JPH0967572A - Backfilling method for buried item - Google Patents

Backfilling method for buried item

Info

Publication number
JPH0967572A
JPH0967572A JP22766695A JP22766695A JPH0967572A JP H0967572 A JPH0967572 A JP H0967572A JP 22766695 A JP22766695 A JP 22766695A JP 22766695 A JP22766695 A JP 22766695A JP H0967572 A JPH0967572 A JP H0967572A
Authority
JP
Japan
Prior art keywords
layer
water
backfilling
sand
earth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP22766695A
Other languages
Japanese (ja)
Other versions
JP3341541B2 (en
Inventor
Hiroshi Abe
大志 安部
Misao Suzuki
操 鈴木
Hideaki Hoshi
秀明 星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Engineering Corp
Original Assignee
NKK Corp
Nippon Kokan Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NKK Corp, Nippon Kokan Ltd filed Critical NKK Corp
Priority to JP22766695A priority Critical patent/JP3341541B2/en
Publication of JPH0967572A publication Critical patent/JPH0967572A/en
Application granted granted Critical
Publication of JP3341541B2 publication Critical patent/JP3341541B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Soil Conditioners And Soil-Stabilizing Materials (AREA)

Abstract

PROBLEM TO BE SOLVED: To obtain a backfilling method for a buried item which method uses a low-cost liquefied soil of a general formulation and enables the formation of an upper layer (e.g. a roadbed) within 2hr after the deposition of the liquefied soil. SOLUTION: In a method for backfilling a buried item 3 buried or constructed under the ground surface, a liquefied soil layer 1 is deposited so as to enclose the item 3; then a sand layer 2 comprising earth and sand contg. 3-20wt.% hydraulic material is formed on the layer 1; and an upper layer 4 (e.g. a roadbed) is formed on the layer 2.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、例えばガス管や通
信ケーブルなどの地下埋設物の埋戻し工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for backfilling underground objects such as gas pipes and communication cables.

【0002】[0002]

【従来の技術】従来より、地下埋設物を埋戻すときに用
いる埋戻し材としては、多くの場合、別の場所から採取
した良質の山砂などが利用されている。これは地下埋設
物の敷設時に発生する掘削土が埋戻し材に適している場
合が少ないためである。
2. Description of the Related Art Conventionally, as a backfill material used when backfilling an underground buried object, in many cases, good quality sand or the like collected from another place is used. This is because excavated soil generated during the laying of underground buried objects is rarely suitable for backfill materials.

【0003】また、近年、天然資源である良質山砂の枯
渇化、その採取による環境破壊、その運搬による交通公
害および掘削土の処分問題などの観点から、埋戻し材と
して不適な掘削土や建設汚泥およびその他の不良土砂を
有効活用する動きが活発化している。
In recent years, from the viewpoints of depletion of high-quality mountain sand, which is a natural resource, environmental damage due to its extraction, traffic pollution due to its transportation, and disposal problems of excavated soil, excavated soil and construction unsuitable as backfill materials. There is a growing movement to effectively utilize sludge and other bad soil.

【0004】良質の山砂などの埋戻し材を直接用いる従
来の埋戻し工法では、埋戻し後の陥没を防ぐために、埋
戻し材を埋設管周辺部などの狭隘部分にも隙間なく充填
し、ランマによる締め固めを十分に行う必要がある。し
かし、この従来法には、埋戻し材の充填やランマによる
締め固めはすべて人力作業であり、また、騒音や振動を
引き起こすというような問題がある。
In the conventional backfilling method in which a backfill material such as high-quality sand is directly used, the backfill material is filled in a narrow portion such as a peripheral portion of the buried pipe without any gap in order to prevent depression after backfilling. Sufficient compaction with a rammer is required. However, in this conventional method, filling of the backfill material and compaction by a rammer are all manual work, and there is a problem that noise and vibration are caused.

【0005】最近、上記良質の山砂などの特別な埋戻し
材を用いる代わりに、埋設物の敷設時に発生する掘削土
や安価な土砂を利用して、しかも上記のような従来法の
問題点を解決できる流動化埋戻し工法が開発され、一部
実用化されている。この工法は、掘削土や安価な土砂に
水と固化材を混合し、埋戻し材に流動性を持たせ、埋設
管周辺部などの狭隘部分にも隙間なく充填させるととも
に、固化材の作用により地山と同等以上の強度を発現し
ようというものである。
Recently, instead of using a special backfill material such as the above-mentioned high quality mountain sand, excavated soil or cheap earth and sand generated when laying an embedded object is used, and the problems of the conventional method as described above. A fluidized backfilling method that can solve the problem has been developed and is partly in practical use. This method mixes water and solidified material with excavated soil and inexpensive earth and sand, gives the backfill material fluidity, fills narrow spaces around the buried pipe without gaps, and uses the effect of solidified material. It is intended to exhibit strength equal to or higher than that of the ground.

【0006】例えば、特開昭63ー233115号公
報、特開平1ー312118号公報、特開平4ー351
388号公報には、土砂に水と固化材を混合し、流動性
を持たせた流動化土として埋設管などの埋戻しに用いる
工法が開示されている。
[0006] For example, Japanese Patent Laid-Open Nos. 63-233115, 1-312118, and 4-351.
No. 388 discloses a method in which water and a solidifying material are mixed with earth and sand, and the resulting soil is used for backfilling a buried pipe or the like as fluidized soil having fluidity.

【0007】また、特開平3ー287909号公報に
は、掘削土に予め固化材を配合混合し、この処理土を埋
戻し現場へ運搬し、埋戻しつつ処理土に注水するととも
に振動を与えて流動化して、埋戻し箇所の完全な充填を
行う工法が開示されている。
Further, in Japanese Patent Laid-Open No. 3-287909, the excavated soil is mixed with a solidifying material in advance, and the treated soil is transported to the backfill site, and water is poured into the treated soil while backfilling and vibration is applied. A method of fluidizing and completely filling the backfilled portion is disclosed.

【0008】一方、ガス埋設配管工事などがその大部分
を占める都市街路の道路占有工事においては、即日交通
開放の条件下で施工することが余儀なくされており、し
たがって短時間の埋戻し作業が必須となっている。特
に、上記のような流動化埋戻し工法で行う場合は、流動
化土層打設後2時間以内に路床などの上層部の施工が可
能であることが要求されている。
On the other hand, in the road occupancy work on the city streets, which occupies the majority of the gas burial piping work, it is inevitable that the work will be carried out under the condition that the traffic will be opened on the same day. Has become. In particular, when the fluidized backfilling method as described above is used, it is required that the upper layer portion such as the roadbed can be constructed within 2 hours after the fluidized soil layer is cast.

【0009】[0009]

【発明が解決しようとする課題】しかしながら、上記の
特許公報に開示された流動化埋戻し工法では、その固化
時間が4〜5時間と長く、市街地における即日復旧工事
には対応できない。
However, with the fluidization backfilling method disclosed in the above-mentioned patent publication, the solidification time is as long as 4 to 5 hours, and it cannot be applied to the same day restoration work in urban areas.

【0010】流動化土に合わせて特殊な固化材を用いれ
ば、固化時間は短縮されるが、コスト高になるととも
に、早く固化し過ぎるため施工管理が困難になる。
If a special solidifying material is used in accordance with the fluidized soil, the solidifying time can be shortened, but the cost becomes high, and the solidification occurs too quickly, which makes the construction management difficult.

【0011】本発明は、このような課題を解決するため
になされたもので、安価な一般的配合の流動化土を用
い、しかも流動化土層打設後2時間以内で路床などの上
層部の施工が可能な埋設物の埋戻し工法を提供すること
を目的とする。
The present invention has been made in order to solve the above problems, and uses inexpensive general fluidized soil having a general composition, and moreover, within 2 hours after placing the fluidized soil layer, the upper layer of a roadbed or the like. It is an object of the present invention to provide a method for backfilling buried objects that enables construction of parts.

【0012】[0012]

【課題を解決するための手段】上記課題は、地表面下に
埋設または構築された各種埋設物を埋戻す埋戻し工法に
おいて、前記埋設物の周囲に流動化土層を打設後、前記
流動化土層の上に重量比で3〜20%の水硬化性材料を
含む土砂からなる土砂層を設け、前記土砂層の上に路床
などの上層部を施工することを特徴とする埋設物の埋戻
し工法によって解決される。
[Means for Solving the Problems] The above-mentioned problems are, in a backfilling method for backfilling various buried objects buried or constructed below the ground surface, after placing a fluidized soil layer around the buried object, A buried object, characterized in that a sediment layer made of sediment containing 3 to 20% by weight of a water-curable material is provided on a fossil layer, and an upper layer portion such as a roadbed is constructed on the sediment layer. It is solved by the backfilling method.

【0013】水硬化性材料含む土砂からなる土砂層を流
動化土層の上に設けると、層中の水硬化性材料が流動化
土層上層部から毛管現象により吸収された水と反応し硬
化するため、層の強度が高くなる。また、このとき流動
化土層の上層部では、脱水されて密度が増大するため、
流動化土層の上層部自体も強度が高くなる。したがっ
て、流動化土層打設後2時間以内の短時間で路床などの
上層部の施工が可能となる。
When a sediment layer composed of sediment containing a water-curable material is provided on the fluidized soil layer, the water-curable material in the layer reacts with water absorbed from the upper portion of the fluidized soil layer by a capillary phenomenon and hardens. Therefore, the strength of the layer is increased. Also, at this time, the upper part of the fluidized soil layer is dehydrated and the density increases,
The strength of the upper part of the fluidized soil layer itself is also high. Therefore, it is possible to construct an upper layer portion such as a roadbed in a short time within 2 hours after placing the fluidized soil layer.

【0014】流動化土層上に設ける土砂からなる土砂層
に含む水硬化性材料の割合は、水硬化性材料が多過ぎる
と、長期強度が高くなり過ぎ再掘削が困難になり、ま
た、少な過ぎると、強度不足になって路床などの上層部
の早期施工が困難になるため、重量比で3〜20%にす
る必要がある。
If the amount of the water-curable material contained in the earth and sand layer formed on the fluidized soil layer is too much, the long-term strength will be too high and re-drilling will be difficult, and the ratio will be small. If too much, the strength becomes insufficient and early construction of the upper layer portion such as the roadbed becomes difficult. Therefore, it is necessary to set the weight ratio to 3 to 20%.

【0015】水硬化性材料含む土砂からなる土砂層の上
に水を散布すると、土砂層の上層部も短時間に硬化させ
ることができるため、より短時間の埋戻しが可能にな
る。
When water is sprinkled on the earth and sand layer made of earth and sand containing a water-curable material, the upper layer of the earth and sand layer can be hardened in a short time, so that backfilling can be performed in a shorter time.

【0016】水硬化性材料を含む土砂からなる土砂層
を、前記土砂層の上に散水しながら所定の層数設けるこ
とにより、新たな路床の打設は不要になり、その土砂層
上へ直接路盤などの上層部を施工できるので、より短時
間の埋戻しが可能になる。土砂層の層数は、埋設物の設
置条件や土砂、水硬化性材料の種類により、適宜決める
必要がある。
By providing a predetermined number of layers of the earth and sand layer containing the water-curable material on the earth and sand layer while sprinkling the water, it is not necessary to place a new subgrade, Since the upper layer part such as the roadbed can be directly constructed, it is possible to backfill in a shorter time. It is necessary to appropriately determine the number of layers of earth and sand depending on the installation conditions of the buried object, the type of earth and sand, and the water-curable material.

【0017】水硬化性材料として、石膏、早強性のセメ
ントあるいは固化材を用いると、強度発現性が早いの
で、より短時間の埋戻しが可能となる。また、石膏を用
いると、その長期強度が小さいため再掘削が容易とな
る。
When gypsum, an early-strength cement or a solidifying material is used as the water-curable material, the strength develops quickly, so that backfilling can be performed in a shorter time. Further, if gypsum is used, its long-term strength is small, so that re-drilling becomes easy.

【0018】また、水硬化性材料として急結剤を含むセ
メントを用いると、固化速度を著しく速めることができ
るので、大幅な時間短縮が可能となる。
Further, when cement containing a quick-setting agent is used as the water-curable material, the solidification rate can be remarkably increased, so that the time can be remarkably shortened.

【0019】水硬化性材料を含む土砂の含水状態は、水
硬化性材料を混合するとき、水硬化性材料と反応して水
硬化性材料を固化したり、水硬化性材料を凝結させ塊状
にすることのないように、表面乾燥状態以下であること
が望ましい。
The water content of the sand containing the water-curable material is such that when the water-curable material is mixed, it reacts with the water-curable material to solidify the water-curable material or to condense the water-curable material into a lump. In order not to do so, it is desirable that the surface is in a dry state or lower.

【0020】[0020]

【発明の実施の形態】図1に本発明の埋設物の埋戻し工
法の実施の形態を示す。図で、1は流動化土層、2は水
硬化性材料を含む土砂からなる層、3はガス管などの埋
設物、4は路床、5は路盤、6は舗装、7は地表面、8
は土留め用鋼矢板である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS FIG. 1 shows an embodiment of a method for backfilling buried objects according to the present invention. In the figure, 1 is a fluidized soil layer, 2 is a layer made of earth and sand containing a water-curable material, 3 is a buried object such as a gas pipe, 4 is a roadbed, 5 is a roadbed, 6 is pavement, 7 is the ground surface, 8
Is a steel sheet pile for retaining soil.

【0021】水硬化性材料を含む土砂からなる層2に用
いる土砂としては、安価で入手し易い通常の土砂、例え
ば通常の山砂などを用いることができる。また、その含
水状態は、上記のように、粒子間の間隙に水を保持して
ない表面乾燥状態以下であることが望ましいが、この状
態は、通常の土砂の場合、その含水比が3〜4%である
状態に相当する。
As the earth and sand used for the layer 2 made of earth and sand containing a water-curable material, it is possible to use ordinary earth and sand that is inexpensive and easily available, for example, ordinary mountain sand. Further, as described above, it is desirable that the water content state is equal to or lower than the surface dry state in which water is not retained in the gaps between the particles, but in the case of ordinary earth and sand, the water content ratio is 3 to It corresponds to a state of 4%.

【0022】水硬化性材料を含む土砂からなる層2に用
いる水硬化性材料としては、各種セメント、固化材、石
膏、生石灰、フライアッシュ、高炉水砕スラグなどを用
いることができるが、上記のように、石膏、早強性のセ
メントあるいは固化材や急結剤を含むセメントを用いる
ことが好ましい。
Various cements, solidifying materials, gypsum, quick lime, fly ash, granulated blast furnace slag and the like can be used as the water-curable material for the layer 2 made of earth and sand containing the water-curable material. Thus, it is preferable to use gypsum, an early-strength cement or a cement containing a solidifying material or a quick-setting agent.

【0023】水硬化性材料を含む土砂からなる層2の上
に水を散布するとき、散水量は、この層2の短期強度、
長期強度の観点から決定する必要があるが、層2中の水
硬化性材料の含有量、層2の厚さ、層2の吸水速度など
によりその適性水量は変化する。その目安としては、層
2の下層部(毛管現象により流動化土層1より吸水した
部分)を除いた全層に行き渡る水量であることが望まし
い。例えば、早強性セメントを重量比で10%程度混合
した土砂からなる層2を設けた場合、含水比で15%に
なるような水量が必要となる。
When water is sprinkled onto the layer 2 made of earth and sand containing a water-curable material, the sprinkling amount is the short-term strength of this layer 2,
Although it needs to be determined from the viewpoint of long-term strength, the appropriate amount of water changes depending on the content of the water-curable material in the layer 2, the thickness of the layer 2, the water absorption speed of the layer 2, and the like. As a guideline, it is desirable that the amount of water permeates all the layers except the lower layer portion of the layer 2 (the portion that absorbs water from the fluidized soil layer 1 due to the capillary phenomenon). For example, when the layer 2 made of earth and sand mixed with early-strength cement at a weight ratio of about 10% is provided, the water content is required to be 15% at a water content ratio.

【0024】水硬化性材料を含む土砂からなる層2の厚
さは、この層2の短期強度、長期強度の観点から決定す
る必要があるが、層2中の水硬化性材料の含有量や散水
量などによりその適性厚さは変化する。
The thickness of the layer 2 made of earth and sand containing a water-curable material needs to be determined from the viewpoint of the short-term strength and long-term strength of the layer 2, but the content of the water-curable material in the layer 2 and The appropriate thickness changes depending on the amount of water sprayed.

【0025】[0025]

【実施例】【Example】

(実施例1)地表面下にガス管を配設後、ガス管周囲に
表1に示す流動化土からなる流動化土層を打設後、流動
化土層の強度がコーン指数で0.01kgf/cm2
なったところで、重量比で8%の超早強性セメントを含
む含水比3%の空気乾燥状態の山砂からなる厚さ約20
0mmの水硬化性材料を含む土砂層を配設した。その
後、この水硬化性材料を含む土砂層の強度がコーン指数
で1.0kgf/cm2となったところで、路床材であ
る山砂を投入し、ランマにて締め固め、さらにその上に
舗装を構築した。このとき、流動化土層の打設終了から
路床材投入までの時間は1時間20分であり、従来法に
比べ、3時間以上短縮できた。また、3カ月後の水硬化
性材料を含む土砂層の1軸圧縮強度は2.5kgf/c
2 であり、スコップによる再掘削が可能な強度であっ
た。なお、山砂は空気中に放置乾燥させ、水硬化性材料
を混合させるとき流動化土製造用ミキサーを用いたた
め、製造コストを最小限に抑えることができた。
(Example 1) After arranging a gas pipe below the surface of the earth, after placing a fluidized soil layer made of fluidized soil shown in Table 1 around the gas pipe, the strength of the fluidized soil layer was 0. At a pressure of 01 kgf / cm 2 , a thickness of about 20% composed of air-dried mountain sand containing 8% by weight of ultra early-strength cement and a water content of 3%.
A layer of earth and sand containing 0 mm of hydraulic material was placed. After that, when the strength of the earth and sand layer containing this water-curable material reached 1.0 kgf / cm 2 in terms of cone index, mountain sand, which is the roadbed material, was added, compacted with a rammer, and paved on top of it. Was built. At this time, the time from the completion of the pouring of the fluidized soil layer to the introduction of the roadbed material was 1 hour and 20 minutes, which was shorter than the conventional method by 3 hours or more. Moreover, the uniaxial compressive strength of the sediment layer containing the water-curable material after 3 months is 2.5 kgf / c.
It was m 2 , and the strength was such that re-drilling with a scoop was possible. In addition, since the sand was left to dry in the air and the mixer for fluidized soil production was used when mixing the water-curable material, the production cost could be minimized.

【0026】(実施例2)地表面下にガス管を配設後、
ガス管周囲に表1に示す流動化土からなる流動化土層を
打設後、流動化土層の強度がコーン指数で0.01kg
f/cm2 となったところで、重量比で20%の半水石
膏を含む含水比5%の空気乾燥させた山砂からなる厚さ
約200mmの水硬化性材料を含む土砂層を配設した。
その後、この水硬化性材料を含む土砂層の上に、この土
砂層の含水比が15%になるように散水した。水硬化性
材料を含む土砂層の強度がコーン指数で1.0kgf/
cm 2 となったところで、路床材である山砂を投入し、
ランマにて締め固め、さらにその上に舗装を構築した。
このとき、流動化土層の打設終了から路床材投入までの
時間は1時間10分であった。また、3カ月後の水硬化
性材料を含む土砂層の1軸圧縮強度は2.0kgf/c
2 であり、スコップによる再掘削が可能な強度であっ
た。なお、山砂は空気中に放置乾燥させ、水硬化性材料
を混合させるとき流動化土製造用ミキサーを用いたた
め、製造コストを最小限に抑えることができた。
(Example 2) After arranging a gas pipe under the ground surface,
A fluidized soil layer consisting of fluidized soil shown in Table 1 was placed around the gas pipe.
After pouring, the strength of the fluidized soil layer is 0.01 kg in terms of cone index.
f / cm2When it became, 20% by weight of hemihydrate
Thickness of air-dried mountain sand containing 5% of water
A layer of earth and sand containing approximately 200 mm of water-curable material was placed.
Then place this soil on top of the layer of sediment containing this water-curable material.
Water was sprinkled so that the water content of the sand layer was 15%. Water hardening
The strength of the soil layer containing the material is 1.0 kgf /
cm 2At that point, throw in the mountain sand that is the roadbed material,
It was compacted with a rammer and pavement was built on it.
At this time, from the completion of pouring the fluidized soil layer to the introduction of roadbed material
The time was 1 hour and 10 minutes. Water hardening after 3 months
Uniaxial compressive strength of soil layer containing elastic material is 2.0kgf / c
m2And the strength is such that it can be re-drilled with a scoop.
Was. It should be noted that mountain sand is left to dry in the air and a water-curable material is used.
A fluidized soil production mixer was used when mixing
Therefore, the manufacturing cost could be minimized.

【0027】(実施例3)地表面下にガス管を配設後、
ガス管周囲に表1に示す流動化土からなる流動化土層を
打設後、流動化土層の強度がコーン指数で0.01kg
f/cm2 となったところで、重量比で20%の半水石
膏を含む含水比3%の空気乾燥状態の山砂からなる厚さ
約300mmの水硬化性材料を含む土砂層を配設した。
その後、この水硬化性材料を含む土砂層の上に、この土
砂層の含水比が15%とになるように散水した。水硬化
性材料を含む土砂層の強度がコーン指数で0.7kgf
/cm2 となったところで、路床材である山砂を投入
し、ランマにて締め固め、さらにその上に舗装を構築し
た。このとき、流動化土層の打設終了から路床材投入ま
での時間は1時間10分であった。また、3カ月後の水
硬化性材料を含む土砂層の1軸圧縮強度は2.0kgf
/cm2 であり、スコップによる再掘削が可能な強度で
あった。なお、山砂と石膏の混合を山砂を乾燥させると
きに行って、現地へ搬入したので、現場での作業を軽減
できた。
(Example 3) After arranging a gas pipe below the ground surface,
After placing the fluidized soil layer consisting of fluidized soil shown in Table 1 around the gas pipe, the strength of the fluidized soil layer is 0.01 kg in terms of cone index.
When f / cm 2 was reached, an earth and sand layer containing a water-curable material having a thickness of about 300 mm made of air-dried mountain sand containing 20% hemihydrate gypsum by weight and a water content of 3% was provided. .
Then, water was sprinkled onto the earth and sand layer containing the water-curable material so that the water content ratio of the earth and sand layer was 15%. The strength of the soil layer containing the water-curable material is 0.7 kgf in cone index
When it reached / cm 2 , the mountain sand, which is the roadbed material, was put in, compacted with a rammer, and pavement was constructed on it. At this time, the time from the completion of the pouring of the fluidized soil layer to the introduction of the roadbed material was 1 hour and 10 minutes. Moreover, the uniaxial compressive strength of the earth and sand layer containing the water-curable material after 3 months is 2.0 kgf.
/ Cm 2 , and the strength was such that re-drilling with a scoop was possible. It should be noted that the sand and gypsum were mixed when the sand was dried and carried into the site, so the work on site could be reduced.

【0028】(実施例4)地表面下にガス管を配設後、
ガス管周囲に表1に示す流動化土からなる流動化土層を
打設後、流動化土層の強度がコーン指数で0.01kg
f/cm2 となったところで、重量比で10%の急結剤
(ポゾリス製QPー55)を含む普通ポルトランドセメ
ントを重量比で5%含む含水比2%の空気乾燥状態の山
砂からなる厚さ約250mmの水硬化性材料を含む土砂
層を配設した。この土砂層の含水比が15%とになるよ
うに散水した。水硬化性材料を含む土砂層の強度がコー
ン指数で1.5kgf/cm2 となったところで、路床
材である山砂を投入し、ランマにて締め固め、さらにそ
の上に舗装を構築した。このとき、流動化土層の打設終
了から路床材投入までの時間は50分であった。また、
3カ月後の水硬化性材料を含む土砂層の1軸圧縮強度は
1.5kgf/cm2 であり、スコップによる再掘削が
可能な強度であった。なお、山砂と普通ポルトランドセ
メントおよび急結剤の混合を山砂を乾燥させるときに行
って、現地へ搬入したので、現場での作業を軽減でき
た。
(Embodiment 4) After disposing a gas pipe below the ground surface,
After placing the fluidized soil layer consisting of fluidized soil shown in Table 1 around the gas pipe, the strength of the fluidized soil layer is 0.01 kg in terms of cone index.
When f / cm 2 was reached, it consisted of 5% by weight of ordinary Portland cement containing 10% by weight of a quick-setting agent (QP-55 made by Pozzolis) and 2% by weight of air-dried mountain sand. An earth and sand layer containing a water-curable material having a thickness of about 250 mm was arranged. Water was sprinkled so that the water content ratio of this sediment layer was 15%. When the strength of the soil layer containing the water-curable material reached a cone index of 1.5 kgf / cm 2 , mountain sand, which is the roadbed material, was added, compacted with a rammer, and pavement was constructed on it. . At this time, the time from the completion of the pouring of the fluidized soil layer to the introduction of the roadbed material was 50 minutes. Also,
The uniaxial compressive strength of the earth and sand layer containing the water-curable material after 3 months was 1.5 kgf / cm 2 , and the strength was such that re-excavation with a scoop was possible. It should be noted that the sand, the ordinary Portland cement and the quick-setting admixture were mixed when the sand was dried and carried into the site, so the work on the site could be reduced.

【0029】(実施例5)地表面下にガス管を配設後、
ガス管周囲に表1に示す流動化土からなる流動化土層を
打設後、流動化土層の強度がコーン指数で0.01kg
f/cm2 となったところで、重量比で4%の早強性セ
メントを含む含水比2%の空気乾燥状態の山砂からなる
厚さ約200mmの水硬化性材料を含む土砂層を配設し
た。この土砂層の含水比が15%とになるように散水し
た。この土砂層と散水をくりかえして路床を構築し、路
盤などの上層部を施工した。このとき、流動化土層の打
設終了から路盤などの上層部施工開始までの時間は1時
間30分であった。また、3カ月後の水硬化性材料を含
む土砂層の1軸圧縮強度は2.0kgf/cm2 であ
り、スコップによる再掘削が可能な強度であった。な
お、山砂と早強性セメントの混合を山砂を乾燥させると
きに行って、現地へ搬入したので、現場での作業を軽減
できた。
(Example 5) After arranging a gas pipe under the ground surface,
After placing the fluidized soil layer consisting of fluidized soil shown in Table 1 around the gas pipe, the strength of the fluidized soil layer is 0.01 kg in terms of cone index.
When f / cm 2 was reached, a sand layer containing a water-curable material with a thickness of about 200 mm made of air-dried mountain sand containing 4% by weight of early-strength cement and a water content of 2% was provided. did. Water was sprinkled so that the water content ratio of this sediment layer was 15%. This earth and sand layer and watering were repeated to construct a subgrade, and the upper layer part such as the subbase was constructed. At this time, the time from the completion of placing the fluidized soil layer to the start of construction of the upper layer portion such as the roadbed was 1 hour and 30 minutes. In addition, the uniaxial compressive strength of the earth and sand layer containing the water-curable material after 3 months was 2.0 kgf / cm 2 , and the strength was such that re-excavation with a scoop was possible. In addition, since the sand and the early-strength cement were mixed when the sand was dried and brought into the field, the work on the site could be reduced.

【0030】[0030]

【表1】 [Table 1]

【0031】[0031]

【発明の効果】本発明は以上説明したように構成されて
いるので、安価な一般的配合の流動化土を用い、しかも
流動化土層打設後2時間以内で路床などの上層部の施工
が可能な埋設物の埋戻し工法を提供することができる。
EFFECTS OF THE INVENTION Since the present invention is configured as described above, fluidized soil of an inexpensive general composition is used, and the upper layer portion of the roadbed or the like is used within 2 hours after the fluidized soil layer is cast. It is possible to provide a method of backfilling a buried object that can be constructed.

【0032】また、本発明である埋戻し工法を用いれ
ば、流動化土層全体が完全に固化する前に、埋戻し工事
を完了できるため、土留め用鋼矢板の引抜きが容易に行
え、しかも鋼矢板の引抜き後に、流動化土層と地山との
間には空隙が生じることがないので、地盤低下も全く発
生しない。
Further, by using the backfilling method of the present invention, the backfilling work can be completed before the entire fluidized soil layer is completely solidified, so that the steel sheet pile for retaining soil can be easily pulled out, and After drawing the steel sheet pile, there is no gap between the fluidized soil layer and the ground, so no ground deterioration occurs.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の埋設物の埋戻し工法の実施の形態を示
す図である。
FIG. 1 is a view showing an embodiment of a method for backfilling a buried object according to the present invention.

【符号の説明】[Explanation of symbols]

1 流動化土層 2 水硬化性材料を含む土砂からなる土砂層 3 ガス管などの埋設物 4 路床 5 路盤 6 舗装 7 地表面 8 土留め用鋼矢板 1 Fluidized soil layer 2 Sediment layer consisting of sediment containing water-curable material 3 Buried objects such as gas pipe 4 Roadbed 5 Roadbed 6 Pavement 7 Ground surface 8 Steel sheet pile for retaining soil

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 地表面下に埋設または構築された各種埋
設物を埋戻す埋戻し工法において、前記埋設物の周囲に
流動化土層を打設後、前記流動化土層の上に重量比で3
〜20%の水硬化性材料を含む土砂からなる土砂層を設
け、前記土砂層の上に路床などの上層部を施工すること
を特徴とする埋設物の埋戻し工法。
1. In a backfilling method for backfilling various buried objects buried or constructed under the surface of the earth, a fluidized soil layer is cast around the buried object, and then a weight ratio is applied on the fluidized soil layer. In 3
A method for backfilling a buried object, comprising: providing a sediment layer made of sediment containing 20% of a water-curable material, and constructing an upper layer portion such as a roadbed on the sediment layer.
【請求項2】 前記土砂層を配設後、前記土砂層の上に
水を散布することを特徴とする請求項1に記載の埋設物
の埋戻し工法。
2. The backfilling method for the buried object according to claim 1, wherein after the earth and sand layer is provided, water is sprayed on the earth and sand layer.
【請求項3】 地表面下に埋設または構築された各種埋
設物を埋戻す埋戻し工法において、前記埋設物の周囲に
流動化土層を打設後、前記流動化土層の上に重量比で3
〜20%の水硬化性材料を含む土砂からなる土砂層を、
前記土砂層の上に散水しながら所定の層数設け、路盤な
どの上層部を施工することを特徴とする埋設物の埋戻し
工法。
3. A backfilling method for backfilling various buried objects buried or constructed under the surface of the earth, in which a fluidized soil layer is cast around the buried object and then a weight ratio is applied on the fluidized soil layer. In 3
A sediment layer consisting of sediment containing ~ 20% water-curable material,
A method for backfilling a buried object, wherein a predetermined number of layers are provided on the earth and sand layer while water is sprinkled, and an upper layer portion such as a roadbed is constructed.
【請求項4】 前記水硬化性材料が、石膏、早強性のセ
メントあるいは固化材であることを特徴とする請求項1
から請求項3のいずれか1項に記載の埋設物の埋戻し工
法。
4. The water-curable material is gypsum, a fast-setting cement or a solidifying material.
4. The method for backfilling the buried object according to any one of claims 3 to 4.
【請求項5】 前記水硬化性材料が、急結剤を含むセメ
ントであることを特徴とする請求項1から請求項3のい
ずれか1項に記載の埋設物の埋戻し工法。
5. The method for backfilling a buried object according to claim 1, wherein the water-curable material is a cement containing a quick-setting agent.
【請求項6】 前記水硬化性材料を含む土砂の含水状態
が表面乾燥状態以下であることを特徴とする請求項1か
ら請求項5のいずれか1項に記載の埋設物の埋戻し工
法。
6. The backfilling method for a buried object according to claim 1, wherein the water content of the sand containing the water-curable material is not more than the surface dry state.
JP22766695A 1995-09-05 1995-09-05 Backfilling method for buried objects Expired - Fee Related JP3341541B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP22766695A JP3341541B2 (en) 1995-09-05 1995-09-05 Backfilling method for buried objects

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP22766695A JP3341541B2 (en) 1995-09-05 1995-09-05 Backfilling method for buried objects

Publications (2)

Publication Number Publication Date
JPH0967572A true JPH0967572A (en) 1997-03-11
JP3341541B2 JP3341541B2 (en) 2002-11-05

Family

ID=16864434

Family Applications (1)

Application Number Title Priority Date Filing Date
JP22766695A Expired - Fee Related JP3341541B2 (en) 1995-09-05 1995-09-05 Backfilling method for buried objects

Country Status (1)

Country Link
JP (1) JP3341541B2 (en)

Also Published As

Publication number Publication date
JP3341541B2 (en) 2002-11-05

Similar Documents

Publication Publication Date Title
JPH10140507A (en) Fluidization treatment method
CN111908853A (en) Self-compacting soil, preparation method thereof and construction method for backfilling municipal cavity
JPH06344328A (en) Fast-curing fluidized threaded soil and rapid construction of roadbed/road body using the same
JP3341541B2 (en) Backfilling method for buried objects
JPH10227003A (en) Construction of base course
JP3552302B2 (en) Solidified material for fluidized backfill method
JP3230147B2 (en) Fluidized soil construction structure and its construction method
JP4112667B2 (en) Solidification material for fluidization backfill
JPH0995949A (en) Back filling construction method for buried pipe
JP2503771B2 (en) Solidifying material for cohesive soil of volcanic ash
JP4743679B2 (en) Water-improving soil-improving solidified material, method for producing water-improving improved soil, and water-sealing
JPH0932969A (en) Back filling method for buried object
JPH0790272A (en) Super-plasticizable back-filling material and back-filling process
JP4020997B2 (en) Cement admixture and soil solidifier for soil solidification
JPH0913357A (en) Backfill method of buried article
JP3599303B2 (en) Light earth method
JPH10195853A (en) Backfilling construction method of buried object
JP3769521B2 (en) Civil engineering groundwork, civil engineering methods using this civil engineering groundwork
JPH0967573A (en) Backfilling method for buried item
JP3158900B2 (en) Construction method of structures such as waterways
JPH0987622A (en) Solidifying material for fluidized backfilling soil and fluidized backfilling soil
JPH04306315A (en) Backfilling construction
JP2001354960A (en) Method for utilizing construction surplus soil
KR100378035B1 (en) Method of restoration about digging of paved road
JPH09235151A (en) Buried material backfill material and buried material backfilling engineering method

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20020723

LAPS Cancellation because of no payment of annual fees