Construction method of footing pileInfo
- Publication number
- JPH1072825A JPH1072825A JP23007496A JP23007496A JPH1072825A JP H1072825 A JPH1072825 A JP H1072825A JP 23007496 A JP23007496 A JP 23007496A JP 23007496 A JP23007496 A JP 23007496A JP H1072825 A JPH1072825 A JP H1072825A
- Authority
- JP
- Japan
- Prior art keywords
- pile
- steel pipe
- knotted
- pipe pile
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本願発明は、節杭と鋼管杭を
長手方向に接合してなる基礎杭の施工方法に関するもの
である。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a foundation pile formed by joining a nodal pile and a steel pipe pile in a longitudinal direction.
【0002】[0002]
【従来の技術】杭外周部に節状の突起を形成した節杭を
施工する場合の施工方法としては、節杭の周囲に砕石等
を充填しながらディーゼルハンマー等の打撃手段により
地盤中に打ち込んで行くのが最も簡単で、経済的な方法
である。しかし、振動、騒音等の問題から、あらかじめ
孔を掘って埋め込む方法が主流となっている。2. Description of the Related Art As a construction method for constructing a knotted pile having knotted protrusions on the outer periphery of a pile, a method of hammering the knotted stone into the ground with a hitting means such as a diesel hammer while filling the knotted pile with the crushed stones is used. It is the easiest and most economical way to go by. However, due to problems such as vibration and noise, a method of digging and embedding a hole in advance has become mainstream.
【0003】これに対し、二重管式のケーシングを利用
し、オーガーを兼ねたケーシングによる削孔とケーシン
グ内での打撃を併用した低振動、低騒音の施工法とし
て、液状化抑止も目的とした節杭砕石ドレーン工法と呼
ばれる工法が開発されている。[0003] On the other hand, the use of a double-pipe type casing, drilling by a casing that also serves as an auger, and hitting in the casing together with low vibration and low noise are intended to prevent liquefaction. A method called the crushed stone crushed stone drain method has been developed.
【0004】一方、既製杭を長手方向に継ぎ足す場合、
従来は同種の既製杭を継ぎ足して行くのが通常であった
が、本願出願人の先の出願に係る特開平2−23241
6号公報には、コンクリート製の節杭の上部に鋼管杭等
の円筒パイルを接合したものが記載されている。これ
は、大きな周面支持力は期待できないが曲げ耐力が大き
い鋼管杭と、曲げ耐力はあまり期待できないが周面支持
力に優れた節杭といった杭性能の異なる杭どうしを長手
方向に接続したものである。[0004] On the other hand, when adding a pre-made pile in the longitudinal direction,
Conventionally, the same type of ready-made stakes were usually added. However, Japanese Patent Application Laid-Open No. Hei.
No. 6 discloses a structure in which a cylindrical pile such as a steel pipe pile is joined to the upper part of a concrete knotted pile. This is a longitudinal connection between piles with different pile performance, such as steel pipe piles that cannot be expected to have large peripheral bearing capacity but have large bending strength, and knotted piles that cannot be expected to have much bending strength but have excellent peripheral bearing capacity. It is.
【0005】地盤の条件や上部構造との関係でも異なる
が、最も一般的な形態としては、地震等に対しては上層
地盤において比較的大きな曲げ耐力が要求され、下層地
盤において周面支持力を含めた鉛直支持力が要求され、
その意味で上記発明の基礎杭は合理的な構造を与えてい
る。[0005] Although different depending on the condition of the ground and the relationship with the upper structure, in the most common form, a relatively large bending strength is required in the upper ground against an earthquake or the like, and the peripheral bearing capacity in the lower ground is required. Vertical support capacity is required,
In that sense, the foundation pile according to the invention has a reasonable structure.
【0006】なお、同公報には、施工方法の例として、
基礎杭を継ぎ足しながらディーゼルハンマー等の打撃手
段により打設する場合と、セメントミルク工法等の先掘
り工法で施工する場合が説明されている。[0006] In this publication, as an example of the construction method,
There is described a case in which the foundation pile is added by a hitting means such as a diesel hammer while being added, and a case in which the foundation pile is constructed by a pre-drilling method such as a cement milk method.
【0007】[0007]
【発明が解決しようとする課題】コンクリート等からな
る節杭は、鉛直荷重や鉛直方向の打撃力に強いため、打
撃による打設が最も簡単な施工方法であるが、打撃の場
合、上述のように振動、騒音の問題があり、住宅地等で
の施工が制限される。A knotted pile made of concrete or the like is the simplest construction method because it is strong against a vertical load and a hitting force in the vertical direction. There is a problem of vibration and noise, and construction in residential areas is restricted.
【0008】また、上方に鋼管杭を継ぎ足した状態で、
その頭部に打撃力を加えると、鋼管杭の部分が変形して
しまい、打ち込みが不可能となる恐れがある。[0008] Further, in a state where a steel pipe pile is added upward,
If a striking force is applied to the head, a portion of the steel pipe pile may be deformed, and it may become impossible to drive.
【0009】本願発明は、上述のような課題の解決を図
ったものであり、節杭と鋼管杭を継ぎ足した基礎杭につ
いて、その機能・特徴を活かした低振動、低騒音の効率
的かつ経済的な施工方法を提供することを目的としてい
る。SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems, and provides a low-vibration, low-noise efficient and economical low-noise and low-noise foundation pile made up of a joint pile and a steel pipe pile. The purpose is to provide an efficient construction method.
【0010】[0010]
【課題を解決するための手段】本願発明は、節杭と鋼管
杭を、節杭の頭部において長手方向に接合してなる基礎
杭の施工方法において、ドロップハンマー、ディーゼル
ハンマー等の杭打撃手段を節杭に接続した鋼管杭内に挿
入し、鋼管杭内部より節杭の頭部を打撃することで、節
杭とこれに接続された鋼管杭とを地盤中に同時に打設し
て行くことを特徴とする。SUMMARY OF THE INVENTION The present invention relates to a method for constructing a foundation pile in which a knotted pile and a steel pipe pile are joined in the longitudinal direction at the head of the knotted pile. Into the steel pipe pile connected to the knotted pile, and hitting the head of the knotted pile from inside the steel pipe pile, thereby simultaneously casting the knotted pile and the steel pipe pile connected to it into the ground It is characterized by.
【0011】なお、本願発明における杭打設のための打
撃は、鋼管杭についてはその底部に対する打撃、節杭に
ついてはその頭部に対する打撃となるが、節杭の頭部に
直接的に打撃力が加わる場合に限らず、間に介在するも
のがあってもよい。In the present invention, the impact for driving the pile is such that the steel pipe pile is hit on the bottom and the knot pile is hit on the head, but the hitting force is directly applied to the head of the knot pile. However, the present invention is not limited to this case, and there may be something intervening.
【0012】節杭と鋼管杭の接合については、種々の形
式が考えられるが、最も簡単なものとしては、それぞれ
の杭端に鋼板等からなる端板を設け、端板どうしの溶接
により接続する形式等を利用することができる。この
他、ネジ式の接合手段等を用いることもできる。There are various types of joints between the knotted pile and the steel pipe pile, but the simplest one is to provide an end plate made of a steel plate or the like at each pile end and connect the end plates by welding. Formats can be used. In addition, a screw type joining means or the like can be used.
【0013】また、これらの杭は打設前にあからじめ接
合しておくこともできるが、杭の打設の進行に合わせて
順次、継ぎ足して行くこともできる。後者の場合、鋼管
杭が接合される前段階においては、単なる節杭の施工と
なり、従来、知られている節杭に関する種々の施工方法
を利用、併用することができる。Although these piles can be joined in advance before driving, they can be added sequentially as the driving of the pile proceeds. In the latter case, prior to the joining of the steel pipe piles, the construction of the knotted piles is simply performed, and various conventionally known construction methods for knotted piles can be used and used together.
【0014】また、節杭の場合、施工性、周面摩擦力の
確保や液状化抑止のための排水路の形成等の目的で、杭
体の外周部に砂、砂利、砕石等の充填材を充填する場合
が多く、本願の請求項2はその場合を限定したものであ
る。In the case of knotted piles, sand, gravel, crushed stones, and other fillers are provided on the outer periphery of the pile for the purpose of ensuring workability, securing the frictional force on the peripheral surface, and forming drainage channels for preventing liquefaction. Is often filled, and claim 2 of the present application limits that case.
【0015】[0015]
【実施の形態】図1(a) 〜(d) は本願発明の基礎杭の施
工方法の一実施形態における施工手順を示したものであ
る。1 (a) to 1 (d) show a construction procedure in one embodiment of a method for constructing a foundation pile according to the present invention.
【0016】まず節杭1を従来工法により、砂、砂利、
砕石等の充填材3を充填しつつ、地盤10中へ所定深さ
まで打設する。この打設は、ディーゼルハンマーやドロ
ップハンマー等の打撃手段を用いることも可能である
が、低騒音、低振動が要求される場所では、埋込み工
法、先掘り工法や節杭砕石ドレーン工法で打設すること
が望ましい(図1(a) 参照)。First, the knotted pile 1 is sanded, gravel,
It is poured into the ground 10 to a predetermined depth while filling the filler 3 such as crushed stone. It is possible to use a hammer such as a diesel hammer or a drop hammer for this casting.However, in places where low noise and low vibration are required, the casting is performed by embedding, excavation, or crushed stone drainage method. (See FIG. 1 (a)).
【0017】次に、所定深さまで打設した節杭1の頭部
に鋼管杭2を接合し、鋼管杭2内に挿入したドロップハ
ンマー等のハンマー4で、節杭1の頭部を打撃して地盤
10中への打込みを行う(図1(b),(c)参照)。Next, a steel pipe pile 2 is joined to the head of the knotted pile 1 which has been driven to a predetermined depth, and the head of the knotted pile 1 is hit with a hammer 4 such as a drop hammer inserted into the steel pipe pile 2. Into the ground 10 (see FIGS. 1 (b) and 1 (c)).
【0018】所定深さまで打込みを行うことで、節杭1
と鋼管杭2とからなる基礎杭1の施工が完了する(図1
(d) 参照)。By driving to a predetermined depth, the knots 1
The construction of the foundation pile 1 composed of the steel pipe pile 2 and the steel pipe pile 2 is completed (Fig. 1
(d)).
【0019】なお、上述の例では、最初に節杭1のみを
打設して、その後鋼管杭2を接続しているが、あらかじ
め鋼管杭2を接続した状態で、地盤10中への打設を行
うことも可能である。In the above-mentioned example, only the knotted pile 1 is first set and then the steel pipe pile 2 is connected. However, the steel pipe pile 2 is connected in advance and the ground pile 10 is set. It is also possible to do.
【0020】また、図では節杭1および鋼管杭2がそれ
ぞれ1本の場合を示しているが、必要に応じそれぞれ長
手方向に複数本継ぎ足すものとする。Although FIG. 1 shows a case where each of the joint pile 1 and the steel pipe pile 2 is one, a plurality of joints are added in the longitudinal direction as necessary.
【0021】図2は、本願発明で用いる基礎杭の一例を
示したもので、下層の節杭1は外周面に複数の節状突起
1aが形成され、下端および上端に端板1b,1cを取
り付けてある。図示した例はコンクリート製のものであ
るが、複合パイル等でもよい。上層の鋼管杭2は、通常
の鋼管杭の下端に節杭1との接続のための端板2aを設
け、溶接により接合できるようにしたものであるが、接
合部の構造もこれに限定されない。FIG. 2 shows an example of a foundation pile used in the present invention. A lower knot pile 1 has a plurality of knot-like projections 1a formed on the outer peripheral surface, and end plates 1b and 1c are provided at lower and upper ends. It is attached. The illustrated example is made of concrete, but may be a composite pile or the like. The upper steel pipe pile 2 is provided with an end plate 2a for connection with the knotted pile 1 at the lower end of a normal steel pipe pile so that it can be joined by welding, but the structure of the joint is not limited to this. .
【0022】図3(a),(b) は本願発明で用いる基礎杭の
形態を示したもので、図3(a) は、図1、図2と同様、
節杭1の節状突起1aの外径が鋼管杭2の外径より大き
い場合である。図3(b) は節杭1の節状突起1aの外径
と鋼管杭2の外径がほぼ等しい場合であり、節杭1と鋼
管杭2をテーパーを有する接続管5を介して接続してい
る。FIGS. 3 (a) and 3 (b) show the form of the foundation pile used in the present invention, and FIG. 3 (a) is similar to FIGS.
This is a case where the outer diameter of the knot-like projection 1a of the knot 1 is larger than the outer diameter of the steel pipe pile 2. FIG. 3B shows a case where the outer diameter of the knot-like projection 1a of the knotted pile 1 and the outer diameter of the steel pipe pile 2 are substantially equal. ing.
【0023】[0023]
【発明の効果】 長手方向に接続した節杭と鋼管杭について、鋼管杭内
部に挿入した打撃手段により打撃力を与えており、下層
の節杭部分については頭部の打撃に相当し、かつ節杭は
鉛直荷重に対し十分な圧縮耐力を有するので、破損する
ことなく、効率よく打ち込みが行なえる。一方、上層の
鋼管杭については、節杭の打ち込みにより地盤中に引き
込まれる形、あるいは底打ちの形であるため、鋼管杭に
作用する力は引張力であり、破損する恐れがない。According to the present invention, a hitting force is applied to a joint pile and a steel pipe pile connected in the longitudinal direction by a striking means inserted into the inside of the steel pipe pile. Since the pile has sufficient compressive strength against vertical load, it can be driven efficiently without breaking. On the other hand, since the upper steel pipe pile has a shape of being pulled into the ground by driving in a nodal pile or a bottom striking shape, the force acting on the steel pipe pile is a tensile force, and there is no possibility of breakage.
【0024】打撃は鋼管内底部で行われるため、低騒
音、低振動の施工が可能である。Since the impact is performed at the inner bottom of the steel pipe, low noise and low vibration can be performed.
【0025】打撃力あるいは打撃回数と押込量との関
係等から、基礎杭一本ごとに支持力の確証が得られる。From the relation between the striking force or the number of striking times and the pushing amount, etc., it is possible to confirm the supporting force for each foundation pile.
【0026】打撃力によって杭を打ち込むため、埋込
み工法等に比べ大きな支持力がとれる。Since the pile is driven by the impact force, a large supporting force can be obtained as compared with the embedding method or the like.
【図1】(a) 〜(d) は本願発明の基礎杭の施工方法の一
実施形態における施工手順を示す鉛直断面図である。1 (a) to 1 (d) are vertical sectional views showing a construction procedure in an embodiment of a method for constructing a foundation pile according to the present invention.
【図2】本願発明で用いる基礎杭の一実施形態を示す鉛
直断面図である。FIG. 2 is a vertical sectional view showing an embodiment of a foundation pile used in the present invention.
【図3】(a),(b) はそれぞれ本願発明で用いる基礎杭の
異なる形態を示す鉛直断面図である。3 (a) and 3 (b) are vertical sectional views showing different forms of a foundation pile used in the present invention.
1…節杭、1a…節状突起、1b,1c…端板、2…鋼
管杭、2a…端板、3…充填材、4…ハンマー、5…接
続管、10…地盤DESCRIPTION OF SYMBOLS 1 ... Knotted pile, 1a ... Knotted projection, 1b, 1c ... End plate, 2 ... Steel pipe pile, 2a ... End plate, 3 ... Filler, 4 ... Hammer, 5 ... Connection pipe, 10 ... Ground
Claims (2)
鋼管杭を、前記節杭の頭部において長手方向に接合し、
杭打撃手段を前記鋼管杭内に挿入して鋼管杭内部より前
記節杭の頭部を打撃することにより、前記節杭および該
節杭に接続された鋼管杭を地盤中に同時に打設して行く
ことを特徴とする基礎杭の施工方法。1. A knot pile and a steel pipe pile each having a knot-shaped protrusion formed on the outer periphery of the pile, and joined in a longitudinal direction at a head of the knot pile,
By inserting a pile hitting means into the steel pipe pile and hitting the head of the node pile from inside the steel pipe pile, the node pile and the steel pipe pile connected to the node pile are simultaneously driven into the ground. Construction method of foundation pile characterized by going.
杭の外周部には、砂、砂利または砕石等の充填材を充填
する請求項1記載の基礎杭の施工方法。2. The method for constructing a foundation pile according to claim 1, wherein a filler such as sand, gravel or crushed stone is filled in the outer peripheral portions of the joint pile and the steel pipe pile joined in the longitudinal direction.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP23007496A JPH1072825A (en) | 1996-08-30 | 1996-08-30 | Construction method of footing pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP23007496A JPH1072825A (en) | 1996-08-30 | 1996-08-30 | Construction method of footing pile |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH1072825A true JPH1072825A (en) | 1998-03-17 |
Family
ID=16902145
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP23007496A Pending JPH1072825A (en) | 1996-08-30 | 1996-08-30 | Construction method of footing pile |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH1072825A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102966089A (en) * | 2012-11-19 | 2013-03-13 | 中交四航工程研究院有限公司 | Plate plug method capable of realizing vibratory compaction |
CN104389305A (en) * | 2014-11-18 | 2015-03-04 | 中淳高科桩业股份有限公司 | Sand-filled bamboo-joint pile and construction method thereof |
JP2018111961A (en) * | 2017-01-10 | 2018-07-19 | 旭化成建材株式会社 | Pile driving method |
CN113944158A (en) * | 2021-11-02 | 2022-01-18 | 浙大宁波理工学院 | Anti-pulling type pipe pile and construction process thereof |
-
1996
- 1996-08-30 JP JP23007496A patent/JPH1072825A/en active Pending
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102966089A (en) * | 2012-11-19 | 2013-03-13 | 中交四航工程研究院有限公司 | Plate plug method capable of realizing vibratory compaction |
CN104389305A (en) * | 2014-11-18 | 2015-03-04 | 中淳高科桩业股份有限公司 | Sand-filled bamboo-joint pile and construction method thereof |
JP2018111961A (en) * | 2017-01-10 | 2018-07-19 | 旭化成建材株式会社 | Pile driving method |
CN113944158A (en) * | 2021-11-02 | 2022-01-18 | 浙大宁波理工学院 | Anti-pulling type pipe pile and construction process thereof |
CN113944158B (en) * | 2021-11-02 | 2023-01-10 | 浙大宁波理工学院 | Anti-pulling type pipe pile and construction process thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101147510B1 (en) | Complex pile with improved end bearing capacity and piling method of complex pile using the same | |
CA2682816A1 (en) | Spiral steel pile | |
KR20070050516A (en) | Structure method of reinforcing head for hollow-concrete piles and its structure | |
JP3284110B2 (en) | Cover plate for steel pipe pile | |
JP3756385B2 (en) | Composite pile and its construction method | |
JPH1072825A (en) | Construction method of footing pile | |
JP2003119775A (en) | Construction of foundation pile | |
JP3649717B2 (en) | Joints and structures for joining steel pipe pile heads to concrete foundations | |
JPH02232416A (en) | Foundation pile structure | |
KR101124203B1 (en) | Pile structure | |
JP2004285698A (en) | Deformed precast pile | |
JPH09111758A (en) | Cast-in-place concrete pile and construction method thereof | |
JP2885077B2 (en) | Connection pile method of ready-made concrete pile | |
JP2651893B2 (en) | Foundation pile structure | |
JPH11100841A (en) | Steel pipe pile | |
JPH07317087A (en) | Connecting structure of wall made of steel and reinforced concrete floor slab | |
JPH09324422A (en) | Cast-in-place compound pile and building method therefor | |
JP4419456B2 (en) | Method of joining reinforced concrete member and steel pipe concrete | |
JPH03275806A (en) | Method of making knotting pile | |
JP4473400B2 (en) | Foundation of construction and construction method | |
JPH08199565A (en) | Pile head joint construction of cast-in-place concrete pile | |
KR200298689Y1 (en) | Coupler with hoop stress for connecting PHC piles | |
JP3851581B2 (en) | Ground strength reinforcement structure of the ground | |
JPS6250516A (en) | Formation work of composite pile | |
JP3466724B2 (en) | Ready-made pile with knots |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20040525 |
|
A02 | Decision of refusal |
Effective date: 20041005 Free format text: JAPANESE INTERMEDIATE CODE: A02 |