JPH09111783A - Constructing method of underground building frame - Google Patents

Constructing method of underground building frame

Info

Publication number
JPH09111783A
JPH09111783A JP7270772A JP27077295A JPH09111783A JP H09111783 A JPH09111783 A JP H09111783A JP 7270772 A JP7270772 A JP 7270772A JP 27077295 A JP27077295 A JP 27077295A JP H09111783 A JPH09111783 A JP H09111783A
Authority
JP
Japan
Prior art keywords
floor
construction
underground
wall
constructing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP7270772A
Other languages
Japanese (ja)
Inventor
Kumehiko Kouno
久米彦 河野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP7270772A priority Critical patent/JPH09111783A/en
Publication of JPH09111783A publication Critical patent/JPH09111783A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To shorten a term of work by constructing a floor by providing PC beams and floor slabs in the horizontal direction in a basement space so that they support earth retaining walls, and by removing shore strut supports in the vicinity of positions where the floor slabs are provided. SOLUTION: A foundation structure part 6 is constructed on the ground inside a basement obtained by repeating alternately erection of shore strut supports supporting earth retaining walls 1 and excavation of an area inside the earth retaining walls 1. Next, iron frame pillars 7a-7f are erected from the foundation structure part 6, PC beams 8a-8g are fitted between the iron frame pillars 7a-7f and the earth retaining walls 1 and floor slabs 9 are provided on the PC beams 8a-8g. Prior to floor construction of the second basement, subsequently, the shore strut supports 5d are disjointed and removed and the floor of the third basement supports the earth retaining walls 1 in place of the shore strut supports 5d. An underground building frame is constructed by repeating the process of the floor construction and the process of removing the shore strut supports and the removal of the shore strut supports is enabled immediately after completion of the erection of the PC members. Accordingly, a term of work can be shortened greatly.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、例えばSRC造地
下躯体の構築方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing an SRC underground structure, for example.

【0002】[0002]

【発明が解決しようとする課題】一般に、SRC造地下
躯体は、山止め壁によって囲まれた地下空間に最下階部
分から順次各階の地下躯体を施工する順打工法によって
構築されている。すなわち、基礎部分の施工が完了した
後、その近傍で山止め壁を支持する切梁支保工を解体撤
去し、それより上方の切梁支保工は残したまま、垂直部
材(壁)を切り欠いて上階躯体の施工が行われる。以
後、同様の工程が繰り返され、そして躯体の強度発現
後、山止め壁反力を躯体に受け替えて、切梁支保工が解
体撤去される。
Generally, the SRC underground structure is constructed by a progressive driving method in which the underground structure of each floor is sequentially constructed from the lowermost floor portion in the underground space surrounded by the mountain retaining wall. That is, after the construction of the foundation portion is completed, the beam support supporting the mountain stop wall is dismantled and removed in the vicinity thereof, and the vertical member (wall) is notched while the beam support above it is left. The construction of the upper building is done. After that, the same process is repeated, and after the strength of the skeleton is developed, the reaction force of the mountain stop wall is transferred to the skeleton, and the beam support is dismantled and removed.

【0003】ところが、こうした順打工法には次のよう
な問題点があった。すなわち、切梁支保工の解体撤去
後、これに代わって山止め壁を支持する水平部材(梁や
床など)は、場所打ちコンクリートによって構成される
ものであるため、強度が発現するまでの間は切梁支保工
を解体することができない。従って、水平部材が設けら
れた階よりも上階部分の施工は、打設されたコンクリー
トの硬化を待たねばならず、これが工期を引き延ばす原
因となっていた。
However, such a sequential driving method has the following problems. That is, the horizontal members (beams, floors, etc.) that support the retaining wall instead of the dismantling and removal of the girder support work are made of cast-in-place concrete, so until the strength develops. Can not dismantle the beam support. Therefore, the construction of the upper floor above the floor where the horizontal member is provided must wait for the cast concrete to harden, which prolongs the construction period.

【0004】又、切梁支保工を解体撤去するために設け
た切欠きの閉塞にも手間が掛かっており、特に外壁部で
は漏水を完全に防止するために多大な労力が必要であ
り、工期の短縮が図り難い。本発明はこうした課題を解
決するためになされたもので、工期の大幅な短縮が図れ
る施工性に優れた地下躯体の構築方法の提供を目的とす
る。
Further, it is troublesome to close the notch provided for dismantling and removing the beam support work, and especially at the outer wall portion, a great deal of labor is required to completely prevent water leakage. Is difficult to shorten. The present invention has been made to solve these problems, and an object of the present invention is to provide a method for constructing an underground skeleton with excellent workability that can significantly shorten the construction period.

【0005】[0005]

【課題を解決するための手段】上記本発明の目的は、山
止め壁を支持する切梁支保工の架設と前記山止め壁内領
域の掘削とを交互に繰り返して得られる地下空間に、最
下階部分から順次地下躯体を構築する方法であって、P
C梁及び/又はS梁、及び床版を前記地下空間内におい
て、前記山止め壁を支持するよう水平方向に架設して、
床を構築する床構築工程と、床構築後、PC梁及び/又
はS梁、及び床版が架設された位置近傍の切梁支保工を
解体し、前記地下空間内から撤去する切梁支保工撤去工
程とを具備し、前記床構築工程と切梁支保工撤去工程と
を必要に応じて交互に繰り返すことを特徴とする地下躯
体の構築方法によって達成される。
The above object of the present invention is to provide an underground space which is obtained by alternately repeating the construction of a girder support for supporting a cliff wall and the excavation of the area inside the cliff wall. It is a method to build an underground skeleton sequentially from the lower floor,
In the underground space, a C beam and / or an S beam and a floor slab are installed horizontally so as to support the mountain retaining wall,
A floor construction process for constructing a floor, and after the floor construction, the beam girder support work that disassembles the PC beam and / or S beam, and the beam girder support structure near the position where the floor slab is installed, and removes it from the underground space It is achieved by a method for constructing an underground skeleton, comprising a removing step, and repeating the floor constructing step and the truss support work removing step alternately as required.

【0006】特に、山止め壁を支持する切梁支保工の架
設と前記山止め壁内領域の掘削とを交互に繰り返して得
られる地下空間に、最下階部分から順次地下躯体を構築
する方法であって、前記地下空間の地盤上に基礎構造部
を構築する基礎構造部構築工程と、前記基礎構造部上に
鉄骨柱を建方する鉄骨柱建方工程と、建方された鉄骨柱
を用い、PC梁及び/又はS梁、及び床版を前記地下空
間内において、前記山止め壁を支持するよう水平方向に
架設して、床を構築する床構築工程と、床構築後、PC
梁及び/又はS梁、及び床版が架設された位置近傍の切
梁支保工を解体し、前記地下空間内から撤去する切梁支
保工撤去工程とを具備し、前記床構築工程と切梁支保工
撤去工程とを必要に応じて交互に繰り返すことを特徴と
する地下躯体の構築方法によって達成される。
[0006] In particular, a method of sequentially constructing an underground skeleton from the lowest floor portion in an underground space obtained by alternately erection of a girder support work for supporting a cliff wall and excavation of an area in the cliff wall alternately. That is, a basic structure part building process of building a basic structure part on the ground of the underground space, a steel column erection process of erection of a steel frame column on the basic structure part, and a erected steel frame column. Using a PC beam and / or an S beam and a floor slab in the underground space in a horizontal direction so as to support the mountain retaining wall, a floor building step of building a floor, and a PC after the floor building,
A beam and / or S beam, and a beam supporting structure removing process for dismantling the beam supporting structure near the position where the floor slab is installed and removing it from the underground space. This is achieved by a method of constructing an underground skeleton, which is characterized in that a supporting work removing process is alternately repeated as necessary.

【0007】又、山止め壁を支持する切梁支保工の架設
と前記山止め壁内領域の掘削とを交互に繰り返して得ら
れる地下空間に、最下階部分から順次地下躯体を構築す
る方法であって、前記地下空間の地盤上に基礎構造部を
構築する基礎構造部構築工程と、前記基礎構造部上に鉄
骨柱を建方する鉄骨柱建方工程と、建方された鉄骨柱を
用い、PC梁及び/又はS梁、及び床版を前記地下空間
内において、前記山止め壁を支持するよう水平方向に架
設して、床を構築する床構築工程と、床構築後、PC梁
及び/又はS梁、及び床版が架設された位置近傍の切梁
支保工を解体し、前記地下空間内から撤去する切梁支保
工撤去工程と、切梁支保工を撤去した後、地下躯体の垂
直部を構築する躯体垂直部構築工程とを具備し、前記床
構築工程と切梁支保工撤去工程と躯体垂直部構築工程と
を必要に応じて交互に繰り返すことを特徴とする地下躯
体の構築方法によって達成される。
Further, a method of constructing an underground skeleton sequentially from the lowest floor part in an underground space obtained by alternately repeating the construction of a girder support for supporting the mountain stop wall and the excavation of the area inside the mountain stop wall. That is, a basic structure part building process of building a basic structure part on the ground of the underground space, a steel column erection process of erection of a steel frame column on the basic structure part, and a erected steel frame column. Using a PC beam and / or S beam and a floor slab in the underground space in a horizontal direction so as to support the mountain retaining wall, a floor building step of building a floor, and a PC beam after the floor building And / or S beam, and the beam supporting structure for dismantling the beam supporting structure near the position where the slab is installed, and removing it from the underground space, and after removing the beam supporting structure, the underground frame A frame vertical part building step of building a vertical part of It is achieved by a method constructing underground building frame, wherein the alternately repeating as necessary and Engineering removal step and the frame vertical portion constructing step.

【0008】すなわち、本発明は、場所打ちコンクリー
トに代えて、PC梁(又はS梁)やPC床版などの水平
部材を用いて床を構築するようにしたもので、このよう
にして構築された床は、山止め壁に作用する土圧を直ち
に負担することができるから、切梁支保工の即時撤去が
可能となる。従って、床が完全に出来上がっていなくと
も、直ちにその上階の施工に移行できるので、工期が大
幅に短縮される。しかも、垂直部材の施工についても水
平部材の架設完了後、直ちに実施可能であり、床の施工
と並行して効率良く作業を進めることができる。
That is, according to the present invention, instead of cast-in-place concrete, a horizontal member such as a PC beam (or S beam) or a PC floor slab is used to construct the floor. Since the ground floor can immediately bear the earth pressure acting on the mountain retaining wall, it is possible to immediately remove the girder support work. Therefore, even if the floor is not completely completed, it is possible to immediately move to the construction on the upper floor, which significantly shortens the construction period. Moreover, the construction of the vertical member can be carried out immediately after the construction of the horizontal member is completed, and the work can be efficiently advanced in parallel with the construction of the floor.

【0009】尚、上記地下躯体の構築方法では、ある階
の床構築後、それより複数階下方にある鉄骨柱の周囲に
柱コンクリートを打設して柱壁を構築することもでき
る。このようにして、それぞれ異なる階において水平部
材と垂直部材との施工を並行させて行うことによって
も、つまり複数階を同時に施工するようにしても工期短
縮が可能である。しかも、例えば二階分だけ間をあけれ
ば、床構築作業に伴う振動の影響を受けず、高品質な柱
壁が得られる。
In the method of constructing an underground skeleton, after constructing a floor on a certain floor, it is possible to construct a column wall by placing pillar concrete around a steel column located a plurality of floors below it. In this way, the construction period can be shortened by performing the construction of the horizontal member and the vertical member in parallel on different floors, that is, by constructing a plurality of floors at the same time. Moreover, for example, if a space for two floors is left, it is possible to obtain a high quality pillar wall without being affected by the vibration associated with the floor construction work.

【0010】又、床版において鉄骨柱に接して設けられ
るものは、前記鉄骨柱の周囲に柱コンクリートを打設し
て構築される柱壁の断面に対応した切欠きが形成されて
なり、この切欠きを利用してコンクリート打設管を下階
に送り込むことが好ましい。これによって床版に駄目穴
を形成しておく必要がなくなり、又、駄目穴を閉塞する
手間を省けるから、手間が掛からず、コストが低廉なも
のとなる。尚、床版の切欠き自体は柱壁によって閉塞さ
れるので、余分な閉塞作業は不要である。
The floor slab provided in contact with the steel column has notches corresponding to the cross section of the column wall constructed by placing column concrete around the steel column. It is preferable to send the concrete casting pipe to the lower floor by utilizing the notch. This eliminates the need to form a blind hole in the floor slab, and saves time and labor for closing the blind hole, which saves time and costs. Since the notch of the floor slab itself is closed by the column wall, no extra closing work is required.

【0011】[0011]

【発明の実施の形態】図1〜図6は本発明に係る地下躯
体の構築方法の一実施形態を示すもので、図1は基礎構
造部の構築が完了した状態を示す断面図、図2はPC梁
及び床版を鉄骨柱に取り付けた状態を示す平面図、図3
は地下3階の床構築が完了した状態を示す断面図、図4
は地下2階の床構築が完了した状態を示す断面図、図5
は地下1階の床構築が完了した状態を示す断面図、図6
は地上1階の床構築が略完了した状態を示す断面図であ
る。
1 to 6 show an embodiment of a method for constructing an underground skeleton according to the present invention, and FIG. 1 is a sectional view showing a state in which the foundation structure has been completed, FIG. 3 is a plan view showing a state in which a PC beam and a floor slab are attached to a steel column, FIG.
4 is a cross-sectional view showing a state where the floor construction on the third basement floor is completed, FIG.
Is a cross-sectional view showing a state where the floor construction of the second basement floor is completed, FIG.
6 is a cross-sectional view showing a state where the floor construction of the first basement floor is completed, FIG. 6
[Fig. 3] is a cross-sectional view showing a state in which floor construction on the first floor above ground is substantially completed.

【0012】以下、本発明を、躯体が地下4階構造の場
合を例に挙げ、図1〜図6を用いて具体的に説明する。
但し、本発明はこの回数に限定されるものではなく、他
の階数であっても同様にして施工することができる。先
ず、地下躯体が構築される領域の周囲に対応して、地中
に山止め壁1を設ける。又、重機を据え付けるための構
台を支持する構台杭2を所定の位置に打ち込み、更に山
止め壁1間に架設される切梁支保工を所定の高さで支持
する棚杭3を所定間隔で地中に打ち込む。
Hereinafter, the present invention will be specifically described with reference to FIGS. 1 to 6 by taking the case where the skeleton has a basement 4 floor structure as an example.
However, the present invention is not limited to this number of times, and the same construction can be performed for other floors. First, the earth retaining wall 1 is provided in the ground corresponding to the periphery of the area where the underground structure is constructed. Further, the gantry piles 2 for supporting the gantry for installing the heavy equipment are driven into a predetermined position, and further the shelving piles 3 for supporting the girder support work erected between the mountain retaining walls 1 at a predetermined height are provided at predetermined intervals. Drive into the ground.

【0013】そして、構台杭2を利用して重機据付用の
構台4a,4bを設置すると共に、棚杭3を利用して切
梁支保工5a,5bを架設し、掘削機械を用いて山止め
壁1内領域の掘削を開始する。地下1階分の掘削完了
後、切梁支保工5cを架設し、更に地下2階分の掘削を
行う。この作業を繰り返し行い、切梁支保工5d,5e
の架設及び地下3階、4階分の掘削を完了させる。そし
て、地下4階の床面位置から更に所定深さまで掘削を行
い、地下空間の地盤上に耐圧版や地中梁などからなる基
礎構造部6を構築する。
Then, the gantry piles 2 are used to install the gantry bases 4a and 4b for installing the heavy equipment, and the shelving piles 3 are used to erection the cross beam support works 5a and 5b, and the digging machine is used to mount the cliffs. Start excavation of the area inside the wall 1. After the excavation of the first basement floor is completed, a beam support structure 5c will be installed, and further excavation of the second basement floor will be performed. Repeating this work, the beam support 5d, 5e
And the excavation of the 3rd and 4th basement floors will be completed. Then, excavation is further performed from the floor surface position on the fourth basement floor to a predetermined depth, and the foundation structure part 6 including a pressure plate and an underground beam is constructed on the ground of the underground space.

【0014】基礎構造部6の構築が完了した状態は図1
に示す通りであり、その強度発現後、地下3階の床構築
が行われるのであるが、図1中、一点鎖線で示す切梁支
保工5eのみはこの地下3階の床構築が完了した後に解
体撤去する。これは基礎構造部6と地下3階の床との間
隔が他よりも大きいからであり、この間隔がさほど大き
なものでなければ、地下3階の床構築に先立って切梁支
保工5eを解体撤去できる。
FIG. 1 shows a state in which the construction of the basic structure 6 is completed.
As shown in Fig. 1, the floor construction of the 3rd basement floor is performed after the strength is developed. However, in Fig. 1, only the girder support work 5e shown by the alternate long and short dash line is after the floor construction of the 3rd basement floor is completed. Dismantle and remove. This is because the space between the foundation structure 6 and the floor on the third basement floor is larger than the others. If this space is not so large, the beam support 5e is dismantled prior to the floor construction on the third basement floor. Can be removed.

【0015】次に、所定間隔で第1節の鉄骨柱7a〜7
fを基礎構造部6から立設させ、これら鉄骨柱7a〜7
f及び山止め壁1間に重機で吊り下ろしたPC梁8a〜
8gを取り付ける。更に、このPC梁8a〜8g上に床
版9を設置する。尚、PC梁8a〜8gや床版9の配置
状態、例えば鉄骨柱7aの周囲の様子を図2に示す。こ
の図2から判るように、床版9において鉄骨柱7a〜7
fに接して設けられるものは、後述する柱壁の断面に対
応した切欠き9aが形成されており、この切欠き9aか
らコンクリート打設管が下階に送り込まれる。尚、地下
1階及び地下2階に設けられる床版についても、同様の
切欠きを有している。
Next, the steel columns 7a to 7 of the first section are arranged at predetermined intervals.
f is erected from the foundation structure part 6, and these steel frame columns 7a to 7
PC beam 8a suspended by a heavy machine between f and the mountain stop wall 1 ~
Attach 8g. Further, the floor slab 9 is installed on the PC beams 8a to 8g. FIG. 2 shows the arrangement of the PC beams 8a to 8g and the floor slab 9, for example, the state around the steel column 7a. As can be seen from FIG. 2, in the floor slab 9, the steel columns 7a-7
The thing provided in contact with f is formed with a notch 9a corresponding to the cross section of the column wall described later, and the concrete pouring pipe is sent to the lower floor from this notch 9a. The floor slabs provided on the first basement floor and the second basement floor also have similar cutouts.

【0016】尚、表面凹凸を修正するために、他の作業
が殆ど終了した後に床版9上には薄くコンクリートが打
設される。地下3階の床構築が完了した状態は図3に示
す通りで、地下2階の床構築に先立って、図3中、一点
鎖線で示す切梁支保工5dを解体撤去する。これによっ
て切梁支保工5dに代わって地下3階の床が山止め壁1
を支持するようになる。
Incidentally, in order to correct the surface irregularities, thin concrete is poured on the floor slab 9 after the other work is almost completed. The state in which the floor construction on the third basement floor is completed is as shown in FIG. 3. Prior to the floor construction on the second basement floor, the beam supporting structure 5d indicated by the alternate long and short dash line in FIG. 3 is dismantled and removed. As a result, the floor of the 3rd basement floor is replaced by the cliff wall 1 in place of the beam support 5d.
To support.

【0017】続いて、鉄骨柱7a〜7f及び山止め壁1
間にPC梁10a〜10gを取り付け、更にこのPC梁
10a〜10g上に床版11を配置する。地下2階の床
構築が完了した状態は図4に示す通りで、地下1階の床
構築に先立って、図4中、一点鎖線で示す切梁支保工5
cを解体撤去する。これによって切梁支保工5cに代わ
って地下2階の床が山止め壁1を支持するようになる。
Next, the steel columns 7a to 7f and the mountain retaining wall 1
The PC beams 10a to 10g are attached between them, and the floor slab 11 is placed on the PC beams 10a to 10g. The state where the floor construction on the second basement floor has been completed is as shown in FIG. 4, and prior to the floor construction on the first basement floor, the girder support work indicated by the dashed line in FIG.
Dismantle and remove c. As a result, the floor of the second basement floor supports the cliff wall 1 in place of the beam supporting structure 5c.

【0018】続いて、第1節の鉄骨柱7a〜7f上に第
2節の鉄骨柱12a〜12fを取り付ける。そして、こ
の鉄骨柱12a〜12f及び山止め壁1間にPC梁13
a〜13gを取り付け、更にPC梁13a〜13g上に
床版14を配置する。地上1階の床の一部もこれと並行
して構築される。すなわち、第2節の鉄骨柱12b〜1
2d間にPC梁15a,15bを取り付け、更にPC梁
15a,15b上に床版16を配置する。
Subsequently, the second-column steel-frame pillars 12a-12f are mounted on the first-column steel-frame pillars 7a-7f. Then, a PC beam 13 is provided between the steel columns 12a to 12f and the mountain stop wall 1.
a to 13g are attached, and the floor slab 14 is placed on the PC beams 13a to 13g. Part of the floor on the first floor above the ground will be constructed in parallel with this. That is, the steel column 12b-1 of Section 2
The PC beams 15a and 15b are attached between 2d, and the floor slab 16 is placed on the PC beams 15a and 15b.

【0019】地下1階の床構築が完了した状態は図5に
示す通りで、地上1階の床構築に先立って、図5中、一
点鎖線で示す切梁支保工5bを解体撤去する。これによ
って切梁支保工5bに代わって地下1階の床が山止め壁
1を支持するようになる。又、地下1階の床構築と同時
進行で地下4階に柱壁が構築される。すなわち、地下2
階の床が構築された後、これより二階下方にある地下4
階において、山止め壁1に面する位置や第1節の鉄骨柱
7a〜7f周囲に柱コンクリートを打設し、柱壁17a
〜17hを構築する。このように二階分だけ間をあける
ことで、構築される柱壁17a〜17hは地下1階の床
構築に用いられるリフターが地下2階の床を走行する際
の振動の影響を受け難くなり、高品質な柱壁が得られ
る。
The state where the floor construction on the first basement floor is completed is as shown in FIG. 5. Prior to the floor construction on the first floor above the ground, the beam supporting structure 5b indicated by the alternate long and short dash line in FIG. 5 is dismantled and removed. As a result, the floor of the first basement floor supports the cliff wall 1 in place of the beam supporting structure 5b. In addition, a pillar wall will be constructed on the 4th basement floor at the same time as the floor construction on the 1st basement floor. That is, underground 2
4 floors below, two floors below, after the first floor is constructed
On the floor, pillar concrete is placed near the mountain stop wall 1 and around the steel columns 7a to 7f of the first section, and the pillar wall 17a
Build ~ 17h. In this way, by separating only two floors, the pillar walls 17a to 17h to be constructed become less susceptible to the vibration when the lifter used for floor construction on the first basement floor travels on the floor on the second basement floor, A high quality pillar wall can be obtained.

【0020】続いて、不要になった構台4aを解体撤去
し、又、重機を構築済の地上1階の床上に移し替え、構
台4bを解体撤去する。そして、第2節の鉄骨柱12d
〜12f間にPC梁15c,15dを取り付け、更にP
C梁15c,15d上に床版18を配置する。地上1階
の床構築が略完了した状態は図6に示す通りであり、こ
の図6から判るように、地上1階の床構築と同時進行
で、地下3階に柱壁19a〜19hを構築する。そし
て、地下2階及び地下1階にも、地下4階及び地下3階
と同様に柱コンクリートを打設して柱壁を構築し、地下
躯体が完成する。
Subsequently, the unnecessary gantry 4a is dismantled and removed, and the heavy equipment is transferred to the already constructed floor on the ground floor, and the gantry 4b is dismantled and removed. And the steel column 12d of Section 2
Install the PC beams 15c and 15d between ~ 12f, and
The floor slab 18 is arranged on the C beams 15c and 15d. The state where the floor construction on the first floor above ground is almost completed is as shown in FIG. 6, and as can be seen from FIG. 6, the pillar walls 19a to 19h are constructed on the third floor below the ground concurrently with the floor construction on the first floor above ground. To do. Then, on the second basement floor and the first basement floor, as in the fourth basement floor and the third basement floor, pillar concrete is placed to construct a pillar wall, and the underground structure is completed.

【0021】上述した如く本発明では、PC部材を水平
方向に架設して床を構築するようにしたから、架設が完
了した後、直ちに山止め壁に作用する土圧を支持するこ
とができ、切梁支保工の即時撤去が可能となる。従っ
て、ある階での床構築が完了すると直ちにその上階の施
工に移行でき、コンクリートを打設して床を構築する場
合の如く、一定期間作業ができないといった不具合がな
い。又、垂直部材である柱壁についても床と並行して施
工できるから、工期の大幅な短縮が図れる。
As described above, in the present invention, the PC member is laid horizontally to construct the floor. Therefore, after the erection is completed, the earth pressure acting on the retaining wall can be supported immediately. It is possible to remove the girder support work immediately. Therefore, as soon as the floor construction on a certain floor is completed, it is possible to immediately shift to the construction on the upper floor, and there is no inconvenience that work cannot be performed for a certain period of time, as in the case of constructing a floor by placing concrete. In addition, since the vertical pillar wall can be installed in parallel with the floor, the construction period can be greatly shortened.

【0022】[0022]

【発明の効果】本発明の地下躯体の構築方法は、施工性
に優れており、工期の大幅な短縮が図れる。
The method for constructing an underground skeleton of the present invention is excellent in workability and can significantly shorten the construction period.

【図面の簡単な説明】[Brief description of the drawings]

【図1】基礎構造部の構築が完了した状態を示す断面図
である。
FIG. 1 is a cross-sectional view showing a state in which construction of a substructure is completed.

【図2】PC梁及び床版を鉄骨柱に取り付けた状態を示
す平面図である。
FIG. 2 is a plan view showing a state where a PC beam and a floor slab are attached to a steel frame column.

【図3】地下3階の床構築が完了した状態を示す断面図
である。
FIG. 3 is a cross-sectional view showing a state where floor construction on the third basement floor is completed.

【図4】地下2階の床構築が完了した状態を示す断面図
である。
FIG. 4 is a cross-sectional view showing a state where floor construction on the second basement floor is completed.

【図5】地下1階の床構築が完了した状態を示す断面図
である。
FIG. 5 is a cross-sectional view showing a state where floor construction on the first basement floor is completed.

【図6】地上1階の床構築が略完了した状態を示す断面
図である。
FIG. 6 is a cross-sectional view showing a state where floor construction on the first floor above ground is substantially completed.

【符号の説明】[Explanation of symbols]

1 山止め壁 5a〜5e 切梁支保工 6 基礎構造部 7a〜7f 第1節の鉄骨柱 8a〜8g 地下3階のPC梁 9 地下3階の床版 9a 切欠き 10a〜10g 地下2階のPC梁 11 地下2階の床版 12a〜12f 第1節の鉄骨柱 13a〜13g 地下1階のPC梁 14 地下1階の床版 15a〜15d 地上1階のPC梁 16,18 地上1階の床版 17a〜17h 地下4階の柱壁 19a〜19h 地下3階の柱壁 1 Mountain stop wall 5a-5e Girder support 6 Foundation structure part 7a-7f Section 1 steel column 8a-8g PC beam on the 3rd basement floor 9 Floor slab on the 3rd basement 9a Notch 10a-10g On the 2nd basement floor PC beam 11 B2 floor slab 12a-12f Section 1 steel columns 13a-13g B1 floor PC beam 14 B1 floor slab 15a-15d 1st floor PC beam 16,18 Ground 1st floor Floor slab 17a-17h Pillar wall on the 4th basement floor 19a-19h Pillar wall on the 3rd basement floor

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 山止め壁を支持する切梁支保工の架設と
前記山止め壁内領域の掘削とを交互に繰り返して得られ
る地下空間に、最下階部分から順次地下躯体を構築する
方法であって、 PC梁及び/又はS梁、及び床版を前記地下空間内にお
いて、前記山止め壁を支持するよう水平方向に架設し
て、床を構築する床構築工程と、 床構築後、PC梁及び/又はS梁、及び床版が架設され
た位置近傍の切梁支保工を解体し、前記地下空間内から
撤去する切梁支保工撤去工程とを具備し、 前記床構築工程と切梁支保工撤去工程とを必要に応じて
交互に繰り返すことを特徴とする地下躯体の構築方法。
1. A method of sequentially constructing an underground skeleton from the lowest floor portion in an underground space obtained by alternately repeating the construction of a girder support for supporting a cliff wall and the excavation of the area inside the cliff wall. In the underground space, a PC beam and / or S beam, and a floor slab are installed horizontally to support the mountain retaining wall, and a floor is constructed to construct a floor, and after the floor construction, The method comprises the steps of dismantling the PC beam and / or S beam, and the beam support in the vicinity of the position where the floor slab is installed, and removing the beam support from the underground space. A method for constructing an underground skeleton, characterized by alternately repeating the beam supporting and removing process as necessary.
【請求項2】 山止め壁を支持する切梁支保工の架設と
前記山止め壁内領域の掘削とを交互に繰り返して得られ
る地下空間に、最下階部分から順次地下躯体を構築する
方法であって、 前記地下空間の地盤上に基礎構造部を構築する基礎構造
部構築工程と、 前記基礎構造部上に鉄骨柱を建方する鉄骨柱建方工程
と、 建方された鉄骨柱を用い、PC梁及び/又はS梁、及び
床版を前記地下空間内において、前記山止め壁を支持す
るよう水平方向に架設して、床を構築する床構築工程
と、 床構築後、PC梁及び/又はS梁、及び床版が架設され
た位置近傍の切梁支保工を解体し、前記地下空間内から
撤去する切梁支保工撤去工程とを具備し、 前記床構築工程と切梁支保工撤去工程とを必要に応じて
交互に繰り返すことを特徴とする地下躯体の構築方法。
2. A method of constructing an underground skeleton sequentially from the lowest floor portion in an underground space obtained by alternately repeating the construction of a girder support work for supporting a cliff wall and the excavation of the area inside the cliff wall. The foundation structure part construction step of constructing a foundation structure part on the ground of the underground space, the steel frame pillar erection process of erection of a steel frame pillar on the foundation structure part, and the erected steel frame pillar Using the PC beam and / or S beam and the floor slab in the underground space in a horizontal direction so as to support the mountain retaining wall, and a floor building step of building a floor, and a PC beam after the floor building And / or S-beams, and a girder support work removing process of dismantling the girder support work near the position where the floor slab is installed, and removing it from the underground space. Construction of an underground skeleton characterized by alternately repeating the work removal process as needed Law.
【請求項3】 ある階の床構築後、それより複数階下方
にある鉄骨柱の周囲に柱コンクリートを打設して柱壁を
構築することを特徴とする請求項1又は請求項2に記載
の地下躯体の構築方法。
3. A pillar wall is constructed by placing pillar concrete around a steel pillar located a plurality of floors below a floor after building a floor. How to build the underground structure.
【請求項4】 床版において鉄骨柱に接して設けられる
ものは、前記鉄骨柱の周囲に柱コンクリートを打設して
構築される柱壁の断面に対応した切欠きが形成されてな
り、この切欠きを利用してコンクリート打設管を下階に
送り込むことを特徴とする請求項1〜請求項3いずれか
に記載の地下躯体の構築方法。
4. A floor slab provided in contact with a steel column has a notch corresponding to the cross section of a column wall constructed by placing column concrete around the steel column. The method for constructing an underground skeleton according to any one of claims 1 to 3, wherein the concrete placing pipe is sent to the lower floor by utilizing the notch.
JP7270772A 1995-10-19 1995-10-19 Constructing method of underground building frame Pending JPH09111783A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7270772A JPH09111783A (en) 1995-10-19 1995-10-19 Constructing method of underground building frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7270772A JPH09111783A (en) 1995-10-19 1995-10-19 Constructing method of underground building frame

Publications (1)

Publication Number Publication Date
JPH09111783A true JPH09111783A (en) 1997-04-28

Family

ID=17490786

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7270772A Pending JPH09111783A (en) 1995-10-19 1995-10-19 Constructing method of underground building frame

Country Status (1)

Country Link
JP (1) JPH09111783A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020060000A (en) * 2018-10-09 2020-04-16 大成建設株式会社 Skeleton construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020060000A (en) * 2018-10-09 2020-04-16 大成建設株式会社 Skeleton construction method

Similar Documents

Publication Publication Date Title
JPH08253946A (en) Reverse placing method for concrete of underground structure under road
RU2220258C1 (en) Process of erection of multilevel underground structure ( variants )
KR101428540B1 (en) Soundproof walls basis structure
JP5977412B2 (en) Basement of new building using existing building
JPH08135245A (en) Construction of case body
JPH11172710A (en) Method for constructing underground part of steel encased reinforced concrete building
JPH09111783A (en) Constructing method of underground building frame
JPS6137692Y2 (en)
JP5925231B2 (en) Building construction method and underground building of new building
JP5506057B2 (en) Building construction method
KR100593203B1 (en) a deck supportframe and a construction methed
KR20210017645A (en) Underground structure using strut and method construturing the same
JPS63280153A (en) Underground inverted lining method
JP3109038B2 (en) Underground skeleton structure and construction method
JPH08291526A (en) Construction method for underground structure
KR200369485Y1 (en) a deck supportframe
JP3105044B2 (en) How to build a unit building
JP3809340B2 (en) Reverse strike method
JP2002174051A (en) Construction method for base isolation
JPS6217233A (en) Foundation base column
JP2990216B2 (en) Construction method of reinforced concrete building
JPS6326215B2 (en)
JPH07150577A (en) Basement building construction method on narrow site
JP3045841B2 (en) Beam formwork structure for unit building
JP3045839B2 (en) Method and apparatus for installing floor slab in unit building