JPH09208152A - Centering device for elevator guide rail - Google Patents

Centering device for elevator guide rail

Info

Publication number
JPH09208152A
JPH09208152A JP2264996A JP2264996A JPH09208152A JP H09208152 A JPH09208152 A JP H09208152A JP 2264996 A JP2264996 A JP 2264996A JP 2264996 A JP2264996 A JP 2264996A JP H09208152 A JPH09208152 A JP H09208152A
Authority
JP
Japan
Prior art keywords
rail
members
hoistway
centering
slide member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2264996A
Other languages
Japanese (ja)
Other versions
JP3083256B2 (en
Inventor
Ryoetsu Kanayama
良悦 金山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Building Systems Co Ltd
Original Assignee
Hitachi Building Systems Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Building Systems Co Ltd filed Critical Hitachi Building Systems Co Ltd
Priority to JP08022649A priority Critical patent/JP3083256B2/en
Publication of JPH09208152A publication Critical patent/JPH09208152A/en
Priority to IDP973000A priority patent/ID19317A/en
Application granted granted Critical
Publication of JP3083256B2 publication Critical patent/JP3083256B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B19/00Mining-hoist operation
    • B66B19/002Mining-hoist operation installing or exchanging guide rails

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

PROBLEM TO BE SOLVED: To precisely carry out centering of a guide rail in a short, time by arranging a position adjusting means by which a mounting position of a slide member to a base member and a mounting position of a gauge member to the slide member can be regulated. SOLUTION: When an adjusting screw part 37 in the first position adjusting device 42 is rotated, a slide member 38 is shifted in the lateral direction. Subsequently, adjusting screw parts 48a, 48b in the second position adjusting devices 481, 482 are rotated, and a gauge member 35 is properly rotated clockwise/ counterclockwise toward the slide member 38 on the horizontal plane, so that rail members 4a, 5a held by the gauge member 35 are shifted in the vertical direction. In this way, centering of the rail members 4a, 5a is carried out.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、据付過程のエレベ
ータにおいて、ガイドレール用のレール部材を昇降路壁
に取り付ける際の芯出し作業に用いて好適な、エレベー
タガイドレールの芯出し装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an elevator guide rail centering device suitable for centering work when mounting a rail member for a guide rail to a hoistway wall in an elevator in the process of installation.

【0002】[0002]

【従来の技術】エレベータガイドレールの芯出し装置と
しては、従来、特開昭61−127583号公報に記載
されている技術が広く知られている。そこで、かかる従
来技術を、図11ないし図14を用いて説明する。
2. Description of the Related Art As a centering device for elevator guide rails, the technique disclosed in Japanese Patent Laid-Open No. 61-127583 has been widely known. Therefore, such a conventional technique will be described with reference to FIGS. 11 to 14.

【0003】まず、ガイドレール用のレール部材を昇降
路壁に取り付ける作業の概略について述べると、図11
および図13に示すように、昇降路3内に一対のピアノ
線1a,1bを垂下させて張設した後、順次連結した複
数のレール部材4a,4b,4c,……を一方のピアノ
線1aを基準として該ピアノ線1a側の昇降路壁に芯出
し固定することにより、昇降路3の全長にわたって立設
したガイドレール4となし、同様に、順次連結した複数
のレール部材5a,5b,……を他方のピアノ線1bを
基準として該ピアノ線1b側の昇降路壁に芯出し固定す
ることにより、昇降路3の全長にわたって立設したガイ
ドレール5となす。
First, the outline of the work for attaching the rail member for the guide rail to the hoistway wall will be described with reference to FIG.
As shown in FIG. 13 and FIG. 13, a pair of piano wires 1a, 1b are hung and stretched in the hoistway 3, and then a plurality of rail members 4a, 4b, 4c ,. Is fixed to the hoistway wall on the piano wire 1a side as a reference to form a guide rail 4 standing upright over the entire length of the hoistway 3, and similarly a plurality of rail members 5a, 5b, ... Is centered and fixed to the hoistway wall on the piano wire 1b side with respect to the other piano wire 1b, thereby forming a guide rail 5 standing upright over the entire length of the hoistway 3.

【0004】図12は、こうして昇降路3内にガイドレ
ール4,5を立設する作業の手順を示すフローチャート
である。同図に示すように、まずステップS1で、建屋
の所定位置を基準として一対のピアノ線1a,1bを機
械室2から昇降路3内へ垂下させる。次にステップS2
で、昇降路3の下部において、一方のガイドレール4の
最下部レール部材4nをピアノ線1aを基準にしながら
芯出し固定するとともに、他方のガイドレール5の最下
部レール部材をピアノ線1bを基準にしながら芯出し固
定する。しかる後、ステップS3で、図11に示すよう
にガイドレール4のレール部材4aをウインチ6で吊り
上げ、このレール部材4aの下端に別のレール部材4b
の上端を接続し、さらに接続したレール部材4a,4b
を吊り上げて、レール部材4bの下端に別のレール部材
4cの上端を接続するという作業を繰り返し、ステップ
S4で最下部レール部材4nを接続することにより、こ
れら複数のレール部材4a,4b,……の一体品で昇降
路3の全長にわたって延びるガイドレール4を形成し、
ステップS5において、このガイドレール4の上端(つ
まりレール部材4aの上端)を機械室床2aにて保持す
る。なお、ガイドレール5のレール部材についても同様
に、吊り上げ作業と接続作業を繰り返すことにより、複
数のレール部材5a,5b,……の一体品で昇降路3の
全長にわたって延びるガイドレール5を形成し、このガ
イドレール5の上端を機械室床2aにて保持する。次に
ステップS6で、ガイドレール4,5の最下部レール部
材と摺動可能に係合するかご枠7および作業床8(図1
1,13参照)を、機械室2内の巻上機の駆動により上
昇させ、ステップS7において、作業床8上に乗った作
業者がガイドレール4,5の各レール部材を芯出しして
昇降路壁に固定する。
FIG. 12 is a flow chart showing the procedure of the work for vertically setting the guide rails 4, 5 in the hoistway 3. As shown in the figure, first, in step S1, a pair of piano wires 1a and 1b are hung from the machine room 2 into the hoistway 3 with reference to a predetermined position of the building. Next, step S2
In the lower part of the hoistway 3, the lowermost rail member 4n of one guide rail 4 is centered and fixed while the piano wire 1a is used as a reference, and the lowermost rail member of the other guide rail 5 is used as the piano wire 1b. While fixing, center and fix. Then, in step S3, as shown in FIG. 11, the rail member 4a of the guide rail 4 is lifted by a winch 6, and another rail member 4b is attached to the lower end of the rail member 4a.
Rail members 4a, 4b connected to the upper ends of the
Is repeated and the upper end of another rail member 4c is connected to the lower end of the rail member 4b, and the lowermost rail member 4n is connected in step S4, whereby the plurality of rail members 4a, 4b ,. The guide rail 4 extending over the entire length of the hoistway 3 is formed by
In step S5, the upper end of the guide rail 4 (that is, the upper end of the rail member 4a) is held on the machine room floor 2a. Similarly, with respect to the rail member of the guide rail 5, by repeating the lifting operation and the connecting operation, the guide rail 5 extending over the entire length of the hoistway 3 is formed by an integrated product of a plurality of rail members 5a, 5b, .... The upper end of the guide rail 5 is held by the machine room floor 2a. Next, in step S6, the car frame 7 and the work floor 8 (see FIG. 1) slidably engaged with the lowermost rail members of the guide rails 4 and 5.
1 and 13) by driving the hoisting machine in the machine room 2, and in step S7, an operator on the work floor 8 centers and lifts each rail member of the guide rails 4 and 5. Secure to the road wall.

【0005】そして、かかる芯出し作業を行う際に、従
来、図13の斜視図および図14の平面図に示すような
芯出し装置9が用いられる。
In performing such centering work, conventionally, a centering device 9 as shown in the perspective view of FIG. 13 and the plan view of FIG. 14 is used.

【0006】すなわち、この芯出し装置9は、作業床8
上に設置されて水平方向に延びる棒状の基部10と、こ
の基部10の一端部に設けられた把持装置11および基
準部12と、基部10の他端部に設けられた把持装置1
3および基準部14とによって概略構成されている。こ
こで、把持装置11は、ガイドレール4を構成するレー
ル部材(例えばレール部材4a)を挟む固定部材11a
および可動部材11bと、これら両部材11a,11b
間を締め付けて該レール部材を把持するボルト11cと
からなる。また、基準部12には、その一端部にX方向
(図14参照)の基準面12aが形成されているととも
に、その上面にY方向(水平面内でX方向と直交する方
向)の基準線12bが付されている。同様に、把持装置
13は、ガイドレール5を構成するレール部材(例えば
レール部材5a)を挟む固定部材13aおよび可動部材
13bと、これら両部材13a,13b間を締め付けて
該レール部材を把持するボルト13cとからなり、また
基準部14には、その一端部にX方向の基準面14aが
形成されているとともに、その上面にY方向の基準線1
4bが付されている。
That is, the centering device 9 is used for the work floor 8
A bar-shaped base 10 installed on the top and extending in the horizontal direction, a gripping device 11 and a reference part 12 provided at one end of the base 10, and a gripping device 1 provided at the other end of the base 10.
3 and the reference unit 14 are generally configured. Here, the gripping device 11 includes a fixing member 11a that sandwiches a rail member (for example, the rail member 4a) that constitutes the guide rail 4.
And the movable member 11b and these members 11a and 11b
It is composed of a bolt 11c for tightening the space and gripping the rail member. The reference portion 12 has a reference surface 12a in the X direction (see FIG. 14) formed at one end thereof, and a reference line 12b in the Y direction (direction orthogonal to the X direction in the horizontal plane) on the upper surface thereof. Is attached. Similarly, the gripping device 13 includes a fixed member 13a and a movable member 13b that sandwich a rail member (for example, a rail member 5a) that constitutes the guide rail 5, and a bolt that clamps between the both members 13a and 13b to grip the rail member. 13c, the reference portion 14 has an X-direction reference surface 14a formed at one end thereof, and the Y-direction reference line 1 is formed on the upper surface thereof.
4b is attached.

【0007】次に、上述した構成の芯出し装置9を用い
て行われるレール部材4a,5aの芯出し固定作業につ
いて説明する。
Next, the centering and fixing work of the rail members 4a and 5a performed by using the centering device 9 having the above-mentioned structure will be described.

【0008】まず、レール部材4aの案内部41aを把
持装置11にて把持し、この状態で該レール部材4aの
固定部42aをレールクリップ15aに取り付けること
により、レール側ブラケット15bおよび壁側ブラケッ
ト15cを介して、該レール部材4aを昇降路壁20に
仮固定する。なお、レールクリップ15aはレール側ブ
ラケット15bに一体化されていて、このレール側ブラ
ケット15bは壁側ブラケット15cにボルト結合され
ていて、この壁側ブラケット15cは昇降路壁20にボ
ルト結合されている。同様に、レール部材5aの案内部
51aを把持装置13にて把持し、この状態で該レール
部材5aの固定部52aをレールクリップ16aに取り
付けることにより、レール側ブラケット16bおよび壁
側ブラケット16cを介して、該レール部材5aを昇降
路壁21に仮固定する。
First, the guide portion 41a of the rail member 4a is grasped by the grasping device 11, and the fixing portion 42a of the rail member 4a is attached to the rail clip 15a in this state, whereby the rail side bracket 15b and the wall side bracket 15c. The rail member 4a is temporarily fixed to the hoistway wall 20 via. The rail clip 15a is integrated with the rail side bracket 15b, the rail side bracket 15b is bolted to the wall side bracket 15c, and the wall side bracket 15c is bolted to the hoistway wall 20. . Similarly, the guide portion 51a of the rail member 5a is grasped by the grasping device 13, and the fixing portion 52a of the rail member 5a is attached to the rail clip 16a in this state, so that the rail side bracket 16b and the wall side bracket 16c are interposed. Then, the rail member 5a is temporarily fixed to the hoistway wall 21.

【0009】次いで、作業者はハンマーでレール側ブラ
ケット15bを叩きながらレール部材4aをX方向へ移
動させて、ピアノ線1aから基準面12aまでの距離が
所定寸法となるように設定し、かつ、ハンマーで壁側ブ
ラケット15cを叩きながらレール部材4aをY方向へ
移動させて、ピアノ線1aから基準線12bまでの距離
が所定寸法となるように設定する。同様に、作業者はハ
ンマーでレール側ブラケット16bを叩きながらレール
部材5aをX方向へ移動させて、ピアノ線1bから基準
面14aまでの距離が所定寸法となるように設定し、か
つ、ハンマーで壁側ブラケット16cを叩きながらレー
ル部材5aをY方向へ移動させて、ピアノ線1bから基
準線14bまでの距離が所定寸法となるように設定す
る。
Next, the operator moves the rail member 4a in the X direction while hitting the rail side bracket 15b with a hammer to set the distance from the piano wire 1a to the reference surface 12a to a predetermined dimension, and The rail member 4a is moved in the Y direction while hitting the wall-side bracket 15c with a hammer, and the distance from the piano wire 1a to the reference line 12b is set to a predetermined dimension. Similarly, the operator moves the rail member 5a in the X direction while striking the rail-side bracket 16b with a hammer to set the distance from the piano wire 1b to the reference surface 14a to a predetermined dimension, and with a hammer. The rail member 5a is moved in the Y direction while striking the wall-side bracket 16c so that the distance from the piano wire 1b to the reference line 14b is set to a predetermined dimension.

【0010】こうしてレール部材4a,5aの芯出しを
完了させたなら、レール側ブラケット15b,16bお
よび壁側ブラケット15c,16cの固定ボルトを本締
めすることにより、レール部材4a,5aはそれぞれ昇
降路壁20,21に本固定されることとなる。
When the centering of the rail members 4a and 5a is completed in this way, the rail members 4a and 5a are respectively moved up and down by fully fastening the fixing bolts of the rail side brackets 15b and 16b and the wall side brackets 15c and 16c. It will be permanently fixed to the walls 20 and 21.

【0011】[0011]

【発明が解決しようとする課題】ところで、上述した従
来の芯出し装置9を用いて行われるエレベータガイドレ
ールの芯出し固定作業では、各レール部材を昇降路壁2
0,21に仮固定した状態で、レール側ブラケット15
b,16bや壁側ブラケット15c,16cをハンマー
等で叩きながら、基準となるピアノ線と該レール部材と
の距離を所定寸法に設定する位置調整作業を行わねばな
らないが、この位置調整作業には多大な時間を要するの
で、作業効率が悪いという不具合があった。
By the way, in the centering and fixing work of the elevator guide rail performed by using the above-mentioned conventional centering device 9, each rail member is attached to the hoistway wall 2.
The rail side bracket 15 is temporarily fixed to 0 and 21.
While the b, 16b and the wall side brackets 15c, 16c are hit with a hammer or the like, a position adjustment work for setting the distance between the reference piano wire and the rail member to a predetermined dimension must be performed. Since it takes a lot of time, there is a problem that work efficiency is poor.

【0012】また、相対向する昇降路壁20,21は原
則として互いの平行度を保った状態に仕上げられていな
ければならないが、実際には昇降路壁の一部が鉛直面に
対し若干傾いて仕上げられることも多く、そのような場
合、平行度が良好でない昇降路壁20,21に取着され
る壁側ブラケット15c,16cどうしの平行度も悪く
なるため、壁側ブラケット15c,16cおよびレール
側ブラケット15b,16bを介して同等の高さに仮固
定された一対のレール部材(例えばレール部材4a,5
a)どうしは互いに捻じれた状態となる。そして、この
ような捻じれの関係にある一対のレール部材に芯出し装
置9を取り付けるべく、その案内部(例えば案内部41
a,51a)を把持装置11,13にて把持すると、こ
れら案内部には過大な曲げ応力が作用するので自身の弾
性で曲がる虞があり、その場合、芯出し固定が終了して
把持装置11,13を取り外したときにレール部材の該
案内部の曲がりが元に戻るので、芯出し位置に狂いを生
じ、芯出し精度の劣化を余儀なくされてしまう。
In principle, the hoistway walls 20 and 21 facing each other must be finished in a state where their parallelism is maintained, but in reality, a part of the hoistway walls is slightly inclined with respect to the vertical plane. In many cases, the parallelism between the wall-side brackets 15c and 16c attached to the hoistway walls 20 and 21 having poor parallelism also deteriorates. A pair of rail members (for example, rail members 4a and 5) temporarily fixed to the same height via the rail-side brackets 15b and 16b.
a) The two are twisted with each other. Then, in order to attach the centering device 9 to the pair of rail members having such a twisted relationship, the guide portion (for example, the guide portion 41) thereof is attached.
a, 51a) is gripped by the gripping devices 11 and 13, there is a possibility that the guide portions are bent due to excessive bending stress, and in that case, the centering and fixing are completed and the gripping device 11 is terminated. Since the bending of the guide portion of the rail member returns to its original position when the rails 13 and 13 are removed, the centering position is misaligned and the centering accuracy is inevitably deteriorated.

【0013】本発明は、このような従来技術の課題に鑑
みてなされたもので、その目的は、ガイドレールを短時
間で精度良く芯出しできるエレベータガイドレールの芯
出し装置を提供することにある。
The present invention has been made in view of the above problems of the prior art, and an object thereof is to provide an elevator guide rail centering device capable of accurately centering the guide rail in a short time. .

【0014】[0014]

【課題を解決するための手段】上述した本発明の目的
は、昇降路内に垂下させた一対のピアノ線を基準として
ガイドレール用のレール部材の据付固定時の芯出しを行
うエレベータガイドレールの芯出し装置において、ベー
ス部材の両端部に該ベース部材からの突出量が変更可能
な伸長部材を設けて、これら一対の伸長部材を介して相
対向する昇降路壁に突っ張り力を付与することにより昇
降路内に保持可能な突っ張り保持手段と、前記ベース部
材に取着されるスライド部材と、このスライド部材の前
記ベース部材に対する取付位置を前記伸長部材の突出方
向(X方向)に沿って調整するための第1の位置調整手
段と、相対向する昇降路壁に据付固定される一対の前記
レール部材を把持可能なレール把持手段を設けて前記ス
ライド部材に取着されるゲージ部材と、このゲージ部材
の前記スライド部材に対する取付位置を前記伸長部材の
突出方向と直交する水平方向(Y方向)に沿って調整す
るための第2の位置調整手段とを備えることによって、
達成される。
SUMMARY OF THE INVENTION The above-mentioned object of the present invention is to provide an elevator guide rail that performs centering when installing and fixing a rail member for a guide rail with reference to a pair of piano wires suspended in the hoistway. In the centering device, by providing extension members whose projecting amount from the base member can be changed at both ends of the base member, and by applying a tension force to the hoistway walls facing each other through the pair of extension members, A tension holding means capable of being held in the hoistway, a slide member attached to the base member, and a mounting position of the slide member with respect to the base member are adjusted along a protruding direction (X direction) of the extension member. And a rail gripping means capable of gripping a pair of the rail members installed and fixed to the hoistway walls facing each other, and attached to the slide member. That a gage member, by providing a second position adjusting means for adjusting along the horizontal direction (Y direction) perpendicular to the projecting direction of the said elongated member to the mounting position with respect to the slide member of the gauge member,
Achieved.

【0015】このように構成される芯出し装置は、相対
向する昇降路壁間に突っ張り力によってベース部材を保
持した状態で、第1の位置調整手段によりスライド部材
を該ベース部材に対してX方向へ適宜変位させるととも
に、第2の位置調整手段により、同等の高さに据付固定
される左右一対のレール部材を把持したゲージ部材を該
スライド部材に対してY方向へ適宜変位させることがで
きるので、前記一対のレール部材どうしを所望の相対位
置関係に保ったまま、その芯出しを行うことができる。
したがって、昇降路壁に仮固定したブラケットをハンマ
ー等で叩きながらレール部材の位置調整を行うという従
来の芯出し作業に比べて、作業効率が大幅に向上し、ま
た、昇降路壁の仕上がり状態が良好でない場合にも、レ
ール部材に不所望な曲げ応力を作用させることなく高精
度な芯出しが行えるようになっている。
In the centering device thus constructed, the slide member is moved relative to the base member by the first position adjusting means while holding the base member by the tension force between the hoistway walls facing each other. In addition to being appropriately displaced in the Y direction, the second position adjusting means can appropriately displace in the Y direction with respect to the slide member the gauge member holding the pair of left and right rail members installed and fixed at the same height. Therefore, the pair of rail members can be centered while maintaining the desired relative positional relationship.
Therefore, compared with the conventional centering work in which the position of the rail member is adjusted by hitting the bracket temporarily fixed to the hoistway wall with a hammer etc., the work efficiency is significantly improved, and the finished state of the hoistway wall is improved. Even when it is not good, it is possible to perform highly accurate centering without applying an undesired bending stress to the rail member.

【0016】さらに、上述した構成に加えて、前記第2
の位置調整手段が、前記スライド部材に回動可能に取着
せしめた第1のナット部材と、前記ゲージ部材に回動可
能に取着せしめた第2のナット部材と、これら第1およ
び第2のナット部材どうしを螺合状態で連結する調整ね
じ部材とを備え、この調整ねじ部材を回して前記第1お
よび第2のナット部材どうしの間隔を変更させると前記
ゲージ部材が水平面内で回転するように構成しておけ
ば、前記Y方向の位置調整作業が簡便に行える。
Further, in addition to the above-mentioned structure, the second
The position adjusting means rotatably attached to the slide member, a second nut member rotatably attached to the gauge member, and the first and second Adjusting screw member for connecting the nut members to each other in a screwed state, and when the adjusting screw member is rotated to change the interval between the first and second nut members, the gauge member rotates in a horizontal plane. With this configuration, the position adjustment work in the Y direction can be easily performed.

【0017】[0017]

【発明の実施の形態】以下、本発明の実施形態を図1な
いし図10に基づいて説明する。ここで、図1は本発明
によるエレベータガイドレールの芯出し装置を示す平面
図、図2は該芯出し装置の正面図、図3は該芯出し装置
を作業床上に配置した芯出し準備段階の平面図、図4は
該芯出し装置の構成要素である突っ張り保持装置を示す
要部平面図、図5は該芯出し装置の構成要素であるレー
ル把持装置がレール部材を把持する前の状態を示す要部
平面図、図6は図5に示すレール把持装置をレール部材
の背面に当接させる工程を示す要部平面図、図7は図6
に示すレール把持装置をレール部材のガイド面に当接さ
せる工程を示す要部平面図、図8は図7に示すレール把
持装置でレール部材を把持した状態を示す要部平面図、
図9は作業床上に配置した該芯出し装置による芯出し作
業中の平面図、図10は該芯出し装置によって芯出しし
たレール部材を昇降路壁に固定するブラケットの取付状
態を示す要部平面図である。
BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of the present invention will be described below with reference to FIGS. 1 is a plan view showing an elevator guide rail centering device according to the present invention, FIG. 2 is a front view of the centering device, and FIG. 3 is a centering preparation step in which the centering device is arranged on a work floor. FIG. 4 is a plan view of a main portion showing a tension holding device which is a component of the centering device, and FIG. 5 shows a state before a rail gripping device which is a component of the centering device grips a rail member. 6 is a plan view of relevant parts, FIG. 6 is a plan view of relevant parts showing the step of bringing the rail gripping device shown in FIG. 5 into contact with the rear surface of the rail member, and FIG.
FIG. 8 is a main part plan view showing a step of bringing the rail gripping device shown in FIG. 6 into contact with the guide surface of the rail member, FIG. 8 is a main part plan view showing a state where the rail gripping device shown in FIG.
9 is a plan view of the centering device placed on the work floor during the centering work, and FIG. 10 is a plan view of a main part showing a mounting state of a bracket for fixing the rail member centered by the centering device to the hoistway wall. It is a figure.

【0018】これらの図に示す芯出し装置は、筒状のベ
ース部材300の両端部に伸縮機構部301,302を
設けてなる突っ張り保持装置30と、ベース部材300
に固設された一対の案内部材18a,18bを貫通して
該ベース部材300と平行に配置されたスライド部材3
8と、このスライド部材38のベース部材300に対す
る取付位置を図1の左右方向に沿って調整するための第
1の位置調整装置42と、相対向する位置に固定される
一対のレール部材を把持可能なレール把持装置451,
452や位置決めの基準となる基準部材41a,41b
を設けてスライド部材38に取着されるゲージ部材35
と、このゲージ部材35のスライド部材38に対する取
付位置を図1の上下方向に沿って調整するための第2の
位置調整装置481,482とによって、概略構成され
ている。
The centering device shown in these figures includes a tension holding device 30 in which expansion and contraction mechanism portions 301 and 302 are provided at both ends of a cylindrical base member 300, and a base member 300.
A slide member 3 which is arranged in parallel with the base member 300 by penetrating a pair of guide members 18a and 18b fixed to the base member 300.
8, a first position adjusting device 42 for adjusting the mounting position of the slide member 38 with respect to the base member 300 along the left-right direction in FIG. 1, and a pair of rail members fixed at opposite positions. Possible rail gripping device 451
452 and reference members 41a and 41b serving as a reference for positioning
And a gauge member 35 attached to the slide member 38.
And second position adjusting devices 481 and 482 for adjusting the mounting position of the gauge member 35 with respect to the slide member 38 in the vertical direction of FIG.

【0019】前記突っ張り保持装置30の伸縮機構部3
01,302はそれぞれ、ベース部材300に対してス
ライド可能に取り付けられた伸長部材33a,33b
と、各伸長部材33a,33bの先端部に螺合して昇降
路壁20,21に当接可能なジャッキボルト31a,3
1bと、回動操作によって伸長部材33a,33bをベ
ース部材300に固定したり固定解除できるレバー32
a,32bとを備えているので、各伸長部材33a,3
3bのベース部材300からの突出量や、各ジャッキボ
ルト31a,31bの伸長部材33a,33bからの突
出量に応じて、突っ張り保持装置30の全長は変更可能
である。つまり、各伸長部材33a,33bの突出量や
各ジャッキボルト31a,31bの突出量を調整して、
この突っ張り保持装置30の全長を適宜寸法に設定して
やれば、相対向する昇降路壁20,21にジャッキボル
ト31a,31bの先端を押し当てて突っ張り力を生じ
させることができるので、ベース部材300を昇降路内
に安定した状態で保持することができる。
Expansion / contraction mechanism section 3 of the strut holding device 30.
01 and 302 are extension members 33a and 33b slidably attached to the base member 300, respectively.
And jack bolts 31a, 3 which can be screwed onto the tip ends of the respective extension members 33a, 33b and abut on the hoistway walls 20, 21.
1b and a lever 32 that can fix or release the extension members 33a and 33b to the base member 300 by rotating operation.
a, 32b, the extension members 33a, 3
The total length of the bracing / holding device 30 can be changed according to the amount of protrusion of 3b from the base member 300 and the amount of protrusion of the jack bolts 31a and 31b from the extension members 33a and 33b. That is, by adjusting the amount of protrusion of each extension member 33a, 33b and the amount of protrusion of each jack bolt 31a, 31b,
If the overall length of the bracing / holding device 30 is appropriately set, the bracing force can be generated by pressing the tips of the jack bolts 31a and 31b against the hoistway walls 20 and 21 facing each other. It can be stably held in the hoistway.

【0020】前記第1の位置調整装置42は、ベース部
材300に固設された雌ねじ部36と、この雌ねじ部3
6に螺合する調整ねじ部37と、前記スライド部材38
に固設されて調整ねじ部37を保持している連結部19
とで構成されており、調整ねじ部37を回転させること
によりスライド部材38を図1の左右方向に沿って、つ
まり前記伸長部材33a,33bのスライド方向に沿っ
て、変位させることができる。
The first position adjusting device 42 includes a female screw portion 36 fixed to the base member 300 and the female screw portion 3
6, an adjusting screw portion 37 screwed onto the screw 6, and the slide member 38.
The connecting portion 19 fixed to and holding the adjusting screw portion 37.
By rotating the adjusting screw portion 37, the slide member 38 can be displaced along the left-right direction of FIG. 1, that is, along the sliding direction of the extension members 33a and 33b.

【0021】前記第2の位置調整装置481は、スライ
ド部材38に回動可能に嵌合する雌ねじ軸46aと、こ
の雌ねじ軸46aに螺合する調整ねじ部48aと、前記
ゲージ部材35に回動可能に嵌合しつつ調整ねじ部48
aを保持している連結軸47aとで構成されており、同
様に、他方の第2の位置調整装置482は、スライド部
材38に回動可能に嵌合する雌ねじ軸46bと、この雌
ねじ軸46bに螺合する調整ねじ部48bと、前記ゲー
ジ部材35に回動可能に嵌合しつつ調整ねじ部48bを
保持している連結軸47bとで構成されている。また、
第2の位置調整装置481の雌ねじ軸46aと第2の位
置調整装置482の連結軸47bは、リンク部材34を
介して互いに連結されている。それゆえ、調整ねじ部4
8aを回転させることによって雌ねじ軸46aと連結軸
47aとの間隔を変えることができ、その際ゲージ部材
35は他方の連結軸47bを中心として回転移動するこ
とになる。同様に、調整ねじ部48bを回転させること
によって雌ねじ軸46bと連結軸47bとの間隔を変え
ることができ、その際ゲージ部材35は他方の連結軸4
7aを中心として回転移動することになる。換言するな
ら、調整ねじ部48a,48bを適宜回転させることに
より、スライド部材38に対するゲージ部材35の取付
位置を図1の上下方向に沿って変位させることができ
る。
The second position adjusting device 481 has a female screw shaft 46a that is rotatably fitted to the slide member 38, an adjusting screw portion 48a that is screwed to the female screw shaft 46a, and is rotatable with respect to the gauge member 35. Adjusting screw part 48 while fitting as much as possible
Similarly, the other second position adjusting device 482 has a female screw shaft 46b rotatably fitted to the slide member 38 and the female screw shaft 46b. It is composed of an adjusting screw portion 48b that is screwed into the above, and a connecting shaft 47b that rotatably fits to the gauge member 35 and holds the adjusting screw portion 48b. Also,
The female screw shaft 46a of the second position adjusting device 481 and the connecting shaft 47b of the second position adjusting device 482 are connected to each other via the link member 34. Therefore, the adjusting screw 4
By rotating 8a, the distance between the female screw shaft 46a and the connecting shaft 47a can be changed, and in this case, the gauge member 35 rotates about the other connecting shaft 47b. Similarly, the distance between the female screw shaft 46b and the connecting shaft 47b can be changed by rotating the adjusting screw portion 48b, in which case the gauge member 35 causes the other connecting shaft 4 to rotate.
It will rotate around 7a. In other words, the mounting position of the gauge member 35 with respect to the slide member 38 can be displaced in the vertical direction of FIG. 1 by appropriately rotating the adjusting screw portions 48a and 48b.

【0022】また、このゲージ部材35に設けられてい
るレール把持装置451,452はそれぞれ、相対向す
る昇降路壁20,21に固定される各レール部材(例え
ばレール部材4a,5a)の背面に当接させるための開
閉可能な背面当接部39a,39bと、該レール部材の
ガイド面に当接させるためのガイド面当接部40a,4
0bと、背面当接部39a,39bを引っ張って該レー
ル部材を前記基準部材41a,41bに押し当てるため
の引っ張りクランプ44a,44bと、該レール部材を
基準部材41a,41bとの間に挟圧保持するための挟
圧ねじ49a,49bとで構成されている。
The rail gripping devices 451 and 452 provided on the gauge member 35 are respectively attached to the back surfaces of the rail members (for example, the rail members 4a and 5a) fixed to the hoistway walls 20 and 21 facing each other. Openable and closable back surface contact portions 39a, 39b and guide surface contact portions 40a, 4 for contacting the guide surface of the rail member.
0b, pulling clamps 44a and 44b for pulling back contact portions 39a and 39b to press the rail member against the reference members 41a and 41b, and clamping the rail member between the reference members 41a and 41b. It is composed of pinching screws 49a and 49b for holding.

【0023】なお、基準部材41a,41bにはそれぞ
れ、レール把持装置451,452との間にレール部材
を挟持したときにピアノ線1a,1bとの位置関係を測
定する基準となる基準板43a,43bが設けられてい
る。また、ゲージ部材35上には、このゲージ部材35
や基準部材41a,41bの水平度を確認するための気
泡管50が固設されている。
The reference members 41a and 41b respectively have reference plates 43a, which serve as a reference for measuring the positional relationship with the piano wires 1a, 1b when the rail member is sandwiched between the rail gripping devices 451 and 452. 43b is provided. Further, on the gauge member 35, the gauge member 35
A bubble tube 50 for confirming the horizontality of the reference members 41a and 41b is fixed.

【0024】次に、上述した芯出し装置を用いて行うエ
レベータガイドレールの芯出し作業について説明する。
Next, the centering work of the elevator guide rail performed using the above-mentioned centering device will be described.

【0025】いま、レール部材4a,5aの芯出しを行
うものとすると、まず、図示せぬかご枠に設置された作
業床8の手摺り51上に、図3に示すように、ベース部
材300に対し伸長部材33a,33bを最大限没入さ
せて短くした状態の突っ張り保持装置30を取り付ける
が、このとき、レール把持装置451,452はまだレ
ール部材4a,5aを挟持しない開放状態としておく。
そして、各レール部材4a,5aを据付固定する所定位
置へレール把持装置451,452が来るように前記か
ご枠を移動させた後、図4に示すように、ジャッキボル
ト31aが昇降路壁20に当接するまで伸長部材33a
をベース部材300から突出させて、レバー32aの回
転操作により該伸長部材33aをスライド不能となすと
ともに、ジャッキボルト31bが昇降路壁21に当接す
るまで伸長部材33bをベース部材300から突出させ
て、レバー32bの回転操作により該伸長部材33bを
スライド不能となす。その結果、ベース部材300と伸
長部材33a,33bは一体化された状態で昇降路壁2
0,21間に保持されるので、この状態でジャッキボル
ト31a,31bをそれぞれ伸長部材33a,33bか
ら突出させるべく回すことにより、昇降路壁20,21
にジャッキボルト31a,31bの先端を強く押し当て
て、突っ張り保持装置30を自らの突っ張り力で昇降路
壁20,21間に確実に固定する。
Now, assuming that the rail members 4a and 5a are to be centered, first, on the handrail 51 of the work floor 8 installed in a car frame (not shown), as shown in FIG. On the other hand, the tension holding device 30 in which the extension members 33a and 33b are fully retracted and shortened is attached, but at this time, the rail gripping devices 451 and 452 are in an open state in which the rail members 4a and 5a are not yet clamped.
Then, after moving the car frame so that the rail gripping devices 451 and 452 come to the predetermined positions where the rail members 4a and 5a are installed and fixed, the jack bolts 31a are attached to the hoistway wall 20 as shown in FIG. Extension member 33a until abutting
Is made to protrude from the base member 300, the extension member 33a is made non-slideable by the rotation operation of the lever 32a, and the extension member 33b is made to protrude from the base member 300 until the jack bolt 31b comes into contact with the hoistway wall 21. The extension member 33b cannot be slid by rotating the lever 32b. As a result, the base member 300 and the extension members 33a and 33b are integrated with each other to form the hoistway wall 2.
Since it is held between 0 and 21, by rotating the jack bolts 31a and 31b so as to project from the extension members 33a and 33b in this state, the hoistway walls 20 and 21
The tip ends of the jack bolts 31a and 31b are strongly pressed against and the tie holding device 30 is securely fixed between the hoistway walls 20 and 21 by its own traction force.

【0026】しかる後、図5〜8に示すような手順で、
レール把持装置451,452によるレール部材4a,
5aの挟圧保持を行い、昇降路壁20,21間に突っ張
り力で保持されている突っ張り保持装置30を介して、
これらのレール部材4a,5aを間接的に昇降路壁2
0,21に固定した状態となす。すなわち、レール把持
装置451について述べると、最初は図5に鎖線で示す
ように一対の背面当接部39aを広げた開放状態となっ
ているが、これらの背面当接部39aを同図の矢印60
方向へ回転させてから、引っ張りクランプ44aのレバ
ー部を引いて各背面当接部39aを図6の矢印61方向
へ移動させることにより、同じく矢印61方向へ引き込
まれるレール部材4aを基準部材41aに押し当てる。
次に、挟圧ねじ49aを回して図7の矢印62方向へ移
動させることにより、ガイド面当接部40aと基準部材
41aとの間にレール部材4aを挟みつけ、これにより
レール部材4aは図8に示すように、各背面当接部39
aとガイド面当接部40aと基準部材41aとで挟圧保
持された状態となる。なお、レール部材5aも同様にし
てレール把持装置452に挟圧保持される。
After that, the procedure as shown in FIGS.
Rail member 4a by rail gripping devices 451 and 452,
5a is clamped and held, and via the tension holding device 30 held by the tension force between the hoistway walls 20 and 21,
These rail members 4a and 5a are indirectly connected to the hoistway wall 2
It is fixed to 0 and 21. That is, when the rail gripping device 451 is described, at first, as shown by a chain line in FIG. 5, the pair of rear surface contact portions 39a are in an open state, and the rear surface contact portions 39a are indicated by arrows in FIG. 60
Direction, and then pulling the lever portion of the tension clamp 44a to move each back contact portion 39a in the direction of arrow 61 in FIG. 6, the rail member 4a also pulled in the direction of arrow 61 becomes the reference member 41a. Press against.
Next, by rotating the pinching screw 49a and moving it in the direction of the arrow 62 in FIG. 7, the rail member 4a is pinched between the guide surface contact portion 40a and the reference member 41a, so that the rail member 4a can As shown in FIG.
It is in a state of being pinched and held by a, the guide surface contact portion 40a, and the reference member 41a. The rail member 5a is also clamped and held by the rail gripping device 452 in the same manner.

【0027】こうしてレール把持装置451,452に
把持されたレール部材4a,5aを突っ張り保持装置3
0を介して間接的に昇降路壁20,21に固定する一連
の作業が終了したなら、これらのレール部材4a,5a
を芯出しするための位置調整作業を行う。
The rail members 4a and 5a thus held by the rail holding devices 451 and 452 are stretched and held by the holding device 3.
When a series of work for indirectly fixing to the hoistway walls 20 and 21 via 0 is completed, these rail members 4a and 5a
Perform position adjustment work for centering.

【0028】かかる位置調整作業は、まず、前記第1の
位置調整装置42の調整ねじ部37を回して、スライド
部材38を図1や図3,9の左右方向(X方向)に変位
させる。このスライド部材38にはゲージ部材35が連
結されていて、このゲージ部材35に設けられているレ
ール把持装置451,452および基準部材41a,4
1bにレール部材4a,5aが挟圧保持されているの
で、調整ねじ部37を回してスライド部材38を変位さ
せるとレール部材4a,5aも同様に変位することにな
り、それゆえ、図9に示す昇降路壁20側のX寸法(ピ
アノ線1aと基準板43aとの間隔)と、昇降路壁21
側のX寸法(ピアノ線1bと基準板43bとの間隔)と
が等しくなるような位置調整が、容易に行える。
In the position adjusting work, first, the adjusting screw portion 37 of the first position adjusting device 42 is rotated to displace the slide member 38 in the left-right direction (X direction) of FIGS. 1 and 3. A gauge member 35 is connected to the slide member 38, and rail gripping devices 451 and 452 and reference members 41a and 4 provided on the gauge member 35 are connected.
Since the rail members 4a and 5a are clamped and held on the rail member 1b, when the adjusting screw portion 37 is rotated to displace the slide member 38, the rail members 4a and 5a are also displaced. The X dimension on the side of the hoistway wall 20 shown (the distance between the piano wire 1a and the reference plate 43a) and the hoistway wall 21
The position can be easily adjusted so that the X dimension on the side (the distance between the piano wire 1b and the reference plate 43b) becomes equal.

【0029】次いで、前記第2の位置調整装置481,
482の調整ねじ部48a,48bを回して、ゲージ部
材35をスライド部材38に対し水平面内で時計回りの
向きや反時計回りの向きに適宜回転させることにより、
このゲージ部材35に保持されているレール部材4a,
5aを図1や図3,9の上下方向(Y方向)に変位させ
る。したがって、図9に示す昇降路壁20側のY寸法
(ピアノ線1aと基準板43aに付したケガキ線43c
との間隔)と、昇降路壁21側のY寸法(ピアノ線1b
と基準板43bに付したケガキ線43dとの間隔)とが
共に許容値内に収まるような位置調整が容易に行え、レ
ール部材4a,5aをY方向に芯出しした状態で保持で
きる。ただし、第2の位置調整装置481,482のそ
れぞれの調整量が同一とならず、水平面内におけるゲー
ジ部材35の回転が先に調整したX方向の設定位置に微
妙なずれを生じることもあるので、Y方向の位置調整を
行った後、再びX方向の位置を微調整してずれを修正す
る。これにより、レール部材4a,5aは、昇降路内に
おいてX方向およびY方向に芯出しされた状態で保持さ
れることとなる。
Next, the second position adjusting device 481,
By turning the adjusting screw portions 48a and 48b of 482 and appropriately rotating the gauge member 35 with respect to the slide member 38 in the clockwise direction or the counterclockwise direction in the horizontal plane,
The rail member 4a held by the gauge member 35,
5a is displaced in the vertical direction (Y direction) of FIGS. Therefore, the Y dimension on the side of the hoistway wall 20 shown in FIG. 9 (piano wire 1a and marking wire 43c attached to the reference plate 43a)
And the Y dimension on the side of the hoistway wall 21 (piano wire 1b).
And the marking line 43d attached to the reference plate 43b) can be easily adjusted so that both are within the allowable value, and the rail members 4a and 5a can be held in a state of being centered in the Y direction. However, since the adjustment amounts of the second position adjusting devices 481 and 482 are not the same, the rotation of the gauge member 35 in the horizontal plane may cause a slight deviation in the previously adjusted setting position in the X direction. , Y-direction position adjustment is performed, and then the X-direction position is finely adjusted again to correct the deviation. As a result, the rail members 4a and 5a are held in the hoistway while being centered in the X and Y directions.

【0030】こうして据付固定すべき所定の芯出し位置
を決定したなら、そこに保持されているレール部材4
a,5aに合わせてブラケットを組み立てて、各レール
部材4a,5aを昇降路壁20,21へ本固定する作業
を行う。かかる本固定作業の詳細をレール部材4aにつ
いて述べると、図10に示すように、まず芯出し済みの
レール部材4aに対し、レールクリップ62を用いてレ
ール側ブラケット61を取り付け、このレール側ブラケ
ット61に壁側ブラケット63を取り付けた後、昇降路
壁20に予め打設されているアンカーボルト64によっ
て、壁側ブラケット63を昇降路壁20に固定する。こ
のとき、昇降路壁20の取付個所が鉛直面に対し若干傾
いて仕上げられていると、図10に示すように壁側ブラ
ケット63と昇降路壁20との間にギャップGが生じる
ことになるので、その場合、作業者はライナ等を用いて
該ギャップGを埋めてから、壁側ブラケット63を固定
すればよい。なお、芯出し済みのレール部材5aの本固
定作業も、同様にして行われる。
When the predetermined centering position to be installed and fixed is determined in this way, the rail member 4 held there is determined.
The bracket is assembled according to a and 5a, and the work of permanently fixing the rail members 4a and 5a to the hoistway walls 20 and 21 is performed. The details of the main fixing work will be described for the rail member 4a. As shown in FIG. 10, first, the rail side bracket 61 is attached to the centered rail member 4a using the rail clip 62, and the rail side bracket 61 is attached. After the wall side bracket 63 is attached to the hoistway wall 20, the wall side bracket 63 is fixed to the hoistway wall 20 by the anchor bolts 64 that are pre-mounted on the hoistway wall 20. At this time, if the mounting portion of the hoistway wall 20 is finished with a slight inclination with respect to the vertical plane, a gap G is created between the wall side bracket 63 and the hoistway wall 20, as shown in FIG. Therefore, in that case, the operator may fix the wall-side bracket 63 after filling the gap G with a liner or the like. The main fixing work of the rail member 5a that has been centered is also performed in the same manner.

【0031】このように、上述した芯出し装置は、相対
向する昇降路壁20,21間に突っ張り力によってベー
ス部材300を保持した状態で、第1の位置調整手段4
2によりスライド部材38を該ベース部材300に対し
てX方向へ適宜変位させるとともに、第2の位置調整手
段481,482により、左右一対のレール部材(例え
ばレール部材4a,5a)を把持したゲージ部材35を
スライド部材38に対してY方向へ適宜変位させること
ができるので、これら一対のレール部材どうしを所望の
相対位置関係に保ったまま、その芯出しを行うことがで
きる。したがって、昇降路壁に仮固定したブラケットを
ハンマー等で叩きながら各レール部材の位置調整を行っ
ていた従来の芯出し作業に比べて、作業効率が大幅に向
上し、エレベータガイドレールの据付作業を短時間で行
うことが可能となる。また、上述した芯出し装置を採用
すると、昇降路壁20,21の仕上がり状態が良好でな
い場合にも、レール部材に不所望な曲げ応力を作用させ
ることなく芯出しが行えるので、常に高い芯出し精度が
確保できて信頼性の向上が図れる。
As described above, in the above-described centering device, the first position adjusting means 4 is held while the base member 300 is held by the tension force between the hoistway walls 20 and 21 facing each other.
2, the slide member 38 is appropriately displaced with respect to the base member 300 in the X direction, and the second position adjusting means 481 and 482 grip the pair of left and right rail members (for example, the rail members 4a and 5a). Since the 35 can be appropriately displaced in the Y direction with respect to the slide member 38, the pair of rail members can be centered while maintaining a desired relative positional relationship. Therefore, compared to the conventional centering work in which the position of each rail member is adjusted by hitting the bracket temporarily fixed to the hoistway wall with a hammer etc., the work efficiency is significantly improved, and the installation work of the elevator guide rail is improved. It can be done in a short time. Further, when the above-described centering device is adopted, even when the hoistway walls 20 and 21 are not finished well, the rail member can be centered without exerting an undesired bending stress. Accuracy can be secured and reliability can be improved.

【0032】[0032]

【発明の効果】以上説明したように、本発明によるエレ
ベータガイドレールの芯出し装置は、同等の高さに据付
固定される左右一対のレール部材どうしを所望の相対位
置関係に保ったまま、その芯出しを容易に行うことがで
きるので、仮固定状態のブラケットをハンマー等で叩き
ながらレール部材の位置調整を行うという従来の芯出し
作業に比べて、作業効率が大幅に向上するという優れた
効果を奏する。また、本発明による芯出し装置を採用す
ると、昇降路壁の仕上がり状態が良好でない場合にも、
レール部材に不所望な曲げ応力を作用させることなく高
精度な芯出しが行えるので、信頼性が向上するという効
果を奏する。
As described above, the centering device for the elevator guide rail according to the present invention maintains the desired relative positional relationship between the pair of left and right rail members installed and fixed at the same height. Since centering can be performed easily, it is an excellent effect that work efficiency is significantly improved compared to the conventional centering work in which the position of the rail member is adjusted while hitting the temporarily fixed bracket with a hammer or the like. Play. Further, when the centering device according to the present invention is adopted, even when the hoistway wall is not finished well,
Since highly accurate centering can be performed without applying an undesired bending stress to the rail member, the reliability is improved.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明によるエレベータガイドレールの芯出し
装置を示す平面図である。
FIG. 1 is a plan view showing a centering device for an elevator guide rail according to the present invention.

【図2】該芯出し装置の正面図である。FIG. 2 is a front view of the centering device.

【図3】該芯出し装置を作業床上に配置した芯出し準備
段階の平面図である。
FIG. 3 is a plan view of a centering preparation stage in which the centering device is arranged on a work floor.

【図4】該芯出し装置の構成要素である突っ張り保持装
置を示す要部平面図である。
FIG. 4 is a plan view of a main portion showing a tension holding device which is a component of the centering device.

【図5】該芯出し装置の構成要素であるレール把持装置
がレール部材を把持する前の状態を示す要部平面図であ
る。
FIG. 5 is a plan view of relevant parts showing a state before a rail gripping device, which is a component of the centering device, grips a rail member.

【図6】図5に示すレール把持装置をレール部材の背面
に当接させる工程を示す要部平面図である。
FIG. 6 is a plan view of relevant parts showing a step of bringing the rail gripping device shown in FIG. 5 into contact with the back surface of the rail member.

【図7】図6に示すレール把持装置をレール部材のガイ
ド面に当接させる工程を示す要部平面図である。
FIG. 7 is a plan view of relevant parts showing a step of bringing the rail gripping device shown in FIG. 6 into contact with a guide surface of a rail member.

【図8】図7に示すレール把持装置でレール部材を把持
した状態を示す要部平面図である。
FIG. 8 is a plan view of relevant parts showing a state where a rail member is gripped by the rail gripping device shown in FIG. 7.

【図9】作業床上に配置した該芯出し装置によるレール
部材の芯出し作業を説明するための平面図である。
FIG. 9 is a plan view for explaining the centering work of the rail member by the centering device arranged on the work floor.

【図10】該芯出し装置によって芯出ししたレール部材
を昇降路壁に固定するブラケットの取付状態を示す要部
平面図である。
FIG. 10 is a plan view of relevant parts showing a mounting state of a bracket for fixing the rail member centered by the centering device to the hoistway wall.

【図11】昇降路内におけるガイドレールの据付作業を
示す説明図である。
FIG. 11 is an explanatory diagram showing a work of installing the guide rail in the hoistway.

【図12】ガイドレールの据付手順を説明するためのフ
ローチャートである。
FIG. 12 is a flowchart for explaining a procedure for installing the guide rail.

【図13】従来の芯出し装置を作業床上に配置した芯出
し準備段階の斜視図である。
FIG. 13 is a perspective view of a centering preparation stage in which a conventional centering device is arranged on a work floor.

【図14】図13に示す従来の芯出し装置によるレール
部材の芯出し作業を説明するための平面図である。
FIG. 14 is a plan view for explaining the centering work of the rail member by the conventional centering device shown in FIG.

【符号の説明】[Explanation of symbols]

1a,1b ピアノ線 4a,5a レール部材 20,21 昇降路壁 30 突っ張り保持装置 31a,31b ジャッキボルト 33a,33b 伸長部材 34 リンク部材 35 ゲージ部材 37 調整ねじ部 38 スライド部材 41a,41b 基準部材 42 第1の位置調整装置 44a,44b 引っ張りクランプ 46a,46b 雌ねじ軸(第1のナット部材) 47a,47b 連結軸(第2のナット部材) 48a,48b 調整ねじ部 49a,49b 挟圧ねじ 300 ベース部材 451,452 レール把持装置 481,482 第2の位置調整装置 1a, 1b Piano wire 4a, 5a Rail member 20, 21 Hoistway wall 30 Stretch holding device 31a, 31b Jack bolt 33a, 33b Extension member 34 Link member 35 Gauge member 37 Adjustment screw part 38 Sliding member 41a, 41b Reference member 42 No. 1 position adjusting device 44a, 44b tension clamps 46a, 46b female screw shaft (first nut member) 47a, 47b connecting shaft (second nut member) 48a, 48b adjusting screw portion 49a, 49b clamping screw 300 base member 451 , 452 Rail gripping device 481, 482 Second position adjusting device

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 昇降路内に垂下させた一対のピアノ線を
基準としてガイドレール用のレール部材の据付固定時の
芯出しを行う装置であって、ベース部材の両端部に該ベ
ース部材からの突出量が変更可能な伸長部材を設けて、
これら一対の伸長部材を介して相対向する昇降路壁に突
っ張り力を付与することにより昇降路内に保持可能な突
っ張り保持手段と、前記ベース部材に取着されるスライ
ド部材と、このスライド部材の前記ベース部材に対する
取付位置を前記伸長部材の突出方向に沿って調整するた
めの第1の位置調整手段と、相対向する昇降路壁に据付
固定される一対の前記レール部材を把持可能なレール把
持手段を設けて前記スライド部材に取着されるゲージ部
材と、このゲージ部材の前記スライド部材に対する取付
位置を前記伸長部材の突出方向と直交する水平方向に沿
って調整するための第2の位置調整手段とを備えたこと
を特徴とするエレベータガイドレールの芯出し装置。
1. A device for performing centering when a rail member for a guide rail is installed and fixed, using a pair of piano wires hanging down in a hoistway as a reference, wherein both ends of the base member are separated from the base member. By providing an extension member that can change the amount of protrusion,
A tension holding means that can be held in the hoistway by applying a tensioning force to the hoistway walls facing each other through the pair of extension members, a slide member attached to the base member, and a slide member of the slide member. First position adjusting means for adjusting a mounting position with respect to the base member along a projecting direction of the extension member, and a rail gripper capable of gripping a pair of the rail members installed and fixed to the hoistway walls facing each other. And a second position adjusting means for adjusting a mounting position of the gauge member attached to the slide member to the slide member along a horizontal direction orthogonal to a projecting direction of the extension member. And a centering device for an elevator guide rail.
【請求項2】 請求項1の記載において、前記第2の位
置調整手段が、前記スライド部材に回動可能に取着せし
めた第1のナット部材と、前記ゲージ部材に回動可能に
取着せしめた第2のナット部材と、これら第1および第
2のナット部材どうしを螺合状態で連結する調整ねじ部
材とを備えており、この調整ねじ部材を回して前記第1
および第2のナット部材どうしの間隔を変更させると前
記ゲージ部材が水平面内で回転するように構成したこと
を特徴とするエレベータガイドレールの芯出し装置。
2. The first nut member rotatably attached to the slide member and the rotatably attached to the gauge member, according to claim 1. A second nut member is provided, and an adjusting screw member for connecting the first and second nut members in a screwed state is provided, and the adjusting screw member is turned to rotate the first nut member.
An elevator guide rail centering device, wherein the gauge member is configured to rotate in a horizontal plane when the distance between the second nut members is changed.
JP08022649A 1996-02-08 1996-02-08 Elevator guide rail centering device Expired - Fee Related JP3083256B2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP08022649A JP3083256B2 (en) 1996-02-08 1996-02-08 Elevator guide rail centering device
IDP973000A ID19317A (en) 1996-02-08 1997-08-28 COMPOSITION OF BLEACH LIQUID PACKED ON FLEXIBLE PACKAGING BAGS

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP08022649A JP3083256B2 (en) 1996-02-08 1996-02-08 Elevator guide rail centering device

Publications (2)

Publication Number Publication Date
JPH09208152A true JPH09208152A (en) 1997-08-12
JP3083256B2 JP3083256B2 (en) 2000-09-04

Family

ID=12088705

Family Applications (1)

Application Number Title Priority Date Filing Date
JP08022649A Expired - Fee Related JP3083256B2 (en) 1996-02-08 1996-02-08 Elevator guide rail centering device

Country Status (2)

Country Link
JP (1) JP3083256B2 (en)
ID (1) ID19317A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104589040A (en) * 2015-01-23 2015-05-06 巨人通力电梯有限公司 T-shaped guide rail mounting tool for elevator
WO2015165806A1 (en) * 2014-05-01 2015-11-05 Inventio Ag Rail securing devices for an elevator installation
EP2993152A1 (en) * 2014-09-04 2016-03-09 Kone Corporation Apparatus and method for aligning guide rails in an elevator shaft
CN110155851A (en) * 2018-02-16 2019-08-23 株式会社日立大厦系统 Cage guide is to core apparatus and cage guide to core method
WO2021053881A1 (en) * 2019-09-19 2021-03-25 株式会社日立ビルシステム Elevator rail positioning device and rail mounting method using same
CN113727934A (en) * 2019-05-21 2021-11-30 因温特奥股份公司 Aligning device and method for aligning guide rails of an elevator installation by means of power pulses
WO2022008180A1 (en) * 2020-07-08 2022-01-13 Tk Elevator Innovation And Operations Gmbh Device for adjusting and assembling lift components
CN114364493A (en) * 2019-12-11 2022-04-15 株式会社日立大厦系统 Anchor driving device, anchor driving method using same, installation device for elevator guide rail, and installation method for elevator guide rail

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2873640B1 (en) * 2013-11-14 2016-06-01 KONE Corporation An apparatus and a method for alignment of an elevator guide rail
EP3090976B1 (en) * 2015-05-06 2020-03-04 KONE Corporation Apparatus and method for aligning guide rails and landing doors in an elevator shaft

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2015165806A1 (en) * 2014-05-01 2015-11-05 Inventio Ag Rail securing devices for an elevator installation
CN106458515A (en) * 2014-05-01 2017-02-22 因温特奥股份公司 Rail securing devices for an elevator installation
CN105398911B (en) * 2014-09-04 2019-11-05 通力股份公司 Device and method for calibrating the guide rail in lift well
EP2993152A1 (en) * 2014-09-04 2016-03-09 Kone Corporation Apparatus and method for aligning guide rails in an elevator shaft
CN105398911A (en) * 2014-09-04 2016-03-16 通力股份公司 Apparatus and method for aligning guide rails in an elevator shaft
US9714156B2 (en) 2014-09-04 2017-07-25 Kone Corporation Apparatus and method for aligning guide rails in an elevator shaft
CN104589040A (en) * 2015-01-23 2015-05-06 巨人通力电梯有限公司 T-shaped guide rail mounting tool for elevator
CN110155851A (en) * 2018-02-16 2019-08-23 株式会社日立大厦系统 Cage guide is to core apparatus and cage guide to core method
JP2019142622A (en) * 2018-02-16 2019-08-29 株式会社日立ビルシステム Elevator guide rail centering device and elevator guide rail centering method
CN113727934A (en) * 2019-05-21 2021-11-30 因温特奥股份公司 Aligning device and method for aligning guide rails of an elevator installation by means of power pulses
CN113727934B (en) * 2019-05-21 2023-04-21 因温特奥股份公司 Alignment device and method for aligning guide rails of an elevator installation by means of power pulses
US11724917B2 (en) 2019-05-21 2023-08-15 Inventio Ag Aligning device and method for aligning a guide rail of an elevator system by means of force pulses
WO2021053881A1 (en) * 2019-09-19 2021-03-25 株式会社日立ビルシステム Elevator rail positioning device and rail mounting method using same
CN114364493A (en) * 2019-12-11 2022-04-15 株式会社日立大厦系统 Anchor driving device, anchor driving method using same, installation device for elevator guide rail, and installation method for elevator guide rail
WO2022008180A1 (en) * 2020-07-08 2022-01-13 Tk Elevator Innovation And Operations Gmbh Device for adjusting and assembling lift components

Also Published As

Publication number Publication date
JP3083256B2 (en) 2000-09-04
ID19317A (en) 1998-07-02

Similar Documents

Publication Publication Date Title
AU2017365063B2 (en) Method for mounting and alignment device for aligning a guide rail of an elevator system
JPH09208152A (en) Centering device for elevator guide rail
CN112091535B (en) Processing method of curved curtain wall plate
CN112255116A (en) Comprehensive test bed for performance test of light steel keel
CN110919847A (en) Anchoring device for T-shaped embedded steel member and using method thereof
JP3370591B2 (en) Elevator guide rail centering device
JP2000000690A (en) Welding jig
JP3343483B2 (en) Elevator guide rail centering device
JPH0940320A (en) Centering device for elevator guide rail
JPH11255450A (en) Centering device for elevator guide rail
JPH0952676A (en) Centering device for elevator guide rail
US2936457A (en) Means for nailing window frame jamb assemblies
JP3301926B2 (en) Elevator guide rail centering device
JPH0948569A (en) Centering device of elevator guide rail
JPH09202564A (en) Centering device for guide rail for elevator
KR102643860B1 (en) Apparatus for manufacturing cable tray and manufacturing method of cable tray using the same
JPH04173689A (en) Positioning device and installing method of three-way frame for elevator entrance
JPH09110335A (en) Alignment device of guide rail of elevator
JP4084244B2 (en) Wheel mounting equipment for wheel balancers
CN217561149U (en) High-strength tensile machine
JP2606512B2 (en) Lower centering device for elevator installation
JPH0629714Y2 (en) Material testing machine
JP2001322776A (en) Template for centering guide rail of elevator and method of centering guide rail of elevator
JPS63176759A (en) Clamp device for vehicle repair and sheeting for automobile and the like
JP2752541B2 (en) Elevator centering

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees