JPH09137430A - Method of water channel construction - Google Patents

Method of water channel construction

Info

Publication number
JPH09137430A
JPH09137430A JP29103895A JP29103895A JPH09137430A JP H09137430 A JPH09137430 A JP H09137430A JP 29103895 A JP29103895 A JP 29103895A JP 29103895 A JP29103895 A JP 29103895A JP H09137430 A JPH09137430 A JP H09137430A
Authority
JP
Japan
Prior art keywords
water channel
walls
wall
inclined walls
continuously inclined
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP29103895A
Other languages
Japanese (ja)
Inventor
Shunsuke Shirai
俊輔 白井
Katsutoshi Miyoshi
勝利 三好
Yasuo Higuchi
安夫 樋口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP29103895A priority Critical patent/JPH09137430A/en
Publication of JPH09137430A publication Critical patent/JPH09137430A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PROBLEM TO BE SOLVED: To eliminate the need for processes such as a landslide protection wall, the curing of concrete on the face of a slope, etc., by preparing continuously inclined walls into the ground while being oppositely faced so that the lower ends of the continuously inclined walls are connected continuously and excavating a triangular sectional section surrounded by the opposed continuously inclined walls. SOLUTION: Oblique underground continuous walls or continuously inclined walls 1a, 1b formed in a wall shape by sheet piles, precast boards, etc., are prepared in the ground while the lower ends of these walls are faced oppositely so as to be continuously connected. A triangular sectional section surrounded by the opposed continuously inclined walls 1a, 1b is excavated, and a ditch as a water channel is prepared. The left and the right are brought to the state, in which they are landslide-protected by the continuously inclined walls 1a, 1b, in the triangular sectional section to be excavated at that time. Since the continuously inclined walls 1a, 1b are constructed beforehand on the side faces of the ditch as the water channel and exposed, the face of a slope is protected by the continuously inclined walls 1a, 1b. Accordingly, processes such as a landslide protection wall, the curing of concrete on the face of the slope, etc., are unnecessitated, and the term of works can be shortened.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、水路の構築工法に
関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a waterway construction method.

【0002】[0002]

【従来の技術】従来、水路を構築するには、水路となる
溝を掘削するに際し、掘削面および周辺地盤の土圧、水
圧等を支え、崩壊を防止するために山留めし、また、掘
削して形成した溝の法面を吹き付けコンクリートやのり
枠等で養生する。
2. Description of the Related Art Conventionally, when constructing a waterway, when excavating a ditch that serves as a waterway, it supports earth pressure and water pressure of the excavation surface and the surrounding ground, and holds a mountain to prevent collapse and excavation. The slope of the formed groove is sprayed and cured with concrete or glue frame.

【0003】[0003]

【発明が解決しようとする課題】溝の掘削の他に、山留
めや法面養生などの工程を要し、工数が多くなり、工期
も長くなる。
In addition to excavation of trenches, steps such as mountain retaining and slope curing are required, resulting in a large number of steps and a long construction period.

【0004】本発明の目的は前記従来例の不都合を解消
し、山留めや法面養生などの工程が不要となって工数が
低減し、簡便、かつ安全に構築できる水路構築工法を提
供することにある。
An object of the present invention is to solve the above-mentioned disadvantages of the prior art, to provide a waterway construction method in which steps such as mountain retaining and slope protection are not required, and the number of steps is reduced, and the method is simple and safe. is there.

【0005】[0005]

【課題を解決するための手段】本発明は前記目的を達成
するため、第1に、地中に斜めの地中連続壁もしくはシ
ートパイル、プレキャスト板等により壁状に形成した斜
連壁をその下端が連接するように対向させて造成し、こ
の対向する斜連壁で囲まれた断面三角形状の部分を掘削
し、対向する斜連壁で水路となる溝を造成することを要
旨とするものである。
In order to achieve the above object, the present invention firstly provides an oblique underground continuous wall in the ground or an oblique continuous wall formed in a wall shape by a sheet pile, a precast plate or the like. The gist of the project is to create a groove that forms a waterway in the opposing diagonal connecting walls by excavating the section with a triangular cross section surrounded by the opposing diagonal connecting walls so that the lower ends connect to each other. Is.

【0006】第2に、地中に斜めの地中連続壁もしくは
シートパイル、プレキャスト板等により壁状に形成した
斜連壁をその下部が近づくように対向させて造成し、こ
の対向する斜連壁で囲まれた部分を掘削し、対向する斜
連壁の下部間に水平な床板を造成して該床板と前記対向
する斜連壁とで水路となる溝を造成することを要旨とす
るものである。
Secondly, an oblique continuous underground wall or an oblique continuous wall formed in the shape of a wall by a sheet pile, a precast plate or the like is formed in the ground so that the lower portions thereof are close to each other. The gist of the present invention is to excavate a portion surrounded by a wall, to form a horizontal floor plate between the lower portions of the facing diagonal connecting walls, and to form a groove serving as a water channel between the floor plate and the facing diagonal connecting walls. Is.

【0007】請求項1記載の本発明によれば、SMW工
法(現位置土混合工法)などにより、地中に斜連壁をそ
の下端が連接するように対向させて造成すれば、この対
向する斜連壁で囲まれた断面三角形状の部分は左右が斜
連壁で山留めされた状態になるから、軟弱地盤でもこの
部分を安全に掘削できる。また、掘削終了後は、断面三
角形状の水路となる溝が形成され、側面には斜連壁が既
に構築されているからこの斜連壁で法面保護を図れる。
According to the first aspect of the present invention, if the slanted connecting walls are formed in the ground so that their lower ends are connected to each other by the SMW method (current position soil mixing method) or the like, they will face each other. The left and right sides of the section with a triangular cross section surrounded by the slanted wall are secured by slanted walls, so this section can be safely excavated even on soft ground. Moreover, after the excavation is completed, a groove serving as a water channel having a triangular cross section is formed, and a sloped connecting wall is already constructed on the side surface, so that the sloped connecting wall can protect the slope.

【0008】請求項2記載の本発明によれば、前記作用
に加えて、対向する斜連壁の下部を離間させておけば、
この間に水平な床板を造成することができ、水路底面を
水平に仕上げることができる。
According to the second aspect of the present invention, in addition to the above action, if the lower portions of the diagonal connecting walls facing each other are separated from each other,
During this time, a horizontal floorboard can be created and the bottom of the waterway can be finished horizontally.

【0009】[0009]

【発明の実施の形態】以下、図面について本発明の実施
形態を詳細に説明する。図1は本発明の水路構築工法の
第1実施形態の第1工程を示す縦断正面図、図2は同上
第2工程を示す縦断正面図で、地中に斜連壁1a,1b
等をその下端が連接するように対向させて造成する。
BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of the present invention will be described in detail below with reference to the drawings. FIG. 1 is a vertical sectional front view showing a first step of a first embodiment of a water channel construction method of the present invention, and FIG. 2 is a vertical sectional front view showing a second step of the same. The oblique connecting walls 1a and 1b are underground.
Etc. are made to face each other so that their lower ends are connected.

【0010】斜連壁1a,1b等の造成の方法は、SM
W工法(現位置土混合工法)などによる連続壁工法、場
所打ち杭、既成杭等を連続的に配置して柱列状の壁体を
構築する柱列式工法によるもの、シートパイルもしくは
プレキャストコンクリートを建て込むなどが考えられ
る。SMW工法(現位置土混合工法)は、現地盤を1エ
レメント単位に壁体状に掘削する際、混練軸先端よりセ
メント、ベントナイト等の目的に適応した混合液を吐出
させて、土中において現位置と混合して、1エレメント
のソイルセメント壁体を造成する。このようにして造成
されたソイルセメント壁の各エレメントを完全にラップ
させて一体に連結した壁体を形成する工法である。
The method of constructing the diagonal connection walls 1a, 1b is SM
Continuous wall construction method such as W construction method (current position soil mixing construction method), pillar row type construction method in which cast-in-place piles, prefabricated piles, etc. are continuously arranged to construct a columnar wall body, sheet pile or precast concrete It is possible to build in. The SMW method (current position soil mixing method) is used in the soil by discharging a mixed liquid suitable for the purpose such as cement and bentonite from the tip of the kneading shaft when excavating the local plate into a wall shape in units of one element. Mix with position to create a one element soil cement wall. In this method, each element of the soil cement wall thus constructed is completely wrapped to form a wall body integrally connected.

【0011】以上のようにして造成した対向する斜連壁
1a,1bで囲まれた断面三角形状の部分を掘削すれば
図2に示すように水路2となる溝が形成される。この掘
削の際、掘削しようとする断面三角形状の部分は左右が
斜連壁1a,1bで山留めされた状態になるから、軟弱
地盤でもこの部分を安全に掘削できる。
By excavating a portion having a triangular cross section surrounded by the opposing diagonal connection walls 1a and 1b constructed as described above, a groove to be a water channel 2 is formed as shown in FIG. At the time of this excavation, the left and right portions of the triangular section to be excavated are clamped by the diagonal connecting walls 1a and 1b, so that this section can be safely excavated even on soft ground.

【0012】掘削により形成された水路2となる溝の側
面には斜連壁1a,1bが既に構築されており、これが
露出するからこの斜連壁1a,1bで法面保護を図れ
る。また、切梁が必要な場合でもその数を低減できる。
Oblique connecting walls 1a and 1b have already been constructed on the side surfaces of the groove formed by excavation to form the water channel 2. Since these are exposed, the slope connecting walls 1a and 1b can protect the slope. Moreover, the number can be reduced even when a cross beam is required.

【0013】水路2の底面を水平に仕上げる必要があれ
ば、断面三角形状の溝を掘削した後に、図3のように底
部にコンクリートを打設するなどして床板3を形成す
る。
If it is necessary to finish the bottom of the water channel 2 horizontally, the floor plate 3 is formed by excavating a groove having a triangular cross section and then pouring concrete on the bottom as shown in FIG.

【0014】図4は第2実施形態を示し、斜連壁1a,
1bをその下部を離間状態で近づくように対向させて造
成し、この対向する斜連壁1a,1bで囲まれた部分を
掘削し台形状の溝を造成するもので、溝の下部は斜連壁
1a,1bで閉鎖されないため、地盤強度が見込まれる
場所での施工に適している。この場合も第1実施形態と
同様に掘削の際、溝となる部分の左右は斜連壁1a,1
bで山留めされた状態になるから、別途山留めを施す必
要がない。
FIG. 4 shows a second embodiment, in which the diagonal connecting walls 1a,
1b is formed so that the lower portions thereof face each other so as to approach each other in a separated state, and the portion surrounded by the opposing diagonal connection walls 1a and 1b is excavated to form a trapezoidal groove. Since it is not closed by the walls 1a and 1b, it is suitable for construction in a place where ground strength is expected. Also in this case, when excavating as in the case of the first embodiment, the diagonal connecting walls 1a, 1
There is no need to perform additional mountain fastening because it is in the state of mountain fastening in b.

【0015】そして、台形状の溝を造成した後、底部に
コンクリートを打設するなどして離間している斜連壁1
a,1bの下方部を連成し床板3を造成する。
After the trapezoidal groove is formed, concrete is placed on the bottom of the slanted connecting wall 1 which is separated.
A floor plate 3 is formed by connecting the lower portions of a and 1b.

【0016】図5は本発明の工法を既設水路を拡幅その
他の目的で改修する場合に適用する例を示し、既設水路
4の外側に拡幅する分だけ離間させて第1実施形態と同
様にして斜連壁1a,1b等をその下端が連接するよう
に対向させて造成し、既設水路4の外側で斜連壁1a,
1bで囲まれた部分を掘削すれば、既設水路4の外側に
これよりも大きい断面三角形状の溝が造成される。
FIG. 5 shows an example in which the construction method of the present invention is applied to the case where the existing water channel is modified for the purpose of widening or for other purposes. The slanted connecting walls 1a, 1b and the like are formed so as to face each other so that their lower ends are connected, and the slanted connecting walls 1a, 1b are formed outside the existing water channel 4.
If the portion surrounded by 1b is excavated, a groove having a triangular cross section larger than this is formed outside the existing water channel 4.

【0017】よって、掘削終了後に既設水路4を撤去す
れば、既設水路4が拡幅された状態でその外側にこれよ
りも大きい水路5が斜連壁1a、1bにより新たに構築
される。
Therefore, if the existing water channel 4 is removed after the completion of excavation, a water channel 5 larger than the existing water channel 4 is newly formed outside the existing water channel 4 by the diagonal connection walls 1a and 1b.

【0018】この場合は、既設水路4を使用したままの
状態で拡幅される水路5を構築できるから、構築工事の
期間中、仮設の水路を別個に設ける必要や、既設水路4
を半分ずつに仕切って掘削部に水が入らないようにして
施工する必要もなく、施工が容易となる。
In this case, since it is possible to construct the water channel 5 which is widened while the existing water channel 4 is being used, it is necessary to provide a temporary water channel separately during the construction work, or the existing water channel 4
There is no need to divide the halves in half to prevent water from entering the excavation part, and the construction is easy.

【0019】既設水路4とは別個に仮設水路を設けるス
ペースのある場合は、図示は省略するが、既設水路4の
外側に図4に示した第2実施形態のような斜連壁1a,
1bの下端を離間させて下部を閉めきらない工法で新た
な水路を施工することができる。
When there is a space for providing a temporary water channel separately from the existing water channel 4, although not shown, the slanted connecting wall 1a as shown in FIG.
It is possible to construct a new water channel by a construction method in which the lower end of 1b is separated and the lower part is not completely closed.

【0020】この場合は、既設水路4の外側で斜連壁1
a,1bに囲まれる部分を掘削して外形が台形の溝を造
成した後、既設水路4を撤去して、溝の底部にコンクリ
ートを打設するなどして離間している斜連壁1a,1b
の下方部を連成し床板3を造成することになり、この間
は既設水路4の使用が不可能となるため、仮設水路を使
用する。
In this case, the oblique connecting wall 1 is provided outside the existing water channel 4.
After excavating the portion surrounded by a and 1b to form a groove having a trapezoidal outer shape, the existing water channel 4 is removed, concrete is placed at the bottom of the groove, and the diagonal connection wall 1a is separated. 1b
The floor plate 3 is formed by connecting the lower part of the above, and the existing water channel 4 cannot be used during this period, so the temporary water channel is used.

【0021】[0021]

【発明の効果】以上述べたように本発明の水路構築工法
は、掘削に先立ち斜連壁等を造成するだけで、掘削の際
の安全が確保でき、掘削が終了すればこの状態でほぼ水
路が完成するから、山留めや法面養生などの工程が不要
となって工数が低減し、簡便、かつ安全に構築できるも
のである。
As described above, according to the waterway construction method of the present invention, the safety at the time of excavation can be ensured only by constructing the oblique connecting wall and the like prior to the excavation. Since the construction is completed, processes such as mountain retaining and slope curing are not required, and the number of steps is reduced, and it is possible to construct simply and safely.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の水路構築工法の第1実施形態の第1工
程を示す縦断正面図である。
FIG. 1 is a vertical sectional front view showing a first step of a first embodiment of a waterway construction method of the present invention.

【図2】本発明の水路構築工法の第1実施形態の第2工
程を示す縦断正面図である。
FIG. 2 is a vertical sectional front view showing a second step of the first embodiment of the waterway construction method of the present invention.

【図3】本発明の水路構築工法の第1実施形態の他の例
を示す縦断正面図である。
FIG. 3 is a vertical sectional front view showing another example of the first embodiment of the waterway construction method of the present invention.

【図4】本発明の水路構築工法の第2実施形態を示す縦
断正面図である。
FIG. 4 is a vertical sectional front view showing a second embodiment of the waterway construction method of the present invention.

【図5】本発明の水路構築工法を既設水路の拡幅に適用
した場合の縦断正面図である。
FIG. 5 is a front view in vertical section when the waterway construction method of the present invention is applied to widening an existing waterway.

【符号の説明】[Explanation of symbols]

1a,1b…斜連壁 2…水路 3…床板 4…既設水路 5…水路 1a, 1b ... Inclined wall 2 ... Waterway 3 ... Floorboard 4 ... Existing waterway 5 ... Waterway

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 地中に斜めの地中連続壁もしくはシート
パイル、プレキャスト板等により壁状に形成した斜連壁
をその下端が連接するように対向させて造成し、この対
向する斜連壁で囲まれた断面三角形状の部分を掘削し、
対向する斜連壁で水路となる溝を造成することを特徴と
する水路構築工法。
1. An oblique underground continuous wall or an oblique continuous wall formed in the shape of a wall by a sheet pile, a precast plate or the like is formed so as to face each other so that the lower ends thereof are connected to each other. Drill a part with a triangular cross section surrounded by
A waterway construction method characterized in that a groove that becomes a waterway is created by facing diagonal connecting walls.
【請求項2】 地中に斜めの地中連続壁もしくはシート
パイル、プレキャスト板等により壁状に形成した斜連壁
をその下部が近づくように対向させて造成し、この対向
する斜連壁で囲まれた部分を掘削し、対向する斜連壁の
下部間に水平な床板を造成して該床板と前記対向する斜
連壁とで水路となる溝を造成することを特徴とする水路
構築工法。
2. An inclined underground continuous wall or an oblique continuous wall formed in the shape of a wall by a sheet pile, a precast plate or the like is made to face each other so that the lower portions thereof are close to each other, and the diagonal continuous walls are opposed to each other. A method for constructing a water channel characterized by excavating an enclosed portion, forming a horizontal floor plate between lower portions of opposing diagonal connecting walls, and forming a groove serving as a water channel between the floor plate and the opposing diagonal connecting wall. .
JP29103895A 1995-11-09 1995-11-09 Method of water channel construction Pending JPH09137430A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP29103895A JPH09137430A (en) 1995-11-09 1995-11-09 Method of water channel construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP29103895A JPH09137430A (en) 1995-11-09 1995-11-09 Method of water channel construction

Publications (1)

Publication Number Publication Date
JPH09137430A true JPH09137430A (en) 1997-05-27

Family

ID=17763643

Family Applications (1)

Application Number Title Priority Date Filing Date
JP29103895A Pending JPH09137430A (en) 1995-11-09 1995-11-09 Method of water channel construction

Country Status (1)

Country Link
JP (1) JPH09137430A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011252350A (en) * 2010-06-03 2011-12-15 Ohbayashi Corp Earth retaining structure and construction method of earth retaining structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011252350A (en) * 2010-06-03 2011-12-15 Ohbayashi Corp Earth retaining structure and construction method of earth retaining structure

Similar Documents

Publication Publication Date Title
JPH11256564A (en) Continuous two-plane soil improvement body and construction method therefor
JP2003193494A (en) Underground hollow structure constructing method and the underground hollow structure
JPH09137430A (en) Method of water channel construction
JPS61122320A (en) Method of coupling continuous underground wall with underground structure
JP3253868B2 (en) Forming method of water passage section in continuous underground wall
JP2558414B2 (en) Construction method of the main retaining wall and the retaining wall
JPH11158865A (en) Underground structure having wall using steel sheet pile as core and method for constructing the same
JPS5851092B2 (en) Earth retaining installation method using advance shoring frame
JPH01315520A (en) Underground outer wall constructing method for superstructure
JP2949595B2 (en) Continuous underground wall construction method
JP2663087B2 (en) How to build underground structures
JP2689743B2 (en) How to build an underground structure
JP2603307B2 (en) Retaining method for the upper part of the continuous underground wall
JPS6313487B2 (en)
JP3441266B2 (en) Underground space construction method
JPS5854124A (en) Constructing method for preliminary underground wall preceding excavation of ditch for continuous underground wall
JP2947083B2 (en) Construction method of deep groove block
JPS6085116A (en) Method of improving ground prior to construction of underground continuous wall
JPH0539611A (en) Method for building underground housing chamber
JPS58150631A (en) Construction work of underground structure
JPS6019369B2 (en) How to build a diaphragm wall
JPH07119160A (en) Method of constructing concrete footing, casing for footing section form of concrete footing and panel for underground girder section form
JPS63312417A (en) Water construction of continuous wall using steel caisson
JPH04258410A (en) Constructing method of underground continuous wall in underground obstruction existing ground
JPH04265311A (en) Constructing method of continuous underground wall