JPH10121490A - Building structure utilizing pile as pillar - Google Patents

Building structure utilizing pile as pillar

Info

Publication number
JPH10121490A
JPH10121490A JP27511796A JP27511796A JPH10121490A JP H10121490 A JPH10121490 A JP H10121490A JP 27511796 A JP27511796 A JP 27511796A JP 27511796 A JP27511796 A JP 27511796A JP H10121490 A JPH10121490 A JP H10121490A
Authority
JP
Japan
Prior art keywords
ground
pile
building structure
piles
pillar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP27511796A
Other languages
Japanese (ja)
Other versions
JP3006710B2 (en
Inventor
Kiyotoshi Sakamoto
清敏 坂本
Shigekatsu Sawabe
繁克 澤邊
Seiya Shiba
勢也 司馬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP8275117A priority Critical patent/JP3006710B2/en
Publication of JPH10121490A publication Critical patent/JPH10121490A/en
Application granted granted Critical
Publication of JP3006710B2 publication Critical patent/JP3006710B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To cope with deformation of piles during an earthquake by positioning piles with their lower portions in the ground and with their upper portions projected above the ground, and by applying ground improvement treatment to the ground surface layer. SOLUTION: A hole 4 is bored with a boring tool such as an earth auger so that the fore-end of the hole 4 reaches a support layer 3a of a ground in a site 1. Next, a pile 6 is inserted into the hole 4 which is simultaneously filled with cement milk 5. Here, the pile 6 is not inserted to its full length but its upper portion projects above the ground so that its top end reaches up to the ceiling height of a building structure 2 to constitute a pillar 7 of the building structure 2. An improved ground layer 8 is formed by injecting solidification agent from the ground surface into the surface layer 3b of the ground 3. When a ground floor concrete 9 is deposited as a floor slab, a specified gap is provided around the pile 6 to isolate the concrete 9 from the pile 6 and to prevent the pile 6 and the floor slab from being damaged during the earthquake.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は杭をそのまま柱と
して利用した建築構造物に関するものであり、特に、低
層の店舗や倉庫等に適した建築構造物に関するものであ
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a building structure using a stake as a pillar as it is, and more particularly to a building structure suitable for a low-rise store or warehouse.

【0002】[0002]

【従来の技術】従来の此種建築構造物として、地中に打
ち込んだコンクリート杭の地上立上がり部(地表から上
方へ突出した部分、即ち、柱になる部分)に、フラット
スラブ(二階以上の階の床乃至天井)を支持させるとと
もに、基礎(基礎フーチング)を設けないこととした手
段が提案されている(特開平6−81342号)。
2. Description of the Related Art As a conventional building structure of this type, a flat pile (two or more floors) is placed on a rising portion of a concrete pile driven into the ground (a portion projecting upward from the ground surface, that is, a column). (Japanese Patent Application Laid-Open No. Hei 6-81342) has been proposed to support the floor or ceiling of the vehicle and to not provide a foundation (foundation footing).

【0003】[0003]

【発明が解決しようとする課題】上掲の手段によれば基
礎フーチングは不要となるが、杭と杭とを繋ぐ地中梁は
建築構造物の所要強度を確保する上で必要不可欠であ
る。然し乍ら、該地中梁は地盤内に埋設するものである
ので、施工が煩雑で相当の工期を必要とする。これに対
し、地盤の表層を地盤改良等すれば地中梁が無くても此
種建築構造物の所要強度を確保できると考えられるが、
その場合には、杭の地震時変形をより一層考慮する必要
がある。
According to the above-mentioned means, the foundation footing is not required, but the underground beams connecting the piles are indispensable for securing the required strength of the building structure. However, since the underground beam is buried in the ground, the construction is complicated and requires a considerable construction period. On the other hand, if the surface layer of the ground is improved, etc., it is thought that the required strength of this type of building structure can be secured without the underground beam,
In that case, it is necessary to further consider the deformation of the pile during an earthquake.

【0004】そこで、此種建築構造物の所要強度を確保
しつつ、地中梁の有無に拘わらず杭の地震時変形に対処
するために解決すべき技術的課題が生じてくるのであ
り、本発明は該課題を解決することを目的とする。
[0004] Therefore, there is a technical problem to be solved in order to deal with the deformation of the pile during an earthquake regardless of the presence or absence of underground beams, while ensuring the required strength of this type of building structure. The invention aims to solve the problem.

【0005】[0005]

【課題を解決するための手段】本発明は上記課題を解決
するために提案されたものであり、杭の下部を地盤中に
位置させるとともに、該杭の上部を地上に突出させて柱
と成し、場合により、前記地盤の表層を地盤改良した上
で、地表に敷設された床スラブと前記杭とを縁切りした
建築構造物を提供するものである。
SUMMARY OF THE INVENTION The present invention has been proposed to solve the above-mentioned problems, and has a structure in which a lower portion of a pile is located in the ground and an upper portion of the pile is projected above the ground to form a pillar. Further, in some cases, a building structure is provided in which a surface slab of the ground is ground-modified and a floor slab laid on the ground and the pile are cut off.

【0006】[0006]

【発明の実施の形態】以下、本発明の実施の形態を図1
乃至図5に従って詳述する。図1は敷地1に建築構造物
2の骨組を構築した状態を示し、地盤3には掘削孔4,
4…がアースオーガ等の掘削具にて掘削され、その先端
は支持層3aまで達している。そして、該掘削孔4,4
…内にセメントミルク5を充填するとともに、杭6,6
…を埋め込む。該杭6,6…はPHCパイル、PRCパ
イル、鋼管巻PCパイル等のコンクリート杭の他、鋼管
やH形鋼等を用いても良く、特にその種類、材質は限定
されない。また、杭6の埋め込みに代え、杭6を打ち込
んでも良い。
FIG. 1 is a block diagram showing an embodiment of the present invention.
This will be described in detail with reference to FIG. FIG. 1 shows a state in which a frame of a building structure 2 has been constructed on a site 1, and excavation holes 4,
4 are excavated with an excavator such as an earth auger, and the tip of the excavator reaches the support layer 3a. And the drilling holes 4, 4
… With cement milk 5 inside,
Embed ... The piles 6, 6,... May be concrete piles such as PHC piles, PRC piles, steel pipe wound PC piles, steel pipes, H-section steels, etc., and the types and materials thereof are not particularly limited. Further, instead of embedding the pile 6, the pile 6 may be driven.

【0007】而して、該杭6,6…はその全長が地中に
埋設されるのではなく、上部が地上に突出してその天端
は建築構造物2の天井高さまで達することにより、該建
築構造物2の柱7,7…を形成している。このように建
築構造物の基礎となる杭をそのまま柱として利用した場
合、その杭(柱)が建築構造物の自重や地震による水平
力等に対して所要強度を確保できるかが問題となる。
The piles 6, 6,... Are not buried in the whole length, but project upward from the ground and reach the ceiling to the ceiling height of the building structure 2. The pillars 7 of the building structure 2 are formed. In this way, when a pile serving as a foundation of a building structure is used as a column as it is, there is a problem whether the pile (column) can secure required strength against the weight of the building structure, horizontal force due to an earthquake, and the like.

【0008】そこで、発明者は図2に示すモデルを用い
て外力による杭変形の解析を行った。具体的には、杭の
モデルとして線材Lを考え、該線材Lの全長を1300
0mmとするとともに、地中へ9000mm打ち込み、地上
に4000mm突出させることとした。また、該線材Lの
先端(下端)をピン支持するとともに、地中に埋設され
た部分には杭が地盤から受ける弾性復原力に相当するも
のとして、合計9個のバネk1 ,k2 …k9 を1000
mm間隔で水平に接続した。更に、線材Lの天端に外力と
して軸力P及び水平力Hを加えた。
Therefore, the inventor analyzed pile deformation due to external force using the model shown in FIG. Specifically, the wire L is considered as a model of the pile, and the total length of the wire L is 1300.
It was set to 0 mm, and 9000 mm was driven into the ground to protrude 4000 mm above the ground. The tip (lower end) of the wire L is supported by a pin, and a portion buried in the ground is equivalent to the elastic restoring force received by the pile from the ground, and a total of nine springs k 1 , k 2 . k 9 to 1000
They were connected horizontally at mm intervals. Further, an axial force P and a horizontal force H were applied to the top end of the wire L as external forces.

【0009】そして、そのケーススタディ結果より、前
記バネk1 ,k2 …k9 のうち線材Lの変形モードを支
配する度合が最も大きいものは最上部のバネk1 であ
り、残りのバネk2 〜k9 は影響度が小さいことが判明
した。即ち、これらのバネk1,k2 …k9 のバネ定数
を種々の大きさに設定して線材Lの変形モードがどのよ
うに変化するかを調べたところ、バネk1 のバネ定数が
変わると線材Lの変形モードも大きく変化するが、その
他のバネk2 〜k9 のバネ定数が変わっただけでは線材
Lの変形モードにそれほど大きな変化は見られなかった
のである。
From the results of the case study, the spring k 1 , k 2 ... K 9 , which has the highest degree of controlling the deformation mode of the wire L, is the uppermost spring k 1 and the remaining springs k 1 , k 2. 2 ~k 9 was found to influence the degree is small. That is, when the spring constants of these springs k 1 , k 2 ... K 9 are set to various sizes, and how the deformation mode of the wire L changes is examined, the spring constant of the spring k 1 changes. However, the deformation mode of the wire L also greatly changes, but only by changing the spring constants of the other springs k 2 to k 9, no significant change was found in the deformation mode of the wire L.

【0010】このことは実際の杭を柱に利用した建築構
造物に於いて、表層(地表から深さ1m程度)の地盤特
性についてのみ、精度良く評価することができれば、柱
となる部分の変形量を制御できることを意味し、その結
果、該建築構造物の所要強度も充分確保できることにな
る。ところで、地盤のボーリングデータから各深さ毎の
バネ定数を定め、前述した解析モデルに当て嵌めようと
しても、通常ボーリングデータ自体のばらつきが大きい
ので信頼の置ける評価は望めない。しかし、評価の対象
が表層だけであれば斯かる問題も解消する。
[0010] This means that in a building structure using actual piles as pillars, if only the ground characteristics of the surface layer (about 1 m deep from the surface of the ground) can be accurately evaluated, the deformation of the pillar portions This means that the amount can be controlled, and as a result, the required strength of the building structure can be sufficiently secured. By the way, even if the spring constant for each depth is determined from the boring data of the ground and is applied to the above-described analysis model, reliable evaluation cannot be expected because the variation of the boring data itself is large. However, if the evaluation target is only the surface layer, such a problem is also solved.

【0011】即ち、図1に示す如く、地盤3の表層3b
に地表から固化剤を注入することにより地盤改良する。
この地盤改良部8の深さは大略1m程度であるが、建築
構造物2の高さや柱7,7…に加わる荷重並びに固化剤
の物性(硬度等)等に応じて増減させる。また、敷地1
の全面を地盤改良するのがベストであるが、図3のよう
に杭6,6…間を縦横に結ぶ格子状に形成すれば経済的
であり、且つ、地中梁と同様の作用を奏するので機能的
にも優れている。更に、図4の如く杭6,6…の周縁を
囲繞するように形成しても良い。
That is, as shown in FIG. 1, the surface layer 3b of the ground 3
The ground is improved by injecting a solidifying agent from the ground surface.
The depth of the ground improvement portion 8 is approximately 1 m, but is increased or decreased according to the height of the building structure 2, the load applied to the columns 7, and the physical properties (hardness and the like) of the solidifying agent. Site 1
It is best to improve the ground over the entire surface, but it is economical if it is formed in a grid shape connecting the piles 6, 6 ... vertically and horizontally as shown in Fig. 3, and it has the same effect as an underground beam. It is also functionally excellent. Further, as shown in FIG. 4, the piles 6 may be formed so as to surround the periphery thereof.

【0012】このように表層3bを人為的に改良するこ
とにより、該表層3bの剛性を高めつつその地盤特性を
精度良く評価することができる。斯くして、柱7,7…
の変形量が制御可能になり、従って、地中梁が無くても
建築構造物2の所要強度を充分に確保することができ
る。
By artificially improving the surface layer 3b as described above, it is possible to accurately evaluate the ground characteristics while increasing the rigidity of the surface layer 3b. Thus, pillars 7, 7 ...
Can be controlled, and therefore the required strength of the building structure 2 can be sufficiently secured even without the underground beam.

【0013】一方、表層3bの剛性が高まるとは言って
も地中梁と比較すると該地盤改良部8の方が柔軟である
ので、地表部分に於ける杭6,6…の地震時変形が大き
くなる。そこで、図1及び図5に示す如く、地表に敷設
する床スラブとしての土間コンクリート9を打設する際
に、前記杭6,6…の周囲に数mm〜数cm程度の間隙(縁
切り部10,10…)を設けて、土間コンクリート9と
杭6,6…とを縁切りする。これにより杭6,6…が地
震で変形しても土間コンクリート9と接触することがな
く、従って、該杭6,6…及び土間コンクリート9が破
壊されることはない。
On the other hand, although the rigidity of the surface layer 3b is increased, the ground improvement portion 8 is more flexible than the underground beam, so that the piles 6, 6,. growing. Therefore, as shown in FIG. 1 and FIG. 5, when the concrete slab 9 is laid as a floor slab laid on the ground surface, a gap of about several mm to several cm around the piles 6, 6. , 10...) To cut off the concrete 9 between the soil and the piles 6, 6,. Thereby, even if the piles 6, 6, ... are deformed by the earthquake, they do not come into contact with the concrete between the soils 9, and therefore, the piles 6, 6, ... and the concrete between the soils 9 are not destroyed.

【0014】然る後に図1に示す如く、柱7,7…の天
端上に桁11,11…を架設し、更に折板葺屋根12を
被せる等して、建築構造物2を完成させる。尚、本発明
は、本発明の精神を逸脱しない限り種々の改変を為すこ
とができ、そして、本発明が該改変されたものに及ぶこ
とは当然である。
After that, as shown in FIG. 1, the girder 11, 11,... Are erected on the top ends of the columns 7, 7,. The present invention can be variously modified without departing from the spirit of the present invention, and it goes without saying that the present invention extends to the modified ones.

【0015】[0015]

【発明の効果】以上説明したように、本発明は地表に敷
設された床スラブと杭とを縁切りしたことにより、杭が
地震で変形しても床スラブと接触することはなく、杭及
び床スラブの破壊を防止することができる。また、地盤
の表層を地盤改良することにより、たとえ地中梁が無く
ても此種建築構造物の所要強度を充分に確保することが
できる。
As described above, according to the present invention, the floor slab laid on the ground surface and the pile are cut off, so that the pile does not come into contact with the floor slab even if it is deformed by an earthquake. Slab destruction can be prevented. Further, by improving the surface layer of the ground, the required strength of this type of building structure can be sufficiently ensured even if there is no underground beam.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の一実施の形態を示し、杭を柱に利用し
た建築構造物の斜視図。
FIG. 1 shows an embodiment of the present invention, and is a perspective view of a building structure using a pile as a pillar.

【図2】外力による杭の変形を調べる解析モデルの解説
図。
FIG. 2 is an explanatory diagram of an analysis model for examining a deformation of a pile due to an external force.

【図3】地盤改良の一例を示す平面図。FIG. 3 is a plan view showing an example of ground improvement.

【図4】地盤改良の他の例を示す平面図。FIG. 4 is a plan view showing another example of ground improvement.

【図5】地表周辺の要部縦断面図。FIG. 5 is a longitudinal sectional view of a main part around the ground surface.

【符号の説明】[Explanation of symbols]

2 建築構造物 3 地盤 3b 表層 6 杭 7 柱 8 地盤改良部 9 土間コンクリート 10 縁切り部 2 Building structure 3 Ground 3b Surface 6 Pile 7 Pillar 8 Ground improvement part 9 Soil concrete 10 Edge cutting part

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 杭の下部を地盤中に位置させるととも
に、該杭の上部を地上に突出させて柱と成し、且つ、地
表に敷設された床スラブと前記杭とを縁切りしたことを
特徴とする杭を柱に利用した建築構造物。
The present invention is characterized in that a lower part of a pile is located in the ground, an upper part of the pile is protruded to the ground to form a pillar, and a floor slab laid on the surface of the ground and the pile are cut off. A building structure that uses piles as pillars.
【請求項2】 杭の下部を地盤中に位置させるととも
に、該杭の上部を地上に突出させて柱と成し、且つ、前
記地盤の表層を地盤改良するとともに、地表に敷設され
た床スラブと前記杭とを縁切りしたことを特徴とする杭
を柱に利用した建築構造物。
2. A floor slab laid on the ground surface, wherein a lower portion of the pile is located in the ground, an upper portion of the pile is projected above the ground to form a pillar, and a surface layer of the ground is improved for the ground. A building structure using a pile as a pillar, characterized in that the pile is cut off from the pile.
JP8275117A 1996-10-17 1996-10-17 Building structures using piles as pillars Expired - Lifetime JP3006710B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8275117A JP3006710B2 (en) 1996-10-17 1996-10-17 Building structures using piles as pillars

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8275117A JP3006710B2 (en) 1996-10-17 1996-10-17 Building structures using piles as pillars

Publications (2)

Publication Number Publication Date
JPH10121490A true JPH10121490A (en) 1998-05-12
JP3006710B2 JP3006710B2 (en) 2000-02-07

Family

ID=17550962

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8275117A Expired - Lifetime JP3006710B2 (en) 1996-10-17 1996-10-17 Building structures using piles as pillars

Country Status (1)

Country Link
JP (1) JP3006710B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012112218A (en) * 2010-11-26 2012-06-14 Taisei Corp Method for constructing new foundation using existing pile, and foundation constructed by the method
JP2015200173A (en) * 2014-03-31 2015-11-12 積水化学工業株式会社 Ground improvement foundation structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012112218A (en) * 2010-11-26 2012-06-14 Taisei Corp Method for constructing new foundation using existing pile, and foundation constructed by the method
JP2015200173A (en) * 2014-03-31 2015-11-12 積水化学工業株式会社 Ground improvement foundation structure
JP2019011678A (en) * 2014-03-31 2019-01-24 積水化学工業株式会社 Ground improvement foundation structure

Also Published As

Publication number Publication date
JP3006710B2 (en) 2000-02-07

Similar Documents

Publication Publication Date Title
US4754588A (en) Foundation piling system
US4911583A (en) Structure and method for shoring a face of an excavation
JP3098719B2 (en) Building structures using piles as pillars
JP3534928B2 (en) Construction method of seismic isolation pit for existing building
JP3027341B2 (en) Method of vertically inserting piles in a building structure using piles as pillars and jig used for the method
JP3118210B2 (en) Building structures using piles as pillars
JP3006710B2 (en) Building structures using piles as pillars
JP3129676B2 (en) Piling columns in building structures using piles as pillars
JPH10299005A (en) Footing equipped with sloped pile bundled and method of construction work
JP2000265574A (en) High floor type steel frame footing beam method
JP2000129696A (en) Pile foundation method and pile foundation constructed by the method
JP4915037B2 (en) Method for controlling the amount of deformation of the mountain wall
JP3768220B2 (en) Pier structure and pier
JP3244324B2 (en) Mountain retaining method
JPH10317486A (en) Bearing structure of floor slab in building structure utilizing pile for column
JP3027340B2 (en) Building structures using piles as pillars
JPH06306872A (en) Formation of pressure plate type grit post footing
JP3700119B2 (en) Pillar construction method
JP3012215B2 (en) Building structures using piles as pillars
JP3162654B2 (en) Construction method of floor slab support structure in building structure using pile as pillar
JP2003336254A (en) Concrete pile and construction method of foundation structure by use thereof
JPH06173284A (en) Construction method for self-standing continuous wall
JPS6018769B2 (en) Construction method of underground structure
JP2555838B2 (en) Independent panel mountain retaining method
JPH09125405A (en) Deep foundation for inclined tower leg

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19991109

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20071126

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081126

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091126

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091126

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101126

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111126

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111126

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121126

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121126

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131126

Year of fee payment: 14

EXPY Cancellation because of completion of term