JPH0995932A - Liquefaction preventing construction method for ground - Google Patents

Liquefaction preventing construction method for ground

Info

Publication number
JPH0995932A
JPH0995932A JP25265295A JP25265295A JPH0995932A JP H0995932 A JPH0995932 A JP H0995932A JP 25265295 A JP25265295 A JP 25265295A JP 25265295 A JP25265295 A JP 25265295A JP H0995932 A JPH0995932 A JP H0995932A
Authority
JP
Japan
Prior art keywords
casing
sheet pile
ground
drain
attached
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP25265295A
Other languages
Japanese (ja)
Other versions
JP2881637B2 (en
Inventor
Shigeru Nakagawa
茂 中川
Mitsugi Fusamae
貢 房前
Takayoshi Morikawa
孝義 森川
Yoshitake Oka
由剛 岡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
JFE Steel Corp
JFE Engineering Corp
Original Assignee
Taisei Corp
Kawasaki Steel Corp
NKK Corp
Nippon Kokan Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp, Kawasaki Steel Corp, NKK Corp, Nippon Kokan Ltd filed Critical Taisei Corp
Priority to JP25265295A priority Critical patent/JP2881637B2/en
Publication of JPH0995932A publication Critical patent/JPH0995932A/en
Application granted granted Critical
Publication of JP2881637B2 publication Critical patent/JP2881637B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide a ground liquefaction preventing construction method which can shorten execution time by giving drainage function to a sheet pile, and moreover is inexpensive and easy in execution. SOLUTION: The tip part of a casing 2 which is formed to be cylindrical or about U-shaped in section is connected to an end protecting member 3 attached to a sheet pile, and the casing 2 is held about parallel to the sheet pile 1 by an attaching member 4 and unified. A bar-shaped or cylindrical drain member having water absorbing ability or permeability is inserted in a cylindrical part formed inside the casing 2 or between the sheet pile 1 and the casing 2. The sheet pile 1 is drivenly installed in the ground in a state where the drain member is inserted. After the sheet pile 1 is drivenly installed, the casing 2 is pulled up in a state where the sheet pile 1, the end protecting member 3 and the drain member are left in the ground.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、地震時に砂質地盤
に発生する液状化を防止し、各種構造物の液状化被害を
防止することのできる地盤の液状化防止工法に関するも
のである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for preventing liquefaction of ground, which can prevent liquefaction occurring in sandy ground during an earthquake and prevent damage to liquefaction of various structures.

【0002】[0002]

【従来の技術】砂質地盤の液状化防止対策としては種々
提案されているが、その一例として特公平6−1199
0号公報(以下従来技術1という)に記載された発明が
ある。この発明は、振動を利用してケーシングを砂質地
盤にその砂質地盤を締固めつつ打込む工程と、地盤の所
定圧力に対する耐圧性を有し周壁に透水用の孔を開設し
たパイプに透水性フィルタを被せてなるドレーンパイプ
をケーシングに挿入する工程と、ケーシングを砂質地盤
から引抜いて砂質地盤にドレーンパイプを残留させる工
程とを有し、砂質地盤中の過剰間隙水圧をドレーンパイ
プを用いて低下させるようにした砂質地盤の液状化防止
工法に関するものである。
2. Description of the Related Art Various measures have been proposed to prevent liquefaction of sandy ground.
There is an invention described in Japanese Patent Publication No. 0 (hereinafter referred to as Prior Art 1). The present invention relates to a process of driving a casing into a sandy ground by using vibration while compacting the sandy ground, and a method of permeating a pipe having a pressure resistance against a predetermined pressure of the ground and having a hole for water permeation formed in a peripheral wall. Inserting a drain pipe covered with a porous filter into the casing, and withdrawing the casing from the sandy ground to leave the drain pipe in the sandy ground, and draining excess pore water pressure in the sandy ground. The present invention relates to a method for preventing liquefaction of sandy ground which is reduced by using the method.

【0003】また、特開平2−225712号公報(以
下従来技術2という)に開示された発明は、矢板本体の
長手方向に沿った所定区間に、多数の開口部とこの開口
部からの地盤の侵入を防止するためのフィルタを備えた
排水用部材を1条又は複数条、少なくとも矢板本体の片
面に設けたものである。
The invention disclosed in Japanese Patent Application Laid-Open No. 2-225712 (hereinafter referred to as "prior art 2") has a large number of openings in a predetermined section along the longitudinal direction of the sheet pile body and the ground from the openings. One or a plurality of drainage members provided with a filter for preventing intrusion are provided on at least one surface of the sheet pile body.

【0004】[0004]

【発明が解決しようとする課題】従来技術1の発明は、
ドレーンパイプと矢板を別々に施工しなければならない
ので、施工時間に制約がある場合は対応が困難であり、
施工性に問題がある。また、従来技術2の発明は、あら
かじめ排水用部材を取付けた鋼矢板を打設するようにし
ているため施工時間の短縮を図ることができるが、施工
時間の短縮による効果以上に排水用部材の加工及び鋼矢
板への取付けにコストがかかり、経済性の面で問題があ
る。
DISCLOSURE OF THE INVENTION The invention of the prior art 1 is
Since the drain pipe and sheet pile must be constructed separately, it is difficult to cope if there are restrictions on the construction time,
There is a problem in workability. Further, the invention of the prior art 2 is capable of shortening the construction time because the steel sheet pile to which the drainage member is previously attached is cast, but the drainage member can be reduced more than the effect of shortening the construction time. Processing and mounting on steel sheet piles are costly and have problems in terms of economy.

【0005】本発明は、上記の課題を解決すべくなされ
たもので、矢板に排水機能を付加することにより施工時
間を短縮でき、その上安価で施工が容易な地盤の液状化
防止工法を得ることを目的としたものである。
The present invention has been made to solve the above-mentioned problems. By adding a drainage function to the sheet pile, the construction time can be shortened, and a method for preventing liquefaction of the ground which is inexpensive and easy to construct is obtained. This is the purpose.

【0006】[0006]

【課題を解決するための手段】[Means for Solving the Problems]

(1)本発明に係る地盤の液状化防止工法は、筒状又は
断面ほぼU字状に形成されたケーシングの先端部を矢板
に取付けられた端面保護部材と連結して取付け部材によ
り該ケーシングを矢板とほぼ平行に保持して一体化する
工程と、前記ケーシング内又は矢板とケーシングとの間
に形成された筒状部に吸水性又は透水性を有する棒状又
は筒状のドレーン部材を装入する工程と、ドレーン部材
を装入した状態で矢板を地盤中に打設する工程と、矢板
を打設したのち、矢板、端面保護部材及びドレーン部材
を地盤中に残した状態で前記ケーシングを引上げる工程
とからなるものである。
(1) In the ground liquefaction prevention method according to the present invention, a tip portion of a casing formed in a tubular shape or a substantially U-shaped cross section is connected to an end face protection member attached to a sheet pile, and the casing is attached by the attachment member. A step of holding the sheet pile substantially parallel to the sheet pile and integrating it, and inserting a rod-shaped or tubular drain member having water absorbability or water permeability into a tubular portion formed in the casing or between the sheet pile and the casing. Step, driving the sheet pile into the ground with the drain member inserted, and after pulling the sheet pile, pull up the casing with the sheet pile, the end face protection member and the drain member left in the ground It consists of a process.

【0007】(2)また、上記(1)の地盤の液状化防
止工法において、端面保護部材及びケーシングと一体化
された矢板を地中に打設したのち、ケーシング内又は矢
板とケーシングとの間に形成された筒状部にドレーン部
材を装入するようにしたものである。
(2) Further, in the ground liquefaction prevention construction method of (1) above, after the sheet pile integrated with the end face protection member and the casing is driven into the ground, it is placed in the casing or between the sheet pile and the casing. The drain member is inserted into the tubular portion formed on the.

【0008】[0008]

【発明の実施の形態】図1は本発明の一実施形態を示す
もので、(a)は正面図、(b)はそのA−A断面図、
図2は図1の分解斜視図である。また、図3は図1
(a)のB−B拡大断面図、C−C拡大断面図及びD−
D拡大断面図である。図において、1は鋼矢板、2は角
鋼管21からなり鋼矢板1より短いケーシング、3は鋼
矢板1の内面下部に固定され、ケーシング2の下部が連
結される端面保護部材、4,4は鋼矢板1の内面上部に
固定され、ケーシング2を保持する取付け部材、5,5
は例えばポリエチレン製の穴あき耐圧管からなるドレー
ン部材である。以下上記各部材についてそれぞれ詳細に
説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS FIG. 1 shows an embodiment of the present invention. (A) is a front view, (b) is a sectional view taken along line AA,
FIG. 2 is an exploded perspective view of FIG. FIG. 3 shows FIG.
(A) BB enlarged sectional view, CC enlarged sectional view and D-
It is a D expanded sectional view. In the figure, 1 is a steel sheet pile, 2 is a casing made of square steel pipes 21 and shorter than the steel sheet pile 1, 3 is an end face protection member that is fixed to the lower inner surface of the steel sheet pile 1, and the lower portion of the casing 2 is connected, 4, 4 Mounting members fixed to the upper inner surface of the steel sheet pile 1 and holding the casing 2, 5, 5
Is a drain member made of, for example, a perforated pressure resistant pipe made of polyethylene. Hereinafter, each of the above members will be described in detail.

【0009】鋼矢板1は、図1〜図3では断面ほぼコ字
状の鋼矢板1を用いた場合を示したが、例えば、図6に
示すH形鋼11、図7(a)に示す矢板付きH形鋼1
2、(b)図に示すような鋼管13、(c)図に示すよ
うな矢板付き鋼管14などを用いてもよく、さらには、
コンクリート杭、既製の鉄筋コンクリート杭、プレスト
レスコンクリート杭、鋼管コンクリート杭など(以下こ
れらを一括してコンリート杭という)であってもよい。
以下本明細書においては、上述の各種矢板、鋼管、杭な
どを総称して矢板という。
The steel sheet pile 1 is shown in FIGS. 1 to 3 in the case where the steel sheet pile 1 having a substantially U-shaped cross section is used. For example, the H section steel 11 shown in FIG. 6 and the steel sheet pile shown in FIG. H-section steel with sheet pile 1
2, a steel pipe 13 as shown in FIG. 2 (b), a steel pipe 14 with a sheet pile as shown in FIG. 2 (c), etc. may be used.
Concrete piles, ready-made reinforced concrete piles, prestressed concrete piles, steel pipe concrete piles, and the like (hereinafter collectively referred to as “concrete piles”) may be used.
Hereinafter, in the present specification, the above-described various sheet piles, steel pipes, piles, and the like are collectively referred to as sheet piles.

【0010】ケーシング2は、図には断面長方形の鋼管
21を用いた場合を示したが、鋼板を溶接して断面長方
形状又は断面ほぼU字状、V字状などに形成してもよ
く、あるいは、図4に示すような断面ほぼU字状の溝形
鋼22や断面ほぼV字状の形鋼、図5に示すような断面
円形の鋼管23を用いるなど、適宜の断面形状の部材を
用いることができる。
The casing 2 is shown in the drawing using a steel pipe 21 having a rectangular cross section, but a steel plate may be welded to form a rectangular cross section or a substantially U-shaped or V-shaped cross section. Alternatively, a member having an appropriate cross-sectional shape, such as a channel steel 22 having a substantially U-shaped cross-section as shown in FIG. 4, a shape steel having a substantially V-shaped cross-section, or a steel pipe 23 having a circular cross-section as shown in FIG. 5, may be used. Can be used.

【0011】端面保護部材3は、図2及び図3〜図5の
(c)に示すように、その内形がケーシング2の外形と
ほぼ等しく、ケーシング2の外面が内側に嵌入しうる大
きさで、かつ上部が開口された平面ほぼコ字状の外面嵌
合部31を有し(外袋タイプ)、下部には船の舳先のよ
うに三角形状又は三角錐状などにより尖鋭部32が形成
されている。
As shown in FIG. 2 and FIGS. 3 to 5C, the end face protection member 3 has an inner shape substantially equal to the outer shape of the casing 2, and the outer surface of the casing 2 can be fitted inward. In addition, the outer surface fitting portion 31 having a substantially U-shape in a plan view and having an upper opening is formed (outer bag type), and the sharp portion 32 is formed in the lower portion by a triangular shape or a triangular pyramid shape like a bow of a ship. Has been done.

【0012】また、この端面保護部材3は、図8に示す
ように、その外形をケーシング2の内形とほぼ等しく、
ケーシング2の内面が外側に嵌合しうる大きさで、かつ
上部が開口された断面ほぼコ字状の内面嵌合部33を有
し(内袋タイプ)、例えば、その両側壁の下方に丸棒な
どを溶接して当接部34,34を設け、あるいは、さら
に、前面にL字状の保持板35を溶接して前壁との間に
ケーシング2の嵌合部36を形成するなど、ケーシング
2の下端部がその外側に嵌合しうるように形成してもよ
い。
As shown in FIG. 8, the end face protecting member 3 has an outer shape substantially equal to the inner shape of the casing 2,
The inner surface of the casing 2 has an inner surface fitting portion 33 having a substantially U-shaped cross-section with an opening so that the inner surface can be fitted to the outer side (inner bag type). Welding a rod or the like to provide the contact portions 34, 34, or further, welding an L-shaped holding plate 35 to the front surface to form the fitting portion 36 of the casing 2 between the front wall and the like. It may be formed so that the lower end of the casing 2 can be fitted to the outside thereof.

【0013】さらに、端面保護部材3を円筒状に形成し
た場合は、上記と同様に平滑な外面嵌合部31又は内面
嵌合部33を設けてもよく、あるいは、外面嵌合部31
の内周にめねじを設け、又は内面嵌合部33の外周にお
ねじを設けると共に、ケーシング2の下部にこれに対応
するおねじ又はめねじを設けてねじ結合するようにして
もよい。上記の説明では、端面保護部材3の下部を尖鋭
に形成した場合を示したが、平坦に形成してもよい。
Further, when the end face protection member 3 is formed in a cylindrical shape, a smooth outer surface fitting portion 31 or inner surface fitting portion 33 may be provided as described above, or the outer surface fitting portion 31.
A female screw may be provided on the inner periphery of the casing 2, or a screw may be provided on the outer periphery of the inner surface fitting portion 33, and a male screw or a female screw corresponding thereto may be provided on the lower portion of the casing 2 for screw connection. In the above description, the case where the lower portion of the end face protection member 3 is formed to be sharp is shown, but it may be formed to be flat.

【0014】このような端面保護部材3は、コ字状の開
口部を矢板1の下部内面に当接して溶接により固定し、
あるいは、ボルト・ナットにより着脱可能に取付けられ
る。なお、円筒状の端面保護部材3の場合は、直接又は
取付腕を介して溶接により矢板1に固定され、又はボル
ト・ナットにより着脱可能に矢板1に取付けられる。
In such an end face protecting member 3, the U-shaped opening is brought into contact with the lower inner surface of the sheet pile 1 and fixed by welding.
Alternatively, it is detachably attached with bolts and nuts. In the case of the cylindrical end face protection member 3, it is fixed to the sheet pile 1 by welding directly or through the mounting arm, or detachably attached to the sheet pile 1 with bolts and nuts.

【0015】取付け部材4,4は、図2〜図4に示すよ
うに、ほぼL字状の金具からなり、一方の片41,41
に設けたねじ挿通穴43に挿通したボルト6を矢板1に
設けたねじ挿通穴11に挿通し、他方の片42,42の
間にケーシング2を挟持してナット61で着脱自在に固
定し、ケーシング2を強固に保持する。この場合、取付
け部材4,4の一方の片41,41を矢板1に溶接して
固定してもよく、また、他方の片42,42とケーシン
グ2とをボルト・ナットで固定してもよい。さらに、一
方の片41,41に設けたねじ挿通穴43,43を長穴
にすれば、ケーシング2の挟持が容易である。
As shown in FIGS. 2 to 4, the mounting members 4 and 4 are substantially L-shaped metal fittings, and one of the pieces 41 and 41.
The bolt 6 inserted into the screw insertion hole 43 provided in the insert is inserted into the screw insertion hole 11 provided in the sheet pile 1, the casing 2 is sandwiched between the other pieces 42, 42, and the nut 61 is detachably fixed, Hold the casing 2 firmly. In this case, one piece 41, 41 of the mounting members 4, 4 may be welded and fixed to the sheet pile 1, or the other piece 42, 42 and the casing 2 may be fixed with bolts and nuts. . Further, if the screw insertion holes 43, 43 provided in the one piece 41, 41 are elongated holes, the casing 2 can be easily clamped.

【0016】また、ケーシング2に鋼管23を用いた場
合は、図5に示すように、取付部材4をほぼΩ状に形成
し、ケーシング2の外周を保持部材45,45を介して
包囲し、その腕部44,44をボルト6とナット61に
より矢板1に着脱自在に固定すればよい。なお、取付け
部材4は上記の構造に限定するものではなく、ケーシン
グ2の形状に応じて適宜変更することができる。
When the steel pipe 23 is used for the casing 2, as shown in FIG. 5, the mounting member 4 is formed into a substantially Ω shape, and the outer periphery of the casing 2 is surrounded by the holding members 45, 45. The arms 44, 44 may be detachably fixed to the sheet pile 1 with the bolt 6 and the nut 61. The mounting member 4 is not limited to the structure described above, and can be appropriately changed according to the shape of the casing 2.

【0017】ドレーン部材5は、例えば、ポリエチレン
の如き合成樹脂製の耐圧管の周壁に多数の穴51を設け
た吸水性又は透水性を有する棒状又は筒状のもので、必
要に応じて、穴51から土砂の侵入を防止するために、
例えば、図8に示すように、吸水性又は透水性及び耐食
性を有する合成繊維製、合成樹脂製、ステンレス製など
のフィルタ52で被覆してもよい。なお、このドレーン
部材5は合成樹脂製に限定するものではなく、ステンレ
スの如き耐食性を有する金属管で構成してもよい。
The drain member 5 is, for example, a water-absorbing or water-permeable rod-shaped or cylindrical member having a large number of holes 51 formed in the peripheral wall of a pressure resistant tube made of synthetic resin such as polyethylene. In order to prevent the infiltration of earth and sand from 51,
For example, as shown in FIG. 8, the filter 52 may be covered with a filter 52 made of synthetic fiber, synthetic resin, stainless steel, or the like having water absorption or water permeability and corrosion resistance. The drain member 5 is not limited to the synthetic resin, and may be a metal tube having corrosion resistance such as stainless steel.

【0018】上記のような各部材からなる本発明におい
ては、図9(a)に示すように、矢板1の内面下部に端
面保護部材3を溶接、ねじ止め等により取付け、ケーシ
ング2を矢板1の内面に沿って配設する。そして図9
(b)に示すように、ケーシング2の下端部を、端面保
護部材3の外面嵌合部31内に、尖鋭部32の内壁に当
るまで嵌入する。ついで、ケーシング2の上部を矢板1
に取付けた取付け部材4,4により矢板1とほぼ平行に
固定し、最後に図9(c)に示すように、ケーシング2
内にドレーン部材5を装入すれば、各部材を一体化する
ことができる。
In the present invention composed of the above-mentioned members, as shown in FIG. 9A, the end face protection member 3 is attached to the lower inner surface of the sheet pile 1 by welding, screwing or the like, and the casing 2 is attached to the sheet pile 1. It is arranged along the inner surface of. And FIG.
As shown in (b), the lower end portion of the casing 2 is fitted into the outer surface fitting portion 31 of the end surface protection member 3 until it comes into contact with the inner wall of the sharp portion 32. Then, place the upper part of the casing 2 on the sheet pile 1.
It is fixed substantially parallel to the sheet pile 1 by the attachment members 4 and 4 attached to the casing 2, and finally, as shown in FIG.
If the drain member 5 is inserted inside, each member can be integrated.

【0019】また、図4に示すように、ケーシング2と
して溝形鋼22又は断面V字状の形鋼などを用いた場合
は、開口部側を矢板1に当接し、その下部を端面保護部
材3に嵌合して上部を取付け部材4で固定し、矢板1と
ケーシング2との間に形成された筒状部にドレーン部材
5,5を挿入すればよい。さらに内面嵌合部33を有す
る端面保護部材3の場合は、ケーシング2をその下端部
が当接部34に当るまで嵌合すればよく、端面保護部材
3及びケーシング2の下端部にねじを設けた場合は、こ
のねじを螺合して両者を連結すればよい。
Further, as shown in FIG. 4, when a grooved steel 22 or a V-shaped cross-section steel is used as the casing 2, the opening side is brought into contact with the sheet pile 1 and the lower part thereof is an end face protection member. 3 and the upper part is fixed by the mounting member 4, and the drain members 5 and 5 may be inserted into the tubular portion formed between the sheet pile 1 and the casing 2. Further, in the case of the end surface protection member 3 having the inner surface fitting portion 33, the casing 2 may be fitted until the lower end portion of the end surface comes into contact with the contact portion 34, and a screw is provided on the end surface protection member 3 and the lower end portion of the casing 2. In this case, these screws may be screwed together to connect the two.

【0020】なお、各部材を一体化するにあたっては、
矢板1に端面保護部材3を取付け、これにあらかじめド
レーン部材5を装入したケーシング2を取付け、あるい
は、端面保護部材3を取付けたケーシング2にドレーン
部材5を装入し、これを矢板1に取付けてもよく、さら
には、あらかじめドレーン部材5を装入したケーシング
2に端面保護部材3を取付け、これを矢板1に取付ける
など、適宜変更することができる。
When integrating the members,
The end face protection member 3 is attached to the sheet pile 1, and the casing 2 in which the drain member 5 is previously attached is attached thereto, or the drain member 5 is placed in the casing 2 in which the end face protection member 3 is attached, and this is attached to the sheet pile 1. The end face protection member 3 may be attached to the casing 2 in which the drain member 5 is inserted in advance, and the end face protection member 3 may be attached to the sheet pile 1.

【0021】このようにして一体化された矢板1、ケー
シング2、端面保護部材3、取付け部材4,4及びドレ
ーン部材5は、図10(a)に示すように、矢板1を地
盤に打設することにより一体的に地盤中に埋設される。
そして、打設が終ったときは、図10(b)に示すよう
に、取付け部材4,4を外すか又は緩め、矢板1、端面
保護部材3及びドレーン部材5を地盤中に残置した状態
でケーシング2を引抜く。この場合、ケーシング2を矢
板1から離脱させてもよく、あるいは、ケーシング2を
途中まで引上げてその位置で保持するようにしてもよ
い。なお、ケーシング2を取付けた状態で矢板1を打設
し、打設が終ったのちドレーン部材5をケーシング2内
に装入し、ついで、ケーシング2を引抜いてもよい。
As shown in FIG. 10A, the sheet pile 1, the casing 2, the end face protection member 3, the attachment members 4, 4 and the drain member 5 which are integrated in this way are driven into the ground. By doing so, it is integrally buried in the ground.
Then, when the driving is finished, as shown in FIG. 10B, the mounting members 4 and 4 are removed or loosened, and the sheet pile 1, the end face protection member 3 and the drain member 5 are left in the ground. Pull out the casing 2. In this case, the casing 2 may be detached from the sheet pile 1, or the casing 2 may be pulled up partway and held at that position. Alternatively, the sheet pile 1 may be driven with the casing 2 attached, the drain member 5 may be inserted into the casing 2 after the driving is finished, and then the casing 2 may be pulled out.

【0022】ところで、ケーシング2を引抜く際に、ド
レーン部材5,5も一緒に上ってしまう(供上り)おそ
れがある。そこで、本発明においては、次のような供上
り防止対策を講じた。すなわち、図8に示すように、端
面保護部材3に内面嵌合部33を形成し、その上端部に
フック38を有するキャップ37を取付ける。そして、
ドレーン部材5,5を被覆した合成繊維製のフィルタ5
2,52の下端部をこのフック38に巻付けて固定する
ようにした。これにより、ケーシング2を引抜いてもド
レーン部材5,5は端面保護部材3に保持され、供上り
することはない。
By the way, when the casing 2 is pulled out, there is a risk that the drain members 5 and 5 will also go up (up). Therefore, in the present invention, the following supply prevention measures are taken. That is, as shown in FIG. 8, the inner surface fitting portion 33 is formed on the end surface protection member 3, and the cap 37 having the hook 38 is attached to the upper end portion thereof. And
Synthetic fiber filter 5 covering the drain members 5 and 5
The lower ends of 2, 52 are wound around the hook 38 to be fixed. As a result, even if the casing 2 is pulled out, the drain members 5 and 5 are held by the end face protection member 3 and do not come up.

【0023】また、ドレーン部材5,5の下端部にフッ
ク付きのキャップを取付け、このフックを端面保護部材
3に設けた止め金具に係止させるようにしてもよく、あ
るいは、ケーシング2が例えば図4に示すように溝形鋼
22からなる開断面の場合は、矢板1のドレーン部材
5,5の頂部と対応する位置に、ドレーン部材5,5側
に突出する押え部材を取付け、ドレーン部材5,5の供
上りを阻止するようにしてもよい。
A cap with a hook may be attached to the lower end portions of the drain members 5 and 5, and the hook may be engaged with a stopper provided on the end face protecting member 3, or the casing 2 may be, for example, as shown in FIG. As shown in FIG. 4, in the case of the open cross section made of the channel steel 22, a holding member projecting to the drain member 5, 5 side is attached at a position corresponding to the top of the drain member 5, 5 of the sheet pile 1. , 5 may be blocked.

【0024】さらに、ドレーン部材5,5の下端部がキ
ャップなどで閉塞されている場合は、例えば、ドレーン
部材5,5の内径より細い棒鋼からなり、上部にワイヤ
などを取付けた重りをドレーン部材5,5内に挿入して
先端部を着底させ、ケーシング2を引抜く際に反力とし
て作用させて供上りを防止し、ケーシング2の引抜きが
終ったときは重りを引上げるようにしてもよい。また、
ドレーン部材5,5の下端部が閉塞されていない場合
は、重りの上部に直接又はワイヤ等を介してドレーン部
材5,5の外形より大きい板材を取付け、重りをドレー
ン部材5,5内に挿入して板材をその頂部に載置し、反
力として作用させるなど、適宜の手段を用いることがで
きる。
Further, when the lower end portions of the drain members 5 and 5 are closed with a cap or the like, for example, a weight made of steel bar having a diameter smaller than the inner diameter of the drain members 5 and 5 and having a wire or the like attached to the upper portion thereof is used as the drain member. Insert the inside of the casing 5 and 5 to set the tip to the bottom, and act as a reaction force when pulling out the casing 2 to prevent it from rising, and pull up the weight when the casing 2 is pulled out. Good. Also,
When the lower ends of the drain members 5 and 5 are not closed, a plate material larger than the outer shape of the drain members 5 and 5 is attached to the upper portion of the weight directly or via a wire, and the weight is inserted into the drain members 5 and 5. Then, an appropriate means such as placing the plate member on the top of the plate member and acting it as a reaction force can be used.

【0025】上記のように構成した本発明装置において
は、矢板1に近接してドレーン部材5を設け、両者を同
時に地盤中に打設するようにしたので、施工が容易で工
期を短縮することができる。また、矢板1の打設に際し
て、矢板1、ケーシング2及び端面保護部材3により周
囲の地盤の土止め、締切り、締固めが並行して行われる
ので、地盤の液状化に対する強度を増加することができ
る。さらに、ドレン部材5に地下水を流入させて地盤中
に発生する過剰間隙水圧を消散させると共に、これに近
接して強度の大きい矢板1を設けたので、各種構造物の
液状化被害を防止することができる。
In the apparatus of the present invention constructed as described above, the drain member 5 is provided close to the sheet pile 1 and both of them are simultaneously driven into the ground, so that the construction is easy and the construction period is shortened. You can In addition, when the sheet pile 1 is driven, the sheet pile 1, the casing 2 and the end face protection member 3 simultaneously perform soil stopping, closing and compaction of the surrounding ground, so that the strength against liquefaction of the ground can be increased. it can. In addition, groundwater flows into the drain member 5 to dissipate excess pore water pressure generated in the ground, and a strong sheet pile 1 is provided close to it to prevent liquefaction damage of various structures. You can

【0026】上記の実施形態では、矢板1の内面側にケ
ーシング2、端面保護部材3及び取付部材4を設けて、
ケーシング2内に1本又は2本のドレーン部材5を挿入
した場合を示したが、これら各部材は矢板1の外面側に
設けてもよく、あるいは内面側と外面側の両方に設けて
もよい。また、ドレーン部材5の数は適宜増減すること
ができる。さらに、図6及び図7に破線で示すように、
矢板1の種類、形状に応じて、適宜の場所に適宜数のド
レーン部材5を設けることができる。
In the above embodiment, the casing 2, the end face protection member 3 and the mounting member 4 are provided on the inner surface side of the sheet pile 1,
Although the case where one or two drain members 5 are inserted into the casing 2 is shown, these respective members may be provided on the outer surface side of the sheet pile 1, or may be provided on both the inner surface side and the outer surface side. . Further, the number of drain members 5 can be appropriately increased or decreased. Further, as shown by the broken lines in FIGS. 6 and 7,
Depending on the type and shape of the sheet pile 1, an appropriate number of drain members 5 can be provided at appropriate locations.

【0027】[0027]

【発明の効果】本発明に係る地盤の液状化防止工法は、
筒状又は断面ほぼU字状に形成されたケーシングの先端
部を矢板に取付けられた端面保護部材と連結して取付け
部材により該ケーシングを矢板とほぼ平行に保持して一
体化する工程と、前記ケーシング内又は矢板とケーシン
グとの間に形成された筒状部に吸水性又は透水性を有す
る棒状又は筒状のドレーン部材を装入する工程と、ドレ
ーン部材を装入した状態で矢板を地盤中に打設する工程
と、矢板を打設したのち、矢板、端面保護部材及びドレ
ーン部材を地盤中に残した状態で前記ケーシングを引上
げる工程とによって構成したので、安価で施工が容易で
あり、工期を短縮することができる。
The method for preventing liquefaction of the ground according to the present invention is
A step of connecting a tip end portion of a casing formed in a tubular shape or a substantially U-shaped section to an end face protection member attached to the sheet pile and holding the casing substantially parallel to the sheet pile by the attachment member to integrate the casing; The step of charging a water-absorbing or water-permeable rod-shaped or cylindrical drain member into the cylindrical portion formed in the casing or between the sheet pile and the casing, and the sheet pile in the ground with the drain member loaded. Since it is configured by a step of driving the sheet pile, and a step of driving the sheet pile, and then pulling up the casing with the sheet pile, the end face protection member and the drain member left in the ground, the construction is inexpensive and easy, The construction period can be shortened.

【0028】また、矢板の打設に際して、矢板及びこれ
と一体化されたケーシング、端面保護部材により、周囲
の地盤の土止め、締切り、締固めが並行して行われるの
で、地盤の耐液状化性を向上させることができる。さら
に、ドレーン部材に地下水を流入させて地盤中に発生す
る過剰間隙水圧を消散させると共に、これに近接して矢
板を設けたので、各種構造物の液状化被害を防止するこ
とができる。
In addition, when the sheet pile is driven, the sheet pile, the casing integrated with the sheet pile, and the end face protection member simultaneously perform earth stopping, closing, and compaction of the surrounding ground. It is possible to improve the sex. Furthermore, since groundwater is caused to flow into the drain member to dissipate excess pore water pressure generated in the ground and a sheet pile is provided in the vicinity thereof, liquefaction damage to various structures can be prevented.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施形態の正面図及びそのA−A断
面図である。
FIG. 1 is a front view of an embodiment of the present invention and a sectional view taken along line AA of FIG.

【図2】図1の分解斜視図である。FIG. 2 is an exploded perspective view of FIG.

【図3】図1のB−B、C−C、D−D拡大断面図であ
る。
3 is an enlarged cross-sectional view of BB, CC, DD of FIG.

【図4】本発明の他の例の図3に相当する拡大断面図で
ある。
FIG. 4 is an enlarged sectional view corresponding to FIG. 3 of another example of the present invention.

【図5】本発明の他の例の図3に相当する拡大断面図で
ある。
FIG. 5 is an enlarged cross-sectional view of another example of the present invention, which corresponds to FIG.

【図6】図1の矢板の他の例の模式図である。FIG. 6 is a schematic view of another example of the sheet pile of FIG. 1;

【図7】図1の矢板の他の例の模式図である。FIG. 7 is a schematic view of another example of the sheet pile of FIG.

【図8】図1の端面保護部材及びドレーン部材の他の例
の正面図及び側面図である。
FIG. 8 is a front view and a side view of another example of the end face protection member and the drain member of FIG.

【図9】本発明に係る工法の一例の工程説明図である。FIG. 9 is a process explanatory view of an example of a construction method according to the present invention.

【図10】本発明に係る工法の一例の工程説明図であ
る。
FIG. 10 is a process explanatory view of an example of a construction method according to the present invention.

【符号の説明】[Explanation of symbols]

1 矢板 2 ケーシング 3 端面保護部材 31 外面嵌合部 33 内面嵌合部 34 当接部 35 保持板 4 取付け部材 5 ドレーン部材 51 穴 52 フィルタ 1 Sheet Pile 2 Casing 3 End Face Protecting Member 31 Outer Surface Fitting Part 33 Inner Surface Fitting Part 34 Abutment Part 35 Holding Plate 4 Mounting Member 5 Drain Member 51 Hole 52 Filter

───────────────────────────────────────────────────── フロントページの続き (72)発明者 中川 茂 東京都千代田区丸の内一丁目1番2号 日 本鋼管株式会社内 (72)発明者 房前 貢 東京都千代田区丸の内一丁目1番2号 日 本鋼管株式会社内 (72)発明者 森川 孝義 東京都千代田区内幸町2丁目2番3号 川 崎製鉄株式会社内 (72)発明者 岡 由剛 東京都千代田区内幸町2丁目2番3号 川 崎製鉄株式会社内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Shigeru Nakagawa 1-2-1, Marunouchi, Chiyoda-ku, Tokyo Nihon Steel Pipe Co., Ltd. (72) 1-2-2-1 Marunouchi, Chiyoda-ku, Tokyo Nippon Steel Tube Co., Ltd. (72) Inventor Takayoshi Morikawa 2-3-2 Uchisaiwaicho, Chiyoda-ku, Tokyo Kawasaki Steel Works (72) Inventor Yugo Oka 2-3-2 Uchisaiwai-cho, Chiyoda-ku, Tokyo Saki Steel Co., Ltd.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 筒状又は断面ほぼU字状に形成されたケ
ーシングの先端部を矢板に取付けられた端面保護部材と
連結し、取付け部材により該ケーシングを前記矢板とほ
ぼ平行に保持して一体化する工程と、 前記ケーシング内又は前記矢板とケーシングとの間に形
成された筒状部に吸水性又は透水性を有する棒状又は筒
状のドレーン部材を装入する工程と、 前記ドレーン部材を装入した状態で前記矢板を地盤中に
打設する工程と、 前記矢板を打設したのち、該矢板、端面保護部材及びド
レーン部材を地盤中に残した状態で前記ケーシングを引
上げる工程とによって構成したことを特徴とする地盤の
液状化防止工法。
1. A casing or a casing formed in a U shape in cross section is connected to an end face protection member attached to a sheet pile, and the attachment member holds the casing substantially parallel to the sheet pile and is integrated. And a step of loading a rod-shaped or tubular drain member having water absorbability or water permeability into a tubular portion formed in the casing or between the sheet pile and the casing, and the drain member is attached. Constituted by a step of driving the sheet pile into the ground in an inserted state, and a step of driving the sheet pile, and then pulling up the casing with the sheet pile, the end face protection member and the drain member left in the ground. The liquefaction prevention method of the ground characterized by the above.
【請求項2】 請求項1において、端面保護部材及びケ
ーシングと一体化された矢板を地盤中に打設したのち、
前記ケーシング内又は前記矢板とケーシングとの間に形
成された筒状部にドレーン部材を装入することを特徴と
する地盤の液状防止工法。
2. The sheet pile according to claim 1, wherein the sheet pile integrated with the end face protection member and the casing is driven into the ground,
A method for preventing the liquid of the ground, wherein a drain member is inserted into a tubular portion formed inside the casing or between the sheet pile and the casing.
JP25265295A 1995-09-29 1995-09-29 Soil liquefaction prevention method Expired - Fee Related JP2881637B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP25265295A JP2881637B2 (en) 1995-09-29 1995-09-29 Soil liquefaction prevention method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP25265295A JP2881637B2 (en) 1995-09-29 1995-09-29 Soil liquefaction prevention method

Publications (2)

Publication Number Publication Date
JPH0995932A true JPH0995932A (en) 1997-04-08
JP2881637B2 JP2881637B2 (en) 1999-04-12

Family

ID=17240341

Family Applications (1)

Application Number Title Priority Date Filing Date
JP25265295A Expired - Fee Related JP2881637B2 (en) 1995-09-29 1995-09-29 Soil liquefaction prevention method

Country Status (1)

Country Link
JP (1) JP2881637B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011058285A (en) * 2009-09-11 2011-03-24 Nippon Steel Corp Steel sheet pile retaining wall with water permeable mat, and method of constructing the same
JP2011219987A (en) * 2010-04-09 2011-11-04 Nippon Steel Corp Ground driving member with drainage function and construction method thereof, continuous wall with plug protection components
CN111676959A (en) * 2020-05-22 2020-09-18 中勘冶金勘察设计研究院有限责任公司 Precast pile construction method capable of dissipating foundation soil pore water pressure and preventing pile body from floating upwards

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011058285A (en) * 2009-09-11 2011-03-24 Nippon Steel Corp Steel sheet pile retaining wall with water permeable mat, and method of constructing the same
JP2011219987A (en) * 2010-04-09 2011-11-04 Nippon Steel Corp Ground driving member with drainage function and construction method thereof, continuous wall with plug protection components
CN111676959A (en) * 2020-05-22 2020-09-18 中勘冶金勘察设计研究院有限责任公司 Precast pile construction method capable of dissipating foundation soil pore water pressure and preventing pile body from floating upwards

Also Published As

Publication number Publication date
JP2881637B2 (en) 1999-04-12

Similar Documents

Publication Publication Date Title
JPH0995932A (en) Liquefaction preventing construction method for ground
JP3493218B2 (en) Rehabilitation method of existing sewer and rehabilitation pipe supporting material used for this rehabilitation method
JPH0995933A (en) Liquefaction preventing device for ground
JPH0995934A (en) Liquefaction preventing device for ground
JP3888174B2 (en) Temporary deadline construction method
JP2906333B2 (en) Soil liquefaction prevention device
JP2881640B2 (en) Soil liquefaction prevention method
KR102028393B1 (en) Construction method of reinforcing anchor for corrugated pipe type
KR101974397B1 (en) Structure of reinforcing anchor for corrugated pipe type
JPH1143933A (en) Ground liquefaction preventing construction method and device
JPH10168868A (en) Construction method for preventing liquefaction of ground, and device therefor
JP3496430B2 (en) Soil liquefaction prevention method and device
JP3399327B2 (en) Soil liquefaction prevention method and device
JPS61216914A (en) Method of fitting steel tubular pile with diagonal member or beam
JPH111922A (en) Equipment for preventing ground-liqueffication
JP2801737B2 (en) Infiltration pipes and buried penetration pipes
JP3128456B2 (en) How to attach impermeable walls to gutter pipes
JPS58110713A (en) Coupler of steel plate cell
JPH111921A (en) Equipment for preventing ground-liquefaction
JP2678659B2 (en) Liquefaction countermeasures
JP2584324Y2 (en) Permeation storage tank
JP3991480B2 (en) Construction method for the junction of the sinking box
JP3473379B2 (en) Underground hydraulic method
KR200268494Y1 (en) Pipe Connecting Device of Manhole
KR200328190Y1 (en) End mould for constructing the box type-water conduit

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees