JPH108420A - Method for erecting steel tube for tube bridge of suspension bridge type - Google Patents
Method for erecting steel tube for tube bridge of suspension bridge typeInfo
- Publication number
- JPH108420A JPH108420A JP8161836A JP16183696A JPH108420A JP H108420 A JPH108420 A JP H108420A JP 8161836 A JP8161836 A JP 8161836A JP 16183696 A JP16183696 A JP 16183696A JP H108420 A JPH108420 A JP H108420A
- Authority
- JP
- Japan
- Prior art keywords
- connecting means
- support ring
- carrying roller
- steel tube
- steel pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、無補剛モノケーブ
ル吊橋(管橋)の鋼管架設方法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of erection of a steel pipe for a non-stiffened mono-cable suspension bridge (tube bridge).
【0002】[0002]
【従来の技術】吊橋型式管橋の鋼管架設では、例えば実
公昭39−1178号公報に支持リングに架設用ローラ
を取り付けた支持装置が開示されている。このような従
来技術の支持リングと架設用搬送ローラの取付例を図5
(側面図)、図6(正面図)に示した。搬送ローラ3の
ローラフレーム10は取付部11をボルトナット接合部
12、13によって、支持リング2にボルト結合されて
おり、鋼管1と支持リング2の間に挟まれている。この
ため搬送ローラ3を撤去するときには、鋼管1を別途吊
上げるか又は支持リング2を吊り下げる必要がある。い
ずれにしても吊ロープ7に余分な荷重が作用し好ましく
ない。また搬送ローラ3の撤去時は搬送ローラ3と鋼管
1との間隙に手を差し込む必要があり、手を挟む危険が
ある。また、撤去作業に手間がかかる。2. Description of the Related Art In the steel pipe erection of a suspension bridge type pipe bridge, for example, Japanese Utility Model Publication No. 39-1178 discloses a support device in which a erection roller is attached to a support ring. FIG. 5 shows an example of mounting such a prior art support ring and an installation transport roller.
(Side view) and FIG. 6 (front view). The roller frame 10 of the transport roller 3 has the mounting portion 11 bolted to the support ring 2 by bolt-nut joints 12 and 13, and is sandwiched between the steel pipe 1 and the support ring 2. For this reason, when removing the transport roller 3, it is necessary to suspend the steel pipe 1 separately or suspend the support ring 2. In any case, an extra load acts on the hanging rope 7, which is not preferable. Also, when removing the transport roller 3, it is necessary to insert a hand into the gap between the transport roller 3 and the steel pipe 1, and there is a risk of pinching the hand. In addition, it takes time to remove.
【0003】[0003]
【発明が解決しようとする課題】吊橋のメインケーブル
から鋼管支持部例えば支持リングを吊下し、この支持リ
ングを通って鋼管を片側から送り出していく場合、従来
の技術では単に吊下されている支持リング同士の間隔が
変位するという問題があり、また、搬送ローラを撤去す
る時の施工性が悪く手間がかかるという問題点があっ
た。In the prior art, when a steel pipe support, for example, a support ring is suspended from a main cable of a suspension bridge, and the steel pipe is sent out from one side through the support ring, the prior art is simply suspended. There is a problem that the interval between the support rings is displaced, and there is a problem that workability when removing the transport roller is poor and time is required.
【0004】本発明は、支持リングの変位を防止し、支
持リングと支持リングとの中間に鋼管架設用搬送ローラ
を設置することにより、前記の問題点を解決する技術を
提供することを目的とする。An object of the present invention is to provide a technique for solving the above-mentioned problems by preventing displacement of a support ring and installing a transfer roller for erection of a steel pipe between support rings. I do.
【0005】[0005]
【課題を解決するための手段】本発明は、前記問題点を
解決するために開発されたもので、支持リングの間隔を
保持すると共に、隣接支持リング相互間に搬送ローラを
設置することにより、支持リング同士の間隔の変位をな
くし、撤去時の施工性を向上させる方法を提案したもの
である。DISCLOSURE OF THE INVENTION The present invention has been developed to solve the above-mentioned problems. The present invention maintains the distance between the support rings and installs a transport roller between adjacent support rings. The present invention proposes a method for eliminating the displacement of the interval between the support rings and improving the workability at the time of removal.
【0006】すなわち本発明は吊橋型式管橋の支柱に架
け渡されたメインケーブルから吊下された多数の支持リ
ング内を通って一方の側から他方の側に鋼管を架設する
場合に適用されるものであって、前記多数の支持リング
を所定の間隔に保持する連結手段を設け、この連結手段
上の隣接支持リング相互の中間部に搬送ローラを設置
し、鋼管を搬送ローラ上を搬送して全スパンに鋼管を架
設し、架設後前記連結手段を撤去し、支持リング内に鋼
管を架設することを特徴とする吊橋型式管橋の鋼管架設
方法である。That is, the present invention is applied to a case where a steel pipe is erected from one side to the other side through a plurality of support rings suspended from a main cable suspended over a column of a suspension bridge type pipe bridge. A connecting means for holding the plurality of support rings at predetermined intervals, installing a transfer roller at an intermediate portion between adjacent support rings on the connection means, transferring the steel pipe on the transfer roller. A method of erection of a steel pipe for a suspension bridge type pipe bridge, wherein steel pipes are erected on all spans, the connecting means is removed after erection, and the steel pipe is erected in a support ring.
【0007】[0007]
【発明の実施の形態】図1に本発明方法の実施例の側面
図を示した。吊ロープ7で吊下された支持リング2,
2,…を仮止め連結手段5にヒンジ連結具4で取付け
る。仮留め連結手段5は簡易なフレームでよく、例え
ば、左右一双の形鋼等を適宜横つなぎ材で結合した長尺
のフレームで、支持リング位置にヒンジ連結具4を備え
ている。連結手段5により、支持リングの間隔を一定に
保持することができる。ヒンジ連結具4の例を図4に示
した。連結手段5はリング2内に支持されるヒンジ連結
具4にボルトナット8によって結合されている。仮止め
連結手段5は互いにヒンジ連結していることにより、支
持リング2が上下に変位しても対応可能である。またこ
のヒンジ連結具4と支持リング2とはボルトナット8で
連結されており、取付撤去が容易である。この仮止め連
結手段5は搬送ローラ支持部材を兼ね、隣接する支持リ
ング用の中間に搬送ローラ3を載設している。鋼管1は
搬送ローラ3上を送り出し方向6に牽引され、支持リン
グ2内を移動する。図2は図1の正面図で鋼管1が支持
リング2内を通って搬送ローラ3上を進行する状態を示
している。図3は平面図で鋼管のない状態の支持リング
2、連結手段5、搬送ローラ3を示したものである。FIG. 1 shows a side view of an embodiment of the method of the present invention. A support ring 2 suspended by a suspension rope 7,
Are attached to the temporary connection means 5 with the hinge connection tool 4. The temporary fastening connecting means 5 may be a simple frame, for example, a long frame in which a pair of right and left shaped steel members or the like are appropriately connected by a horizontal connecting member, and the hinge connecting tool 4 is provided at a support ring position. By the connecting means 5, the distance between the support rings can be kept constant. FIG. 4 shows an example of the hinge connector 4. The connecting means 5 is connected to a hinge connecting tool 4 supported in the ring 2 by a bolt and nut 8. Since the temporary fixing connection means 5 are hingedly connected to each other, even if the support ring 2 is vertically displaced, it is possible to cope with the displacement. The hinge connector 4 and the support ring 2 are connected by bolts and nuts 8 so that attachment and removal are easy. The temporary fixing connecting means 5 also serves as a transport roller support member, and has the transport roller 3 mounted at an intermediate position between adjacent support rings. The steel pipe 1 is pulled on the conveying roller 3 in the feeding direction 6 and moves in the support ring 2. FIG. 2 is a front view of FIG. 1 and shows a state in which the steel pipe 1 travels on the transport roller 3 through the inside of the support ring 2. FIG. 3 is a plan view showing the support ring 2, the connecting means 5, and the transport roller 3 without steel pipe.
【0008】本発明の搬送ローラは支持リング2の中間
部に配設され、連結手段5上に設置されているので、図
5、図6に示す従来の搬送ローラの撤去に手間がかかる
構造と比較すると、連結手段5と共にきわめて容易に取
付、撤去ができる。以上のように本発明は支持リング
2、2を連結手段5で仮留めし、支持リング2、2の中
間に搬送ローラ3を設置することによって、支持リング
2、2の間隔の修正が不要となり、かつ搬送ローラ3の
撤去時の施工性の格段の向上を図ることができる。Since the transport roller of the present invention is disposed at the intermediate portion of the support ring 2 and is installed on the connecting means 5, it takes time to remove the conventional transport roller shown in FIGS. In comparison, attachment and removal together with the connecting means 5 can be performed very easily. As described above, according to the present invention, by temporarily fixing the support rings 2 and 2 with the connecting means 5 and installing the transport roller 3 between the support rings 2 and 2, it is not necessary to correct the interval between the support rings 2 and 2. In addition, the workability at the time of removing the transport roller 3 can be significantly improved.
【0009】[0009]
【発明の効果】本発明は、無補剛モノケーブル吊り橋
(管橋)の鋼管架設において、支持リング連結装置を設
け、支持リングの中間に搬送ローラを設置したから、支
持リング同士の間隔の保持、が確実にできることとな
り、搬送ローラの撤去時の施工性の著しく向上するとい
う効果がある。According to the present invention, in the steel pipe erection of a non-stiffened mono-cable suspension bridge (pipe bridge), a support ring connecting device is provided and a transport roller is installed in the middle of the support ring, so that the distance between the support rings can be maintained. And the workability at the time of removing the transport roller is significantly improved.
【図1】実施例の側面図である。FIG. 1 is a side view of an embodiment.
【図2】実施例の正面図である。FIG. 2 is a front view of the embodiment.
【図3】実施例の平面図である。FIG. 3 is a plan view of the embodiment.
【図4】ヒンジ連結具の一例を示す説明図である。FIG. 4 is an explanatory view showing an example of a hinge connector.
【図5】従来の支持リングの側面図である。FIG. 5 is a side view of a conventional support ring.
【図6】従来の支持リングの正面図である。FIG. 6 is a front view of a conventional support ring.
1 鋼管 2 支持リング 3 搬送ローラ 4 ヒンジ連結具 5 連結手段 6 送り出し方向 7 吊ロープ 8 ボルトナット 10 ローラフレーム 11 取付部 12,13 ボルトナット結合部 DESCRIPTION OF SYMBOLS 1 Steel pipe 2 Support ring 3 Conveyance roller 4 Hinge connection tool 5 Connection means 6 Sending direction 7 Suspension rope 8 Bolt nut 10 Roller frame 11 Mounting part 12, 13 Bolt nut connection part
Claims (1)
した多数の支持リング内を通って鋼管を架設するに当
り、前記多数の支持リングを所定の間隔に保持する連結
手段を設け、該連結手段上の隣接支持リング相互の中間
部に搬送ローラを設置し、鋼管を搬送ローラ上を搬送し
て全スパンに鋼管を架設し、架設後前記連結手段を撤去
し、支持リング内に鋼管を架設することを特徴とする吊
橋型式管橋の鋼管架設方法。When connecting a steel pipe through a plurality of support rings suspended from a main cable of a suspension bridge type pipe bridge, connecting means for holding the plurality of support rings at predetermined intervals is provided. A transport roller is installed at an intermediate portion between the adjacent support rings on the means, the steel pipe is transported on the transport roller, the steel pipe is erected over the entire span, and after the erection, the connecting means is removed, and the steel pipe is erected in the support ring. A method for erection of steel pipes of a suspension bridge type pipe bridge.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP16183696A JP3751366B2 (en) | 1996-06-21 | 1996-06-21 | Steel pipe erection method for suspension bridge type pipe bridge |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP16183696A JP3751366B2 (en) | 1996-06-21 | 1996-06-21 | Steel pipe erection method for suspension bridge type pipe bridge |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH108420A true JPH108420A (en) | 1998-01-13 |
JP3751366B2 JP3751366B2 (en) | 2006-03-01 |
Family
ID=15742863
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP16183696A Expired - Fee Related JP3751366B2 (en) | 1996-06-21 | 1996-06-21 | Steel pipe erection method for suspension bridge type pipe bridge |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3751366B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109024289A (en) * | 2018-08-01 | 2018-12-18 | 中交公局第二工程有限公司 | A kind of steel strand wires whole strand pricking method |
CN114232504A (en) * | 2022-01-24 | 2022-03-25 | 岳西县彩虹瀑布旅游有限公司 | Construction method of glass plank road in scenic spot |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS63246584A (en) * | 1987-04-01 | 1988-10-13 | 三菱電線工業株式会社 | Method of laying long-sized piping made of resin |
JPH03253602A (en) * | 1990-03-01 | 1991-11-12 | Kawasaki Steel Corp | Erection of suspended type bridge for pipe |
JPH04228709A (en) * | 1990-12-27 | 1992-08-18 | Kawasaki Steel Corp | Erecting method for un stiffened suspension pipe bridge |
-
1996
- 1996-06-21 JP JP16183696A patent/JP3751366B2/en not_active Expired - Fee Related
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS63246584A (en) * | 1987-04-01 | 1988-10-13 | 三菱電線工業株式会社 | Method of laying long-sized piping made of resin |
JPH03253602A (en) * | 1990-03-01 | 1991-11-12 | Kawasaki Steel Corp | Erection of suspended type bridge for pipe |
JPH04228709A (en) * | 1990-12-27 | 1992-08-18 | Kawasaki Steel Corp | Erecting method for un stiffened suspension pipe bridge |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109024289A (en) * | 2018-08-01 | 2018-12-18 | 中交公局第二工程有限公司 | A kind of steel strand wires whole strand pricking method |
CN114232504A (en) * | 2022-01-24 | 2022-03-25 | 岳西县彩虹瀑布旅游有限公司 | Construction method of glass plank road in scenic spot |
Also Published As
Publication number | Publication date |
---|---|
JP3751366B2 (en) | 2006-03-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
NZ241415A (en) | Gas turbine engine transporting frames | |
EP1050688A2 (en) | Connecting element for rail sections of exhaust extraction devices | |
JP7100896B2 (en) | How to install the wheel unit in the center and the wheel unit guide device in the center | |
JPH108420A (en) | Method for erecting steel tube for tube bridge of suspension bridge type | |
JP6819724B2 (en) | Passenger conveyor parts transport tools and parts transport methods using them | |
US6312193B1 (en) | Coupling system for subsea pipelines and method for establishing such system | |
JP2000186310A (en) | Method for erection of structure | |
JP3590852B2 (en) | Mounting jig for small crane for pole mounting | |
JP2838760B2 (en) | How to relocate a suspended scaffold | |
JP2951228B2 (en) | Carriage rail end connection device | |
JP3428377B2 (en) | Transfer equipment | |
JPH08282958A (en) | Hanging device | |
JPH02266810A (en) | Cable hanger | |
JPH10192434A (en) | Hose bridge | |
JPS5854819Y2 (en) | Separators for utility pole reconstruction and new installation | |
US4286523A (en) | System for supporting overhead trolley rail | |
CN216663862U (en) | Construction system for erecting main beam of large-span cable-stayed bridge | |
JPH07145602A (en) | Rail way for transferring pipe | |
JP3087191U (en) | Conveyor unit with unit assembly | |
JP6678484B2 (en) | Furnace frame mounting method and jig used for the method | |
JPH02131310A (en) | Stringing wheel | |
JPH11190199A (en) | Segment conveying device in tunnel | |
JPS6245456Y2 (en) | ||
JPS63134702A (en) | Method for aerial assembling and suspension of moving type suspension scaffold | |
CN114232487A (en) | Construction system for erecting main beam of large-span cable-stayed bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20050802 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20051206 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20051207 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313111 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081216 Year of fee payment: 3 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091216 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091216 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101216 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111216 Year of fee payment: 6 |
|
LAPS | Cancellation because of no payment of annual fees |