CN106567342A - Method for erecting precast beam of super-wide bridge deck at narrow space by using high-low leg gantry crane - Google Patents
Method for erecting precast beam of super-wide bridge deck at narrow space by using high-low leg gantry crane Download PDFInfo
- Publication number
- CN106567342A CN106567342A CN201610989441.8A CN201610989441A CN106567342A CN 106567342 A CN106567342 A CN 106567342A CN 201610989441 A CN201610989441 A CN 201610989441A CN 106567342 A CN106567342 A CN 106567342A
- Authority
- CN
- China
- Prior art keywords
- gantry crane
- precast
- bridge
- supporting leg
- precast beam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The present invention relates to a method for erecting a precast beam of a super-wide bridge deck at a narrow space by using a high-low leg gantry crane. The method comprises the concrete steps of installing a traversing type bridge-erecting machine and the high-low leg gantry crane at a beam hoisting area, erecting the precast beam at the beam hoisting area through the traversing of the bridge-erecting machine, completing the erection of the precast beam at the beam hoisting area, and erecting the precast beam in a beam-on-beam conveyance way. By applying the method, the problems of conveyance and erection of precast beams at narrow spaces can be well solved, the safety in the conveyance and erection processes of precast beams is guaranteed, and the working efficiency is greatly improved. The method in which the high-low leg gantry crane and the traversing type bridge-erecting machine are matched for construction is applied to complex terrains and narrow spaces for the first time, and the successful experience can guide the engineering construction under the type conditions.
Description
Technical field
The present invention relates to a kind of narrow space erection of precast beams method, especially a kind of pre- for complicated landform Super wide bridge
The installation method of beam processed.
Background technology
At present, in the design of city and highway bridge, precast beam is widely used.But Bridges in Our Country with
Rapid speed is in development, including city, mountain area etc..And the big small stream mouth of Yibin City closes on to southern wide traffic transformation and landscape engineering
The Changjiang river, belongs to the Changjiang river second-order terrace, belongs to eroded deposit landform, and second-order terrace area near Project Areas in the Changjiang river is extremely narrow and small.This
Engineering is mainly underground interchange and constitutes with elevated bridge, forms the form of Bridge-wire fusing time, and elevated bridge bridge floor the widest part reaches
To 68m.It is due to narrow field and with a varied topography, and affected restriction, the transporting precast beams of routine and erection by tunnel structure
Condition cannot meet, therefore the transport channel of precast beam is into the key point of whole engineering erection of precast beams.
The content of the invention
The present invention is to solve the technical problem of narrow space erection of precast beams, and a kind of narrow space Super wide bridge is provided
Height leg gantry crane sets up precast beam method.
The present invention solves the technical scheme that adopted of above-mentioned technical problem:A kind of narrow space Super wide bridge height leg door
Suspension bracket sets prefabricated beam method, it is characterised in that:Using height leg gantry crane, can cross sliding type Bridge Erector erecting beam be divided into two ranks
Section:
First stage:Bale handle area erection of precast beams
(1)Installation height leg gantry crane, Bridge Erector
In bale handle area, upper beam point is respectively mounted Bridge Erector and the high supporting leg of gantry crane, the high supporting leg of Bridge Erector cross moving track connection gantry crane;
(2)Prefabricated beam support is installed
Cleaning bearing pad stone top surface simultaneously marks support position center line by design drawing, by support position center line erection support;
(3)Transporting precast beams
Bridge Erector is traversing to be in state of setting a roof beam in place to gantry crane, and beam car transports beam immediately below Bridge Erector;
(4)Precast beam lifting sets up
Bridge Erector transfers suspender, and steel wire rope is revealed all the details binding precast beam, and Bridge Erector lifts precast beam, is lifted to after predetermined altitude along horizontal
Move track carries out transverse shifting to the direction that precast beam makes a reservation for set up;
(5)Precast beam is accurately in place
Bridge Erector laterally moves to precast beam slowly falls after the predetermined decorating position of precast beam, drops down onto 10cm directly over bearing,
Check that precast beam is installed to support position by axis after errorless;
Second stage:Transporting precast beams set up
(1)The low supporting leg of installation height leg gantry crane, hoisting overhead travelling crane
Cross moving track on high supporting leg is withdrawn, high supporting leg is increased, low supporting leg and gantry crane crossbeam, gantry crane hoisting overhead travelling crane are installed;
(2)Transporting precast beams
In operational readiness immediately below gantry crane, ground beam car transports beam under gantry crane to beam car on beam, gantry crane lifting precast beam,
Put to beam on beam car, beam is transported to bridge formation drive end unit by beam car on beam, realize feeding beam construction technology on beam.
The first stage(1)In step, high supporting leg combines architectonical with Bridge Erector cross moving track.
The second stage(1)In step, high supporting leg combines architectonical with low supporting leg.
The present invention useful achievement be:The present invention can greatly put forward the installation rate of precast beam, while guaranteeing what is constructed
Security;The present invention is first using height leg gantry crane and cross moving track combined system in narrow space and Super wide bridge construction
Method, its successful experience can instruct type engineering construction.
Description of the drawings
Fig. 1 is installation height leg gantry crane, Bridge Erector, installs prefabricated beam support, transporting precast beams schematic diagram;
Fig. 2 is that precast beam lifting sets up schematic diagram;
Fig. 3 is the accurate schematic diagram in place of precast beam;
Fig. 4 is the low supporting leg of installation height leg gantry crane, hoisting overhead travelling crane schematic diagram;
Fig. 5 is that beam car is in operational readiness immediately below gantry crane on beam, and beam is transported schematic diagram under gantry crane by ground beam car;
Fig. 6 is that gantry crane lifts by crane precast beam, is put to beam on beam car, and beam is transported to bridge formation drive end unit and is illustrated by beam car on beam
Figure.
Specific embodiment
With reference to instantiation, embodiments of the present invention are expanded on further.
The present invention is directed to the difficult point of transporting precast beams erection method, and measure is:
(1)According to site contour geological condition, gantry crane basis, mass of foundation of keeping under strict control are determined.
(2)Gantry crane height of landing leg and load are calculated according to actual conditions, accurate processing, combination(Supporting leg+cross moving track,
Gantry crane supporting leg+gantry crane crossbeam)Elevation is mutually matched with bridge elevation.
(3)It is accurate that gantry crane supporting leg and cross moving track are installed, meet Bridge Erector bale handle and beam car beam transporting passage space, protect
Must not collide during card fortune beam.Cross moving track must keep smooth safe.
(4)Meticulously establishment Design of Construction Organization and special scheme, arrange reasonable erection of precast beams sequence of construction, gantry crane with
Bridge Erector must carry out signalman by accredited and special messenger.
With reference to the big small stream mouth of Yibin City to southern wide traffic transformation and the construction of landscape engineering erection of precast beams(Fig. 1 to Fig. 6), explanation
The specific implementation method of the present invention:
The erection of precast beams of the present invention is divided into two stages.
First stage concrete steps:(Fig. 1 to Fig. 3)
(1)Installation height leg gantry crane, Bridge Erector
In bale handle area, upper beam point is respectively mounted Bridge Erector and the high supporting leg of gantry crane, the high supporting leg of Bridge Erector cross moving track connection gantry crane
(2)Prefabricated beam support is installed
Cleaning bearing pad stone top surface simultaneously marks support position center line by design drawing, by support position center line erection support.
(3)Transporting precast beams
Bridge Erector is traversing to be in state of setting a roof beam in place to gantry crane, and beam car transports beam immediately below Bridge Erector.
(4)Precast beam lifting sets up
Bridge Erector transfers suspender, and steel wire rope is revealed all the details binding precast beam, and Bridge Erector lifts precast beam, is lifted to after predetermined altitude along horizontal
Move track carries out transverse shifting to the direction that precast beam makes a reservation for set up.
(5)Precast beam is accurately in place
Bridge Erector laterally moves to precast beam slowly falls after the predetermined decorating position of precast beam, drops down onto 10cm directly over bearing,
Check that precast beam is installed to support position by axis after errorless.
Second stage concrete steps:(Fig. 4 to Fig. 6)
After the completion of first stage i.e. bale handle area erection of precast beams, set up into second stage transporting precast beams.
(1)The low supporting leg of installation height leg gantry crane, hoisting overhead travelling crane
Cross moving track on high supporting leg is withdrawn, high supporting leg is increased, low supporting leg and gantry crane crossbeam, gantry crane hoisting overhead travelling crane are installed.
(2)Transporting precast beams
In operational readiness immediately below gantry crane, ground beam car transports beam under gantry crane to beam car on beam, gantry crane lifting precast beam,
Put to beam on beam car, beam is transported to bridge formation drive end unit by beam car on beam, realize feeding beam construction technology on beam.
Claims (3)
1. a kind of narrow space Super wide bridge height leg gantry crane sets up precast beam method, it is characterised in that:Using height leg gantry crane,
Can cross sliding type Bridge Erector erecting beam be divided into two stages:
First stage:Bale handle area erection of precast beams
(1)Installation height leg gantry crane, Bridge Erector
In bale handle area, upper beam point is respectively mounted Bridge Erector and the high supporting leg of gantry crane, the high supporting leg of Bridge Erector cross moving track connection gantry crane;
(2)Prefabricated beam support is installed
Cleaning bearing pad stone top surface simultaneously marks support position center line by design drawing, by support position center line erection support;
(3)Transporting precast beams
Bridge Erector is traversing to be in state of setting a roof beam in place to gantry crane, and beam car transports beam immediately below Bridge Erector;
(4)Precast beam lifting sets up
Bridge Erector transfers suspender, and steel wire rope is revealed all the details binding precast beam, and Bridge Erector lifts precast beam, is lifted to after predetermined altitude along horizontal
Move track carries out transverse shifting to the direction that precast beam makes a reservation for set up;
(5)Precast beam is accurately in place
Bridge Erector laterally moves to precast beam slowly falls after the predetermined decorating position of precast beam, drops down onto 10cm directly over bearing,
Check that precast beam is installed to support position by axis after errorless;
Second stage:Transporting precast beams set up
(1)The low supporting leg of installation height leg gantry crane, hoisting overhead travelling crane
Cross moving track on high supporting leg is withdrawn, high supporting leg is increased, low supporting leg and gantry crane crossbeam, gantry crane hoisting overhead travelling crane are installed;
(2)Transporting precast beams
In operational readiness immediately below gantry crane, ground beam car transports beam under gantry crane to beam car on beam, gantry crane lifting precast beam,
Put to beam on beam car, beam is transported to bridge formation drive end unit by beam car on beam, realize feeding beam construction technology on beam.
2. narrow space Super wide bridge height leg gantry crane according to claim 1 sets up precast beam method, it is characterised in that:
The first stage(1)In step, high supporting leg combines architectonical with Bridge Erector cross moving track.
3. narrow space Super wide bridge height leg gantry crane according to claim 1 sets up precast beam method, it is characterised in that:
The second stage(1)In step, high supporting leg combines architectonical with low supporting leg.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610989441.8A CN106567342A (en) | 2016-11-10 | 2016-11-10 | Method for erecting precast beam of super-wide bridge deck at narrow space by using high-low leg gantry crane |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610989441.8A CN106567342A (en) | 2016-11-10 | 2016-11-10 | Method for erecting precast beam of super-wide bridge deck at narrow space by using high-low leg gantry crane |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106567342A true CN106567342A (en) | 2017-04-19 |
Family
ID=58540925
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610989441.8A Pending CN106567342A (en) | 2016-11-10 | 2016-11-10 | Method for erecting precast beam of super-wide bridge deck at narrow space by using high-low leg gantry crane |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106567342A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109868747A (en) * | 2019-03-14 | 2019-06-11 | 中交一公局海威工程建设有限公司 | Precast beam construction method and device |
CN110331672A (en) * | 2019-08-14 | 2019-10-15 | 中交一公局第一工程有限公司 | Across the pier bale handle holder device in bridge side position and its simple and fast construction method |
CN110606447A (en) * | 2019-10-15 | 2019-12-24 | 合肥正浩机械科技有限公司 | Lifting and carrying device for precast beam of bridge girder erection machine on beam transporting vehicle and working method of lifting and carrying device |
WO2020233501A1 (en) * | 2019-05-23 | 2020-11-26 | 中铁二局集团有限公司 | Construction method for upright lifting of large-tonnage box girder to bridge, and erection method for large-tonnage box girder |
CN112593492A (en) * | 2020-12-11 | 2021-04-02 | 保利长大工程有限公司 | Method for transporting bridge deck beam slab |
CN113957793A (en) * | 2021-06-28 | 2022-01-21 | 中国能源建设集团安徽电力建设第一工程有限公司 | Construction method for prefabricating box girder support in complex urban environment |
WO2023010644A1 (en) * | 2021-08-04 | 2023-02-09 | 中铁上海工程局集团有限公司 | Synchronous transporting and erecting construction method for small-space multi-bridge parallel section box girder |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU908989A1 (en) * | 1980-04-14 | 1982-02-28 | Специальное Конструкторское Бюро Главмостостроя Министерства Транспортного Строительства Ссср | Gantry crane and method of erecting bridges |
CN102102317A (en) * | 2009-12-22 | 2011-06-22 | 中铁科工集团有限公司 | Method for laying mixed passenger and freight jointless track and bridge erecting machine for erecting railway T-beam |
JP2012202076A (en) * | 2011-03-24 | 2012-10-22 | Toda Constr Co Ltd | Construction device of overhead viaduct and construction method of overhead viaduct |
CN203877780U (en) * | 2014-05-15 | 2014-10-15 | 中交四公局第三工程有限公司 | High-leg and low-leg handle gantry crane for road |
CN104878693A (en) * | 2015-04-24 | 2015-09-02 | 中铁六局集团有限公司 | Lateral girder erection and construction method for truss double-girder type bridge girder erection machine |
CN106087775A (en) * | 2016-08-08 | 2016-11-09 | 郑州新大方重工科技有限公司 | For setting up intercity track and subway U beam self-balancing via hole type Bridge Erector |
-
2016
- 2016-11-10 CN CN201610989441.8A patent/CN106567342A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU908989A1 (en) * | 1980-04-14 | 1982-02-28 | Специальное Конструкторское Бюро Главмостостроя Министерства Транспортного Строительства Ссср | Gantry crane and method of erecting bridges |
CN102102317A (en) * | 2009-12-22 | 2011-06-22 | 中铁科工集团有限公司 | Method for laying mixed passenger and freight jointless track and bridge erecting machine for erecting railway T-beam |
JP2012202076A (en) * | 2011-03-24 | 2012-10-22 | Toda Constr Co Ltd | Construction device of overhead viaduct and construction method of overhead viaduct |
CN203877780U (en) * | 2014-05-15 | 2014-10-15 | 中交四公局第三工程有限公司 | High-leg and low-leg handle gantry crane for road |
CN104878693A (en) * | 2015-04-24 | 2015-09-02 | 中铁六局集团有限公司 | Lateral girder erection and construction method for truss double-girder type bridge girder erection machine |
CN106087775A (en) * | 2016-08-08 | 2016-11-09 | 郑州新大方重工科技有限公司 | For setting up intercity track and subway U beam self-balancing via hole type Bridge Erector |
Non-Patent Citations (2)
Title |
---|
中铁电气化局集团建设管理分公司: "《城市轨道交通工程投融资及建设管理》", 31 August 2015, 中国铁道出版社 * |
林凯: "狭窄受限地形箱梁架设方法探讨", 《公路交通科技》 * |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109868747A (en) * | 2019-03-14 | 2019-06-11 | 中交一公局海威工程建设有限公司 | Precast beam construction method and device |
WO2020233501A1 (en) * | 2019-05-23 | 2020-11-26 | 中铁二局集团有限公司 | Construction method for upright lifting of large-tonnage box girder to bridge, and erection method for large-tonnage box girder |
US11391004B1 (en) | 2019-05-23 | 2022-07-19 | China Railway No. 2 Engineering Group Co. LTD. | Construction method for upright lifting of large-tonnage box girder to bridge, and erection method for large-tonnage box girder |
CN110331672A (en) * | 2019-08-14 | 2019-10-15 | 中交一公局第一工程有限公司 | Across the pier bale handle holder device in bridge side position and its simple and fast construction method |
CN110606447A (en) * | 2019-10-15 | 2019-12-24 | 合肥正浩机械科技有限公司 | Lifting and carrying device for precast beam of bridge girder erection machine on beam transporting vehicle and working method of lifting and carrying device |
CN112593492A (en) * | 2020-12-11 | 2021-04-02 | 保利长大工程有限公司 | Method for transporting bridge deck beam slab |
CN112593492B (en) * | 2020-12-11 | 2021-08-17 | 保利长大工程有限公司 | Method for transporting bridge deck beam slab |
CN113957793A (en) * | 2021-06-28 | 2022-01-21 | 中国能源建设集团安徽电力建设第一工程有限公司 | Construction method for prefabricating box girder support in complex urban environment |
WO2023010644A1 (en) * | 2021-08-04 | 2023-02-09 | 中铁上海工程局集团有限公司 | Synchronous transporting and erecting construction method for small-space multi-bridge parallel section box girder |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106567342A (en) | Method for erecting precast beam of super-wide bridge deck at narrow space by using high-low leg gantry crane | |
CN102182147B (en) | Steel box girder erection method | |
CN104499433B (en) | One wears high ferro low clearance erecting beam construction method under acutangulating intersection | |
CN101787678B (en) | Large-span section assembling bridge manufacturing machine and assembling construction process thereof | |
CN108532465A (en) | A kind of construction method of Through Steel case arch bridge | |
CN104195952A (en) | Steel box girder erection method applied to steel and concrete hybrid girder cable-stayed bridge | |
CN111852521B (en) | Mouth-shaped piece assembling trolley for construction of internal structure of large-section shield tunnel and synchronous construction method | |
CN105822310A (en) | Rapid low-risk station tunnel digging method | |
CN107675630A (en) | A kind of overhead prefabricated box girder erection device of light rail and its construction method | |
CN110017024A (en) | The construction method of the horizontal girder steel of contrary sequence method basement | |
CN104018426A (en) | Steel truss installation method | |
CN108385451A (en) | Board-like ballastless track boards replacing options under a kind of special operation condition | |
CN105544409B (en) | Double guide beam bridge erecting machine sets up combination beam and now spells a section girder steel construction technology | |
JP5184248B2 (en) | Construction method of level crossing | |
CN110093863A (en) | A kind of double face integration Bridge Erector being not provided with front leg strut | |
CN202703579U (en) | Large slope inclined shaft rail transport construction apparatus | |
JP4559370B2 (en) | Girder erection method by erection gutter from the side of bridge | |
JP7559273B2 (en) | Deck replacement method | |
CN107022958A (en) | The method in cable-stayed bridge across girder is installed using cable crane | |
CN102747693B (en) | Railway T-beam erecting construction method based on continuous beam laying reloading points | |
CN105484166A (en) | Ladder-shaped mast type cantilever assembling crane | |
CN211973152U (en) | Large-tonnage box girder erection construction system capable of realizing height control | |
CN109371852A (en) | A kind of high-level bridge construction method across rail yard | |
CN209338005U (en) | A kind of mobile height leg gantry crane of erecting beam construction | |
CN113322819B (en) | Method for erecting first-span T beam at tunnel outlet |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170419 |