JPH10183642A - Method for constructing structure foundation in viscous soil ground - Google Patents

Method for constructing structure foundation in viscous soil ground

Info

Publication number
JPH10183642A
JPH10183642A JP34844496A JP34844496A JPH10183642A JP H10183642 A JPH10183642 A JP H10183642A JP 34844496 A JP34844496 A JP 34844496A JP 34844496 A JP34844496 A JP 34844496A JP H10183642 A JPH10183642 A JP H10183642A
Authority
JP
Japan
Prior art keywords
soil
ground
pile
capital
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP34844496A
Other languages
Japanese (ja)
Other versions
JP3230448B2 (en
Inventor
Kouki Maeda
耕喜 前田
Haruo Shimomura
治男 下村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP34844496A priority Critical patent/JP3230448B2/en
Publication of JPH10183642A publication Critical patent/JPH10183642A/en
Application granted granted Critical
Publication of JP3230448B2 publication Critical patent/JP3230448B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Foundations (AREA)

Abstract

PROBLEM TO BE SOLVED: To improve construction feasibility by a method wherein after improved soil is banked on a viscous soil ground, a foundation pile is made to penetrate to a load bearing layer, and a floor slab having a floor steel plate forming permanent forms is formed on pile heads. SOLUTION: Improved soil 5 comprising a cement curing material and soil is cured as a bank on a viscous soil ground 1 of a present ground 11 and a given strength is provided. A foundation pile 3 is then driven down to penetrate through an underlying load bearing layer 2 and a capital made of precast reinforced concrete is arranged such that a central hole is fitted in a pile head. Floor steel plates forming permanent forms are laid on a frame assembled on modified soil 5 between the capitals. After reinforcing bars are arranged on the floor plates, floor slab concrete 4 is placed, a gap between a pile 3 and the capital is filled with mortar, and the concrete 4 and the capital are integrally formed by means of reinforcing bars. This method remarkably reduces a banking amount and a viscous soil ground subsidence, and uses piles of property quality, and further improves workability of a flat slab construction method.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は水田跡地などの粘性
土地盤上に建造物を構築する際の基礎の構築方法に関す
るものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a foundation for constructing a building on a viscous ground such as a former rice paddy field.

【0002】[0002]

【従来の技術】水田跡地などの粘性土地盤1を敷地とし
てその上に建造物を構築する際には、建設工事に先立っ
て、現地盤11を埋土13によって計画地盤12まで嵩
上げする地盤造成工事が行われる。粘性土地盤は通常は
正規圧密状態(粘性土の有効応力度が圧密降伏応力度に
等しい状態)であり、その儘の状態では変形は起こさな
いが、その地盤上に埋土13の荷重が載荷され有効応力
度が増加すると粘性土中の水が排出されて変形し圧密に
よる地盤沈下を生じ、現地盤11は14まで沈下する。
(図4参照)。
2. Description of the Related Art When constructing a building on a viscous ground 1 such as a site of a paddy field as a site, prior to the construction work, the ground 11 is raised to a planned ground 12 with a buried land 13. Construction is performed. The cohesive ground is normally in a normal consolidation state (a state in which the effective stress of the cohesive soil is equal to the consolidation yield stress), and the cohesive soil is not deformed as it is, but the load of the embedded soil 13 is loaded on the ground. When the effective stress increases, the water in the viscous soil is discharged and deformed, causing land subsidence due to consolidation.
(See FIG. 4).

【0003】この圧密による地盤沈下対策としては、通
常は大別して次の2つの方法が採られている。
As a countermeasure against land subsidence due to this consolidation, the following two methods are usually adopted.

【0004】(1)時間的余裕のある場合。(1) When there is enough time.

【0005】埋土13の上にさらに大量の盛土15を載
荷してその重量により粘性土地盤1の沈下を促進させ、
十分地盤沈下が進行したと考えられる時点で大量の盛土
15を撤去し、改めて地盤造成工事を行う。(図5参
照)。
[0005] A large amount of embankment 15 is loaded on the buried land 13 to promote the settlement of the viscous ground 1 by its weight,
When it is considered that the subsidence has sufficiently proceeded, a large amount of the embankment 15 is removed, and the ground preparation work is performed again. (See FIG. 5).

【0006】(2)時間的余裕のない場合。(2) When there is not enough time.

【0007】粘性土地盤1による建造物の支持を諦め、
地盤造成工事後、基礎杭3を粘性土地盤1下方の支持層
2まで打ち込み建造物全体を基礎杭3を介して支持層2
で支持し、粘性土地盤1の地盤沈下は起こるのに任せて
おく。(図6参照)
[0007] Give up the support of the building by viscous ground 1,
After the ground preparation work, the foundation pile 3 is driven into the support layer 2 below the viscous ground 1 and the entire building is supported via the foundation pile 3.
And the land subsidence of the viscous ground 1 is left to occur. (See Fig. 6)

【0008】[0008]

【発明が解決しようとする課題】上記(1) の方法では地
盤造成工事の他に、大量の盛土の載荷・撤去の工事が加
わり、工期が長くなり、工事費も増大する。特に大きい
課題は地盤沈下が完了したと判断されるまでに年単位の
長い時間を必要とすることである。
According to the above-mentioned method (1), in addition to the ground preparation work, the work of loading and removing a large amount of embankment is added, so that the construction period becomes longer and the construction cost increases. A particularly big challenge is that it takes a long time per year to determine that land subsidence is complete.

【0009】上記(2) の方法では杭打ち込み後、載荷し
た埋土重量による地盤沈下が起き、その地盤沈下が基礎
杭に対して負の摩擦力として働くのみでなく、杭頭部に
隙間16を生じ基礎杭の支持力を低下させる。このた
め、基礎杭としては支持力の低下を見込んで過大な品質
のものを使用する必要がある。
In the above method (2), after the pile is driven into the ground, land subsidence occurs due to the weight of the loaded soil, and the land subsidence acts not only as a negative frictional force on the foundation pile but also as a gap 16 at the pile head. And lower the bearing capacity of the foundation pile. For this reason, it is necessary to use foundation piles of excessive quality in anticipation of a decrease in bearing capacity.

【0010】[0010]

【課題を解決するための手段】本発明は、上記(2) の時
間的余裕のない場合に適正品質の基礎杭を使用し、か
つ、工事用車輛の運行を容易にして短工期、低工事費で
効率的に基礎を構築する構築方法を提供することを目的
とするものである。
SUMMARY OF THE INVENTION The present invention uses a foundation pile of appropriate quality in the case where there is not enough time in the above (2), and facilitates the operation of a construction vehicle, thereby shortening the construction period and reducing the construction work. It is intended to provide a construction method for efficiently building a foundation at a low cost.

【0011】即ち、本発明は、(A)粘性土地盤上にセ
メント系固化材と土との混合物である改良土を盛土して
粘性土地盤の表層を改良する工程、(B)改良土の固化
後、杭先端が下方の支持層に貫入し、杭頭が改良土層上
方に突出するように基礎杭を打ち込む工程、(C)突出
している基礎杭杭頭にプレキャスト鉄筋コンクリート製
キャピタルを嵌合して設置し、隣接するキャピタル間に
床鋼板を敷設する工程、(D)床鋼板を捨て型枠とし、
その上に鉄筋コンクリートを打設して床スラブを構築す
る工程、よりなることを特徴とする粘性土地盤への建造
物基礎の構築方法である。
That is, the present invention provides (A) a step of embedding improved soil, which is a mixture of a cement-based solidifying material and soil, on a cohesive ground to improve the surface layer of the cohesive ground; After the solidification, the pile tip penetrates into the lower support layer and the foundation pile is driven so that the pile head projects above the improved soil layer. (C) Precast reinforced concrete capital is fitted to the protruding foundation pile pile head. And laying the floor steel sheet between adjacent capitals, (D) the floor steel sheet as a form,
A method for constructing a floor slab by casting reinforced concrete thereon, and a method for constructing a foundation for a building on a viscous ground.

【0012】本発明の第1の要点は、嵩上げのための盛
土としてセメント系固化材と土との混合物である改良土
を使用して粘性土地盤の表層を改良し、その上方の計画
地盤レベルに床スラブをフラットスラブ工法により構築
して、構築された床スラブを計画地盤とする点である。
盛土する改良土の量は、その上を走行する工事用車輛の
運行に支障を及ぼさない範囲でできるだけ少ないのが、
地盤沈下を抑制する面から好ましく、通常は数十cm程度
の厚みに盛土される。従来の嵩上げのための盛土量に比
して大幅に少なく、盛土量は大幅に節減される。
A first point of the present invention is to improve the surface layer of a cohesive ground by using an improved soil which is a mixture of a cement-based solidifying material and soil as an embankment for raising the level, and to improve a planned ground level above the ground. First, the floor slab is constructed by the flat slab method, and the constructed floor slab is used as the planned ground.
The amount of improved soil to be embanked should be as small as possible without impeding the operation of construction vehicles running on it.
It is preferable from the viewpoint of suppressing land subsidence, and is usually embanked to a thickness of about several tens of cm. The amount of embankment is significantly less than the conventional embankment for raising, and the amount of embankment is greatly reduced.

【0013】本発明の第2の要点は、上記フラットスラ
ブ工法において、基礎杭頭のキャピタルとしてプレキャ
スト鉄筋コンクリート製品を使用し、床スラブを構築す
る後打ち鉄筋コンクリートの型枠として床鋼板を捨て型
枠として使用し、作業性良く床スラブと基礎杭とをキャ
ピタルを介して一体化する点である。
A second point of the present invention is that, in the above flat slab method, a precast reinforced concrete product is used as capital for a foundation pile head, and a floor steel plate is discarded as a post-cast reinforced concrete form for constructing a floor slab. The point of use is to integrate the floor slab and the foundation pile via capital with good workability.

【0014】[0014]

【発明の実施の形態】以下、図面を参照しながら本発明
について説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below with reference to the drawings.

【0015】図1は本発明により構築した基礎の1例の
立断面図であり、図2はプレキャスト鉄筋コンクリート
製キャピタルの設置例を示し、(a)は角型キャピタル
の平面図、(b)は角型キャピタルを設置し、床スラブ
コンクリートを打設した状態の立断面図、(c)は丸型
キャピタルの平面図、(d)は丸型キャピタルを設置
し、床スラブコンクリートを打設した状態の立断面図で
あり、図3は床スラブコンクリートの打設時の床鋼板の
配置例を示し(a)は平面図、(b)は(a)のB−B
矢視図、(c)は(b)のC−C矢視図である。
FIG. 1 is an elevational sectional view of one example of a foundation constructed according to the present invention, FIG. 2 shows an example of installation of a precast reinforced concrete capital, (a) is a plan view of a square capital, and (b) is A vertical sectional view of a state in which square capital is installed and floor slab concrete is cast, (c) is a plan view of a round capital, and (d) is a state in which round capital is installed and floor slab concrete is cast. FIG. 3 shows an example of arrangement of floor steel plates at the time of placing floor slab concrete, (a) is a plan view, and (b) is BB of (a).
FIG. 2C is a view as viewed from the direction of the arrow, and FIG.

【0016】図1〜図3を参照しながら本発明の施工手
順について説明する。
The construction procedure of the present invention will be described with reference to FIGS.

【0017】(1)現地盤11の粘性土地盤1の上にセ
メント系固化材と土との混合物である改良土5を数十cm
の厚さに盛土して養生し、改良土5の硬化を待つ。
(1) An improved soil 5 which is a mixture of a cement-based solidifying material and soil is tens of cm on the viscous ground 1 of the local ground 11.
Fill and cure to a thickness of 5mm and wait for the improved soil 5 to harden.

【0018】(2)改良土5が硬化し、所定の強度を発
現すると、その上に工事用車輛を乗り入れることが可能
となり、併せて、次に打ち込む基礎杭3の杭頭部の地盤
剛性が高くなる。改良土5上に工事用車輛を乗り入れ、
基礎杭3をその先端が下方の支持層2に貫入するまで打
ち込む。基礎杭3の杭頭は改良土5の上方に数十cm程度
突出させておく。
(2) When the improved soil 5 hardens and develops a predetermined strength, it becomes possible for a construction vehicle to ride on it, and at the same time, the ground rigidity of the pile head of the foundation pile 3 to be driven next is reduced. Get higher. A construction vehicle is loaded on the improved soil 5,
The foundation pile 3 is driven in until its tip penetrates into the lower support layer 2. The pile head of the foundation pile 3 is projected about several tens of cm above the improved soil 5.

【0019】(3)基礎杭3の杭頭にプレキャスト鉄筋
コンクリート製キャピタル6の中心の穴を嵌合してプレ
キャスト鉄筋コンクリート製キャピタル6を設置する。
(3) The precast reinforced concrete capital 6 is installed by fitting the center hole of the precast reinforced concrete capital 6 into the pile head of the foundation pile 3.

【0020】(4)キャピタル6間の改良土5の上にL
形鋼9により架台を組立て、その架台の上に捨て型枠と
なる床鋼板8を敷設する。床鋼板8としては通常のデッ
キプレートやキーストンプレートが使用される。
(4) L on the improved soil 5 between the capitals 6
A gantry is assembled from the shape steel 9, and a floor steel plate 8 serving as a disposal form is laid on the gantry. As the floor steel plate 8, a normal deck plate or keystone plate is used.

【0021】(5)床鋼板8の上に床スラブ用の所定の
配筋を行い、床スラブコンクリート4を打設する。基礎
杭3の杭頭とプレキャスト鉄筋コンクリート製キャピタ
ル6の穴との隙間にはコンクリートまたはモルタルを充
填する。床スラブコンクリート4とキャピタル6とはキ
ャピタル6から突出している連結鉄筋7により一体化し
キャピタル6と基礎杭3とは充填したコンクリートまた
はモルタルにより一体化する。床スラブコンクリート4
の硬化を待って粘性土地盤1上への基礎の構築が完了す
る。
(5) Predetermined reinforcement for the floor slab is provided on the floor steel plate 8 and the floor slab concrete 4 is poured. The gap between the pile head of the foundation pile 3 and the hole of the precast reinforced concrete capital 6 is filled with concrete or mortar. The floor slab concrete 4 and the capital 6 are integrated by a connecting reinforcing bar 7 protruding from the capital 6, and the capital 6 and the foundation pile 3 are integrated by the filled concrete or mortar. Floor slab concrete 4
After the hardening of the soil, the construction of the foundation on the viscous ground 1 is completed.

【0022】構築された床スラブコンクリート4の上面
が計画地盤12となり、現地盤11は所定の高さ嵩上げ
されたこととなる。同時に嵩上げ高さに対応した高さの
空間が床スラブコンクリート4の下面と改良土5の上面
との間に形成される。
The upper surface of the constructed floor slab concrete 4 becomes the planned ground 12, and the local ground 11 is raised to a predetermined height. At the same time, a space having a height corresponding to the raised height is formed between the lower surface of the floor slab concrete 4 and the upper surface of the improved soil 5.

【0023】[0023]

【発明の効果】【The invention's effect】

(1)嵩上げのための埋土としてセメント系固化材を混
合した改良土を使用することにより埋土量を大幅に減ら
すことが可能となり、正規圧密状態である粘性土地盤の
地盤沈下を大幅に減らすことができる。この結果、従来
は、地盤沈下の影響を見込んで過剰品質のものを使用せ
ざるを得なかった基礎杭を本来の適正品質のものとする
ことができ、経費が節減される。
(1) It is possible to greatly reduce the amount of buried soil by using improved soil mixed with cement-based solidification material as buried soil for raising the soil, and to significantly reduce the land subsidence of the cohesive ground that is in a normally consolidated state. Can be reduced. As a result, foundation piles, which had to be used in the past and had to use excessive quality in anticipation of the effects of land subsidence, can be replaced with original proper quality piles, and costs can be reduced.

【0024】(2)基礎杭頭のキャピタルとしてプレキ
ャスト鉄筋コンクリート製品を使用し、床スラブを構築
する後打ち鉄筋コンクリートの型枠として床鋼板を捨て
型枠として使用することにより、フラットスラブ工法の
作業性が向上する。
(2) The workability of the flat slab method can be improved by using a precast reinforced concrete product as the capital of the foundation pile head and using the floor steel plate as the formwork of the post-cast reinforced concrete for constructing the floor slab. improves.

【0025】以上を総合して、工期、経費、品質の全て
の面で合理的な基礎が提供される。
In summary, a reasonable basis is provided in all aspects of construction period, cost and quality.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明により構築した基礎の1例の立断面図で
ある。
FIG. 1 is a sectional elevation view of an example of a foundation constructed according to the present invention.

【図2】プレキャスト鉄筋コンクリート製キャピタルの
設置例を示し、(a)は角型キャピタルの平面図、
(b)は角型キャピタルを設置し、床スラブコンクリー
トを打設した状態の立断面図、(c)は丸型キャピタル
の平面図、(d)は丸型キャピタルを設置し、床スラブ
コンクリートを打設した状態の立断面図である。
FIG. 2 shows an example of installation of precast reinforced concrete capital, (a) is a plan view of square capital,
(B) is a vertical sectional view in a state where square capital is installed and floor slab concrete is cast, (c) is a plan view of round capital, and (d) is a round capital is installed and floor slab concrete is installed. It is an elevation sectional view in the state where it was cast.

【図3】床スラブコンクリートの打設時の床鋼板の配置
例を示し、(a)は平面図、(b)は(a)のB−B矢
視図、(c)は(b)のC−C矢視図である。
3A and 3B show an example of the arrangement of floor steel plates at the time of placing floor slab concrete, wherein FIG. 3A is a plan view, FIG. 3B is a view taken along the line BB of FIG. 3A, and FIG. It is a CC arrow view.

【図4】現地盤を埋土によって計画地盤まで嵩上げする
地盤造成工事の概念立断面図である。
FIG. 4 is a conceptual sectional view of a ground preparation work for raising a local ground to a planned ground by burying soil.

【図5】大量の盛土の載荷による圧密促進により地盤を
改良する工法の概念立断面図である。
FIG. 5 is a conceptual elevation sectional view of a method for improving the ground by promoting consolidation by loading a large amount of embankment.

【図6】従来の杭基礎工法の概念立断面図である。FIG. 6 is a conceptual vertical sectional view of a conventional pile foundation method.

【符号の説明】[Explanation of symbols]

1…粘性土地盤、2…支持層、3…基礎杭、4…床スラ
ブコンクリート、5…改良土、6…プレキャスト鉄筋コ
ンクリート製キャピタル、7…連結鉄筋、8…床鋼板、
9…L形鋼、11…現地盤、12…計画地盤、13…埋
土、14…沈下後現地盤、15…盛土、16…杭頭部隙
間。
DESCRIPTION OF SYMBOLS 1 ... viscous ground, 2 ... support layer, 3 ... foundation pile, 4 ... floor slab concrete, 5 ... improved soil, 6 ... precast reinforced concrete capital, 7 ... connecting rebar, 8 ... floor steel plate,
9: L-shaped steel, 11: local soil, 12: planned ground, 13: buried, 14: local soil after sinking, 15: embankment, 16: clearance of pile head.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 (A)粘性土地盤上にセメント系固化材
と土との混合物である改良土を盛土して粘性土地盤の表
層を改良する工程、(B)改良土の固化後、杭先端が下
方の支持層に貫入し、杭頭が改良土層上方に突出するよ
うに基礎杭を打ち込む工程、(C)突出している基礎杭
杭頭にプレキャスト鉄筋コンクリート製キャピタルを嵌
合して設置し、隣接するキャピタル間に床鋼板を敷設す
る工程、(D)床鋼板を捨て型枠とし、その上に鉄筋コ
ンクリートを打設して床スラブを構築する工程、よりな
ることを特徴とする粘性土地盤への建造物基礎の構築方
法。
(A) a step of embedding an improved soil, which is a mixture of a cement-based solidifying material and soil, on a cohesive ground to improve the surface layer of the cohesive ground; and (B) a pile after solidification of the improved soil. Driving the foundation pile so that the tip penetrates the lower support layer and the pile head protrudes above the improved soil layer. (C) Fit the precast reinforced concrete capital to the protruding foundation pile head and install it. A step of laying a floor steel sheet between adjacent capitals, and (D) a step of constructing a floor slab by disposing of the floor steel sheet as a formwork and placing reinforced concrete thereon. How to build a building foundation into a building.
JP34844496A 1996-12-26 1996-12-26 Construction method of building foundation on cohesive ground Expired - Fee Related JP3230448B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP34844496A JP3230448B2 (en) 1996-12-26 1996-12-26 Construction method of building foundation on cohesive ground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP34844496A JP3230448B2 (en) 1996-12-26 1996-12-26 Construction method of building foundation on cohesive ground

Publications (2)

Publication Number Publication Date
JPH10183642A true JPH10183642A (en) 1998-07-14
JP3230448B2 JP3230448B2 (en) 2001-11-19

Family

ID=18397051

Family Applications (1)

Application Number Title Priority Date Filing Date
JP34844496A Expired - Fee Related JP3230448B2 (en) 1996-12-26 1996-12-26 Construction method of building foundation on cohesive ground

Country Status (1)

Country Link
JP (1) JP3230448B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102677661A (en) * 2012-05-07 2012-09-19 中铁上海工程局有限公司 Reinforcement method for foundation of silt soft-based cast-in-place box girder support
ES2489300A1 (en) * 2013-02-19 2014-09-01 Iconkrete 2012, S.L. Prefabricated foundation for structures of solar thermal and photovoltaic plants, and procedure for realization of the foundations (Machine-translation by Google Translate, not legally binding)
JP2016223094A (en) * 2015-05-28 2016-12-28 ジャパンパイル株式会社 Pile head connection device, pile head connection structure, and pile head connection method
CN112030979A (en) * 2020-08-11 2020-12-04 江苏纬信工程咨询有限公司 Construction process for excavating after consolidation of miscellaneous filling

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101476324A (en) * 2009-01-20 2009-07-08 叶长青 Raft plate base and its construction method
CN104233941B (en) * 2014-09-05 2016-04-27 中铁第四勘察设计院集团有限公司 A kind of grooved pile plate composite structure of roadbed on dike

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102677661A (en) * 2012-05-07 2012-09-19 中铁上海工程局有限公司 Reinforcement method for foundation of silt soft-based cast-in-place box girder support
ES2489300A1 (en) * 2013-02-19 2014-09-01 Iconkrete 2012, S.L. Prefabricated foundation for structures of solar thermal and photovoltaic plants, and procedure for realization of the foundations (Machine-translation by Google Translate, not legally binding)
JP2016223094A (en) * 2015-05-28 2016-12-28 ジャパンパイル株式会社 Pile head connection device, pile head connection structure, and pile head connection method
CN112030979A (en) * 2020-08-11 2020-12-04 江苏纬信工程咨询有限公司 Construction process for excavating after consolidation of miscellaneous filling

Also Published As

Publication number Publication date
JP3230448B2 (en) 2001-11-19

Similar Documents

Publication Publication Date Title
US6719492B1 (en) Top arch overfilled system
JP3327191B2 (en) Underground structure and its construction method
JP2002256573A (en) Foundation for existing foundation reinforcing steel tower and construction method for it
US20100325819A1 (en) Bridge approach and abutment construction and method
JP3010356B1 (en) How to build a tunnel
CN110777569A (en) Expansive soil limited deformation anti-upwarp foundation structure and construction method of foundation structure
JP3230448B2 (en) Construction method of building foundation on cohesive ground
JPH0579049A (en) Constructing method for beam and slab in underground body construction work
JP3956226B2 (en) Road construction method and upper construction plate used therefor
JPH0475966B2 (en)
JPH059928A (en) Method for making embankment slope steep
JP3407168B2 (en) Foundation of new building using existing pile foundation
JP3752082B2 (en) Fabric foundation construction method
JP3059058U (en) Solid foundation structure with stabilizer
JP4233025B2 (en) How to construct a three-dimensional intersection
WO2023175836A1 (en) Method for constructing foundation of structure
JPH083463Y2 (en) Basic structure of building
CN218713281U (en) Near-track foundation pit external construction platform
CN114318991B (en) Highway bench back structure in plain area, highway structure and construction method
JP3335593B2 (en) Underground structure construction structure
CN211227880U (en) Expansive soil limited deformation anti-upwarp foundation structure
JPH07138972A (en) Construction method for underground skeleton
JP2896464B2 (en) Concrete body reinforcement laying method
JPH07279184A (en) Floating underground beam foundation for building
JPH07292618A (en) Construction method of temporarily installed bridge

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20010814

LAPS Cancellation because of no payment of annual fees