JPH0988353A - Mass constructing method using earth anchor - Google Patents

Mass constructing method using earth anchor

Info

Publication number
JPH0988353A
JPH0988353A JP27719095A JP27719095A JPH0988353A JP H0988353 A JPH0988353 A JP H0988353A JP 27719095 A JP27719095 A JP 27719095A JP 27719095 A JP27719095 A JP 27719095A JP H0988353 A JPH0988353 A JP H0988353A
Authority
JP
Japan
Prior art keywords
underground
building
foundation
existing building
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP27719095A
Other languages
Japanese (ja)
Other versions
JP3457440B2 (en
Inventor
Kazuhiro Inoue
一博 井ノ上
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP27719095A priority Critical patent/JP3457440B2/en
Publication of JPH0988353A publication Critical patent/JPH0988353A/en
Application granted granted Critical
Publication of JP3457440B2 publication Critical patent/JP3457440B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

PROBLEM TO BE SOLVED: To establish reutilization of an underground concrete mass, suppressing the costs to a great extent, and shorten the construction term in dismantling an existing building having center column and replacing with a new building having no center column, by adjusting the stress condition in the underground portion and/or foundation of the existing building by the use of an earth anchor. SOLUTION: By this method according to present invention, an existing building consisting of underground floors and over-ground floor each equipped with center colmns 13, 23 is dismantled, and a building having no center column is to be built anew, wherein an earth anchor is furnished in the foundation part of the underground concrete mass of the existing building in such an a way as mating with the position of the center column 13 to be removed, and the over-ground structural mass 1 is dismantled and removed. Unnecessary center column 13 of the ground floor is removed while the underground mass 1 is left, and over-ground mass 2 having no center column 13 is built anew upon the underground mass 1, and introduction and adjustment of the axial force to each earth anchor are made from during works for the new building till its completion so that the stress shares of different places of the foundation are approached to the condition before the works.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、既存の建物の建替
工事におけるアースアンカーを用いた躯体構築法に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a skeleton construction method using an earth anchor in rebuilding existing buildings.

【0002】[0002]

【従来の技術】最近、建物の建替工事(リニューアル工
事)が増加し、更に大規模化している。また、景気の停
滞とともに、建築業界での価格競争も一段と厳しくなっ
ている。さて、従来のこの種の建替工事では、一般に、
地上部及び地下部の全てを解体した後に新築されてお
り、再利用したとしても、地下外壁の山留利用や既存基
礎杭の再使用に限られているため、地下躯体の面積の減
少、解体工事費の上昇、解体されたコンクリート等の廃
棄物の増大など、多くの問題点があった。
2. Description of the Related Art Recently, the number of building rebuilding works (renewal works) has increased, and the scale has been further increased. In addition, with the economic stagnation, price competition in the construction industry has become more severe. Now, in this kind of conventional rebuilding work, in general,
It is newly built after dismantling all the above-ground and underground parts, and even if it is reused, it is limited to the use of mountain retaining on the outer wall of the underground and the reuse of existing foundation piles, so the area of the underground structure is reduced and dismantled. There were many problems such as an increase in construction costs and an increase in waste such as dismantled concrete.

【0003】一方、傾斜地に構築される建物では、偏土
圧を受ける地下部分に生ずる応力を斜めアースアンカー
で低減させることが提案されている(特開平5-247935号
公報)。この場合、斜めアースアンカーは、地下階部分
に生ずる水平力、特に、地震力によって生ずる水平力の
低減に有効なものである。
On the other hand, in a building constructed on a sloping ground, it has been proposed to reduce the stress generated in the underground portion which is subjected to uneven earth pressure by an oblique earth anchor (Japanese Patent Laid-Open No. 5-247935). In this case, the diagonal earth anchor is effective in reducing the horizontal force generated in the basement, particularly the horizontal force generated by the seismic force.

【0004】[0004]

【発明が解決しようとする課題】ところで、地下階は、
壁も多く、旧耐震設計法の建物でも、地震力に対しては
余力もあり、地下躯体を適宜に残して再利用を図ること
が考えられる。このような地下躯体の再利用には、新築
地上部の柱が既存部の柱配置と適合すれば、構造的な問
題点は少ないが、一般的には、建築計画的に無理な点が
多い。例えば、地上躯体に中柱を配置できないような場
合には、基礎部や柱の応力分担が既存建物と新築時で大
幅に異なってくるため、再利用が困難となる。しかし、
長期応力の処理ができれば、再利用のための技術的な解
決策を立て得る可能性は高い。そこで、本発明は、中柱
を有する既存建物を解体して、中柱を有しない新築建物
に建替えする場合などに、アースアンカーを用いて既存
建物の地下や基礎部の応力状態を調整することにより、
地下躯体の再利用を可能にして、大幅なコストダウンと
工期短縮を図ろうとするものである。
By the way, in the basement,
There are many walls, and even buildings with the old seismic design method have surplus capacity for seismic force, so it is conceivable that the underground structure will be left as appropriate for reuse. There are few structural problems in the reuse of such underground structures if the pillars of the newly built aboveground part are compatible with the pillar layout of the existing part, but in general, there are many points that are impossible in terms of construction planning. . For example, in the case where the middle pillar cannot be placed on the above-ground structure, the stress sharing of the foundation and the pillar is significantly different between the existing building and the new building, which makes reuse difficult. But,
If long-term stress can be dealt with, it is likely that a technical solution for reuse can be created. Therefore, the present invention adjusts the stress state of the underground or foundation of the existing building by using an earth anchor when the existing building having the center pillar is dismantled and is rebuilt to a new building without the center pillar. By
The purpose is to make it possible to reuse the underground structure and to significantly reduce costs and shorten the construction period.

【0005】[0005]

【課題を解決するための手段】請求項1の発明は、既存
の建物を解体して各種構造の建物を新築する建替工事に
おいて、既存建物の地下躯体を再利用し、該地下躯体の
基礎部の適所にアースアンカーを付設して、該アースア
ンカーの軸方向力で地下や基礎部各所の応力分担を建替
前の状態に近づけることを特徴とする。
According to the invention of claim 1, in a rebuilding work for dismantling an existing building to newly construct a building having various structures, the underground structure of the existing building is reused and the foundation of the underground structure is reused. It is characterized in that an earth anchor is attached to an appropriate place of the part, and the axial force of the earth anchor brings the stress sharing of the underground and each part of the foundation close to the state before the rebuilding.

【0006】請求項2の発明は、各階に中柱を有する地
下階と地上階とから成る既存の建物を解体して中柱を有
しない建物を新築する建替工事において、不要の中柱を
撤去して既存建物の地下躯体を再利用に供し、該地下躯
体の基礎部に、撤去した中柱の位置に対応させてアース
アンカーを付設し、該アースアンカーの軸方向力で地下
や基礎部各所の応力分担を建替前の状態に近づけること
を特徴とする。
According to the invention of claim 2, in the rebuilding work for dismantling an existing building consisting of a basement floor and a ground floor having a middle pillar on each floor to newly construct a building without a middle pillar, unnecessary middle pillars are removed. The underground skeleton of the existing building was removed and reused, and the ground anchor was attached to the foundation of the underground skeleton corresponding to the position of the removed middle pillar. The feature is that the stress distribution at each place is brought closer to the state before rebuilding.

【0007】請求項3の発明は、各階に中柱を有する地
下階と地上階とから成る既存の建物を解体して中柱を有
しない建物を新築する建替工事において、既存建物の地
下躯体の基礎部に、撤去予定の中柱の位置に対応させて
アースアンカーを配備させ、地上躯体を解体撤去し、地
下階の不要の中柱を撤去して地下躯体を残し、地下躯体
の上に中柱のない地上躯体を新築し、該新築工事の施工
中から完了時までに前記各アースアンカーに軸方向力の
導入・調整を行って地下や基礎部各所の応力分担を建替
前の状態に近づけることを特徴とする。
The invention according to claim 3 is a substructure of an existing building in a rebuilding work for dismantling an existing building having a basement floor and a ground floor having a middle pillar on each floor and newly building a building having no middle pillar. In the foundation of the, the ground anchor is deployed corresponding to the position of the middle pillar to be removed, the ground structure is dismantled and removed, the unnecessary middle pillar on the basement floor is removed and the underground structure is left, and it is placed on the underground structure. A new ground structure without a center pillar is newly constructed, and axial forces are introduced / adjusted to each of the above-mentioned earth anchors from the time of construction to completion of the new construction work so that stress is shared between the underground and various parts of the foundation before rebuilding. It is characterized by approaching to.

【0008】[0008]

【発明の実施の形態】図面は、請求項1乃至請求項3の
発明に係るアースアンカーを用いた躯体構築法の実施の
形態を示している。図1乃至図5は、下記(1) 乃至 (6)
の施工の手順であり、以下、これを順次に説明する。な
お、図中、Aは、建物の縦断側面を示し、Bは、同地下
躯体の地下一階部の横断平面を示し、B′は、同地下躯
体の地下二階部の横断平面を示している。また、以下の
説明では、鉄骨鉄筋コンクリート造の建物を対象として
いるが、鉄筋コンクリート造その他の建物であってもよ
い。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The drawings show an embodiment of a method for constructing a skeleton using an earth anchor according to the inventions of claims 1 to 3. 1 to 5 show the following (1) to (6)
This is a procedure of construction, and will be described below one by one. In addition, in the figure, A shows the vertical side surface of the building, B shows the transverse plane of the first basement of the underground structure, and B ′ shows the transverse plane of the second basement of the underground structure. . Further, in the following description, a building made of steel-framed reinforced concrete is targeted, but a building made of reinforced concrete or another building may be used.

【0009】(1) 既存建物(図1) 図1は、建替えるべき鉄骨鉄筋コンクリート造の既存建
物を示している。この既存建物は、地下階が2階の地下
躯体1の上に地上階が5階の地上躯体2を築造したもの
であり、各階には、外周壁11,21 に10本の柱(外柱)
12,22 を配設し、また、それぞれの中間部に2本の中柱
13,23 を配設している。なお、地下階、地上階は、上述
の階数に限るものではなく、地下階がない場合でも適用
可能である。(以下同じ)。この場合、既存建物の基礎
部すなわち基礎梁14には、地反力分布b1 が生じ、中柱
13,23 の部分で負となる長期曲げモーメントa1 が加わ
る。なお、上記基礎部は、独立基礎でも連続基礎でもよ
く、上記基礎梁14の他、フーチング、マットスラブ等適
宜である(以下同じ)。
(1) Existing Building (FIG. 1) FIG. 1 shows an existing building of steel reinforced concrete structure to be rebuilt. This existing building is one in which the ground floor 2 with 5 floors above ground is built on the basement 1 with 2 basement floors, and each floor has 10 columns (outer columns) on the outer walls 11 and 21. )
12 and 22 are arranged, and two middle pillars are provided in each middle part.
13,23 are arranged. The basement floor and the ground floor are not limited to the above-mentioned number of floors, and can be applied even when there is no basement floor. (same as below). In this case, the ground reaction force distribution b1 occurs in the foundation of the existing building, that is, the foundation beam 14, and
A long-term bending moment a1 is added, which becomes negative in the part of 13,23. The foundation part may be an independent foundation or a continuous foundation, and other than the foundation beam 14, footing, mat slab, and the like are appropriate (the same applies hereinafter).

【0010】(2) アンカーセット(図2) 地下二階部の各中柱13の両脇で基礎梁14に鉛直方向にア
ースアンカー15をセットする。このアースアンカー15
は、既存のものでよいが、例えば、下端に固定支圧板及
び耐荷体を有し、上端に可動支圧板及び定着くさびを備
えたシース入りアンボンドPC鋼より線を用いる。この
場合、基礎梁14から支持地盤にかけて鉛直な掘削孔を削
孔し、該掘削孔内に注入材を充填し、その直後に当該ア
ースアンカーを挿入して、シース、固定支圧板及び耐荷
体を掘削孔内に定着させる。ただし、ここでは上端の可
動支圧板はフリーの状態におくが、基礎梁14との取り合
いについては、基礎梁又はスラブ上に突出させる状態に
しても、或いは、凹没させる状態にしてもよく、また、
最終的には埋込み状態にしてもよい。
(2) Anchor set (Fig. 2) Ground anchors 15 are set vertically on the foundation beams 14 on both sides of each middle pillar 13 in the second basement. This earth anchor 15
May be an existing one, but for example, a sheathed unbonded PC steel stranded wire having a fixed bearing plate and a load bearing body at the lower end and a movable bearing plate and a fixing wedge at the upper end is used. In this case, a vertical excavation hole is drilled from the foundation beam 14 to the support ground, the injection material is filled in the excavation hole, and immediately after that, the earth anchor is inserted, and the sheath, the fixed bearing plate and the load bearing body are inserted. Establish in the borehole. However, here, the movable support plate at the upper end is left in a free state, but with respect to the engagement with the foundation beam 14, it may be in a state of being projected onto the foundation beam or slab, or may be in a depressed state, Also,
Finally, it may be embedded.

【0011】(3) 解体(図2) 建築計画に基づき、上記既存建物の地上躯体2全体を解
体撤去し、かつ、地下一階部の各中柱13を除去するとと
もに、各壁付き柱12の内側を一部切除して、地下外周壁
11を含む地下躯体1の大半を残す。また、この既存建物
の解体撤去を行いながら、上記アンカー15に張力の一部
を導入し、基礎部等の応力を調整する。
(3) Demolition (Fig. 2) Based on the construction plan, the entire above-ground building 2 of the existing building is demolished and removed, and the middle pillars 13 on the first basement floor are removed and the pillars 12 with walls are also removed. Part of the inner side of the basement is cut off,
Most of underground structure 1 including 11 is left. Further, while the demolishing and removing the existing building, a part of the tension is introduced into the anchor 15 to adjust the stress of the foundation and the like.

【0012】(4) 新築工事(図3) 地下の一部と地上では、既存地下躯体の上に地上5階で
中柱のない地上躯体3を新築する。
(4) New construction work (Fig. 3) On a part of the underground and above ground, a ground structure 3 without a middle pillar is newly constructed on the existing base structure with 5 floors above ground.

【0013】(5) 新築工事完了(図4) 上記地上躯体3の新築工事を完了する。この時点では、
アンカーを用いないと中柱13,23 の部分で最小となる地
反力分布b2 が生じ、基礎梁14には、全体的に正で中柱
13,23 の周辺が最大となる長期曲げモーメントa2 が加
わる。
(5) Completion of new construction (Fig. 4) Completion of new construction of the above-mentioned ground frame 3. At this point,
If anchors are not used, the minimum ground reaction force distribution b2 will occur in the central columns 13 and 23.
A long-term bending moment a2 that maximizes around 13,23 is added.

【0014】(6) アンカー軸方向力導入・調整(図5) 図4の基礎部の応力にならないようにセットした各アー
スアンカー15に軸方向力を導入するとともに、基礎梁14
における長期曲げモーメントa3 が解体前の既存建物の
長期曲げモーメントa1 に近い状態になるよう調整し、
結果として、地反力分布b3 についても解体前の既存建
物の地反力分布b1 と同様にする。つまり、上記アンボ
ンドPC鋼より線では、上端に外部テンションを加え、
該外部テンションを基礎梁14における所要の長期曲げモ
ーメントに対応する適値に調整した後、基礎梁14へとア
ースアンカー15の軸方向力を伝え、基礎梁14に所要の長
期曲げモーメントを生じさせるのである。
(6) Anchor axial force introduction / adjustment (FIG. 5) The axial force is introduced to each earth anchor 15 set so as not to give stress to the foundation portion of FIG.
Adjust so that the long-term bending moment a3 at is close to the long-term bending moment a1 of the existing building before demolition,
As a result, the ground reaction force distribution b3 is the same as the ground reaction force distribution b1 of the existing building before demolition. That is, in the above unbonded PC stranded wire, external tension is applied to the upper end,
After adjusting the external tension to an appropriate value corresponding to the required long-term bending moment in the foundation beam 14, the axial force of the earth anchor 15 is transmitted to the foundation beam 14 to generate the required long-term bending moment in the foundation beam 14. Of.

【0015】[0015]

【発明の効果】請求項1、請求項2及び請求項3の発明
によれば、既存建物の地下躯体を再利用して所要建物を
建替し、その地下躯体の基礎梁の適所にアースアンカー
を付設することで、該アースアンカーの軸方向力により
基礎梁各所の応力分担を建替前の状態に近づけるので、
新築部の柱配置が既存部の柱配置と異なる状況であって
も、地下躯体を建替前の建物と同様の長期応力状態で支
障なく活用できる。したがって、 解体工事を大幅に減少できる。 解体撤去期間を大幅に短縮できる。 解体廃材を大幅に減少できる。 解体撤去費用を大幅に減少できる。 新築工事の工期を大幅に短縮できる。 土工事がなく、安全に施工できる。 新築工事の躯体工事費を大幅に減少できる。 総じて、延べ面積2400平方メートル程度の鉄骨
鉄筋コンクリート造建物で総工費を15〜20パーセン
ト程度低減できる。
According to the inventions of claim 1, claim 2 and claim 3, the underground building of the existing building is reused to reconstruct the required building, and the ground anchor is placed at the proper position of the foundation beam of the underground building. By attaching, the stress sharing of each part of the foundation beam can be made closer to the state before rebuilding by the axial force of the earth anchor,
Even if the pillar layout of the new building is different from the pillar layout of the existing building, the underground structure can be used under the same long-term stress condition as the building before rebuilding without any trouble. Therefore, dismantling work can be significantly reduced. The dismantling and removal period can be greatly shortened. The amount of dismantled waste materials can be greatly reduced. The cost of dismantling and removal can be greatly reduced. The construction period for new construction can be greatly shortened. There is no earthwork and it can be installed safely. The construction cost of new construction can be reduced significantly. Overall, the total construction cost can be reduced by about 15 to 20% in a steel frame reinforced concrete building with a total area of about 2,400 square meters.

【0016】加えて、請求項2及び請求項3の発明によ
れば、各階に中柱を有する既存建物から中柱を有しない
新築建物に建替えする場合、不要の中柱を撤去して既存
建物の地下躯体を再利用に供し、該地下躯体の基礎部
に、撤去した中柱の位置に対応させてアースアンカーを
付設しているので、新築建物に中柱がなくても、該アー
スアンカーにおける軸方向力の導入・調整で地下や基礎
部各所の長期応力の分担を建替前の状態に簡単に近づけ
ることができて、既存建物の地下躯体を支障なく再利用
することができる。
In addition, according to the inventions of claims 2 and 3, when rebuilding an existing building having a middle pillar on each floor to a new building having no middle pillar, the unnecessary middle pillar is removed and the existing building is removed. Since the underground structure of the building is reused and the ground anchor is attached to the foundation of the underground structure so as to correspond to the position of the removed middle pillar, even if the new building does not have the middle pillar, the earth anchor By introducing and adjusting the axial force in, the long-term stress sharing in the underground and various parts of the foundation can be easily approached to the state before rebuilding, and the underground structure of the existing building can be reused without any trouble.

【0017】更に、請求項3の発明によれば、新築工事
の施工中から完了時までに各アースアンカーに軸方向力
の導入・調整を行なうなど、特定の手順としているの
で、手戻り作業を生ずることが少なく、作業を手順よく
スムーズにかつ的確に遂行でき、作業性、品質、安全
性、経済性等を一層向上させることができる。
Further, according to the third aspect of the invention, since a specific procedure is performed such as introducing and adjusting the axial force to each earth anchor from the completion of the new construction to the completion of the new construction, rework work is required. It is possible to perform work smoothly and accurately in a procedural manner with little occurrence, and it is possible to further improve workability, quality, safety, economical efficiency, and the like.

【図面の簡単な説明】[Brief description of drawings]

【図1】 請求項1乃至請求項3の発明のアースアンカ
ーを用いた躯体構築法に係る実施の形態を示す手順(1)
の説明図である。
FIG. 1 is a procedure (1) showing an embodiment relating to a method of constructing a frame using the earth anchor of the invention of claims 1 to 3;
FIG.

【図2】 同手順(2) (3) の説明図である。FIG. 2 is an explanatory diagram of steps (2) and (3).

【図3】 同手順(4) の説明図である。FIG. 3 is an explanatory diagram of the same procedure (4).

【図4】 同手順(5) の説明図である。FIG. 4 is an explanatory diagram of the same procedure (5).

【図5】 同手順(6) の説明図である。FIG. 5 is an explanatory diagram of the same procedure (6).

【符号の説明】 1…地下躯体 2…地上躯体 3…地上躯体 11,21 …外周壁 12,22 …柱 13,23 …中柱 14…基礎梁 15…アースアンカー a1,a2,a3 …長期曲げモーメント b1,b2,b3 …地反力分布[Explanation of symbols] 1 ... Underground structure 2 ... Ground structure 3 ... Ground structure 11,21 ... Outer wall 12,22 ... Pillar 13,23 ... Middle pillar 14 ... Foundation beam 15 ... Earth anchor a1, a2, a3 ... Long-term bending Moment b1, b2, b3 ... Ground reaction force distribution

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 既存の建物を解体して各種構造の建物を
新築する建替工事において、既存建物の地下躯体を再利
用し、該地下躯体の基礎部の適所にアースアンカーを付
設して、該アースアンカーの軸方向力で地下や基礎部各
所の応力分担を建替前の状態に近づけることを特徴とす
るアースアンカーを用いた躯体構築法。
1. In a rebuilding work for dismantling an existing building to newly construct a structure of various structures, the underground structure of the existing building is reused, and an earth anchor is attached to an appropriate place of the foundation of the underground structure, A method for constructing a skeleton using an earth anchor, characterized in that an axial force of the earth anchor causes stress distribution in various parts of the underground or foundation to be close to a state before rebuilding.
【請求項2】 各階に中柱を有する地下階と地上階とか
ら成る既存の建物を解体して中柱を有しない建物を新築
する建替工事において、不要の中柱を撤去して既存建物
の地下躯体を再利用に供し、該地下躯体の基礎部に、撤
去した中柱の位置に対応させてアースアンカーを付設
し、該アースアンカーの軸方向力で地下や基礎部各所の
応力分担を建替前の状態に近づけることを特徴とするア
ースアンカーを用いた躯体構築法。
2. In a rebuilding work for dismantling an existing building consisting of a basement floor and a ground floor having a middle pillar on each floor to newly construct a building without a middle pillar, the unnecessary middle pillar is removed to remove the existing building. The underground skeleton of is used for reuse, the ground anchor is attached to the foundation of the underground skeleton in correspondence with the position of the removed pillar, and the axial force of the earth anchor contributes to the stress sharing of the underground and various parts of the foundation. A structure construction method using an earth anchor, which is characterized by bringing it closer to the state before rebuilding.
【請求項3】 各階に中柱を有する地下階と地上階とか
ら成る既存の建物を解体して中柱を有しない建物を新築
する建替工事において、既存建物の地下躯体の基礎部
に、撤去予定の中柱の位置に対応させてアースアンカー
を配備させ、地上躯体を解体撤去し、地下階の不要の中
柱を撤去して地下躯体を残し、地下躯体の上に中柱のな
い地上躯体を新築し、該新築工事の施工中から完了時ま
でに前記各アースアンカーに軸方向力の導入・調整を行
って地下や基礎部各所の応力分担を建替前の状態に近づ
けることを特徴とするアースアンカーを用いた躯体構築
法。
3. In a rebuilding work for dismantling an existing building consisting of a basement floor and a ground floor having a middle pillar on each floor to newly construct a building without a middle pillar, at the foundation portion of the underground structure of the existing building, A ground anchor is deployed corresponding to the position of the center pillar to be removed, the ground structure is dismantled and removed, unnecessary middle pillars on the basement floor are removed, leaving an underground structure, and there is no center pillar above the base structure. Characterized by newly constructing a skeleton and introducing / adjusting axial force to each of the earth anchors during construction and completion of the new construction work so that the stress distribution in the underground and various parts of the foundation is close to the state before rebuilding. Building method using earth anchors.
JP27719095A 1995-09-28 1995-09-28 Building construction method using earth anchor Expired - Fee Related JP3457440B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP27719095A JP3457440B2 (en) 1995-09-28 1995-09-28 Building construction method using earth anchor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP27719095A JP3457440B2 (en) 1995-09-28 1995-09-28 Building construction method using earth anchor

Publications (2)

Publication Number Publication Date
JPH0988353A true JPH0988353A (en) 1997-03-31
JP3457440B2 JP3457440B2 (en) 2003-10-20

Family

ID=17580068

Family Applications (1)

Application Number Title Priority Date Filing Date
JP27719095A Expired - Fee Related JP3457440B2 (en) 1995-09-28 1995-09-28 Building construction method using earth anchor

Country Status (1)

Country Link
JP (1) JP3457440B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012237111A (en) * 2011-05-10 2012-12-06 Ohbayashi Corp Construction method for base-isolated building, and base-isolated building

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012237111A (en) * 2011-05-10 2012-12-06 Ohbayashi Corp Construction method for base-isolated building, and base-isolated building

Also Published As

Publication number Publication date
JP3457440B2 (en) 2003-10-20

Similar Documents

Publication Publication Date Title
JP5373979B2 (en) Construction Method of Steel Composite Girder Bridge {ConstructionMethod SteelCompositeGirderBridge}
KR20200032316A (en) Method for Forming Top-down-typed Underground Strucutre using Trus-typed Support
JP5854506B2 (en) How to change the basic form of an existing building
JP2001349065A (en) Underground base isolating construction method for existing building
JP3457440B2 (en) Building construction method using earth anchor
JPH11172710A (en) Method for constructing underground part of steel encased reinforced concrete building
JP2980567B2 (en) How to replace the bearing device
JPH09144049A (en) Temporary holding method of construction
JP3053938B2 (en) Double striking method
JPH05179647A (en) Supporting structure for earth retaining wall
JP2004197373A (en) Earthquake resistant reinforcement method of existing concrete container structure and earthquake resistant reinforcement structure
JP7106305B2 (en) Structural columns and seismically isolated buildings
JP2001271499A (en) Temporary bearing construction method for existing building by steel batter brace member
JP3407168B2 (en) Foundation of new building using existing pile foundation
JP6710064B2 (en) Seismic isolation retrofit construction method and building construction
JP7270412B2 (en) Reinforcement structure of masonry building
JP3882536B2 (en) Reconstruction method for existing buildings
JP3755118B2 (en) Cast-in-place reinforced concrete piles resisting drawing and compressive forces and methods of construction
JPH10317486A (en) Bearing structure of floor slab in building structure utilizing pile for column
JPH07150577A (en) Basement building construction method on narrow site
JP5300389B2 (en) Bridge support structure and construction method
JP3353166B2 (en) Method of rebuilding building structure and basic structure used for it
JPH09170340A (en) Base isolation method of existing building and base isolation device therefor
JPH0742179A (en) Modified inversion placing construction method
JP2000291030A (en) Construction method for underground structure

Legal Events

Date Code Title Description
FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080801

Year of fee payment: 5

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090801

Year of fee payment: 6

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100801

Year of fee payment: 7

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110801

Year of fee payment: 8

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120801

Year of fee payment: 9

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130801

Year of fee payment: 10

LAPS Cancellation because of no payment of annual fees