JPH10227398A - Disposal facility of boiloff gas and method thereof, manufacturing facility of natural gas and method thereof - Google Patents

Disposal facility of boiloff gas and method thereof, manufacturing facility of natural gas and method thereof

Info

Publication number
JPH10227398A
JPH10227398A JP3191397A JP3191397A JPH10227398A JP H10227398 A JPH10227398 A JP H10227398A JP 3191397 A JP3191397 A JP 3191397A JP 3191397 A JP3191397 A JP 3191397A JP H10227398 A JPH10227398 A JP H10227398A
Authority
JP
Japan
Prior art keywords
gas
boil
natural gas
lng
stage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP3191397A
Other languages
Japanese (ja)
Inventor
Yasuhiro Ueno
康弘 上野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Osaka Gas Co Ltd
Original Assignee
Osaka Gas Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Osaka Gas Co Ltd filed Critical Osaka Gas Co Ltd
Priority to JP3191397A priority Critical patent/JPH10227398A/en
Publication of JPH10227398A publication Critical patent/JPH10227398A/en
Pending legal-status Critical Current

Links

Landscapes

  • Filling Or Discharging Of Gas Storage Vessels (AREA)

Abstract

PROBLEM TO BE SOLVED: To reduce cost by mixing liquefied natural gas(LNG) with a boiloff gas(BOG) line on the intermediate stage of multistage compression while regulating the flow through the mixing line. SOLUTION: BOG 2 accumulated in the upper part of a tank 1 is introduced to a BOG disposal facility 8 by the pressure through a BOG piping 5. The facility 8 is provided with a first stage compressor 81, a second stage compressor 82, a third stage compressor 83, an intercooler 84, an aftercooler 85, a LNG feed piping 86 as a LNG mixing line L-mix, a LNG flow regulating valve 87, and a BOG/LNG mixing nozzle 88. Because LNG pressure in a LNG piping 6 is higher than BOG pressure compressed by the compressor 82, they can be easily mixed by the mixing nozzle 88, compressed mass flow at the compressor 83 is increased but the suction temperature is lowered, and the required load of the compressor is lowered. Consequently, by appropriately regulating the LNG flow to be mixed, the compressor load is reduced, and hence the cost can be reduced.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、都市ガス等として
利用される天然ガスの製造技術に関するものであり、原
料としての液化天然ガス(以後LNGと呼ぶ)の貯蔵設
備等から発生するボイルオフガス(以後BOGと呼ぶ)
を利用する技術に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a technology for producing natural gas used as city gas and the like, and relates to a boil-off gas generated from a storage facility or the like of liquefied natural gas (hereinafter referred to as LNG) as a raw material. (Hereinafter referred to as BOG)
Related to technology that utilizes

【0002】[0002]

【従来の技術】都市ガスの製造にあたっては、LNGを
主原料とし、これを気化器で昇温するとともに、その後
昇圧して、所定の温度、圧力状態の天然ガスを得る。そ
こで、LNG基地には、LNG貯蔵用の貯蔵設備が備え
られるとともに、この貯蔵設備に接続される配管系が設
けられている。このような貯蔵設備、配管系において
は、外界からの入熱のため、BOGが発生する。このB
OGの発生量は無視できない量であり、このようなBO
Gを、所定の温度、圧力状態まで、昇温、昇圧して利用
することが行われている。このような例の代表例は、図
4に示す従来例に見られるものであり、この例にあって
は、LNGタンク1から発生するBOG2を多段に圧縮
して、その圧力、温度を適切に調節して、天然ガスの製
造ラインに合流させることによって、BOG2を使用で
きるようにしている。こういった図4に示す天然ガスの
製造設備は、液化天然ガスを貯蔵する貯蔵設備(LNG
タンク1)を備え、この貯蔵設備より供給される液化天
然ガスを、昇温、昇圧して、第2温度、大気圧より高い
第2圧力の天然ガスを得る天然ガス供給ラインL−LN
Gを備えるとともに、液化天然ガスから発生するBOG
を、圧縮機により多段圧縮して、第1温度、大気圧より
高い第1圧力の昇圧ボイルオフガスを得るボイルオフガ
ス処理ラインL−BOGを備え、このラインで得られた
昇圧ボイルオフガスを、天然ガス供給ラインL−LNG
の下流側に合流して、BOGを利用できる形態としてい
る。
2. Description of the Related Art In the production of city gas, LNG is used as a main raw material, which is heated in a vaporizer and then pressurized to obtain natural gas at a predetermined temperature and pressure. Therefore, the LNG base is provided with storage facilities for storing LNG and a piping system connected to the storage facilities. In such storage facilities and piping systems, BOG is generated due to heat input from the outside. This B
The amount of OG generation is not negligible, and such BO
G has been used by raising the temperature and pressure to a predetermined temperature and pressure state. A typical example of such an example is found in the conventional example shown in FIG. 4. In this example, BOG 2 generated from the LNG tank 1 is compressed in multiple stages, and the pressure and temperature are appropriately adjusted. The BOG2 can be used by adjusting it to join the natural gas production line. The natural gas production facility shown in FIG. 4 is a storage facility (LNG) for storing liquefied natural gas.
A natural gas supply line L-LN which is provided with a tank 1) and which raises and raises the temperature of the liquefied natural gas supplied from this storage facility to obtain a natural gas having a second temperature and a second pressure higher than the atmospheric pressure.
G, and BOG generated from liquefied natural gas
And a boil-off gas processing line L-BOG for obtaining a boosted boil-off gas at a first temperature and a first pressure higher than the atmospheric pressure by multi-stage compression by a compressor. Supply line L-LNG
To the downstream side to use BOG.

【0003】天然ガス供給ラインL−LNGには、気化
器7、圧力調整弁9が備えられている。一方、ボイルオ
フガス処理ラインL−BOGには、3個の圧縮機81、
82、83が備えられるとともに、第2圧縮機82と第
3圧縮機83との間にインタークーラ84が、第3圧縮
機83の下手(下流)側に、アフタークーラ85が備え
られている。このような構造を採用することにより、天
然ガス供給ラインL−LNGを経た天然ガスにBOG由
来の天然ガスを良好に混合して、以後の用に供すること
ができる。
[0003] The natural gas supply line L-LNG is provided with a vaporizer 7 and a pressure regulating valve 9. On the other hand, in the boil-off gas processing line L-BOG, three compressors 81,
82 and 83, an intercooler 84 is provided between the second compressor 82 and the third compressor 83, and an aftercooler 85 is provided on the downstream side (downstream) of the third compressor 83. By adopting such a structure, natural gas derived from BOG can be favorably mixed with natural gas that has passed through the natural gas supply line L-LNG, and can be used for subsequent uses.

【0004】[0004]

【発明が解決しようとする課題】このようなBOGの処
理には、圧縮機に対する所定の動力を要するとともに、
インタークーラ、アフタークーラ用の設備費、さらに
は、これらの熱源及び運転費も必要となる。ここで、B
OGの発生は、設備としては避けられないものであるた
め、これを有用化するためのコストはできるだけ低減化
したい。従って、本発明は、上記の希望を満足するため
のものであり、BOGの有用化にあたって、必要となる
コストをできるだけ低減化することができる技術を提供
することにある。
The processing of such a BOG requires a predetermined power to the compressor,
Equipment costs for the intercooler and aftercooler, as well as these heat sources and operating costs are required. Where B
Since the occurrence of OG is inevitable as a facility, it is desired to reduce the cost for making this useful as much as possible. Accordingly, the present invention satisfies the above-mentioned demands, and it is an object of the present invention to provide a technology capable of minimizing the cost required for making BOG useful.

【0005】[0005]

【課題を解決するための手段】このような目的を達成す
るための本発明による液化天然ガスから発生するBOG
を、圧縮機により多段圧縮して、第1温度、大気圧より
高い第1圧力の昇圧BOGを得るBOGの処理設備の特
徴構成は、多段圧縮の中間段にあるボイルオフガスライ
ンに対して、液化天然ガスを流量調節しながら混合でき
るLNG混合ラインを備えたことにある。圧縮機に必要
とされる動力は、この圧縮機の入り側のガス(本願の場
合はBOG及びこのBOGに混合された液化天然ガス)
の量、温度、圧力状態、及び、出側のガスの温度、圧力
状態によって変化する。また、一般に、このようなBO
Gを使用するに場合にあっては、最終段を終えたBOG
に必要とされる温度、圧力状態は一義的に決まる。従っ
て、最終段の圧縮を終えた段階で、このような温度、圧
力の状態となるように、熱交換系を含めて各圧縮段に於
ける圧縮状態を決定するのであるが、多段階の初段にお
いて、例え比較的低温の状態が得られていたとしても、
連続的な多段圧縮をおこなうと、必要以上の動力を要し
たり、温度が最終段で高すぎ、インタークーラや、アフ
タークーラを必要とする場合がある。そこで、この本願
構成にあっては、中間段にあるBOGに対して、このB
OGより低温状態にあるLNGを、流量調整しながら、
LNG混合ラインを介して混合する。この場合、LNG
の混合流量は調整される。従って、この混合部以降の圧
縮段において必要となる動力、圧縮後の温度、圧力を、
この混合流量に従って調節することができる。結果、多
段圧縮工程において、圧縮に要する動力をできるだけ低
減化できるようにしたり、最終段を経て得られるガス状
態を、以降のBOGの使用状態に見合った(例えば、そ
の状態のまま気化後の天然ガスに合流できるように)状
態とすることができる。結果、BOGガスを、効率的に
有効に利用することができる。
SUMMARY OF THE INVENTION In order to achieve the above object, BOG generated from liquefied natural gas according to the present invention is provided.
Is processed in a multistage by a compressor to obtain a boosted BOG at a first temperature and a first pressure higher than the atmospheric pressure. The characteristic configuration of the BOG processing equipment is that a boil-off gas line at an intermediate stage of the multistage compression is liquefied. There is an LNG mixing line that can mix natural gas while adjusting the flow rate. The power required for the compressor is the gas on the inlet side of the compressor (in this case, BOG and liquefied natural gas mixed with this BOG)
, Temperature, and pressure, and the temperature and pressure of the outlet gas. In general, such a BO
When using G, BOG after finishing the last stage
The temperature and pressure conditions required for the operation are uniquely determined. Therefore, the compression state in each compression stage including the heat exchange system is determined such that the temperature and pressure are at the stage after the final stage of compression is completed. In, even if a relatively low temperature state was obtained,
Performing continuous multi-stage compression may require more power than necessary, or the temperature may be too high in the final stage, requiring an intercooler or aftercooler. Therefore, in the configuration of the present invention, the BOG in the middle stage is
While adjusting the flow rate of LNG in a lower temperature state than OG,
Mix via LNG mixing line. In this case, LNG
Is adjusted. Therefore, the power required in the compression stage after the mixing section, the temperature and pressure after compression,
It can be adjusted according to this mixing flow rate. As a result, in the multi-stage compression process, the power required for compression can be reduced as much as possible, or the gas state obtained through the final stage can be matched to the subsequent use state of BOG (for example, natural gas after vaporization in that state). (So that it can merge with the gas). As a result, the BOG gas can be used efficiently and effectively.

【0006】さて、上記の目的を達成することができる
天然ガスの製造設備としては、以下の形態を採ることが
好ましい。即ち、液化天然ガスを貯蔵する貯蔵設備を備
え、この貯蔵設備より供給される液化天然ガスを、昇
温、昇圧して、第2温度、大気圧より高い第2圧力にあ
る天然ガスを得る天然ガス供給ラインを備えるととも
に、液化天然ガスから発生するボイルオフガスを、圧縮
機により多段圧縮して、第1温度、大気圧より高い第1
圧力の昇圧ボイルオフガスを得るボイルオフガス処理ラ
インを備え、得られた昇圧ボイルオフガスを、第2温
度、圧力の天然ガスに合流して、ボイルオフガスを利用
する天然ガスの製造設備に以下の構成を追加する。ボイ
ルオフガス処理ラインに於ける多段圧縮中間段にあるボ
イルオフガスに、液化天然ガスを流量調節しながら混合
できるLNG混合ラインを天然ガス供給ラインから分岐
させて備えるのである。この設備においては、LNG混
合ラインを備える場合に、これが、天然ガス供給ライン
からLNGの供給を受け、受けたLNGをボイルオフガ
ス処理ラインに備わる多段圧縮の中間圧縮段に流量調節
しながら供給するものとする。従って、ボイルオフガス
処理ラインに関しては、先にボイルオフガスの処理設備
に関する項で説明した作用・効果を得ることができる。
さらに、この構成は、図4に示すような従来構成の天然
ガス製造プラントにおいて、所定部位に、流量調節弁等
を備えたLNG混合ラインを設けるだけで、構築でき
る。結果、従来プラントの改造等により、効率的で有用
な設備を得ることができる。
[0006] As a natural gas production facility capable of achieving the above object, the following form is preferably adopted. That is, a natural gas is provided which has a storage facility for storing liquefied natural gas and which raises and raises the temperature of the liquefied natural gas supplied from the storage facility to obtain a natural gas at a second temperature and a second pressure higher than the atmospheric pressure. A gas supply line is provided, and boil-off gas generated from liquefied natural gas is compressed in multiple stages by a compressor to a first temperature higher than the first temperature and an atmospheric pressure.
A boil-off gas processing line for obtaining a pressurized boil-off gas is provided. The obtained pressurized boil-off gas is combined with a natural gas at a second temperature and a pressure, and the following configuration is applied to a natural gas production facility using the boil-off gas. to add. An LNG mixing line, which can mix liquefied natural gas with the boil-off gas in the middle stage of the multi-stage compression in the boil-off gas treatment line while adjusting the flow rate, is provided by branching off from the natural gas supply line. In this equipment, when an LNG mixing line is provided, this receives LNG from a natural gas supply line and supplies the received LNG to the intermediate compression stage of the multistage compression provided in the boil-off gas treatment line while adjusting the flow rate. And Therefore, with respect to the boil-off gas processing line, the operation and effect described above in the section relating to the boil-off gas processing equipment can be obtained.
Further, this configuration can be constructed only by providing an LNG mixing line provided with a flow control valve or the like at a predetermined position in a conventional natural gas production plant as shown in FIG. As a result, efficient and useful equipment can be obtained by remodeling a conventional plant or the like.

【0007】さてここで、多段圧縮に於ける初段圧縮を
除く、複数の圧縮段それぞれの中間部位に、前記LNG
混合ラインを各別に設けることが好ましい。このように
する場合は、各圧縮段に於けるBOGの圧縮状態を、圧
縮機の運転条件のみならず、各別に供給される液化天然
ガスの温度、圧力、流量等の条件から設定できるように
なり、さらに、制御できるようになる。結果、各圧縮段
に於ける圧縮を、細かく調整して設備全体の運転設定
上、好適なものとすることができる。このような設備系
を構築する場合にあっては、後にも、本願の有利な点と
して説明するように、インタークーラ(又はヒータ)、
アフタークーラ(又はヒータ)を一切必要としない設備
を構築することもできる。(効果の差はあるが、このよ
うな熱交換系を必要としない設備系の構築は、必ずしも
各圧縮段にLNG混合ラインを備えることをしない場合
にあっても可能である。)
Here, the LNG is provided at an intermediate portion of each of a plurality of compression stages except for the first stage compression in the multistage compression.
It is preferred to provide separate mixing lines. In this case, the compression state of the BOG in each compression stage can be set not only from the operating conditions of the compressor but also from the conditions such as the temperature, pressure, and flow rate of the liquefied natural gas supplied separately. And more control. As a result, the compression in each compression stage can be finely adjusted to make it suitable for the operation setting of the entire equipment. In the case of constructing such an equipment system, an intercooler (or heater),
A facility that does not require any aftercooler (or heater) can be constructed. (Although there is a difference in the effects, it is possible to construct a facility system that does not require such a heat exchange system even when each compression stage is not necessarily provided with the LNG mixing line.)

【0008】さて、LNG混合ラインに、LPG混合ラ
インが合流されていることが好ましいが、この場合、本
管側の天然ガス供給ラインから得られる天然ガスの発熱
量調整のみならず、BOG側の発熱量調整をも良好にお
こなうことができる。
The LPG mixing line is preferably joined to the LNG mixing line. In this case, not only is the calorific value of the natural gas obtained from the natural gas supply line on the main pipe side adjusted, but also the BOG side. The calorific value can be well adjusted.

【0009】さて、先に説明したボイルオフガスの処理
設備にあっては、以下のような処理方法を採用するもの
となっている。即ち、液化天然ガスから発生するボイル
オフガスを、圧縮機により多段圧縮して、第1温度、大
気圧より高い第1圧力の昇圧ボイルオフガスを得る場合
に、この多段圧縮の中間段にあるボイルオフガスに、液
化天然ガスを流量調節しながら混合して、昇圧ボイルオ
フガスを得ることとなっている。
In the boil-off gas processing equipment described above, the following processing method is adopted. That is, when a boil-off gas generated from liquefied natural gas is multi-stage compressed by a compressor to obtain a boosted boil-off gas having a first temperature and a first pressure higher than the atmospheric pressure, a boil-off gas in an intermediate stage of the multi-stage compression is obtained. Then, the liquefied natural gas is mixed while adjusting the flow rate to obtain a pressurized boil-off gas.

【0010】一方、先に説明した天然ガスの製造設備に
あっては、液化天然ガスを貯蔵する貯蔵設備を備え、前
記貯蔵設備より供給される液化天然ガスを、昇温、昇圧
して、第2温度、大気圧より高い第2圧力にある天然ガ
スを得る天然ガス供給ラインを備えるとともに、液化天
然ガスから発生するボイルオフガスを、圧縮機により多
段圧縮して、第1温度で、大気圧より高い第1圧力の昇
圧ボイルオフガスを得るボイルオフガス処理ラインを備
え、前記昇圧ボイルオフガスを、前記第2温度、圧力の
天然ガスに合流する天然ガスの製造する場合にあって、
前記ボイルオフガス処理ラインの多段圧縮中間段に、液
化天然ガスを、前記天然ガス供給ラインより分岐して、
液化天然ガスを流量調節しながら混合するものとなって
いる。
On the other hand, the natural gas production facility described above is provided with a storage facility for storing liquefied natural gas, and the liquefied natural gas supplied from the storage facility is heated and pressurized. A natural gas supply line for obtaining a natural gas at a second temperature higher than the atmospheric pressure at a second temperature, and boil-off gas generated from the liquefied natural gas is compressed in multiple stages by a compressor to obtain a natural gas at a first temperature higher than the atmospheric pressure. A boil-off gas processing line for obtaining a high pressure boil-off gas having a high first pressure, wherein the pressure boil-off gas is produced at the second temperature, where natural gas is combined with the natural gas having a pressure,
Liquefied natural gas is branched from the natural gas supply line to a multistage compression intermediate stage of the boil-off gas processing line,
Liquefied natural gas is mixed while adjusting the flow rate.

【0011】さて、ボイルオフガスの利用にあたって
は、これが熱量的に充分でないため、石油ガスを添加し
て、所謂、増熱をおこなう場合がある。このように、増
熱を行おうとする場合、従来、LPGの気化機構(これ
は、少なくともLPG気化用の気化器を備える)を設
け、この機構により得られた石油ガスをボイルオフガス
に混合するものとしていた。このような機構を必要とし
た理由は、LPGがボイルオフガス内で液滴として残留
しやすく、混合を均一にし難いためである。しかしなが
ら、このような気化機構は、設備費、運転費の点で、好
ましくない。当然、このように増熱をおこなう場合にあ
っても、ボイルオフガスの多段圧縮を伴った昇圧、昇温
は必要である。従って、このように、液化天然ガスから
発生するボイルオフガスを、圧縮機により多段圧縮する
とともに、液化石油ガスを混合して、第1温度、大気圧
より高い第1圧力の状態にあり、発熱量が高められた昇
圧増熱ボイルオフガスを得る場合にあっては、液化石油
ガスを液化天然ガスに混合して増熱混合物を得た後、こ
の増熱混合物を、多段圧縮の初段もしくは中間段にある
ボイルオフガスに混合して、昇圧され、増熱された状態
にあるボイルオフガスを得ることが好ましい。この手法
を採用する場合は、一旦、液化石油ガスを液化天然ガス
に混合し、この混合により得られる混合物を、多段圧縮
の初段もしくは中間段にあるボイルオフガスに混合する
こととなり、結果的に、圧縮工程において、高い均質な
混合状態を実現でき、良好な昇圧、増熱された状態にあ
るボイルオフガスを得ることができる。
Now, when using the boil-off gas, since it is not sufficient in terms of calorific value, a so-called heat increase may be performed by adding petroleum gas. As described above, when the heat is to be increased, a conventional LPG vaporization mechanism (which includes at least a vaporizer for LPG vaporization) is provided, and the oil gas obtained by this mechanism is mixed with the boil-off gas. And had The reason for requiring such a mechanism is that LPG tends to remain as droplets in the boil-off gas, and it is difficult to make the mixing uniform. However, such a vaporization mechanism is not preferable in terms of equipment costs and operation costs. Naturally, even when the heat is increased in this way, it is necessary to increase the pressure and the temperature with the multi-stage compression of the boil-off gas. Accordingly, the boil-off gas generated from the liquefied natural gas is compressed in a multistage by the compressor, and the liquefied petroleum gas is mixed to be in the state of the first temperature and the first pressure higher than the atmospheric pressure. In the case of obtaining a pressurized heat-up boil-off gas with an increased pressure, the liquefied petroleum gas is mixed with liquefied natural gas to obtain a heat-up mixture, and this heat-up mixture is used in the first or intermediate stage of multistage compression. It is preferable to obtain a boil-off gas which is mixed with a certain boil-off gas to be pressurized and heated. When this method is adopted, the liquefied petroleum gas is once mixed with the liquefied natural gas, and the mixture obtained by this mixing is mixed with the boil-off gas at the first stage or the middle stage of the multistage compression. In the compression step, a highly homogeneous mixed state can be realized, and a boil-off gas in a good pressurized and heated state can be obtained.

【0012】従って、本願のような構成を採用すること
により、以下のような効果を得られるようになった。 1.ボイルオフガスの圧縮に要する動力を低減すること
ができる。 2.動力の低減化の程度が低い場合にあっても、インタ
ークーラ等の熱交換用の設備を省略できるので、設備費
を低減できる。 3.さらに、ボイリングガスの熱量調整を、少ない設
備、動力でおこなうことが可能となる。
Therefore, the following effects can be obtained by adopting the configuration as in the present application. 1. The power required for compressing the boil-off gas can be reduced. 2. Even when the degree of reduction in power is low, equipment for heat exchange such as an intercooler can be omitted, so that equipment costs can be reduced. 3. Further, the calorific value of the boiling gas can be adjusted with less equipment and power.

【0013】[0013]

【発明の実施の形態】以下、LNG取り扱い基地に設置
された本願発明に係わる天然ガスの製造設備に関して、
図面に基づいて説明する。図1に示すように、ガス原料
であるLNG3は0.05kg/cm2G、−162℃
で、貯蔵設備であるLNGタンク1に貯蔵されている。
LNGは需要に応じてLNGポンプ4の動力によりLN
G配管6を介して払い出されLNG気化器7で海水を熱
源として気化される。気化されたガスは圧力調整弁9に
よって必要な圧力に制御される。このようにして、本願
にいう第2温度圧力の天然ガスが得られる。このライン
が、本願にいう天然ガス供給ラインL−LNGであり、
ガスが都市ガス用として使用される場合はこの後、図示
していない熱量調整装置により熱量調整され、付臭装置
により付臭され需要先に送られる。
BEST MODE FOR CARRYING OUT THE INVENTION A natural gas production facility according to the present invention installed at an LNG handling base will be described below.
This will be described with reference to the drawings. As shown in FIG. 1, LNG3, which is a gas source, is 0.05 kg / cm 2 G at -162 ° C.
And stored in the LNG tank 1 which is a storage facility.
LNG is driven by the power of the LNG pump 4 according to demand.
Discharged through the G pipe 6 and vaporized by the LNG vaporizer 7 using seawater as a heat source. The vaporized gas is controlled to a required pressure by the pressure regulating valve 9. Thus, the natural gas of the second temperature and pressure referred to in the present application is obtained. This line is the natural gas supply line L-LNG referred to in the present application,
When the gas is used for city gas, the calorific value is adjusted by a calorie adjusting device (not shown), and the gas is then odorized by an odorizing device and sent to a demand destination.

【0014】LNGタンク1の周囲には図示していない
保冷材が施工されており大気からの入熱を防いでいる。
しかしながら、完全に入熱を防止することはできず、8
0,000kLのLNGタンク1基で約2t/hのBO
G2が発生する。また、基地内のLNG配管6の中のL
NGからもBOGは発生し配管を通してLNGタンク1
に集まるような構成となっている。タンク上部に溜まっ
たBOG2は自らの圧力によりBOG配管5を介して本
願のボイルオフガス処理設備8に導かれる。このボイル
オフガス処理設備8は、第1段圧縮機81、第2段圧縮
機82、第3段圧縮機83、インタークーラー84、ア
フタークーラー85、LNG混合ラインL−mixとし
てのLNG供給配管86、LNG流量調整弁(FCV)
87、BOG/LNG混合ノズル88を備えている。こ
のボイルオフガス処理設備8を経るラインが、本願にい
うボイルオフガス処理ラインである。このようにして、
本願にいう第1温度、圧力の天然ガスが得られる。ここ
で、インタークーラー84及びアフタークーラー85は
BOGが圧縮され温度が大気温度を大きく超えるため、
海水を冷媒として冷却するために設けられている。図1
に示す例にあっては、LNG混合ラインは、インターク
ーラ84の下手側、第3段圧縮機83の上手側で、合流
が起こるように配設されている。a〜iは位置を示す符
号であり、これらの位置にあるガスの状態を説明する場
合に使用する。
A cooling material (not shown) is provided around the LNG tank 1 to prevent heat input from the atmosphere.
However, heat input cannot be completely prevented, and 8
Approximately 2t / h BO with one 000kL LNG tank
G2 occurs. In addition, L in the LNG pipe 6 in the base
BOG is also generated from NG and LNG tank 1
It is structured to gather in. The BOG 2 accumulated in the upper part of the tank is guided to the boil-off gas processing equipment 8 of the present invention through the BOG pipe 5 by its own pressure. The boil-off gas treatment equipment 8 includes a first-stage compressor 81, a second-stage compressor 82, a third-stage compressor 83, an intercooler 84, an aftercooler 85, an LNG supply pipe 86 as an LNG mixing line L-mix, an LNG Flow control valve (FCV)
87, a BOG / LNG mixing nozzle 88 is provided. The line passing through the boil-off gas processing equipment 8 is the boil-off gas processing line referred to in the present application. In this way,
Natural gas at the first temperature and pressure referred to in the present application is obtained. Here, the intercooler 84 and the aftercooler 85 compress the BOG and the temperature greatly exceeds the atmospheric temperature.
It is provided for cooling seawater as a refrigerant. FIG.
In the example shown in FIG. 7, the LNG mixing line is disposed on the lower side of the intercooler 84 and on the upper side of the third-stage compressor 83 so as to be merged. Symbols a to i denote positions, which are used to describe the state of gas at these positions.

【0015】設備の作動状況に関して説明すると、LN
G配管6内のLNGの圧力は第2段圧縮機82で圧縮さ
れたBOGの圧力より高いので前記混合ノズル88で容
易に混合することができる。BOGにLNGを混合すれ
ば第3段圧縮機83で圧縮すべき質量流量は増えるが吸
入温度は下がる。一般に、質量流量が増えると圧縮機の
必要負荷は増えるが、吸入温度が下がれば圧縮機の必要
負荷は下がる。従って、混入するLNG流量を適度に調
整すれば圧縮機(図1に示す例の場合は、第3段圧縮機
83)に必要な負荷は削減することができる。図1に記
したa点〜i点の流量/圧力/温度の値を表1に示す。
基地全体で発生し、処理すべきBOGは15t/hであ
る。
The operation of the equipment will be described.
Since the pressure of LNG in the G pipe 6 is higher than the pressure of BOG compressed by the second-stage compressor 82, the mixing can be easily performed by the mixing nozzle 88. If LNG is mixed with BOG, the mass flow rate to be compressed by the third-stage compressor 83 increases, but the suction temperature decreases. Generally, as the mass flow rate increases, the required load on the compressor increases, but as the suction temperature decreases, the required load on the compressor decreases. Therefore, the load required for the compressor (the third stage compressor 83 in the example shown in FIG. 1) can be reduced by appropriately adjusting the flow rate of the mixed LNG. Table 1 shows values of flow rate / pressure / temperature at points a to i shown in FIG.
The BOG generated and processed in the entire base is 15 t / h.

【0016】[0016]

【表1】 [Table 1]

【0017】ケース1ではLNGの流入量を0t/hと
した、即ち、LNGを混入しない従来の方法に対応する
ものであり、図4に示す天然ガス製造設備の構成に対応
するものである。この場合、圧縮機に必要な負荷の合計
は2441kWとなる。一方、15t/hのBOGに対
して第2段圧縮機出側に7t/hのLNGを混入させる
ケース2では、第3段圧縮機入口側の温度が23℃から
−91℃まで下がり第3段圧縮機83の必要負荷は20
1kW減り、多段圧縮に必要な負荷の合計も201kW
減ることになる。第3段圧縮機出側のBOGの温度は−
30℃であり、このケースではアフタークーラー85は
昇温器として17℃まで加温することになる。またこの
構成にあって、第3段圧縮機側の−30℃のBOGでf
点でBOGを予冷すれば、もっと少ないLNGの混合量
で同等の圧縮機負荷の低減を図ることができる。従っ
て、本願技術を採用することで、このようにして少ない
動力で効率的にガスの圧縮を行うボイルオフガス処理設
備8の提供が可能となる。この場合、LNG混合ライン
L−mix(86)を経てBOG側に混入するLNGの
量は、g点の温度を測定しながら目標温度に近づける制
御を行う。また、LNG及びBOGの温度が安定してい
る場合は両者の比率を一定にするような制御とすること
もできる。
Case 1 corresponds to the conventional method in which the inflow of LNG is set to 0 t / h, that is, the conventional method in which LNG is not mixed, and corresponds to the configuration of the natural gas production facility shown in FIG. In this case, the total load required for the compressor is 2441 kW. On the other hand, in case 2 in which 7 t / h LNG is mixed into the output side of the second stage compressor with respect to BOG of 15 t / h, the temperature at the inlet side of the third stage compressor decreases from 23 ° C. to −91 ° C. The required load of the stage compressor 83 is 20
1kW reduction, total load required for multi-stage compression is also 201kW
Will be reduced. The temperature of the BOG at the outlet of the third stage compressor is-
30 ° C., and in this case, the aftercooler 85 is heated to 17 ° C. as a heater. Further, in this configuration, the BOG at −30 ° C. on the third stage compressor side is f
If the BOG is precooled at this point, the compressor load can be reduced by the same amount with a smaller amount of LNG. Therefore, by adopting the technology of the present application, it becomes possible to provide the boil-off gas treatment equipment 8 that efficiently compresses gas with a small amount of power in this manner. In this case, the amount of LNG mixed on the BOG side via the LNG mixing line L-mix (86) is controlled to approach the target temperature while measuring the temperature at point g. Further, when the temperatures of LNG and BOG are stable, control may be performed so that the ratio between the two is constant.

【0018】図1の構成に対してインタークーラー84
を設置せずに、LNGをBOGに混入することにより直
接冷やすことも可能である。この場合は前記インターク
ーラー84の設置費用の削減が可能となる。インターク
ーラー省略の仮定の下、LNGの混入量を前述のケース
2と同じとすると(この例を先に示した表1にケース2
−1として記載した)、第3段圧縮機の負荷は735k
Wになるが、これでもLNGの混入のないケース1に比
べて78kWの削減になる。
The intercooler 84 shown in FIG.
It is also possible to cool directly by mixing LNG into BOG without installing the BOG. In this case, the installation cost of the intercooler 84 can be reduced. Under the assumption that the intercooler is omitted, the amount of LNG mixed is assumed to be the same as in the case 2 described above.
-1), the load of the third stage compressor is 735 k
W, but this also results in a reduction of 78 kW compared to Case 1 with no LNG contamination.

【0019】図2は、都市ガス用のLNG取り扱い基地
に設置された本願の天然ガス製造設備に於ける別の実施
形態を示したものである。図面を一見して判明するよう
に、先に説明したLNG混合ラインL−mix86に、
LPGの混合ラインL−LPG104が合流する構成と
されている。同図において、1〜8及び81〜88は図
1に示したものと同じである。101はLPGタンクで
あり、内部に蓄えられたLPG102は必要に応じてL
PGポンプ103でLPG配管104を介して、本願の
ボイルオフガス処理設備8に送られる。この時i点の発
熱量を一定に保つようにLPG流量調節弁89でLPG
流量を制御し、LNG/LPG混合ノズル90でLNG
と混合される。この後LPGとLNGの混合物はBOG
/LNG混合ノズル88でBOGと混合される。BOG
及びLNGに対して高沸点の割合が多くなるにつれ、混
合しにくくなり液滴が発生しやすくなる。本構成では、
混合した直後に第3段圧縮機83に吸い込まれ、圧縮さ
れBOGの温度が上昇する。従って、混合直後に液滴が
発生した場合でも第3段圧縮機83の中でガスとして均
一に混ざり合うことができる。
FIG. 2 shows another embodiment of the natural gas production facility of the present invention installed at an LNG handling base for city gas. As can be seen at a glance from the drawing, the LNG mixing line L-mix
The LPG mixing line L-LPG 104 is configured to join. In this figure, 1 to 8 and 81 to 88 are the same as those shown in FIG. Reference numeral 101 denotes an LPG tank, and the LPG 102 stored inside the LPG tank
The PG is sent to the boil-off gas treatment facility 8 of the present invention via the LPG pipe 104 by the PG pump 103. At this time, the LPG flow control valve 89 controls the LPG so that the heat value at the point i is kept constant.
The flow rate is controlled and the LNG / LPG mixing nozzle 90
Mixed with. After this, the mixture of LPG and LNG is BOG
/ LNG is mixed with BOG by the mixing nozzle 88. BOG
As the proportion of the high boiling point with respect to LNG and LNG increases, mixing becomes difficult and droplets tend to be generated. In this configuration,
Immediately after mixing, it is sucked into the third-stage compressor 83, compressed, and the temperature of the BOG increases. Therefore, even when droplets are generated immediately after mixing, they can be uniformly mixed as gas in the third stage compressor 83.

【0020】図3は、都市ガス用のLNG取り扱い基地
に設置された本願の天然ガス製造設備に於ける別の実施
形態を示したものである。図1の構成と比較すると、イ
ンタークーラ、アフタークーラを備えることなく、第2
段圧縮機82及び第3段圧縮機83の上流側に、各別に
LNG混合ラインL−mixが設けられていることに特
徴がある。各ラインを流れるガスの流量(単位t/
h)、圧力(kg/cm2 G)/温度(℃)を所要部位
に付いて、図面上に示した。この構成は、図4に示す構
成と対照が可能である。この系に於ける圧縮機の運転負
荷は、第1〜第3の順に813kW、735kW、73
5kWとなり、合計で、2283kWとなる。結果、図
4に示す従来例のものと比較して、158kWの動力低
減を図ることができる。さらに、この例にあっては、イ
ンタークーラ、アフタークーラを備える必要がないた
め、その設備コスト、運転コストを低減することができ
る。この効果は、非常に大きい。
FIG. 3 shows another embodiment of the natural gas production facility of the present invention installed at an LNG handling base for city gas. Compared to the configuration of FIG. 1, the second cooler does not include an intercooler and an aftercooler.
It is characterized in that an LNG mixing line L-mix is separately provided upstream of the stage compressor 82 and the third stage compressor 83. Flow rate of gas flowing through each line (unit: t /
h), pressure (kg / cm 2 G) / temperature (° C.) are shown on the drawings with reference to required parts. This configuration can be contrasted with the configuration shown in FIG. The operating load of the compressor in this system is 813 kW, 735 kW, 73
5 kW, for a total of 2283 kW. As a result, a power reduction of 158 kW can be achieved as compared with the conventional example shown in FIG. Further, in this example, since it is not necessary to provide an intercooler and an aftercooler, it is possible to reduce equipment costs and operation costs. This effect is very large.

【0021】さて、これまで説明してきた例にあって
は、昇温、昇圧後の天然ガスの圧力状態として、現行の
37kg/cm2 Gのものに関して説明してきた。しか
しながら、気化した天然ガスを遠距離の消費地に輸送す
る場合には、天然ガスの圧力を更に高める必要がある。
この場合の例として、天然ガスの圧力を72kg/cm
2 G程度まで上昇させる試みが、今日なされている。こ
の場合、図7にしめすように、圧縮機は、図4のものを
ベースとして考えると、もう1段余分に必要となる。さ
らに、同図からも明らかなように、この例の場合は、イ
ンタークーラICが2機、アフタークーラACが1機必
要である。この図にあっても、各ラインを流れるガスの
流量(単位t/h)、圧力(kg/cm2 G)/温度
(℃)を所要部位に付いて、図面上に示した。この例の
場合は、圧縮機の運転負荷は、第1〜第4の順に756
kW、755kW、755kW、755kWとなり、合
計で、3021kWとなる。
In the examples described so far, the current state of 37 kg / cm 2 G as the natural gas pressure state after the temperature rise and pressure rise has been described. However, when transporting vaporized natural gas to a distant consumption area, it is necessary to further increase the pressure of the natural gas.
In this case, as an example, the pressure of natural gas is set to 72 kg / cm.
Attempts to raise up to about 2 G have been made today. In this case, as shown in FIG. 7, when the compressor shown in FIG. 4 is used as a base, another extra compressor is required. Further, as is apparent from FIG. 5, in this example, two intercooler ICs and one aftercooler AC are required. Also in this figure, the flow rate (unit: t / h), pressure (kg / cm 2 G) / temperature (° C.) of the gas flowing through each line are shown on the drawing with the required parts. In the case of this example, the operating load of the compressor is 756 in the first to fourth order.
kW, 755 kW, 755 kW, 755 kW, which is 3021 kW in total.

【0022】さて、比較のために、図7に示す構成に対
する本願の構成の例を図5、6にしめした。図5は、図
1に対応した例であり、複数のLNG混合ラインL−m
ixとアフターヒータAHを備えた構成とされる。一
方、図6は、図3に対応した例であり、インタークーラ
IC、アフターヒータAH(これらは所謂熱交換器であ
る)を削除した例である。これらの例に於ける必要動力
比較をおこなうと、図5に示す例にあっては、第1〜第
4の順に756kW、633kW、562kW、510
kWとなり、合計で、2491kWとなり、LNG混合
ラインL−mixを備えない例に対して、530kWの
動力削減と、インタークーラーICの削減が可能とな
る。一方、図6に示す例にあっては、第1〜第4の順に
756kW、663kW、618kW、732kWとな
り、合計で、2769kWとなり、LNG混合ラインL
−mixを備えない例に対して、252kWの動力削減
と、インタークーラーIC等の熱交換器が無しで済む。
For comparison, FIGS. 5 and 6 show examples of the configuration of the present invention with respect to the configuration shown in FIG. FIG. 5 is an example corresponding to FIG. 1 and shows a plurality of LNG mixing lines L-m.
ix and the afterheater AH. On the other hand, FIG. 6 is an example corresponding to FIG. 3, in which the intercooler IC and the afterheater AH (these are so-called heat exchangers) are deleted. Comparing the required power in these examples, in the example shown in FIG. 5, 756 kW, 633 kW, 562 kW, 510 kW
kW, which is 2491 kW in total, which makes it possible to reduce the power by 530 kW and reduce the number of intercooler ICs, as compared with an example without the LNG mixing line L-mix. On the other hand, in the example shown in FIG. 6, 756 kW, 663 kW, 618 kW, and 732 kW are obtained in the first to fourth order, and the total is 2769 kW.
As compared with the example without the -mix, the power consumption is reduced by 252 kW and the heat exchanger such as the intercooler IC is not required.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本願の天然ガス製造設備の構成例を示す図FIG. 1 is a diagram showing a configuration example of a natural gas production facility of the present application.

【図2】LPGの混合系を備えた本願の天然ガス製造設
備の構成例を示す図
FIG. 2 is a diagram showing a configuration example of a natural gas production facility of the present application provided with a mixed system of LPG.

【図3】熱交換器を排除した本願の天然ガス製造設備の
構成例を示す図
FIG. 3 is a diagram showing a configuration example of a natural gas production facility of the present invention without a heat exchanger.

【図4】従来の天然ガス製造設備の構成例を示す図FIG. 4 is a diagram showing a configuration example of a conventional natural gas production facility.

【図5】本願の天然ガス製造設備の構成例を示す図FIG. 5 is a diagram showing a configuration example of a natural gas production facility of the present application.

【図6】熱交換器を排除した本願の天然ガス製造設備の
構成例を示す図
FIG. 6 is a diagram showing a configuration example of a natural gas production facility of the present application from which a heat exchanger is eliminated.

【図7】従来の天然ガス製造設備の構成例を示す図FIG. 7 is a diagram showing a configuration example of a conventional natural gas production facility.

【符号の説明】[Explanation of symbols]

1 LNGタンク(貯蔵設備) 8 ボイルオフガス処理設備 81 第1段圧縮機 82 第2段圧縮機 83 第3段圧縮機 84 インタークーラ 85 アフタークーラ L−LNG 天然ガス供給ライン L−BOG ボイルオフガス処理ライン L−LPG LPG混合ライン L−mix LNG混合ライン DESCRIPTION OF SYMBOLS 1 LNG tank (storage equipment) 8 Boil-off gas processing equipment 81 1st stage compressor 82 2nd stage compressor 83 3rd stage compressor 84 Intercooler 85 Aftercooler L-LNG Natural gas supply line L-BOG boil-off gas treatment line L-LPG LPG mixing line L-mix LNG mixing line

Claims (7)

【特許請求の範囲】[Claims] 【請求項1】 液化天然ガスから発生するボイルオフガ
スを、圧縮機により多段圧縮して、第1温度、大気圧よ
り高い第1圧力の昇圧ボイルオフガスを得るボイルオフ
ガスの処理設備であって、 前記多段圧縮の中間段にあるボイルオフガスラインに、
液化天然ガスを流量調節しながら混合できるLNG混合
ラインを備えたボイルオフガスの処理設備。
1. A boil-off gas treatment facility, wherein boil-off gas generated from liquefied natural gas is multi-stage compressed by a compressor to obtain a boosted boil-off gas having a first temperature and a first pressure higher than the atmospheric pressure. In the boil-off gas line in the middle stage of multi-stage compression,
A boil-off gas treatment facility equipped with an LNG mixing line that can mix liquefied natural gas while adjusting the flow rate.
【請求項2】 液化天然ガスを貯蔵する貯蔵設備を備
え、 前記貯蔵設備より供給される液化天然ガスを、昇温、昇
圧して、第2温度、大気圧より高い第2圧力の天然ガス
を供給できる天然ガス供給ラインを備えるとともに、 液化天然ガスから発生するボイルオフガスを、圧縮機に
より多段圧縮して、第1温度、大気圧より高い第1圧力
の昇圧ボイルオフガスを得るボイルオフガス処理ライン
を備え、 前記昇圧ボイルオフガスを、前記第2温度、圧力の天然
ガスに合流させる天然ガスの製造設備であって、 前記ボイルオフガス処理ラインに於ける多段圧縮中間段
にあるボイルオフガスに、液化天然ガスを流量調節しな
がら混合できるLNG混合ラインを前記天然ガス供給ラ
インから分岐させて備えた天然ガスの製造設備。
2. A storage facility for storing liquefied natural gas, wherein the liquefied natural gas supplied from the storage facility is heated and pressurized to produce natural gas at a second temperature and a second pressure higher than the atmospheric pressure. A boil-off gas processing line that includes a natural gas supply line that can supply the boil-off gas generated from the liquefied natural gas, and that compresses the boil-off gas from the liquefied natural gas in multiple stages to obtain a boosted boil-off gas at a first temperature and a first pressure higher than the atmospheric pressure. A natural gas production facility for combining the pressurized boil-off gas with the natural gas at the second temperature and pressure, wherein the boil-off gas in a multi-stage compression intermediate stage in the boil-off gas treatment line includes liquefied natural gas. A natural gas production facility comprising an LNG mixing line that can be mixed while controlling the flow rate of the natural gas by branching off the natural gas supply line.
【請求項3】 多段圧縮に於ける初段圧縮を除く、複数
の圧縮段それぞれの中間部位に、前記LNG混合ライン
を各別に設けた請求項2記載の天然ガスの製造設備。
3. The natural gas production facility according to claim 2, wherein the LNG mixing line is separately provided at an intermediate portion of each of the plurality of compression stages except for the first stage compression in the multistage compression.
【請求項4】 前記LNG混合ラインに、液化石油ガス
を合流するLPG混合ラインを備えた請求項2または3
記載の天然ガスの製造設備。
4. An LPG mixing line for combining liquefied petroleum gas with the LNG mixing line.
Natural gas production equipment as described.
【請求項5】 液化天然ガスから発生するボイルオフガ
スを、圧縮機により多段圧縮して、第1温度、大気圧よ
り高い第1圧力の昇圧ボイルオフガスを得るボイルオフ
ガスの処理方法であって、 前記多段圧縮の中間段にあるボイルオフガスに対して、
液化天然ガスを流量調節をしながら混合して、前記昇圧
ボイルオフガスを得るボイルオフガスの処理方法。
5. A method for treating a boil-off gas, wherein a boil-off gas generated from liquefied natural gas is multi-stage compressed by a compressor to obtain a boosted boil-off gas at a first temperature and a first pressure higher than the atmospheric pressure. For boil-off gas in the middle stage of multi-stage compression,
A method for treating a boil-off gas in which liquefied natural gas is mixed while controlling the flow rate to obtain the pressurized boil-off gas.
【請求項6】 液化天然ガスを貯蔵する貯蔵設備を備
え、 前記貯蔵設備より供給される液化天然ガスを、昇温、昇
圧して、第2温度、大気圧より高い第2圧力の天然ガス
を供給できる天然ガス供給ラインを備えるとともに、 液化天然ガスから発生するボイルオフガスを、圧縮機に
より多段圧縮して、第1温度、大気圧より高い第1圧力
の昇圧ボイルオフガスを得るボイルオフガス処理ライン
を備え、 前記昇圧ボイルオフガスを、前記第2温度、圧力の天然
ガスに合流させる天然ガスの製造方法であって、 前記ボイルオフガス処理ラインの多段圧縮中間段に、前
記天然ガス供給ラインより分岐して、液化天然ガスを流
量調節しながら混合する天然ガスの製造方法。
6. A storage facility for storing liquefied natural gas, wherein the liquefied natural gas supplied from the storage facility is heated and pressurized to produce natural gas at a second temperature and a second pressure higher than the atmospheric pressure. A boil-off gas processing line that includes a natural gas supply line that can supply the boil-off gas generated from the liquefied natural gas, and that compresses the boil-off gas from the liquefied natural gas in multiple stages to obtain a boosted boil-off gas at a first temperature and a first pressure higher than the atmospheric pressure. A method for producing natural gas wherein the pressurized boil-off gas is combined with natural gas at the second temperature and pressure, wherein the natural gas supply line branches to a multi-stage compression intermediate stage of the boil-off gas treatment line. And a method for producing natural gas by mixing liquefied natural gas while controlling the flow rate.
【請求項7】 液化天然ガスから発生するボイルオフガ
スを、圧縮機により多段圧縮するとともに、液化石油ガ
スを混合して、第1温度、大気圧より高い第1圧力の状
態にあり、発熱量が高められた昇圧増熱ボイルオフガス
を得るボイルオフガスの処理方法であって、 前記液化石油ガスを液化天然ガスに混合して増熱混合物
を得た後、前記増熱混合物を、前記多段圧縮の初段もし
くは中間段にあるボイルオフガスに混合して、前記昇圧
増熱ボイルオフガスを得るボイルオフガスの処理方法。
7. A boil-off gas generated from liquefied natural gas is compressed in a multistage by a compressor, liquefied petroleum gas is mixed, and the boil-off gas is in a state of a first temperature and a first pressure higher than the atmospheric pressure. A method of treating a boil-off gas to obtain an increased pressure-increased boil-off gas, wherein the liquefied petroleum gas is mixed with liquefied natural gas to obtain a heated mixture, and the heated mixture is subjected to the first stage of the multi-stage compression. Alternatively, a method of treating a boil-off gas, wherein the boil-off gas is mixed with a boil-off gas at an intermediate stage to obtain the boosted boil-off gas.
JP3191397A 1997-02-17 1997-02-17 Disposal facility of boiloff gas and method thereof, manufacturing facility of natural gas and method thereof Pending JPH10227398A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3191397A JPH10227398A (en) 1997-02-17 1997-02-17 Disposal facility of boiloff gas and method thereof, manufacturing facility of natural gas and method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3191397A JPH10227398A (en) 1997-02-17 1997-02-17 Disposal facility of boiloff gas and method thereof, manufacturing facility of natural gas and method thereof

Publications (1)

Publication Number Publication Date
JPH10227398A true JPH10227398A (en) 1998-08-25

Family

ID=12344231

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3191397A Pending JPH10227398A (en) 1997-02-17 1997-02-17 Disposal facility of boiloff gas and method thereof, manufacturing facility of natural gas and method thereof

Country Status (1)

Country Link
JP (1) JPH10227398A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007024311A (en) * 2005-07-11 2007-02-01 Atlas Copco Energas Gmbh Device and method for utilizing gas
JP2007518017A (en) * 2004-01-16 2007-07-05 クライオスター・ソシエテ・パール・アクシオンス・サンプリフィエ compressor
KR100777136B1 (en) 2005-07-19 2007-11-28 신영중공업주식회사 Boil off gas reliquefaction apparatus using line mixer
JP2009079665A (en) * 2007-09-26 2009-04-16 Ihi Corp Liquefied gas storage and re-liquefaction device and its operating method
JP2011517749A (en) * 2008-03-10 2011-06-16 ブルクハルト コンプレッション アーゲー Natural gas fuel supply apparatus and method
JP2011117562A (en) * 2009-12-05 2011-06-16 Jfe Engineering Corp Evaporated gas re-liquefying apparatus
JP2013108623A (en) * 2011-11-17 2013-06-06 Air Products & Chemicals Inc Compressor assembly and method to minimize venting of process gas during startup operation
JP2013155879A (en) * 2013-05-10 2013-08-15 Jfe Engineering Corp Method for reliquefying boil-off gas
US20170067685A1 (en) * 2014-02-24 2017-03-09 Daewoo Shipbuilding & Marine Engineering Co., Ltd. System and method for processing boil-off gas
CN113063086A (en) * 2021-03-17 2021-07-02 上海汇舸环保科技有限公司 Natural gas treatment system for ship engine
CN113357531A (en) * 2021-05-21 2021-09-07 厚普清洁能源股份有限公司 System and method capable of simultaneously filling LNG cold liquid and hot liquid

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007518017A (en) * 2004-01-16 2007-07-05 クライオスター・ソシエテ・パール・アクシオンス・サンプリフィエ compressor
JP2007024311A (en) * 2005-07-11 2007-02-01 Atlas Copco Energas Gmbh Device and method for utilizing gas
JP4677375B2 (en) * 2005-07-11 2011-04-27 アトラス・コプコ・エネルガス・ゲゼルシヤフト・ミト・ベシユレンクテル・ハフツング How to use gas
KR100777136B1 (en) 2005-07-19 2007-11-28 신영중공업주식회사 Boil off gas reliquefaction apparatus using line mixer
JP2009079665A (en) * 2007-09-26 2009-04-16 Ihi Corp Liquefied gas storage and re-liquefaction device and its operating method
US9273675B2 (en) 2008-03-10 2016-03-01 Burckhardt Compression Ag Device and method for preparing liquified natural gas (LNG) fuel
US8821132B2 (en) 2008-03-10 2014-09-02 Burckhardt Compression Ag Device and method for preparing liquefied natural gas (LNG) fuel
KR101527824B1 (en) * 2008-03-10 2015-06-10 부르크하르트 콤프레션 아게 Device and method for preparing liquefied natural gas(lng) fuel
JP2015132382A (en) * 2008-03-10 2015-07-23 ブルクハルト コンプレッション アーゲー Device and method for supplying natural gas fuel
JP2011517749A (en) * 2008-03-10 2011-06-16 ブルクハルト コンプレッション アーゲー Natural gas fuel supply apparatus and method
JP2018091488A (en) * 2008-03-10 2018-06-14 ブルクハルト コンプレッション アーゲー Supply device and method for natural gas fuel
JP2020122579A (en) * 2008-03-10 2020-08-13 ブルクハルト コンプレッション アーゲー Supply device and method for natural gas fuel
JP2011117562A (en) * 2009-12-05 2011-06-16 Jfe Engineering Corp Evaporated gas re-liquefying apparatus
JP2013108623A (en) * 2011-11-17 2013-06-06 Air Products & Chemicals Inc Compressor assembly and method to minimize venting of process gas during startup operation
JP2013155879A (en) * 2013-05-10 2013-08-15 Jfe Engineering Corp Method for reliquefying boil-off gas
US20170067685A1 (en) * 2014-02-24 2017-03-09 Daewoo Shipbuilding & Marine Engineering Co., Ltd. System and method for processing boil-off gas
CN113063086A (en) * 2021-03-17 2021-07-02 上海汇舸环保科技有限公司 Natural gas treatment system for ship engine
CN113357531A (en) * 2021-05-21 2021-09-07 厚普清洁能源股份有限公司 System and method capable of simultaneously filling LNG cold liquid and hot liquid

Similar Documents

Publication Publication Date Title
US10036589B2 (en) Apparatus and method for producing low-temperature compressed gas or liquefied gas
CN100529620C (en) Operating system of liquefied natural gas ship for sub-cooling and liquefying boil-off gas
US8893515B2 (en) Methods and configurations of boil-off gas handling in LNG regasification terminals
JPH10227398A (en) Disposal facility of boiloff gas and method thereof, manufacturing facility of natural gas and method thereof
JPS63302169A (en) Gas supply device for gas fired diesel engine
EP0881444B1 (en) Method and apparatus for control of an integrated cryogenic air separation unit/gas turbine system
JP2007511717A (en) Apparatus and method for boil-off gas temperature control
US20180313603A1 (en) Apparatus and method for producing liquefied gas
JP4347037B2 (en) Fuel supply apparatus for gas-fired internal combustion engine such as gas turbine and LNG ship equipped with the same
JPWO2019188957A1 (en) Natural gas liquefaction device and natural gas liquefaction method
JP2009079665A (en) Liquefied gas storage and re-liquefaction device and its operating method
US20220404094A1 (en) System and m ethod for supplying cryogenic refrigeration
JP7393607B2 (en) Gas liquefaction method and gas liquefaction device
JPH0545050A (en) Method for liquefying permanent gas using cryogenic cold of liquefied natural gas
JP4551548B2 (en) Power generation facility and power generation method using the same
JPH0392700A (en) Boil-off gas processing method of low temperature liquefied gas
JP4240589B2 (en) Method of starting operation of low-temperature gas turbocompressor
JPH11210993A (en) Cryogenic liquid gas storage equipment
JPH11325714A (en) Heat exchange type gas liquefier
EP0855518A2 (en) Process and apparatus for controlling the inlet temperature of an air compressor
JPH0875284A (en) Cryogenic freezing device
JP2008064126A (en) Operating method for boiloff gas delivery facility
JP4134373B2 (en) Cooling equipment for suction header mother pipe of reciprocating compressor for low temperature gas
US11913719B2 (en) Liquefaction apparatus
US20220112083A1 (en) Method to convert excess liquid oxygen into liquid nitrogen