JPH09310589A - Method and equipment for moving form - Google Patents

Method and equipment for moving form

Info

Publication number
JPH09310589A
JPH09310589A JP8126077A JP12607796A JPH09310589A JP H09310589 A JPH09310589 A JP H09310589A JP 8126077 A JP8126077 A JP 8126077A JP 12607796 A JP12607796 A JP 12607796A JP H09310589 A JPH09310589 A JP H09310589A
Authority
JP
Japan
Prior art keywords
formwork
moving
mold
support beam
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP8126077A
Other languages
Japanese (ja)
Inventor
Shigeru Okada
滋 岡田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP8126077A priority Critical patent/JPH09310589A/en
Publication of JPH09310589A publication Critical patent/JPH09310589A/en
Pending legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

PROBLEM TO BE SOLVED: To improve the efficiency of the movement of forms, to shorten the term of works and to reduce construction cost. SOLUTION: When a form device 20 is moved forward, a pair of two rails 50, 50 are laid on an executing base G in front by a rail hanger 52 installed at the front end section of a form support beam 22 while a pair of two transfer trucks 45, 46 are mounted at the front and the rear of the form support beam 22. The form support beam 22 is shifted forward by making these transfer tracks 45, 46 travel along the upper sections of the rails 50, 50, the diameter of a form unit 21 is shrunk, the form unit 21 is moved forward along the form support beam 22 by a drive mechanism (not shown), and the diameter of the form unit 21 is expanded.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、例えば地下導水路
やトンネル等の地中構造物を構築するための型枠を施工
方向前方に移動させるに際して用いて好適な型枠の移動
方法および型枠の移動装置に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of moving a formwork and a formwork suitable for use in moving a formwork for constructing an underground structure such as an underground canal or a tunnel forward in the construction direction. Mobile device of the present invention.

【0002】[0002]

【従来の技術】地下導水路やトンネル等の地下構造物の
うち、地表面下の比較的浅い位置に設けられる地中構造
物の施工方法としては、地盤を地表面から溝状に掘り下
げ、その底部に上記構造物を形成した後に地盤を埋め戻
す、といういわゆるオープンカット工法が最も一般的に
採用されている。この工法において、溝の底部で地中構
造物を形成するには、地中構造物の内周面を形成するた
めの型枠を、該構造物が連続する方向において一定長に
わたって組み立て、コンクリートを打設し、これが硬化
した後に型枠を解体している。この後は、当該地中構造
物の施工方向前方に前記型枠を盛り替え、前記と同様に
して型枠の組立・解体を行うことを繰り返して、地中構
造物を所定長にわたって形成している。ところが、この
ような工法では、型枠の組立および解体作業がいずれも
現場での手作業で行われるので作業性が悪く、このこと
が工期短縮や工費削減を妨げていた。
2. Description of the Related Art Among underground structures such as underground conduits and tunnels, as a method of constructing an underground structure that is provided at a relatively shallow position below the ground surface, the ground is dug down from the ground surface The so-called open-cut construction method of filling the ground after forming the structure on the bottom is most commonly used. In this method, in order to form an underground structure at the bottom of a groove, a formwork for forming the inner peripheral surface of the underground structure is assembled over a certain length in the continuous direction of the structure, and concrete is formed. After casting, the mold is dismantled after it has hardened. After this, the formwork is rearranged forward in the construction direction of the underground structure, and assembling and disassembling the formwork is repeated in the same manner as above to form the underground structure over a predetermined length. There is. However, in such a construction method, the assembling and disassembling work of the formwork are both performed manually at the site, so the workability is poor, which hinders the reduction of the construction period and the reduction of the construction cost.

【0003】このような問題の解決を図るための手段の
一つとして、ニードルビーム式のスチール型枠を用いた
工法がある。この工法は、図8に示すような型枠装置1
を用いる。この型枠装置1は、筒状の型枠本体2と、型
枠本体2の軸線と平行に配置された型枠支持ビーム3と
から概略構成されている。図9に示すように、型枠本体
2は、周方向に複数のユニットに分割されて、底部型枠
2Aと、側部型枠2B,2Bと、上部型枠2Cとから構
成されている。このうち、上部型枠2Cはさらに二分割
されて、その両端部において内方に折り畳むことができ
る構成とされている。そして、この型枠本体2は、上部
型枠2Cを折り畳み、底部型枠2Aおよび側部型枠2
B,2Bを断面方向内方に引き込むことによって、全体
として縮径できるようになっている。また、図8に示し
た型枠支持ビーム3には、型枠本体2を型枠支持ビーム
3が連続する方向に沿って進退移動させる駆動機構(図
示なし)が備えられている。
As one of means for solving such a problem, there is a construction method using a needle beam type steel frame. This method is used in the formwork apparatus 1 as shown in FIG.
Is used. The formwork apparatus 1 is roughly composed of a cylindrical formwork body 2 and a formwork support beam 3 arranged in parallel with the axis of the formwork body 2. As shown in FIG. 9, the formwork main body 2 is divided into a plurality of units in the circumferential direction, and includes a bottom formwork 2A, side formworks 2B and 2B, and an upper formwork 2C. Of these, the upper frame 2C is further divided into two parts, and both ends thereof can be folded inward. Then, in the mold body 2, the upper mold 2C is folded to form the bottom mold 2A and the side mold 2
By drawing B and 2B inward in the cross-sectional direction, the diameter can be reduced as a whole. The form supporting beam 3 shown in FIG. 8 is provided with a drive mechanism (not shown) for moving the form main body 2 forward and backward along the direction in which the form supporting beam 3 continues.

【0004】このような型枠装置1を用いて地中構造物
4を形成するには、まず、型枠装置1の施工方向前方側
において、地中構造物4を構成する鉄筋を先組みする。
続いて、型枠本体2を縮径させておき、これを型枠支持
ビーム3に沿って前進させて先組みした鉄筋の内方に移
動させた後、型枠本体2を拡径する。そして、型枠2の
外周側にコンクリートCを打設し、これが硬化すること
によって、この区間の地中構造物4が形成される。この
後は、前記と同様にして、鉄筋の先組、型枠装置1の前
進、コンクリートCの打設・養生を繰り返すことによっ
て、地中構造物4を延長構築していくようになってい
る。
In order to form the underground structure 4 by using such a formwork device 1, first, the reinforcing bars constituting the underground structure 4 are first assembled on the front side in the construction direction of the formwork device 1. .
Then, the diameter of the mold body 2 is reduced, the mold body 2 is advanced along the mold support beam 3 to move inwardly of the pre-assembled rebar, and then the diameter of the mold body 2 is expanded. Then, concrete C is cast on the outer peripheral side of the mold 2 and is hardened, whereby the underground structure 4 in this section is formed. After that, in the same manner as described above, the underground structure 4 is extendedly constructed by repeating the front assembly of the reinforcing bars, the advance of the formwork device 1, and the placing and curing of concrete C. .

【0005】上記型枠装置1の前進に際しては、まず、
駆動機構(図示なし)を作動させることによって型枠支
持ビーム3のみを前進させた後、型枠支持ビーム3の前
後に備えた脚5、6を前方の施工底面Gおよび後方の地
中構造物4の底部4a上に立脚させる。続いて、型枠本
体2を縮径させた後に、この型枠本体2を駆動機構(図
示なし)で型枠支持ビーム3に沿って前進させ、この後
に型枠本体2を拡径させるようにしている。なお、型枠
本体2周囲へのコンクリートCの打設・養生が完了した
状態で型枠支持ビーム3の前進を行う場合には、型枠本
体2を拡径させた状態で周囲に形成した地中構造物4に
反力を得て型枠支持ビーム3を前進させるようにしてい
る。一方、型枠本体2周囲へのコンクリートCの打設・
養生が完了していない状態で型枠支持ビーム3の前進を
行う場合には、図10に示すように、上面が型枠本体2
の外形に沿った形状の受け台7を施工底面G上に設置
し、この受け台7上で型枠本体2を仮受けするようにす
る。
In advancing the formwork apparatus 1, first of all,
After advancing only the formwork support beam 3 by operating a drive mechanism (not shown), the legs 5 and 6 provided in front of and behind the formwork support beam 3 are installed on the front construction bottom surface G and the rear underground structure. 4 is made to stand on the bottom part 4a. Then, after the diameter of the mold body 2 is reduced, the mold body 2 is advanced by a drive mechanism (not shown) along the mold support beam 3, and then the diameter of the mold body 2 is expanded. ing. In addition, when advancing the mold support beam 3 in a state where the casting and curing of the concrete C around the form main body 2 is completed, the form formed around the form main body 2 is expanded. A reaction force is obtained from the intermediate structure 4 to move the form supporting beam 3 forward. On the other hand, placing concrete C around the form body 2
When the form supporting beam 3 is advanced while the curing is not completed, as shown in FIG.
The pedestal 7 having a shape conforming to the outer shape of the above is installed on the construction bottom surface G, and the formwork main body 2 is temporarily received on the pedestal 7.

【0006】[0006]

【発明が解決しようとする課題】しかしながら、上述し
たような従来の型枠の移動方法には、以下のような問題
が存在する。まず、型枠本体2周囲へのコンクリートC
の打設・養生が完了した状態で型枠支持ビーム3の前進
を行う場合には、コンクリートCの硬化が完了した後で
ないと型枠装置1の前進作業を行うことができないた
め、工期短縮の妨げとなり、これが工費削減の妨げとも
なっていた。また、型枠本体2周囲へのコンクリートC
の打設・養生が完了していない状態で受け台7を用いて
型枠支持ビーム3の前進を行う場合には、上記に比較し
て工期の短縮化を図ることが可能となるものの、受け台
7を別途準備しなければならないのでコストがかかるだ
けでなく、この受け台7を順次前方に盛り替えていかな
ければならず、依然として工期短縮、工費削減の余地が
あった。本発明は、以上のような点を考慮してなされた
もので、型枠の移動の効率化を図り、工期短縮および工
費削減を図ることのできる型枠の移動方法および型枠の
移動装置を提供することを課題とする。
However, the conventional method of moving a mold as described above has the following problems. First, concrete C around the formwork body 2
When the formwork support beam 3 is advanced with the casting and curing of the formwork completed, the advancement work of the formwork device 1 can be performed only after the hardening of the concrete C is completed, so that the construction period can be shortened. It was an obstacle, and this also hindered the reduction of construction costs. In addition, concrete C around the formwork body 2
When the form support beam 3 is advanced using the cradle 7 in a state in which the casting and curing of No. 1 have not been completed, the construction period can be shortened compared to the above, but Not only is it costly because the stand 7 must be prepared separately, but also the receiving stand 7 has to be rearranged in order forward, and there is still room for shortening the construction period and reducing the construction cost. The present invention has been made in consideration of the above points, and provides a mold moving method and a mold moving device capable of improving the efficiency of mold movement, shortening the construction period, and reducing the construction cost. The challenge is to provide.

【0007】[0007]

【課題を解決するための手段】請求項1に係る発明は、
一方向に連続する鉄筋コンクリート造の筒状の地中構造
物の内壁を形成するための型枠が、その周方向の一部が
内方に折り畳み可能とされて、他の部分が縮径可能な構
成とされた型枠本体と、該型枠本体の内方に配設され
て、前記型枠本体をその軸線方向に移動自在に支持する
型枠支持梁と、該型枠支持梁に沿って前記型枠本体を移
動させる駆動機構とから構成され、該型枠を施工方向前
方に搬送するに際しては、前方の施工底面上に該型枠の
移動方向に沿って延在する2本一対のレールを敷設する
とともに、前記型枠支持梁の前後に2基一対の移動台車
を取り付けておき、これら移動台車を前記レール上に沿
って走行させることによって前記型枠支持梁を前方に移
動させた後、前記型枠本体を縮径させて、前記駆動機構
によって前記型枠支持梁に沿って前方に移動させた後に
拡径することを特徴としている。
The invention according to claim 1 is
A formwork for forming the inner wall of a tubular underground structure made of reinforced concrete that is continuous in one direction, part of its circumferential direction can be folded inward, and the other part can be reduced in diameter A mold main body having a structure, a mold support beam disposed inside the mold main body and movably supporting the mold main body in the axial direction thereof, and along the mold support beam A pair of two rails that are configured by a drive mechanism that moves the mold body, and that, when the mold is conveyed forward in the construction direction, extend on the construction bottom surface in the front along the movement direction of the mold. After laying, and attaching a pair of two moving carriages before and after the form supporting beam, and moving these moving carriages along the rails to move the form supporting beam forward. , The diameter of the mold body is reduced, and the mold support is performed by the drive mechanism. It is characterized in that the diameter increases after moving forward along the beam.

【0008】請求項2に係る発明は、請求項1記載の型
枠の移動方法において、前記型枠支持梁の前部に前記レ
ールを吊り込むためのレール吊り込み部材を備えてお
き、該レール吊り込み部材を用いて前記レールを施工底
面上に敷設していくことを特徴としている。
According to a second aspect of the present invention, in the method for moving the formwork according to the first aspect, a rail suspending member for suspending the rail is provided in front of the formwork supporting beam, and the rail is provided. It is characterized in that the rail is laid on the construction bottom surface using a suspending member.

【0009】請求項3に係る発明は、一方向に連続する
鉄筋コンクリート造の筒状の地中構造物の内壁を形成す
る型枠本体の内方においてその軸線に沿って延在するよ
う配設された型枠支持梁を施工方向前方に移動させるた
めの移動装置が、前記型枠支持梁の前後に取り付けられ
た2基一対の移動台車からなり、各移動台車が、左右
に、それぞれ前後方向に列設された2個一対の車輪をそ
れぞれ備えてなることを特徴としている。
The invention according to claim 3 is arranged so as to extend along the axis of the form body which forms the inner wall of the reinforced concrete tubular underground structure continuous in one direction. The moving device for moving the mold support beam forward in the construction direction is composed of a pair of two movable carriages attached to the front and rear of the form support beam. It is characterized by comprising a pair of two wheels arranged in a row.

【0010】[0010]

【発明の実施の形態】以下、本発明に係る型枠の移動方
法および型枠の移動装置の実施の形態の一例を、図1な
いし図7を参照して説明する。図1に示すように、型枠
装置(型枠)20は、形成すべきトンネル(地中構造
物)Tの内面の断面形状、すなわち円形に対応した筒状
の型枠ユニット(型枠本体)21と、型枠ユニット21
の軸線方向に沿って延在する型枠支持ビーム(型枠支持
梁)22とから構成されている。
BEST MODE FOR CARRYING OUT THE INVENTION An example of an embodiment of a method for moving a mold and a device for moving a mold according to the present invention will be described below with reference to FIGS. 1 to 7. As shown in FIG. 1, a formwork device (formwork) 20 is a tubular formwork unit (formwork body) corresponding to a sectional shape of an inner surface of a tunnel (underground structure) T to be formed, that is, a circle. 21 and the formwork unit 21
And a form support beam (form support beam) 22 extending along the axial direction of.

【0011】型枠ユニット21は、複数、例えば7個の
リング状の型枠21aが、その軸線方向において分離可
能に連接された構成からなっている。図2に示すよう
に、この型枠ユニット21は、周方向においても、底部
(インバート)型枠23と、側部型枠24,25と、上
部型枠26とに4分割されている。そして、この型枠ユ
ニット21には、その中央部に略ロ字状のフレーム27
が設けられており、このフレーム27に、前記底部型枠
23、側部型枠24,25、上部型枠26が以下のよう
にして支持されている。
The mold frame unit 21 is composed of a plurality of ring molds 21a, for example, seven ring-shaped molds 21a, which are separably connected in the axial direction. As shown in FIG. 2, the mold unit 21 is also divided into four in the circumferential direction into a bottom (invert) mold 23, side molds 24 and 25, and an upper mold 26. The frame unit 21 has a substantially square-shaped frame 27 at its center.
The bottom mold 23, the side molds 24 and 25, and the upper mold 26 are supported on the frame 27 in the following manner.

【0012】図3に示すように、底部型枠23は、周方
向に二分割されており、両端部に備えられたヒンジによ
って、内方に向けて折り畳み自在となっている。そし
て、これら二個一対の底部型枠23は、底部用油圧シリ
ンダ28,28によって開閉駆動されるようになってい
る。
As shown in FIG. 3, the bottom frame 23 is divided into two in the circumferential direction, and can be folded inward by hinges provided at both ends. The two bottom molds 23 are opened and closed by the bottom hydraulic cylinders 28, 28.

【0013】側部型枠24,25と上部型枠26は、側
部用油圧シリンダ29,29によって、略馬蹄形を成し
た状態のまま、内方に引き込まれ、その断面方向の外径
寸法が縮小可能とされている。
The side molds 24 and 25 and the upper mold 26 are drawn inward by the side hydraulic cylinders 29 and 29 in a substantially horseshoe-shaped state, and their outer diameters in the cross-sectional direction are reduced. It can be reduced.

【0014】図1に示したように、このような型枠ユニ
ット21には、その型枠面にコンクリート注入口33,
33,…が形成されており、各コンクリート注入口33
には、コンクリート注入管34が接続されている。これ
により、コンクリート注入管34からコンクリート注入
口33を介して型枠ユニット21の外周側にコンクリー
トを注入するようになっている。また、型枠ユニット2
1の前端周縁部には、型枠ユニット21と周囲地山との
間隙を全周にわたって閉塞する妻板35が備えられてい
る。
As shown in FIG. 1, such a formwork unit 21 has a concrete injection port 33,
33, ... Are formed and each concrete injection port 33 is formed.
A concrete injection pipe 34 is connected to the. As a result, concrete is injected from the concrete injection pipe 34 to the outer peripheral side of the form unit 21 through the concrete injection port 33. In addition, the formwork unit 2
The front end peripheral portion of No. 1 is provided with a gable plate 35 that closes the gap between the form unit 21 and the surrounding ground over the entire circumference.

【0015】図2に示したように、型枠支持ビーム22
は、断面視矩形の立体トラス構造からなり、上記型枠ユ
ニット21の中心軸線上に配設されている。この型枠支
持ビーム22は、その上下において、フレーム27を型
枠ユニット21の軸線方向に沿って摺動自在に支持して
いる。これにより、型枠ユニット21と型枠支持ビーム
22とは、その軸線方向において互いに進退自在とされ
ている。そして、この型枠支持ビーム22には、これを
型枠ユニット21に対して進退駆動させる駆動機構(図
示なし)が備えられている。
As shown in FIG. 2, the formwork support beam 22
Is formed of a three-dimensional truss structure having a rectangular cross section, and is arranged on the central axis of the mold frame unit 21. The frame support beam 22 supports a frame 27 slidably above and below the frame 27 in the axial direction of the frame unit 21. As a result, the mold frame unit 21 and the mold frame support beam 22 are movable back and forth in the axial direction. The formwork support beam 22 is provided with a drive mechanism (not shown) for driving the formwork support beam 22 to move back and forth with respect to the formwork unit 21.

【0016】また、図1に示したように、この型枠支持
ビーム22は、前後に、下方に向けて伸縮自在な脚4
0,41を有しており、これら脚40,41によって施
工底面G上またはトンネルTの底面T1上に立脚するよ
うになっている。
Further, as shown in FIG. 1, the form supporting beam 22 has a leg 4 which can extend and retract in the front and rear direction.
0 and 41, and these legs 40 and 41 stand on the construction bottom surface G or the bottom surface T1 of the tunnel T.

【0017】図4に示すように、この型枠支持ビーム2
2には、その前部と後部とに、2基一対の移動台車(移
動装置)45,46が着脱自在に備えられている。図5
に示すように、これら移動台車45,46は、それぞ
れ、型枠支持ビーム22の断面方向において所定間隔を
隔てた2本一対の脚47,47を有した構成となってい
る。図6に示すように、各脚47には、それぞれ型枠支
持ビーム22の軸線方向において2個一対の車輪48,
48が回転自在に軸支されて設けられている。また、図
4に示したように、一方の移動台車45には、車輪4
8,48を回転駆動させる自走装置49が備えられてお
り、これによってこの移動台車45は自走可能となって
いる。このような移動台車45,46は型枠支持ビーム
22の所定位置の下面にボルト等で着脱自在に固定され
ており、型枠支持ビーム22の移動時には、その移動方
向に沿って施工底面G上に敷設された2本一対の走行レ
ール(レール)50,50上を走行できるようになって
いる。
As shown in FIG. 4, this form supporting beam 2
The front and rear portions of the vehicle 2 are detachably provided with a pair of two movable carriages (moving devices) 45 and 46. FIG.
As shown in FIG. 5, each of the movable carriages 45 and 46 has a pair of legs 47 and 47 that are spaced apart by a predetermined distance in the cross-sectional direction of the form support beam 22. As shown in FIG. 6, each leg 47 has a pair of wheels 48, 2 in the axial direction of the form support beam 22.
A rotary shaft 48 is rotatably supported. In addition, as shown in FIG.
A self-propelled device 49 for rotating and driving 8, 8 is provided, which allows the movable carriage 45 to be self-propelled. The movable carriages 45 and 46 are detachably fixed to the lower surface of the formwork supporting beam 22 at predetermined positions with bolts or the like, and when the formwork supporting beam 22 moves, the moving carriages 45 and 46 are placed on the construction bottom surface G along the moving direction. It is possible to travel on a pair of traveling rails (rails) 50, 50 laid on the.

【0018】また、型枠支持ビーム22の前端部には、
前記走行レール50,50を施工方向前方の施工底面G
上に順次敷設していくためのレール吊り込み装置(レー
ル吊り込み部材)52が備えられている。図7に示すよ
うに、このレール吊り込み装置52は、電動トロリー付
きの電動チェーンブロック53と、型枠支持ビーム22
の軸線と直交するよう水平に設けられたレール54とか
ら構成されており、電動チェーンブロック53がレール
54に沿って移動自在に設けられている。レール54
は、型枠支持ビーム22の前端部から前方に延出する二
本一対の支持部材55,55間に架設されており、電動
チェーンブロック53で図4に示したように走行レール
50,50を敷設するのに十分な長さを有している。
At the front end of the form supporting beam 22,
The running rails 50, 50 are installed on the construction bottom surface G in front of the construction direction.
A rail suspension device (rail suspension member) 52 for sequentially laying the rails is provided. As shown in FIG. 7, the rail suspension device 52 includes an electric chain block 53 with an electric trolley and a form supporting beam 22.
And a rail 54 horizontally provided so as to be orthogonal to the axis of the electric chain block 53. The electric chain block 53 is movably provided along the rail 54. Rail 54
Is installed between a pair of two support members 55, 55 extending forward from the front end of the formwork support beam 22, and the electric chain block 53 guides the traveling rails 50, 50 as shown in FIG. It is long enough to be laid.

【0019】次に、図1に示したように、このような型
枠装置20を用いてトンネルTを形成するには、基本的
には従来と同様にして、シールド掘削機等で掘削した坑
H内において、 鉄筋の組立、 鉄筋を組み立てた区間への型枠支持ビーム22の前
進、 縮径した状態での型枠ユニット21の型枠支持ビーム
22に沿った前進、 型枠ユニット21の拡径 コンクリート注入管34,コンクリート注入口33か
ら、坑Hと型枠ユニット21との間の空間へのコンクリ
ートCの充填、 コンクリートCが所定の強度を発現した後における、
型枠ユニット21の縮径、を行った後、前記からの
工程の繰り返しによって、所定長のトンネルTを形成し
ていく。
Next, as shown in FIG. 1, in order to form the tunnel T by using such a formwork device 20, basically, a tunnel excavated by a shield excavator or the like in the same manner as the conventional one. In H, assembling the rebar, advancing the form support beam 22 to the section where the rebar is assembled, advancing along the form support beam 22 of the form unit 21 in a reduced diameter state, expanding the form unit 21. From the diameter concrete injection pipe 34 and the concrete injection port 33, filling the space between the mine H and the formwork unit 21 with the concrete C, after the concrete C exhibits a predetermined strength,
After the diameter of the mold unit 21 is reduced, the tunnel T having a predetermined length is formed by repeating the above steps.

【0020】ここで、上記の型枠支持ビーム22の前
進に際しては、以下のようにして作業を行う。まず、上
記の鉄筋の組立が完了した状態において、型枠ユニッ
ト21の周囲に既にコンクリートCが打設・養生されて
いる場合においては、型枠ユニット21を拡径したまま
の状態としておく。そして、脚40,41を縮めた後、
周囲の硬化したコンクリートC、すなわちトンネルTに
反力を得て、駆動機構(図示なし)により型枠支持ビー
ム22を前進させる。そして、型枠支持ビーム22を所
定距離前進させた後、脚40,41を伸ばし、施工底面
GあるいはトンネルTの底面T1上に立脚させる。
Here, in advancing the form supporting beam 22, the work is performed as follows. First, in a state in which the above-mentioned reinforcing bars have been assembled, when concrete C has already been cast and cured around the form unit 21, the form unit 21 is left in the expanded state. And after contracting the legs 40 and 41,
A reaction force is applied to the surrounding hardened concrete C, that is, the tunnel T, and the form supporting beam 22 is advanced by a driving mechanism (not shown). Then, after the formwork support beam 22 is advanced by a predetermined distance, the legs 40 and 41 are extended and made to stand on the construction bottom surface G or the bottom surface T1 of the tunnel T.

【0021】また、上記の鉄筋の組立が完了した状態
において、型枠ユニット21の周囲にコンクリートCが
打設されていない場合には以下のようにする。まず、図
4に示したように、型枠支持ビーム22に備えたベルト
コンベア56(図1参照)で、走行レール50,50を
前方に搬送し、これをレール吊り込み装置52で前方の
施工底面Gに吊り込んで敷設する。このときには図7に
示した電動チェーンブロック53をレール54に沿って
左右に移動させることによって走行レール50,50を
所定の位置に設置するようにする。続いて、型枠支持ビ
ーム22の前後に移動台車45,46を取り付ける。こ
のとき、移動台車45,46を走行レール50,50上
に載せるのは言うまでもない。そして、脚40,41を
縮めた後に、一方の移動台車45に備えた自走装置49
で移動台車45を施工方向前方に向けて自走させること
により、型枠支持ビーム22を走行レール50,50に
沿って前進させていく。この後は、走行レール50,5
0の敷設作業と、型枠支持ビーム22の前進とを繰り返
して、この型枠支持ビーム22を所定距離前進させてい
き、前進完了後に脚40,41を延ばして立脚させる。
Further, when concrete C is not placed around the form unit 21 in the state where the above-mentioned rebar assembly is completed, the following is performed. First, as shown in FIG. 4, the belt conveyor 56 (see FIG. 1) provided on the form supporting beam 22 conveys the traveling rails 50, 50 to the front side, and the rail suspension device 52 performs the front construction. It is hung and laid on the bottom surface G. At this time, the electric chain block 53 shown in FIG. 7 is moved left and right along the rail 54 so that the traveling rails 50, 50 are set at predetermined positions. Subsequently, the movable carriages 45 and 46 are attached before and after the formwork support beam 22. At this time, it goes without saying that the movable carriages 45 and 46 are placed on the traveling rails 50 and 50. Then, after retracting the legs 40 and 41, the self-propelled device 49 provided on one of the movable carriages 45.
By moving the movable carriage 45 forward in the construction direction, the form supporting beam 22 is advanced along the traveling rails 50. After this, travel rails 50, 5
The laying work of 0 and the advancement of the form support beam 22 are repeated to advance the form support beam 22 by a predetermined distance, and after the advancement is completed, the legs 40 and 41 are extended to stand.

【0022】上述した型枠装置20の移動方法では、型
枠支持ビーム22の前端部に備えたレール吊り込み装置
52によって前方の施工底面G上に2本一対のレール5
0,50を敷設するとともに、型枠支持ビーム22の前
後に2基一対の移動台車45,46を取り付けるように
している。そして、これら移動台車45,46をレール
50,50上に沿って走行させることによって型枠支持
ビーム22を前方に移動させた後、型枠ユニット21を
縮径させて、これを駆動機構(図示なし)によって型枠
支持ビーム22に沿って前方に移動させた後、型枠ユニ
ット21を拡径する構成となっている。また、このよう
な移動方法に用いるため型枠支持ビーム22の前後に取
り付けられた2基一対の移動台車45,46は、それぞ
れ、前後に列設された2個一対の車輪48,48を左右
の脚47,47のそれぞれに備えてなる構成となってい
る。このようにして、トンネルTの施工の進捗に伴う型
枠装置20の移動に際し、レール50,50を敷設しつ
つ移動台車45,46によって型枠支持ビーム22を前
進させることによって、型枠ユニット21の周囲に打設
したコンクリートCが硬化していない状態であっても、
これを養生している間に型枠支持ビーム22を前進させ
ることができ、作業の効率化を図ることができる。ま
た、従来のように受け台7(図10参照)を準備し、こ
れを順次前方に盛り替えていく必要もない。これらの結
果、工期短縮および工費削減を図ることが可能となる。
In the method of moving the formwork apparatus 20 described above, a pair of rails 5 are provided on the front construction bottom surface G by the rail suspending device 52 provided at the front end of the formwork support beam 22.
0 and 50 are laid, and two pairs of moving carriages 45 and 46 are attached to the front and rear of the form supporting beam 22. Then, by moving the movable carriages 45 and 46 along the rails 50 and 50 to move the formwork support beam 22 forward, the formwork unit 21 is reduced in diameter to drive it. None), the mold unit 21 is moved forward along the form supporting beam 22, and then the form unit 21 is expanded in diameter. Further, for use in such a moving method, the pair of two moving carriages 45 and 46 attached to the front and rear of the form supporting beam 22 respectively move the pair of front and rear wheels 48 and 48 to the left and right. It is configured to be provided for each of the legs 47, 47 of the. In this way, when the formwork apparatus 20 is moved along with the progress of the construction of the tunnel T, the formwork supporting beam 22 is moved forward by the moving carriages 45 and 46 while laying the rails 50 and 50, so that the formwork unit 21 is moved. Even if the concrete C placed around the
The mold support beam 22 can be moved forward while this is being cured, and work efficiency can be improved. Further, it is not necessary to prepare the pedestal 7 (see FIG. 10) as in the conventional case, and sequentially rearrange it. As a result, it is possible to reduce the construction period and the construction cost.

【0023】なお、上記実施の形態において、レール5
0,50については、例えば他の用途でレールが既設さ
れている場合にはそのレールのゲージに合わせた移動台
車45,46を用いればよい。また、この場合にはレー
ル吊り込み装置52を設ける必要がないのは言うまでも
ない。また、上記の実施の形態においては、構築すべき
地中構造物として断面視円形のトンネルTを例として挙
げたが、例えば導水路等、トンネル以外の他の地中構造
物であっても同様に適用することができる。さらには断
面視円形以外の他の形状、例えば矩形の場合にも同様の
構成を適用することができる。
In the above embodiment, the rail 5
For rails 0 and 50, for example, when rails are already installed for other purposes, the moving carriages 45 and 46 that match the gauge of the rails may be used. Further, in this case, it goes without saying that it is not necessary to provide the rail suspension device 52. Further, in the above-mentioned embodiment, the tunnel T having a circular cross-section is given as an example of the underground structure to be constructed, but the same applies to other underground structures other than the tunnel, such as a headrace. Can be applied to. Further, the same configuration can be applied to a shape other than the circular shape in cross section, for example, a rectangular shape.

【0024】[0024]

【発明の効果】以上説明したように、請求項1に係る型
枠の移動方法によれば、型枠が、型枠本体と、型枠支持
梁と、型枠支持梁に沿って型枠本体を移動させる駆動機
構とから構成され、型枠を施工方向前方に搬送するに際
しては、前方の施工底面上に2本一対のレールを敷設す
るとともに、型枠支持梁の前後に2基一対の移動台車を
取り付け、これら移動台車をレール上に沿って走行させ
ることによって型枠支持梁を前方に移動させた後、型枠
本体を型枠支持梁に沿って前方に移動させる構成となっ
ている。また、請求項2に係る型枠の移動方法によれ
ば、型枠支持梁の前部にレール吊り込み部材を備えてお
き、該レール吊り込み部材を用いてレールを施工底面上
に敷設していく構成となっている。このようにして、施
工の進捗に伴う型枠の移動に際し、レールを前方に敷設
しつつ移動台車によって型枠支持梁を前進させることに
よって、型枠本体周囲に打設したコンクリートが硬化し
ていない状態であっても、これを養生している間に型枠
支持梁を前進させることができ、作業の効率化を図るこ
とができる。また、従来のように受け台を準備し、これ
を順次前方に盛り替えていく必要もない。これらの結
果、工期短縮および工費削減を図ることが可能となる。
As described above, according to the method for moving a formwork according to the first aspect, the formwork includes a formwork body, a formwork support beam, and a formwork body along the formwork support beam. It is composed of a drive mechanism for moving the mold, and when transporting the formwork forward in the construction direction, a pair of two rails are laid on the front construction bottom and two pairs of movements are made in front of and behind the formwork support beam. After the dolly is attached and the moving dolly is moved along the rails to move the formwork support beam forward, the formwork main body is moved forward along the formwork support beam. Further, according to the method of moving the formwork according to claim 2, a rail suspending member is provided in front of the formwork supporting beam, and the rail is laid on the construction bottom surface using the rail suspending member. It has become a configuration. In this way, when moving the formwork as the construction progresses, the concrete laid around the formwork body is not cured by laying the rails forward and advancing the formwork support beam by the moving carriage. Even in the state, it is possible to advance the formwork supporting beam while curing it, and work efficiency can be improved. In addition, it is not necessary to prepare a cradle and rearrange it forward one by one as in the conventional case. As a result, it is possible to reduce the construction period and the construction cost.

【0025】請求項3に係る型枠の移動装置によれば、
型枠支持梁を施工方向前方に移動させるための移動装置
が型枠支持梁の前後に取り付けられた2基一対の移動台
車からなり、各移動台車が、前後方向に列設された2個
一対の車輪を左右それぞれに備えてなる構成となってい
る。これにより、請求項1または2に係る型枠の移動方
法を実現することができ、工期短縮および工費削減とい
う効果を得ることが可能となる。
According to the form moving device of the third aspect,
The moving device for moving the form supporting beam forward in the construction direction is composed of a pair of two moving carriages attached to the front and rear of the form supporting beam, and each moving carriage is a pair of two arranged in the front-rear direction. The left and right wheels are provided. This makes it possible to realize the method for moving a mold according to claim 1 or 2, and it is possible to obtain the effects of shortening the construction period and reducing the construction cost.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明に係る型枠の移動方法および型枠の移動
装置を適用する型枠の一例を示す側面図である。
FIG. 1 is a side view showing an example of a mold to which a mold moving method and a mold moving device according to the present invention are applied.

【図2】同型枠の正面図である。FIG. 2 is a front view of the same formwork.

【図3】同型枠を縮径させた状態を示す正断面図であ
る。
FIG. 3 is a front sectional view showing a state in which the diameter of the mold is reduced.

【図4】同型枠の移動方法を示す側面図である。FIG. 4 is a side view showing a method for moving the same frame.

【図5】前記型枠の移動装置を示す正面である。FIG. 5 is a front view showing a moving device of the mold.

【図6】図5の側面図である。FIG. 6 is a side view of FIG. 5;

【図7】前記型枠に備えた吊り込み装置を示す側面図で
ある。
FIG. 7 is a side view showing a suspending device provided in the mold.

【図8】従来の型枠の一例を示す側面図である。FIG. 8 is a side view showing an example of a conventional mold.

【図9】同型枠の正面図である。FIG. 9 is a front view of the mold.

【図10】同型枠に備えた受け台を示す平面図および正
面図である。
FIG. 10 is a plan view and a front view showing a pedestal provided in the same frame.

【符号の説明】[Explanation of symbols]

20 型枠装置(型枠) 21 型枠ユニット(型枠本体) 22 型枠支持ビーム(型枠支持梁) 45,46 移動台車(移動装置) 48 車輪 50 走行レール(レール) 52 レール吊り込み装置(レール吊り込み部材) G 施工底面 T トンネル(地中構造物) 20 Formwork Device (Formwork) 21 Formwork Unit (Formwork Main Body) 22 Formwork Support Beam (Formwork Support Beam) 45, 46 Moving Carriage (Moving Device) 48 Wheels 50 Traveling Rail (Rail) 52 Rail Lifting Device (Rail suspension member) G Construction bottom T Tunnel (Underground structure)

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 一方向に連続する鉄筋コンクリート造の
筒状の地中構造物の内壁を形成するための型枠が、その
周方向の一部が内方に折り畳み可能とされて、他の部分
が縮径可能な構成とされた型枠本体と、該型枠本体の内
方に配設されて、前記型枠本体をその軸線方向に移動自
在に支持する型枠支持梁と、該型枠支持梁に沿って前記
型枠本体を移動させる駆動機構とから構成され、 該型枠を施工方向前方に搬送するに際しては、前方の施
工底面上に該型枠の移動方向に沿って延在する2本一対
のレールを敷設するとともに、前記型枠支持梁の前後に
2基一対の移動台車を取り付けておき、 これら移動台車を前記レール上に沿って走行させること
によって前記型枠支持梁を前方に移動させた後、 前記型枠本体を縮径させて、前記駆動機構によって前記
型枠支持梁に沿って前方に移動させた後に拡径すること
を特徴とする型枠の移動方法。
1. A formwork for forming an inner wall of a tubular underground structure made of reinforced concrete that is continuous in one direction, a circumferential part of which can be folded inward, and the other part of the formwork can be folded. And a mold support beam which is arranged inside the mold body and movably supports the mold body in the axial direction thereof. A drive mechanism for moving the mold body along a support beam. When the mold is conveyed forward in the construction direction, it extends along the movement direction of the mold on the front construction bottom surface. A pair of two rails are laid, and two pairs of movable carriages are attached to the front and rear of the form supporting beam, and these moving carriages are run along the rails to move the form supporting beam forward. After that, the diameter of the mold body is reduced to allow the drive mechanism to Therefore, the method of moving the formwork is characterized in that the formwork is moved forward along the formwork support beam and then the diameter is expanded.
【請求項2】 請求項1記載の型枠の移動方法におい
て、前記型枠支持梁の前部に前記レールを吊り込むため
のレール吊り込み部材を備えておき、該レール吊り込み
部材を用いて前記レールを施工底面上に敷設していくこ
とを特徴とする型枠の移動方法。
2. The method of moving a formwork according to claim 1, further comprising a rail suspending member for suspending the rail in front of the formwork supporting beam, and using the rail suspending member. A method of moving a formwork, characterized in that the rail is laid on a construction bottom surface.
【請求項3】 一方向に連続する鉄筋コンクリート造の
筒状の地中構造物の内壁を形成する型枠本体の内方にお
いてその軸線に沿って延在するよう配設された型枠支持
梁を施工方向前方に移動させるための移動装置が、前記
型枠支持梁の前後に取り付けられた2基一対の移動台車
からなり、各移動台車が、左右に、それぞれ前後方向に
列設された2個一対の車輪をそれぞれ備えてなることを
特徴とする型枠の移動装置。
3. A form supporting beam arranged so as to extend along an axis of a form main body forming an inner wall of a tubular underground structure of reinforced concrete continuous in one direction. The moving device for moving forward in the construction direction is composed of a pair of two moving carriages attached to the front and rear of the form support beam, and each moving carriage has two left and right rows arranged in the front-rear direction. A form moving device, comprising a pair of wheels, respectively.
JP8126077A 1996-05-21 1996-05-21 Method and equipment for moving form Pending JPH09310589A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8126077A JPH09310589A (en) 1996-05-21 1996-05-21 Method and equipment for moving form

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8126077A JPH09310589A (en) 1996-05-21 1996-05-21 Method and equipment for moving form

Publications (1)

Publication Number Publication Date
JPH09310589A true JPH09310589A (en) 1997-12-02

Family

ID=14926051

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8126077A Pending JPH09310589A (en) 1996-05-21 1996-05-21 Method and equipment for moving form

Country Status (1)

Country Link
JP (1) JPH09310589A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101372842B1 (en) * 2013-08-20 2014-04-01 주식회사 인터컨스텍 Apparatus for repairing ballasting rail bridge using double chain driving, and method for the same
CN103982200A (en) * 2014-05-21 2014-08-13 中国葛洲坝集团股份有限公司 Full-face inner sliding rail moving steel mould trolley
CN104763447A (en) * 2015-03-25 2015-07-08 三峡大学 Beret piece combined steel mold trolley
CN107060831A (en) * 2017-06-09 2017-08-18 中建八局第建设有限公司 One kind is used for tunnel groove constructing device
CN107338810A (en) * 2017-07-07 2017-11-10 中交第四公路工程局有限公司总承包分公司 City integrated piping lane self-propelled hydraulic trolley formwork and its construction method
JP2020193533A (en) * 2019-05-30 2020-12-03 有限会社 伊藤 Method of moving ceiling foam in arch center and device to move ceiling foam in arch center
CN115305842A (en) * 2022-08-19 2022-11-08 中交路桥建设有限公司 Rapid circulating installing and detaching construction method for external template of rainwater box culvert

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101372842B1 (en) * 2013-08-20 2014-04-01 주식회사 인터컨스텍 Apparatus for repairing ballasting rail bridge using double chain driving, and method for the same
CN103982200A (en) * 2014-05-21 2014-08-13 中国葛洲坝集团股份有限公司 Full-face inner sliding rail moving steel mould trolley
CN104763447A (en) * 2015-03-25 2015-07-08 三峡大学 Beret piece combined steel mold trolley
CN107060831A (en) * 2017-06-09 2017-08-18 中建八局第建设有限公司 One kind is used for tunnel groove constructing device
CN107060831B (en) * 2017-06-09 2023-12-22 中建八局第一建设有限公司 Be used for tunnel slot construction equipment
CN107338810A (en) * 2017-07-07 2017-11-10 中交第四公路工程局有限公司总承包分公司 City integrated piping lane self-propelled hydraulic trolley formwork and its construction method
JP2020193533A (en) * 2019-05-30 2020-12-03 有限会社 伊藤 Method of moving ceiling foam in arch center and device to move ceiling foam in arch center
CN115305842A (en) * 2022-08-19 2022-11-08 中交路桥建设有限公司 Rapid circulating installing and detaching construction method for external template of rainwater box culvert

Similar Documents

Publication Publication Date Title
CN110076889A (en) A kind of integral prefabricated immersed tube template system of dry-docking sequential method tunneling boring
JP2017002630A (en) Tunnel lining device and tunnel lining method
JPH09310589A (en) Method and equipment for moving form
JP5794794B2 (en) Tunnel construction method and tunnel construction system
CN107100648B (en) Auxiliary facility and method for tunnel plain concrete lining construction
JP2020037807A (en) Center rail delivery system and center
JPH09151471A (en) Movable form device and work execution method for underground structure using the device
CN210564558U (en) Secondary lining equipment for tunnel
JP3822525B2 (en) Tunnel invert construction method using mobile jetty and mobile jetty
JP3821919B2 (en) Mobile back anchor device and shield start method using the same
JP3067939B2 (en) Telher
JPH0639878B2 (en) Moving mechanism for mobile formwork for lining
JP2956486B2 (en) Forming equipment for lining tunnel arches
JPH0455118Y2 (en)
JPH09310590A (en) Form structure
JPH0640717Y2 (en) Primary lining mobile formwork for tunnels
JP2967773B2 (en) Pipe laying equipment
JP4118420B2 (en) Tunnel excavation and lining method and its equipment
JP3215091B2 (en) Segment shape holding device
JP2002242596A (en) Tunnel lining method and lining apparatus
CN221002779U (en) Disposable lining combined trolley for full-round tunnel with interrupt surface
JP7375501B2 (en) Construction method of large cross-section tunnel structure
JPH01207598A (en) Form disassembling device used for on-site laying type shield driving method
JPH0781485B2 (en) How to construct an excavation space
CN207161115U (en) It is a kind of to be used to go along with sb. to guard him mould trolley outside the arch of pile cutoff open trench tunnel

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20040216

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20040224

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20040421

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20040525