JPH1060864A - Concrete placement system of dam bank and concrete placement method of dam bank using the same system - Google Patents

Concrete placement system of dam bank and concrete placement method of dam bank using the same system

Info

Publication number
JPH1060864A
JPH1060864A JP22493996A JP22493996A JPH1060864A JP H1060864 A JPH1060864 A JP H1060864A JP 22493996 A JP22493996 A JP 22493996A JP 22493996 A JP22493996 A JP 22493996A JP H1060864 A JPH1060864 A JP H1060864A
Authority
JP
Japan
Prior art keywords
concrete
area
cable
placing
concrete placement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP22493996A
Other languages
Japanese (ja)
Inventor
Nobuhiro Ito
信宏 伊藤
Ichiro Shikae
一郎 鹿江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hazama Corp
Original Assignee
Hazama Gumi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hazama Gumi Ltd filed Critical Hazama Gumi Ltd
Priority to JP22493996A priority Critical patent/JPH1060864A/en
Publication of JPH1060864A publication Critical patent/JPH1060864A/en
Pending legal-status Critical Current

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

PROBLEM TO BE SOLVED: To make it possible to carry concrete and place concrete to a concrete placement area definitely by guiding the concrete which is to be carried at least with one cable crane deviated from the concrete placement area accompanied by the progress of the construction of a bank by means of a hopper. SOLUTION: The concrete which is manufactured in a batcher plant 10, is placed into buckets 21, and 21' which move along a banker line 11. These buckets 21 and 21' are guided on a transportation track of cable cranes 20 and 20'. The concrete transported with the crane 20' is placed directly on a concrete placement area A'. On the other hand, the concrete, which is to be transported with the crane 20 deviated from the concrete placement area A' with the progress of the construction of the bank is further transported to the concrete placement area A' and placed therein by way of a hopper 30. It is, therefore, possible to transport and place concrete to the concrete placement area definitely.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明はダム堤体のコンクリ
ート打設システム、及び該システムを用いたダム堤体の
コンクリート打設工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a system for placing concrete in a dam body and a method for placing concrete in a dam body using the system.

【0002】[0002]

【従来の技術】従来からダム堤体を構築するにあたって
用いられるケーブルクレーンとしては、図1及び図2に
示すように両岸部B,B’に渡って張設される態様のも
のが知られている。図1は、比較的小規模のダム堤体を
構築する際に採用される態様のものであって、張設され
るケーブルクレーン20の一端20aを固定し、この固
定した一端20aを中心とした円周軌道上において他端
20bが移動可能とされたものである。他方、図2
(a)及び(b)は、図1におけるダム堤体に比べて大
規模のダム堤体を構築する際に採用される態様のもので
あって、両岸部B,B’に渡って2基(複数)のケーブ
ルクレーン20,20’が張設されたものである。尚、
図1及び図2において、10はバッチャープラントであ
り、11はバンカー線であり、20a,20a’,20
b,20b’はケーブルクレーンの端部であり、21,
21’はケーブルクレーンに昇降可能に吊設されたバケ
ットである。
2. Description of the Related Art Conventionally, as a cable crane used for constructing a dam embankment, a cable crane which is stretched over both banks B and B 'as shown in FIGS. 1 and 2 is known. I have. FIG. 1 shows a mode adopted when a relatively small dam embankment is constructed, in which one end 20a of a cable crane 20 to be stretched is fixed, and the fixed one end 20a is centered. The other end 20b is movable on a circumferential orbit. On the other hand, FIG.
(A) and (b) are of a mode employed when constructing a large-scale dam embankment as compared with the dam embankment in FIG. 1, and two units are provided across both banks B and B ′. A plurality of cable cranes 20, 20 'are stretched. still,
1 and 2, reference numeral 10 denotes a batcher plant, 11 denotes a bunker line, and 20a, 20a ', 20
b, 20b 'are the ends of the cable crane;
Reference numeral 21 'denotes a bucket suspended from a cable crane so as to be able to move up and down.

【0003】一般に、ケーブルクレーンを用いてダム堤
体を構築にするにあたっては、ケーブルクレーンによる
コンクリート運搬許容域が可能な限り広く確保されるこ
とが望ましく、その運搬許容量についても可能な限り大
きいことが望ましいといった環境設備が求められる。特
に、大規模のダム堤体を構築するにあたっては、上述し
たような望ましい環境設備を提供するために、複数のケ
ーブルクレーンをある程度の間隔をおいて張設すること
になる。
[0003] Generally, when constructing a dam embankment using a cable crane, it is desirable that the allowable area for transporting concrete by the cable crane is as wide as possible, and that the allowable transport capacity is as large as possible. Environmental facilities are desirable. In particular, when constructing a large-scale dam embankment, a plurality of cable cranes are to be installed at a certain interval in order to provide the desirable environmental facilities as described above.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、上述し
た前者の態様(図1)にあっては、1基のケーブルクレ
ーン20を張設しているにすぎず、運搬許容量において
満足し得ない状況を来す恐れがあるうえ、1基のケーブ
ルクレーン20であるにもかかわらず一端20aを中心
とした円周軌道上を他端20bが移動し得るようにする
という特殊な機能を有するため、この設備自体が高価で
あるといった欠点がある。また、上述した後者の態様
(図2(a)及び(b))にあっては、図2(b)に示
すように、堤体頂部付近のコンクリート打設域A’にコ
ンクリートを打設しようとする場合において、これに対
応できないケーブルクレーン20’が生じて設備の有効
な利用ができなくなり、不経済であるといった欠点があ
る。
However, in the former embodiment (FIG. 1) described above, only one cable crane 20 is stretched, and it is not possible to satisfy the allowable transport capacity. And has a special function of allowing the other end 20b to move on a circumferential track centered on one end 20a despite being a single cable crane 20. There is a disadvantage that the equipment itself is expensive. In the latter embodiment (FIGS. 2 (a) and 2 (b)), as shown in FIG. 2 (b), concrete will be poured into the concrete placing area A 'near the top of the embankment. In such a case, there is a disadvantage that the cable crane 20 ′ that cannot cope with this occurs, making it impossible to use the equipment effectively, which is uneconomical.

【0005】本発明は上述の従来の技術の欠点に着目
し、これを解決せんとしたものであり、その目的は、両
岸部に渡って張設されたケーブルクレーンを簡易にしか
も有効に利用し、コンクリートのコンクリート打設域へ
の確実な運搬打設を可能にするダム堤体のコンクリート
打設システムを提供すること、及び両岸部に渡って張設
されたケーブルクレーンを簡易にしかも有効に利用し、
コンクリートをコンクリート打設域に確実に運搬して打
設することができるダム堤体のコンクリート打設工法を
提供することにある。
The present invention has been made to solve the above-mentioned drawbacks of the prior art and to solve the problem. The purpose of the present invention is to use a cable crane stretched over both shores simply and effectively. To provide a concrete pouring system for dam embankments that enables reliable transport and pouring of concrete into concrete pouring areas, and to easily and effectively use cable cranes stretched across both banks And
It is an object of the present invention to provide a concrete embankment method for a dam embankment capable of reliably transporting concrete to an area for concrete installation.

【0006】[0006]

【課題を解決するための手段】本発明は上記の目的に鑑
みてなされたものであり、その要旨とするところは、ダ
ム堤体を構築するにあたって用いられ、コンクリートを
所定のコンクリート打設域に打設するためのシステムで
あって、岸部に設置され、コンクリートを製造するバッ
チャープラントと、両岸部に渡して張設され、上記バッ
チャープラントにおいて製造されたコンクリートを、所
定のコンクリート打設域に運搬するための複数のケーブ
ルクレーンと、堤体構築の進行に伴いコンクリート打設
域から外れた少なくとも1基の上記ケーブルクレーンに
よって運搬されるコンクリートを、該コンクリート打設
域に案内するためのホッパー手段と、を備えてなること
を特徴とするダム堤体のコンクリート打設システムにあ
る。
DISCLOSURE OF THE INVENTION The present invention has been made in view of the above-mentioned object, and its gist is to use concrete for constructing a dam embankment and to put concrete in a predetermined concrete casting area. A system for casting, comprising a batcher plant installed on the shore and producing concrete, and a concrete installed in the batcher plant stretched across both shores and produced in the batcher plant. And a hopper for guiding concrete transported by at least one of the cable cranes deviating from the concrete placing area to the concrete placing area as the embankment construction progresses Means for placing concrete in the dam embankment.

【0007】この態様によれば、堤体構築の進行に伴い
コンクリート打設域から外れた少なくとも1基の上記ケ
ーブルクレーンによって運搬されるコンクリートを、ホ
ッパー手段によって、該コンクリート打設域に案内する
ようにしたので、両岸部に渡って張設されたケーブルク
レーンを簡易にしかも有効に利用し、コンクリートのコ
ンクリート打設域への確実な運搬打設を可能にする。
According to this aspect, the concrete carried by the at least one cable crane deviating from the concrete placing area as the embankment construction progresses is guided to the concrete placing area by the hopper means. As a result, a cable crane stretched across both shores can be easily and effectively used, and the concrete can be reliably transported and poured into the concrete placing area.

【0008】本発明の他の要旨は、上記システムを用
い、コンクリートを所定のコンクリート打設域に打設す
るための工法であって、コンクリートをバッチャープラ
ントにおいて製造する工程と、該工程において製造され
たコンクリートを、複数のケーブルクレーンによって運
搬し、直接、コンクリート打設域に打設する工程と、上
記工程において製造されたコンクリートを、堤体構築の
進行に伴いコンクリート打設域から外れた少なくとも1
基の上記ケーブルクレーンによって運搬し、該コンクリ
ート打設域に案内するためのホッパー手段を介して更に
運搬し、該コンクリート打設域に打設する工程と、を含
むことを特徴とするダム堤体のコンクリート打設工法に
ある。
Another aspect of the present invention is a method of placing concrete in a predetermined concrete placing area using the above-described system, comprising the steps of: producing concrete in a batcher plant; The concrete is transported by a plurality of cable cranes and directly cast into the concrete placing area, and the concrete produced in the above step is separated from the concrete placing area by at least the concrete placing area with the progress of the embankment construction. 1
Transporting by said cable crane, further transporting through hopper means for guiding to said concrete placing area, and placing in said concrete placing area. Concrete casting method.

【0009】この態様によれば、堤体構築の進行に伴い
コンクリート打設域から外れた少なくとも1基の上記ケ
ーブルクレーンによって運搬されるコンクリートを、該
コンクリート打設域に案内するためのホッパー手段を介
して更に運搬し、該コンクリート打設域に打設するよう
にしたので、両岸部に渡って張設されたケーブルクレー
ンを簡易にしかも有効に利用し、コンクリートをコンク
リート打設域に確実に運搬して打設することができる。
According to this aspect, the hopper means for guiding the concrete conveyed by the at least one cable crane deviating from the concrete placing area with the progress of the construction of the embankment body to the concrete placing area. The concrete is transported further to the concrete placing area by simply and effectively using a cable crane stretched across both shores. Can be cast.

【0010】[0010]

【発明の実施の形態】本発明のダム堤体のコンクリート
打設システムにおいて、コンクリートを製造するバッチ
ャープラントは、少なくとも一方の岸部に設置されれば
よく、両岸部に夫々設置する態様であってもよい。
BEST MODE FOR CARRYING OUT THE INVENTION In the concrete embankment concrete damping system of the present invention, a batcher plant for producing concrete may be installed on at least one shore, and is installed on both shores. Is also good.

【0011】上記バッチャープラントにおいて製造され
たコンクリートを、所定のコンクリート打設領域に運搬
するための複数のケーブルクレーンは、ダム堤体の底部
分全体に対して所定の間隔をおいて両岸部に渡して張設
されるが、その数は限定されない。
[0011] A plurality of cable cranes for transporting the concrete produced in the batcher plant to a predetermined concrete casting area are provided on both shores at a predetermined interval with respect to the entire bottom portion of the dam embankment. They are handed over, but the number is not limited.

【0012】ホッパー手段は、堤体構築の進行に伴いコ
ンクリート打設域から外れた少なくとも1基の上記ケー
ブルクレーンによって運搬されるコンクリートを、該コ
ンクリート打設域に案内するもの、即ちケーブルクレー
ンの運搬許容域外のコンクリート打設域にコンクリート
を案内するものであれば、どのような態様のものであっ
てもよく、その形状は限定されない。尚、このホッパー
手段は、堤体の両岸部対向方向において任意の所定間隔
毎に設置することができる。具体的な態様としては、例
えばケーブルクレーンによって運搬されたコンクリート
を直接受理するホッパーと、このホッパーにおいて受理
したコンクリートを、コンクリート打設域に更に運搬す
るベルトコンベヤとを備える態様等、適当なものを採用
することができる。
The hopper means guides concrete conveyed by at least one of the cable cranes deviating from the concrete laying area with the progress of the construction of the embankment to the concrete laying area, ie, the cable crane conveyance. Any form may be used as long as it guides the concrete to the concrete pouring area outside the allowable area, and the shape is not limited. The hopper means can be installed at any given interval in the direction opposite to the banks on both banks. As a specific embodiment, an appropriate one such as an embodiment including a hopper that directly receives concrete transported by a cable crane and a belt conveyor that further transports the concrete received in the hopper to a concrete placing area is used. Can be adopted.

【0013】本発明のダム堤体のコンクリート打設工法
において、「コンクリートを、複数のケーブルクレーン
によって運搬し、直接、コンクリート打設域に打設す
る」とは、コンクリートを、ケーブルクレーンの搬送許
容域内のみで運搬し、打設することをいう。また、「コ
ンクリートを、堤体構築の進行に伴いコンクリート打設
域から外れた少なくとも1基の上記ケーブルクレーンに
よって運搬し、該コンクリート打設域に案内するための
ホッパー手段を介して更に運搬し、該コンクリート打設
域に打設する」とは、コンクリートを、上述したような
ホッパー手段を介して案内し、ケーブルクレーンの運搬
許容域外のコンクリート打設域に打設することをいう。
In the concrete embankment construction method of the present invention, "conveying concrete by a plurality of cable cranes and directly laying the concrete in a concrete laying area" means that concrete can be transported by a cable crane. It means transporting and casting only in the area. Further, "concrete is transported by at least one of the cable cranes deviated from the concrete placing area as the embankment construction progresses, and further transported through hopper means for guiding the concrete to the concrete placing area, “Putting in the concrete casting area” means that concrete is guided through the above-mentioned hopper means and is poured into the concrete casting area outside the allowable area for transporting the cable crane.

【0014】[0014]

【実施例】以下、本発明の実施例を添付図面に基づいて
説明するが、本発明はこれに限定されるものではない。
ここで、図3(a)は本発明の実施例を示す概略平面図
であり、図3(b)は図3(a)を3b−3b線に沿っ
て拡大して示す概略側面図であり、図3(c)は図3
(b)の概略平面図である。また、図4(a)〜(c)
は図3(b)のコンクリートホッパー設備を矢印4方向
から拡大して示す概略側面図である。
Embodiments of the present invention will be described below with reference to the accompanying drawings, but the present invention is not limited to these embodiments.
Here, FIG. 3A is a schematic plan view showing an embodiment of the present invention, and FIG. 3B is a schematic side view showing FIG. 3A in an enlarged manner along line 3b-3b. , FIG. 3 (c) shows FIG.
It is a schematic plan view of (b). 4A to 4C.
FIG. 4 is a schematic side view showing the concrete hopper facility of FIG.

【0015】図3(a)〜(c)及び図4(a)〜
(c)に示す本発明のダム堤体のコンクリート打設シス
テムは、ダム堤体(A,A’)を構築するにあたって用
いられ、コンクリートを所定のコンクリート打設域A,
A’に打設するためのシステムであって、岸部Bに設置
され、コンクリートを製造するバッチャープラント10
と、両岸部B,B’に渡して張設され、上記バッチャー
プラント10において製造されたコンクリートを、所定
のコンクリート打設域A,A’に運搬するための複数の
ケーブルクレーン20,20’と、堤体構築の進行に伴
いコンクリート打設域A’から外れたケーブルクレーン
20によって運搬されるコンクリートを、該コンクリー
ト打設域A’に案内するためのコンクリートホッパー設
備30(ホッパー手段)と、を備えて構成されている。
FIGS. 3A to 3C and FIGS.
The concrete embankment concrete embedding system of the present invention shown in (c) is used for constructing a dam embankment (A, A ′), and concrete is transferred to a predetermined concrete embedding area A,
A system for casting concrete at A ', which is installed at the shore B and is a batcher plant 10 for producing concrete.
And a plurality of cable cranes 20, 20 'for stretching concrete stretched across the banks B, B' and transporting the concrete produced in the batcher plant 10 to predetermined concrete placing areas A, A '. Concrete hopper equipment 30 (hopper means) for guiding concrete transported by the cable crane 20 that has deviated from the concrete placing area A ′ as the embankment construction progresses to the concrete placing area A ′; It is provided with.

【0016】上記バッチャープラント10は、製造した
コンクリートを投入するために、バケット(21,2
1’)を積載してバンカー線11に沿って移動し得るト
ロッコ(図示せず)を備えている。
The batcher plant 10 has a bucket (21, 21) for charging the produced concrete.
1 ') is equipped with a minecart (not shown) which can be loaded and moved along the bunker line 11.

【0017】また、ケーブルクレーン20,20’は、
従来と同様に、所定の間隔をおいて両岸部B,B’に張
設されており、上記トロッコに積載されたバケット2
1,21’を吊持して、その内部に投入されているコン
クリートを、所定のコンクリート打設域A,A’に運搬
する。
The cable cranes 20, 20 '
As in the conventional case, the buckets 2 are stretched at both sides B, B 'at a predetermined interval, and are loaded on the minecart.
The concrete put in the inside is suspended and transported to predetermined concrete placing areas A and A '.

【0018】コンクリートホッパー設備30は、図3
(b)及び(c)並びに図4(a)〜(c)に示される
ように、ホッパー31と、組み立てられたポスト体32
と、ホッパー31に投入されたコンクリートを、ホッパ
ー31から引き継いでコンクリート打設域A’に運搬す
るベルトコンベヤ33と、ポスト体32に沿って設けら
れ、ホッパー31及びベルトコンベヤ33を上昇移動さ
せるための昇降装置34とを備え、ケーブルクレーン2
0の運搬軌道の下方に所定の間隔をおいて設置されてお
り、ケーブルクレーン20によって運搬されるコンクリ
ートを、コンクリート打設域A’に案内する。このよう
に、各コンクリートホッパー設備30は、堤体構築の進
行に伴いコンクリート打設域A’から外れたケーブルク
レーン20によって運搬されるコンクリートを、該コン
クリート打設域A’に案内するもの、即ちケーブルクレ
ーン20の運搬許容域外のコンクリート打設域A’にコ
ンクリートを案内するものである。尚、図4(b)及び
(c)に示すような、ポスト体32の継ぎ足しにおける
組立て、及び昇降装置34によるホッパー31及びベル
トコンベヤ33の上昇移動は、コンクリート打設域A’
の打設が進行することによる頂部面の上昇に伴って生じ
るベルトコンベヤ33の勾配を、適宜修正するために行
われる。
The concrete hopper equipment 30 is shown in FIG.
As shown in FIGS. 4B and 4C and FIGS. 4A to 4C, the hopper 31 and the assembled post body 32
A belt conveyor 33 that carries the concrete put into the hopper 31 from the hopper 31 and conveys it to the concrete placing area A ′, and is provided along the post body 32 to move the hopper 31 and the belt conveyor 33 upward. And the lifting device 34 of the cable crane 2
The concrete transported by the cable crane 20 is installed at a predetermined interval below the transport track 0, and guides the concrete to the concrete placing area A ′. As described above, each concrete hopper facility 30 guides concrete transported by the cable crane 20 deviating from the concrete placing area A ′ with the progress of the embankment construction to the concrete placing area A ′, that is, The concrete is guided to the concrete placing area A ′ outside the allowable area of the cable crane 20 for transportation. As shown in FIGS. 4B and 4C, the assembling of the post body 32 at the time of adding the post body 32 and the upward movement of the hopper 31 and the belt conveyor 33 by the elevating device 34 are performed in the concrete placing area A ′.
Is carried out in order to appropriately correct the inclination of the belt conveyor 33 caused by the rise of the top surface due to the progress of the casting.

【0019】このダム堤体(A,A’)のコンクリート
打設システムを用い、コンクリートを打設するにあたっ
ては、先ずコンクリートが、バッチャープラント10に
おいて製造され、バンカー線11に沿って移動し得るト
ロッコ(図示せず)に積載されたバケット(21,2
1’)に投入されるようになっている。次いでコンクリ
ートが投入されたバケット(21,21’)は、上記ト
ロッコ(図示せず)によってケーブルクレーン20,2
0’の運搬軌道上まで案内される。そして、ケーブルク
レーン20’によって運搬されたコンクリートは、直
接、コンクリート打設域A’に打設される。他方、堤体
構築の進行に伴いコンクリート打設域A’から外れたケ
ーブルクレーン20によって運搬されたコンクリート
は、上記コンクリートホッパー設備30を介して更に運
搬され、コンクリート打設域A’に打設される。
In placing concrete using the concrete placing system for dam body (A, A '), concrete is first produced in batcher plant 10 and can move along bunker line 11. Buckets (21, 2) loaded on a trolley (not shown)
1 '). Next, the buckets (21, 21 ') into which the concrete has been put are used for the cable cranes 20, 2 by the trolley (not shown).
It is guided to the transport trajectory of 0 '. Then, the concrete carried by the cable crane 20 'is directly poured into the concrete placing area A'. On the other hand, the concrete transported by the cable crane 20 which has deviated from the concrete placing area A ′ with the progress of the embankment construction is further transported through the concrete hopper equipment 30 and is placed in the concrete placing area A ′. You.

【0020】尚、2基のケーブルクレーン20,20’
を並行に張設した従来のコンクリート打設システム(図
2(a)及び(b))においては下流側に設けられたケ
ーブルクレーン20が一切利用することができなかった
のに対し、本発明においては下流側に設けられたケーブ
ルクレーン20においても継続してコンクリートを運搬
して打設することができ、2基(複数)のケーブルクレ
ーン20,20’を簡易にしかも有効に利用することが
できるといった顕著な効果を奏する。具体的には、従来
のコンクリート打設工法においては堤体頂部付近の打設
時に上流側のケーブルクレーン20’のみを利用するこ
とできるにすぎず、従ってこの1基のケーブルクレーン
20’はその利用時間の割合において7割がコンクリー
ト打設に使用され、残りの3割が雑運搬に使用されてい
たのに対し、本発明のコンクリート打設工法においては
上流側のケーブルクレーン20’を従来の工法と同様に
使用するとしても、他方のケーブルクレーン20が、コ
ンクリートホッパー設備30(ホッパー手段)の設置作
業にかかる時間を除いた全ての時間においてコンクリー
ト打設に使用することができる。このように、本発明の
コンクリート打設工法においては、従来のコンクリート
打設工法に比べ、2基(複数)のケーブルクレーン2
0,20’を簡易にしかも有効に利用することができ
る。
The two cable cranes 20, 20 '
In the conventional concrete pouring system (FIGS. 2A and 2B) in which the cable crane 20 provided on the downstream side cannot be used at all, the present invention Can transport and cast concrete continuously in the cable crane 20 provided on the downstream side, and two (plural) cable cranes 20, 20 'can be used simply and effectively. It has a remarkable effect. Specifically, in the conventional concrete casting method, only the cable crane 20 'on the upstream side can be used at the time of casting near the top of the embankment. While 70% of the time was used for concrete placing and the remaining 30% was used for miscellaneous transportation, in the concrete placing method of the present invention, the cable crane 20 'on the upstream side was replaced by the conventional method. Even if it is used in the same manner as above, the other cable crane 20 can be used for concrete casting at all times except for the time required for installation work of the concrete hopper equipment 30 (hopper means). As described above, in the concrete placing method of the present invention, two (plural) cable cranes 2 are used as compared with the conventional concrete placing method.
0, 20 'can be used simply and effectively.

【0021】[0021]

【発明の効果】本発明のダム堤体のコンクリート打設シ
ステムは、堤体構築の進行に伴いコンクリート打設域か
ら外れた少なくとも1基の上記ケーブルクレーンによっ
て運搬されるコンクリートを、ホッパー手段によって、
該コンクリート打設域に案内する態様を採用したことに
より、両岸部に渡って張設されたケーブルクレーンを簡
易にしかも有効に利用し、コンクリートのコンクリート
打設域への確実な運搬打設を可能にするといった顕著な
効果を奏する。
According to the concrete embedding system of the dam embankment of the present invention, concrete conveyed by at least one of the cable cranes deviating from the concrete pouring area as the embankment construction progresses is carried out by hopper means.
By adopting the mode of guiding to the concrete placing area, it is possible to easily and effectively use a cable crane stretched across both shores, and to transport concrete to the concrete placing area reliably. It has a remarkable effect such as

【0022】本発明のダム堤体のコンクリート打設工法
は、堤体構築の進行に伴いコンクリート打設域から外れ
た少なくとも1基の上記ケーブルクレーンによって運搬
されるコンクリートを、該コンクリート打設域に案内す
るためのホッパー手段を介して更に運搬し、該コンクリ
ート打設域に打設する態様を採用したことにより、両岸
部に渡って張設されたケーブルクレーンを簡易にしかも
有効に利用し、コンクリートをコンクリート打設域に確
実に運搬して打設することができるといった顕著な効果
を奏する。
According to the concrete casting method of a dam embankment of the present invention, concrete transported by at least one of the cable cranes deviating from the concrete casting area as the embankment construction proceeds is transferred to the concrete casting area. By adopting the mode of further transporting via the hopper means for guiding and placing the concrete in the concrete placing area, the cable crane stretched across both shores can be easily and effectively used, and the concrete can be effectively used. Has a remarkable effect that the concrete can be reliably transported and cast into the concrete casting area.

【0023】このように、本発明のコンクリート打設シ
ステム及びコンクリート打設工法によれば、堤体頂部付
近においても、各ケーブルクレーンを簡易にしかも有効
に利用することができ、従ってコンクリート打設能力を
向上させて工期の短縮を図ることができるといった更に
他の顕著な効果が得られる。
As described above, according to the concrete placing system and the concrete placing method of the present invention, each cable crane can be used easily and effectively even near the top of the embankment, and accordingly, the concrete placing capacity And other remarkable effects such that the construction period can be shortened can be obtained.

【図面の簡単な説明】[Brief description of the drawings]

【図1】従来のダム堤体のコンクリート打設システムを
示す概略平面図である。
FIG. 1 is a schematic plan view showing a conventional concrete pouring system for a dam embankment.

【図2】(a)は従来の他のダム堤体のコンクリート打
設システムを示す概略平面図であり、(b)は図2
(a)を2b−2b線に沿って示す概略側面図である。
FIG. 2 (a) is a schematic plan view showing another conventional concrete pouring system for a dam embankment, and FIG. 2 (b) is a schematic plan view.
It is a schematic side view which shows (a) along the 2b-2b line.

【図3】(a)は本発明の実施例を示す概略平面図であ
り、(b)は図3(a)を3b−3b線に沿って拡大し
て示す概略側面図であり、(c)は図3(b)の概略平
面図である。
3 (a) is a schematic plan view showing an embodiment of the present invention, FIG. 3 (b) is a schematic side view showing FIG. 3 (a) on an enlarged scale along line 3b-3b, and FIG. 3) is a schematic plan view of FIG.

【図4】(a)〜(c)は図3(b)のコンクリートホ
ッパー設備を矢印4方向から拡大して示す概略側面図で
ある。
4 (a) to 4 (c) are schematic side views showing the concrete hopper equipment of FIG. 3 (b) in an enlarged manner from the direction of arrow 4. FIG.

【符号の説明】 10 バッチャープラント 11 バンカー線 20 ケーブルクレーン 21 バケット 30 コンクリートホッパー設備(ホッパー手段) 31 ホッパー 32 ポスト体 33 ベルトコンベヤ 34 昇降装置 A,A’ ダム堤体のコンクリート打設域 B,B’ 岸部[Description of Signs] 10 Batcher Plant 11 Bunker Line 20 Cable Crane 21 Bucket 30 Concrete Hopper Equipment (Hopper Means) 31 Hopper 32 Post Body 33 Belt Conveyor 34 Lifting Device A, A 'Concrete Casting Area of Dam Embankment B, B 'shore

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 ダム堤体を構築するにあたって用いら
れ、コンクリートを所定のコンクリート打設域に打設す
るためのシステムであって、 岸部に設置され、コンクリートを製造するバッチャープ
ラントと、 両岸部に渡して張設され、上記バッチャープラントにお
いて製造されたコンクリートを、所定のコンクリート打
設域に運搬するための複数のケーブルクレーンと、 堤体構築の進行に伴いコンクリート打設域から外れた少
なくとも1基の上記ケーブルクレーンによって運搬され
るコンクリートを、該コンクリート打設域に案内するた
めのホッパー手段と、を備えてなることを特徴とするダ
ム堤体のコンクリート打設システム。
1. A system for placing concrete in a predetermined concrete placing area, which is used in constructing a dam embankment, comprising: a batcher plant installed on a shore for producing concrete; A plurality of cable cranes for transporting concrete manufactured in the batcher plant to a predetermined concrete placing area, and And a hopper means for guiding concrete carried by one of the cable cranes to the concrete placing area.
【請求項2】 上記システムを用い、コンクリートを所
定のコンクリート打設域に打設するための工法であっ
て、 コンクリートをバッチャープラントにおいて製造する工
程と、 該工程において製造されたコンクリートを、複数のケー
ブルクレーンによって運搬し、直接、コンクリート打設
域に打設する工程と、 上記工程において製造されたコンクリートを、堤体構築
の進行に伴いコンクリート打設域から外れた少なくとも
1基の上記ケーブルクレーンによって運搬し、該コンク
リート打設域に案内するためのホッパー手段を介して更
に運搬し、該コンクリート打設域に打設する工程と、を
含むことを特徴とするダム堤体のコンクリート打設工
法。
2. A method for placing concrete in a predetermined concrete placing area using the above system, comprising: a step of producing concrete in a batcher plant; Transporting the concrete by a cable crane and placing it directly in a concrete placing area; Transporting through a hopper means for guiding to the concrete placing area, and placing the concrete in the concrete placing area. .
JP22493996A 1996-08-27 1996-08-27 Concrete placement system of dam bank and concrete placement method of dam bank using the same system Pending JPH1060864A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP22493996A JPH1060864A (en) 1996-08-27 1996-08-27 Concrete placement system of dam bank and concrete placement method of dam bank using the same system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP22493996A JPH1060864A (en) 1996-08-27 1996-08-27 Concrete placement system of dam bank and concrete placement method of dam bank using the same system

Publications (1)

Publication Number Publication Date
JPH1060864A true JPH1060864A (en) 1998-03-03

Family

ID=16821564

Family Applications (1)

Application Number Title Priority Date Filing Date
JP22493996A Pending JPH1060864A (en) 1996-08-27 1996-08-27 Concrete placement system of dam bank and concrete placement method of dam bank using the same system

Country Status (1)

Country Link
JP (1) JPH1060864A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015094161A (en) * 2013-11-13 2015-05-18 鹿島建設株式会社 Dam construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015094161A (en) * 2013-11-13 2015-05-18 鹿島建設株式会社 Dam construction method

Similar Documents

Publication Publication Date Title
EP0283225B1 (en) Apparatus for mixing, transporting and placing concrete
KR100701494B1 (en) A stockyard for bulk materials
CN106567342A (en) Method for erecting precast beam of super-wide bridge deck at narrow space by using high-low leg gantry crane
US5853264A (en) Bridge, dock and pier shoring-up bulk-delivery floating conveyor unit
JPH1060864A (en) Concrete placement system of dam bank and concrete placement method of dam bank using the same system
CN106994743B (en) Rail transport device and method between surface lines of high-speed rail ballastless track bed concrete construction
AU2019303339B2 (en) Apparatus and method for conveying into and out of a hollow
KR101566130B1 (en) Method for constructing dam dock and mono rail using incline equipment
JP3381043B2 (en) Dam concrete placement equipment
KR20100091290A (en) A method of construction of load earth and sand for a cost road side on the sea
KR20100087569A (en) Loading conveyer system of conveyer barge for loading earth and sand
JP3491244B2 (en) Dam construction equipment and dam construction method
JPH0541763B2 (en)
CN112344096B (en) Construction method of submarine pipeline leveling, laying, locking and burying equipment
JPH11236707A (en) Concrete casting method and device thereof
JP2003027448A (en) System for continuously conveying concrete in field of dam construction
JPH07300839A (en) Construction method of dam
JP4759754B2 (en) Transporting excavated soil in dam construction
JP2000345544A (en) Concrete production facilities
JPH10245829A (en) Casting device and casting method of dam concrete
JPH0921124A (en) Long distance-transportation system of large quantity of soil
JPH10147935A (en) Throw-down device below water surface and method thereof
JPS6340020A (en) Method and apparatus for covering bottom under water with sand
JPS5950808B2 (en) Landfill construction method
JPH0853826A (en) Construction method of dam