

Effective date: 20061128

Free format text: JAPANESE INTERMEDIATE CODE: A131

A02 Decision of refusal

Effective date: 20070417

Free format text: JAPANESE INTERMEDIATE CODE: A02