JPH0854918A - Production management system - Google Patents

Production management system

Info

Publication number
JPH0854918A
JPH0854918A JP18917794A JP18917794A JPH0854918A JP H0854918 A JPH0854918 A JP H0854918A JP 18917794 A JP18917794 A JP 18917794A JP 18917794 A JP18917794 A JP 18917794A JP H0854918 A JPH0854918 A JP H0854918A
Authority
JP
Japan
Prior art keywords
operator
plan
work time
production
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP18917794A
Other languages
Japanese (ja)
Other versions
JP3403822B2 (en
Inventor
Masayuki Murata
昌之 村田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujitsu Ltd
Original Assignee
Fujitsu Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujitsu Ltd filed Critical Fujitsu Ltd
Priority to JP18917794A priority Critical patent/JP3403822B2/en
Publication of JPH0854918A publication Critical patent/JPH0854918A/en
Application granted granted Critical
Publication of JP3403822B2 publication Critical patent/JP3403822B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Abstract

PURPOSE:To easily and steadily carry out a production plan by making each operator grasp accurately the progress state of the work time included in the production plan. CONSTITUTION:A production management system includes a scheduled work time calculation means 7 which calculates the scheduled work time of an operator included in a production plan 4 based on this plan produced by a plan production means 5, an operator work time calculation means 9 which calculates the actual work time of the operator based on the basic information 1 that is always changed while the product processing is carried on by each equipment as designated by the plan 4 produced by the means 5, and an output means 10 which outputs the work contents, the scheduled work time of the operator and the actual work time by referring in real time to the scheduled work time calculated by the means 7 and the operator work time calculated by the means 9.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、生産管理システムに係
り、詳しくは、上位システムより与えられた多品種ジョ
ブの生産計画に対して生産効率を向上させるジョブの投
入順序を自動的に作成する生産管理システムに適用する
ことができ、特に、各オペレータに製造計画に含まれる
作業時間の進捗状況を正確に把握させることができると
ともに、人員不足やオペレータの製造計画に対する認識
不足等による人為的な製造計画の遅延が生じた場合で
も、作業時間の進捗状況を正確に把握することができる
生産管理システムに関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a production management system, and more specifically, it automatically creates a job submission sequence for improving production efficiency in accordance with a production plan of a multi-product job given by a host system. It can be applied to a production management system, and in particular, it allows each operator to accurately grasp the progress status of the working time included in the manufacturing plan, and it can be artificially reduced due to lack of personnel or operator's lack of awareness of the manufacturing plan. The present invention relates to a production management system capable of accurately grasping the progress status of working hours even if a manufacturing plan is delayed.

【0002】近年の生産管理システムには、より効率的
な製品製造を実現するため、無駄のない各設備の稼働と
製造スケジュールの管理が要求されている。そのため、
各製品を全工程における最善と思われる製造計画の基に
生産スケジュール管理を行うことができる生産管理シス
テムが要求されている。
[0002] In recent years, production management systems are required to operate each facility without waste and manage the production schedule in order to realize more efficient product production. for that reason,
There is a demand for a production management system capable of performing production schedule management for each product based on the production plan that is considered to be the best in all processes.

【0003】[0003]

【従来の技術】図5は従来の生産管理システムのシステ
ム構成を示すブロック図である。従来の生産管理システ
ムは、計画作成手段1001、評価手段1002、解析
手段1003、改善案作成手段1004及び履歴記録手
段1005から構成されている。
2. Description of the Related Art FIG. 5 is a block diagram showing a system configuration of a conventional production management system. The conventional production management system is composed of a plan creating unit 1001, an evaluating unit 1002, an analyzing unit 1003, an improvement plan creating unit 1004, and a history recording unit 1005.

【0004】ここで、計画作成手段1001は、製品情
報、工程情報、生産仕掛情報及びディスパッチングルー
ルを含む基礎情報1006と、どういう物をどれくらい
生産すれば良いかというジョブの生産計画1007と、
実際に製品をどのように流すかを計画に基づいて優先順
位を決定するための着手順序決定ルール及びディスパッ
チング決定ルールを含む投入順序決定ルール1008と
により、対象とする生産システム内の特定工程における
ジョブの着手順序を決定し、時間軸に沿って展開した全
工程のシミュレーションをPC,WS等のシミュレータ
ーで行うことにより、全工程での製造計画を出力し、評
価手段1002は、基礎情報1006を参照し、生産し
たい品種に対してどれくらい生産できるのかを評価する
要素となる評価ルール1009を適用して、製造計画1
010に対して実際の製造結果と比較し、その評価結果
1011を出力する。
Here, the plan creating means 1001 has basic information 1006 including product information, process information, production in process information, and dispatching rules, and a job production plan 1007 of what kind of thing should be produced and how much.
In the specific process in the target production system, by the start order determination rule 1008 including the start order determination rule and the dispatching determination rule for determining the priority order based on the plan of how to actually flow the products. By determining the start order of the jobs and performing simulation of all processes developed along the time axis with a simulator such as PC or WS, the manufacturing plan for all processes is output, and the evaluation means 1002 outputs the basic information 1006. The manufacturing plan 1 is applied by applying the evaluation rule 1009, which is an element for evaluating how much can be produced for the variety to be produced.
010 is compared with the actual manufacturing result, and the evaluation result 1011 is output.

【0005】解析手段1003は、基礎情報1006と
製造計画1010とを参照し、評価結果1011が悪か
った場合に何が悪かったのかを解析するために判断する
解析ルール1012を適用して、評価結果1011にお
ける評価項目の中で予め設定された目標値に達しなかっ
た評価項目に対して、その原因となるジョブ及び工程に
関する解析結果1013を出力する。
The analysis means 1003 refers to the basic information 1006 and the manufacturing plan 1010, applies the analysis rule 1012 for judging what is wrong when the evaluation result 1011 is bad, and applies the evaluation result. Among the evaluation items in 1011, with respect to the evaluation item that does not reach the preset target value, the analysis result 1013 regarding the job and the process that causes it is output.

【0006】改善案作成手段1004は、基礎情報10
06と解析結果1013とを参照し、どの部分を改善す
れば良いかの判断ルール1014を適用して、目標値に
達しなかった評価項目の評価結果1011を改善し、か
つ他の評価項目の評価結果1011の悪化を予め設定さ
れた範囲内に収めるように、計画作成手段1001で採
用した着手順序、設備割付及びディスパッチングを一部
変更する戦略を求めて表示し、履歴記録手段1005
は、計画作成手段1001と解析手段1003と改善案
作成手段1004とにおいて適用したルールの履歴を記
録する。
The improvement plan creating means 1004 uses the basic information 10
06 and the analysis result 1013, the judgment rule 1014 of which part should be improved is applied to improve the evaluation result 1011 of the evaluation item that did not reach the target value, and evaluate other evaluation items. In order to keep the deterioration of the result 1011 within a preset range, a strategy for partially changing the starting order, equipment allocation and dispatching adopted by the plan creating means 1001 is sought and displayed, and the history recording means 1005.
Records the history of the rules applied by the plan creating unit 1001, the analyzing unit 1003, and the improvement plan creating unit 1004.

【0007】この従来の生産管理システムでは、多品種
少量生産を対象とする場合の多種多様な状況の中で、全
ての評価項目を満足する製造計画が一回のオペレーショ
ンで作り難いため、オペレータの経験により一部分ずつ
試行錯誤しながら、再計画を繰り返す支援を行って最善
な生産計画を作成し、この生産計画を基に工場で生産を
行うように構成している。
In this conventional production management system, it is difficult to make a manufacturing plan satisfying all the evaluation items in one operation in a wide variety of situations in which high-mix low-volume production is targeted. Based on experience, we make trial and error one by one, and support the repetition of re-planning to create the best production plan, and then it is configured to produce at the factory based on this production plan.

【0008】[0008]

【発明が解決しようとする課題】上記した従来の生産管
理システムは、オペレータによる製造計画1010の再
計画を支援して最善な生産計画を得ようとするものだ
が、目標値に達していない項目についての解析結果によ
っては、製造計画1010に対する遅延要因のために目
標値を達成することができないのにも拘らず、生産計画
1007が正しく実行されているか等、どのように生産
計画1007を見直せばよいかを確認し難い。このた
め、製造計画1010に含まれるオペレータの作業時間
がのびるなど進捗状況を正確に把握し難いので、製造計
画1010を着実に実行することが困難であるという問
題がある。
The above-described conventional production management system tries to obtain the best production plan by assisting the operator in rescheduling the production plan 1010, but regarding the items that have not reached the target value. Depending on the analysis result of the above, although the target value cannot be achieved due to the delay factor with respect to the manufacturing plan 1010, the production plan 1007 should be reviewed how the production plan 1007 is correctly executed. It's difficult to confirm. For this reason, it is difficult to accurately grasp the progress status such as the work time of the operator included in the manufacturing plan 1010 being extended, and thus it is difficult to steadily execute the manufacturing plan 1010.

【0009】また、従来の生産管理システムでは、製造
計画1010を作成するために全工程のシミュレーショ
ンを行うため、そのための基礎情報1006は、信頼で
きなくてはならない。この場合、各設備の処理時間や搬
送時間等機械的なものは、故障時以外は略一定であり、
故障の場合も設備稼働情報を参照すれば、即座に検知す
ることができる。
Further, in the conventional production management system, since the simulation of all processes is performed to create the manufacturing plan 1010, the basic information 1006 for that purpose must be reliable. In this case, mechanical things such as processing time and transportation time of each equipment are almost constant except when there is a failure,
Even if a failure occurs, it can be detected immediately by referring to the equipment operation information.

【0010】しかしながら、従来の生産管理システムで
は、製品を各設備で処理するには、オペレータの作業に
依存しなければならず、人員不足やオペレータの製造計
画1010に対する認識不足等による人為的な製造計画
1010の遅延を生じた場合には、その項目を指定して
いなければ、他の項目の評価に悪影響を及ぼすと同時に
解析が行い難くなり、結局、上記と同様作業時間の進捗
状況を正確に把握し難いという問題があった。
However, in the conventional production management system, in order to process a product in each facility, it is necessary to depend on the work of the operator, and man-made production due to lack of personnel or lack of recognition of the operator's production plan 1010. When the plan 1010 is delayed, if the item is not specified, the evaluation of other items is adversely affected, and at the same time, it becomes difficult to perform the analysis. There was a problem that it was difficult to grasp.

【0011】そこで、本発明は、各オペレータに製造計
画に含まれる作業時間の進捗状況を正確に把握させるこ
とができるとともに、人員不足やオペレータの製造計画
に対する認識不足等による人為的な製造計画の遅延が生
じた場合でも、作業時間の進捗状況を把握することがで
き、製造計画を着実に、かつ容易に実行することができ
る生産管理システムに関する。
Therefore, according to the present invention, each operator can accurately grasp the progress status of the working time included in the manufacturing plan, and at the same time, the artificial manufacturing plan can be changed due to lack of personnel or operator's lack of recognition of the manufacturing plan. The present invention relates to a production management system capable of grasping the progress of working hours even if a delay occurs, and steadily and easily executing a manufacturing plan.

【0012】[0012]

【課題を解決するための手段】請求項1記載の発明は、
製品情報、工程情報、生産仕掛情報、設備稼働情報及び
ディスパッチングルールからなる基礎情報と、ジョブの
生産計画と、着手順序決定ルール、設備割付決定ルール
及びディスパッチング決定ルールからなる投入順序決定
ルールにより、対象とする生産システム内の特定工程に
おけるジョブの着手順序を決定し、時間軸に沿って展開
した全工程のシミュレーションを行うことにより、全工
程での製造計画を出力する計画作成手段と、該計画作成
手段により作成された製造計画を基に全工程を制御しつ
つ、前記基礎情報を変更する工程制御手段とを有し、前
記計画作成手段及び前記工程制御手段により全工程の生
産スケジュール管理を行う生産管理システムにおいて、
前記計画作成手段により作成された製造計画を参照し、
計画に含まれるオペレータの予定作業時間を算出する予
定作業時間算出手段と、前記計画作成手段により作成さ
れた製造計画通りに各設備での製品処理が進められるな
か、前記基礎情報を参照し、実際のオペレータの作業時
間を算出するオペレータ作業時間算出手段と、前記予定
作業時間算出手段により算出された予定作業時間と前記
オペレータ作業時間算出手段により算出されたオペレー
タ作業時間とを参照し、作業内容とオペレータの予定作
業時間と実際の作業時間とを出力する出力手段とを有す
ることを特徴とするものである。
According to the first aspect of the present invention,
Based on basic information consisting of product information, process information, production in process information, equipment operation information and dispatching rules, job production plans, and start order decision rules consisting of start order decision rules, equipment allocation decision rules and dispatching decision rules. A plan creating means for outputting a production plan for all processes by determining the start order of jobs in a specific process in a target production system and simulating all processes developed along a time axis; While controlling all processes based on the manufacturing plan created by the plan creating unit, the process control unit for changing the basic information is provided, and the production schedule management of all processes is performed by the plan creating unit and the process controlling unit. In the production management system to perform,
Referring to the manufacturing plan created by the plan creating means,
With the planned work time calculation means for calculating the planned work time of the operator included in the plan and the product processing at each facility proceeded according to the manufacturing plan created by the plan creation means, refer to the basic information and actually The operator work time calculating means for calculating the operator's work time, the planned work time calculated by the planned work time calculation means and the operator work time calculated by the operator work time calculation means, and It is characterized by having an output means for outputting the scheduled work time of the operator and the actual work time.

【0013】請求項2記載の発明は、上記請求項1記載
の発明において、前記予定作業時間算出手段と前記オペ
レータ作業時間算出手段により作成された作業時間情報
を履歴として記録する履歴記録手段を有することを特徴
とするものである。請求項3記載の発明は、上記請求項
2記載の発明において、前記履歴記録手段から読み出し
た作業時間の履歴を出力する出力手段を有することを特
徴とするものである。
According to a second aspect of the present invention, in the first aspect of the invention, there is a history recording means for recording the work time information created by the scheduled work time calculating means and the operator work time calculating means as a history. It is characterized by that. The invention according to claim 3 is the invention according to claim 2 characterized in that the invention further comprises an output means for outputting a history of the working time read from the history recording means.

【0014】[0014]

【作用】本発明では、後述する実施例の図1に示す如
く、計画作成手段5により作成された製造計画4を参照
し、計画に含まれるオペレータの予定作業時間を予定作
業時間算出手段7により算出し、計画作成手段5により
作成された製造計画4通りに各設備での製品処理が進め
られるなか、常時変更される基礎情報1を参照し、実際
のオペレータの作業時間をオペレータ作業時間算出手段
9により算出し、予定作業時間算出手段7により算出さ
れた予定作業時間とオペレータ作業時間算出手段9によ
り算出されたオペレータ作業時間とをリアルタイムに参
照し、作業内容とオペレータの予定作業時間と実際の作
業時間とを出力手段10により出力するように構成して
いる。
In the present invention, as shown in FIG. 1 of the embodiment described later, the planned work time of the operator included in the plan is calculated by the planned work time calculation means 7 by referring to the manufacturing plan 4 created by the plan preparation means 5. The actual work time of the operator is calculated by referring to the basic information 1 which is constantly changed while the product processing in each facility is advanced in accordance with the four production plans created by the plan creating means 5 according to the operator work time calculating means. 9, the scheduled work time calculated by the scheduled work time calculation means 7 and the operator work time calculated by the operator work time calculation means 9 are referred to in real time, and the work content, the scheduled work time of the operator and the actual work time are calculated. The working time is output by the output means 10.

【0015】このため、システム全体において各工程で
の各オペレータの作業時間をリアルタイムに管理するこ
とができるので、製造計画に含まれる各オペレータの作
業時間の進捗状況を正確に把握することができる。しか
も、人員不足や休憩時間等から、仕掛、設備状態が整っ
ているにも拘らず、製品処理が進んでいない等人為的な
製造計画の遅延が生じた場合も、その情報をシステム全
体内の何処にでも提供することができるため、オペレー
タの作業時間の進捗状況を正確に把握することができ
る。従って、製造計画を着実に、かつ容易に実行するこ
とができる。
Therefore, the working time of each operator in each process can be managed in real time in the entire system, and the progress of the working time of each operator included in the manufacturing plan can be accurately grasped. In addition, due to lack of personnel or break time, even if the work process and equipment are in good condition, but the product manufacturing process is not progressing and the artificial manufacturing plan is delayed, the information is stored in the entire system. Since it can be provided anywhere, it is possible to accurately grasp the progress status of the working time of the operator. Therefore, the manufacturing plan can be steadily and easily executed.

【0016】[0016]

【実施例】以下、本発明の実施例を図面を参照して説明
する。図1は本発明に係る一実施例の生産管理システム
の構成を示すブロック図である。本実施例では、まず、
製品情報、工程情報、生産仕掛情報、設備稼働情報及び
ディスパッチングルールを含む基礎情報1と、ジョブの
生産計画2と、着手順序決定ルール、設備割付決定ルー
ル及びディスパッチング決定ルールを含む投入順序決定
ルール3と、予め設定された各製品の工程や納期等を含
む生産計画2とを参照し、対象とする生産システム内の
特定工程におけるジョブの着手順序を決定し、時間軸に
沿って展開した全工程のシミュレーションを行うことに
より、最善と思われる全工程での製造計画4を出力する
計画作成手段5を用いて、製造計画4が作成される。
Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 is a block diagram showing the configuration of a production management system according to an embodiment of the present invention. In this embodiment, first,
Basic information 1 including product information, process information, production in process information, equipment operation information and dispatching rules, job production plan 2, start order determination rules, equipment allocation determination rules and dispatching order determinations including dispatching determination rules By referring to the rule 3 and the production plan 2 including the preset process and delivery date of each product, the order of starting the job in the specific process in the target production system is determined and expanded along the time axis. By simulating all the processes, the manufacturing plan 4 is created by using the plan creating means 5 that outputs the manufacturing plan 4 in all the processes which seems to be the best.

【0017】次に、計画作成手段5により作成された製
造計画4を基に、対象とする生産システム内の全工程へ
の作業指示や製品情報、工程情報、生産仕掛情報、設備
稼働情報の収集を行って全工程を制御しながら、基礎情
報1を変更する工程制御手段6により、全工程の生産ス
ケジュールの管理を行っている。なお、従来の生産管理
システムでは、システム内の各設備との通信網を用い、
製造計画に対する進捗状況に対し基礎情報1等の情報を
収集しているが、その評価・解析技術としては、各工程
の総処理時間で行っており、不確定要素の強いオペレー
タの作業時間のリアルタイムな算出と情報の提供は行っ
ていない。
Next, on the basis of the manufacturing plan 4 created by the plan creating means 5, collection of work instructions, product information, process information, production in-process information, and equipment operation information for all processes in the target production system. The production schedule of all the processes is managed by the process control means 6 that changes the basic information 1 while performing the above process. In the conventional production control system, a communication network with each facility in the system is used,
Information such as basic information 1 is collected for the progress status of the manufacturing plan, but the evaluation / analysis technology is based on the total processing time of each process, and the real-time work time of operators with strong uncertainties. We do not calculate or provide information.

【0018】これに対し、本実施例では、製造計画4内
の時間軸に沿って展開した製造スケジュールと、基礎情
報1内の各工程におけるオペレータによる予定作業時間
とを参照し、オペレータに依存する作業に関し、予定さ
れる作業内容、作業担当者(班)、作業時間を予定作業
時間算出手段7により算出して作業時間情報8にセット
する。
On the other hand, in this embodiment, the manufacturing schedule developed along the time axis in the manufacturing plan 4 and the scheduled work time by the operator in each step in the basic information 1 are referred to and depend on the operator. Regarding the work, the scheduled work content, the worker (group), and the work time are calculated by the planned work time calculation means 7 and set in the work time information 8.

【0019】次に、基礎情報1内の製品情報、生産仕掛
情報、設備稼働情報と、予定作業時間算出手段7により
セットされた内容とを比較し、予定された各設備からの
動作アクションを検知しながら、実際のオペレータの作
業時間をオペレータ作業時間算出手段9により算出して
作業時間情報8に予定作業時間算出手段7と同様にセッ
トする。
Next, the product information, production in-process information, and equipment operation information in the basic information 1 are compared with the contents set by the scheduled work time calculating means 7 to detect the action action from each scheduled equipment. On the other hand, the actual work time of the operator is calculated by the operator work time calculation means 9 and set in the work time information 8 in the same manner as the planned work time calculation means 7.

【0020】次に、予定作業時間算出手段7とオペレー
タ作業時間算出手段9とをリアルタイムに利用し、セッ
トされた作業時間を既存または設置した出力手段10に
より表示する。そして、予定作業時間算出手段7とオペ
レータ作業時間算出手段9により作成された作業時間情
報8を履歴記録手段11により履歴として記録する。こ
れにより、オペレータの作業時間をリアルタイムに提供
・履歴記録する。
Next, the scheduled work time calculation means 7 and the operator work time calculation means 9 are utilized in real time, and the set work time is displayed by the existing or installed output means 10. Then, the work time information 8 created by the scheduled work time calculating means 7 and the operator work time calculating means 9 is recorded as a history by the history recording means 11. Thereby, the working time of the operator is provided and recorded in real time.

【0021】次に、図2は図1に示す生産管理システム
を用いたシステム構成を示す図である。図2に示すシス
テムは、本発明に係る生産管理システムを付加した上位
CPU21と、この上位CPU21とLAN22を介し
て繋がれた中央管理室端末23、廊下のモニター装置2
4及び各装置端末25〜27とから構成されている。な
お、各装置端末25〜27及び各モニター装置24は、
従来の生産管理用システムのものと兼用でも良く、LA
N22を用いて各装置状態及び製品仕掛情報等の基礎情
報1からオペレータの作業情報を収集するように構成し
ている。
Next, FIG. 2 is a diagram showing a system configuration using the production management system shown in FIG. The system shown in FIG. 2 includes a host CPU 21 to which the production management system according to the present invention is added, a central control room terminal 23 connected to the host CPU 21 via a LAN 22, and a corridor monitor device 2.
4 and each device terminal 25-27. In addition, each device terminal 25-27 and each monitor device 24,
It may be combined with the conventional production management system, and LA
N22 is used to collect the work information of the operator from the basic information 1 such as each device status and product in-process information.

【0022】次に、図3は図2に示す各装置端末での作
業指示情報表示例を示す図である。製品仕掛がなくオペ
レータが製品待ちの場合は、計画通りに待っていれば良
く、製品が仕掛りオペレータの作業を要する場合は、作
業内容と予定時間が表示され、時間が経過するととも
に、現在の作業時間がリアルタイムに更新されるため、
担当オペレータは、表示された作業内容を予定時間内に
終了させるように心がけていれば、迷うことなく、製造
計画が進行する。
Next, FIG. 3 is a diagram showing a display example of work instruction information on each device terminal shown in FIG. If there is no product in process and the operator is waiting for the product, it is sufficient to wait as planned.If the product is in process and the operator's work is required, the work content and the scheduled time are displayed, and the time passes and the current Working time is updated in real time,
If the operator in charge is trying to finish the displayed work content within the scheduled time, the manufacturing plan proceeds without hesitation.

【0023】また、人員不足等ですぐにオペレータが作
業を始められずに予定時間を過ぎた場合も、システム内
の何処ででも、その状況を把握することができるため、
すぐに対応することができる。なお、製品の待ち時間が
終了し、作業開始時刻になると、画面は、図3(a)か
ら図3(b)に切り替わる。次に、図4は図1に示す生
産管理システムにおける作業時間の履歴表示例を示す図
である。本実施例では、各担当オペレータの作業時間の
遅延状況等を任意に表示することができるため、極端に
遅延時間が長いオペレータの箇所に人員を追加する等し
て、人員配置や各担当オペレータの評価を行い易くする
ことができる。
In addition, even if the operator cannot start work immediately and the scheduled time has passed due to lack of personnel, etc., the situation can be grasped anywhere in the system.
You can respond immediately. When the work waiting time ends and the work start time comes, the screen is switched from FIG. 3A to FIG. 3B. Next, FIG. 4 is a diagram showing an example of a history display of work hours in the production management system shown in FIG. In this embodiment, since it is possible to arbitrarily display the delay status of the work time of each operator in charge, etc., personnel is added to the location of the operator whose delay time is extremely long, etc. The evaluation can be facilitated.

【0024】このように、本実施例では、計画作成手段
5により作成された製造計画4を参照し、計画に含まれ
るオペレータの予定作業時間を予定作業時間算出手段7
により算出し、計画作成手段5により作成された製造計
画4通りに各設備での製品処理が進められるなか、常時
変更される基礎情報1を参照し、実際のオペレータの作
業時間をオペレータ作業時間算出手段9により算出し、
予定作業時間算出手段7により算出された予定作業時間
とオペレータ作業時間算出手段9により算出されたオペ
レータ作業時間とをリアルタイムに参照し、作業内容と
オペレータの予定作業時間と実際の作業時間とを出力手
段10により出力するように構成している。
As described above, in the present embodiment, the planned work time of the operator included in the plan is calculated by referring to the manufacturing plan 4 prepared by the plan preparation means 5.
According to the basic information 1 that is constantly changed while the product processing in each facility is advanced according to the four manufacturing plans created by the plan creating means 5, the actual working time of the operator is calculated by the operator working time. Calculated by means 9,
The scheduled work time calculated by the planned work time calculation means 7 and the operator work time calculated by the operator work time calculation means 9 are referred to in real time, and the work content, the operator's planned work time and the actual work time are output. It is configured to output by means 10.

【0025】このため、システム全体において各工程で
の各オペレータの作業時間をリアルタイムに管理するこ
とができるので、製造計画に含まれる各オペレータの作
業時間の進捗状況を正確に把握することができる。しか
も、人員不足や休憩時間等から、仕掛、設備状態が整っ
ているにも拘らず、製品処理が進んでいない等人為的な
製造計画の遅延が生じた場合も、その情報をシステム全
体内の何処にでも提供することができるため、オペレー
タの作業時間の進捗状況を正確に把握することができ
る。従って、製造計画を着実に、かつ容易に実行するこ
とができる。
Therefore, the working time of each operator in each process can be managed in real time in the entire system, so that the progress of the working time of each operator included in the manufacturing plan can be accurately grasped. In addition, due to lack of personnel or break time, even if the work process and equipment are in good condition, but the product manufacturing process is not progressing and the artificial manufacturing plan is delayed, the information is stored in the entire system. Since it can be provided anywhere, it is possible to accurately grasp the progress status of the working time of the operator. Therefore, the manufacturing plan can be steadily and easily executed.

【0026】また、本実施例では、作業時間情報を提供
することができるため、オペレータに製造計画に対して
自己の役割を認識させて、作業効率を向上させることが
できる他、各設備担当オペレータの作業状況を把握でき
るため、人員配置等の参考にすることができる。また、
本実施例では、予定作業時間算出手段7とオペレータ作
業時間算出手段8により作成された作業時間情報8を履
歴記録手段11により履歴として記録しておき、この履
歴記録手段11から読み出した作業時間の履歴を表示す
るように構成している。このため、各担当オペレータの
作業時間の遅延状況等を任意に表示することができるの
で、極端に遅延時間が長いオペレータの箇所に人員を追
加する等して、人員配置や各担当オペレータを容易に評
価することができる。
Further, in the present embodiment, since the working time information can be provided, the operator can be made aware of his / her role in the manufacturing plan to improve the working efficiency, and the operator in charge of each equipment. Since the work status of can be grasped, it can be used as a reference for staffing. Also,
In the present embodiment, the work time information 8 created by the scheduled work time calculation means 7 and the operator work time calculation means 8 is recorded as a history by the history recording means 11, and the work time read from the history recording means 11 is recorded. It is configured to display history. For this reason, it is possible to arbitrarily display the delay status of the work time of each operator in charge, so it is possible to easily assign staff and assign each operator by adding staff to the location of the operator whose delay is extremely long. Can be evaluated.

【0027】[0027]

【発明の効果】本発明によれば、各オペレータに製造計
画に含まれる作業時間の進捗状況を正確に把握させるこ
とができるとともに、人員不足やオペレータの製造計画
に対する認識不足等による人為的な製造計画の遅延が生
じた場合でも、作業時間の進捗状況を把握することがで
き、製造計画を着実に、かつ容易に実行することができ
るという効果がある。
According to the present invention, each operator can accurately grasp the progress of the working time included in the manufacturing plan, and artificial manufacturing due to lack of personnel or operator's lack of recognition of the manufacturing plan. Even if the plan is delayed, the progress of the working time can be grasped, and the manufacturing plan can be steadily and easily executed.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明に係る一実施例の生産管理システムの構
成を示すブロック図である。
FIG. 1 is a block diagram showing a configuration of a production management system according to an embodiment of the present invention.

【図2】図1に示す生産管理システムを用いたシステム
構成を示す図である。
FIG. 2 is a diagram showing a system configuration using the production management system shown in FIG.

【図3】図1に示す生産管理システムにおける作業指示
情報表示例を示す図である。
FIG. 3 is a diagram showing a display example of work instruction information in the production management system shown in FIG.

【図4】図1に示す生産管理システムにおける作業時間
の履歴表示例を示す図である。
FIG. 4 is a diagram showing an example of a history display of work hours in the production management system shown in FIG.

【図5】従来の生産管理システムの構成を示すブロック
図である。
FIG. 5 is a block diagram showing a configuration of a conventional production management system.

【符号の説明】[Explanation of symbols]

1 基礎情報 2 生産計画 3 投入順序決定ルール 4 製造計画 5 計画作成手段 6 工程制御手段 7 予定作業時間算出手段 8 作業時間情報 9 オペレータ作業時間算出手段 10 出力手段 11 履歴記録手段 21 上位CPU 22 LAN 23 中央管理室端末 24 モニター装置 25,26,27 装置端末 1 Basic Information 2 Production Plan 3 Input Sequence Decision Rule 4 Manufacturing Plan 5 Plan Making Means 6 Process Control Means 7 Scheduled Working Time Calculation Means 8 Working Time Information 9 Operator Working Hours Calculation Means 10 Output Means 11 History Recording Means 21 Higher CPU 22 LAN 23 Central control room terminal 24 Monitor device 25, 26, 27 Device terminal

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】製品情報、工程情報、生産仕掛情報、設備
稼働情報及びディスパッチングルールからなる基礎情報
(1)と、ジョブの生産計画(2)と、着手順序決定ル
ール、設備割付決定ルール及びディスパッチング決定ル
ールからなる投入順序決定ルール(3)により、対象と
する生産システム内の特定工程におけるジョブの着手順
序を決定し、時間軸に沿って展開した全工程のシミュレ
ーションを行うことにより、全工程での製造計画(4)
を出力する計画作成手段(5)と、該計画作成手段
(5)により作成された製造計画(4)を基に全工程を
制御しつつ、前記基礎情報(1)を変更する工程制御手
段(6)とを有し、前記計画作成手段(5)及び前記工
程制御手段(6)により全工程の生産スケジュール管理
を行う生産管理システムにおいて、前記計画作成手段
(5)により作成された製造計画(4)を参照し、計画
に含まれるオペレータの予定作業時間を算出する予定作
業時間算出手段(7)と、前記計画作成手段(5)によ
り作成された製造計画(4)通りに各設備での製品処理
が進められるなか、前記基礎情報(1)を参照し、実際
のオペレータの作業時間を算出するオペレータ作業時間
算出手段(9)と、前記予定作業時間算出手段(7)に
より算出された予定作業時間と前記オペレータ作業時間
算出手段(9)により算出されたオペレータ作業時間と
を参照し、作業内容とオペレータの予定作業時間と実際
の作業時間とを出力する出力手段(10)とを有するこ
とを特徴とする生産管理システム。
1. Basic information (1) consisting of product information, process information, production in process information, equipment operation information and dispatching rules, job production plan (2), start order determination rule, equipment allocation determination rule and According to the input order determination rule (3) including the dispatching determination rule, the start order of the jobs in the specific process in the target production system is determined, and the simulation of all the processes developed along the time axis is performed. Manufacturing plan in process (4)
And a process control means (5) for changing the basic information (1) while controlling all the processes based on the manufacturing plan (4) created by the plan creating means (5) 6) and a production management system that manages the production schedule of all processes by the plan creation means (5) and the process control means (6), the manufacturing plan (5) created by the plan creation means (5). 4), the planned work time calculation means (7) for calculating the planned work time of the operator included in the plan, and the manufacturing plan (4) created by the plan creation means (5) for each facility While product processing is in progress, reference is made to the basic information (1) to calculate the actual working time of the operator by the operator working time calculating means (9) and the scheduled working time calculating means (7). work And an output means (10) for outputting the work content, the scheduled work time of the operator, and the actual work time with reference to the interval and the operator work time calculated by the operator work time calculation means (9). Characteristic production management system.
【請求項2】前記予定作業時間算出手段(7)と前記オ
ペレータ作業時間算出手段(9)により作成された作業
時間情報(8)を履歴として記録する履歴記録手段(1
1)を有することを特徴とする請求項1記載の生産管理
システム。
2. A history recording means (1) for recording work time information (8) created by the scheduled work time calculating means (7) and the operator work time calculating means (9) as a history.
The production management system according to claim 1, further comprising 1).
【請求項3】前記履歴記録手段(11)から読み出した
作業時間の履歴を出力する出力手段(10)を有するこ
とを特徴とする請求項2記載の生産管理システム。
3. The production management system according to claim 2, further comprising output means (10) for outputting the history of the working time read from the history recording means (11).
JP18917794A 1994-08-11 1994-08-11 production management system Expired - Fee Related JP3403822B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP18917794A JP3403822B2 (en) 1994-08-11 1994-08-11 production management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP18917794A JP3403822B2 (en) 1994-08-11 1994-08-11 production management system

Publications (2)

Publication Number Publication Date
JPH0854918A true JPH0854918A (en) 1996-02-27
JP3403822B2 JP3403822B2 (en) 2003-05-06

Family

ID=16236786

Family Applications (1)

Application Number Title Priority Date Filing Date
JP18917794A Expired - Fee Related JP3403822B2 (en) 1994-08-11 1994-08-11 production management system

Country Status (1)

Country Link
JP (1) JP3403822B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104616098A (en) * 2014-12-31 2015-05-13 国网山东省电力公司青岛供电公司 Task management method and system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104616098A (en) * 2014-12-31 2015-05-13 国网山东省电力公司青岛供电公司 Task management method and system

Also Published As

Publication number Publication date
JP3403822B2 (en) 2003-05-06

Similar Documents

Publication Publication Date Title
US7966220B2 (en) Method and apparatus for planning, monitoring and illustrating multiple tasks based on user defined criteria and predictive ability
US8458117B2 (en) System and method for dependency and root cause discovery
JP2002023823A (en) Production control system
JPH09259181A (en) Work flow managing system
JP4321020B2 (en) Cell production operation system
JPH1034499A (en) Capacity information gathering method for production facility and production control system
Peng et al. Real-time control and scheduling of flexible manufacturing systems: an ordinal optimisation based approach
JP3403822B2 (en) production management system
JPH03251351A (en) Production progress management device
JP2555880B2 (en) Manufacturing planning device
Nehme et al. Using discrete-event simulation to model situational awareness of unmanned-vehicle operators
JP3355303B2 (en) Maintenance patrol work table creation device
JPH04347769A (en) Process management device
Vinod et al. Development and analysis of scheduling decision rules for a dynamic flexible job shop production system: a simulation study
Bohács et al. Simulation support in construction uncertainty management: A production modelling approach
Zikos et al. Human-Resources optimization & re-adaptation modelling in enterprises
Fernandes et al. Worker assignment in dual resource constrained systems subject to machine failures: a simulation study
JPH0573574A (en) Production controller
KR100374391B1 (en) Apparatus for integration controlled of simulation with control for factory automation system and Method for driving thereof
JP2001155062A (en) System and method for predicting arrival of work flow and storage medium stored with program related to the same method
JPH08292985A (en) Maintenance work support device
Krishnaiah Chetty et al. Modelling, simulation and scheduling of flexible assembly systems with coloured Petri nets
JPH09128440A (en) Production planning method and system using it
Bing-hai et al. Agent-based decision support system for dynamic scheduling of a flexible manufacturing system
JP3169079B2 (en) Production line automatic operation equipment

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20030218

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080229

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090228

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees