JPH09250110A - Construction method of arch concrete - Google Patents

Construction method of arch concrete

Info

Publication number
JPH09250110A
JPH09250110A JP8723296A JP8723296A JPH09250110A JP H09250110 A JPH09250110 A JP H09250110A JP 8723296 A JP8723296 A JP 8723296A JP 8723296 A JP8723296 A JP 8723296A JP H09250110 A JPH09250110 A JP H09250110A
Authority
JP
Japan
Prior art keywords
concrete
arch
semi
height
trusses
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP8723296A
Other languages
Japanese (ja)
Inventor
Nobuyuki Matsugashita
信之 松ケ下
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Okabe Co Ltd
Original Assignee
Okabe Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Okabe Co Ltd filed Critical Okabe Co Ltd
Priority to JP8723296A priority Critical patent/JPH09250110A/en
Publication of JPH09250110A publication Critical patent/JPH09250110A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To promote economic efficiency construction accuracy of arch concrete form construction. SOLUTION: The lower ends of semi-arch-shaped trusses 3a and 3b having height dividing a span of an arch concrete C into approximately two parts are connected to leg structures 1 and 1, the top of one semi-arch-shaped truss 3a connected to one side 13 of the upper end of a post 5 having a height adjusting device 10, and a form timbering A mounting the top of the other semi-arch-shaped truss 3b on the other side of the upper end of the same post 5 thereon in a slidable manner is used to construct the arch concrete C. When the post 5 is settled in case of placing concrete, the height of the post 5 is restored to an original state, the occurrence of excessive stress in the concrete casted to solidify is prevented and, at the same time, construction accuracy of the arch concrete C is matained in a good state.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、アーチ形トラスと支柱
との組合せによる型枠支保工を用いたアーチコンクリー
トの施工方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing arch concrete using a form supporting method using a combination of arch trusses and columns.

【0002】[0002]

【従来の技術】アーチ橋等におけるアーチコンクリート
の施工に適用する型枠支保工については、例えば特公平
3−64001号公報に記載されているような、橋台
(橋脚)間にアーチ形のトラスを架構することが行われ
るようになり、施工性及び経済性が著しく向上されるこ
とになった。
2. Description of the Related Art For formwork support applied to the construction of arch concrete in arch bridges, for example, an arch truss is to be installed between abutments (piers) as described in Japanese Patent Publication No. 3-64001. Construction work has come to be carried out, and workability and economic efficiency have been significantly improved.

【0003】しかし、上記方式の型枠支保工でも、長大
なスパンのものにそのまま適用するとなると、大規模な
構造物となって、その利点が失われることになる。そこ
で、例えば特開平4−194169号公報や特開平5−
17913号公報に記載されているような、分割したト
ラスと支柱との組合せによる型枠支保工が開発され、長
大スパンや扁平なアーチコンクリートの施工に適用され
るようになった。
However, even if the above-mentioned form supporting work is applied to a long span as it is, it will become a large-scale structure and its advantages will be lost. Therefore, for example, Japanese Patent Laid-Open No. 4-194169 and Japanese Patent Laid-Open No. 5-194169
Form support by combining divided trusses and struts as described in Japanese Patent No. 17913 has been developed and applied to the construction of long spans and flat arch concrete.

【0004】[0004]

【発明が解決しようとする課題】ところで、上記型枠支
保工においては、コンクリートを打設した際、支柱が若
干沈下することもあり、その場合、トラスに過大な荷重
がかかることになることから、支柱の沈下に対応できる
構造としている。
By the way, in the above-mentioned form supporting work, when the concrete is placed, the props may sink a little, and in that case, an excessive load is applied to the truss. It has a structure that can cope with the sinking of columns.

【0005】しかし、地盤というものは本来不確定性の
ものであるから、支柱が予測以上に大きく沈下すること
もある。そうした場合、上記型枠支保工では、支柱の大
きな沈下に対応させるには、構造上困難な問題が生ずる
ことになる。
However, since the ground is inherently uncertain, the columns may sink more than expected. In such a case, in the above-mentioned form supporting work, a structurally difficult problem arises in order to cope with a large sinking of the column.

【0006】他方、アーチコンクリートの施工は、型枠
支保工上に設置した型枠上にコンクリートを打設して行
うのであるが、このコンクリートはスパン全長を同時に
打設することは物理的にできないので、コンクリートを
一度に打設できる範囲の区間を設定して分割打設するよ
うにしている。この分割打設は、施工性を考慮すれば型
枠の両下端部から順次上方に向って打ち進めるのが得策
である。
On the other hand, the construction of arch concrete is carried out by placing concrete on the formwork installed on the formwork support, but this concrete cannot physically place the span length at the same time. Therefore, we set the section of the range where concrete can be poured at one time and divide it. Considering the workability, it is a good idea to carry out this divided driving in order, starting from both lower ends of the formwork upwards.

【0007】そうした場合、コンクリートの打設が上方
へと進むにしたがい、支柱への鉛直荷重の負担は次第に
増大して行くことになる。その際、支柱が沈下するよう
なことがあると、型枠支保工は全体に変形、沈降するこ
とになって、さきに打設した区間の硬化しているコンク
リートとの型離れが生じ、そのコンクリートに過大な応
力が働くことになるとともに、次に打設するコンクリー
トとの間に段差が生じるなどの不都合が生じることにな
る。
In such a case, the load of the vertical load on the support column will gradually increase as the concrete pouring progresses upward. At that time, if the pillars may sink, the form support will be deformed and settled as a whole, causing mold separation from the hardened concrete in the section that was placed earlier, Excessive stress will be applied to the concrete, and there will be inconvenience such as a step between the concrete and the next concrete to be placed.

【0008】それを防止するためには、例えば特開平5
−280013号公報に記載されているような、下端部
区間に打設のコンクリートと脚部構造物や各区間のコン
クリートどうしの結合を強化するための特別の対策を講
ずる必要があり、それによる施工の面倒や経費が増大す
ることになる。また、型枠支保工の変形、沈降量が大と
なれば、アーチコンクリート自体も設計通りの形態、強
度が得られなくなるという問題も生ずることになる。
In order to prevent this, for example, Japanese Patent Application Laid-Open No. Hei 5
-280013, it is necessary to take special measures for strengthening the connection between the concrete cast in the lower end section and the leg structure or the concrete in each section, and the construction by this This will increase the trouble and expense. Further, if the amount of deformation and settling of the formwork support work is large, there is a problem that the arch concrete itself cannot obtain the shape and strength as designed.

【0009】また、上記特開平5−17913号公報記
載の型枠支保工では、半アーチ状としたトラスと支柱の
合成体の一対は完全に分離された構造で、アーチ中央部
の対の支柱もそれぞれ独立しており、両者の間に横つな
ぎやブレースが全くないことが特徴である。したがっ
て、対の支柱は近接位置にありながらコンクリート打設
により発生する荷重に対して共同して抵抗することはで
きず、それぞれの柱は単独で荷重に対抗しなければなら
ないから、大きい断面の支柱材が必要となり、それだけ
費用も増大する。近接位置にあるこの対の柱を一体の柱
として構成して安価なものにする技術は求められて当然
である。
Further, in the form supporting work disclosed in the above-mentioned Japanese Patent Laid-Open No. 5-179913, a pair of a semi-arched truss and a composite body of columns is completely separated, and a pair of columns at the center of the arch. Is independent of each other, and is characterized by no horizontal connections or braces between them. Therefore, while the pair of columns are in close proximity, they cannot jointly resist the load generated by concrete pouring, and each column must stand against the load independently, so that the columns with large cross section Material is required, and the cost increases accordingly. It is natural that a technology for constructing the pair of pillars in the close position as an integral pillar to be inexpensive is required.

【0010】本発明は、上記のような型枠支保工におけ
る諸問題点を解決するためになされたもので、2分割さ
れたアーチ状トラスの各頂部を、単一の支柱によって支
持させるとともに、構造解析の結果の信頼性を高める目
的で両アーチ状トラスを相対的にスパン方向に摺動でき
るようにした型枠支保工を用い、コンクリートの打設に
よって支柱が沈下した際に、その沈下量に対応して支柱
の高さを調節して、トラスの支持点の高さを元の状態に
復帰させ、型枠支保工の沈降、変形を抑制して、型枠と
打設コンクリートとの型離れを防止し、同コンクリート
に過大な応力の生ずるのを防ぐとともに、アーチコンク
リートの施工精度を向上し、かつ、コンクリートの打設
施工の容易化と能率化を図ろうとするものである。
The present invention has been made in order to solve various problems in the above-mentioned form supporting work, and the tops of the arch-shaped trusses divided into two are supported by a single strut, and In order to increase the reliability of the results of structural analysis, a formwork supporting structure that allows both arch-shaped trusses to slide relative to each other in the span direction was used. Adjusting the height of the columns to restore the height of the support points of the truss to the original state, suppressing the settling and deformation of the formwork support work, and the formwork of the formwork and the cast concrete. It aims to prevent separation and to prevent excessive stress from occurring in the concrete, to improve the construction accuracy of arch concrete, and to facilitate and improve the efficiency of concrete placing work.

【0011】[0011]

【課題を解決するための手段】上記の目的を達成するた
めの本発明の構成について、実施例に対応する図面を参
照して説明すると、請求項1の施工方法は、アーチコン
クリートCのスパンをほぼ2分割した長さの半アーチ状
トラスの一対3a,3bを、その各下端部を脚部構造物
1,1に結合するとともに、地盤Bに高さ調節自在に立
設した単一の支柱5に、一方の半アーチ状トラス3aの
頂端部を結合13、支持し、他方の半アーチ状トラス3b
の頂端部を、スパン方向に摺動自在に載架14、支持して
形成した型枠支保工Aを用いて、アーチコンクリートC
を施工するにあたり、コンクリートの打設等にともなう
上記支柱5の沈下が生じた場合、上記支柱5の高さを調
節して、その沈下の補正を行うことを特徴とするもので
ある。
The construction of the present invention for achieving the above object will be described with reference to the drawings corresponding to the embodiments. A pair of semi-arched trusses 3a and 3b, each of which has a length substantially divided into two, are connected to the leg structures 1 and 1 at their lower ends, and a single column is erected on the ground B so that the height of the truss can be adjusted. 5, the top end portion of one semi-arched truss 3a is connected and supported 13, and the other semi-arched truss 3b is connected.
Using the frame support A formed by supporting and mounting the top end of the frame 14 slidably in the span direction, arch concrete C
When the pillar 5 is submerged due to the pouring of concrete, etc., the height of the pillar 5 is adjusted to correct the subsidence.

【0012】また、請求項2の施工方法は、複数個のト
ラス4a,4bを結合して、アーチコンクリートCのス
パンをほぼ2分割した長さの半アーチトラスの一対3
a,3bを、その各下端部を脚部構造物1,1に結合す
るとともに、地盤Bに高さ調節自在に立設した単一の支
柱5に、一方の半アーチ状トラス3aの頂端部を結合1
3、支持し、他方の半アーチ状トラス3bの頂端部を、
スパン方向に摺動自在に載架14、支持し、また、各トラ
ス相互の結合部17を、地盤Bに高さ調節自在に立設した
支柱6によりそれぞれ支持して形成した型枠支保工Aを
用いて、アーチコンクリートCを施工するにあたり、コ
ンクリートの打設等にともなう上記支柱5,6の沈下が
生じた場合、その沈下した支柱5,6の高さを調節し
て、その沈下の補正を行うことを特徴とするものであ
る。
Further, the construction method of claim 2 is such that a plurality of trusses 4a and 4b are connected to each other, and a pair of half arch trusses having a length obtained by substantially dividing the span of the arch concrete C into two are provided.
a, 3b are connected to the leg structures 1, 1 at their lower ends, respectively, and a single strut 5 is installed on the ground B so that the height of the semi-arched truss 3a can be adjusted. Combine 1
3, support, the top end of the other semi-arched truss 3b,
Formwork support A that supports and supports the platform 14 slidably in the span direction, and also supports the joints 17 of the respective trusses by the columns 6 that are erected on the ground B and whose height is adjustable. When constructing the arch concrete C using, the subsidence of the above-mentioned struts 5 and 6 due to the placing of concrete, etc. occurs, the height of the submerged struts 5 and 6 is adjusted to correct the subsidence. It is characterized by performing.

【0013】[0013]

【発明の実施の形態】以下、本発明の実施の形態につい
て図面を参照して説明する。図1は本発明の第1の実施
例を示し、図2は第2の実施例を示したものである。
BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 shows a first embodiment of the present invention, and FIG. 2 shows a second embodiment.

【0014】まず、第1の実施例について説明する。図
1において、1,1はアーチコンクリートCを打設する
に先立って所定の間隔をおき構築された橋台、橋脚等の
脚部構造物、Aは本発明において使用される型枠支保工
(以下支保工という)で、その上面にはアーチ状の型枠
2が設置される。
First, the first embodiment will be described. In FIG. 1, 1, 1 are leg structures such as abutments, piers, etc., which are constructed at a predetermined interval prior to placing the arch concrete C, and A is a form supporter used in the present invention (hereinafter referred to as "framework support"). An arch-shaped formwork 2 is installed on the upper surface of the supporting structure.

【0015】支保工Aは、アーチコンクリートCのスパ
ンを約2分割した長さに形成された半アーチ状トラスの
一対3a,3bと、脚部構造物1,1間の中央部の地盤
B上に立設された支柱5とよりなる。
The support A is a pair of semi-arched trusses 3a and 3b each having a length obtained by dividing the span of the arch concrete C into about two, and the ground B at the center between the leg structures 1 and 1. It is composed of a pillar 5 standing upright.

【0016】支柱5は、図1〜図3に示すように、アー
チコンクリートCのスパン方向に所要の間隔をおいて並
列した柱部材7,7を多数の横杆8,8及び斜材9,9
で連結して形成されている。このような構造にすれば、
安価な既製材を使って強度、剛性の高い支柱が形成でき
る。なお、支柱5は、このような構造のものに限らず、
例えば、比較的高さ(アーチコンクリートCのスパン方
向の巾)のあるH型鋼等を単体或は複合体として用いる
こともできる。そして、支柱5の上端には、その一側に
ブラケット11が、他側に受台12がそれぞれ上方に向けて
突設されているとともに、支柱5の下端部には、支柱5
の高さを調節することのできるようにした、油圧ジャッ
キ等による高さ調節装置10が設けられ、支柱5はこの高
さ調節装置10を介して地盤Bに立設される。
As shown in FIGS. 1 to 3, the support column 5 includes a plurality of horizontal rods 8 and 8 and diagonal members 9, which are column members 7 and 7 arranged in parallel in the span direction of the arch concrete C at a required interval. 9
It is formed by connecting with. With this structure,
Posts with high strength and rigidity can be formed using inexpensive ready-made materials. The pillar 5 is not limited to such a structure,
For example, H-shaped steel or the like having a relatively high height (width in the span direction of arch concrete C) may be used as a single body or a composite body. A bracket 11 is provided on one side of the upper end of the column 5, and a pedestal 12 is provided on the other side of the column 5 so as to project upward.
A height adjusting device 10 such as a hydraulic jack is provided so that the height of the column 5 can be adjusted, and the support column 5 is erected on the ground B via the height adjusting device 10.

【0017】上記一対の半アーチ状トラス3a,3b
は、それぞれ下端が脚部構造物1にピン等により結合15
され、一方の半アーチ状トラス3aの頂部は、上記支柱
5の上端に突設のブラケット11にピン等により結合13
し、他方の半アーチ状トラス3bの頂部は、受台12上
に、アーチコンクリートCのスパン方向に摺動自在に載
置14する。
The pair of semi-arched trusses 3a and 3b
Is connected to the leg structure 1 by a pin or the like at the lower end.
The top of one of the semi-arched trusses 3a is connected to a bracket 11 projecting on the upper end of the pillar 5 by a pin or the like 13
Then, the top of the other semi-arched truss 3b is placed 14 on the pedestal 12 slidably in the span direction of the arch concrete C.

【0018】上記構成の支保工Aは、施工するアーチコ
ンクリートCの奥行き方向に所要の間隔をおいて複数列
設し、互いに連結杆(図示を略す)を用いて結合する。
また、型枠2は、架設された上記支保工Aの梁構造物に
取付けたボルトやバタ材等の支持具16,16を介して取付
けられる。そして、型枠2上にコンクリートCが打設さ
れる。
The supporting work A having the above structure is provided in a plurality of rows at a predetermined interval in the depth direction of the arch concrete C to be constructed, and is connected to each other by using connecting rods (not shown).
Further, the formwork 2 is attached via the support tools 16, 16 such as bolts and flaps that are attached to the beam structure of the above-mentioned support and support A installed. Then, concrete C is placed on the formwork 2.

【0019】コンクリートの打設は、アーチコンクリー
トCのスパン方向に一回に打設できる区間を設定して打
設される。本発明においては、まず、アーチコンクリー
トCの最下部区間のコンクリートを、脚部構造物1に接
続して打設し、以後上方に順次打ち継いで行く。その
際、コンクリートの打設荷重は、半アーチ状トラス3
a,3b及び支柱5が分担して受けることになるが、そ
れにともない半アーチ状トラス3a,3bに撓みが生じ
る場合は、一方の半アーチ状トラス3bの頂部が支柱5
上でスパン方向に撓みに応じて摺動し、過大な応力の発
生を防止することができる。
The concrete is poured by setting a section in the span direction of the arch concrete C that can be poured once. In the present invention, first, the concrete in the lowermost section of the arch concrete C is connected to the leg structure 1 to be placed, and thereafter, the concrete is successively placed upward. At that time, the placing load of the concrete is the semi-arched truss 3
When the semi-arched trusses 3a and 3b are flexed as a result, the tops of the semi-arched trusses 3b are supported by the pillars 5a and 3b.
It is possible to prevent the generation of excessive stress by sliding in the span direction in accordance with the bending.

【0020】また、アーチコンクリートCを打ち継いで
行く過程で、地盤Bの状態が悪かったりすると、支柱5
は沈下することになる。そうした場合には、半アーチト
ラス3a,3bは、その頂部が降下して、結合部15を中
心に下方に傾くことになるので、すでに硬化している、
初回に打設した最下部区間のコンクリート或はそれに打
ち継いでいるコンクリートとの型離れが生ずることにな
り、それらのコンクリートは、片持式で自体の重量を支
えなければならないから、過大な応力が生じ、その部分
のコンクリートが破壊するおそれがある。
In addition, when the condition of the ground B is bad in the process of staking the arch concrete C, the pillar 5
Will sink. In such a case, the semi-arch trusses 3a and 3b are already hardened because the tops of the semi-arch trusses 3a and 3b are lowered and the half arch trusses 3a and 3b are inclined downward with the joint portion 15 as the center.
There will be mold release from the concrete in the lowest section that was initially cast or the concrete that is being spliced to it, and these concretes must be cantilevered to support their own weight. May occur and the concrete in that part may be destroyed.

【0021】また、型離れの生じた状態でコンクリート
を打継ぐことになると、その打設したコンクリートと、
すでに硬化しているコンクリートとの間に打継ぎの段部
が形成されるようになるばかりでなく、アーチコンクリ
ートC全体も扁平化することになり、アーチコンクリー
ト全体の形状及び耐力が設計値を逸脱することにもな
る。
When the concrete is to be spliced in a state where the mold is separated, the concrete that has been placed,
Not only will the step portion of the splice be formed with the already hardened concrete, but the entire arch concrete C will also be flattened, and the shape and yield strength of the entire arch concrete will deviate from the design values. It will also be done.

【0022】本発明では、上記のように、コンクリート
を打設した際に支柱5が沈下した場合、その支柱5の沈
下量に対応して高さ調節装置10を伸長させ、半アーチ状
トラス3a,3bの頂部と結合、載置13,14した支柱5
の上端位置(高さ位置)を沈下前の元の状態に補正する
のである。支柱5の沈下は、コンクリートの段階的な打
設により、その都度生ずることがあるので、支柱5の沈
下補正は、それに応じてその都度必要量ずつ行うように
すればよい。
In the present invention, as described above, when the pillar 5 sinks when pouring concrete, the height adjusting device 10 is extended in accordance with the sinking amount of the pillar 5, and the semi-arched truss 3a. , 5 b, which is combined with the tops of 3b and placed 13 and 14
The upper end position (height position) of is corrected to the original state before subsidence. Since the subsidence of the pillar 5 may occur each time due to the stepwise pouring of concrete, the subsidence correction of the pillar 5 may be performed in accordance with the required amount each time.

【0023】次に、第2の実施例について説明する。こ
の実施例は、特に長大なスパンのアーチコンクリートの
施工に適するように形成した支保工Aを使用する。すな
わち、支保工Aを構成する半アーチ状トラス3a,3b
を、それぞれ複数に分割して形成した分割トラス4a,
4bをピン等により連結17して半アーチ状に形成する。
そして、その連結部17は、さきの支柱5と同様に、地盤
Bに立設した高さ調節装置10を備えた支柱6の上端部に
結合、支持される。また、分割トラス4aの下端部は脚
部構造物1に結合され、分割トラス4bの頂部は支柱5
の上端部に結合、載置13,14される。
Next, a second embodiment will be described. This embodiment uses a supporting structure A formed so as to be suitable for construction of arch concrete having a long span. That is, the semi-arched trusses 3a and 3b that form the support A
Of the divided trusses 4a,
4b is connected 17 by a pin or the like to form a semi-arched shape.
Then, the connecting portion 17 is coupled and supported to the upper end portion of the pillar 6 provided with the height adjusting device 10 standing on the ground B, like the pillar 5 above. In addition, the lower end of the split truss 4a is connected to the leg structure 1, and the top of the split truss 4b is the pillar 5.
It is connected to the upper end of the and mounted 13 and 14.

【0024】この実施例の場合も、コンクリートの打設
にともない支柱5,6が沈下したときには、各支柱5,
6ごとに、その沈下量に対応して高さを調節し、沈下補
正を行うようにすることはいうまでもない。
Also in the case of this embodiment, when the columns 5, 6 sink due to the pouring of concrete, the columns 5, 5
It goes without saying that the height of each 6 is adjusted in accordance with the amount of subsidence and the subsidence is corrected.

【0025】なお、上記分割トラス4a,4bの結合数
は2個に限らず必要に応じて増加することができ、ま
た、それに応じて分割トラスの連結部を支持する支柱の
数も増大することになる。
The number of joints of the divided trusses 4a and 4b is not limited to two, but can be increased if necessary, and the number of columns supporting the connecting portions of the divided trusses can be increased accordingly. become.

【0026】[0026]

【発明の効果】以上説明したように、本発明によれば、
脚部構造物間に架設するアーチ形の型枠支保工を、2分
割した半アーチ状トラスの一対で構成し、それらを脚部
構造物と高さ調節自在とした支柱に、一方を結合し、他
方を摺動自在に載置して各独立して架設したので、各半
アーチ状トラスが静定梁として計算でき、したがって、
構造解析の信頼性が極めて高いものであるとともに、一
対の半アーチ状トラスは一本の支柱を介して関連してい
るため、型枠支保工が単純化され、安価な構造物として
提供することができ、特に大スパンのアーチコンクリー
トの施工を経済的に行うことができる。
As described above, according to the present invention,
The arch-shaped frame supporting work to be installed between the leg structures is composed of a pair of half-arched trusses that are divided into two, and one of them is connected to the leg structure and the post whose height is adjustable. , Since the other is slidably placed and erected independently, each semi-arched truss can be calculated as a static beam, and therefore
The structural analysis is extremely reliable, and since the pair of semi-arched trusses are related to each other through a single strut, the formwork support is simplified and the structure is provided as an inexpensive structure. In particular, arch concrete with a large span can be economically constructed.

【0027】また、半アーチ状トラスを支持する支柱
が、コンクリートの打設等によって沈下した場合、その
支柱の高さを調節して半アーチ状トラスの頂部支持点の
高さを元の状態に復帰させるので、先行して打設したコ
ンクリートとの型離れを防いで、そのコンクリートに過
大な応力の生じるのを防止することができ、したがって
施工の簡易化と能率化が図れるとともに、設計形状に忠
実な精度の高いアーチコンクリートの施工ができる。
Further, when the pillar supporting the semi-arched truss is sunk by pouring concrete or the like, the height of the pillar is adjusted to restore the height of the top support point of the semi-arched truss to the original state. Since it is returned, it is possible to prevent the mold from separating from the concrete that was placed in advance, and to prevent excessive stress from occurring in the concrete, thus simplifying construction and improving efficiency, and at the same time designing the shape. Highly accurate and accurate arch concrete construction is possible.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施態様を示す概略正面図である。FIG. 1 is a schematic front view showing an embodiment of the present invention.

【図2】同他の実施態様を示す概略正面図である。FIG. 2 is a schematic front view showing another embodiment.

【図3】支柱の要部を示す拡大正面図である。FIG. 3 is an enlarged front view showing a main part of a column.

【符号の説明】[Explanation of symbols]

A 型枠支保工 B 地盤 C アーチコンクリート 1 脚部構造物 2 型枠 3a,3b 半アーチ状トラス 4a,4b 分割トラス 5,6 支柱 10 高さ調節装置 11 ブラケット 12 受台 13 結合部 14 載置部 15 結合部 16 支持具 17 連結部 A formwork support B ground C arch concrete 1 leg structure 2 formwork 3a, 3b semi-arched truss 4a, 4b split truss 5,6 prop 10 height adjuster 11 bracket 12 cradle 13 joint 14 mounting Part 15 Joining part 16 Supporting part 17 Connecting part

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 アーチコンクリートのスパンをほぼ2分
割した長さの半アーチ状トラスの一対を、その各下端部
を脚部構造物に結合するとともに、地盤に高さ調節自在
に立設した単一の支柱に、一方の半アーチ状トラスの頂
端部を結合、支持し、他方の半アーチ状トラスの頂端部
を、スパン方向に摺動自在に載架、支持して形成した型
枠支保工を用いて、アーチコンクリートを施工するにあ
たり、コンクリートの打設等にともなう上記支柱の沈下
が生じた場合、上記支柱の高さを調節して、その沈下の
補正を行うことを特徴とする、アーチコンクリートの施
工方法。
1. A pair of semi-arched trusses each having a length obtained by substantially dividing an arch concrete span into two, each lower end of which is connected to a leg structure, and which is vertically erected on the ground so that its height can be adjusted. Form support that is formed by connecting the top end of one semi-arched truss to one column and supporting it, and by mounting and supporting the top end of the other semi-arched truss slidably in the span direction. When the arch concrete is constructed by using, when the subsidence of the pillar due to the placing of concrete occurs, the height of the pillar is adjusted, and the subsidence is corrected, the arch. Concrete construction method.
【請求項2】 複数個のトラスを結合して、アーチコン
クリートのスパンをほぼ2分割した長さの半アーチトラ
スの一対を、その各下端部を脚部構造物に結合するとと
もに、地盤に高さ調節自在に立設した単一の支柱に、一
方の半アーチ状トラスの頂端部を結合、支持し、他方の
半アーチ状トラスの頂端部を、スパン方向に摺動自在に
載架、支持し、また、各トラス相互の結合部を、地盤に
高さ調節自在に立設した支柱によりそれぞれ支持して形
成した型枠支保工を用いて、アーチコンクリートを施工
するにあたり、コンクリートの打設等にともなう上記支
柱の沈下が生じた場合、その沈下した支柱の高さを調節
して、その沈下の補正を行うことを特徴とする、アーチ
コンクリートの施工方法。
2. A pair of semi-arch trusses each having a length obtained by joining a plurality of trusses to divide the span of arch concrete into two parts, each lower end portion of which is joined to a leg structure, and a height of the ground. The top end of one semi-arched truss is connected and supported by a single strut that is adjustable, and the top end of the other semi-arched truss is mounted and supported slidably in the span direction. In addition, when constructing arch concrete by using formwork supports formed by supporting the joints of each truss with the stanchions that are erected on the ground so that the height can be adjusted freely, when placing concrete, etc. A method for constructing arch concrete, characterized in that, when subsidence of the above-mentioned pillar occurs, the height of the submerged pillar is adjusted to correct the subsidence.
JP8723296A 1996-03-15 1996-03-15 Construction method of arch concrete Pending JPH09250110A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8723296A JPH09250110A (en) 1996-03-15 1996-03-15 Construction method of arch concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8723296A JPH09250110A (en) 1996-03-15 1996-03-15 Construction method of arch concrete

Publications (1)

Publication Number Publication Date
JPH09250110A true JPH09250110A (en) 1997-09-22

Family

ID=13909116

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8723296A Pending JPH09250110A (en) 1996-03-15 1996-03-15 Construction method of arch concrete

Country Status (1)

Country Link
JP (1) JPH09250110A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669229A (en) * 2014-01-04 2014-03-26 中铁二十五局集团第二工程有限公司 Device for preventing arch frame from rolling over in dragging process
CN107245955A (en) * 2017-08-06 2017-10-13 中国水利水电第七工程局成都水电建设工程有限公司 A kind of band translation sliding formwork spirally falls the cast-in-place beam forms of rack supporting device
CN112709153A (en) * 2020-12-30 2021-04-27 中铁二院工程集团有限责任公司 Method for adjusting bridge deck line shape of high-speed rail large-span deck type arch bridge in operation period
CN113389146A (en) * 2021-06-29 2021-09-14 中交二公局第七工程有限公司 Highway bridge and culvert supporting structure for bridge engineering
CN113818355A (en) * 2021-10-13 2021-12-21 中电建十一局工程有限公司 Method for adjusting installation deviation of arch rib of large-span steel pipe arch bridge

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669229A (en) * 2014-01-04 2014-03-26 中铁二十五局集团第二工程有限公司 Device for preventing arch frame from rolling over in dragging process
CN103669229B (en) * 2014-01-04 2015-11-18 中铁二十五局集团第二工程有限公司 A kind of device preventing bow member from turning on one's side in heave
CN107245955A (en) * 2017-08-06 2017-10-13 中国水利水电第七工程局成都水电建设工程有限公司 A kind of band translation sliding formwork spirally falls the cast-in-place beam forms of rack supporting device
CN112709153A (en) * 2020-12-30 2021-04-27 中铁二院工程集团有限责任公司 Method for adjusting bridge deck line shape of high-speed rail large-span deck type arch bridge in operation period
CN112709153B (en) * 2020-12-30 2022-04-26 中铁二院工程集团有限责任公司 Method for adjusting bridge deck line shape of high-speed rail large-span deck type arch bridge in operation period
CN113389146A (en) * 2021-06-29 2021-09-14 中交二公局第七工程有限公司 Highway bridge and culvert supporting structure for bridge engineering
CN113389146B (en) * 2021-06-29 2022-09-20 中交二公局第七工程有限公司 Highway bridge and culvert supporting structure for bridge engineering
CN113818355A (en) * 2021-10-13 2021-12-21 中电建十一局工程有限公司 Method for adjusting installation deviation of arch rib of large-span steel pipe arch bridge

Similar Documents

Publication Publication Date Title
CN112095495A (en) Bridge underpinning support structure and construction method
JPH09217321A (en) Arch concrete work execution method
JPH09250110A (en) Construction method of arch concrete
JPH10183999A (en) Method of building movable form for arched concrete body
JPH07300817A (en) Concrete-filled steel pipe truss pier and construction method
JPH08134847A (en) Erection method of steel-pipe arch
JP2691260B2 (en) Form support for arch concrete construction
JP2858176B2 (en) Formwork support for construction of art concrete
JPH09217320A (en) Arch concrete work execution method
CN218059930U (en) Steel pipe concrete arch bridge arch rib vertical splicing hydraulic jig frame
CN217352174U (en) Pier edge side span cast-in-place support
JPH10183998A (en) Form timbering for building arched concrete body
JP2516357B2 (en) Form support for arch concrete construction
JPH07189217A (en) Form support for construction of concrete arch
JP2516358B2 (en) Form support for arch concrete construction
JP2977273B2 (en) Formwork support for arch concrete construction
SU1491981A1 (en) Support arrangement for column
CN116463956A (en) Continuous beam bridge low pier curved surface hollow column nondestructive support template system and construction method
JP2563808B2 (en) Form support for arch concrete construction
JP2700163B2 (en) Formwork support for arch concrete construction
CN117403557A (en) Y-shaped pier construction system and construction method for long-span arch continuous rigid frame bridge
US3833959A (en) Method of erecting a cantilever truss bridge; bridge; panel for a bridge; and dummy chords for panel
JP2691261B2 (en) Facility method of arch form support
JPH0849417A (en) Method for installing formwork during construction of arch concrete
JPH05280013A (en) Process for forming arch concrete with use of arch-like form timberwork