JPH10228463A JP3167097A JP3167097A JPH10228463A JP H10228463 A JPH10228463 A JP H10228463A JP 3167097 A JP3167097 A JP 3167097A JP 3167097 A JP3167097 A JP 3167097A JP H10228463 A JPH10228463 A JP H10228463A
Authority
JP
Japan
Prior art keywords
demand
value
supply
cost
evaluation method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP3167097A
Other languages
Japanese (ja)
Inventor
Hideki Nakada
英樹 中田
Isato Sudo
勇人 須藤
Kazuyasu Honda
和保 本田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP3167097A priority Critical patent/JPH10228463A/en
Publication of JPH10228463A publication Critical patent/JPH10228463A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a demand prediction model evaluation method nor speeding up and facilitating evaluation work verifying availability to a real job by means of the application of a demand prediction model, and suppressing a wasteful prediction model reconstruction work that is to secure precision more than that requested in a job system. SOLUTION: The evaluation method is constituted of processing procedures for taking in a demand result value in the evaluation period of the demand prediction model and a demand prediction value, calculating the deviation value of the demand result value and the demand prediction value at every supply cycle of a product to a market, which is inputted from an input device, calculating supply excess cost and supply lack cost in accordance with the deviation value and outputting supply excess cost and supply lack cost to an output device.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、販売計画、生産計
画などの前段業務として行われる需要予測に関わり、特
に構築済み需要予測モデルの実業務への有用性を評価す
る際に好適な需要予測モデル評価方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to demand forecasting performed as a preceding stage of sales planning, production planning, etc., and is particularly suitable for demand forecasting when evaluating the usefulness of an established demand forecasting model for actual work. Model evaluation method.

【0002】[0002]

【従来の技術】需要予測では予測精度の向上を狙いに各
種の統計・予測手法により需要特性を定式化した予測モ
デルが用いられている。この予測モデルの構築に当たっ
ては、代替案として考えられる複数の予測モデルから基
準となる評価指標に従い業務で活用する適切な予測モデ
ルを絞り込んでいくというアプローチをとることが多
い。その際、評価指標として採用される代表的指標の一
つにAIC(An Information Criterion)がある。文献
(広松、浪花著:「経済時系列分析」、朝倉書店、1990.
11、pp58)によると、AICは最尤法によって決定され
るパラメータをもつモデルの悪さを比較するための指標
であり、同一のデータについてAICが大きいほど悪い
モデルとされる。従って、予測モデルを評価する立場か
らはAICの大小に着目すれば良いことになる。
2. Description of the Related Art In demand forecasting, a forecasting model in which demand characteristics are formulated by various statistical and forecasting methods is used in order to improve forecasting accuracy. In constructing this prediction model, an approach is often taken to narrow down an appropriate prediction model to be used in the business from a plurality of prediction models that can be considered as alternatives according to a reference evaluation index. At that time, AIC (An Information Criterion) is one of the representative indices adopted as evaluation indices. Literature
(Hiromatsu, Namika: Economic Time Series Analysis, Asakura Shoten, 1990.
According to 11, pp58), the AIC is an index for comparing the poorness of a model having a parameter determined by the maximum likelihood method, and the larger the AIC is for the same data, the worse the model is. Therefore, from the standpoint of evaluating the prediction model, attention should be paid to the magnitude of AIC.

【0003】[0003]

【発明が解決しようとする課題】上記従来技術では統計
・予測理論的見地からの評価指標でのみしか予測モデル
の良否を評価していない。そのため、統計・予測に関す
る専門家以外の人に対して、予測モデル適用の効果をわ
かりやすく説明するには、予測モデル適用による予測精
度向上が業務系システムに及ぼす効果までを踏まえた評
価結果が新たに必要になるという問題があった。更に、
上記従来技術ではAICのみが予測モデルを更に緻密化
すべきか否かの判断基準であることから、業務系システ
ムで要求している以上の精度を確保しようと過度な予測
モデル再構築作業に陥りやすいという問題があった。
In the above prior art, the quality of a prediction model is evaluated only by an evaluation index from a statistical / prediction theoretical viewpoint. Therefore, in order to clearly explain the effects of applying a prediction model to people other than experts in statistics and prediction, evaluation results that take into account the effect of improving the prediction accuracy by applying a prediction model on business systems will be added. Was necessary. Furthermore,
In the above prior art, since only the AIC is a criterion for determining whether or not the prediction model should be further refined, an excessive prediction model rebuilding operation is likely to occur in order to secure more accuracy than required by the business system. There was a problem.

【0004】本発明の目的は、上記の問題を鑑み、需要
予測モデル適用による実業務への有用性を検証する評価
作業を迅速化、容易化すると共に、業務系システムで要
求している以上の精度を確保しようとする無駄な予測モ
デル再構築作業を抑止する需要予測モデル評価方法を提
供することにある。
SUMMARY OF THE INVENTION In view of the above problems, it is an object of the present invention to speed up and facilitate an evaluation work for verifying the usefulness of a demand forecasting model for an actual business, and to provide a business system which is more than required. It is an object of the present invention to provide a demand forecasting model evaluation method that suppresses useless forecasting model reconstruction work for ensuring accuracy.

【0005】[0005]

【課題を解決するための手段】上記の目的は下記の
(1)〜(7)の手段により達成される。
The above object is achieved by the following means (1) to (7).

【0006】(1)入力装置、出力装置、製品の需要実
績値に関する情報の記憶領域および需要予測モデルによ
り算出された該製品の需要予測値に関する情報の記憶領
域を含む記憶装置、並びに、前記記憶装置内の情報をも
とに前記入力装置から入力された評価期間における需要
予測モデルの評価値を算出する演算装置を有する計算機
を用いた需要予測モデル評価方法において、前記評価期
間における需要実績値と需要予測値を取り込み、前記入
力装置から入力された市場への製品の供給サイクルごと
に前記需要実績値と前記需要予測値との乖離値を算出
し、前記乖離値に応じて供給過剰コスト及び供給不足コ
ストを算出し、前記出力装置に前記供給過剰コスト及び
前記供給不足コストを出力する。
(1) An input device, an output device, a storage device including a storage area for information relating to the actual demand value of a product and a storage area for storing information relating to the predicted demand value of the product calculated by a demand prediction model, and the storage device In a demand forecasting model evaluation method using a computer having an arithmetic unit that calculates an evaluation value of a demand forecasting model in an evaluation period input from the input device based on information in the device, an actual demand value in the evaluation period and Incorporating demand forecast values, calculating a divergence value between the actual demand value and the demand forecast value for each supply cycle of a product to the market input from the input device, and determining an excess supply cost and supply according to the divergence value. A shortage cost is calculated and the excess supply cost and the insufficient supply cost are output to the output device.

【0007】(2)供給サイクル内での需要予測値から
需要実績値を減じた値が正の場合には市場への製品の供
給量が過剰と判定した後、供給過剰に伴うコストを算出
することを特徴とする。
(2) If the value obtained by subtracting the actual demand value from the demand forecast value in the supply cycle is positive, it is determined that the supply of the product to the market is excessive, and then the cost associated with the excess supply is calculated. It is characterized by the following.

【0008】(3)供給サイクル内での需要予測値から
需要実績値を減じた値が市場において在庫可能な限界値
より小さい場合には在庫保持コスト、大きい場合には処
分コストにそれぞれ分類して供給過剰に伴うコストを算
出する。
(3) If the value obtained by subtracting the actual demand value from the demand forecast value in the supply cycle is smaller than the limit value that can be stocked in the market, it is classified into inventory holding cost, and if larger, it is classified into disposal cost. Calculate the costs associated with oversupply.

【0009】(4)供給サイクル内での需要予測値から
需要実績値を減じた値が負の場合には市場への製品の供
給量が不足と判定した後、供給不足に伴うコストを算出
する。
(4) If the value obtained by subtracting the actual demand value from the predicted demand value in the supply cycle is negative, it is determined that the supply amount of the product to the market is insufficient, and then the cost associated with the supply shortage is calculated. .

【0010】(5)供給サイクル内での需要予測値から
需要実績値を減じた値が市場において緊急調達可能な限
界値より小さい場合には緊急調達コスト、大きい場合に
は機会損失コストにそれぞれ分類して供給不足に伴うコ
ストを算出する。
(5) If the value obtained by subtracting the actual demand value from the demand forecast value in the supply cycle is smaller than the limit value for urgent procurement in the market, it is classified into emergency procurement cost, and if larger, it is classified into opportunity loss cost. And calculate the cost associated with the supply shortage.

【0011】(6)供給サイクルごとの需要実績値と需
要予測値との乖離値を理論在庫と見做し、需要予測モデ
ル評価期間の開始時点から終了時点までを対象に理論在
庫の時系列推移図を出力装置に出力する。
(6) The difference between the actual demand value and the demand forecast value for each supply cycle is regarded as the theoretical stock, and the time series transition of the theoretical stock from the start to the end of the demand forecast model evaluation period The figure is output to an output device.

【0012】(7)理論在庫の時系列推移図は需要実績
値と需要予測値との乖離値の正負に応じて出力形態を変
えることで過剰在庫と不足在庫とを識別する。
(7) In the time series transition diagram of the theoretical inventory, the excess inventory and the short inventory are identified by changing the output form according to the sign of the difference between the actual demand value and the predicted demand value.

【0013】[0013]

【発明の実施の形態】以下、本発明の実施例を図面を用
いて詳細に説明する。
Embodiments of the present invention will be described below in detail with reference to the drawings.

【0014】図1は、本実施例の装置構成図であり、入
力装置1、出力装置2、記憶装置3、演算装置4、およ
び、それらを制御する制御装置5から構成される。記憶
装置3内には、図2に示すように予測対象製品名称記憶
欄201と予測対象製品の販売量実績(本実施例では販
売量を需要量と見做す)を示す販売量実績デ−タ欄20
2とを有する販売実績情報テ−ブル200、図3に示す
ように予測対象製品名称記憶欄301と需要予測モデル
により予測対象製品の販売量を予測した値を示す予測値
デ−タ欄302とを有する販売予測情報テ−ブル30
0、図4に示すように入力装置1から入力された需要予
測モデルの評価期間を示す評価期間テ−ブル400が格
納されている。演算装置4は、四則演算や各種関数演算
を行う演算機能6と本発明に基づき需要予測モデル適用
による効果を評価する需要予測モデル評価機能7から成
る。以下、図5のフロ−チャ−トに沿って本発明の中心
である需要予測モデル評価機能7の処理動作および情報
の伝達動作を説明する。なお、本実施例で用いる予測値
データは需要予測モデルにより製品別に既に算出済みと
し、また、その算出に用いられる需要予測モデル(以降
予測モデルと略す)はモデル構造、構造パラメ−タが適
正化されていることを前提にする。
FIG. 1 is an apparatus configuration diagram of the present embodiment, which comprises an input device 1, an output device 2, a storage device 3, an arithmetic device 4, and a control device 5 for controlling them. In the storage device 3, as shown in FIG. 2, a sales volume actual data indicating a predicted target product name storage column 201 and a sales volume performance of the prediction target product (in this embodiment, the sales volume is regarded as a demand volume). Column 20
2, a forecast target product name storage column 301 as shown in FIG. 3, a forecast value data column 302 indicating a value obtained by predicting the sales volume of the forecast target product by the demand forecast model. Forecast information table 30 having
0, an evaluation period table 400 indicating the evaluation period of the demand forecast model input from the input device 1 is stored as shown in FIG. The arithmetic unit 4 includes an arithmetic function 6 for performing four arithmetic operations and various function operations, and a demand prediction model evaluation function 7 for evaluating the effect of applying the demand prediction model based on the present invention. Hereinafter, the processing operation and the information transmission operation of the demand forecasting model evaluation function 7, which is the center of the present invention, will be described with reference to the flowchart of FIG. It should be noted that the forecast value data used in the present embodiment has already been calculated for each product by the demand forecast model, and the demand forecast model (hereinafter abbreviated as “forecast model”) used for the calculation has been optimized for the model structure and structural parameters. Assume that it is.

【0015】<ステップ501>販売実績・販売予測デ
−タの取込み 記憶装置3に格納されている販売実績情報テ−ブル20
0及び販売予測情報テ−ブル300からそれぞれ予測対
象製品の販売実績デ−タ及び販売予測デ−タを取り込
み、図6に示す形式の評価対象デ−タテ−ブル600に
格納する。
<Step 501> Import of sales performance / sales prediction data Sales performance information table 20 stored in storage device 3
0 and the sales forecast information table 300, the sales performance data and the sales forecast data of the product to be predicted are fetched, and stored in the evaluation target data table 600 in the format shown in FIG.

【0016】<ステップ502>予測モデル評価用条件
の取込み 予測モデルを評価する上で必要となる条件として、ま
ず、図7のように市場(以降本実施例では市場を在庫の
保管倉庫として扱う)に対し、どのくらいの間隔で製品
を供給していくかを示す供給サイクルを入力装置1から
取込み、図8に示す形式の供給サイクルテ−ブル800
に格納する。さらに、予測モデルよる予測値および前記
の供給サイクルに従い倉庫に在庫を補充した場合、損失
コストがどの程度発生するかを算出するためのコスト算
出用パラメータを入力装置1から取込み、図9に示す形
式のコスト算出用パラメータテ−ブル900に格納す
る。ここで、コスト算出用パラメータテ−ブル900に
は、供給過剰コスト算出用情報901として供給量が需
要量を上回った場合どの程度まで倉庫での在庫保持が可
能な否かを示す在庫保持限界値902、供給量が需要量
を上回った場合の乖離量が在庫保持限界値902以下に
おける単位量当たりの在庫保持に要するコストを示す在
庫保持単位コスト903、供給量が需要量を上回った場
合の乖離量が在庫保持限界値902を超える際に発生す
る単位量当たりの製品処分に要するコストを示す処分単
位コスト904が格納されていると共に、供給不足コス
ト算出用情報905として供給量が需要量を下回った場
合どの程度まで製品の緊急調達が可能な否かを示す緊急
調達限界値906、供給量が需要量を下回った場合の乖
離量の絶対値が緊急調達限界値906以下における単位
量当たりの緊急調達に要するコストを示す緊急調達単位
コスト907、供給量が需要量を下回った場合の乖離量
の絶対値が緊急調達限界値906を超える際に発生する
単位量当たりの機会損失を示す機会損失単位コスト90
8が格納されている。
<Step 502> Incorporation of Conditions for Evaluating Predictive Model As conditions necessary for evaluating the predictive model, first, as shown in FIG. 7, a market (hereinafter, the market is treated as a stock storage warehouse in this embodiment) is shown in FIG. In response to this, a supply cycle indicating the intervals at which the products are supplied is taken from the input device 1, and a supply cycle table 800 of the type shown in FIG.
To be stored. Further, a cost calculation parameter for calculating how much a loss cost is generated when a warehouse is restocked in accordance with a predicted value by a prediction model and the supply cycle described above is fetched from the input device 1 and has a format shown in FIG. Is stored in the cost calculation parameter table 900. Here, the cost calculation parameter table 900 includes, as information 901 for excess supply cost calculation, a stock holding limit value indicating how much stock can be held in the warehouse when the supply amount exceeds the demand amount. 902, a stock holding unit cost 903 indicating a cost required for stock holding per unit amount when the deviation amount is larger than the demand amount when the supply amount exceeds the demand amount 902, and a deviation when the supply amount exceeds the demand amount. A disposal unit cost 904 indicating the cost required for product disposal per unit amount generated when the amount exceeds the stock holding limit value 902 is stored, and the supply amount is lower than the demand amount as the supply shortage cost calculation information 905. The emergency procurement limit value 906 indicates to what extent emergency procurement of the product is possible, and the absolute value of the deviation amount when the supply amount falls below the demand amount is urgently adjusted. Emergency procurement unit cost 907 indicating the cost required for urgent procurement per unit amount below the limit value 906, a unit generated when the absolute value of the deviation amount exceeds the emergency procurement limit value 906 when the supply amount falls below the demand amount Opportunity loss unit cost 90 indicating opportunity loss per amount
8 is stored.

【0017】<ステップ503>供給量と需要量との乖
離量の算出 供給サイクル内における供給量と需要量との乖離量を算
出する。具体的には、図10に示すように評価期間テ−
ブル400の評価開始時点から評価終了時点までの期間
を対象に、供給サイクルテ−ブル800内の供給サイク
ル単位に評価対象デ−タテ−ブル600内の販売実績デ
ータ及び販売予測デ−タを集計して供給時点tにおける
販売実績累計値J(t)及び販売予測累計値Y(t)を求めた
後、次式により供給量と需要量との乖離量R(t)を算出
し、その結果を図11に示す乖離量テ−ブル1100に
格納する。
<Step 503> Calculation of deviation between supply amount and demand amount The deviation amount between supply amount and demand amount in the supply cycle is calculated. Specifically, as shown in FIG.
The sales performance data and the sales forecast data in the evaluation target data table 600 are totaled for each supply cycle in the supply cycle table 800 for the period from the evaluation start time to the evaluation end time of the table 400. After obtaining the cumulative sales value J (t) and the cumulative sales forecast value Y (t) at the supply time t, the deviation amount R (t) between the supply amount and the demand amount is calculated by the following equation. This is stored in the deviation amount table 1100 shown in FIG.

【0018】R(t) = Y(t) − J(t) <ステップ504>損失コストの算出 予測モデルよる予測値および設定された供給サイクルに
従い倉庫に在庫を補充した場合を想定し、供給サイクル
内における供給量と需要量との乖離がもたらす損失をコ
ストとして算出する。その具体的な処理手順を図12の
フロ−チャ−トに沿って説明する。
R (t) = Y (t) -J (t) <Step 504> Calculation of loss cost Assuming a case where inventory is replenished to the warehouse in accordance with the predicted value by the prediction model and the set supply cycle, the supply cycle is assumed. The loss caused by the divergence between the supply amount and the demand amount is calculated as the cost. The specific processing procedure will be described with reference to the flowchart of FIG.

【0019】まず、乖離量テ−ブル1100から供給時
点tにおける供給量と需要量との乖離量R(t)を取込み
(ステップ1201)、乖離量R(t)の大小により損失
コストの種別を判定する(ステップ1202)。乖離量
R(t)が正でかつ在庫保持限界値902を超える値であ
れば次式で処分コストS(t)を算出する(ステップ12
03)。
First, the difference R (t) between the supply amount and the demand amount at the supply time t is fetched from the difference amount table 1100 (step 1201), and the type of the loss cost is determined based on the magnitude of the difference R (t). A determination is made (step 1202). If the deviation R (t) is positive and exceeds the stock holding limit value 902, the disposal cost S (t) is calculated by the following equation (step 12).
03).

【0020】 S(t) = K1*C1+(R(t)−K1)*C2 ここで、 K1:在庫保持限界値902 C1:在庫保持単位コスト903 C2:処分単位コスト904 乖離量R(t)が正でかつ在庫保持限界値902以下であ
れば次式で在庫保持コストZ(t)を算出する(ステップ
1204)。
S (t) = K1 * C1 + (R (t) −K1) * C2 where K1: inventory holding limit value 902 C1: inventory holding unit cost 903 C2: disposal unit cost 904 Deviation amount R (t) Is positive and equal to or less than the stock holding limit value 902, the stock holding cost Z (t) is calculated by the following equation (step 1204).

【0021】Z(t) = R(t) * C1 乖離量R(t)が負でかつその絶対値が緊急調達限界値9
06以下であれば次式で緊急調達コストW(t)を算出す
る(ステップ1205)。
Z (t) = R (t) * C1 The deviation R (t) is negative and its absolute value is the emergency procurement limit value 9
If it is not more than 06, the emergency procurement cost W (t) is calculated by the following equation (step 1205).

【0022】W(t) = |R(t)|* C3 ここで、C3:緊急調達単位コスト907 乖離量R(t)が負でその絶対値が緊急調達限界値906
を超える値であれば次式で機会損失コストV(t)を算出
する(ステップ1206)。
W (t) = | R (t) | * C3 where C3: emergency procurement unit cost 907 The deviation R (t) is negative and its absolute value is the emergency procurement limit value 906.
If the value exceeds the value, the opportunity loss cost V (t) is calculated by the following equation (step 1206).

【0023】 V(t) = K2*C3+(|R(t)|−K2)*C4 ここで、K2:緊急調達限界値906 C4:機会損失単位コスト908 以上のように乖離量R(t)の大小により供給時点tにお
ける損失コストを算出した後、その結果と供給時点(T
−1)までの累計損失コストとを加算したコストを供給
時点tまでの累計損失コストとして、図13に示す形式
の累計損失コストテーブル1300に格納する(ステッ
プ1207)。最後に、評価期間テ−ブル400に格納
されている評価開始時点から評価終了時点までの期間を
対象に全供給時点において損失コストの算出が完了した
か否かを判定し(ステップ1208)、未完であれば供
給時点を更新してステップ1201に戻り、完了したな
らば本ステップを終了する。
V (t) = K2 * C3 + (| R (t) | -K2) * C4 where K2: emergency procurement limit value 906 C4: opportunity loss unit cost 908 As described above, the deviation amount R (t) After calculating the loss cost at the supply time t according to the magnitude of the
The cost obtained by adding the cumulative loss cost up to -1) is stored in the cumulative loss cost table 1300 of the format shown in FIG. 13 as the cumulative loss cost up to the supply time t (step 1207). Finally, it is determined whether or not the calculation of the loss cost has been completed at all supply points in the period from the evaluation start point to the evaluation end point stored in the evaluation period table 400 (step 1208). If so, the supply point is updated and the process returns to step 1201, and if completed, this step ends.

【0024】<ステップ505>予測モデル評価結果の
出力 累計損失コストテーブル1300の内容を出力装置2に
出力する。具体的には図14 のように、評価対象予
測モデルを適用した際の損失コスト、及び、比較対象と
する基準予測モデル(ここでは評価期間内における各時
点の需要量は一定であるという前提に基づき予測値を算
出するモデルを採用する)を適用した際の損失コスト、
をそれぞれ出力する損失コスト出力領域1401、基準
予測モデルに比べ評価対象予測モデルがどの程度コスト
低減に寄与するかを示すコスト低減情報出力領域140
2を中心に画面を構成する。なお、コスト低減情報出力
領域1402においてコスト低減額CG、コスト低減率
CRはそれぞれ次式で算出する。
<Step 505> Output of prediction model evaluation result The contents of the accumulated loss cost table 1300 are output to the output device 2. Specifically, as shown in FIG. 14, the loss cost when the evaluation target prediction model is applied, and the reference prediction model to be compared (here, it is assumed that the demand at each point in the evaluation period is constant). Using a model that calculates the predicted value based on
, A cost reduction information output area 1401 showing how much the evaluation target prediction model contributes to cost reduction compared to the reference prediction model.
The screen is constructed around 2. The cost reduction amount CG and the cost reduction rate CR in the cost reduction information output area 1402 are calculated by the following equations.

【0025】CG = M − N CR = ((M − N)/M)*100 ここで、N:評価対象予測モデルを適用した際の損失コ
スト M:基準予測モデルを適用した際の損失コスト 更に、同図において在庫推移図ボタン1403がクリッ
クされた場合には、供給サイクルごとの供給量と需要量
との乖離を理論在庫と見做し、予測モデル評価期間の開
始時点から終了時点までを対象に理論在庫の時系列推移
図を出力装置2に出力する。その出力の一例を図15に
示す。同図では理論在庫が正の場合と負の場合とそれぞ
れ異なった出力形態をとることにより、過剰在庫と不足
在庫とを識別しやすくしている。識別方法としては本実
施例のように網掛けの種類を変更する方法があるが、他
にも色や塗りつぶしなどの種類を変更する方法も考えら
れる。
CG = M−NCR = ((M−N) / M) * 100 where N: loss cost when the evaluation target prediction model is applied M: loss cost when the reference prediction model is applied When the stock transition diagram button 1403 is clicked in the same figure, the difference between the supply amount and the demand amount for each supply cycle is regarded as theoretical stock, and the target from the start time to the end time of the prediction model evaluation period is considered. Then, a time series transition diagram of the theoretical stock is output to the output device 2. FIG. 15 shows an example of the output. In the figure, different output forms are used for the case where the theoretical stock is positive and the case where the theoretical stock is negative, so that it is easy to distinguish between the excess stock and the short stock. As the identification method, there is a method of changing the type of hatching as in the present embodiment, but other methods of changing the type of color, fill, and the like are also conceivable.

【0026】<ステップ506>予測モデル評価処理の
終了判定 ステップ505で出力された予測モデル評価結果が満足
のいくものであれば、本ステップを終了し、不満足なら
ばステップ502に戻り予測モデル評価用条件を変更し
再度予測モデルの評価を実行する。
<Step 506> Judgment of Completion of Prediction Model Evaluation Processing If the prediction model evaluation result output in step 505 is satisfactory, the present step is terminated. Change the conditions and evaluate the prediction model again.

【0027】以上のような処理ステップにより、予測モ
デル適用により発生するであろう供給過剰及び供給不足
に関する損失コストを定量的算出できると共に、その結
果を予測モデル評価者にわかりやすく提示できる。これ
により、予測モデル評価作業の迅速化、容易化が図れる
と共に、業務系システムで要求している以上の精度を確
保しようとする無駄な予測モデル再構築作業の抑止が期
待できる
Through the above-described processing steps, it is possible to quantitatively calculate the loss cost relating to the excess supply and the shortage of supply that may occur by applying the prediction model, and to present the result to the predictive model evaluator in an easy-to-understand manner. As a result, the prediction model evaluation work can be speeded up and facilitated, and it can be expected that useless prediction model rebuilding work for securing accuracy higher than required by the business system is suppressed.

【0028】[0028]

【発明の効果】本発明によれば、需要予測モデル適用に
よる実業務への有用性を検証する作業の迅速化、容易化
が図れると共に、業務系システムで要求している以上の
精度を確保しようとする無駄な予測モデル再構築作業を
抑止できるようになる。さらに副次的な効果ではある
が、本発明により、需要予測モデル適用による実業務へ
の有用性がわかわりやすく提示されるので、需要予測モ
デル導入の重要性、必要性に対する認識が経営層、エン
ドユーザ層の人たちにも高まることが期待できる。
According to the present invention, it is possible to speed up and simplify the operation of verifying the usefulness of the actual business by applying the demand forecasting model, and to secure the accuracy higher than required by the business system. Useless prediction model rebuilding work can be suppressed. As a further side effect, the present invention makes it easy to understand the usefulness of the demand forecasting model by applying it to actual work. It can be expected to increase for end users.

【図面の簡単な説明】[Brief description of the drawings]

【図1】一実施例の装置構成図である。FIG. 1 is an apparatus configuration diagram of an embodiment.

【図2】予測対象製品に関する販売実績情報テ−ブルの
構成図である。
FIG. 2 is a configuration diagram of a sales performance information table relating to a product to be predicted.

【図3】予測対象製品に関する販売予測情報テ−ブルの
構成図である。
FIG. 3 is a configuration diagram of a sales prediction information table relating to a product to be predicted.

【図4】需要予測モデル評価期間テ−ブルの構成図であ
る。
FIG. 4 is a configuration diagram of a demand prediction model evaluation period table.

【図5】需要予測モデル評価方法の処理動作および情報
の伝達動作を説明するための図である。
FIG. 5 is a diagram for explaining a processing operation and an information transmission operation of the demand prediction model evaluation method.

【図6】評価対象デ−タテ−ブルの構成図である。FIG. 6 is a configuration diagram of an evaluation target data table.

【図7】供給サイクルを説明するための図である。FIG. 7 is a diagram for explaining a supply cycle.

【図8】供給サイクルテ−ブルの構成図である。FIG. 8 is a configuration diagram of a supply cycle table.

【図9】コスト算出用パラメータテ−ブルの構成図であ
る。
FIG. 9 is a configuration diagram of a cost calculation parameter table.

【図10】供給量と需要量の乖離量を説明するための図
である。
FIG. 10 is a diagram for explaining a deviation amount between a supply amount and a demand amount.

【図11】乖離量テ−ブルの構成図である。FIG. 11 is a configuration diagram of a deviation amount table.

【図12】損失コストの算出手順を示すフロ−チャ−ト
である。
FIG. 12 is a flowchart showing a procedure for calculating a loss cost.

【図13】累計損失コストテ−ブルの構成図である。FIG. 13 is a configuration diagram of a cumulative loss cost table.

【図14】予測モデル評価結果の出力画面の一例を示す
図である。
FIG. 14 is a diagram illustrating an example of an output screen of a prediction model evaluation result.

【図15】理論在庫の時系列推移図の出力画面の一例を
示す図である。
FIG. 15 is a diagram illustrating an example of an output screen of a time-series transition diagram of theoretical stock.

【符号の説明】[Explanation of symbols]

1・・・入力装置、2・・・出力装置、3・・・記憶装置、4・・・
演算装置、7・・・予測モデル評価機能、502・・・予測モ
デル評価用条件の取込み、504・・・損失コストの算
出、505・・・予測モデル評価結果の出力
DESCRIPTION OF SYMBOLS 1 ... Input device, 2 ... Output device, 3 ... Storage device, 4 ...
Arithmetic unit, 7: predictive model evaluation function, 502: capture of predictive model evaluation conditions, 504: calculation of loss cost, 505: output of predictive model evaluation results

Claims (7)

【特許請求の範囲】[Claims] 【請求項1】入力装置、出力装置、製品の需要実績値に
関する情報の記憶領域および需要予測モデルにより算出
された該製品の需要予測値に関する情報の記憶領域を含
む記憶装置、並びに、前記記憶装置内の情報をもとに前
記入力装置から入力された評価期間における需要予測モ
デルの評価値を算出する演算装置を有する計算機を用い
た需要予測モデル評価方法において、前記評価期間にお
ける需要実績値と需要予測値を取り込み、前記入力装置
から入力された市場への製品の供給サイクルごとに前記
需要実績値と前記需要予測値との乖離値を算出し、前記
乖離値に応じて供給過剰コスト及び供給不足コストを算
出し、前記出力装置に前記供給過剰コスト及び前記供給
不足コストを出力することを特徴とする需要予測モデル
評価方法。
1. An input device, an output device, a storage device including a storage area for information relating to a demand actual value of a product and a storage area for storing information relating to a demand prediction value of the product calculated by a demand prediction model, and the storage device A demand prediction model evaluation method using a computer having an arithmetic unit that calculates an evaluation value of a demand prediction model in an evaluation period input from the input device based on information in the demand period. A predicted value is fetched, a deviation value between the actual demand value and the predicted demand value is calculated for each supply cycle of the product to the market input from the input device, and an excess supply cost and an insufficient supply are determined according to the deviation value. A demand prediction model evaluation method, comprising calculating a cost and outputting the excess supply cost and the insufficient supply cost to the output device.
【請求項2】請求項1記載の需要予測モデル評価方法に
おいて、供給サイクル内での需要予測値から需要実績値
を減じた値が正の場合には市場への製品の供給量が過剰
と判定した後、供給過剰に伴うコストを算出することを
特徴とする需要予測モデル評価方法。
2. The demand prediction model evaluation method according to claim 1, wherein when the value obtained by subtracting the actual demand value from the demand forecast value in the supply cycle is positive, it is determined that the supply amount of the product to the market is excessive. And then calculating the cost associated with excess supply.
【請求項3】請求項2記載の需要予測モデル評価方法に
おいて、供給サイクル内での需要予測値から需要実績値
を減じた値が市場において在庫可能な限界値より小さい
場合には在庫保持コスト、大きい場合には処分コストに
それぞれ分類して供給過剰に伴うコストを算出すること
を特徴とする需要予測モデル評価方法。
3. The demand forecasting model evaluation method according to claim 2, wherein if a value obtained by subtracting the actual demand value from the demand forecast value in the supply cycle is smaller than a limit value that can be stocked in the market, an inventory holding cost; A demand forecasting model evaluation method characterized in that when it is large, it is classified into disposal costs and the costs associated with excess supply are calculated.
【請求項4】請求項1記載の需要予測モデル評価方法に
おいて、供給サイクル内での需要予測値から需要実績値
を減じた値が負の場合には市場への製品の供給量が不足
と判定した後、供給不足に伴うコストを算出することを
特徴とする需要予測モデル評価方法。
4. A demand forecasting model evaluation method according to claim 1, wherein if the value obtained by subtracting the actual demand value from the demand forecast value in the supply cycle is negative, it is determined that the supply amount of the product to the market is insufficient. And calculating a cost associated with a shortage of supply.
【請求項5】請求項4記載の需要予測モデル評価方法に
おいて、供給サイクル内での需要予測値から需要実績値
を減じた値が市場において緊急調達可能な限界値より小
さい場合には緊急調達コスト、大きい場合には機会損失
コストにそれぞれ分類して供給不足に伴うコストを算出
することを特徴とする需要予測モデル評価方法。
5. The demand forecasting model evaluation method according to claim 4, wherein when a value obtained by subtracting the actual demand value from the demand forecast value in the supply cycle is smaller than a limit value for urgent procurement in the market, the emergency procurement cost. A demand prediction model evaluation method characterized by classifying the costs into opportunity loss costs when the costs are large, and calculating costs associated with supply shortages.
【請求項6】請求項1記載の需要予測モデル評価方法に
おいて、供給サイクルごとの需要実績値と需要予測値と
の乖離値を理論在庫と見做し、需要予測モデル評価期間
の開始時点から終了時点までを対象に理論在庫の時系列
推移図を出力装置に出力することを特徴とする需要予測
モデル評価方法。
6. The demand forecasting model evaluation method according to claim 1, wherein a deviation value between the actual demand value and the demand forecasting value for each supply cycle is regarded as theoretical stock, and the demand forecasting model evaluation period is started and ended. A demand forecasting model evaluation method characterized by outputting a time-series transition diagram of theoretical stock to an output device for up to a time point.
【請求項7】請求項6記載の需要予測モデル評価方法に
おいて、理論在庫の時系列推移図は需要実績値と需要予
測値との乖離値の正負に応じて出力形態を変えることで
過剰在庫と不足在庫とを識別することを特徴とする需要
予測モデル評価方法。
7. The demand forecasting model evaluation method according to claim 6, wherein the time series transition diagram of the theoretical inventory is determined by changing the output form according to the sign of the difference between the actual demand value and the predicted demand value to thereby determine the excess inventory. A demand forecast model evaluation method characterized by identifying shortage stock.
JP3167097A 1997-02-17 1997-02-17 Demand prediction model evaluating method Pending JPH10228463A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3167097A JPH10228463A (en) 1997-02-17 1997-02-17 Demand prediction model evaluating method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3167097A JPH10228463A (en) 1997-02-17 1997-02-17 Demand prediction model evaluating method

Publications (1)

Publication Number Publication Date
JPH10228463A true JPH10228463A (en) 1998-08-25

Family

ID=12337572

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3167097A Pending JPH10228463A (en) 1997-02-17 1997-02-17 Demand prediction model evaluating method

Country Status (1)

Country Link
JP (1) JPH10228463A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001014295A (en) * 1999-06-30 2001-01-19 Sumitomo Metal Ind Ltd Data estimating method and data estimating device, and recording medium
JP2004072286A (en) * 2002-08-05 2004-03-04 Nippon Telegr & Teleph Corp <Ntt> Method and device for detecting structural change and communication network abnormal state and program
JP2005216125A (en) * 2004-01-30 2005-08-11 Hitachi Ltd Evaluation method for facility value and facility operation method value, device and program for the method, evaluation method for facility operation method value and device therefor
JP2007018216A (en) * 2005-07-07 2007-01-25 Nec Corp Reasonable inventory quantity calculation system and reasonable inventory quantity calculation method
US8135797B2 (en) 2005-06-29 2012-03-13 Fujitsu Limited Management policy evaluation system and recording medium storing management policy evaluation program
JP2018136806A (en) * 2017-02-23 2018-08-30 沖電気工業株式会社 Demand prediction model evaluation apparatus and demand prediction model evaluation method
WO2019065610A1 (en) * 2017-09-29 2019-04-04 日本電気株式会社 Information processing device, control method and program
JP2019053684A (en) * 2017-09-19 2019-04-04 株式会社プロフィールド Information processing device, information processing method, and program
WO2019187341A1 (en) 2018-03-30 2019-10-03 Necソリューションイノベータ株式会社 Index computation device, prediction system, progress prediction evaluation method, and program
JP2020160822A (en) * 2019-03-27 2020-10-01 株式会社オービック Decision support device, decision support program and decision support method

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001014295A (en) * 1999-06-30 2001-01-19 Sumitomo Metal Ind Ltd Data estimating method and data estimating device, and recording medium
JP2004072286A (en) * 2002-08-05 2004-03-04 Nippon Telegr & Teleph Corp <Ntt> Method and device for detecting structural change and communication network abnormal state and program
JP2005216125A (en) * 2004-01-30 2005-08-11 Hitachi Ltd Evaluation method for facility value and facility operation method value, device and program for the method, evaluation method for facility operation method value and device therefor
JP4504695B2 (en) * 2004-01-30 2010-07-14 株式会社日立製作所 Calculation method of procurement cost of procurement items according to storage facilities and operation method, and comparison method of operation rules
US8135797B2 (en) 2005-06-29 2012-03-13 Fujitsu Limited Management policy evaluation system and recording medium storing management policy evaluation program
JP2007018216A (en) * 2005-07-07 2007-01-25 Nec Corp Reasonable inventory quantity calculation system and reasonable inventory quantity calculation method
JP2018136806A (en) * 2017-02-23 2018-08-30 沖電気工業株式会社 Demand prediction model evaluation apparatus and demand prediction model evaluation method
JP2019053684A (en) * 2017-09-19 2019-04-04 株式会社プロフィールド Information processing device, information processing method, and program
WO2019065610A1 (en) * 2017-09-29 2019-04-04 日本電気株式会社 Information processing device, control method and program
JPWO2019065610A1 (en) * 2017-09-29 2020-10-22 日本電気株式会社 Information processing equipment, control methods, and programs
WO2019187341A1 (en) 2018-03-30 2019-10-03 Necソリューションイノベータ株式会社 Index computation device, prediction system, progress prediction evaluation method, and program
JP2020160822A (en) * 2019-03-27 2020-10-01 株式会社オービック Decision support device, decision support program and decision support method

Similar Documents

Publication Publication Date Title
US9423989B2 (en) System and method for dynamically reconfiguring one or more autonomous cells in a print shop environment
US8271983B2 (en) Workload scheduler with cumulative weighting indexes
Fox et al. ISIS—a knowledge‐based system for factory scheduling
JP4739472B2 (en) Performance prediction apparatus and method, and recording medium
US7881920B2 (en) Systemic enterprise management method and apparatus
US20130238399A1 (en) Computer-Implemented Systems and Methods for Scenario Analysis
CN113112088B (en) Edge cloud cooperative digital twin intelligent scheduling application operation position adaptation method
JP2002073746A (en) Demand predicion method in part stock control
CN111915254A (en) Inventory optimization control method and system suitable for automobile after-sales accessories
EP3652644A1 (en) Data centre utilisation forecasting system and method
JPH10228463A (en) Demand prediction model evaluating method
JP3668642B2 (en) Data prediction method, data prediction apparatus, and recording medium
US8019638B1 (en) Dynamic construction of business analytics
CN114358380A (en) Method, equipment and processor for engineering vehicle scheduling
US20230267007A1 (en) System and method to simulate demand and optimize control parameters for a technology platform
WO2013013137A1 (en) Conflicting expert systems
CN117350640A (en) Project progress management method and system
CN110689278A (en) Sheet metal material management method and system, storage medium and electronic equipment
Serpell Improving conceptual cost estimating performance
JPH08279013A (en) Proper inventory volume setting system
JPH09101947A (en) Time series forcasting method
CN110858355A (en) Project budget balance prediction method and device
Liu Scheduling via reinforcement
JP3260333B2 (en) Production management device, production management system, production planning method, and storage medium
CN113762842A (en) Warehouse scheduling method, server and system